Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017 Page 1 of 14 Tank Farm Plant Operating Procedure 242-A Evaporator USQ # EV-17-0516-S, Rev. 0 CHANGE HISTORY ( LAST 5 REV-MODS ) Rev-Mod Release Date Justification: Summary of Changes A-2 04/25/2017 Operations request to reflect current location. Page 13 bottom row modified PD-2 to PD-1 A-1 07/14/2016 Inconsequential change Updated records section. A-0 03/12/2015 New Procedure Standalone Procedure for Stack Monitoring Table of Contents Page 1.0 PURPOSE AND SCOPE ................................................................................................................ 3 1.1 Purpose................................................................................................................................ 3 1.2 Scope ................................................................................................................................... 3 2.0 INFORMATION............................................................................................................................. 3 2.1 General Information ............................................................................................................ 3 2.2 Terms and Definitions......................................................................................................... 3 3.0 PRECAUTIONS AND LIMITATIONS......................................................................................... 4 3.1 Personnel Safety.................................................................................................................. 4 3.2 Equipment Safety ................................................................................................................ 4 3.3 Radiation and Contamination Control ................................................................................ 4 3.4 Environmental Compliance ................................................................................................ 4 3.5 Limits .................................................................................................................................. 4 4.0 PREREQUISITES .......................................................................................................................... 5 4.1 Special Tools, Equipment, and Supplies............................................................................. 5 4.2 Performance Documents ..................................................................................................... 5 4.3 Field Preparations ............................................................................................................... 5 5.0 PROCEDURE ................................................................................................................................. 6 5.1 Operate the Stack Monitoring Cabinet ............................................................................... 6 5.2 Start the Stack Monitoring Cabinet in REMOTE Mode on the MCS ................................ 8 5.3 Start Stack Monitoring Cabinet Locally (K1-ENCL-400) in AUTO ................................. 9 5.4 Switch/Swap Sample Pumps............................................................................................. 10

Upload: others

Post on 18-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

1 of 14

Tank Farm Plant Operating Procedure 242-A Evaporator

USQ # EV-17-0516-S, Rev. 0

CHANGE HISTORY ( LAST 5 REV-MODS )

Rev-Mod Release Date Justification: Summary of Changes

A-2 04/25/2017 Operations request to reflect

current location. Page 13 bottom row modified PD-2 to PD-1

A-1 07/14/2016 Inconsequential change Updated records section.

A-0 03/12/2015 New Procedure Standalone Procedure for Stack Monitoring

Table of Contents Page

1.0 PURPOSE AND SCOPE ................................................................................................................ 3

1.1 Purpose ................................................................................................................................ 3

1.2 Scope ................................................................................................................................... 3

2.0 INFORMATION............................................................................................................................. 3

2.1 General Information ............................................................................................................ 3

2.2 Terms and Definitions......................................................................................................... 3

3.0 PRECAUTIONS AND LIMITATIONS......................................................................................... 4

3.1 Personnel Safety.................................................................................................................. 4

3.2 Equipment Safety ................................................................................................................ 4

3.3 Radiation and Contamination Control ................................................................................ 4

3.4 Environmental Compliance ................................................................................................ 4

3.5 Limits .................................................................................................................................. 4

4.0 PREREQUISITES .......................................................................................................................... 5

4.1 Special Tools, Equipment, and Supplies............................................................................. 5

4.2 Performance Documents ..................................................................................................... 5

4.3 Field Preparations ............................................................................................................... 5

5.0 PROCEDURE ................................................................................................................................. 6

5.1 Operate the Stack Monitoring Cabinet ............................................................................... 6

5.2 Start the Stack Monitoring Cabinet in REMOTE Mode on the MCS ................................ 8

5.3 Start Stack Monitoring Cabinet Locally (K1-ENCL-400) in AUTO ................................. 9

5.4 Switch/Swap Sample Pumps............................................................................................. 10

Page 2: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

2 of 14

5.5 Restore sample pumps after fan swap or short term shutdown ........................................ 10

5.6 Shutdown of the Stack Monitoring System ...................................................................... 11

5.7 Records ............................................................................................................................. 12

Checklist 1 – Electrical Configuration Control ........................................................................................ 13

Signature Sheet 1 ...................................................................................................................................... 14

Page 3: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

3 of 14

1.0 PURPOSE AND SCOPE

1.1 Purpose

To provide instructions for the startup, operation, and shut down of the 242-A Ventilation

Stack Monitor System.

