    Tender Documents for

    Dismantling/Structural fabrication/erection

    of structure and equipments

    For debottlenecking of

    Blast Furnace No#1

    Sesa Industries Ltd.,

    Pig Iron Plant. Amona

    Dismantling/structural fabrication/erection of

    structure, equipment & refractory

  • 8/8/2019 T 7 Services Structural Annexure

    2/18

    Page 2 of 18

    Tendering Document No.:

    DETAIL INDEX FOR PRELIMARY DOCUMENT FOR TENDERINGSr. No. Description Page No

    01 General 0302 Project schedule 0403 Scope 0404 Detailed scope of work 04 A Mechanical

    B Refractory 06C Civil 06D Electrical and Inst 0705 General guidelines to tenderer 08 A Mechanical B Refractory 09C Civil 09D Electrical and Inst 0906 Instruction to tenderer 1007 Wastage 11

    08 Tolerance in workmanship 1209 Special Note 13 Annexure 1: Mechanical Annexure1a: Bill of Material 14 Annexure1b: piping Annexure 1C: hydraulic Piping 16 Annexure 2: Electrical Annexure 3: Instrumentation Annexure4: refractory Annexure5:Civil

  • 8/8/2019 T 7 Services Structural Annexure

    3/18

    Page 3 of 18

    1.GeneralM/s SESA INDUSTRIES LTD. (SIL) a group company of Vedanta Plc., a UK Stockexchange listed company, is presently operating two blast furnaces, each of 173 m3working volume in its existing plant at Amona, Goa. The two blast furnaces, named asBF1 and BF2 are producing around1.4 lac MT of hot metal per year from each . Thefurnaces were initially designed for 0.75 lac MT of hot metal per year by Tata Korfduring their commissioning in 1992 and 1994. Over a period of time, throughimprovement in furnace peripheral system and with better operational practices theproduction capacity has been increased to its present level. With the increase inproduction, other facilities like hot metal handling, hot metal runner length, etc. became

    just adequate to handle the hot metal produced and proving to be a bottleneck in thesystem. Any further improvement in production demanded de-bottlenecking of thesefacilities.

    BF 1 is running in its fifth campaign since May 2006 and SIL has planned a capacityincrease of this furnace to 215 m3 along with its relining from March 2010 to April 2011.SIL also plans to introduce Pulverised Coal Injection (PCI), Oxygen (O2) Enrichment andSinter in due course of time to improve the productivity. As a result, to handle theincreased hot metal production, the de-bottlenecking of allied facilities will also be takenup along with upgradation of blowing capacity and raw material handling facility.

    This is part of the tender inquiry is for services of Mechanical, Civil, Refractory,

    Electrical and Instrumentation.

  • 8/8/2019 T 7 Services Structural Annexure

    4/18

    Page 4 of 18

    2 PROJECT SCHEDULE:The Blast furnace will be shut down for upgradation from 1

    st

    March for 55days (consideringshutdown to start up) and the tenderer shall complete execution of all the jobs as perrespective offer within this schedule.

    All prefabrication (e.g. steel fabrication with its painting, concrete foundations, shifting ofequipments from fabrication yard to erection site, dismantling of pg casting machineetc)shall be completed by February 20, 2010.

    3 SCOPE :The tenderers scope of work shall be for services of following areas;

    1 Civil2 Mechanical (Structural fabrication , erection , dismantling and Equipment erection)3 Electrical & Instrumentation4 Refractory

    Tenderers brief general scope will be as follows;1 Shell of BF, Stave cooler,casthouse modification including eqipments2 Gas cleaning sytem3 Blower house4 Platforms and monorails etc.

