    GENERAL SPECIFICATION

    SUPPLIER DOCUMENT REQUIREMENTS (SDR)

    5 040305 EvB Various Changes DZO CvB

    4 020703 GvS Various additions DZO CvB

    3 020403 JRO Change Logo DZO CvB

  • 8/17/2019 Supplier Document Requirements SDR GDF

    2/14

     

    TABLE OF CONTENTS

    1. DOCUMENT IDENTIFICATION

    2. LANGUAGE

    3. FORMATS

    4. UNITS OF MEASURE

    5. DOCUMENTS FOR REVIEW

    6. FINAL DOCUMENTS

    7. SUPPLIER DATA BOOKS

    8. NUMBER AND TYPE OF DOCUMENTS

    9. INSTALLATION, MAINTENANCE AND OPERATING MANUAL

    10. MANUFACTURING DATA RECORD

  • 8/17/2019 Supplier Document Requirements SDR GDF

    3/14

     

    1.0 DOCUMENT IDENTIFICATION

    1.1 All documents shall be properly marked with Buyer’s Purchase Order number and item/tag number (for

    drawings in the title block at the bottom right hand corner).The SDR Code System shall be used by Supplier to identify information requested by Buyer.

    Strict compliance with the SDR Code System is required. Non-conformance may lead to a delayed review

    cycle.

    1.2 For identical equipment/material, Supplier shall provide typical drawings/documents applicable to each

    separate equipment/material.

    The correlation between tag number, line number etc. and an equipment/material item number shall be

    specified by an index on the drawing/document.

    2.0 LANGUAGE

    All drawings and documents shall be written in the ENGLISH language.

    3.0 FORMATS

    Size of drawings shall not exceed A-1 size.

    4.0 UNITS OF MEASURE

    The international System of Units (SI Units) shall be used throughout, dual units (SI Units with imperial in

     parentheses or vice versa) are also permitted. However, with following exceptions:

    a. Nominal pipe/fitting/valve sizes in inches and pressure rating in lbs in accordance with ASME pressure

    classes

     b. Pressure in bar

    c. Liquid flow in m3/h

    d. Gas flow in Nm3/h (0°C, 1.01325 bara).

    5.0 DOCUMENTS FOR REVIEW

    5.1 Review by Buyer shall mean that Buyer will retrieve data for its design and will check the document for

    interface data. Supplier shall not start fabrication until Buyer has acknowledged such review and possible

    comments have been incorporated.

    5.2 Documents submitted "For Review" will be returned within three (3) calendar weeks.

  • 8/17/2019 Supplier Document Requirements SDR GDF

    4/14

     

    7.0 SUPPLIER DATA BOOKS

    7.1 Supplier shall ensure that the formats of the Supplier Data Books, i.e.

    1. Installation, Maintenance & Operating Manual (IMO)2. Manufacturing Data Record (MDR)

    are in accordance with paragraph 9.0 and 10.0. The requirements as described in latter paragraphs are

    minimum requirements, which shall be supplemented as necessary to fulfil the requirements and to allow

     professional operation and use of the subject equipment. In case of doubt Supplier shall contact Buyer for final

    advise. In all cases Supplier to complete the attached SDR.

    7.2 All Supplier Data Books shall be bound in A-4 heavy-duty binders with transparent pockets on the cover and

    spine and 4 hole ring binder mechanisms. Maximum spine width to be 60 mm.

    7.3 Each section shall be separated by using numbered dividers.

    8.0 NUMBER AND TYPE OF DOCUMENTS

    Required number and type of documents for Buyer shall be as defined hereafter:

    "With Bid" documents : 2 prints

    "For Review" documents : 3 prints

    "For Final" documents : 3 prints

    "Certified as-built" drawings : on disk in AutoCAD version 2000.

    Installation, Maintenance & : 5 copies (after final review of the master set by Buyer)

    Operating Manual (IMO)

    Manufacturing Data Record : 2 copies (after final review of the master set by Buyer’s

    (MDR)/Certificates inspector)

    9.0 INSTALLATION, MAINTENANCE AND OPERATING MANUAL (IMO)

    IMO formats shall be compiled according to following format and contents (in so far as appropriate for the

    ordered equipment) and shall be applicable for the complete package including deliveries from sub-suppliers:

    - Cover sheet and spine * Equipment tag number.

    * Equipment description.

    * Purchase Order number.

    * Supplier details.