1.2 Scope

This procedure applies to the 242-A Ventilation Stack Monitor System and its associated

instrumentation and controls.

2.0 INFORMATION

2.1 General Information

2.1.1 None.

2.2 Terms and Definitions

AFC - Automatic Frequency Control

SOE - Stationary Operating Engineer

VCS - Ventilation Control System

VFD - Variable Frequency Drive

Page 4: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

4 of 14

3.0 PRECAUTIONS AND LIMITATIONS

3.1 Personnel Safety

3.1.1 Routine K1 system shutdown does not require the condenser room access to

be restricted.

3.2 Equipment Safety

3.2.1 None.

3.3 Radiation and Contamination Control

3.3.1 Follow radiological work planning process(s) contained in

TFC-ESHQ-RP_RWP-C-03, ALARA Work Planning.

3.4 Environmental Compliance

3.4.1 To ensure reporting requirements are met, all unplanned outages of the K-1

exhaust ventilation system to include the exhaust monitoring systems, must

be immediately reported to the appropriate Shift Office and Environmental

per TF-REC-001.

3.4.2 Operation of the K-1 exhaust ventilation system without the exhaust

monitoring systems should be minimized and not occur until the appropriate

Shift Office and Environmental are notified per TF-REC-001.

3.4.3 Shutdown of the K-1 ventilation exhaust system in co-junction with the

vessel vent for periods of time greater than or equal to 24 hours requires the

implementation of ALARACT 29.1 controls. (TFC-ESHQ-ENV-STD-06)

3.5 Limits

3.5.1 None.

Page 5: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

5 of 14

4.0 PREREQUISITES

4.1 Special Tools, Equipment, and Supplies

None.

4.2 Performance Documents

TO-620-020, Operate the 242-A Evaporator Ventilation System.

4.3 Field Preparations

4.3.1 IF starting the HVAC system up after a power outage or when exhausters

have been secured for greater than 24 hours, PERFORM Checklist 1, to

ensure proper line up of electrical systems.

Page 6: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

6 of 14

5.0 PROCEDURE

5.1 Operate the Stack Monitoring Cabinet

NOTE - Activity Levels of Section 5.1 may be performed as directed by Shift Manager.

- Switching or shutting down Exhaust Fans will shut down the operating sample

pump and activate alarms (Low Beta Sample Flow, Low Record Sample Flow,

Pump #1 Failure and #2 Failure). Vacuum pumps will not start unless alarms

(Low Beta Sample Flow, Low Record Sample Flow, Pump #1 Failure and #2

Failure) have been cleared.

- Stack Monitoring cabinet K1-ENCL-400 is powered from distribution panel

A242-DP-L, by way of MCC-2 Compartment A3.

- When starting sample pumps flow will normally stabilize in 1-3 minutes.

Initial Start Up of K1-ENCL-400 Stack Monitoring Cabinet

5.1.1 CHECK enclosure K1-ENCL-400 is energized.

5.1.1.1 IF K1-ENCL-400 is not energized, PERFORM Electrical

Configuration per Checklist 1 AND

CONTINUE with this section.

5.1.2 OPEN door of K1-ENCL-400 stack sampling cabinet.

Page 7: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

7 of 14

5.1 Operate the Stack Monitoring Cabinet (Cont.)

5.1.3 PERFORM stack sampling cabinet valving located in K1-ENCL-400 as

follows.

K1-ENCL-400 Valving

I.D.# Description Position Complete

()

HV-3 BETA MONITOR ISOLATION OPEN

HV-4 RECORD SAMPLE ISOLATION OPEN

HV-5 FIT-1 SIGNAL, STACK FLOW MASS-TRON II

(INPUT) OPEN

HV-6 FIT-1 SIGNAL, STACK FLOW MASS-TRON II

(OUTPUT) OPEN

HV-7 FITC-2 SIGNAL, BETA MONITOR MASS-TRON II

(INPUT) OPEN

HV-8 FITC-2 SIGNAL, BETA MONITOR MASS-TRON II

(OUTPUT) OPEN

HV-9 FITC-3 SIGNAL, RECORD SAMPLE MASS-TRON II

(INPUT) OPEN

HV-10 FITC-3 SIGNAL, RECORD SAMPLE MASS-TRON II

(OUTPUT) OPEN

HV-11 PITC-4 SIGNAL OPEN

5.1.4 CLOSE door on the K1-ENCL-400 stack sampling cabinet.

5.1.5 IF any alarms on front of K1-ENCL-400 cabinet are active,

PRESS ALARM RESET push button PB-6.

