“Surat City Development Plan (CDP) and its Implementation”
National Seminar on
“Urban Governance in the Context of JNNURM”
24th November, 2006
New Delhi
Presented By Surat Municipal Corporation, Surat.
City Development Plan - Structure
1. Introduction to Surat
2. Exiting Stage of City's Development
3. Perspective Vision of CDP for the City
4. Investment Plan and Financing Strategies
5. Project Features
6. Implementation of CDP
7. Conclusion
Introduction to Surat
• Global City with global standards and global values.
• Proactive in strategizing its future. • Known for textile trade, diamond cutting &
polishing. • Strength to convert adversity into advantage. • Formulated • City Corporate Plan in 1999 • Vision Document in 2004 • City Development Plan in 2005.
• Successfully filled the infrastructure gap.
Growth of City
• Historical Development - 300 BC
• Municipality Established In 1852 AD.
• Municipal Corporation Formed In 1966.
• Area Expanded from 6.3 Sq km to 334 Sq Km.
MAP SHOWING EXTENSION OF CITY
LIMIT OF SURAT MUNICIPAL CORPORATION
LEGENDCITY LIMIT UPTO
FEB 2006
NEWLY ADDED AREA IN MARCH
2006
AREA ADDED IN JULY '06
Glory of Surat The Silk City, the Diamond City •Historical City • East India Company Landed First in the City • Traditional Trade & Commerce Center • Focal Point on the Western Corridor • Commercial Capital of Gujarat •Hub of Mixed Religious and Cultural Character • Known for Peace and Harmony • Blessing of Perennial River Tapi
Linkages & Connectivity • Vicinity to Arabian Sea and Magdalla Port • On the Mumbai- Ahmedabad Golden Corridor • Connected to National Highway No.- 8 • Directly connected via Rail and Bus
Canal
Tapi River
Canal
Canal
Surat
Dum
as R
oad
Ring Road
Surat - Navsari State Highway
Bhim
rad - A
lthan
Roa
d
Udna - Magdalla Road
South Gujarat University
Civil Hospital
Textile Market
Magdalla - Sachin State Highway
Udna Udhyog Sangh
Udna Railway Station
Surat Railway Station
A.P.M.C.
N
Transport Godown
Godh Dhod RoadCi
ty Lig
ht Ro
ad
Agricultural University
To Bhusawal
Puna - Bardoli State Highway
Surat Kamrej State Highway
To
Ahm
edab
ad
NH-8N
H-8 To
Mum
bai
To M
umbai
To
Ahm
edab
ad
To Hazira
Dandi Road
Olpad Road
Surat - Navsari
State Highway
Sachin - Magdalla State Highway
Tapi
River
Airport
Existing Stage of City's Development
• Unprecedented growth in last four
decades.
• 10-fold population rise.
• Now ranks the 9th largest city in the
country.
• Jurisdictional limits extended by 3 fold.
Salient Features • Area under Urbanisation –
more than 700 sq.km. • Population – more than 35
lakh • Civic Agencies – SUDA,
SMC, Municipalities & Panchayats
• SMC Area – 334 Sq km • Catering to 28 Lakh
population • 9 Municipalities
• SUDA Area – 722 Sq. km. • More than 140 Villages • 4 Talukas
Urban Sprawl
Area of City : 334.23 Sq.Km.
Total Population: 28.77 Lakhs
(Census 2001)
Total Zone : 7 Nos.
MAP SHOWING EXTENSION OF CITY LIMIT OF SURAT MUNICIPAL
CORPORATIONLEGEND
CITY LIMIT UPTO FEB 2006
NEWLY ADDED AREA IN MARCH
2006
AREA ADDED IN JULY '06
City Population
Surat City Growth-Population
35
9
15
35
24
63.75%
85.36%
60.23%66.22%
43.81%
0
5
10
15
20
25
30
35
40
1961 1971 1981 1991 2001 2006
Census Year
Po
pu
lati
on
(P
ers
on
s i
n
Lacs)
0%10%20%30%40%50%60%70%80%90%
Decad
al
Gro
wth
Rate
(%
)
Census Year
Area (Sq. Km.)
