system impact study for def gisrs, queue positions 125 & 126 · 2019-12-23 · to-ground faults...
TRANSCRIPT
![Page 1: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/1.jpg)
System Impact Study
for DEF GISRs, Queue Positions 125 & 126
May 2014
Transmission Planning, Florida
Jeffrey Van Dyke
Michael Alexander, P.E.
![Page 2: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/2.jpg)
This document and any attachments hereto (“document”) is made available by Duke Energy Company upon and subject to the express understanding that: (a) neither Duke Energy Company nor any of its officers, directors, affiliates, agents, or employees makes any warranty, assurance, guarantee, or representation with respect to the contents of the document or the accuracy or completeness of the information contained or referenced in the document, and (b) Duke Energy Company, its officers, directors, affiliates, agents, and employees shall not have any liability or responsibility for inaccuracies, errors , or omission in, or any business or policy decisions made by any direct or indirect recipient in reliance on, this document or the information contained or referenced therein; all such liability is expressly disclaimed.
![Page 3: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/3.jpg)
Table of Contents Summary 1 Interconnection Points Evaluated 1 Criteria for Determining Transmission Impact 3 Model Development 4 Analyses Performed 5 Screening Criteria 5 Study Results & Costs 6 Feasibility of In-Service Date 10 Appendix A, Most Significant Thermal Analysis Results 11 Appendix B, Most Significant Voltage Analysis Results 13 Appendix C, Short Circuit Analysis Results 14 Appendix D, Stability Analysis Results 16 Appendix E, P-V Analysis Results 18
![Page 4: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/4.jpg)
Transmission Planning, Florida
Summary These two GISRs (Generator Interconnection Service Requests) are each for a new CT (Combustion Turbine) generator, with 167 MW summer net output and 187 MW winter net output. The anticipated commercial operation date is June 1, 2016. The points of interconnection will be at Duke Energy Florida’s (DEF’s) Suwannee River 230 kV substation, with one unit interconnecting to the 230 kV and the other unit interconnecting to the 115 kV. The type of interconnection services being requested is NRIS (Network Resource Interconnection Service). This study showed several thermal impacts to DEF’s transmission system in the surrounding area and marginal impacts to third parties in the area. Several third-party voltage impacts were found, though slight. In addition to analysis performed using the FRCC 2013 Databank Rev2d cases, a stressed generation case involving maximum FRCC imports from Southern Company was performed. There were no transmission breakers identified on the DEF system that will be pushed above their interrupting rating by the addition of these units. Lastly, the new CTs and their associated transmission upgrades will not have an adverse impact on the transient stability response of the bulk electric system.
Interconnection Points Evaluated Point of interconnection requested for study by interconnection customer for the 115kV unit:
• Connection to DEF’s existing 115 kV Suwannee River Substation.
Alternative point of interconnection considered by DEF for the 115 kV unit: • No other options were considered reasonable or necessary.
1
![Page 5: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/5.jpg)
Transmission Planning, Florida
Point of interconnection requested for study by interconnection customer for the 230kV unit: • Connection to DEF’s existing Suwannee Peakers 230 kV switchyard.
Alternative point of interconnection considered by DEF for the 230 kV unit:
• No other options were considered reasonable or necessary.
Aerial Diagram showing location of new CTs
2
![Page 6: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/6.jpg)
Transmission Planning, Florida
Criteria for Determining Transmission Impact DEF’s criteria for identifying transmission facilities impacted by the interconnection of new generation facilities are as follows: Thermal Impact
• System-intact loading over 100% Rate A. • B/C1/C2/C5 post-contingency loading over 100% Rate B. • C3 or C3-gen post-contingency loading over 100% Rate C. • Minimum loading increase from Base Case to Interconnection Case of 3%.
Voltage Impact
• System-intact bus voltages lower than 0.95 p.u. or higher than 1.05 p.u. • B/C1/C2/C5 post-contingency bus voltages lower than 0.90 p.u. or higher than 1.05 p.u. • Minimum voltage change from Base Case to Interconnection Case of 0.02 p.u.
Short-circuit Impact
• Three-phase and single line-to-ground fault current over 100% breaker fault duty capability. • Minimum fault current increase from Base Case to Interconnection Case of 3%.
Dynamics Impact
• The new Suwannee CTs must remain connected and synchronized with the transmission system for a normally clearing 3φ fault.
