supplemental modeling and analysis report

82
Supplemental Modeling and Analysis Report Atlas Corporation Moab Mill, Moab, Utah February $1998 Prepared for the U.S. Fish and Wildlife Service Lincoln Plaza, Suite 404 Salt Lake City, Utah 84115 Prepared by Oak Ridge National Laboratory Environmental Technology Section 2597 B 314 Road Grand Junction, Colorado 81503

Upload: others

Post on 10-May-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Supplemental Modeling and Analysis Report

SupplementalModeling and AnalysisReport

Atlas Corporation Moab Mill, Moab, Utah

February $1998

Prepared for the U.S. Fish and Wildlife ServiceLincoln Plaza, Suite 404Salt Lake City, Utah 84115

Prepared by Oak Ridge National LaboratoryEnvironmental Technology Section2597 B 314 RoadGrand Junction, Colorado 81503

Page 2: Supplemental Modeling and Analysis Report

Table of Contents, .

1.0 Introduction . . a . . . . . . a 1 . a 1 I . . e a . e ~ . . I . 1 . D . . . . . J.

I.1 Project Scope . . . . 1 1 ~ . a a . a . a ~ s D . 1 . ~ 1 . j ~ ~ . ~ 1 . ~ . D 1

2.0 Groundwater and Contaminant Transport Modeling . D . . 3

3* -2.1 Modeling Constraints 1 . a . . e . a a e * * 0 . . *

2.2 Drainage Modeling ~ . a . . . . ~ . . ~ , . . . . . ~ . . 4. -

2.3 Contaminant Transport Simulations . . . . . * . . . .

2.3.1 Plume Simulations . . . . . . . . . . . . . . . . * . . . * . I

2.3.2 Source Removal Simulations . . . . . . . . . . . . . . .

3.0 Sensitivity Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . fi

4.0 Retardation of Contaminants . . . . . . . . . . . . . , . . . . . . . 15

6* -

4D -

11

5.0 Trend Analysis of Groundwater Contamination Data . . . 16

6.0 River Fluctuations on Contaminant Discharge Rates . . . 20

ir?7.0 Review of Historical Water Level Data . . _ . . , . . . . . . . 2,. ,jl, ,. __.i_ ,^ ,_:

1: 1 8.0 Impact of Moving Tailings . . . . . . . . .“. . . . . . . . . . . . . 23

9.0 Ccnclusions ~ . . , D . ~ . ~ . . ~ . . . . . . . . . . . . . . . . 1 . . . . 3

10.0 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95. . 5

Appendix A: Statistical Analysis of Historical Water Quality Data

Appendix B: Historical Water Level Data

Page 3: Supplemental Modeling and Analysis Report

-- ,_ _i ‘. .- .,a. . 7 a,,:, . ,,Y.,>. ., 1

1 .O Introdutitibn

Rm

1:; 1 The purpose of this report is to provide additional numerical modeling ano data evaluation for the

r,Atlas tailings pile near Moab, Utah. A previous report (Tailings Pile Seepage Model: The Atlas

1 Corporation Moab Mill, Moab, Utah, January 9, 1998) prepared for the Nuclear Regulatory

Commission (NRC) by Oak Ridge National Laboratory/Grand Junction (ORNL/GJ) presented the

results of steady-state modeling of water flow and subsequent discharge to the underlying

groundwater system. At the request of the Fish and Wildlife Service (FWS), this model was.)

expanded to evaluate the impact of drainage from the tailings pile in addition to recharge from

precipitation in a transient mode simulation. In addition, the FWS requested transient simulations

of contaminant transport in the alluvial aquifer. Subsequently, NRC requested an evaluation of

additional hydrologic issues related to the results presented in the Tailings Pile Seepage Model

(ORNL/GJ 1998a) and the Limited Groundwater Investigation (ORNL/GJ 1998b). Funding for

the report was provided by the U.S. Department of Energy. The following section lists the

individual tasks with subsequent sections providing the results. A map for the Atlas Moab Millr?i ! site is presented in Fig. 1.1.

ri / I.% Project Scope

The scope of this report was based on requests by‘the FWS and’NRC during a January 13

conference call with ORNL/GJ. Listed below are the individual tasks that are addressed in this.‘ ;, _-,,, ,^ ._. .., I. L 3 ‘. : “.,l~ _ ,., 1, _report.

FWS REOUESTED TASKS

l Task FWS-1: Transient simulations of pile drainage.

l Task FWS-2: Transient simulations of the contaminant concentrations discharging from

the pile.

0 Task FWS-3: Impact of tailings pile removal on contaminant flux discharging to the

alluvial aquifer and the Colorado River.

Supplemental Modeling and Analysis Report 1

Page 4: Supplemental Modeling and Analysis Report

._

3’ I ,.’ ;,

., ,,,_ -’ ‘. ‘. / ‘” “, ._

Page 5: Supplemental Modeling and Analysis Report

a’+ai&&;i: ~e~;iti.t~-~;al;sis of& hydrol~gi:gic pa;g;net;rs;used i& ahe model.

f7 .Task NRC3;%Impacts of retardation on contaminant migration in the alluvial

1 groundwater.

a Task NRC-3: Transient effects of river stage fluctuation.“I ,. _. I ;. I _.0 Task NRC-4: Review of historical water level and water quality data and the subsequent

I-i, ;i :

impact on seepage rates from the tailings pile.