1961 8.18
1971 33.85
1981 55.56
1991 111.16
2001 112.27
2006 334
580
440
676
97 97 97
530550
510480440
380
269216199180
565
343
335329
318308297275 286
45 48 5085 97959490
0
100
200
300
400
500
600
700
800
1995
-96
1996
-97
1997
-98
1998
-99
1999
-00
2000
-01
2001
-02
2002
-03
2003
-04
2004
-05
2005
-06
Years
Supp
ly (M
LD)
Av. Water Supply (MLD) Requirement (MLD) % Area Covered
City Services
Water Supply
Treatment Capacity increased from 360 MLD to 628 MLD Daily water supply increased from 440 MLD to 580 MLD Gross per capita water supply increased from 160 to 195 ltrs.
71
142.5
262.5
562.5
425
142.5142.5
462.5
262.5225
281 292 306341
380405
30
65544485 95
4330
0
100
200
300
400
500
600
1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03
Years
Sew
erag
e (M
LD)
Sewage Treatment Capacity Available Sewage Generation (MLD) % Area & Pop. Covered
Sewerage
City Services
Capacity augmented from 262 MLD to 562.5 MLD & 1028.50 km main trunk line laid
Total 6 Sewerage Treatment Plants No. of sewerage pumping station increased from 18 (in 1996) to 28 now
Solid Waste Management
City Services
Collection and disposal of 98% of total solid waste generated Door to Door Garbage Collection Night Brushing and Scraping Scientific Land Filling Centralised Bio-medical waste Collection, transportation,
treatment & final disposal facility
A Primary collection 98%Regular employees 4503
Part time employees 601Grants to Societies 400
B Collection , transportation & disposal 980 M.T. 98%Privatised
SMCC Night brushing 384649 Sq.Mt.D Equipments
Dumper/Dumper placer 67
Trucks/Loaders/Escavators 49
Tractors 39
Wheel burrows 4255Containers 1703
F Scientific Sanitary Land Fll Site 1 Unit
172 roads
60%40%
Components/YearRoad length in kms 673 1133% area covered 60 94Fly overs 0 4Bridges 2 5Traff ic Signals (Junctions) 4 29Traff ic Islands 9 89No. of Street lights 18227 46108% area covered 60 98
1995 2005
City Services
Roads & Bridges
Physical Infrastructure Water Supply – 97% Population covered Sewerage – 95% Population covered Solid Waste – 98% Population covered Roads – 94% Coverage (> 1000 k.m. ) Street Light – 98% Population Covered Spatial Planning – 93% Area Covered
Social Infrastructure • Medical Facility & Education • Indoor Stadium • Museum • Planetarium • Swimming pools • Zoo and Nature Park • Libraries • Auditoriums • Vegetable Market
Achievement - Surat
Achievement - Surat Urban Governance & Management • Efficient & Responsive Governance • Daily Monitoring System • Public Participation • IT Policy • e-governance • Bio-matrix attendance system • Efficient Establishment • Outsourcing - PPP • Advanced Accounting System • Grievance Redressal System
Reforms
• Accrual Based Double Entry Book Keeping • Area Based Self Assessed Property Tax System- Initialised
• e-Governance & GIS • Efficient Tax Collection • Reduction in Establishment Charges • Out Sourcing & PPP • DCR Revision • User Charges
User Charges
Services Cost Recovered Recovery Target Time Frame 2003-04 2004-05 2003-04 2004-05
Water Supply 5692 7642 2992 3563 5 Yr
Conservancy 8554 10500 3342 3591 4 Yr
Roads & Illumination
1677 2549 4 Yr
Rs. In Lakhs
Achievement - Surat Financial Performance • Budget Size : Rs. + 1000 Cr.
