systematic large-scale restoration of organic muck

34
woodplc.com Systematic Large-Scale Restoration of Organic Muck-Impaired Waterways Mary Szafraniec and Lance Lumbard Florida Stormwater Association 2020 Annual Conference July 17, 2020

Upload: others

Post on 30-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Systematic Large-Scale Restoration of Organic Muck

woodplc.com

Systematic Large-Scale Restoration of Organic

Muck-Impaired Waterways

Mary Szafraniec and Lance Lumbard

Florida Stormwater Association2020 Annual Conference

July 17, 2020

Page 2: Systematic Large-Scale Restoration of Organic Muck

External versus Internal Pollutant Loading

2 A presentation by Wood.

External Internal

Page 3: Systematic Large-Scale Restoration of Organic Muck

• External

– Basin delineations

– Soil types

– Land uses

– Runoff models

– Site specific EMCs

– Flow measurements

Differences in Pollutant Loading

3

• Internal

– Legacy load

– Organic accumulation (muck)

– Sediment flux

– Biological availability

– Physical sediment characterization

– Redox / dissolved oxygen profiles

– Water quality response (turbidity, chlorophyll-a, etc.)

Sediment Flux

Page 4: Systematic Large-Scale Restoration of Organic Muck

• Provides substrate for habitat or transports up and out

• Can be a source or sink for pollutants

– Lability, storage capacity and saturation level

– Internal cycling rates dependent on conditions

• Drives water quality that can lead to impairments

Sediment as a Driver

Oxygen

present

No

oxygenBioturbation

Turbulence/wind

mixing

Page 5: Systematic Large-Scale Restoration of Organic Muck

Sediment Phosphorus Fractionation

Organic

Metal-Oxide

Reductant-Soluble

Residual

Apatite

Labile Loosely Adsorbed

Fe Adsorbed

Al Adsorbed

Loosely Bound Organics

Minerals

Minerals & Organics

Nuisance algae may be better able to access internal accumulation

Page 6: Systematic Large-Scale Restoration of Organic Muck

• Waterbody or alternatives analysis studies indicate that sediment cycling generates a significant portion of the pollutant loading

• Untreated stormwater inputs are limited or being addressed

• Upstream sediment transport is limited or has been addressed

• Permitting is feasible

• Funding source has been identified

How and When to Pursue a Sediment-Focused Waterbody Management Project

6 A presentation by Wood.

Page 7: Systematic Large-Scale Restoration of Organic Muck

Alternative Development and Analysis

Sediment Management Plan Formulation

Human Risk

Ecological Risk

Physical/

Chemical

Composition

Disposal Sites/

Environmental

Damage

Transport

Other Factors

Trap, Cap

and/or

Remove

(passive)

Excavate and

Remove

(active)

Monitored

Natural

Recovery

Other

Alternatives

Alternatives:Inputs:

7 A presentation by Wood.

Page 8: Systematic Large-Scale Restoration of Organic Muck

• Water quality credits from managing

internal sources

– Issue: most models have not

accounted for internal cycling or

underestimated in nutrient budgets

– Solution: Measure nutrient sediment

flux to estimate load contributions

• Site-specific is ideal

– Means of obtaining load reduction

credit

• Sediment removal

• Sediment inactivation

Sediments and Load Reduction Credits

8 A presentation by Wood.

Page 9: Systematic Large-Scale Restoration of Organic Muck

Modeled

• Regionally-specific

predictive models

developed by Wood to

predict pre and post

dredging net flux rates

and loads

Estimating Sediment Nutrient Flux and Loads

Measured

• Wood Flux Field and

Lab SOP (accepted by

FDEP) to measure site-

specific flux and

internal nutrient loads

• Assess various

treatment alternativesR² = 0.9192

R² = 0.8421

R² = 0.9353

0

50

100

150

200

250

300

350

400

0 5000 10000 15000 20000 25000

BA

P (

mg

/kg

)

Fe (mg/kg)

Lake Seminole McKay Creek Roosevelt Creek

Page 10: Systematic Large-Scale Restoration of Organic Muck

• Sediment removal / dredging

– Mechanical

– Hydraulic

– Sump

– Water injection

• Sediment capping / cover

– Physical – sand and/or rock (backfill)

