system engineering - summer school alpbach

37
ESA UNCLASSIFIED – Releasable to the Public System Engineering Christian Erd Alpbach 27/07/2012

Upload: others

Post on 18-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

ESA UNCLASSIFIED – Releasable to the Public

System Engineering

Christian Erd Alpbach 27/07/2012

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 2

ESA UNCLASSIFIED – Releasable to the Public

Mission Flow Diagram

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 3

ESA UNCLASSIFIED – Releasable to the Public

Mission Phases

1. Phase 0 – Analysis/needs identification a. Understanding of functional

and technical requirements (correct requirements formulation and priorities), mission statement

b. Definition of mission concept (design, profile, configuration)

2. Phase A – Feasibility a. Freezing of requirements b. Breakdown of subsystems,

definition of interfaces and 3. Phase B – Preliminary Definition

a. Subsystem requirements b. Preliminary subsystem

design

1. Phase C – Detailed Definition a. Detailed subsystem design b. Performance simulations c. Mathematical models (thermal,

power, structural; observation, comm., etc)

2. Phase D – Production & Qualification a. EM, STM, PFM b. Environment qualifications &

verifications (thermal-vac, vibration, EMC, etc)

3. Phase E – Utilization a. Mission operations planning b. Navigations support c. Science operations planning d. Data analysis/exploitation

4. Phase F – Disposal a. Data archiving and final

documentation

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 4

ESA UNCLASSIFIED – Releasable to the Public

Approximate Timeline of Phases

Activity Approximate Duration ESA Internal Assessment Phase 0 1.25 yrs Industrial Assessment Phase A 2.25 yrs Definition Phase B1 0.5 yrs Preparation of Implementation Phase 1 yr Implementation Phase B2/C/D 5 – 7 yrs

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 5

ESA UNCLASSIFIED – Releasable to the Public

Properties of Requirements

1. Requirements: Formal statement expressing what is needed to fulfil the mission objectives

2. Mission statement: captures the objectives and measurements required in a single sentence

3. Requirements should be product related, not process related 4. Good Examples:

a. The mission shall provide a measurement of the x constant with an accuracy better than 10–13

b. The mission shall allow scanning of the sky with an angular rate of 60 arsec/s around an axis of rotation which is 50°±0.1° away from the Sun direction

c. The mission shall have a nominal in-orbit duration of 4 years 5. Bad Examples:

a. The system design shall maximise the spectral resolution b. The mass shall be below 1000 kg

6. Clear requirements are key to good design 7. Requirements are hierarchical: lower level system requirements shall come

from higher level mission requirements

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 6

ESA UNCLASSIFIED – Releasable to the Public

Requirements Example

The science telemetry shall be downloaded using Ka-band telemetry

Good or Bad ??

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 7

ESA UNCLASSIFIED – Releasable to the Public

Requirements & Design Drivers

1. Identification of design drivers is result of requirements analysis a. First iteration during definition of mission concept

2. Design drivers constrain flexibility of system design there should be as few as possible!

3. Classification of requirements: unavoidable – negotiable

4. Typical (expected) unavoidable design drivers for outer planet missions a. Power generation b. Communications

5. Negotiable (examples):

a. Telemetry downlink b. Mission profile: mission duration, flybys, sequence of events

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 8

ESA UNCLASSIFIED – Releasable to the Public

Design Driver – Distance

http://nssdc.gsfc.nasa.gov/planetary/factsheet

1. (solar) Power generation

2. Telemetry slant range

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 9

ESA UNCLASSIFIED – Releasable to the Public

Design Driver – Environment

1. Example: Jupiter mission

1.E+03

1.E+04

1.E+05

1.E+06

1.E+07

1.E+08

1.E+09

0 2 4 6 8 10 12 14 16 18 20

Shielding Thickness [mm Al - solid sphere]

Dose

[rad

(Si)]

JGO (full mission)GEO (12 year mission)MEO (12 year mission)

Shieldose

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 10

ESA UNCLASSIFIED – Releasable to the Public

Design Driver – Planetary Protection

Planet Priorities Mission Type

Mission Category

Not of direct interest for understanding the process of chemical evolution. No protection of such planets is warranted.