  • 8/17/2019 Supplier Document Requirements SDR GDF

    5/14

     

    - Section 3 * Installation

    - Equipment installation, alignment and replacement procedures.

    - Commissioning procedures and checklists.- Access and lifting.

    - Section 4 * Operation 

    - Operation instructions.

    - Functional descriptions.

    - Operation and control procedures.

    - Instrument set point list.

    - Valve numbering drawings.

    - Section 5 * Maintenance

    - Preventative maintenance schedules/details.

    - Routine maintenance.

    - Condition monitoring including lube oil analysis/ condemning

    limits.

    - Routine test procedures.

    - Trouble shooting procedures including diagnostic charts.

    - Section 6 * Data sheets (completed by manufacturer)

    - Mechanical/instrumentation/electrical data sheets.

    - Instrument list.

    - Section 7 * Drawings

    - For type of supply list of applicable drawings including, but not

    limited to:•  General arrangement drawings and weights

    •  Process and instrumentation diagrams

    •  Cause and Effect diagrams

    •  Piping/Electrical and Instrumentation/Structural

    •  Parts drawings.

    - "Certified as-built" drawings.

    - Material lists.

    - Section 8 * Parts data

    - Equipment/package component details (for re-ordering from

    original manufacturer, including parts not supplied as spare).

    - Completed spare parts list, including all sectional/exploded view

    drawings necessary to identify and install the spare parts.

  • 8/17/2019 Supplier Document Requirements SDR GDF

    6/14

     

    10.0 MANUFACTURING DATA RECORD (MDR)

    MDR formats shall be compiled according to following format and contents (in so far as appropriate for the

    ordered equipment):

    - Cover sheet and spine * Equipment tag number.

    * Equipment description.

    * Purchase Order number.

    * Supplier details.

    - Contents/index sheet

    - Section 1 * General- Summary of sub-ordered equipment/material/services with sub-

    Supplier details and scope descriptions.

    - Section 2 * Data sheets

    - Manufacturer's completed data sheets.

    - Section 3 * Specification/code references

    - Concessions and waivers.- Non-conformance reports.

    - Section 4 * Design Calculations

    - Latest revision as reviewed by Buyer.

    - Section 5 * Manufacturer's fabrication report

    - Manufacturer's certificate of compliance (confirmation that the

     package is designed, fabricated and inspected in accordance withPurchase Order requirements).

    - Completed quality control plan.

    - Government related documents.

    - Inspection release certificates.

    - Section 6 * Procedure

    - Manufacturing, fabrication, examination and repair procedures.

    - Welding procedures WPS.- Welder qualification records plus welder list with names, stamp,

    qualification and WPS.

    - NDT operator qualifications and certificates.

    - Performance/string test procedures.

    - Dimensional control procedure.

  • 8/17/2019 Supplier Document Requirements SDR GDF

    7/14

     

    - Section 8 * Inspection/Test Reports

    - Material inspection.

    - Mechanical inspection.- Balancing, dynamic and overspeed tests.

    - Hydrostatic/leakage test.

    - Runouts and clearances inspection.

    - Performance test.

    - Optional tests, such as:

    ⋅  NPSHR test;

    ⋅  complete unit test;

    ⋅  tandem test;. gear test;

    . helium test;

    . sound level test;

    ⋅  spare parts test;

    . auxiliary equipment test;

    ⋅  post-test inspection of casing;

    . full pressure/full load/full speed test;

    ⋅  post-test inspection of the hydraulic coupling fit.- Electrical functional test.

    - Instrumentation functional test.

    - Painting/surface preparation.

    - Lifting and weighing.

    - Preparation for shipment.

    - Section 9 * Drawings

    - Index.- Fabrication and design drawings.

    - Weld and NDE identification drawings.

    - "Certified as-built" drawings.

    - Section 10 * Other relevant documentation

    The SDR code(s) selected are shown on following page(s).

  • 8/17/2019 Supplier Document Requirements SDR GDF

    8/14

    SUPPLIER DOCUMENT REQUIREMENTS (SDR) 

    DOCUMENTS SHOWN BELOW SHALL BE LISTED ON THE SUPPLIER DOCUMENT REGISTER (SDR CODE

    PJ-01). ABBREVIATIONS ARE SHOWN BELOW.

    Abbreviations Key: A-award (i.e. telefax, letter) P-Purchase Order placement, T-test, D-delivery, '-'-before, '+'-after,

     blank - no requirement, R-review by inspector. Example: +4A = four weeks after award, -2D = two weeks, before

    delivery.