• The new Suwannee CTs must remain connected and synchronized with the transmission system for a delayed clearing single line-to-ground fault.
• The addition of the new Suwannee CTs cannot create a transient unstable response resulting in widespread system collapse.
• The addition of the new Suwannee CTs cannot create a transiently stable response with undamped power system oscillations.
• The addition of the new Suwannee CTs cannot cause the activation of automatic under-frequency load shedding schemes.
3
![Page 7: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/7.jpg)
Transmission Planning, Florida
Model Development Power Flow Models Power flow models were built using the Siemens PSS/E power system simulation program (PSS/E) and were based on the FRCC 2013 series (Revision 2d, February 2014) cases, which were the most recent models available at the time of the study. The model seasons studied for power flow impacts were 2016 summer, 2016/17 winter, 2019 summer, and 2019/20 winter. These FRCC models were updated with relevant new information from the study area, including updated thermal ratings and the dispatch of Crystal River & Citrus generation. After these adjustments, FRCC Block & Priority Economic Dispatch was used to reallocate generation within Duke Energy Florida. Finally, an erroneous MVAR load model at PCS/Occidental was corrected, a capacitor bank at Jasper was installed, and several upcoming transmission improvement projects in the area were included. In addition to developing standard 2,400 MW FRCC import cases, high-import sensitivity cases were created assuming a 3,700 MW generation import from the Southern Company. The differential between base and study cases was to turn off all three Suwannee Steam 115kV units and then turn on the new 115 & 230 kV CTs. Short Circuit Models Short circuit models were built using the PSS/E power system simulation program and were based on the FRCC 2013 series (Revision 1, December 2013) short circuit cases, which were the most recent models available at the time of the study. The model year studied for short circuit impacts was 2016. In addition to the primary analysis using data provided by the customer in the system impact study agreement, a sensitivity was performed using an alternative 7.5% impedance generator step-up transformer (GSU) for each combustion turbine. Dynamics Models Dynamics analyses were performed using the FRCC 2013 series (Revision 1, April 2014) 2014 summer peak load and 50% summer peak load models, modified for 2016 load levels and anticipated local transmission projects, to determine the impact of the Suwannee 115 and 230 kV combustion turbines on the dynamic stability of the transmission system. The customer provided generator, exciter, governor, and power system stabilizer data for use with models within the PSS/E dynamics model library. In addition to the primary analysis using data provided by the customer in the system impact study agreement, a sensitivity was performed using an alternative 7.5% impedance generator step-up transformer (GSU) for each combustion turbine. Generation Interconnection Queue Considerations The DEF Generation Interconnection Queue was reviewed, and thus a prior-queued item was included in both the base and the study cases. That item is Queue #s 123&124, a new Combined Cycle plant proposed for interconnection in Citrus County. No other prior-queued requests were deemed relevant to this study. Transmission Service Request Priority List Considerations A review of transmission service requests in the FRCC coordinated priority list was performed and no relevant transmission service requests were identified in the study area that were not already built into the FRCC cases.
4
![Page 8: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/8.jpg)
Transmission Planning, Florida
Analyses Performed Power flow analyses of the base cases and Suwannee CT study cases were performed using PowerGEM TARA software (TARA) to determine the impact of interconnecting the queued generation to the transmission system in the Suwannee River Plant area. The base cases and the interconnection study cases were compared to determine if the interconnection option created thermal overloads or voltage violations, or exacerbated existing thermal overloads or voltage violations. All single element transmission contingencies (69 kV and above) were analyzed as well as NERC Category C3 (N-1-1) contingencies resulting in Rate C overloads. All branch flows and bus voltages were monitored (69 kV and above) in the FRCC region. The FRCC reliability region consists of peninsular Florida east of the Apalachicola River. The State of Georgia (to the north) and the panhandle area of Florida west of the Apalachicola River in the State of Florida are within the SERC reliability region. PSS/E short circuit analyses were performed using PSS/E activity ASCC. Three phase and single line-to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation in both the base case and the study case to measure short circuit impacts. Fault analysis was performed with all nearby generation in service.
