Task 6: Short Period Nb3Sn Superconducting Helical Undulator
Jim Clarke/George Ellwood28/11/2012
![Page 2: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/2.jpg)
Contents• Goals• Status• Testing• Schedule
2
![Page 3: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/3.jpg)
3
NbTi Helical Undulator• Final Parameters:
• 215A
• Beam tube ID: 4.7 mm
• Winding ID: 6.35 mm
• Field on axis: 0.86 T
• Margin with this conductor: 30%
![Page 4: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/4.jpg)
(Revised) Goals• To create two identical undulators with Nb3Sn
• 300mm long and direct comparison with previous NbTi undulators
• The same period, diameter, winding groove etc as NbTi
4
![Page 5: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/5.jpg)
Supercon – final wire choice
5
•Field on axis 1.2T 40%> NbTi
•Operating current 720A
•Peak field on conductor 3.5T
![Page 6: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/6.jpg)
Supercon Test Results from CERN
6
• Operating current 720A required
• Wire will quench at <4T
• Not ideal but we will gain useful experience by winding an undulator with this wire
• So, we will wind two 300mm helical undulators and measure their performance in terms of quench, stability, and peak field
![Page 7: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/7.jpg)
Alumina Coating
7
50µm Alumina plasma sprayed coating.
This has been electrically tested to over 1000V without breaking down.
![Page 8: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/8.jpg)
Heat treatment and vacuum impregnation tooling
8
![Page 9: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/9.jpg)
1st Milestone Undulator
9
Now fully fabricated, wound, impregnated and heat treated – ready for tests
![Page 10: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/10.jpg)
10
![Page 11: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/11.jpg)
11
![Page 12: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/12.jpg)
12
![Page 13: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/13.jpg)
13
![Page 14: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/14.jpg)
14
![Page 15: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/15.jpg)
Testing• No suitable test cryostat at RAL• LASA Milan (Giovanni Volpini) have kindly
offered to carry out the tests of both undulators
• Thanks to Amalia/CERN and Frank/KIT for also trying to fit us in!
15
![Page 16: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/16.jpg)
4.3mm diameter bore
Arepoc Hall probe mounted on a carbon fibre rodMaximum diameter 4mm
![Page 17: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/17.jpg)
• Good interaction with LASA• Drawings developed• Interfaces all being considered
17
![Page 18: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/18.jpg)
Schedule• Undulator 1 ready for test now• Undulator 2 ready for test by end December• Both undulators should be tested at LASA by
mid Feb 2013.• Test one after the other ~3 days each• Simple peak B field check with Hall probe and
magnet performance as function of current
18
![Page 19: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/19.jpg)
Summary• We are still on target to achieve our goals by
the end of M48• We have completed the first undulator, fully
impregnated and heat treated• Second undulator to follow shortly• Tests will be carried out at LASA Milan
19
![Page 20: Task 6: Short Period Nb 3 Sn Superconducting Helical Undulator Jim Clarke/George Ellwood 28/11/2012](https://reader035.vdocuments.site/reader035/viewer/2022062518/5697bf881a28abf838c89737/html5/thumbnails/20.jpg)
Acknowledgements• Many thanks to our colleagues at LASA, CERN,
KIT and others within HFM without whom we would not have been able to achieve our goals
20