syba tiles-manufacturing process - morocco...
TRANSCRIPT
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 1
A stable precision frame and a polished plate guarantee the future dimensions and smooth surface of the tiles
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 2
For each motif there is a metal template which divides the various colour zones from each other. This metal template is placed in the precision frame
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 3
The individual fields are filled with a pasty mixture of marble dust, mineral granulate and pigments
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 4
The metal template is carefully removed. This produces the typical soft transitions between the zones of the decor
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 5
The tile pattern is now ready and is carefully inspected once more
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 6
The coloured top layer of the tile is now quickly covered with almost-dry mortar
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 7
The stamp is placed on it and the tile is then hydraulically pressed under great pressure
Marrakech - Maroc
email [email protected]
Telephone +212-661-499 445 fax +212-524-423435
SYBA TILES SARL A.U
TILES - CARREAUX - FLIESEN
Manufacturing ProcessStep 8
The stamp and the frame are removed, the tile is carefully released from the mould. The tiles are then stored for the cement to dry and harden
Marrakech - Maroc