Dynamic analyses were performed for this generation using the PSS/E dynamic simulation tool. Analyses were run for NERC category C delayed-clearing single line-to-ground (SLG) faults and NERC category D delayed-clearing 3φ faults. Clearing times for faults at the Suwannee River and Suwannee Plant substations were obtained from DEF’s Protection & Control Department. Typical “worst-case” clearing times were used for faults at neighboring substations and transmission lines.
Screening Criteria The following criteria were used for screening TARA power flow thermal results.
• GSU transformers were excluded from consideration. • Transmission system elements operated at less than 69 kV nominal voltage were excluded. • System-intact overloads greater than 100 percent of rate A were reported • Post-contingency (N-1) overloads greater than 85 percent of rate B were reported • Post-contingency (N-1-1) overloads greater than 85 percent of rate C were reported • Post-contingency loadings with changes of at least 5 MW were reported
*It is important to note that even though DEF’s new ratings methodology was applied before analyzing, since this GISR was queued prior to the implementation of DEF’s new ratings, this GISR will be grandfathered with the old ratings if there are any impacts that only occur with the new ratings. The following criteria were used for screening TARA power flow voltage results.
• Transmission system buses operated at less than 69 kV nominal voltage were excluded. • System-intact bus voltages outside the range 0.95–1.05 p.u were reported • Post-contingency bus voltages outside the range 0.95–1.05 p.u were reported • Post-contingency bus voltages with changes of at least 0.005 p.u. were reported.
The following screening criteria were used for screening the PSS/E short circuit results.
• All results within three breakered buses of the proposed interconnection point were examined.
5
![Page 9: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/9.jpg)
Transmission Planning, Florida
Study Results Thermal:
System impacts identified by the addition of these queued resources:
• Rebuild of the 0.9 mile 115kV line between the Suwannee 230/115 kV Substation and the Suwannee Plant 115kV Substation (limited by the sag-limited conductor and line jumpers)… this is a Rate C overload caused by a NERC Category B (N-1) contingency: loss of the Fort White to Suwannee 230kV line.
• Upgrade limiting elements on the 0.65 mile 230kV line between Suwannee Peakers 230kV collector bus and the Suwannee River 230 kV substation (limited by relay protection equipment at the Suwannee River 230kV substation)… this is a NERC Category A (N-0) Base Case overload that occurs even when no contingencies occur.
• Customer will be subject to redispatch to remedy a rare overload on the Suwannee 230/115 kV Transformer #2… this is a Rate B overload caused by a NERC Category C breaker failure contingency scenario due to the existing 230kV yard configuration. As an alternative, a $0.5 million project could be assigned to the customer to perform a terminal-swap.
System impacts identified for which there is already an existing DEF project with a compatible need date to remediate the impact and thus no project assigned: • Upgrade of the Ft White 115/69kV transformer (impacts are Rate C overloads caused by
NERC Category C3 contingency scenarios). DEF has an internal need for this upgrade in June 2016, but has scheduled the upgrade for December 2016, based on normal project pacing. DEF will accelerate this project with no costs assigned to the customer.
• Rebuild of the Alachua Tap to Alachua, Alachua to GE Alachua, and GE Alachua to Hull Road 69kV line segments. DEF has an internal need for these rebuilds in 2016, but has scheduled the rebuild for 2017, based on normal project pacing. However, since these are non-Bulk-Electric overloads that occur only under high FRCC import scenarios, DEF will not accelerate the project and will continue targeting 2017. No costs will be assigned.
• Rebuild of Hanson – Greenville 115kV. DEF has an internal need for this rebuild in 2016, but has scheduled the rebuild for 2018, based on normal project pacing. A system impact was found in this study for a different scenario , but that scenario is not significant enough to warrant a project since the overloads are less than 104% and only occur in an extremely rare system condition. Therefore, the DEF will not accelerate the project and will continue targeting 2018. No costs will be assigned to the customer.