– Chemical treatment alternatives

• Phoslock®

• Alum

• “Floc&Lock” (Phoslock® and Alum)

• Biological (e.g. Purple Sulfur Bacteria)

• Oxygenation

• Organic soil / muck

• Others TBD

Sediment Restoration Alternatives

Page 11: Systematic Large-Scale Restoration of Organic Muck

Treatment Alternatives Analysis

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0 24 48 72 96 120 144 168

Tota

l Ph

osp

ho

rus,

as

P,

(mg

/L)

Time (hours)

Alum-Filtered

Floc&Lock-Filtered

Phoslock-Filtered

Sand-Filtered

Sediment Control-Filtered

Treatment alternatives analysis can provide informative results prior to making $$$ management and

restoration decisions233

1,320

1,681

1,840 1,908

59262

442573 570

0

500

1000

1500

2000

2500

3000

Initial Site

Water

1 WAT 2 WAT 3 WAT 4 WAT

ug

PO

4-P

/ L

Control

Cylinders

Treatment

Cylinders

Page 12: Systematic Large-Scale Restoration of Organic Muck

Planning a Sediment Removal Project

12 A presentation by Wood.

Page 13: Systematic Large-Scale Restoration of Organic Muck

13

Approach to Sediment Management

No Action

• Natural Attenuation

Cap/Inactivate

• Sand• Mats• Alum

• Phoslock®

• Others

Dredge/Dewater

• Mechanical• Hydraulic

DMMAsGeotextile tubes

SubaqueousWastewater plant

IslandsRelocation

Page 14: Systematic Large-Scale Restoration of Organic Muck

• Permitting/Disposal Constraints

• Data Collection

• Stakeholder/Public Support

• Planning & Design

• Dredging, Dewatering, & Disposal Design

• Sediment & Water Quality Issues

• Available Budget

– Minimize Dredging Cost

– Maximizing Environmental Restoration Benefit

Environmental Muck Dredging’s Unique Challenges

14 A presentation by Wood.

Project

Understanding

Programmatic

Objectives

Waterbody

Objectives

Agency

Permitting

Concerns

Public

Stakeholder

Interests

Sediment

Characteristics

Disposal

Alternatives

Project Site

Characteristics

Funding

Opportunities

Page 15: Systematic Large-Scale Restoration of Organic Muck

Common Dredge Types

15 A presentation by Wood.

Hyd

raul

icM

echanical

Page 16: Systematic Large-Scale Restoration of Organic Muck

Rotating Auger Cutter Head

16 A presentation by Wood.

Page 17: Systematic Large-Scale Restoration of Organic Muck

Vacuum Suction Head Only

17 A presentation by Wood.

Page 18: Systematic Large-Scale Restoration of Organic Muck

Planning a Dredge Project

18 A presentation by Wood.

Sediment

characteristics (physical

and chemical) define

boundaries of

reasonable end use.

The End (placement, beneficial

reuse) defines the means &

methods for land-based needs,

transport, & dredging method

(hydraulic, mechanical).

The End Drives Cost!