‘a Task NRC-5: Impact of construction activities during tailings pile removal on

contaminant discharge to the groundwater.

Each of these tasks are addressed but at varying levels of detail. The bulk of this report discusses

the results of transient numerical modeling for the drainage of the tailings pore water and

contaminant transport simulations. Because’of time and budget limitations, several of the tasks

are addressed only in limited detail. In particular, ORNUGJ acknowledges that the sensitivity

analysis task (Task NRC- 1) has not been adequately addressed.

rt:

2.0 Groundwater and Contaminant Transport Modeling

Ail”

2.1 Modeling Constraints

The,information presented in this and the previous reports (ORNL,/GJ 1998a, b) is preliminary‘ ,, ‘%“‘. -’and is intended- to provide an order of magnitude estimate of the geochemical and hydrologic

processes at the site. Further work, particularly regarding sensitivity analysis of the model and

impacts of contaminant retardation as well as heterogeneities in the tailings pile, variable

saturation of the pile, and transient river effects is needed to improve the reliability of the model

predictions.

Supplemental Modeling and Analysis Report 3

Page 6: Supplemental Modeling and Analysis Report

c

. . ’

2.2 Drainage Modeling

The existing two-dimensional model (Fig. 2.1) used in’ the previous simulations (OR.NL/GJ

(”I+

1998a) was modified for the pile drainage simulations (Task FWS-1). Based on recent and-.“?._*_ Jo ,._ ,_historic soil borings drilled through the pile, very fine-grain slimes located at the base of the pile

were included in the simulation. It was assumed that the slimes cover the entire bottom of the

tailings pile. Boring logs indicate that there are areas where the slimes are absent but there is

Fii .,

insufficient data to construct a reliable map of their extent and thickness. The same permeabilityI,and unsaturated hydraulic characteristics (0.0003 ft/d [IO-’ cm/s]) used for the clay cover were

used to represent the slimes. It should be noted that the tailings material above the slimes is

mostly fine to very fine-grained sand.p*

ti

t;

Boundary conditions consisted of mixed conditions of constant head or flux boundaries. Thet?I; lateral boundaries consisted of constant head values for the alluvial acluifer immediately“_ I. ,. ,,I,, ,. _

upgradient of the tailings pile and the river elevation downgradient of the pile. The lateral

Fi boundaries above the water table were set as “no flux” boundaries. Head values were based onF- , . /water-level measurements from monitoring wells or surveyed river elevations taken during

1c:1 J December 1997. The lower boundary, which was’also set as a “no flux’ boundary, may not be% , .

Ecompletely accurate considering the evidence of vertical flow from the underlying salt formations

,_,.4 ,

,; as i;ldic;t;d by the eibv;ted .~~oride’~oncentrations y-wng;;i;;& &ie pile ((L&.&

1998b). Nevertheless, any vertical flow should have little impact on transport calculations through

the cover and pile. The upper boundary was set as a ‘fixed f&x value that corresponds to the

estimated yearly infiltration rate which was estimated to be 0.0002 ft/yr based on a fixed

percentage of the average yearly rainfall of 8 in/yr (Blanchard, 1990). This recharge rate,

cc: Iresulting from precipitation, is an estimate and is subject to a range of interpretations.

Initial conditions consisted of saturated moisture contents for the tailings material based on the

assumption that the slimes and tailingswere saturated when placed in the impoundment.

Simulations were run in the transient mode with small incremental time steps that increase based

on the convergence criteria. Moisture content and vertical flux values for water discharging

through the pile were recorded during the simulations.

m Supplemental Modeling and Analysis Report 4

I‘

Page 7: Supplemental Modeling and Analysis Report
Page 8: Supplemental Modeling and Analysis Report

Figures 2.2 and 2.3 show the vertical flux and saturation as a function of time for the center of the

fine-grain sand tailings and at the base of the slimes immediately above the alluvial aquifer. The

graphs show that the bulk of the pile drainage occurs within the first 100 years. Steady-state

conditions, defined as the point in time where the flux at the base of the pile matches the recharge

rate, occur after 238 years. The relatively flat nature of the curves (Figs. 2.2 and 2.3) between

100 and 238 years represents continued drainage of bore water in the tailings and slimes but at a

rate of approximately 5 percent of the recharge flux fi-om precipitation.

6” .

s

.

“./ :t,

F?

SDll

eC”

PT”

2.3 Contaminant Transport Simulations

Two separate contaminant transport simulations were conducted for this investigation. The first

simulation (Section 2.3.1) consisted of the transport of contaminants from the pile into the

alluvial aquifer for a period of 41 years (Task FWS-2). Forty-one years represents the available

time for transport since the initial placement of tailings in the impoundment in 1956. The second

simulation (Section 2.3.2) assumed that the sources of contamination, the tailings pile and all

other potential sources, were removed (Task FWS-3). This simulation predicts the time required

for contaminant levels in the aquifer to return to pre-1956 levels.