    5 Hot Blast Main modification, Bustle pipe, up takes, down comer, Gas line ducts and allother ducts.

    6 Truss, purlins,etc.7 Platforms, Walkways, Access Stairs, Ladders, Duct supports, Monorails, Crane girders,

    rail, etc.8 Conveyors bins, bunker and structures9 Hot metal crane parts dismantling and fixing10Pig casting machine with hydraulic tilter

    DETAILED SCOPE OF WORK:

    MECHANICAL

    Dismantling of structures and equipmentExisting BF Shell with stiffeners and bustle pipeCast house Platform, runners and slag pitCast house equipments like Mudgun, Tap hole Drill machine, blow pipes, tuyer and

    tuyere coolerCast house shed, truss purling

    All Maintenance platforms attached to shell including connecting stairwaysAll cooling water pipeline, steam line and compress air line.

  • 8/8/2019 T 7 Services Structural Annexure

    5/18

    Page 5 of 18

    Back draft valve and back draft stack.Uptake, down comer and equalisation duct.

    Furnace top EquipmentEqualisation valves and hydraulic systemFurnace top Walk waysBleeder valvesGas Cleaning System including Dust catcher, Saturator, Venturies and Cyclone, flare

    stack, etcGas cleaning system Platform and stairwaysGas line, Pipeline and valvesCharging conveyor CB5, CB4 and CB 311, Weighing Bins and bunkersPig Casting Machine 2nosLadle Tilter -1 noComplete Roof sheetingHot Blast & other stove valveBlower equipments dismantling and duct

    Fabrication of steel structuresFabrication of shell (Mock trials)Fabrication of Platforms, Staircase, hand railing and monkey laddersFabrication of ducts like bustle pipe, Uptake and down comerEqualisation dust

    Four pole/leg structureDust catcher, Saturator, Interconnecting ducting, Dri-pot, pipelineColumns, trusses, purlins etcTemporary PlatformsConveyor structuresBins & Fixing of liner platesOther Misc structures

    Erection of steel structures and equipmentsShell including base plate preparationCooling stave including all caps etcFour pole/leg structure including maintenance platformBustle pipeBack draft valve, duct and supportCooling pipe for carbon blocks and chimneyCast house equipments like Tap hole drill machine, Mud gun mass, Blow pipe, Power

    pack, tuyeres, tuyer cooler, heating pipe etcInterconnection of hot blast main and bustle.Uptake and down comers

    Hot Blast & other stove valveTemping Nozzle, RTD

  • 8/8/2019 T 7 Services Structural Annexure

    6/18

    Page 6 of 18

    Furnace top equipment like charging hopper, fixed hopper, Upper bell, Lower bell,hydraulic system, bleeders, equalisation valve, stock rods etc.

    Furnace top platforms and staircaseGas cleaning system like Dust catcher, saturator, interconnecting ducting, venture-s,Cyclone, flare stack, etc.Gas cleaning system Platform and staircase.Column platform and staircasesCharging conveyor CB5, CB4 and CB 311, Weighing Bins and bunkersPig Casting Machine 1 NosNew Ladle Tilter -1 no and dismantling & erection of old mechanical tilter.Complete Roof sheetingHot Blast & other stove valveGas line ducts, drip pot, valves, pipingHydraulic pipingBlower equipment erection and duct work.

    REFRACTORYDismantling of Refractory:Coke raking and BF bricks dismantlingCast house soling bricksMain Runner, Emergency Launder, Salamander launder and PCM launderBack draught pipe, blow pipe etcEntire Bustle pipe and Hot blast main of certain length.

    Refractory Lining:Blast furnace along with stave cooling system.Bustle pipe and Hot blast main of dismantled length.Soling of the cast house platform.Main runner, Emergency Launder, and PCM.Back draught pipe, blow pipe.Gunniting of castable to up take, down comer, and dust catcher.

    CIVILBreaking and shifting of RCC structuresExisting GCS structure foundationsCast house RCC platformsSlag pit raft and vertical RCC wallsBlower foundationBreaking of RCC flooring at pig yardBreaking of RCC flooring at Glendon areaConcretingRaft columns pedestals. Drains for Gas cleaning structuresCast house RCC platforms

    Slag pit raft and vertical RCC wallsBlower foundation

  • 8/8/2019 T 7 Services Structural Annexure

    7/18

    Page 7 of 18

    RCC flooring at pig yard

    ELECTRICAL AND INSTRUMENTATION:Detail scope of Job involve Up gradation of panel HT panel, Dismantling of Old cable& laying of new cable, Removal of old equipment & installation of new equipment.

