tcm 303-05 power point slides - unit 1
TRANSCRIPT
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
1/17
TCM303 Building Quantity Practice
Unit 1
ESTIMATING PROCESS AND METHODS
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
2/17
Unit Overview
This unit is divided into three sections.
Section one, you are introduced to cost estimation, the
application and use of cost estimation and the methods
and processes involved in preparing cost estimates.
Section two discusses two case studies amplifying the
different functions of cost estimating and the methods
used to prepare cost estimates for different purposes.
Section three, introduces an overview of project
procurement methods used for building works
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
3/17
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
4/17
Introduction to Cost
EstimatingThe main purpose of a cost estimate is to
provide an indication of the probable cost
of construction so that the client will have
an idea how much finance he needs for
his project. Thus, the cost estimate will
usually be one of the deciding factors in
the clients development strategy. It willalso form the basis for his budget and his
financing strategy.
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
5/17
Introduction to Cost
EstimatingThe various estimates can be classified into
the following categories: -
Initial budgeting preliminary estimate,
feasibility, viability, authorisation
Cost control final budget
Design comparison exercise conductedprogressively before the construction
commenced
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
6/17
Methods of Cost EstimatingMethod RemarksFinancial methods Used to determine cost limits or the building costs in a
developers budgetUnit Applicable to projects having standard units of accommodation
like schools and hospitals. It is usually used to fix cost limits for
public sector building projectsSuperficial area Still widely used, and the most popular method of approximate
estimating. Can be applied to virtually all types of buildingsCube Used to be a popular method amongst architects where the
volume of the building is used as a basis tocalculate the cost. It is
not in used anymoreStorey-enclosure Not an accurate method and is hardly used nowApproximate quantities Still a popular method on difficult and awkward contracts. This is
a more accurate method if time permits
Elemental estimatingNot strictly a method of approximate estimating, but more
associated with cost planning; used widely in both the public
and private sectors for controlling costsCost models These methods are still in the course of development
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
7/17
Cost estimate for budgeting Case
Study 1
In the initial stage of a project, design drawings may not be
ready as the architect would still be preparing the
conceptual sketch.
However, the client would still want to know the estimated
cost in order to decide if he has sufficient funds to
proceed with the project.
As such, the quantity surveyor (QS) would prepare a
preliminary cost appraisal just by using the gross floor
area.
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
8/17
Cost estimate for budgeting Case
Study 1
Parameters that would have to be considered are: -
Type of building to be constructed
Location of the building
Size of the site Site conditions/constraint
An indication of the standard of finishes and fittings
Additional feature to roof or wall
Exclusion items
Cost of external works in relation to the
development like flyover to site, demolition of buildings,
etc
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
9/17
Cost estimate for budgeting Case
Study 1
Reporting the cost estimate (preliminary cost appraisal
format)
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
10/17
Cost estimate for feasibility
study - Case Study 2
A feasibility study is requested by the client when the
client intends to sell the buildings.
As such, the client would need to know if the project
generates a good return. If the return is not good, the
client will ask the architect to change the design or
development mix to produce a mix that gives good
return.
A feasibility study is used for this purpose and is an ideal
method to calculate and recalculate the return of variousdesign and development mix. Gender neutrality
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
11/17
Parameters
to
consider
item Parameters Notes1. Types of buildings to be constructed The client/architect would have to decide what
type of building they are going to develop on the
site and list it out.
a) Highrise or lowriseb) Apartment, condominium,high end
condominium, office tower, shop office,
terrace houses, factory, etcc) The number of storey and number of unitsd) The nett saleable floor area of each unit
2. Selling price for each type of building The selling price of the development will beadvised by the client. If none is provided, the QS
would have to look at the current selling/rental
price to apply to the proposed development 3. Land value Land cost is usually provided by the client.
Otherwise, the QS would have to look at
rental/selling rate for land nearby the proposed
development area4. Construction cost of the various buildings The cost appraisal would have to be generated by
the QS prior to be able to run the feasibility
studies5. Soft cost relating to the entire development The soft cost in relation are:-
a) Marketing, promotion and agency feesb) Financing chargesc) Local authorities contributionsd) Professional feese) Project management and administrationf ) Construction supervisiong) Pre-development expenses and statutory
contribution
h) Land costi ) Legal fees and stamp duty
6. Phasing if the development is big If the development is a mixed development andthe site is very big, then phasing would have to be
incorporated.7. Construction period The construction period would have to be advised
by the QS based on the various type of building.8. Loan interest This is based on the latest base lending rate as
advised by Bank Negara
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
12/17
Cost estimate for feasibility
study - Case Study 2
RM000Gross Development Value 130,000Less Gross Development Cost 85,000Net Cash Surplus/(Deficit) 45,000Cash surplus/(deficit) 45,000Less paid up capital (land value) (8,800)
36,200Return on Development Cost (RODC) 42.58%Return on Development Value (RODV) 27.84%
Reporting the cost estimateThe most important figure the client is interested to view in a feasibility
studies is the return on development cost (RODC) and return on
development value (RODV). This will be generated once the selling price,
soft cost and construction cost is calculated. The format which the
feasibility study can be presented is as follows:-
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
13/17
Project Procurement Methods
Traditional Procurement
Employer
Architect
QuantitySurveyor
Mechanical &Electrical
Engineers
Civil &
Structural
Engineers
Main
Contractor
Sub -
Contractors
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
14/17
Project Procurement Methods
Design and Build
Employer
Architect
QuantitySurveyor
Mechanical &
Electrical
Engineers
Civil &
StructuralEngineers
Sub-
Contractors
Contractor
Employers
advisers
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
15/17
Project Procurement Methods
Management Contracting
Employer
Architect
Quantity
Surveyor
Mechanical &
Electrical
Engineers
Civil &
Structural
Engineers
ManagementContractor
Works -
Contractors
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
16/17
Project Procurement Methods
Public Private Partnerships (PPP)
Employer
Design team
Project
manager
Finance
Suppliers
Main Contractor
Sub -
Contractorss
-
7/27/2019 TCM 303-05 Power Point Slides - Unit 1
17/17
Thank you