system recap may 24, 2017 - drpwg.org€¦ · system recap may 24, 2017 . 1 agenda •timeline for...
TRANSCRIPT
System Recap May 24, 2017
1
Agenda
• Timeline for IOU Distribution Planning Processes
• Presentation of proposed system level DER assumptions for 2017/18 Distribution Planning Process (DPP)
• Current System Forecast Review
2
Distribution Planning Timing Needs IOU’s need for a ruling on the Assumptions and Framework for use in the 2017/18 DPP
• PG&E would like to have a ruling by not later than mid-July on the system level starting points
• SCE/SDG&E would need a ruling in by end of Q3 (August)
The current IEPR is aligned with the needs incorporated in the TPP
How can the IEPR be further aligned to support the needs in the DPP?
3
Proposed System Level DER Assumptions for
2017/18 Distribution Planning Process
SCE PG&E SDG&E
DG (BTM) SCE Latest Forecast
(November 2017)
PG&E Latest Forecast
(2017 IEPR Submittal)
SDG&E Latest Forecast
(2017 IEPR Submittal)
Energy Efficiency 2016 IEPR - Low Mid AAEE (C&S)
2016 IEPR - Low Mid AAEE 2016 IEPR - Low Mid AAEE
2017 EE Potential and Goals Study (EE)
DR (Load-
modifying)
2017 DR Load Impact Report
(Filed 4/3/17)
2016 IEPR Update Mid Case
(2015 DR Load Impact Report )
2017 DR Load Impact Report
(Filed 4/3/17)
DR (Supply-side) n/a n/a n/a
Electric Vehicles SCE Latest Forecast
(November 2017) 2016 IEPR Update Mid Case
SDG&E Latest Forecast
(2017 IEPR Submittal)
Storage (BTM) Existing storage + SCE Contracted Procurement Existing Storage + AB2514 Targets Existing Storage + AB2514
Targets
Consistent with 2017 ACR* for the 2017/18 TPP Deviation from 2017 ACR* for the 2017/18 TPP
*CPUC Assumptions ACR issued via Integrated Resource Plan (IRP) process outlining preferred assumptions and scenarios for use in long term planning processes such as the CAISO transmission planning process (TPP)
4
Current Stakeholder Review of System
Forecasts • Existing CPUC Regulatory Processes provide oversight of:
– Using system forecasts for grid investments
• Each IOU litigates their system forecasts as well as distribution forecasts as part of the GRC
– Using IOU system forecasts for procurement
• Each IOU’s system forecast is litigated via ERRA, the BPP, and the LTPP process
• Further transparency regarding the assumptions and methodology is provided via review by the Procurement Review Group of the IOU forecasts
• CEC IEPR Stakeholder Process
– IOU’s submit their latest corporate forecast via the IEPR process in odd years for incorporation into the CEC’s IEPR
– The Demand Analysis Working Group serves as a place to discuss and refine methodologies as well as coordinate methods to capture policy impacts
– Series of public stakeholder meetings are held during the IEPR process to discuss inputs, modeling and results of CEC's forecasting process
5
Appendix
6
Due to SCE’s DPP Timeline, SCE will align its
forecast more closely with the 2017 IEPR SCE Rationale
DG (BTM) SCE Latest Forecast
(November 2017)
• Recent policy changes since the 2016 IEPR including ZNE, FITC, and NEM 2.0 and
re-calibration to latest adoption data
(consistent with changes CEC seeks to reflect in 2017 IEPR)
Energy Efficiency
2016 IEPR - Low Mid
AAEE (C&S)
2017 EE Potential and
Goals Study (EE) • SCE’s programs are designed to meet targets laid out in the EE Potential and Goals
study
DR (Load-modifying) DR Load Impact
Report (4/3/17)
• This represents the best information available. Further, this report is the source
that would likely be utilized in the updated 2018 ACR containing A&F for the TPP
issued during SCE’s 2017/18 DPP
DR (Supply-side) n/a
Electric Vehicles SCE Latest Forecast
(November 2017)
• SCE’s 2017 forecast will reflect the acceleration in EV adoption in line with planned EV infrastructure investment from utilities and third parties
• SCE’s forecast will also support statewide GHG reduction targets
Storage (BTM)
Existing storage + SCE
Contracted
Procurement
Consistent with 2017 ACR for the 2017/18 TPP Deviation from 2017 ACR for the 2017/18 TPP
*CPUC Assumptions ACR issued via Integrated Resource Plan (IRP) process outlining preferred assumptions and scenarios for use in long term planning processes such as the CAISO transmission planning process (TPP)
7
SDG&E’s Forecast Correlation with the IEPR
Process for 2017-18 Distribution Planning
Assumption Rationale
DG (BTM) SDG&E Latest Forecast
(2017 IEPR Submittal) • Recent policy changes since the 2016 IEPR including ZNE, FITC, and NEM 2.0 and
re-calibration to latest adoption data
Energy Efficiency 2016 IEPR - Low Mid
AAEE
DR (Load-modifying) 2016 DR Load Impact
Report
• This represents the best information available. Further, this report is the primary
source that would likely be utilized in the updated 2018 ACR containing A&F for
the TPP issued during SDG&E’s 2017/18 DPP
DR (Supply-side) n/a
Electric Vehicles SDG&E Latest Forecast
(2017 IEPR Submittal)
• SDG&E’s 2017 forecast will reflect the acceleration in EV adoption in line with planned EV infrastructure investment
• SDG&E’s forecast will also include the results of the EVCC survey
Storage (BTM) Existing Storage +
AB2514 Targets
Consistent with 2017 ACR for the 2017/18 TPP Deviation from 2017 ACR for the 2017/18 TPP
*CPUC Assumptions ACR issued via Integrated Resource Plan (IRP) process outlining preferred assumptions and scenarios for use in long term planning processes such as the CAISO transmission planning process (TPP)