For all simulations performed, contaminant concentrations were normalized to the average

oontaminant concentrations in the tailings pile pore water. It was assumed that the contan&ants

were conservative, therefore, Kd values were set to zero: Based on published values (Freeze and

Cherry 1979) of the coefficients of dispersivity for a sand aquifer, the longitudinal dispersivity was

set at 0.5 ft”/d and the transverse dispersivity was set at 0.05 fi2/d. Future sensitivity analyses

should be conducted to evaluate the importance of these parameters on the contaminant transport

simuiations.

2.3.1 Plume Simulations.; :. ;_.

Initial groundwater flow conditions consisted of a saturated tailings pile at a normalized

contaminant concentration of 1 .O. Contaminant concentrations in the underlying alluvium were

Supphnental Modeling and Analysis Report 6

_ ,

Page 9: Supplemental Modeling and Analysis Report

-L :

i : DISCHARGE vs. TIMEv i‘0.0020 -l--

l-9t :

b”nb 0 . 0 0 1 6 -t !

0 . 0 0 0 8 -

0 . 0 0 0 4 -

- l - l * Center of tailings- - - - Base of slimes

i 1i :i 1\i 1.

0.0000F i 0 2 5 5 0 7 5 1 0 0 1 2 5 1 5 0 1 7 5 2 0 0 2 2 5 2 5 0*L # ~\“t.lkl,L\~l~*lg~\mrc145.dwg

Time, years

Figure 2.2. Flux rates in the tailings pile during desaturation.. _.,

\/

Page 10: Supplemental Modeling and Analysis Report

.:

L-Y: I SA TURA T/ON VS. TIMEf > 1.0. , \

I

iiiiii

- - - - Base of slimes-.-.- Center of tailings

‘\‘\

‘\‘\ -w --.a. -.-.-.-.l.-.-.-.-.~.~.~.

0 . 5 -j- I0 2 5 50 7 5 1 0 0 1 2 5 1 5 0 1 7 5 2&O 2 2 5 2 5 C

hlusr\klrk\mscdwgf\msc2~.dwg

p”, T I M E , Y E A R S ,i !a,

Figure 2.3. Moisture contents (6s) changes with timein tkiiings pile ri&ed.“bn ntini~ri~al tktidelirig simulation.

Page 11: Supplemental Modeling and Analysis Report

F”

1‘ ;

b 1

f””

i..

r

”L j

m

i

” :

Fa

: ’?

set to zero.‘. ‘,,

Figure 2.4 illustrates the contaminant plume in the alluvial aquifer after 41 years. The simulations

predict a mature plume that reached the river several years prior to the end of the 41-year

simulation period. This is consistent with contaminant plume maps based on water sample results

presented in the 0RNIJG.I groundwater report (ORNIJGJ 1998b).

The model predicts that the contaminants emanating from the tailings pile are diluted by 60

percent by the groundwater. Although the 60 percent dilution rate is consistent with mixing

simulations for ammonia, the extent of retardation by aquifer sediments and the extent of

oxidation of ammonia to nitrate is unknown, therefore, reducing the reliability of the ammonia

simulation. In a similar fashion, sulfate simulations are questionable because the solubility limits of

several of its salts are probably exceeded. The mixing simulations are, perhaps, best served by the

uranium data due to the conservative nature of the uranyl carbonate ion in this geochemical

environment. For uranium mixing calculations, however, a 60 percent dilution results in a

reduction of the tailings pore water concentration of 23.5 mg/l to 9.4 mg/l in the alluvial

groundwater downgradient of the pile. The actual average uranium concentration in the alluvial

groundwater is 4.62 mg/l--approximately one-half the amount predicted by the model. Thus,

these results suggest that the initial input of contaminated water is high by a factor of two during

the first 30 years of the simulation. Most likely, the initial condition of total saturation is not

correct and a lower saturation value should be used for future simulations. Using a lower

saturation value will permit a more accurate simulation of the concentrations that are now being

measured. Relative concentrations, as described in the next two paragraphs, are also affected by

the choice of initial saturation conditions. The relative concentrations predicted later

are probably too high but still within a factor of 2 or 3 of the actual values._- - ,./

A simulation was conducted to evaluate the long-term contaminant concentrations near the river

based on the assumption that the tailings pile is not removed. Figure 2.5 shows the normalized

contaminant concentrations at a node in the center of the groundwater contaminant plume/. , ,. ,v.- _ .,a, ./. ..,‘ /.A,^ ,.r_ ,I :. ,L%%.-r . j.l”., ,i (_ ‘._ ,, >- ,,.. I . . . . . . . ., .(“.&1 _.,,I) .,~ri,,r,<l--‘ .,ii”,*“r;.adjacent to the Colorado River. This node is only one foot thick. Actual contaminant

concentrations as measured in a monitoring well would be lower because the well is screened over

Supplemental Modeling and Analysis Report 9

Page 12: Supplemental Modeling and Analysis Report

51laA!y

-0pelo~o~

rk ,

Page 13: Supplemental Modeling and Analysis Report

NORMALIZED CONTAMINANT CONCENTRATION

P P P P 00

P P Pd N W P In 0, ;iPm

000”0

‘I0Itt

‘:I

Page 14: Supplemental Modeling and Analysis Report

several nodes that exhibit Power contaminant concentrations.