    PURPOSE AND TIMING

    Data Book(Yes)SDR

    CODE

    SDR - CODE DESCRIPTION With

    Bid

    For

    ReviewIMO MDR

    PROCUREMENT 

    PC-01 START-UP AND COMMISSIONING SPARE PARTS LIST- Itemized and priced. X +8P X

    PC-02 OPERATIONAL SPARE PARTS LIST

    Completed/priced spare parts list for 2 years normal operation

    complete with drawings, views for identification of spares

    X +8P X

    PC-03 SPECIAL TOOLS LIST - Itemized and priced. X +8P X

    PC-04 PROJECT QUALITY CONTROL & INSPECTION PLAN

    Supplier's proposed inspection plan identifying specific qualitycontrol activities, based on Supplier’s Quality Manual. X +4P X

    PC-05 PROJECT SCHEDULE

    Bar chart identifying Supplier's engineering, procurement,

    fabrication and testing schedules including detailed sub-ordered

    activities.

    +2P

    PC-06 SUB-SUPPLIERS/CONTRACTORS LIST +8P X

    GENERAL

    GE-01 SUPPLIER DOCUMENT REGISTER

    Listing of all documents, identified SDR codes, to be submitted to

    satisfy the SDR codes, as per attached format.

    +2P

    GE-02 CATALOGUE INFORMATION/DESCRIPTIVE LITERATURE

    OF MECHANICAL EQUIPMENTX X

    GE-03 TRANSPORT/LIFTING/STORAGE RECOMMENDATIONS

    Provide proposed packing, lifting and storage details andrecommendations.

    -2D X X

    GE-04 WEIGHT DATA SHEET

    Data sheet as contained in the specification completed by Supplier.+8P X

    GE-05 NOISE DATA SHEET+8P X

  • 8/17/2019 Supplier Document Requirements SDR GDF

    9/14

    SUPPLIER DOCUMENT REQUIREMENTS (SDR) 

    DOCUMENTS SHOWN BELOW SHALL BE LISTED ON THE SUPPLIER DOCUMENT REGISTER (SDR CODE

    PJ-01). ABBREVIATIONS ARE SHOWN BELOW.

    Abbreviations Key: A-award (i.e. telefax, letter) P-Purchase Order placement, T-test, D-delivery, '-'-before, '+'-after,

     blank - no requirement, R-review by inspector. Example: +4A = four weeks after award, -2D = two weeks, before

    delivery.

    PURPOSE AND TIMING

    Data Book(Yes)SDR

    CODE

    SDR - CODE DESCRIPTION With

    Bid

    For

    ReviewIMO MDR

    CIVIL/MARINE

    ST-01 FOUNDATION DRAWINGS

    Show dimensions, locate supports, weights, inflicted loads

    (static/dynamic), size and location of anchor bolts and civil details.

    +6P X

    ST-02 STRUCTURAL FABRICATION DRAWINGS

    Tubulars, plate girders, etc.+8P X

    ST-03 STRUCTURAL DESIGN CALCULATIONS +8P X

    ST-04 STRUCTURAL SUPPORT DRAWINGSLocation, loads and specific requirements.

    +8P X

    ST-05 MANUFACTURING AND TESTING PROCEDURES

    Structural steel (tubulars/girders/sections).+8P X

    MECHANICAL

    ME-01 MECHANICAL UNIT OUTLINE DRAWING

    Preliminary general arrangement (foot print) showing sizes, layout

    major components, connections.

    +4P X X

    ME-02 EQUIPMENT DATA SHEETS

    Data sheets as contained in the specification completed by Supplier.+6P X X

    ME-03 PERFORMANCE DATA AND CURVES X +4P X

    ME-04 GENERAL ARRANGEMENT/CROSS

    SECTIONAL/ASSEMBLY DRAWING - Shows dimensions, all

    components with tag numbers, layout, locations, all connections,routing and location of piping, valves and instruments and electrical

    materials.

    +6P X X

    ME-05 PARTS LIST

    Identify all materials, make, type, material, quantity.+6P X X

    ME-06 NOZZLE LOADING

  • 8/17/2019 Supplier Document Requirements SDR GDF

    10/14

    SUPPLIER DOCUMENT REQUIREMENTS (SDR) 

    DOCUMENTS SHOWN BELOW SHALL BE LISTED ON THE SUPPLIER DOCUMENT REGISTER (SDR CODE

    PJ-01). ABBREVIATIONS ARE SHOWN BELOW.