System impacts identified for which there is an existing DEF project planned which has a later need date that will require acceleration in order to remediate the impact: • None
DEF internally-planned projects that were in-service in the study model that DEF must not defer or delay beyond the customer’s in-service date of June 2016: • new Drifton – Perry 115kV circuit • rebuild of Wrights Chapel to Jasper 115kV • Suwannee Capacitor Banks to increase total MVARs at Suwannee to 150MVAR
6
![Page 10: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/10.jpg)
Transmission Planning, Florida
Narrative Summary of Thermal Impacts The 0.9 mile 115kV line between the Suwannee 230/115 kV Substation and the Suwannee Plant 115kV Substation will need to be rebuilt with a recommended conductor of 1272 ACSS/TW, due to overloading under various contingency scenarios. This cost is estimated to be $1.3 million. All impacts to the 230kV line between Suwannee Peakers and the Suwannee River 230kV (N-0 and post-contingency) can be resolved by upgrading relay protection components at the Suwannee River 230kV sub. Estimated cost: $0.3 million. The impact to the 230/115kV transformer #2 at Suwannee, caused by a rare breaker-failure of breaker 900, can be resolved with a post-contingency redispatch of Suwannee generation. Alternatively, the customer can elect to fund a project to swap the Ft White 230 kV terminal and the Suwannee Peakers 230 kV terminal. The estimated cost for this work is $0.5 million (optional). Please note that DEF Transmission may elect to apply the cost for the aforementioned 115 kV substation rebuilds as credit toward a more expensive but more prudent alternative to instead create a new 115kV switchyard. DEF Transmission currently does not have internal drivers of its own to create this new yard, but a new yard offers more flexibility for the future versus doing the bare minimum upgrades and changeouts to the existing ring.
Please see the electronic appendices for the full thermal analysis results in Microsoft Excel format. All other impacts shown in the results were deemed pre-existing issues or were NERC Category C3 impacts for which there were adequate pre-2nd-contingency solutions which did not cause real-time issues and did not set up more potential Rate C overloads. In particular, issues south of Crystal River were deemed pre-existing when considering projects Duke Energy would need to perform in order to preserve its full existing transmission rights for the maximum output of Crystal River generation.
7
![Page 11: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/11.jpg)
Transmission Planning, Florida
Voltage: The quantitative analysis showed numerous voltage impacts. However, upon applying qualitative analysis and engineering judgment, the only impacts clearly attributable to the customer are 3rd-party impacts (see below) Please see the electronic Appendices for the complete results of voltage analysis.
Third Party Impacts: The screening criteria revealed many small third-party thermal impacts throughout the FRCC, none of which were deemed significant. These impacts will be investigated in a future coordinated study, and it is possible that more impacts will be revealed, in particular given the complexity of interconnecting generation in close proximity to the Florida-Southern Interface. The only voltage impacts clearly attributable to the customer are 3rd-party impacts to the Florida-Southern Transfer Import Capability. These impacts are slight, but it is possible that a 3rd party will demand compensation for some new capacitor banks. These impacts will be investigated in a future coordinated study, and it is possible that more impacts will be revealed, in particular given the complexity of interconnecting generation in close proximity to the Florida-Southern Interface.
Short Circuit: Short circuit analyses revealed that the interconnection of the Suwannee 115 and 230 kV facilities would cause impacts greater than 3% at the Suwannee, Fort White, and Perry substations. However, the magnitude of the fault current revealed in the system impact analysis does not exceed the fault capability of existing components at the substation. The 7.5% GSU Sensitivity revealed additional impacts at these same substations, none of which exceeded the fault capability of existing substation components.
See Appendix C for a summary of short circuit analysis results.
System Stability: Based on the dynamics modeling data provided by the customer, the Suwannee 115 and 230 kV combustion turbine units will not jeopardize system stability.
For a tabulation of disturbances and their respective simulation results, refer to Appendix D.
P-V Analysis The results of the analysis indicate that in order to maintain the existing transfer capability of the SOCO-FLA interface, a 75 MVar cap bank should be installed at the 230 kV Perry substation. Appendix E shows that the transfer capability margin of the interconnection in the base case is maintained by using 7.5% impedance GSUs for the new units.
8
![Page 12: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/12.jpg)
Transmission Planning, Florida
Costs
The “Zero MVA” Interconnection Facility costs to interconnect the units are $0.8 million for the expansion of the existing 115kV ring at the Suwannee River 230kV substation from five positions to six.
As for Network Upgrades, based on this System Impact Study, the additional costs for “Full MVA Output” are estimated to be approximately $8.6 million. This includes a conservative estimate of $5 million in Protection & Control projects that are anticipated to be identified in Facility Study.
A table of all estimated costs is below.
The overall total is estimated to be $9.4 million.
If the option is elected for reduced risk of redispatch upon a breaker failure, the new total cost would be estimated at $9.9 million.