The model simulation predicts that after 50 years, the decline in the contribution of contaminants

due to the drainage of tailings pore water begins to impact concentrations at the river (see Figs.P,_

2.2 and 2.3). Because 41 years have passed’ since the tailings were first placed in the

impoundment, these results suggest that contaminant concentrations at the river will continue to

increase for 9 more years. The simulation further suggests that the peak of the contamination is

located near the downgradient edge of the tailings pile. This result is consistent with the trend

analysis conducted in Section 5.0 that indicates that there is no discernable trend in contaminant

concentrations.

2.3.2 Source Removal Simulations

The source removal simulation assumed that after 5 1 years of contaminant release from the

tailings pile and subsequent transport by the alluvial aquifer, the source of contamination was

I!7B ;

completely removed by remedial actions. after 41 years of contaminant transport, an additional

10 years of continuous input of contaminants was simulated based on the assumption that tailings

removal will require approximately 10 years to complete. During these 10 years, contaminant flux

rates were consistent tith existing rates under the no source removal scenario.

-Figures 2.6 through 2.8 show the extent of the plume at 10, 16 and 27 years afier source removal.

After 35 years, the model predicts that contaminant concentrations near the river will be less than

10 percent of what was present in the initial tailings pile pore water. Results of the simulations

are consistent with average linear groundwater flow velocities for the alluvial aquifer as reported

previously (ORNL/GJ 1998a). Finally, using an average linear velocity of 107 ft/yr (ORNUGJ

l998a) and approximately 3800 feet of travel distance, 3 5.5 years would be required to clean the

aquifer. This value, however, is unrealistic because this simulation does not consider the effect of

E molecular diffusion of contaminants from permeable zones into adjacent low permeable zones,_.and subsequent diffusion back to permeable zones as the concentration gradient reverses. The

net result of these factors is that there will be an increased amount of time before the aquifer

?--I

i /

Supplemental Modeling and Analysis Report 12

Page 15: Supplemental Modeling and Analysis Report

years after source is removed

e- --s.- J

--._ L 3 ““‘3

Inactive Zone

Vertical Exaggeration = 10xGrid spacing: X=100 ft, Y=lft 0.20 Relative Concentration

m 0.60 Relative Contamination

Fig. 2.6. Extent of groundwater contaminant plume 10 yearsafter source removal.

Page 16: Supplemental Modeling and Analysis Report

,I..

, , _ i * , (I _,Ck ,I_

Xg:0,r IIII *

Page 17: Supplemental Modeling and Analysis Report

27 years after source is removed

-w-I. 1

-or?91. . .‘3

v---w“3

Inactive Zone

Vertical Exaggeration = 10xGrid spacing: X=100 ft, Y=lft

0.20 Relative Concentration

Fig. 2.8. Extent of groundwater contaminant plume 27 yearsafter source removal.

Page 18: Supplemental Modeling and Analysis Report

rI :. /

completely cleans itself Results from other tailings pile removal projects should be evaluated to

improve the estimate for cleaning the aquifer.

3.0 Sensitivity Analysis

The purpose of a sensitivity analysis is to quantify the uncertainty in the calibrated model caused

by uncertainties in the estimate of aquifer parameters, initial conditions, boundary conditions, and

contaminant concentrations (Task NRC-l). A sensitivity analysis is an essential step in all

modeling applications. During a sensitivity analysis, values for hydraulic conductivity, storage,

recharge, and boundary conditions are systematically changed within previously established

plausible ranges. The magnitude of changes in head and contaminant concentrations from the

calibrated solution is a measure of the sensitivity to that particular parameter.

Because of the limited time frame available to conduct this modeling of the Atlas site, it was not

Fi , possible to conduct a sensitivity analysis. ORNL/Gi recommends that future Work be performed

to complete this task. If this recommendation is followed, the most important hydraulic

parameters will be identified. Additional field Work Can then be pro@sed to better define the most

important parameters.

L 4.0 Retardation of Contaminants

,Pl“ r ’i

No specific studies have been performed to address retardation of contaminants (Task NRC-2).