    Panel up gradationRemoval of old set of cast resin current transformerInstallation of new set of current transformerTesting & commissioning of breaker

    Cable laying & cable removalCable removal means removal of glanding, termination, De-clamping of cable fromthe cable tray & removal of cable from tray/trench & shifting to store yard.Cable laying means, laying of cable on M.S/G.I cable tray or cable trench with therequired supports at an interval of as instructed by the company Engineer.

    Cable testingAll High voltage test, Leakage current test, IR value test

    Dismantling of Electrical equipmentRemoval of blowers from the foundation & shifting it to the location

    HT capacitor including mounting frameTransformer oil to be drained from the radiators. Radiators to be isolated & separatedfrom the transformer before lifting of transformer.Panel to be decoupled & dismantled at the place in sections so as to ease the removal& shifting

    Installation of blowerBlower Installation includes taking the delivery of the material from Sesas

    stores, shifting to site & installation of the motor on the foundation frame asinstructed by the company Representative.

    Installation of transformerShifting of transformer & installation on existing foundation.

    Assembly of transformer accessories like radiator, conservator tank,breather etc.Filteration of oilConnection of cables (HV,LV-1 & LV-2)Liasoning & taking approval from the Electrical inspector.

    Installation of PanelShifting of panel to siteFabrication of M.S base frame for the panel

  • 8/8/2019 T 7 Services Structural Annexure

    8/18

    Page 8 of 18

    4. GENERAL GUIDELINES TO THE TENDERER:

    i) The jobs carried out in the SIL premises shall require proper safety attention as per norms laiddown by SIL.

    ii) All activities inside SIL premises shall be carried out in close supervision. Tenderer shall deploy asafety steward round the clock to monitor the safety at all job sites

    iii)Mobilize all labourers-skilled, semi-skilled, riggers, fabricators, certified welders, pipefitter,instrument tube fitter, licensed electricians, mechanics, foreman, masons, helpers, carpenters, tile

    fitters, etc.

    iv)All structural steel materials, roofing sheets, liners, cables, panels, bricks, cement, constructionsteel etc the tenderer should collect from SILs yard.

    v) Loading, transportation from site of fabrication to site of erection, unloading at site of erection

    including multiple handling of all steel structural components/ units assemblies complete in allrespects

    vi)All defective materials / works which do not conform to the specification shall be dismantled andremoved from site by the Contractor at his own cost

    4.1 Mechanical:

    i) Fabrication of steel structural components covered under design drawings and fabricationdrawings/sketches and generally described under the scope of the project.

    ii) Cold straightening of sections and plates, whenever they are bent and kinked including checkingmaterials received from SIL in respect of defects like crack , lamination etc.

    iii)Making arrangements for and providing all facilities for conducting ultrasonic, x-ray or gamma raytests on butt welds, getting the test conducted by reputed testing laboratories, making available test

    films/graphs, reports and interpretation.

    iv)Dismantling of all steel structures shall be done by the tenderer by proper planning and withsafety at top most priority.

    v) Dismantled material/ equipments shall be immediately transported to scrap yard/ assigned area bythe tenderer by own vehicles.

    vi)Blast cleaning shall be done by copper slag blasting or shot blasting as per following grades toSwedish Standard. SIS 055900.Grade Sa-2

    1/2This involves very thorough blast cleaning. Mill

    scale, rust and foreign matter shall be removed to the extent that the only traces remaining are

    slight stains in the form of spot or strips. Finally, the surface is cleaned with a vaccum cleaner,

    clean dry compressed air or a clean brush. It shall then correspond in appearance to the prints

    designated as Sa-21/2

    vii)Application of paint shall be as per IS : 487-1985.viii) Fixing of installation materials on steam pipe lines, cold blast line, etc. Including all

    required materials as shown in the drawing or as directed by SGL representatives.

    ix)Painting and touching up of all equipment, pipes and technological structure, etc. As directed bySGL/EPSs representative

    x) Inspection, testing and commissioning of process and auxiliary equipment/piping andducting/hoisting and handling equipment, etc

    xi)Oxygen, LPG and argon cylinders used in gas cutting/welding shall be in the tenderer scope.