Any I

Of significant interest relative to the process of chemical evolution and the origin of life, but only a remote chance that contamination by spacecraft could compromise future investigations

Any II

Of significant interest relative to the process of chemical evolution and the origin of life and for which scientific opinion provides a significant chance of contamination which could compromise future investigations.

Flyby, Orbiter

III

Lander, Probe

IV

Any solar system body Earth-Return

V

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 11

ESA UNCLASSIFIED – Releasable to the Public

Planetary Protection – Target Classification

1. Category I: Flyby, Orbiter, Lander: Undifferentiated, metamorphosed asteroids; others TBD

2. Category II: Flyby, Orbiter, Lander: Venus; Moon (with organic inventory); Comets; Carbonaceous Chondrite Asteroids; Jupiter; Saturn; Uranus; Neptune; Ganymede*; Titan*; Triton*; Pluto/Charon*; Ceres; Kuiper-Belt Objects > 1/2 the size of Pluto*; Kuiper-Belt Objects < 1/2 the size of Pluto; others TBD

3. Category III: Flyby, Orbiters: Mars; Europa; Enceladus; others TBD

4. Category IV: Lander Missions: Mars; Europa; others TBD

5. Category V: Any Earth-return mission. a. “Restricted Earth return”: Mars; Europa; others TBD b. “Unrestricted Earth return”: Venus, Moon; others TBD

* The mission-specific assignment of these bodies to Category II must be supported by an analysis of the “remote” potential for contamination of the liquid-water environments that may exist beneath their surfaces (a probability of introducing 1 viable terrestrial organism of <10–4), addressing both the existence of such environments and the prospects of accessing them.

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 12

ESA UNCLASSIFIED – Releasable to the Public

Spacecraft Subsystems

Structure

Communi- cations

Propulsion

Power

Avionics AOCS

Thermal

Configuration Payload

Launcher

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 13

ESA UNCLASSIFIED – Releasable to the Public

Trade-off

1. Trade-off allows exploring alternative solutions to a baseline

2. The parameter space needs to be prepared, and an evaluation criterion shall be established

3. Most common criteria: mass, cost; several system properties can be translated into them –

a. Power consumption generation of more power solar array size mass

b. Higher telemetry volume larger HGA, more power for TM&C mass

c. Very complex solutions more effort for verification longer integration time cost

Mass Cost

System Performance

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 14

ESA UNCLASSIFIED – Releasable to the Public

Trade-off Example: optimisation of solar array mass

1. Cover glass thickness: a. Thicker cover glass: better protection

against radiation, more mass b. Thinner cover glass: less mass, higher

degradation of solar cells

Radiation damage Cover glass obscuration

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 15

ESA UNCLASSIFIED – Releasable to the Public

Orbital Elements

1. Orbital plane is defined by a. The right ascension of the

ascending node Ω b. The inclination i

2. Orientation of the orbital trajectory (ellipse) is defined by

a. The argument of periapsis ω b. Eccentricity of the orbit e c. Semi-major axis

3. Reference times a. Epoch is the time since last

passage of periapsis b. The reference date for one

periapsis passage

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 16

ESA UNCLASSIFIED – Releasable to the Public

Other Local Coordinate Systems

1. Magnetic coordinates offset from bulk coordinates

2. Local coordinates rotating with the planet

3. Also left-handed systems in use!

4. Local coordinates of moons a. Similar to local planet

coordinates b. Longitude =0 at

meridian facing planet

Europa

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 17

ESA UNCLASSIFIED – Releasable to the Public

Technology Readiness Levels

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 18

ESA UNCLASSIFIED – Releasable to the Public

The TRL of a given technology is always evaluated in the context of a specific application, not by itself.