However, in general, the oxidized, sandy, gravelly, highly alkaline nature of the alluvial aquifer- ”

will promote migration of the contaminants, particularly those found as anions: uranium,

molybdenum, sulfate, and nitrate. Ammonium is a special case because it is apparently being

F:

converted to nitrate due to the oxidizing nature of the alluvial system. In addition, sulfate species

may be near their solubility limits. The discussion below, therefore, focuses on uranium because

its geochemistry in this type of environment is well understood. Because of their similar behavior,

this discussion can also be applied, in a general way, to molybdenum..(, : .(_ ” ,

Supplemental Modeling and Analysis Report 16

Page 19: Supplemental Modeling and Analysis Report

gaI

The distribution of uranium species is highly dependent on the carbonate concentration. The third

graph in Fig. 4.1 (Waite and Payne 1993) is probably not too dissimilar from what might be

expected for the groundwater at the Atlas site. Thus, ‘[UOi(CO 3) J2- and UO,CO, may be

important species. However, the speciation is so dependent on the partial pressure of carbon_“” ‘. ,._,’ ‘, j ‘;_ .’ “l.i., I ““.; ~.‘,,_. :;. _. ,‘I, ,” ‘.,‘,. :dioxide that it is difficult to generalize. For example, Duff and Amrhein (11996) state that “in the

m/

I /presence of dissolved carbonates, U(W) forms several strong carbonate complexes: @JO,),

C03(OH)3-, UO2CO3, UO2(CO3)2 2-, UO2(CO3),4-.” Nevertheless, it is concluded that uranium in

F”:I 1

the alluvial aquifer will be in the form of one of several negatively-charged carbonate species.

As can be inferred by the previous discussion, adsorption decreases with decreasing pH and

increasing alkalinity. The reason for this effect is that formation of the dicarbonate species is

increasingly favored and bicarbonate ion competes for available adsorption sites (van Geen et al.

1994). Soil and mineral surfaces are general&negatively-charged. Thus, the negatively-charged

or neutral carbonate species have little propensity to sorb on the soil minerals,?-i

This conclusion is supported by Duff and Amrhein (1996) who concluded that “with increasing

carbonate alkalinity, U(VI) most likely formed negatively charged carbonate complexes which did

not strongly adsorb to the soil or goethite in the study. Therefore, U(VI) adsorption to soils

dominated by permanently charged clays is not a likely factor controlling U(VI) solubility . . . ”

”L if :

To summarize, conditions at the Atlas site appear to be favorable to the formation of carbonate

complexes of U(VI). Such complexes are not strongly adsorbed by soil materials and are,

therefore, relatively mobile in the environment. Extensive sampling and analysis regarding

uranium speciation and’ the effects of other ions would be needed to apply a geochemical model

that would more accurately simulate uranium mobility.

p5.0 Trend Analysis of Groundwater Contamination Data

NRC requested that historical water quality data be reviewed and that a trend analysis be provided

(Task NRC-4). Several wells at the site have been sampled and analyzed on a regular basis since

1987. The objective of the statistidal analysis presented i‘n this se&ion is to detect changes or

Supplemental Modeling and Analysis Report 17

Page 20: Supplemental Modeling and Analysis Report

i

gm

i,b. ,

00

80

t

70

60

w so

g40

20

10

PH h:\atlag\corelm~~ndp.cdr

Figure 4,f. Speciatim of lU%d V(W) as a Rmction of pIi. a) in theabsence of carbonate, b) in equilibrium with the atmosphere(fC0~ = 10-‘.’ atm), c) in soIutions containing 2 mM totalcarbonate. porn waite CNW m, ~~93)

Page 21: Supplemental Modeling and Analysis Report

trends in contaminant levels. For the groundwater chemistry data collected, the nonparametric

ati ,

Mann-Kendall test for trend analysis was conducted. This procedure is particularly use&l because

missing values are allowed and the data need not conform to any particular distribution. Also,

Fi1,

data reported as trace or less than the detection limit can be used by assigning them a common

value that is smaller than the smallest measured value in the data sets (Gilbert, I987). Tests were

!-- conducted with the null hypothesis being no trend in the data. The null hypothesis is rejected ift;, ..( ;.. I, , I~ I , :

the probabrhty value (p) &respondingto the &mputed ‘ha&Kendall statistic (s) is less than a

specified significance level. For the Atlas site, both 90 and 95 percent confidence levels were

selected to evaluate the data. The use of a 90 percent confidence interval reflects the high

variability inherent in environmental data and is intended to provide an indication of trends but at

a lower confidence interval.

If the p value is less than 0.05 or 0. I, then the evidence is insufficient to reject the null hypothesis

that there is no trend in, the data. Mann-Kendall- tests were conducted on selected analytes from a

total of 4 wells located downgradient of the tailing pile (Fig. 5.1). Results are presented in Table

5.1. The statistical and analytical data are presented in Appendix A. Of the eight analytes tested,

four yielded a trend that was within the 90 percent confidence interval. Of these four, two

showed downward or decreasing concentrations while two showed an upward trend. The

remaining four analytes showed no trend within a 90 percent confidence interval. For

concentrations that exhibited a trend within the 95 percent confidence interval, two wells showed

”rb

a downward trend and one well showed an upward trend.

pL

The Mann-Kendall test on uranium data from well ATP-2-S showed no trend within the 90

percent confidence interval. However, the characteristics of the data for this well show a repeated

increase and decrease in concentration values.which results in an uncertainty in the statistical

analysis. Time was not available to conduct further statistical tests, but it is recommended that

the Seasonal Kendall test be conducted on this data set. Using this analysis, the cyclic trend can

be removed and it is expected that a statistically significant downward trend in uranium

concentrations for ATP-2-S will emerge.