  • 8/8/2019 T 7 Services Structural Annexure

    9/18

    Page 9 of 18

    4.2 Refractory:

    i) The Lining should be under control supervision of company approved agency or company representative.

    ii) Contractor should line the furnace according the drawings provided to him.

    iii)Any deviations found in the drawing should bring to the notice of company representative.

    iv)Any deviations found in the lining, company have every right to get it rectified by the contractor without

    any extra cost to the company.

    4.3 Civil:i) All Civil jobs to be carried out as per drawingsii) Tenderer shall execute Civil jobs well within time prior to shut down

    iii) Contractor shall plan and sequence all works so as to achieve the desired progress keeping in mind overallsafety and stability at all points of time.

    iv) To ensure quality of construction, the Contractor shall ensure inspection and testing of all materials andworks like cement, aggregate, sand, bricks, concrete cubes & all other materials of construction as per

    instructions of the Client at his own cost conforming to specifications.

    v) Before covering up any work within excavated pits, clearance has to be taken from Engineer in writing inrespect of completion of said works as per drawing and specification

    vi) The latest Indian Standards shall become applicable. The respective Indian Standards wherever referred toin the specifications shall be deemed to be the latest

    4.4 Electrical and Instrumentation:i) Bidder should have required licences issued by competent authority which shall be valid to carry out job in

    Goa.

    ii) The contractor shall mobilize all manpower, skilled as well as semiskilled, erection and testing engineersand supervisors as required at site.

    iii) All tools and tackles like spanners, screw drivers; pliers shall be properly insulated wherever required andshall be certified by company representative.

    iv) For all materials Unloading, unpacking, packing, & storing at site is included in the Contractors scope.4.5 painting

    Sch

    No

    Paint details Make Surface

    preparati

    on

    composition Appx

    area in

    m2

    2 2 coats of Rust-O-Cap + 2coats of Acothane

    Polyurethene paint

    (DFT:2X100+2x50 micr)

    Asian /Berger Copperslag

    blasting

    Surface tolerant coatingwith acrylic aliphatic

    polyurethene coating

    5000

    3 1 coat of inorganic Zinc

    silicate Apcosil 605 & 2 coats

    of Apcotherm HR (DFT:

    75+70+70 micr)

    Asian /

    Berger

    Copper

    slag

    blasting

    Zinc slilcate for -90 to 600

    deg C & HR paint for

    +400deg C

    1000

    5 2 coats of HR aluminum paint

    (DFT:40+40 micr)

    Asian /

    Beger

    paints

    Manual

    cleaning

    Heat resistant aluminum

    paint alkyd basedsynthetic (250 degc)

    1000

  • 8/8/2019 T 7 Services Structural Annexure

    10/18

    Page 10 of 18

    5. INSTRUCTIONS TO THE TENDERER

    Sr

    No

    Item Name Description

    1 PPEs PPEs like hand gloves, helmets, safety shoes, safety goggles and nose mask

    should be taken from company stores on chargeable basis

    2 Aprons & dress All the contract labour should wear boiler suit (cotton )with name of contractor.

    Welders must wear apron while working

    3 Electrodes Following Welding electrodes are approved by company:

    E 6013

    Super Bond: Advani Oerlikon, Norma: D&H Secheron, Esab 36h: Esab

    E7018 approved as GR-3 of DNV/LRS/ABS/IRS etc.