• Spared Revenue Surplus for Capital Works
• Outsourcing of Services (PPP)
• Efficient Tax Collection (85% of Current)
• Accrual Type of Double Entry Accounting System
• Bare Minimum Debt Servicing
Year
Income Expenditure Revenue Capital Loan Revenue Capital
2000-01 40036 12147 4306 30982 20739 2001-02 41543 13923 8266 36253 15927 2002-03 49403 1696 0 33371 16640 2003-04 52977 5375 0 35386 17270 2004-05 61984 4657 0 43906 17487
Rs. In Lakhs
Achievement - Surat
Financial Performance
Composition of Revenue Expenditure
19.6%
10.1%
4.6%4.3%
17.4%
44.1%
0.0%
Estab. Expenditure Admn.& General Exp.Repairs & Maintenance Service & Prog.(Direct Expenses)Other Expenses AppropriationDebt Servicing
Composition of Revenue Income
29.6%
13.3%
3.7%
48.2%
1.8%3.4%
Own sources Octroi Taxes
Non-tax sources Other income Grants & Subsidies
Average of 5 Years : 2000-2005 Average of 5 Years : 2000-2005
Composition of Capital Income
9%
33%
58%
Own Sources Grant and Contribution Borrowings
Average of 5 Years : 2000-2005 Average of 5 Years : 2000-2005
Alternative Planning Approaches • Conventional mode - Physical Master
Planning Approach • Long preparation periods • Technocratic orientation • Focused on land use planning • Limited Public Participation • Inadequate Attention on Infrastructure Development &
Financing • Missing project identification and prioritization
approach • The Strategic Planning Process provides
• Evolves Vision and Goals through Participatory Process • Fundamental decisions and actions that shapes and
guides the city • what the City is, • what it should be & • what it should do in future
• Frames Policies, Programmes to achieve the Vision • Integrates physical, economic, fiscal and institutional
aspects of the city
Participatory process involving all stakeholders and comprising: • A Strategic Plan- A Plan relating Master Plan proposals and Sectoral
Strategies • A Capital Investment Plan- Prioritizing Physical Investments
• Multi- Year scheduling of public physical improvements and investments • Rolling five year perspective, Priorities for investment through
consultation • Iterative exercise- Linked to the Financial and Operating Plan • Involves identification of public capital facilities to cater to the demand of
the city populace
• A Financial and Operating Plan- A Financial Viability test for Proposed Investment Plan • - A Forecast of revenues and expenses during the planning horizon under
alternative revenue performance and Project implementation options • Projection of yearly revenue under various heads and alternative
assumptions. • Estimation of capital expenditure for providing infrastructure at different
service levels. • Estimation of additional O & M cost due to the new schemes. • Estimation of annual debt servicing burden under alternative scenarios of
loan / grant mix
An Approach
Stake holders’ opinion – 2000-2002
City Corporate Plan – 2003
Vision Document – 2004
Stake holder’s review - 2005
City Development Plan - 2005
Events
Public Participation
Disbursement of 30,000 Questionnaires to the stakeholders
Key Partners
Political & Executive wings of SMC & SUDA, GMFB, GSRTC, GCCI, GIDB, CEPT,CII, Educationists, Medical Association, Chamber of Commerce, Trade Unions, leading citizens, etc.
Visioning Exercise Initiated by SMC with assistance of World Bank in January 2000 Stakeholders : Representatives from all sectors- politicians, NGOs, business, civil servants, citizens Follow up meetings throughout 2000-2002
Public Participation
• Evaluation of Existing Services To measure the satisfaction level for the existing services, SMC had distributed approximately 30,000 copies of
Questionnaires to the identified general and specific stakeholders.
12.6 percent of the questionnaires were duly filled in by the
stakeholders and suggestions made were analysed.
• SWOT Analysis Analysis of the duly filled in questionnaires made SMC have a
close look at what it believed to be the STRENGTHS, areas for IMPROVEMENTS together with the THREATS and OPPORTUNITIES it faced.