*Please note these costs do not include 3rd party impacts, which could be significant in additional scope and cost and will be fully determined in an independent study performed by the FRCC.
9
![Page 13: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/13.jpg)
Transmission Planning, Florida
Feasibility of In-Service Date Based on the identified projects for interconnection and network upgrades, the feasibility of completing these projects in time for the customer’s requested in-service date of June 2016 (two years from the publication of this report) will be challenging with normal project pacing and normal engineering & construction resources. Considerable efforts will be made to achieve the customer’s date, but that date cannot be guaranteed.
It is advised that the customer enter into the Facility Study stage at once.
10
![Page 14: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/14.jpg)
Transmission Planning, Florida
Appendix A - Most significant results from thermal contingency analysis:
11
![Page 15: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/15.jpg)
Transmission Planning, Florida
12
![Page 16: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/16.jpg)
Transmission Planning, Florida
Appendix B - Most significant results from voltage contingency analysis:
*Note: These voltage violations are 3rd-party impacts
13
![Page 17: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/17.jpg)
Transmission Planning, Florida
Appendix C - Short Circuit Analysis Results:
Primary Analysis
BASE STUDY Delta Capacity DutyBus Number Bus Name Bus kV Fault Type (Amps) (Amps) (%) (Amps) (%)
3-Phase to Ground 5,710 5,716 0.11% --- ---Single Line to Ground 3,846 3,858 0.31% --- ---
3-Phase to Ground 6,074 6,616 8.18% 25000 26.46%Single Line to Ground 4,858 4,874 0.32% 25000 19.49%
3-Phase to Ground 7,572 7,660 1.14% 20000 38.30%Single Line to Ground 5,062 5,076 0.27% 20000 25.38%
3-Phase to Ground 7,365 7,234 -1.81% 40000 18.09%Single Line to Ground 4,523 4,520 -0.06% 40000 11.30%
3-Phase to Ground 18,954 17,913 -5.81% 25000 71.65%Single Line to Ground 18,365 18,464 0.54% 25000 73.86%
3-Phase to Ground 19,343 19,829 2.45% 40000 49.57%Single Line to Ground 18,224 20,196 9.76% 40000 50.49%
3-Phase to Ground 7,321 7,353 0.44% 20000 36.77%Single Line to Ground 4,830 4,838 0.15% 20000 24.19%
3-Phase to Ground 18,954 17,913 -5.81% 25000 71.65%Single Line to Ground 18,365 18,464 0.54% 25000 73.86%
3-Phase to Ground 8,288 8,320 0.38% --- ---Single Line to Ground 7,238 7,253 0.21% --- ---
3-Phase to Ground 8,699 8,951 2.82% 40000 22.38%Single Line to Ground 6,066 6,112 0.75% 40000 15.28%
3-Phase to Ground 6,479 6,540 0.93% --- ---Single Line to Ground 4,179 4,184 0.12% --- ---
3-Phase to Ground 6,446 6,640 2.91% 33000 20.12%Single Line to Ground 4,614 4,760 3.08% 33000 14.42%
3-Phase to Ground 10,829 12,471 13.17% 40000 31.18%Single Line to Ground 9,830 11,910 17.47% 40000 29.78%
3-Phase to Ground 11,183 12,790 12.56% 40000 31.98%Single Line to Ground 10,177 12,236 16.83% 40000 30.59%
3-Phase to Ground 6,592 6,629 0.55% --- ---Single Line to Ground 4,910 4,926 0.34% --- ---
3-Phase to Ground 8,138 8,219 0.99% 40000 20.55%Single Line to Ground 5,392 5,409 0.31% 40000 13.52%
3-Phase to Ground 8,524 8,544 0.24% --- ---Single Line to Ground 7,039 7,060 0.29% --- ---
3-Phase to Ground 11,067 11,274 1.84% 25000 45.10%Single Line to Ground 10,744 10,896 1.39% 25000 43.58%
