Sydenham School Residents Meeting 11-02-14. Caretakers House Demolition. Decking to STEM and ARTS. Decking to STEM and ARTS. Concrete Frame. First Floor Slab. Rebar – Second Floor. Arts First Floor - Rebar. External MUGA and Lighting Layout. Car Park - Denver Pole Luminaire 5m columns. - PowerPoint PPT PresentationTRANSCRIPT
Sydenham School
Residents Meeting11-02-14
Caretakers House Demolition
Decking to STEM and ARTS
Decking to STEM and ARTS
Concrete Frame
Arts First Floor - Rebar
Rebar – Second Floor
First Floor Slab
External MUGA and Lighting Layout
Car Park - Denver Pole Luminaire 5m
columns
MUGA - Scorpius Luminaire 8m
columns
Upcoming Works
• Brickwork/Blockwork • Continue installing pre cast walls and columns along with In-
Situ elements• Scaffolding continuing • Decking continuing along lower ARTS – F/F and upwards• Concrete Pour to upper ARTS