Although there is some indication of a downward trend for a few analytes, the data taken as a

Supplemental Modeling and Analysis Report 19

Page 22: Supplemental Modeling and Analysis Report
Page 23: Supplemental Modeling and Analysis Report

., .,

.*, <.. .,‘whole inaicat‘ed’no‘reliable trend &I concenti-aiions. ‘Thus, there is not c&&tent evidence for a

ptrend, in the groundwater contaminant concentrations downgradient of the pile.

bi ,“. ., / ;:- ,

Table 5.1 Statistical analysis of water quality trends based on groundwater samples from

downgradient wells

Well Analyte P-Value Trend

ATP-2-S 1

v- L

Consequently, there is no strong evidence that contaminant lev& in ihe groundwater arer”:i :

decreasing due to a decrease in the contaminant concentrations in the tailings pile or because of

reduced discharge rates. Additional evaluation of geochemical factors is needed to provide ar ,.‘ _.1 comprehensive understanding of ihe obs&%d co;ltaminant-conceati~~s downgradi&nt bf the

tailings pile. Such an evaluation would include calculation of the solubility limits of selectedri analytes within the tailings pore water and measurement of geochemical factors that affect the

i”ik i

migration of the contaminants.

p6.0 River Fluctuations on Contaminant Discharge Rates,. . .,,_ ^.

FThe,N$C requested an evaluation of how fluctuating river stages affect groundwater discharge of

contatina&‘i&o the ‘Colorado ‘five; (Task &C-j). Specifically, as the Colorado &ver stage

I? rises during spring runoff, how are contaminant flux rates fi-om the alluvial groundwater to theh ; river affected? Although’ there was in$uffici&t time to &lly anal$ze ttie isstie;.ther&” ares reaso’tisrrr(r AEl

why the contaminant flux values presented in the OIXNUGJ groundwater report (OlWL/GJ

P1, !i i

Supplemental Modeling and Analysis Report 21 ’

Page 24: Supplemental Modeling and Analysis Report

1998b) are a reasonable estimate of a yearly average. H’irst, the hydraulic gradient across the

Atlas site reflects average boundary conditions for the aquifer. For example, Canonie (1994)

reported a hydraulic gradient across the Atlas site of 0.004. A potentiometric map based on water

level measurements taken by ORNL/GJ in December I997 also yielded a hydraulic gradient of

0.004 (ORNLIGJ 1998b). Second, a review of stream gage records for the nearest W.S.G.S.

station at Cisco, Utah shows the daily discharge values since 1922 (Fig. 6-la). Figure 6-lb shows

recentwater”levels for January of this’year. At the time of the ORNL/GJ field effort(December

1997), the Colorado river was discharging approximately 5000 cfs. If this discharge value is-, _ .I-_ ., ,. \, .,

compared with the historical flow, there are brief periods (two or three months) of peak now that

exceed that discharge rate, but the bulk of historical river discharge values are below 5000 cfs.,. “. ., ,, _ ,_ ._‘. ._For peak discharge rates associated with spring runoff, groundwater discharge rates will decrease

in response to the higher river levels. This decrease in groundwater discharge rates during late

spring and early fall is offset by higher groundwater discharges in the late fall and winter in

response to lower river levels. Consequently, the contaminant discharge values based on

December1997 hydrologic data are a reasonable estimate of an average yearly value.

A more definitive approach to address this question would be to vary the downstream constant

head boundary of the contaminant transport model to represent on-site river stage data. Then the

model could be used to calculate the resulting time dependent contaminant flux rates. Time and

budget were not available to perform this task!Nevertheless, as de&bed‘ al&$ there would

probably not be a substantial change regarding the present description of the contaminants in the

alluvial aquifer.

Pp.;

7.0 Review of Hist.cyical Water ,@I@ Data.

$7 ,,c 1 NRC requested that the historical water level data from the Atlas monitoring wells be reviewed0 with respect to the tailings pile dewatering program that began in mid-1990. In particular, the

&“1P ’ impact on water levels in the tailings pile and the implications to seepage rate estimates was to be1

addressed (Task NRC-4). Water-level data reviewed for this evaluations were obtained from the

Canonie report (1994) and are presented in Appendix B. Interim water level data collected by

Supplemental Modeling and Analysis Report 22.

Page 25: Supplemental Modeling and Analysis Report

Colorado River Nmr Cisco, UtStrtlm Nuwbcr: llY1811500

199a

PROVISIONAL DATA SUBJECT TO REVlSiON

15 16 l? l(1 1s 20 21 22

updatd: 91 l 2rn1998 99:r5 bawd on ?Oyeareofrndrd.

h:\dasiskam.cdr

Figure 6.1. (a) Flow records since 1922 for the Colorado River at Cisco, UT and’ (b) recent flow records.