Readiness Level Definition Explanation

TRL 1 Basic principles observed and reported

Lowest level of technology readiness. Scientific research begins to be translated into applied research and development. (See Paragraph 4.2)

TRL 2 Technology concept and/or application formulated

Once basic principles are observed, practical applications can be invented and R&D started. Applications are speculative and may be unproven. For SW, individual algorithms or functions are prototyped. (See Paragraph 4.3).

TRL 3

Analytical and experimental critical function and/or characteristic proof-of-concept

Active research and development is initiated, including analytical / laboratory studies to validate predictions regarding the technology. For SW, a prototype of the integrated critical system is developed. (See Paragraph 4.4)

TRL 4 Component and/or breadboard validation in laboratory environment

Basic technological components are integrated to establish that they will work together. For SW, most functionality is implemented. (See Paragraph 4.5)

TRL 5 Component and/or breadboard validation in relevant environment

The basic technological components are integrated with reasonably realistic supporting elements so it can be tested in a simulated environment. For SW, Implementation of the complete software functionality. (See Paragraph 4.6)

TRL 6

System/subsystem model or prototype demonstration in a relevant environment (ground or space)

A representative model or prototype system is tested in a relevant environment. For SW, ready for use in an operational/production context, including user support. (See Paragraph 4.7)

TRL 7 System prototype demonstration in a space environment

A prototype system that is near, or at, the planned operational system. For SW, used in IOD or applied to pilot project. (See Paragraph 4.8)

TRL 8

Actual system completed and “flight qualified” through test and demonstration (ground or space)

In an actual system, the technology has been proven to work in its final form and under expected conditions. For SW, ready to be applied in the execution of a real space mission. (See Paragraph 4.9)

TRL 9 Actual system “flight proven” through successful mission operations

The system incorporating the new technology, or software, in its final form has been used under actual mission conditions. (See Paragraph 4.2.10)

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 19

ESA UNCLASSIFIED – Releasable to the Public

Margins – Contingencies

1. Equipment level margins according to maturity a. 5% for off-the-shelf items (no changes) b. 10% for off-the-shelf items with minor modifications c. 20% for new designs, new developments, major modifications

2. System margin (at least 20%) a. On top of and in addition to equipment margins; applied after

summing best estimates + margin b. Two options for the propellant calculation +10% margin + 2%

residuals – Margin on total dry mass and margin on launcher: typically

used during early study phases +10% margin – Margin on maximum separated mass: typically used later,