    Abbreviations Key: A-award (i.e. telefax, letter) P-Purchase Order placement, T-test, D-delivery, '-'-before, '+'-after,

     blank - no requirement, R-review by inspector. Example: +4A = four weeks after award, -2D = two weeks, before

    delivery.

    PURPOSE AND TIMING

    Data Book(Yes)SDR

    CODE

    SDR - CODE DESCRIPTION With

    Bid

    For

    ReviewIMO MDR

    ME-12 DYNAMIC BALANCING REPORT: ROTATING

    COMPONENTS+10P X

    ME-13 RUNNING CLEARANCE REPORT +10P X

    ME-14 HYDROSTATIC TEST REPORT R X

    ME-15 TEST PROCEDURES R X

    ELECTRICAL 

    EL-01 ELECTRICAL EQUIPMENT DATA SHEETS

    Data sheets as contained in the specification completed by Supplier. X +4P X X

    EL-02 ONE LINE DIAGRAM

    Show the electrical distribution system, with branch circuits to the

    various consumers. Also show voltage level(s), nominal and short

    circuit rating of buses, main components, number of phases,

    neutral, PE bus, etc.

    +8P X

    EL-03 BLOCK DIAGRAM

    Show various installation units, with all interconnecting cabling.

    +6P X X

    EL-04 LOAD LIST

    Identify all electrical consumers and provide following data, as

    applicable: nameplate rating, power demand, power absorbed from

    mains, pf and efficiency at load conditions, simultaneity factor;

    under winter as well as summer conditions.

    +6P X X

    EL-05 CABLE LIST

    List all cables with identification number, operating voltage, type,

    number and size of conductors and installed length.

    +8P X X

    EL-06 DIMENSIONAL DRAWING, INCLUDING WEIGHT LIST

    Show overall dimensions, including free space required for

    ventilation, operation and for maintenance, location and size of

    cable entries or cable entry area, details of bus duct connection,

    hi i lit l ti f f d ti b lt t

    +6P X

  • 8/17/2019 Supplier Document Requirements SDR GDF

    11/14

    SUPPLIER DOCUMENT REQUIREMENTS (SDR) 

    DOCUMENTS SHOWN BELOW SHALL BE LISTED ON THE SUPPLIER DOCUMENT REGISTER (SDR CODE

    PJ-01). ABBREVIATIONS ARE SHOWN BELOW.

    Abbreviations Key: A-award (i.e. telefax, letter) P-Purchase Order placement, T-test, D-delivery, '-'-before, '+'-after,

     blank - no requirement, R-review by inspector. Example: +4A = four weeks after award, -2D = two weeks, before

    delivery.

    PURPOSE AND TIMING

    Data Book(Yes)SDR

    CODE

    SDR - CODE DESCRIPTION With

    Bid

    For

    ReviewIMO MDR

    EL-11 BATTERY ARRANGEMENT AND RACK/ENCLOSURE

    ASSEMBLY DRAWING - Show battery installation arrangement.

    Also show and identify make and type of battery cells or blocks,

    type and size of intercell connectors and terminal covers.

    +10P X

    EL-12 PARTS LIST – List all used components and materials, together

    with information regarding make and type.+6P X X

    EL-13 NAME PLATES DRAWING +6P X

    EL-14 ELECTRICAL EQUIPMENT SIZING CALCULATIONS +6P X

    EL-15 CHARACTERISTIC CURVES IF/AS SPECIFIED ELSEWHERE

    Refer to equipment specification or Purchase Order.+6P X

    INSTRUMENTATION 

    IN-01 INSTRUMENT LIST - Completed list according to provided

    example.X +6P X X

    IN-02 INSTRUMENT LOCATIONS AND CABLE LAYOUT

    Show location of instruments with tag numbers, routing and layout.+8P X

    IN-03 CAUSE AND EFFECT DIAGRAMS

    Show causes to system trips/shutdowns, resulting effects and

    actions.

    +6P X

    IN-04 LIST OF ALARM/TRIP SETTINGS

    List all instruments initiating an alarm and/or shutdown by tag

    number and show conditions where alarm or shutdown is required.

    +6P X

    IN-05 INSTRUMENT TERMINATION DRAWINGProvide full termination details.