8
PG&E's System-Level Forecast Assumptions
for 2017/2018 Distribution Planning
PG&E Rationale
DG (BTM) PG&E Latest Forecast
(2017 IEPR Submittal )
• Policy developments that are not incorporated in the 2016 IEPR including
the extension of the 30% Federal ITC for solar, NEM 2.0,and increased
policy emphasis on Zero Net Energy homes
Energy Efficiency 2016 IEPR - Low Mid AAEE
DR (Load-modifying) 2016 IEPR Update Mid Case
(2015 DR Load Impact Report
DR (Supply-side) n/a
Electric Vehicles 2016 IEPR Update Mid Case
Storage (BTM) Existing Storage + AB2514
Targets
Consistent with 2017 ACR for the 2017/18 TPP Deviation from 2017 ACR for the 2017/18 TPP
*CPUC Assumptions ACR issued via Integrated Resource Plan (IRP) process outlining preferred assumptions and scenarios for use in long term planning processes such as the CAISO transmission planning process (TPP)
9
Load Forecasts for 2017/18 DPP
• The current statewide forecast (2016 IEPR) is a system forecast largely supporting the TPP
• Distribution Planning requires more granular local forecasts/information which are not currently in the IEPR – Pushing the IEPR down to a sub-regional level (e.g. A-Bank for SCE) would
allow for better reconciliation between the system forecast and local planning knowledge
• Each IOU has developed methods that best serve its customers by maintaining reliability on each distribution system
SCE PG&E SDG&E
Load Forecast for
2017/18 DPP
SCE Latest Forecast (November 2017),
benchmarked against 2017 IEPR, and
informed by local known growth
projects
2016 IEPR Forecast
informed by local
known growth
projects
2016 IEPR Forecast informed by local
known growth projects
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Hour
Substation A Substation B Substation C System
Example of System vs. Local Peak Forecasts
The system forecast represents the overall peak for the system • Underlying subs will have different local peaks due to differing factors (e.g.
climate, customer composition) • Capacity planning for local regions must consider the local peak as
opposed to the system peak • Coincidence describes the relationship between the local and system peak
System Peak (TPP)
Local Peaks (Distribution Planning)
Note: This example assumes all substations peak on the same day. In actuality, Substations peak on different days and different time of year compared to system 10
Disaggregation Methodologies
In future cycles, IOUs will continue to work toward more
robust methods incorporating the following principles: Utilize statistically appropriate, data-driven methodologies for each
DER, customer segment, and level of disaggregation
Integrate data from DER industry partners to enhance forecasting
accuracy
Develop approaches to manage uncertainty associated with granular
allocation of DER
Periodically re-assess the modeling approach for each DER as
increased adoption leads to better data
Share best practices and leverage learning process to strive for
continuous improvement both in forecasting and in using the
forecasts for distribution planning
11
12
PG&E DER forecasts (Illustrative)
DER Type Unit 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
PV MW - Cumulative Capacity 3,168 3,894 4,671 5,333 5,926 6,306 6,713 7,129 7,526 7,799 8,037
EE
GWh - Mean Forecast -
Cumulative Savings,
beginning 2017
1,922 4,073 5,778 7,488 9,178 10,872 12,556 14,185 15,802 17,368 19,013
EV GWh - Cumulative 441 514 594 689 842 1,014 1,224 1,481 1,778 2,147 2,585
DRMW - Peak Impact (Total
System)508 524 526 529 531 533 533 534 534 535 535
Storage MW - Cumulative Capacity 74 125 187 246 310 381 459 544 632 722 810
Notes:
1. All DER forecasts presented are included in PG&E's 2017 Approved corporate long-term forecast
2. Forecasts of PV, EE, EV and DR provided as part of April 13, 2017 IEPR submission.
3. Storage cumulative capacity courtesy of Swetha Meenakshi
13
SCE DER forecasts (Illustrative)
DER Type Unit 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
PVMW - Cumulative
Capacity2271 3008 3869 4730 5486 6117 6651 7099 7475 7797 8080
EE/C&S1 GWh (Low-Mid) -
Cumulative2419 3104 3802 4509 5216 5938 6674 7404 8155 8933
EV - Light Duty GWh - Cumulative 509 893 1,353 1,876 2,460 3,102 3,776 4,387 5,021 5,665 6,316
LMDR MW - Peak Impact 50 62 74 93 86 92 97 102 107 112 117
Energy Storage MW 31 MW Existing2 + 220.6 MW of BTM ES Procurement
1. SCE Presented the system wide Mid case #s at the GSWG meeting however for distribution planning, consistent with the TPP SCE intends to utilize the low-mid scenario 2. Existing as of 12/31/2016
14
SDG&E DER forecasts (Illustrative)
DER 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
BTM PV 690 780 850 910 970 1050 1130 1220 1320 1420 1530 1640 Capacity
EE 40 70 100 130 160 190 220 250 270 300 340 370 Peak
EV 0 10 10 10 10 20 20 20 20 30 30 40 Peak
Storage 20 20 20 30 30 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! Capacity
Non-event DR 20 20 20 20 20 20 20 20 20 20 20 20 Peak
For DERs w/ Capacity rather than peak: • IEPR peak forecast for PV has changed significantly due to peak-load shift
analysis. Capacity, for this purpose, provides clearer understanding. Coincident peak will be analyzed with LoadSEER.
• IEPR forecast for storage is not available. Statewide mandates are capacity only. Operating characteristics for storage are not clear yet so coincident peak is not available.