when mission analysis and launcher analysis become available

3. Always keep lots of margins 4. “Margin philosophy for Science Assessment Studies” (in library)

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 20

ESA UNCLASSIFIED – Releasable to the Public

Spacecraft Subsystems

Structure

Communi- cations

Propulsion

Power

Avionics AOCS

Thermal

Configuration Payload

Launcher

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 21

ESA UNCLASSIFIED – Releasable to the Public

Power – Nuclear Sources

1. Basically using heat generated by radioactive decay and a thermo-electric converter

2. Degradation a. Half life: Pu (88 yrs), 241Am (433 yrs) b. Themo-electric element: ~0.8% /yr

3. Radioisotope Heating Unit (RHU)

a. US: 1 W 40 g b. Rus: 8 W 200 g

Name Electrical Thermal Mass

MMRTG (238Pu) 110 W 2000 W 45 kg

ASRG (238Pu) 160 W 500 W 34 kg

ESA (Am2O3) <1 W/kg

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 22

ESA UNCLASSIFIED – Releasable to the Public

Power – Solar Arrays

1. Rosetta: 62 m2, Si technology, 443 W at 5.35 AU

2. JUICE: 64 m2, Triple junction GaAs Low-Intensity-Low-Temperature (LILT) technology, ~30% efficiency (BOL)

3. Physical properties (typical): 9.4 W/m2, 3 W /kg

4. Radiation damage (NIEL=Non-Ionising Energy Loss)

a. Protons: ∫𝑑Φ𝑝+ 𝐸

𝑑𝐸𝑁𝑁𝑁𝑁𝑝+ 𝑁 𝑑𝑁

b. Electrons: ∫𝑑Φ𝑒– 𝐸

𝑑𝐸𝑁𝑁𝐸𝑁𝑒–(𝐸)𝑎

𝑁𝑁𝐸𝑁𝑒–(1𝑀𝑀𝑀) 𝑎−1 𝑑𝑁

5. Need to include batteries for energy storage during eclipse!

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 23

ESA UNCLASSIFIED – Releasable to the Public

Power – Solar Arrays

-160 -140 -120 -100 -80 -60 -40 -20 0 20 4024

26

28

30

32

34

36

η

3.7 % AM0 BOL

ηAM0 BOL

Effic

ienc

y [%

]

Temperature [°C]1E14 1E15 1E16

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

1.1

AM0 relative degredation curve (established under room temperature)

η/η 0

1MeV electron fluence [cm-2]

Relative degredation of 3G28 solar cells (established under LILT conditions)

cell 73-7 cell 73-10 cell 92-3

Radiation Damage Efficiency

Radiation models at SPENVIS: http://www.spenvis.oma.be

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 24

ESA UNCLASSIFIED – Releasable to the Public

Communications

1. Telemetry budget, receiver margin: Eb/N0 ratio of received-energy-per-bit to noise-density

2. Transmitter a. P transmitter power b. Ll transmitter line loss c. Gt transmitter antenna gain (area, shape, λ–2)

3. Transmission a. Ls space loss (slant range) b. La transmission path loss (atmosphere,

etc) 4. Receiver

a. Gr receiver antenna gain b. kTs system noise energy

5. Data rate: R

𝑁𝑏𝑁0

=𝑃 ∙ 𝑁𝑙 ∙ 𝐺𝑡 ∙ 𝑁𝑠 ∙ 𝑁𝑎 ∙ 𝐺𝑟

𝑘 ∙ 𝑇𝑠 ∙ 𝑅

see also in SMAD

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 25

ESA UNCLASSIFIED – Releasable to the Public

Communications

1. High Gain Antenna (HGA) versus pointing performance 2. Optimum antenna diameter for known AOCS off-pointing 3. Further iteration to be done once AOCS performance is known

Diam1

Diam2 > Diam1Pointin

P

1

2

3

4

(the

Diam1

Diam2 > Diam1Pointin

P

11

22

33

44

(the

Parabolic reflector antenna @ 32,05GHz

0,00

0,05

0,10

0,15

0,20

0,25

0,30

0,35

2 2,2 2,4 2,6 2,8 3 4 5 6

Antenna diameter [m]

Dou

ble

side

d be

amw

idth

[deg

]

51,50

52,00

52,50

53,00

53,50

54,00

54,50

55,00

55,50

56,00

Gai

n w

ith o

ff-po

intin

g [d

Bi]

3dB double sided beamwidth [deg] Gain with off-pointing of 0,1deg [dBi]see also in SMAD

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 26

ESA UNCLASSIFIED – Releasable to the Public

Attitude and Orbit Control System

1. Allows maintaining the desired spacecraft attitudes 2. Trade-off: spinner versus 3-axis stabilized 3. Composed of

a. Sensors (to measure actual attitude) – Star trackers measure attitude wrt to inertial directions and

have accuracy between 1 arcsec and 1 arcmin – Sun sensors have accuracy between 20 arcsec and – 1 deg – Gyros measure angular rates and can be used together with

Star trackers for high accuracy pointing b. Actuators (to achieve desired attitude)

– Reaction wheels – Thrusters

4. Choice of sensors and actuators widely depends on requirements

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 28

ESA UNCLASSIFIED – Releasable to the Public

Attitude Control Definitions

see also ECSS-E-ST-60-10C

MPE mean performance error APE absolute performance error RPE relative performance error AKE absolute knowledge error MKE mean knowledge error RKE relative knowledge error PDE performance drift error PRE performance reproducibility error