Public Participation
Capital Investment Need (MIP)
Capital Investment
Program (CIP)
Finances • Sources & Uses of
funds • Base and basis of levy
of major taxes and
charges • Collection issues • Uses • Rate of growth • Per-capita Analysis
Services • Current levels of services • Water supply • Sanitation • Roads • Solid Waste Management • Drainage • Lighting • Others
City Development Plan
• Rates of growth • Revenue revision assumptions • Collection performance • Expenditure growth Assumptions • Assumption on O&M for new investments • Lending options • - Loan grant mix • - Loan terms
Strategic Plan
Financial and
Operating Plan
Project Identification & Facility Siting • Sectoral Strategies • Integration of Line Agency Projects • Public Priorities
Situation Assessment Capital Improvement Program
Vision & Goals
Methodology
1. Promoting Growth business to flourish by adopting a judicious mix of policies, in centives,
tariff structure, assured power supply, access to the serviced l and, creation of markets and high quality affordable infrastructure,
1B Improve Connectivity Improve connectivity through a combination of high
2. Good Governance
2A Managing Urban Growth
2B Strengthening Urban Governance
Inter - 3. Improved Service Delivery
3A Access to Basic Services
3B Mass Rapid Transit
3C Road Network Improvements -
Strategic Focus
1. Promoting Growth
1A Enabling Economic Development
1B Improve Connectivity 2. Good Governance
2A Managing Urban Growth
2B Strengthening Urban Governance
2C Inter Agency Coordination - 3. Improved Service Delivery
3A Access to Basic Services
3B Mass Rapid Transit
3C Road Network Improvements -
SURAT VISION 2020
A Global City with Global Standards Strategic Focus
4.Environmental Improvement
CDP Vision
Strategic Focus : CDP
Promoting Growth Good Governance
Improved Service Delivery Environmental Improvement
CDP- Strategies Promoting Growth
Enabling Economic Development • Creating business friendly environment
• Rejuvenating markets • Provide quality infrastructure • Gas & Power supply • Service land
• Streamlining processes • Trade & Tariff
Improved Connectivity • High speed strategic links via air, surface & water
• Airport • Coastal Highway • Water Transport
• IT & Telecom • Mass / Rapid Transport System
• Expressway • Ring Road
CDP- Strategies Good Governance Managing Urban Growth
• Evolving Vision/ City Development Plan
• Concept of Greater Surat region
• Resource Mobilisation
• Inter Agency Coordination
Strengthening Urban Governance
• Transparent, Accountable & Responsive Governance
• e-governance, GIS
• Capacity building
• Public Private Participation
• Out sourcing
• IT & Use of state of the art technology
CDP- Strategies
Improved Service Delivery • Access to Basic Services
• 24 X 7 Water Supply
• Efficient Transport System • Bridges, Flyovers,
• Integrated Road Development
• Public Transport System
• World Class Infrastructure • C.C. Roads
• SCADA for All Services
• ISO Certification
• Center for Excellence with Industrial Focus • Business/Industrial Tourism
• Stadium/ Sports Complex
CDP- Strategies Environmental Improvement • Safe Environment
• Reducing Flood Risk
• River Front Development
• Reduction in Pollution • Use of Eco-Friendly Resources
• No Pollution Zone
• Ecological Balance • Mass Scale Tree Plantation
• Water Conservation
• River Conservation
• Water Harvesting
SWOT Analysis in CDP for Surat
Strength • Economic Diversity • Sustained Growth • Mega Industrial Establishments • Quality – Cheap labour • Social Harmony • Sense of belongingness • Alternate to Mumbai
Weakness • Medium Quality Power Supply • Weak Connectivity by roads • Lack of Premier Institution • Unregulated Peri-Urban growth • Absence of Air connectivity & Public Transport
Opportunity • Growth potential of a Global city
• Demand of International Trade, Transit & Social Infrastructure • Enhancing quality of life
Threat • Environmental degradation
• Policy risks
• Health concerns
Future Augmentation Strategies
• With stabilized trend, Surat would be reaching to a population of 43.25 Lakhs in 2011 and 58.39 Lakhs in 2021 would required following capacities to be augmented :
Sector Particulars Year 2011
Year 2021
Water Supply Total water demand (MLD) 956 1241
Augmentation WTP 4 nos. (MLD) 1000 1440
Intake well capacity Augmentation 3 nos. (MLD)
1440 -
Sewage System STPs capacity augmentation 7nos. (MLD)
912.5 1194.5
Strom Water Drainage System
Network length (km) 401.08 -
Solid Waste Management
Generation & disposal (M.T.) 1278 1549.70
Housing for urban poor (By Year 2012)
Rehabilitation (Houses) 31781
Redevelopment (Houses) 34553
Up gradation (Houses) 27321
Strategic Approach - JNNURM
Strategy Action Preparing City Development Plan (CDP) Stake holders’ consultation
City Corporate Plan (CCP) Surat Vision 2020 Stake holders’ review City Development Plan (CDP)2006-2012
Initiating Reforms Double Entry Book Keeping, e-Governance & GIS User Charges & efficient tax collection Administrative Reforms Area Base Self Assessed Property Tax
Preparing Projects & Submission
Identification of Projects Prioritization of projects Detailed Project Reports.