Page 26: Supplemental Modeling and Analysis Report

Atlas since the Canon& report were not available to be in&&d in the following discussion..

Graphs B- 1 through B-4 in Appendix B compare individual alluvial wells located downgradient of

the tailings pile with river stage elevations from 1989 to 1994. Fluctuations in monitoring well

water levels correspond to river stage.fluctuations’indicating that there is hydraulic connection

between the river and the alluvial aquifer downgradient of the tailings pile.

!-ic

rI

Graph B-5 in Appendix B shows a comparison of the water elevation in the pond at the top of the

tailings pile to the river stage from 1989 to 1994. As expected, there is no discernable correlation

between the two, indicating no hydraulic connection.

r Graph B-6 in Appendix B compares water levels in wells drilled into the tailings pile with riverI

stage levels. There is a large variation in water levels among these wells. A source of the

k”: variation be that the wells are completed in different lithologic units. Review of the well

completion information presented in the Canonie report (1994) and the Dames & Moore reports

F (1973 and 1981) provided the data presented in Table 2. As shown in Table 2, the wells

represented in Graph B-6, are completed within the alluvium, the sand tailings, and the slimes./!7k! Water level data in Table 2 is from January 1989, June 1990, and February 1994 and were used to, . /.

I”calculate the change is head values before and after the dewatering program began. The largest

k I! / decline in water level is observed in well B-4 and is representative of conditions before the

mc >b :

dewatering program began. Although this‘well shows no influence from the river (Graph B-5 in

Appendix B), it yields the greatest decline in water levels. However, there is no obvious

i-e ic (I

explanation for this decline based on the available data. Comparing water levels in wells A-9 and

BAA-4 shows a higher water level in well Bti4, which is underlain by slimes, compared with

A-9 that is screened in both the sand and alluvium. This difference in water levels may be due to,_” .,’

the low permeable slimes acting as an aquitard resulting in perched water in the vicinity of well

BAA-4.

,.As shown in Table 2, there is a larger average decline in water levels for the 17 months prior to

the initiation of the dewatering program than for the 42 months after pumping began. This

evidence indicates that the pumping is having little or no effect on the dewatering of the tailings

Supplemental Modeling and Analysis Report 24

Page 27: Supplemental Modeling and Analysis Report

Table 2. Well completion, lithology, and water level data for wells located on the Atlas Tailings Pile

Well Surfacenumber elevation

B-4 4,040

BAA-4 4,052.3

Screen TotalI I

Lithology Waterinterval, depth? elevation,

R I f-t 1 l/14/89I I

70 to 80 110I I

Alluvial well, no 4,035indication of slimes

39.2 to 41.2 ? Based on B-15 logSand tailings well,no slimes

4,020

29 to 49 50 Sand tailings, 3,978alluvial well, noindication of slimes

80 to 82 119I I

Completed well in 3,973slime tailings

51.7 to 53.7 N/A Based on B-l 4,015Screened in sandtailings with 5 A ofslime below I

Water Elevation Water Elevationelevation, difference, elevation, difference,6/l l/90 l/89 t o 6/90 2/25/94 6/90 to 2/91

4,024 1 -11 1 4,022 1 -2

3,976 -2 3,973 -3

All data compiled from Canonie report (1994) and Dames & Moore reports (1973 and 198 1).

I1

,

‘, 1

:

‘_

Supplemental Modeling and Analysis Repot-t 25

Page 28: Supplemental Modeling and Analysis Report

jq .

b 4

mb !

t

.__. .<.

pile. It appears that ‘natural drainage @ior to pumping sad&d the larger water-level decline.

Canonie (1994) reported that the remedial wells pump at a combined total of approximately 3

gpm when averaged over the period from July 1990 to’1Febiuar-y 1994. Assuming that the pores

drained to the residual moisture content.of 0.63 (ORNL/GJ 1998a) and that all of the decline in._ I . ._ _ ;. _.

water levels is due solely to pumping, the resulting drop in water levels in the tailings pile in .-

response to pumping would be 0.73 ft over this 42-month period or 0.21 fi per year.

If it is assumed that water level declines in monitoring wells completed in the sand tailings are due

to the discharge of water into the underlying aquifer, then it is possible to estimate the recent

P discharge of tailings pore water. This estimate of discharge would be in addition to dischargeE:

p5P‘

occurring in response to infiltration due to precipitation. For this evaluation, recharge rates in

response to water level declines were estimated before and afler dewatering began. Wells EE-4

BAA-4, both completed in the sand tailings, exhibited water level declines. From 1989 to 1990,mi: p water levels declined three and five feet, respectively. Multiplying these water level declines byi ,

the surface area of the pile (3868103 R2), the porosity of the sand tailings (0.66)[ORNL/GJ

1998a], the drainable portion of the porosity as predicted by the numerical simulation