    +6P X

    IN-06 INSTRUMENT HOOK-UP DETAILS

    Show principle and materials.+6P X

    IN-07 FUNCTIONAL LOGIC DIAGRAM +6P X

  • 8/17/2019 Supplier Document Requirements SDR GDF

    12/14

    SUPPLIER DOCUMENT REQUIREMENTS (SDR) 

    DOCUMENTS SHOWN BELOW SHALL BE LISTED ON THE SUPPLIER DOCUMENT REGISTER (SDR CODE

    PJ-01). ABBREVIATIONS ARE SHOWN BELOW.

    Abbreviations Key: A-award (i.e. telefax, letter) P-Purchase Order placement, T-test, D-delivery, '-'-before, '+'-after,

     blank - no requirement, R-review by inspector. Example: +4A = four weeks after award, -2D = two weeks, before

    delivery.

    PURPOSE AND TIMING

    Data Book(Yes)SDR

    CODE

    SDR - CODE DESCRIPTION With

    Bid

    For

    ReviewIMO MDR

    IN-14 CERTIFIED DIMENSIONAL DRAWINGS +10P X

    IN-15 CALIBRATION SHEET +10P

    IN-16SOFWARE DOCUMENTATION - Configuration, database,

    graphics, etc.+8P X

    IN-17 INSTRUMENT LOOP DIAGRAMS +8P X

    IN-18 NOT APPLICABLE - SEE IN-20

    IN-19 DIMENSIONAL DRAWING, INCLUDING WEIGHT LIST

    Show overall dimensions, including free space required for

    ventilation, operation and for maintenance, location and size ofcable entries or cable entry area, details of bus duct connection,

    shipping splits, location of foundation bolts, etc.

    +8P X X

    IN-20 WIRING DIAGRAM FOR ALL ACCESSORIES

    Show wiring/connections up to and including terminals for

    connection of external wiring or cabling.

    +8P X

    IN-21 PARTS LIST – Identify all materials, make, type, material and

    quantity

    +6P X

    IN-22 PAINTING/COATING PROCEDURE/REPORT +4A X

    IN-23 MATERIAL CERTIFICATES

    In accordance with NEN-EN-10204 3.1.+4A X

    IN-24 HYDROSTATIC TEST REPORT +2T X

    IN-25 TEST PROCEDURES +6A X

    IN-26 AUTHORITY/CODE REQUIREMENTS PRESSURE

    CONTAINING PARTS (ACCORDING TO PED DIRECTIVE)

    Documents, i.e. calculations, drawings, manufacturing/test

     procedures required to meet authority and/or code requirements.

    +4A X

    IN-27 EXPLOSION PROOF CERTIFICATE ACCORDING TO ATEX +4A X

    PROCESS

  • 8/17/2019 Supplier Document Requirements SDR GDF

    13/14

    SUPPLIER DOCUMENT REQUIREMENTS (SDR) 

    DOCUMENTS SHOWN BELOW SHALL BE LISTED ON THE SUPPLIER DOCUMENT REGISTER (SDR CODE

    PJ-01). ABBREVIATIONS ARE SHOWN BELOW.

    Abbreviations Key: A-award (i.e. telefax, letter) P-Purchase Order placement, T-test, D-delivery, '-'-before, '+'-after,

     blank - no requirement, R-review by inspector. Example: +4A = four weeks after award, -2D = two weeks, before

    delivery.

    PURPOSE AND TIMING

    Data Book(Yes)SDR

    CODE

    SDR - CODE DESCRIPTION With

    Bid

    For

    ReviewIMO MDR

    PI-03 AUTHORITY/CODE REQUIREMENTS PRESSURE

    CONTAINING PARTS

    Documents, i.e. calculations, drawings, manufacturing/test

     procedures required to meet authority and/or code requirements.

    +10P X

    PI-04 DESIGN CALCULATIONS PIPING COMPONENTS +10P X

    PI-05 PIPING NOZZLE LOADINGS +8P X

    PI-06 NAME/TAG PLATE LIST +10P X

    PI-07 CERTIFIED DIMENSIONAL DRAWINGS +8P X

  • 8/17/2019 Supplier Document Requirements SDR GDF

    14/14

     

    GDF Production Nederland B.V.

    Specification 103 Rev. 5. Page 14 of 14

    SUPPLIER DOCUMENT REGISTER (SDR CODE PJ-01) 

    SDR Code Document Description Document Number Rev. Number Issue Date according SDR Code