Release and Leveraging of Funds Tripartite Agreement & MOA Signed Projects Sanctioned worth Rs. 370 Crores
Incorporating Private Sector Efficiencies PPP Initiated
Investment Plan - Sectoral Outlay (Rs. In Lakhs)
S. No Projects SMC SUDA
1 Inner City Revitalization &
Heritage 8200 2 Water Supply ( incl. scada ) 22210 39600 3 Sewerage 29100 42000 4 Solid Waste Management 800 8000
5 Environment Improvement with Urban Forestry 16300 17600
6 Transportation 180762 98000 7 EWS / LIG Housing 73885 35175 8 Special Projects 27400 2000 9 GIS Applications 500
10 Social Infrastructure 4763 9350 11 Tapi Riverfront Development 100000 Total 496817 251725
• Total Outlay – Rs. 7485.42 Crores (2006-12)
Project Features (City)
Sr. No.
Name of Project TOTAL
1 Cement Concrete Roads, Illumination 915
2 Inner Ring Road development 130
3 Parking Facility/ traffic junction 570
4 Sewerage Network 400
5 Storm Water Drainage Network 760
6 Gopi Talao Development 500
7 Heritage –Building/Ovara/precincts restoration 3400
8 Public buildings - community hall, markets, etc. 1480
TOTAL 8200
(Rs. In Lakhs) Inner City Revitalization & Heritage
Project Features - City
Projects Capacity Estimated Cost
(Rs. In Lacs) Present Proposed
Augmentation of Source
Intake wells 840 MLD 1440 MLD 3290 Water Treatment Plants 628 MLD 1440 MLD 5422 Storage Reservoirs 147 ML 216.75 ML 1698 Transmission Pipelines 2000 All Elect-Mechanical Works at Water Works 450 24 X 7 Water supply Scheme & System Up gradation With ISO 9001: 2000 Certification 1530
Zone Level Water Supply Schemes 7821 Total Estimated Cost (Rs. In Lacs) 22211
• Water Supply- 580 MLD to 1241 MLD by 2011 with 100 % area coverage • 24 X 7 water supply with ISO 9001:2000 Quality Standard • As a Part of Long-term Water Supply Master Plan up to Year 2021.
Water Supply
Projects in Periphery Area Water Supply • GWSSB scheme - 3 locations as under : Pal 1. Under ground tank 110 lacs litres. 2. Pumping capacity 2800 m3/hr. 3. Supply hours : Eight hours in a day. Vesu 1. Under ground tank 178 lacs litres. 2. Pumping capacity 4600 m3/hr. (4 Nos. of pumps) 3. Supply hours : Eight hours in a day. • 38 km of pipes in Pal area • 60 km pipes in Vesu area • Door to door connection
• In addition to this, other areas will also be provided with water supply
scheme. • Total cost of water supply component will be Rs. 396 crores.