Page 19: Systematic Large-Scale Restoration of Organic Muck

Two Canal Dredge Projects – Very Different Methods

19 A presentation by Wood. #RFQ –5–19-10 Dredging and Sediment Management Continuing Consulting Services

Case 1 – high density with

multiple methods

Case 2 – medium density with

hydraulic dredging

Page 20: Systematic Large-Scale Restoration of Organic Muck

Case 3: Hydraulic Dredging Provides Efficiency

20 A presentation by Wood.

300-acre dredge

footprint6-mile

pipeline route

dredge material for restoration

Page 21: Systematic Large-Scale Restoration of Organic Muck

Case 4 – Economic Hydraulic Dredging to DMMA

21 A presentation by Wood. #RFQ –5–19-10 Dredging and Sediment Management Continuing Consulting Services

No available restoration area so dredge material management area

was designed creating public space and saving millions over landfilling

Page 22: Systematic Large-Scale Restoration of Organic Muck

• Agricultural applications are rarely feasible due to cost and chemistry

• Dredge sediments can sometimes be utilized very effectively to cover former

agricultural “hot-spots” and facilitate restoration

• Hydraulically dredged sediments can effectively be pumped many miles away

• DMMAs can be re-purposed after use for creation of public recreation areas

• Geotextile tubes can be used to stabilize shorelines

Beneficial Reuse

22 A presentation by Wood.

Page 23: Systematic Large-Scale Restoration of Organic Muck

Strategic Dredging Methodology

23 A presentation by Wood.

Page 24: Systematic Large-Scale Restoration of Organic Muck

Identify the Sediment Causing the Problem

24 A presentation by Wood.

Page 25: Systematic Large-Scale Restoration of Organic Muck

Sediment Sampling and Characterization

25 A presentation by Wood.

Page 26: Systematic Large-Scale Restoration of Organic Muck

Targeting Unconsolidated Flocculant (UCF) Sediment

26 A presentation by Wood.

• Targeted removal of UCF

could address issues

including resuspension,

disposal, and increased

depth as a result of

conventional dredging

• Additional technologies

include sump (sediment

trap) construction, UCF

pumping, and thin layer

placement (TLP)

Page 27: Systematic Large-Scale Restoration of Organic Muck

Targeted Dredging vs. Sump Pumping

27 A presentation by Wood.

• Dredge operator +

support team

• Booster pumps

• Multiple Permits

• Avoidance areas

• Navigational hazards

• Traditional dredging

initially

• Automation

• Fixed location

• One permit

Page 28: Systematic Large-Scale Restoration of Organic Muck

Challenges

• Dredges aren’t precision instruments

• Dredges normally operate blind

• Dredgers don’t normally understand why we want to target UCF sediment

• Difficult to tell when the dredge is removing UCF or CF sediment by looking at

the discharge

Solutions

• Utilize special suction head design

• Real time TSS feedback to operator

• Operator training

• Core sampling and new methods

Targeted UCF Pumping Challenges and Solutions

28 A presentation by Wood.

Page 29: Systematic Large-Scale Restoration of Organic Muck

Real Time Turbidity Monitoring

29 A presentation by Wood.

Page 30: Systematic Large-Scale Restoration of Organic Muck

Dredge Effluent Treatment

30 A presentation by Wood.

Page 31: Systematic Large-Scale Restoration of Organic Muck

• N and P are not often addressed in dredge return water and there are no regulatory limits

• Dissolved nutrients (N and P) are of primary concern because they are highly available to algae

• Dissolved nutrients are the most challenging to remove

• Hydraulic dredge operations increase the amount of water requiring treatment

• Nutrient reduction processes become the limiting factor for the entire operation unless the proper technology and capacity is selected

Water Quality in Dredge Effluent

Challenges

A presentation by Wood.31

Page 32: Systematic Large-Scale Restoration of Organic Muck

Dredge Process Stream for IRL Projects

32 A presentation by Wood.

Dredge Influent

Unpolished

WaterFlocculants &

Coagulants

HydrocyloneSettling Pond

Belt PressCentrifuge

GeotubeRolloff

ParabolicOthers

Available Dewatering

Technologies

N

reduction

P

reduction

ZeolitesOzonation

Air flotationBiological

ElectochemicalChemical

Air flotationChemicalSorption

Biological

Clean

return

water

Semi-dry

Solids

Available Best Use

Alternatives

Restoration Cap/cover

Soil blendingOff-site fill

Spoil islandsOthers

“Clean”

“Dirty”

Landfill

Challenge 1

Challenge 2

Page 33: Systematic Large-Scale Restoration of Organic Muck

• Internal loading from organic sediments can be a significant source of water

quality impairments

• Understanding and quantifying internal loading is critical

• Sediment capping and chemical inactivation can result in significant load

reduction under certain conditions

• Dredging projects can be designed to remove sediments contributing to

internal loading sources and often address multiple issues simultaneously

• Strategic dredging can provide considerable savings over traditional “all-or-

nothing” dredging

• Nutrient control in return water is an emerging concern particularly in impaired

waters

Summary

33 A presentation by Wood.

Page 34: Systematic Large-Scale Restoration of Organic Muck

woodplc.com

Mary Szafraniec, PhD, PWS

Associate Scientist

Water Resources

Wood Environment &

Infrastructure Solutions

Mobile - 813.748.3625

[email protected]

Lance Lumbard, CLP

Senior II Scientist

Water Resources

Wood Environment &

Infrastructure Solutions

Mobile – 407.592.3235

[email protected]