    The approved brands and makes of electrodes shall be as follows:Super Base Advani Oerlikon , SuprathermD&H Secheron, Esab 36 H- Esab India make

    4 Welding

    Machine

    rectifier

    Welding machine should be 3Phase thyristorised rectifier with range of 10 to

    400A or 10 to 600A, 415V +/- 10,50Hz.Every machine should be fitted with 30

    milli amps earth leakage circuit breaker on the welding machine.

    5 Welding

    Transformer

    Welding machine should be 3Phase with range of 10 to 400A or 10 to 600A,

    415V +/- 10,50Hz.Every machine should be fitted with 30 milli amps earth

    leakage circuit breaker on the welding machine.

    6 Welding Cable Welding cable should be of copper with double insulation and confirming to IS

    9857-1990.It should withstand 600A current.50mm2 area for welding cable

    properly lugged7 Welding Holder Welding holder used should confirm IS 2641-1989 and should withstand

    600Amps. Holder should be fully insulated and it should also have spatter guard

    for welder.

    8 Heating ovens

    for rods

    Heating oven used shall be from a reputed supplier and should have a ELCB.

    9 Earthing Clamps Welding holder used should confirm IS 2641-1989 and should withstand

    600Amps. Holder should be fully insulated and it should also have spatter guard

    for welder.

    10 Cutting set

    trolley

    Cutting set trolley should have brake system and standard wheel as per company

    drawing. It should have cylinder locking arrangement and it should have proper

    handle.

    11 Hoses Hoses should confirm IS 477- 1990 and should be ofDunlopor Premier

    Make. Minimum 25 mtr in length

    Flash back arrestors, regulators & torches shall be of Messer /Esab / Advani-

    Oerlikon make only.

    12 Flash back

    arrestor,

    Regulator and

    torches

    Should be purchased from reputed company like

    Messer, Esab / Advani Oerlikar . Flash back arrester required in cylinder as well

    as torch side

    13 Grindingmachine Should be purchased from Bosch or other reputed company. It should have guardfor grinding wheel and handle should have insulation. Supply should be 230V

  • 8/8/2019 T 7 Services Structural Annexure

    11/18

    Page 11 of 18

    AG5/AG7 only.

    14 D shackles D Shackle from 0.5 T to 15 T should be available. All the D shackle should have

    test certificates..15 Wire rope and

    web slings

    Wire rope slings from 2 T to 15T should be available with test certificate.

    Contractor should have slings from 0.5 mt length to 4 mt length sling and of

    various capacities.

    16 Mobile cranes

    and Hydra

    Tenderer shall use hydraulic cranes (except crawler crane) as per the required

    capacity. SIL shall not arrange for this.

    17 Tools (hammer,

    spanner etc.)

    Tenderer shall use tools from a standard supplier.

    18 Full body safety

    harness

    Full body harness Ref PN22 with 2 forked lanyards Ref PN 351, made of 12mm

    3 strand twisted polyamide rope, length 1.8 metres with hook PN131. Make

    KARAM OR equivalent only after approval from company Maint Manager.

    19 Fixed drillingmachine

    Fixed drilling machine should be from reputed party and It should be ELCB.

    20 Service

    Vehicles/HCV

    Contractor should have Service Vehicles/HCV with valid documents like RC

    book, vehicle passing certificate, insurance for Road and insurance of vehicle.

    Reverse horn and side glasses are compulsory.

    21 Chain block Contactor should have chain block of reputed company like Indef ,etc and it

    should have test certificate. Company will have authority to recheck the chain

    block from companys certified party as partys cost. Length of the load carrying

    should be minimum 15 mts.

    22 Magnet drilling

    machine

    Magnet drilling machine should be from reputed company and should have

    ELCB. Supply will be 230V.

    23 Rolling machine Rolling machine should be from reputed company. Supply should be 415V +/-

    10,50Hz.