(Rs. in Lakhs)
Sr. No. Zone / Projects Project Cost Major Benefits
1 Central Zone 600.00Sewerage System works Elimination of untreated sewage flow
2 North Zone 7600.00Biogas based power plant Energy saving - conservationTertiary Treatment Plant Reduce pollutants load in the riverAugmentation of Sewage Treatment Plant Facility with increased populationSewerage System works Elimination of untreated sewage flow
3 East Zone 2770.00Biogas based power plant Energy saving - conservationAugmentation of Sewage Treatment Plant Facility with increased populationSewerage System works Elimination of untreated sewage flow
4 South-East Zone 1700.00Upgradation of Sewage Treatment Plant Reduce pollutants loadSewerage System works Facility to low-cost and slum area
Project Features- City
Sewerage
• Provide Sanitation facility to all • Protecting sub-soil contamination
(Rs. in Lakhs)
Sr. No. Zone / Projects Project Cost Major Benefits
5 South Zone 10900.00Biogas based power plant Energy saving - conservationSecondary Treatment Plant Reduce pollutants loadCommon Effluent Treatment Plant Comprehensive wastwater systemAugmentation of Sewage Treatment Plant Facility with increased populationSewerage System works Facility to low-cost and slum area
6 South-West Zone 5500.00Biogas based power plant Energy saving - conservationAugmentation of Athwa Sewerage Scheme Facility with increased populationAugmentation of Sewage Treatment Plant Facility with increased populationSewerage System works Elimination of untreated sewage flow
7 West Zone 4700.00Augmentation of Adajan Sewerage Scheme Facility with increased populationAugmentation of Sewage Treatment Plant Facility with increased populationBiogas based power plant Energy saving - conservationSewerage System works Elimination of untreated sewage flow
Total: 33770.00
Project Features-City Sewerage
Sewerage -Periphery Area • Initially project covering area of 1800 hectors comprising Vesu & Pal-
Palanpur at a cost of Rs. 77 Crores is being taken up. Total land admeasuring 22,29,344 m2 have been reserved for constructing treatment plants at various places for covering the entire network of SUDA.
PAL Auxiliary Pumping Station with a pumping capacity of 31.17 mLd . Pipeline
network 44 Kms. With size ranging from 300 mm dia. to 1400 mm dia. VESU Intermediate Pumping Station and Auxiliary Pumping Station have a capacity of
10.87 & 57.00 mLd respectively. The network will have a length of 68 Kms. And having a pipe size of dia. 300 mm dia. to 1600 mm dia.
Amroli – Chhaprabhatha (six villages) first phase for this area is designed for 25 MLD of sewage at an estimated cost
of Rs. 220 million. Puna-Simada and Parvat – Goddhara first Phase scheme for this area is designed for 50 MLD of sewage at an
estimated cost of Rs. 450 million. Total cost of sewerage schemes in 68 TP schemes will be Rs. 420 crores.
Project Features - City Solid Waste Management
Sr. Item Cost
1 Earth moving & road equipments 310 2 MSW transportation 165 3 Workshop 125 4 Sanitary Land Fill, Waste to Energy 200
Total 800
(Rs. In Lakhs)
• 100% door to door waste collection •100% Segregation at source •Waste to energy
Storm Water Drainage - Periphery Area • Due to its location on banks of the river Tapi and on the bank of river
Mindhola near the estuary of the Arabian Sea, the land drainage in SUDA area is relatively not well developed. The table shows Year-wise Area to be Covered Under Storm Water Drains in SUDA Area.
• Initially projects are prepared for Vesu and Pal-Palanpor area at a cost of Rs. 60 crores covering the total area of 1800 Ha.
• It is proposed to cover the major part of the SUDA area by efficient network of storm water disposal at a cost of Rs. 176 crores over a period of 7 years. Also, to prevent the flood water entering into SUDA area, provisions are to be made for flood gates at disposal points.
Year Area in Ha. 2006 285 2006-07 2385 2007-08 2385 2008-09 2385 2009-10 480 2010-11 240 2011-12 240 Total 8400
Area to be Covered under Storm Water Drains
Project Features - City Environment Improvement & Urban Forestry
Sr Detail Cost 1 Drainage Works 2700
2 Barrage project in river Tapi 5000
3 Flood protective sluice regulator 600
4 Diversion of storm drains in Tapi 2500
5 Flood protective RCC wall 5300
6 Surat Pushpa Nagri Project 200
Total 16300
(Rs. In Lakhs)
• Taking up mass scale tree plantation • Flood Protection on Tapi River • Water & Air Quality Monitoring
Project Features - City
Transportation Sr. Details Cost
1 Bridges & Flyovers 74840
2 C. C. Roads 23349
3 Canal Road Development
30000
4 Traffic Management 41573
5 Integrated Road Development
11000
Total 180762
(Rs. In Lakhs)
Roads, Flyovers and Bridges - Periphery Area PROPOSAL for Roads:
