Supporting Industry Change Planning:
Risk, Issue & Milestone Assessment Process Clarifications
04/08/2014
![Page 2: Supporting Industry Change Planning: Risk, Issue & Milestone Assessment Process Clarifications 04/08/2014](https://reader035.vdocuments.site/reader035/viewer/2022072015/56649ed35503460f94be2f0c/html5/thumbnails/2.jpg)
Context
• Xoserve presented a risk and milestone assessment approach at the COB on 7th July
• The concept was well received and support given to piloting the process
• Prior to commencing the pilot the COB attendees requested that Xoserve provides some clarifications on certain specific details of the process and tools
• This deck aims to clarify the following:
1. How data confidentiality will be maintained within the process2. The approach for maximising participation3. Enhancements to the data capture form following the feedback in COB
![Page 3: Supporting Industry Change Planning: Risk, Issue & Milestone Assessment Process Clarifications 04/08/2014](https://reader035.vdocuments.site/reader035/viewer/2022072015/56649ed35503460f94be2f0c/html5/thumbnails/3.jpg)
Data confidentiality
• Xoserve encourages respondents to exercise their discretion concerning the information shared to safeguard highly sensitive commercial information
• The information presented at COB will be an aggregated, industry view of risks, issues, and milestone progress without named reference to particular respondents
• The information presented at COB will be published and publically available
• Individual respondent data will not be published or used for any other purposes
• Xoserve can confirm it is not subject to requests under the FOIA
![Page 4: Supporting Industry Change Planning: Risk, Issue & Milestone Assessment Process Clarifications 04/08/2014](https://reader035.vdocuments.site/reader035/viewer/2022072015/56649ed35503460f94be2f0c/html5/thumbnails/4.jpg)
Inclusiveness
• The COB will only derive value from the process if the level of response is sufficiently high to represent an ‘industry view’
• All industry participants who need to undertake change programmes associated with the assessed change drivers are invited to participate in the process
• Xoserve will proactively encourage participation from the broadest possible range of industry stakeholders via the following measures:
1. All materials pertaining to the process will be published on the Joint Office website to ensure access for all
2. Questions or clarifications on the process and tools are encouraged and can be directed to the Xoserve Stakeholder Engagement team
3. Xoserve will proactively engage with organisations who have not been represented at COB to stimulate their participation in the process
![Page 5: Supporting Industry Change Planning: Risk, Issue & Milestone Assessment Process Clarifications 04/08/2014](https://reader035.vdocuments.site/reader035/viewer/2022072015/56649ed35503460f94be2f0c/html5/thumbnails/5.jpg)
Data Capture Form Enhancements
ToolTool / Process Enhancement
Rationale Update Made
Risk and Issue Assessment
Clarify guidelines on impact and probability scoring
To aid consistency in scoring the risk and issues
New tab added to the data capture form which provides guidance on risk and issue scoring
Risk and Issue Assessment
Expand the framework to include issue tracking
A view of current issues (and resolution actions) is also valuable to COB
New tab added to the data capture form to enable respondents to record issues
Milestone Reporting
Reduce the no. of reported key milestones
Reduces the reporting burden. Focuses the reporting on milestones which are on the critical path
Modified the reporting template to adopt the following key milestones:
•Design •Internal Test •Market Test•Implementation
Milestone Reporting
Include Xoserve change programme key milestone dates within the data capture form
COB requested the central programme dates to factor into their delivery plans
Reporting template modified to include Xoserve key milestone dates
• The table below summarises updates made to the data capture form following feedback from the COB on 7th July
![Page 6: Supporting Industry Change Planning: Risk, Issue & Milestone Assessment Process Clarifications 04/08/2014](https://reader035.vdocuments.site/reader035/viewer/2022072015/56649ed35503460f94be2f0c/html5/thumbnails/6.jpg)
Next Steps: Activities & Timelines
Xoserve
Industry
w/c 07-Jul w/c 14-Jul w/c 21-Jul w/c 28-Jul w/c 04-Aug w/c 11-Aug w/c 18-Aug w/c 25-Aug w/c 01-Sep
COB COB COB
Process & tools
presented at COB
Progress Update
Risk, Issue and Milestone
Data Presented
Answering questions, tool & process refinement
Data collated & packaged
Detailed review of the tools & dialogue with Xoserve
Prepare status check
Complete and submit the data capture form
Xoserve will present an update on the progress of the initiative at the August COB. The update will cover
levels of engagement and clarifications following any queries
on the process or tools
Please review the process and tools within your own organisation and begin to record risk, issue and
milestone information. Please proactively engage with Xoserve
should you have any queries.
Please submit a complete data capture form to Xoserve no later
than Friday 15th August.
Xoserve intends to present the packaged risk, issue and milestone
information at the COB on September 1st