NOTE - Placing selector switch SW-1 in the AUTO position for both the

LOCAL (K1-ENCL-400) and REMOTE (MCS) activates the

AUTOMATIC Sample Pump switch over functions. Either PB-1 or PB-2

buttons being latched in will defeat the auto pump switch.

- Placing selector switch SW-1 in the HAND position will not allow Sample

Pump switch over to occur.

5.1.6 CONFIRM selector switch SW-1 is in the AUTO position.

5.1.7 CONFIRM PB-1 and PB-2 are not LATCHED IN.

5.1.8 IF starting the sample pumps from the MCS, GO TO Section 5.2.

5.1.9 IF starting the sample pumps LOCALLY at K1-ENCL-400,

GO TO Section 5.3.

Page 8: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

8 of 14

5.2 Start the Stack Monitoring Cabinet in REMOTE Mode on the MCS

5.2.1 GO TO Graphic Screen (G22) AND

PERFORM the following:

5.2.1.1 CLICK switch HS-1-1 icon AND

SELECT Accept.

5.2.1.2 WAIT approximately 30 seconds.

5.2.1.3 CHECK flow is indicated at FI-1-1 and FI-1-2.

5.2.1.4 WHEN flow has stabilized on FI-1-1 and FI-1-2 at 1.9-2.1

SCFM, PRESS PB-6 at K1-ENCL-400 to clear alarms.

5.2.1.5 IF alarms did not clear, INFORM Shift Manager.

Page 9: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

9 of 14

5.3 Start Stack Monitoring Cabinet Locally (K1-ENCL-400) in AUTO

5.3.1 TO start sample pump locally at the K1-ENCL-400,

PRESS push button PB-3.

5.3.2 WAIT approximately 30 seconds.

5.3.3 CHECK sample pump run status, PUMP #1 ACTIVATED lamp is LIT,

OR

CHECK sample pump run status, PUMP #2 ACTIVATED lamp is LIT.

5.3.3.1 CONFIRM CB3 is ON.

a. IF sample pump did not start, CYCLE selector switch

SW-1 to OFF then back to AUTO one time only AND

GO TO Step 5.3.1,

OR

IF sample pump still will not start,

NOTIFY the Shift Manager.

5.3.4 ALLOW flow to stabilize on both FITC-2 and FITC-3 at 1.9-2.1 SCFM.

5.3.5 IF in Alarm, PRESS ALARM RESET push button PB-6.

5.3.5.1 IF alarms do not clear, INFORM Shift Manager.

Page 10: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

10 of 14

5.4 Switch/Swap Sample Pumps

5.4.1 IF switching the sample pumps REMOTELY on the MCS,

GO TO Step 5.4.3.

5.4.2 IF switching the sample pumps LOCALLY at K1-ENCL-400, using AUTO

position GO TO Step 5.4.4.

5.4.3 TO switch the sample pumps REMOTELY on the MCS,

GO TO Graphic Screen (G22).

5.4.3.1 CLICK hand switch HS-1-2 AND

SELECT Accept.

5.4.3.2 WAIT until flow on FI-1-1 and FI-1-2

has stabilized at 1.9-2.1 SCFM.

5.4.3.3 PRESS ALARM RESET push button PB-6

located at K1-ENCL-400.

5.4.3.4 CHECK alarms have cleared.

5.4.3.5 IF alarms did not clear, INFORM Shift Manager.

5.4.4 TO switch the sample pumps LOCALLY in AUTO position

at K1-ENCL-400, PRESS push button PB-5.

5.4.4.1 WAIT until flow on FITC-2 and FITC-3

has stabilized at 1.9 - 2.1 SCFM.

5.4.4.2 PRESS ALARM RESET button PB-6.

5.4.4.3 CHECK all lights and alarms have cleared.

5.4.4.4 IF alarms do not clear, INFORM Shift Manager.

5.5 Restore sample pumps after fan swap or short term shutdown

5.5.1 AT K1-ENCL-400, PRESS PB-6 Alarm Reset AND

WAIT 30 seconds for pump to start.

5.5.2 ALLOW flow to stabilize on FITC-2 and FITC-3 at 1.9-2.1 SCFM and

PRESS PB-6 Alarm Reset.