    24 Plate lifting

    tackles

    Plate lifting tackles of good party and it should have the load testing certificates

    25 Brick cutting

    machine, pan

    mixer,

    Tenderer shall use machines of standard suppliers and should have a ELCB

    26 pneumatic

    breaker, rammer

    Tenderer shall use breaker from reputed suppliers

    27 Hydraulic jack Hydraulic jack with valid test certificate to be used.

    28 Tile cuttingmachine

    Tenderer shall use machines of standard suppliers and should have a ELCB

    29 Concrete

    Vibrator

    Tenderer shall use machine from a standard supplier

    30 Concrete mixer Tenderer shall use machine from a standard supplier

    6 WASTAGE:

    Wastage of materials supplied by the Company shall be kept to the minimum. Reinforcement rods and

    structural steel sections will be supplied to the Contractor in available lengths. Off-cuts below 300mm in

    length in case of reinforcement and rolled structural steel sections and 300mm X 75mm in case of Plates

    shall be treated as non-recoverable scrap. A maximum of 2% of the weight of reinforcement work andstructural steelwork as measured and certified respectively will be allowed as non-recoverable scrap.

  • 8/8/2019 T 7 Services Structural Annexure

    12/18

    Page 12 of 18

    Reconciliation statement duly authorized by the Companys Engineer in charge for free issue items shall

    be submitted along with every running bill or as per demand of site engineers.

    Housekeeping:

    Contractor should maintain good housekeeping in the allotted area.All the scraps should be returned to

    store as per company category, with note duly signed by Company department Incharge.

    7. FREE SUPPLY OF MATERIAL

    Sr. #Materials

    Mode ofSupply

    Place ofSupply

    1 Land, Water, electric power supply atcontractor yard

    Free supply CompanysStores/Yard orany other placeinside theCompanysWorks.

    2 Structural Steel like Plates, Angles, Channels,pipes, flanges, valves etc.

    3 Nuts, Bolts, Washers and Gaskets except forthose required in AC/GI corrugated sheet

    4 All equipments like upper bell, lower bell,charging hopper, blow pipe, tuyere, drums, etc

    for erection5 Portland slag cement, reinforcement steel.

    8 TOLERANCE IN WORKMANSHIP

    The permissible tolerance in workmanship shall be as per tables - 1 to 3 and also shall be as per IS:

    7215-1974.

    All workmanship shall be of the best quality and shall conform to the best approved method of

    fabrication/ erection and dismantling. All materials shall be finished straight and shall be machined

    / ground true and square where so specified. All holes and edges shall be free of burrs. Shearing

    and chipping shall be neatly and accurately done and all portions of work exposed to view shall beneatly finished. Unless otherwise directed/ approved, reference maybe made to relevant IS codes

    for providing standard fabrication tolerance. Material at the shops shall be kept clean and protected

    from weather. All the fitters, Riggers, welders, cutters and helper shall be of good quality.

    9 SPECIAL NOTE:

    a) A project time bar chart for fabrication, erection, equipment erection and alignment, sheeting andpainting etc. giving starting and completion dates of all activities, shall be submitted by the

    tenderer.

  • 8/8/2019 T 7 Services Structural Annexure

    13/18

    Page 13 of 18

    b) The purchaser may change or alter the detailed working programme for the sequence of work andfor the fabrication of components of structures, within the frame work of the agreed schedule,

    which will be binding on the tenderer.

    c) If due to design or other stipulations in the bid or requirements at site, a particular sequence ofoverall construction has to be followed due to which certain interruptions to any one or more items

    of work are inherent, no claims for such interruption will be admissible.

    d) Tenderer should note that there could be variation in quantity of any item and no claim shall beentertain on this account.

    e) Work need deployment of labours in all three shifts ( during shutdown period)to complete thework in stipulated time. The contractor shall observe provisions of the Factories Act/ Rules in

    respect of working hours, holidays, rest intervals, leaves and overtime to his employees.