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 29

ESA UNCLASSIFIED – Releasable to the Public

Propulsion

1. The subsystem in charge of satellite manoeuvring 2. Includes thrusters, tanks, piping and valves 3. Many technologies available

a. Solid thruster: single one off, high thrust b. Monopropellant c. Bi-propellant: d. Solar Electric

4. For orbital manoeuvres with high ΔV: “high” Isp (> 300 s) – e.g. bipropellant or electric propulsion

5. For orbital manoeuvres with low ΔV: “medium” Isp and thrust (~1 N) – e.g. monopropellant - hydrazine

6. For fine control: “low” thrust: (≤10 mN) – cold gas or FEEP based

7. Specifics for deep space missions: a. Pressurized tanks will be necessary (engine re-start) b. Valve isolation and redundancy

500 N engine

22N thruster

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 30

ESA UNCLASSIFIED – Releasable to the Public

Propulsion Design

1. Propellant mass 𝑀prop = 𝑀dry × (𝑒∆𝑣

𝑔∙𝐼sp − 1)

2. Needs to include: a. All deterministic manoeuvres (ΔV) b. Navigations manoeuvres (stochastic) c. All AOCS needs (momentum wheel off-loading, SAFE mode,

etc) 3. Propulsion system dry mass rule of thumb: 0.2 × Mprop

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 31

ESA UNCLASSIFIED – Releasable to the Public

Example Propulsion System

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 32

ESA UNCLASSIFIED – Releasable to the Public

Propulsion – RCS Thrusters

1. Definition and location of thrusters

2. Force-free layout

3. Thrusting in any direction in any attitude

4. Redundancy required

5. RCS Thrusters could act as backup for main engine

Messenger RCS layout

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 33

ESA UNCLASSIFIED – Releasable to the Public

Avionics

1. The subsystem in charge of handling all mission and system onboard data, of hosting and running the onboard software

2. Composed of a. On-board computer (CDMU), Mass Memory Unit,

RTUs/interface electronics 3. Often payload has its own computer for on-board science data

processing

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 34

ESA UNCLASSIFIED – Releasable to the Public

Thermal

1. The subsystem that allows keeping the spacecraft and payload temperatures within allowable limits

2. Generally, separated thermal control for spacecraft and payload due to different temperature requirements

3. Basic principles: a. Insulate the spacecraft from the

environment to keep stable temperatures inside and provide an aperture for dissipation of excess heat (radiator).

b. During eclipse provide heating power to keep the spacecraft warm

4. Composed of : thermal blankets (MLI), external paints to modify optical properties, radiator(s) and associated heat transport devices (heat pipes, high conductivity paths)

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 35

ESA UNCLASSIFIED – Releasable to the Public

Thermal Design

1. Spacecraft Thermal verification: 2. Assume single node and make thermal balance

𝑄intin + 𝑄extin = 𝑄out

𝑄out = ε𝜎𝑇4𝐴rad

𝑄int𝑖𝑖 = 𝑃dissipated

𝑄extin = 𝛼𝐴exposed𝑆 + 𝑄PlanetIR + 𝑄Albedo

3. Solve first for Arad (radiator area) fixing max allowed T and optical

properties 4. Solve then to find Pdissipated needed to keep T within limits in eclipse for

Arad

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 36

ESA UNCLASSIFIED – Releasable to the Public

Structure

1. The subsystem that supports all the spacecraft equipment and payload and allows withstanding the mission loads

2. Primary structure: Satellite “backbone”, carrying the loads transmitted to the spacecraft by the launcher through the launcher interface. It includes external panels if they support high mass components

3. Secondary structure: supports harness, propellant lines, and panels and brackets for small components

4. Structure is a large fraction of the total satellite mass: ~30 % 5. Many different types and shapes depending on mission architecture

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 37

ESA UNCLASSIFIED – Releasable to the Public

System Summary

1. Budgets: Mass, Power

2. Mission profile & lifetime

3. Launcher: launch mass, fairing

4. Total system margin

System Engineering | Christian Erd | Alpbach | 27/07/2012 | SRE-F | Slide 38

ESA UNCLASSIFIED – Releasable to the Public

Launch !