1. Approximately 670 K.M. of Roads will be constructed in 67 T.P. Schemes to facilitate movement of vehicles.
2. A Ring Road of 66 K.M. length will be constructed, out of 66 K.M. length 44 K.M. is existing Road, which will be upgraded to 4-lane roads, and remaining 22 K.M. of new road will be constructed.
3. Approximate cost for development of roads will be Rs. 675 crores
4.The cost for construction of Ring Road will be Rs. 195 Crores.
Proposals for Bridges:
1.Construct Bridge on River Tapi Near Valak to complete the Ring Road.
2.To construct Bridge on River Mindhola near Abhwa for shortening the travel distance to Ubhrat the well known tourism.
3. Construction of ROB at Sachin, Kosad and Gothan to complete the Ring Road.
No. Width (Mtr)
Lane Total length (Mts)
Total length (Kms)
1 6 1 13400 13.40
2 7.5 1.5 26800 26.80
3 9 2 93800 93.80
4 12 2.5 180900 180.90
5 .15 2.5 388600 38.86
6 18 4 160800 160.80
7 24 4 56950 58.95
8 30 6 80400 80.40
9 36 6 6700 6.70
10 40 6+2 11390 11.39
670000 670.00
Housing for Urban Poor - City HOUSING AND BASIC SERVICES TO URBAN POOR
Description No. of Slum settlements
No. of Huts/
Houses
Cost (Rs. In lakhs)
Rehabilitation 121 31781 31700
Redevelopment 111 34553 40000
Upgradation 80 27321 2185
• Housing for urban poor • Providing Infrastructure to all • Open defecation free cities
Housing for Poor- Periphery Area PROPOSAL: • To construct 1500 houses every
year for Low Income Group in 5 different areas of SUDA. Total 10500 houses will be constructed in 7 years.
• To construct 1500 houses every year for Economically Weaker Section of Society at 5 different locations of SUDA. Total 10500 houses will be constructed in 7 years.
• Providing Infrastructure in the housing colonies of EWS and LIG Schemes
• Providing community toilets – bath, childcare centres, community halls, health centers etc.
• Estimated cost of housing for LIG is Rs. 273 crores and for EWS Rs. 78.75 crores.
The expenditure for LIG and EWS will be Rs. 351.75 crores
No Year LIG Amount in Crores
No. of EWS houses
Amount in Rs. crores
1 2 3 4 5 6
1 2006 154 4 -- --
2 2006-07 1923 50 1333 10
3 2007-08 1923 50 2000 15
4 2008-09 1923 50 2000 15
5 2009-10 1923 50 2000 15
6 2010-11 1923 50 2000 15
7 2011-12 731 19 1167 8.75
Total 10500 273 10500 78.75
Project Features • Special Projects
• Science Centre, Museum And Art Gallery -on an 18,420 sq. mt. site.
• Trade Center - 10000 sq.mt. - cost of 22 crores. • Multidisciplinary aquarium • Alia bet development • Water sports
Project Features G.I.S. Application
• Land Records • Building Permission • T.P.Schemes & Base Map Preparation • Property Tax Assessment • Basic Services like water supply, sewerage, road network, etc. • Traffic Management • Supervision & Monitoring of Services by Staff • Operation & Maintenance of Infrastructure • Solid Waste Collection and Disposal • Vehicle tracking system, • Total Cost of the Project is Rs. 3 Crores
Project Features - City Social Infrastructure Sr Details Cost 1 Slaughter house 900 2 Auditorium in South West Zone 700 3 Swimming pool in east and north zone 750 4 Diving Pool in West Zone 332 5 Vegetable market 700 6 Lake development and garden 1181 7 Sports complex 200
Total 4763
(Rs. In Lakhs)
Social Infrastructure - Periphery Area
• One Garden in each T.P.Scheme will be develop at the cost of Rs. 50 Lacs per Garden with a total cost of Rs. 33.5 Crores.