    f) Tenderer shall comply with all labour rules, ESI, PF, health card, Police verificationfor migrant employee etc., which will be strictly followed.

    g) Tenderer shall make arrangement for accommodation and transportation of theiremployees .

    h) Tenderer shall have to construct own temporary shed at their cost for working in theallotted area inside the premises. This shed shall be only for office and store purpose.

    i) Tenderer shall submit the number of man power used for different areas, number ofcranes and their capacities, note on past experience in this line along with the tenderamount and other details along with offer

    Annexure 1 MechanicalAnnexure1A: Bill of Material

    Item Description Uom QuantityFabrication, mock assembly and erection of shell MT 110Fabrication ,painting and erection of ducts, flare stack, saturator, etc MT 255

    Fabrication ,painting and erection of platforms, truss, conveyorstructure, staircases, railings, etc MT 553Erection of steel materials like gratings, crane girder, roof truss etc MT 20

    Erection of equipment MT310

    Dismantling of structures and equipment MT 435Roof sheet dismantling and erection M2 2000

    Erection of stave coolers MT 250Painting with copper slag blasting M2 7000

  • 8/8/2019 T 7 Services Structural Annexure

    14/18

    Page 14 of 18

    Annexure 1B Piping ScopePiping Scope

    Sr.No. Description Uom Quantity

    TUYERE HEADER

    150 nb Seamless header = service m 1

    150/40NB seamless reducer no 10

    150 NB flange no 15

    150 NB gate valve no 3

    100NB pipe m 30

    100 NB flange no 20100NB valve no 0

    40 NB pipeline m 20

    40 NB elbow no 30

    40NB flange no 110

    40 NB valve no 63

    Cast house header

    150NB pipe m 15

    150 NB elbow no 7

    150 NB flange no 12150 NB gate valve no 0

    Fire hydrant line

    150NB pipe m 20

    150 NB flange no 12

    150 NB elbow no 6

    150 NB gate valve no 0

    Tuyere bottom spray

    100NB pipe m 35

    100NB elbow no 6

    100NB flange no 22100 NB valve no 1

    40 NB pipeline m 30

    40 NB flange no 70

    40 NB ball valve no 0

    Stack header

    150 NB pipe m 50

    150 NB flange no 30

    150 NB elbow no 12

    150 NB valve no 140 NB pipeline m 30

  • 8/8/2019 T 7 Services Structural Annexure

    15/18

    Page 15 of 18

    40 NB flange no 40

    40 NB elbow no 16

    40 NB valve no 0Upper stack

    100NB pipe m 60

    100NB elbow no 30

    100NB flange no 12

    100 NB valve no 1

    40NB pipeline m 30

    40NB flange no 40

    40 NB elbow no 8

    40NB valve no 0

    Furnace top header

    150 NB pipe m 40

    150 NB flange no 20

    150NB elbow no 6

    50 NB pipe m 50

    50 NB flange no 12

    50 NB elbow no 12

    50NB valve no 0

    Tap hole bottom spray

    50 NB pipe m 3050 NB flange no 15

    50 NB elbow no 10

    50NB valve no 0

    Header 300 NB M 20

    400 NB M 20

    600 NB M 20

    VALVES ERECTION 400 NB No 3GAS CLEANING SYSTEM 250 NB M 150

    Annexure 1C --- Hydraulic PipingDescription Size of pipe Unit of measure qtyMudgun 38mm OD M 64

    20mm OD M 6416mm OD M 96

    Top chargingequipments

    48mmOD M 160

    20mm OD M 160Hot Blast Stove 16 mm OD M 1115

  • 8/8/2019 T 7 Services Structural Annexure

    16/18

    Page 16 of 18

    Annexure-2 ElectricalSr.No Item Description Uom Quantity Unit Rate

    1 Up gradation of HT Panela) 11KV transformer breaker feeder which involves

    removal of old 3 nos Ct's & Testing, Installation &Commissioning of new 3 nos 400/1 amps CT's