Page 11: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

11 of 14

5.6 Shutdown of the Stack Monitoring System

5.6.1 IF shutting down the sample Pump remotely on the MCS, PERFORM the

following:

5.6.1.1 GO TO Graphic Screen (G22).

5.6.1.2 CLICK on switch HS-1-1 icon AND

SELECT Accept.

5.6.1.3 IF full valve out of the sample cabinet is required,

GO TO Step 5.6.3.

5.6.2 IF shutting down the Sample Pump LOCALLY at K1-ENCL-400,

PERFORM the following:

5.6.2.1 PRESS PB-3 Start/Stop button.

5.6.2.2 TURN selector switch SW-1 to the OFF position.

5.6.3 IF required by Shift Manager, PERFORM stack sampling cabinet valving

located in K1-ENCL-400 as follows:

K1-ENCL-400

I.D.# Description Position Complete

()

HV-3 BETA MONITOR ISOLATION CLOSED

HV-4 RECORD SAMPLE ISOLATION CLOSED

HV-5 FIT-1 SIGNAL, STACK FLOW MASS-TRON II

(INPUT) CLOSED

HV-6 FIT-1 SIGNAL, STACK FLOW MASS-TRON II

(OUTPUT) CLOSED

HV-7 FITC-2 SIGNAL, BETA MONITOR MASS-TRON II

(INPUT) CLOSED

HV-8 FITC-2 SIGNAL, BETA MONITOR MASS-TRON II

(OUTPUT) CLOSED

HV-9 FITC-3 SIGNAL, RECORD SAMPLE MASS-TRON II

(INPUT) CLOSED

HV-10 FITC-3 SIGNAL, RECORD SAMPLE MASS-TRON II

(OUTPUT) CLOSED

HV-11 PITC-4 SIGNAL CLOSED

Page 12: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

12 of 14

5.7 Records

5.7.1 PERFORM the following for records identified within this procedure.

5.7.1.1 RECORD the number of times the record was generated in

applicable column

OR

PLACE a check mark () in the N/A column.

5.7.1.2 SUBMIT the package to FWS/OE/Shift Manager.

Records Submittal Checklist

Number

of times

completed

N/A

()

5.1 Operate the Stack Monitoring Cabinet

Step 5.1.3

5.6 Shutdown of the Stack Monitoring System

Step 5.6.3

5.7 Records

Step 5.7.2

Checklists

Checklist 1 – Electrical Configuration Control

Signature Sheets

Signature Sheet 1

5.7.2 FWS/OE/Shift Manager SEND the completed records to the Central Shift

Office for records retention.

/ /

Signature Print (First & Last) Date

FWS/OE/Shift Manager

The record custodian identified in the company-level Records Inventory and Disposition

Schedule (RIDS) is responsible for record retention in accordance with

TFC-BSM-IRM_DC-C-02.

Page 13: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

13 of 14

Checklist 1 – Electrical Configuration Control

ALL CONTROL SYSTEMS

(main feed then equipment)

COMPONENT

DESCRIPTION LOCATION

DESIGN

REFERENCE

REQUIRED

POSITION AS-FOUND AS-LEFT Initials

Stack Monitoring Cabinet

Cabinet Inst.

CB-1

Stack Monitoring

Cabinet

H-2-99085, Sht 41 ON

Sample Pumps

Motor Starter

Circuit

CB-2

Stack Monitoring

Cabinet

H-2-99085, Sht 42 ON

Sample Pumps

P1 & P2

CB-3

Stack Monitoring

Cabinet

H-2-99085, Sht 42 ON

Heaters/Air

Conditioning

Circuit

CB-4

Stack Monitoring

Cabinet

H-2-99085, Sht 42 ON

Heat Trace

CB-5

Stack Monitoring

Cabinet

H-2-99085, Sht 42 ON

Stack Monitoring

Cabinet

PD-1 Outside of

Cabinet H-2-99085, Sht 41 ON

Page 14: Table of Contents Page - emcbc.doe.gov · Operate the 242-A Evaporator Ventilation Stack Monitor System Type CONTINUOUS Document No. TO-620-021 Rev/Mod A-2 Release Date 04/25/2017

Operate the 242-A Evaporator Ventilation Stack Monitor System

Type

CONTINUOUS Document No.

TO-620-021 Rev/Mod

A-2 Release Date

04/25/2017 Page

14 of 14

Signature Sheet 1

All persons participating in the performance of this procedure shall enter their printed name, signature

and initials below.

Name (Print) Signature Initials