• Existing 4 Lakes in SUDA Area will be developed at the cost of Rs. 5 Crores per Lake with a total cost of Rs. 20 Crores.
• Two Crematorium in the SUDA Area will be
constructed at the cost of Rs. 5 Crores each with a total cost of Rs. 10 Crores.
• Community Hall at 5 locations is proposed in SUDA area
Project Features Tapi River Front Development Sr. Details Cost 1 2 * 3 Lane River Drive Road – 30 km length 14000 2 Bank Protection Works 120000 3 Strengthening of Existing Bridges, Weir,
etc. 10000
4 Interceptor Storm Drain 10000 5 Rehabilitation of Slums 6 Street Furniture 5000 7 Land Development 3000 8 Rubber Dam – Barrage Projects 10000
Total Rs. in Crores 171000
(Rs. In Lakhs)
Capital Investment Plan (City)
Total project cost Rs. 4968 Crores
Phasing Over 7 Years Up to 2011-12
JNNURM capital grant Rs. 3770 Crores
SMC contribution Rs. 1655 Crores
Loans Rs. 92 Crores
Investment sustainability 144% (with JNNURM) 46% (without JNNURM)
Capital Investment Plan (Periphery Area)
Total project cost Rs. 2517 Crores
Phasing Over 7 Years Up to 2011-12
JNNURM capital grant Rs. 1385 Crores
SUDA contribution Rs. 1076 Crores
Loans Rs. 56 Crores
Investment sustainability 58% (withJNNURM)
Outlay phasing (2006-2011)
Year
Total Out Lay JNNURM Grant Own Resources
City Periphery City Periphery City Periphery
2005-06 19826 5000 13878 3500 5948 1500
2006-07 86969 51850 60878 36295 26091 15555
2007-08 75027 61000 52519 42700 22508 18300
2008-09 96629 56500 67640 39550 28989 16950
2009-10 103883 46000 72718 32200 31165 13800
2010-11 81586 31375 57110 21963 24476 9413
Total
496817 251725 324744 176208 139176 75518
Rs. In Lakhs
Implementation of City Development Plan under JNNURM
Projects/ DPRs City Periphery Total
Total Projects as per City Development Plan-
2006-12, Surat
Rs. 4968.17 Cr. Rs. 2517.25 Cr. Rs. 7485.42 Cr.
DPRs submitted to SLNA, Govt. of Gujarat
39 Nos. worth Rs. 883.6 Cr.
8 Nos. worth Rs. 301.97 Cr.
47 Nos. worth Rs..1185.57Cr.
DPRs sanctioned by SLSC, Govt. of Gujarat and submitted to Govt. of India.
26 Nos. worth Rs. 665.18 Cr.
8 Nos. worth Rs. 301.97 Cr.
34 Nos. worth Rs. 967.15 Cr.
DPRs sanctioned by CSMC, Govt. of India.
7 Nos. worth Rs. 235.41 Cr.
5 Nos. worth Rs. 134.74 Cr.
12 Nos. worth Rs. 370. 15 Cr.
DPR Technical Scrutiny Sanctioned by Govt. of India.
2 Nos. worth Rs. 109.95 Cr.
1 Nos. worth Rs.107 Cr.
3 Nos. worth Rs. 216.95Cr.
Forth Coming Projects for year 2006-07 &
2007-08
69 Nos. worth Rs. 925.56 Cr.
Conclusion
• CDP to be considered as a flexible document – Revision recommended from time to time as per changed scenario.
• It is CDP’s vision to make Surat a self-
motivated, vital, futuristic city and to see that citizens live a life with new dimensions of global standards.
• Surat Municipal Corporation has promised to
make utmost efforts to realize the citizen’s dream and work transparent in a democratic way.
Let us make Surat… ….. future global city
….GREEN CITY ....CLEAN CITY
....VIBRANT CITY ....SAFE CITY
....CULTURED CITY ....PROSPEROUS CITY
For further information please Visit Surat Municipal Corporation,