    No 01b) 3.3 KV panel which involves removal of 21 nos 3.3

    KV current transformer & installation testing &commissioning of new Current transformer No 01

    2 Laying testing & Commissioning of cable

    a) 11 KV 3Cx 400 mm2 XLPE Cable. Metre 200b) 3.3 KV 3Cx 185 mm2 XLPE Cable. metre 450c) 1.1 KV, 31/2 cX400mm2 cable including glanding &

    termination Metre 200d) 1.1.KV, 3Cx 50mm2 Cu cable including glanding &

    termination Metre 200

    3Installation, Testing & commissioning of End terminationKit

    a) 11 KV 3Cx400mm2 indoor end termination. No 02

    b) 3.3kv KV 3Cx185mm2 indoor end termination. No 14

    4 Dismantling, removal & shifting of cable

    a) 3.3 KV 3Cx95mm2 cable Metre 200

    b) 1.1 KV 3Cx 50mm2 Al cable Metre 200c) 1.1 KV 31/2Cx 300mm2 Al cable Metre 200

    5 Dismantling removal & shifting of equipment

    a) Blower motors from foundation of 425 KW No 06

    b) 3.3 KV 80KVAR capacitor along with Mounting box No 06

    c) 4 MVA ONAN type transformer with radiators No 06

    d) MCC panel having size2400(L)x500(D) 2350(H) No 01

    e) MCC panel having size7250(L)x500(D) 2350(H) No 02

    6 Unloading Installation & testing of Equipment

    a) 500KW blower motors No 06

    b) 100KVAR capacitor No 06c) 6.5 MVA,11KV/3.3KV/.415KVV ONAN type

    transformer No 01

    d) MCC panel of size 2400(L)x500(D) 2350(H) No 01

    e) MCC panel of size7250(L)x500(D) 2350(H) No 02

    Annexure 3: InstrumentationActivity/Item description UOM Quantity Unit Rate

    A Blower House

    1

    Mounting and installation of orifice plate for

    Pipe size 750mm no 1

  • 8/8/2019 T 7 Services Structural Annexure

    17/18

    Page 17 of 18

    B Control Room

    1 Panel shifting of size 2800mm x 2200mm x 600mm nos. 1

    2 Panel shifting of size 800mm x 2200mm x 600mm nos. 13 Panel mounting of size 800mm x 2200mm x 600mm nos. 1

    4 Cable re-routing 3C x 1.5 sq.mm metre 1000

    5 Cable re-routing 36C x 1.5 sq.mm metre 100

    6 Cable re-routing 10C x 1.5 sq.mm metre 100

    7 Cable re-routing 1C x 1.5 sq.mm metre 100

    C Control Room PLC

    1

    PLC Logic modifications for batching sequence changes

    (S7-300 PLC) Set 1

    2 VB reports modifications Set 1

    C Hearth and Tuyere region

    1 Installation of thermocouples for hearth nos 19

    2 Installation of thermocouples/rtd's for stave coolers nos. 125

    3

    Cable laying for indications in control room for the

    hearth tc's and the stave coolers 3C x 1.5 sq.mm metres 2500

    4

    Cable laying for indications in control room for the

    hearth tc's and the stave coolers 36C x 1.5 sq.mm metres 500

    D RMHS region

    1 Load cells mounting for 7 bins @ 3/4 per bin nos. 21

    2 Load cells cable laying 6C x 1 sq.mm metres 1000

    E GCS up gradation

    1

    Mounting and installation of orifice plate for pipe ID

    1100 mm no 1

    Annexure 4: REFRACTORIESDismantling of refractory T 600Lining of refractory T 900

    Annexure 5: CIVILConcrete Breaking 195 m3Soil Excavation 518 m3Reinforced cementconcrete

    349 m3

    Plain cement quantities 66 m3Shuttering 1065 m2

    Reinforcement steel 31 TTiling 30 m2

  • 8/8/2019 T 7 Services Structural Annexure

    18/18