3-Phase to Ground 26,744 26,823 0.29% --- ---Single Line to Ground 26,074 26,125 0.19% --- ---
317205 6N TIFTON 230
316109 3TWINLAKS 115
317203 6PINEGRVE 230
3172 ST MARKS 230
3174 GINNIE 230
3168 SUWANNEE PKR 230
3169 SUWANNEE RV 230
3165 NEWBERRY 230
3167 PERRY 230
3160 CRAWFORDVLLE 230
3162 FT WHITE N 230
3134 OCC SWIFTCK1 115
3158 SUWAN PLT B 115
3132 SUWANNEE PLT 115
3133 SUWANNEE RV 115
3113 JASPER 115
3116 MADISON 115
384 COLUMBIA 115
3108 FT WHITE 115
14
![Page 18: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/18.jpg)
Transmission Planning, Florida
7.5% Generator Step-Up Transformer Sensitivity
BASE STUDY Delta Capacity DutyBus Number Bus Name Bus kV Fault Type (Amps) (Amps) (%) (Amps) (%)
3-Phase to Ground 5,710 5,731 0.36% --- ---Single Line to Ground 3,846 3,871 0.65% --- ---
3-Phase to Ground 6,074 6,663 8.83% 25000 26.65%Single Line to Ground 4,858 4,912 1.10% 25000 19.65%
3-Phase to Ground 7,572 7,731 2.05% 20000 38.65%Single Line to Ground 5,062 5,124 1.20% 20000 25.62%
3-Phase to Ground 7,365 7,326 -0.53% 40000 18.32%Single Line to Ground 4,523 4,574 1.11% 40000 11.43%
3-Phase to Ground 18,954 18,490 -2.51% 25000 73.96%Single Line to Ground 18,365 19,345 5.06% 25000 77.38%
3-Phase to Ground 19,343 20,589 6.05% 40000 51.47%Single Line to Ground 18,224 21,797 16.39% 40000 54.49%
3-Phase to Ground 7,321 7,421 1.34% 20000 37.11%Single Line to Ground 4,830 4,883 1.08% 20000 24.41%
3-Phase to Ground 18,954 18,490 -2.51% 25000 73.96%Single Line to Ground 18,365 19,345 5.06% 25000 77.38%
3-Phase to Ground 8,288 8,338 0.59% --- ---Single Line to Ground 7,238 7,268 0.41% --- ---
3-Phase to Ground 8,699 9,018 3.54% 40000 22.55%Single Line to Ground 6,066 6,178 1.82% 40000 15.45%
3-Phase to Ground 6,479 6,561 1.25% --- ---Single Line to Ground 4,179 4,202 0.55% --- ---
3-Phase to Ground 6,446 6,712 3.96% 33000 20.34%Single Line to Ground 4,614 4,837 4.61% 33000 14.66%
3-Phase to Ground 10,829 12,925 16.21% 40000 32.31%Single Line to Ground 9,830 12,874 23.65% 40000 32.18%
3-Phase to Ground 11,183 13,246 15.57% 40000 33.12%Single Line to Ground 10,177 13,185 22.82% 40000 32.96%
3-Phase to Ground 6,592 6,650 0.86% --- ---Single Line to Ground 4,910 4,943 0.68% --- ---
3-Phase to Ground 8,138 8,259 1.47% 40000 20.65%Single Line to Ground 5,392 5,446 1.00% 40000 13.62%
3-Phase to Ground 8,524 8,575 0.60% --- ---Single Line to Ground 7,039 7,079 0.57% --- ---
3-Phase to Ground 11,067 11,338 2.39% 25000 45.35%Single Line to Ground 10,744 10,950 1.88% 25000 43.80%
3-Phase to Ground 26,744 26,845 0.37% --- ---Single Line to Ground 26,074 26,139 0.25% --- ---
317205 6N TIFTON 230
316109 3TWINLAKS 115
317203 6PINEGRVE 230
3172 ST MARKS 230
3174 GINNIE 230
3168 SUWANNEE PKR 230
3169 SUWANNEE RV 230
3165 NEWBERRY 230
3167 PERRY 230
3160 CRAWFORDVLLE 230
3162 FT WHITE N 230
3134 OCC SWIFTCK1 115
3158 SUWAN PLT B 115
3132 SUWANNEE PLT 115
3133 SUWANNEE RV 115
3113 JASPER 115
3116 MADISON 115
384 COLUMBIA 115
3108 FT WHITE 115
15
![Page 19: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/19.jpg)
Transmission Planning, Florida
Appendix D – Dynamic Analysis Results
Tabulation of Disturbances Tested in Stability Analyses Contingency
Name Description Sequence of events Timing in
Cycles SUW115_3PH 3-PHASE FAULT ON THE SUWANNEE RIVER
115KV BUS
Clear remote end Columbia FPL 115 Clear remote end Suwannee Plant 115 Clear remote end Occidental Swift Creek 115 Clear remote end Pine Grove 230 Clear remote end Fort White 230 Clear remote end Perry 230 Trip Suwannee 115 kV CT on overspeed Trip Suwannee 230 kV CT on overspeed Trip Suwannee 230 kV P1-3 on overspeed
