tata steel, india - paul...

4
TATA STEEL, India Upgrade of Blast Furnace “G” 2005 Blast Furnace Constructions, Rebuilds & Relines

Upload: lamduong

Post on 10-May-2018

244 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: TATA STEEL, India - Paul Wurthbrochures.paulwurth.com/iron/...Constructions-Tata-Steel-BF-G-en.pdf · TATA STEEL, India Upgrade of Blast Furnace “G” 2005 Blast Furnace Constructions,

TATA STEEL, India

Upgrade of Blast Furnace “G”2005

Blast Furnace Constructions, Rebuilds & Relines

Page 2: TATA STEEL, India - Paul Wurthbrochures.paulwurth.com/iron/...Constructions-Tata-Steel-BF-G-en.pdf · TATA STEEL, India Upgrade of Blast Furnace “G” 2005 Blast Furnace Constructions,

Introduction

During the 12 years’ life of its first cam-paign, BF “G” produced 14 million tons of hot metal. The upgrading work was undertaken to enhance the capacity of the furnace to 1.8 MTPA and a projected minimum life of 15 years, using state-of-the-art technology.

Tata Steel chose Paul Wurth as technologi-cal supplier in association with L&T for the upgrade of BF “G”.

Project Realisation

To achieve a cost effective upgrade, a critical study of existing and proposed new facilities, and striking a judicious balance between old and new facilities, was carried out. In addition to capacity enhancement, the upgraded “G” furnace has been equipped with a sophisti-cated monitoring and control system and an up-to-date automation system to enable the furnace to produce high quality hot metal at the lowest cost.

To minimize the shutdown period, a project monitoring system comparable to the world’s best practices was put in place to execute the project in optimum time. A substantial quantity of work was completed during the pre-shutdown period while the furnace was in operation. Areas of concerns were: Safety hazards of BF gas, space constraint, working at heights.

Project Description

Supermicropore hearth carbon blocks

Gas cleaning plant Blow-in

Project Data

Project overall duration (from order placement to blow-in) : 24 months

Pre-shutdown activities : 15 months

BF shutdown activities : 125 days

Blow-in date : 6 April 2005

Major Technical Reline Objectives

` increase of working volume from 1 581 m3 to 2 308 m3

` improve BF cooling by introduction of copper staves and 5 closed loop cooling circuits

` provision of a new 2nd casthouse

` extension of cooled surface area

` hearth geometry/materials quality upgrade

Page 3: TATA STEEL, India - Paul Wurthbrochures.paulwurth.com/iron/...Constructions-Tata-Steel-BF-G-en.pdf · TATA STEEL, India Upgrade of Blast Furnace “G” 2005 Blast Furnace Constructions,

Services

` Basic engineering and detail engineering for selected items

` Supervision of detail engineering developed in India (for critical items)

` Supervision and testing of critical items manufactured in India

` Supervision of erection, commissioning and performance tests

Supplies

` Raw material preparation

y Upgrade of existing stockhouse equipment

y Remote flow control for ore and sinter

` Furnace top equipment

y Expansion of hopper volume

y New bleeder valves

y Increased length of rotating chute

` Furnace body

y Introduction of stave coolers (copper & cast iron)

y Profilemeter for improvement in burden distribution *

y Introduction of supermicropore carbon in hearth

` Coal injection

y Enhancement of coal injection capacity up to 200 kg/tHM

y Installation of one new additional coal mill (15 tph)

` Stoves

y Hydraulic actuation of stove valves

` Cooling system

y Demin water system for stave coolers

y Five separate closed cooling circuits

` Casthouse equipment *

y New powerful hydraulic drill machines & mud gun

y Splash cover manipulator

y Provision of a new 2nd casthouse

` Gas Cleaning Plant

y Introduction of ceramic tiles in cyclone

y Improvement in venturi scrubber

y Addition of external demister

Paul Wurth Reline Scope

Phases of shell erection

Bustle pipe gunniting

Major Technical Reline Objectives

` increase of working volume from 1 581 m3 to 2 308 m3

` improve BF cooling by introduction of copper staves and 5 closed loop cooling circuits

` provision of a new 2nd casthouse

` extension of cooled surface area

` hearth geometry/materials quality upgrade

Blast Furnace Data

Daily Production : 5 150 tHM

Hearth Diameter : 11.05 m

BF working volume : 2 308 m3

BF inner volume : 2 648 m3

Top pressure : 1.5 bar g

Tuyeres : 30

Number of tapholes : 2

Tuyere injection : PCI

Page 4: TATA STEEL, India - Paul Wurthbrochures.paulwurth.com/iron/...Constructions-Tata-Steel-BF-G-en.pdf · TATA STEEL, India Upgrade of Blast Furnace “G” 2005 Blast Furnace Constructions,

International presence:Brazil, Chile, Czech Republic, Germany, India, Italy, Japan, Korea, Mexico, P.R. China, Russia, South Africa, Taiwan, Ukraine, U.S.A., Vietnam

© Copyright 2005-2015 Paul Wurth S.A. – all rights reserved

Non Contractual Data: Paul Wurth believes that the data contained in this folder are correct and accurate, but cannot guarantee same or better performances for any specific site without a detailed quote. Patents and Patents pending. — Paul Wurth equipment and processes are protected in many countries by patents.

Paul Wurth, the Paul Wurth Logo, Bell Less Top and BLT are trademarks of Paul Wurth S.A. and may be registered in your jurisdiction.

VCA**CER

TIFIED SAFETY SYSTEM

VINCOTTE

ISO 9001ISO 14001

BUREAU VERITASCertification

Technical Highlights

Paul Wurth S.A.32, rue d’AlsaceL-1122 LuxembourgPhone: (+352) 4970-1Fax: (+352) [email protected]

* TMT – Tapping Measuring Technology, a joint company of Dango & Dienenthal and Paul Wurth.

Bell Less Top®

Copper staves

Casthouse *Furnace shell lifting by crane

Blast furnace “G” Hot stoves & blast furnace