35.0 35.0 35.0 80.0
130.0 180.0 180.0 180.0 180.0
SUW115_SLG SINGLE LINE TO GROUND FAULT ON THE SUWANNEE RIVER 115KV BUS
Clear remote end Suwannee Plant 115 Clear remote end Occidental Swift Creek 115 Clear remote end Fort White 230 Clear remote end Pine Grove 230 Clear remote end Perry 230 Clear remote end Columbia FPL 115 Trip Suwannee 115 kV CT on overspeed Trip Suwannee 230 kV CT on overspeed Trip Suwannee 230 kV P1-3 on overspeed
35.0 35.0 55.0 69.0
119.0 119.0 119.0 119.0 119.0
SUW230_3PH 3-PHASE FAULT ON THE SUWANNEE RIVER 230 KV BUS
Clear remote end Columbia FPL 115 Clear remote end Pine Grove 230 Clear remote end Fort White 230 Clear remote end Perry 230 Trip Suwannee 230 kV CT Trip Suwannee 230 kV P1-3 Clear remote end Suwannee Plant 115 Clear remote end Occidental Swift Creek 115 Trip Suwannee 115 kV CT on overspeed
29.0 29.0 30.0 30.0 55.0 55.0 95.0
185.0 185.0
SUW230_SLG SINGLE LINE TO GROUND FAULT ON THE SUWANNEE RIVER 230 KV BUS
Clear remote end Pine Grove 230 Clear remote end FTW230 Clear remote end Perry 230 Clear remote end Suwannee Plant 115 Clear remote end Occidental Swift Creek 115 Trip Suwannee 115 kV CT on overspeed Trip Suwannee 230 kV CT on overspeed Trip Suwannee 230 kV P1-3 on overspeed
29.0 30.0 30.0 95.0
185.0 185.0 185.0 185.0
SUWPLT_3PH 3-PHASE FAULT ON THE SUWANNEE PLANT 115 KV BUS
Clear remote end Suwannee Plant 115 Clear remote end Madison 115 Clear remote end Twin Lakes 115 Clear remote end Fort White 115 Clear remote end Jasper 115 Clear remote end Hanson 115
29.0 35.0 35.0 35.0 35.0 35.0
SUWPLT_SLG SINGLE LINE TO GROUND FAULT ON THE SUWANNEE PLANT 115 KV BUS
Clear remote end Suwannee Plant 115 Clear remote end Madison 115 Clear remote end Fort White 115 Clear remote end Jasper 115 Clear remote end Twin Lakes 115 Clear remote end Hanson 115
34.0 35.0 35.0 35.0 59.0 65.0
OSC115_3PH 3-PHASE FAULT ON THE OCCIDENTAL SWIFT CREEK 115 KV BUS WITH DELAYED CLEARING
Clear remote end Suwannee 115 kV Clear remote end Jasper 115 kV
95.0 95.0
LVO115_3PH 3-PHASE FAULT ON THE LIVE OAK (FPL) 115 KV BUS WITH DELAYED CLEARING
Clear remote end Suwannee 115 kV Clear remote end WELBRN 115 kV
95.0 95.0
FTW230_3PH 3-PHASE FAULT ON THE FORT WHITE 230 KV BUS WITH DELAYED CLEARING
Clear remote end Suwannee 230 kV Clear remote end Newberry 230 kV Clear remote end Ginnie 230 kV Clear Ft White 230/69 kV Transformers
55.0 55.0 55.0 55.0
PER230_3PH 3-PHASE FAULT ON THE PERRY 230 KV BUS WITH DELAYED CLEARING
Clear remote end Suwannee 230 kV Clear remote end Fl Gas Trsmsn 230 kV Clear Perry 230/115 kV Transformers
55.0 55.0 55.0
PGV230_3PH 3-PHASE FAULT ON THE PINE GROVE (SOCO) 230 KV BUS WITH DELAYED CLEARING
Clear remote end Suwannee 230 kV Clear Pine Grove 230/115 kV Transformers Clear remote end Valdosta 230 kV Clear remote end Tifton 230 kV
55.0 55.0 55.0 55.0
SUW115-SUWPLT_3PH
3-PHASE FAULT ON THE SUWANNEE RIVER TO SUWANNEE PLANT 115 KV LINE
Clear remote ends on the Suwannee River to Suwannee Plant 115 kV Line
95.0
16
![Page 20: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/20.jpg)
Transmission Planning, Florida
SUW115-OSC115_3PH
3-PHASE FAULT ON THE SUWANNEE RIVER TO OCCIDENTAL SWIFT CREEK 115 KV LINE
Clear remote ends on the Suwannee River to Occidental Swift Creek 115 kV Line
95.0
SUW115-LVO115_3PH
3-PHASE FAULT ON THE SUWANNEE RIVER TO LIVE OAK (FPL) 115 KV LINE
Clear remote ends on the Suwannee River to Live Oak (FPL) 115 kV Line
95.0
SUW230-FTW230_3PH
3-PHASE FAULT ON THE SUWANNEE RIVER TO FORT WHITE 230 KV LINE
Clear remote ends on the Suwannee River to Fort White 230 kV Line
55.0
SUW230-PER230_3PH
3-PHASE FAULT ON THE SUWANNEE RIVER TO PERRY 230 KV LINE
Clear remote ends on the Suwannee River to Perry 230 kV Line
55.0
SUW230-PGV230_3PH
3-PHASE FAULT ON THE SUWANNEE RIVER TO PINE GROVE (SOCO) 230 KV LINE
Clear remote ends on the Suwannee River to Pine Grove (SoCo) 230 kV Line
55.0
Tabulation of Stability Analyses Results
Contingency Name
2016 Peak Load Case Results
2016 50% Load Case Results
2016 Peak Load Case Results
(7.5% GSU Sensitivity)
2016 50% Load Case Results
(7.5% GSU Sensitivity) SUW115_3PH Damped response;
Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
SUW115_SLG Damped response; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
SUW230_3PH Damped response; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
SUW230_SLG Damped response; FPL Columbia line relay tripped at 110 cyc; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; FPL Columbia line relay tripped at 29 cyc; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
Damped response; FPL Columbia line relay tripped at 111 cyc; Suwannee Units tripped on overspeed; 489MW of generation lost; no UFLS activated
Damped response; FPL Columbia line relay tripped at 29 cyc; Suwannee Units tripped on overspeed; 334MW of generation lost; no UFLS activated
SUWPLT_3PH Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
SUWPLT_SLG Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
OSC115_3PH Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
LVO115_3PH Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
FTW230_3PH Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
PER230_3PH Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
PGV230_3PH Damped response; no units tripped; no UFLS activated
Damped response; FPL Columbia line relay tripped at 55 cyc; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; FPL Columbia line relay tripped at 55 cyc; no units tripped; no UFLS activated
SUW115-SUWPLT_3PH
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
SUW115-OSC115_3PH
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
SUW115-LVO115_3PH
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
SUW230-FTW230_3PH
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
SUW230-PER230_3PH
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
SUW230-PGV230_3PH
Damped response; no units tripped; no UFLS activated
Damped response; FPL Columbia line relay tripped at 55 cyc; no units tripped; no UFLS activated
Damped response; no units tripped; no UFLS activated
Damped response; FPL Columbia line relay tripped at 55 cyc; no units tripped; no UFLS activated
Note: Detailed stability analysis results are available upon request.
17
![Page 21: System Impact Study for DEF GISRs, Queue Positions 125 & 126 · 2019-12-23 · to-ground faults were applied up to three breakered buses away from the DEF Suwannee River 230 kV substation](https://reader036.vdocuments.site/reader036/viewer/2022081217/5f9d56a45c3c3e202c6c5e8d/html5/thumbnails/21.jpg)
Transmission Planning, Florida
Appendix E – P-V Analysis Results:
SOCO-FLA Interface Transfer Capability Margin (MW) Summer 2017
Perry 75 MVar Contingency Base 16.6% 7.5%
Duval 76 91 84 91 Duval 82 131 113 125 Thalmann 80 103 109 118 Sanford #5 203 200 206 Sanford #4 216 212 222
18