(O.l6)[ORNL/GJ 1998a], and dividing by the time required for the water level decline (17 mo.), af”It:I- I discharge rate of 12 to 20 gpm results. If water level declines from 1990 are used, and the

ri._ r

drainable portion of the porosity is adjusted to 0.23 to reflect the increased drainage time, then the

recharge rate due to drainage of the tailings pore water ranges from 2.5 to 5.0 gpm. This

f-7i

recharge rate is comparable to the value (6.7 gpm) predicted using the uranium mixing calculation

f-Yft I

8.0 Impact of Moving Tailings

NRC expressed the concern that excavation of the tailings pile could result in a “pulse” of

contaminated water entering the groundwater system (Task NRC-5). The additional source of

the water, according to the NRC, that could cause this pulse was attributed to dust suppression/

control measures used during tailings pile excavation activities. To address this concern,

ORNLIGJ discussed the dust suppression/control measures used by the DOE with Don Metzler, a

hydrologist with the DOE in Grand Junction. According to Mr. Metzler, the volume of water

typically used for dust suppression during tailings pile excavation above the water table would

F; i

Supplemental Modeling and Analysis Report 26

Page 29: Supplemental Modeling and Analysis Report

I

rt- :

not result in a “pulse” of’contamination to the groundwater system if proper management of

construction/excavation activities is provided. Water added for dust suppression during”excavation would only penetrate a few centimeters into the tailings and evaporation losses would

be significant. Further, low velocities associated with unsaturated transport would be insufficient:

to move the moisture to any significant depth before the tailings were excavated. however, for

excavation activities below the water table, DOE has found that dissolution of contaminants may

be increased by the remedial action (D. Metzler, U. S. DOE Grand Junction Office - personal

communication with F. Gardner, 2/3/98).

9.0 Conclusions

n Results of the modeling simulations have resulted in estimates of the time for the pore water in the

r!t (: ;

tailings pile to drain and for the amount of time needed for the groundwater system to clean up

after total source removal. In addition, several issues raised by the FWS and NRC were

addressed. Listed below are the individual conclusions from the modeling and data analysis.

a Model simulations indicate that the bulk of the pore water in the tailings drains after 100

years with 238 years required to reach steady state conditions

l The model predicts that the contaminant plume entering the river is mature-- a finding

consistent with site characterization data.

0 Simulations predict that the peak contaminant concentration reaches the river 50 years”after emplacement of the tailings (9 years from the present) and then declines to a steady

rate after approximately 100 years.

0 Source removal simulations indicate that it would require a minimum of 35 years for the

aquifer to clean up to pre-1956 levels.:

a Retardation of uranium and molybdenum in the alluvial aquifer is not believed to be

significant.

a Statistical trend analysis.of the downgradient water’quality indicates that there is no

consistent evidence for a trend in, the data. The contaminant transport modeling is, , . _..,consistent with this finding.

a River fluctuations are not believed to have a large impact on average contaminant* ., . . i . . .’

Supplemental Modeling and Analysis Report 27

Page 30: Supplemental Modeling and Analysis Report

discharge estimates presented in the initial ORNL’GJ groundwater investigation report

(ORNL/GJ 1998b).

Historical water levels indicate that the present dewatering system is having minimal

impact on the water balance in the tailings pile.

a Excavation and removal of tailings is not expected to adversely impact groundwater

I”

i 1( :quality.

Pp 4c 1

Based on the analysis presented in this and the previous ORNL/GJ reports, there is evidence

supporting a total discharge rate from 6.7 to 20 gpm (ORNL/GJ 1998 a, b). Uranium mixing

simulations and post dewatering water-level declines in the tailings pile support the lower

discharge rate. Ammonia mixing simulations and pre-dewatering water level declines in the

tailings pile support the higher discharge rate. Additional data and sensitivity analysis are needed

to better define the actual discharge rate ofwater from the tailings pile to the underlying

i*: groundwater system.!

F

g+

10.0 References

Blanchard, Paul %. 1990. Ground-Water Conditions in the Grand County Area, Utah, With Emphasis on

the Mill Creek-Spanish Valley Area. Technical Publication No. 100, S&e of Utah, Department of

Natural Resources. Prepared by the United States Geological Survey in cooperation with the Utah

r Department of Natural Resources Division of Water Rights.

i-; ’i , Canonie Environmental 1994. NRC Technical Information Request, Atlas Corporation Ground

Water Corrective Action Plan Uranium Mill Tailings Disposal Area. Moab, Utah.

Project 88-067. July 1994. Canonie’Environmental Services Corporation, Englewood,

pF/

Colorado.

Dames & Moore 1973. Supplement to Environmental Report, Moab, Utah Facility for Atlas

Aknerals. Job No. 5467-063-06. ’

Supplemental Modeling and Analysis Report 28

Page 31: Supplemental Modeling and Analysis Report

.,

rr Dames & Moore 198 1. Report of Engineer@ Design Stu& Additions to Tailings Pond -

cF. ,

embankment System. Moab, Utah for Atlas Minerals. Job No. 5467-O 1 S-06. February 15,

1978. New printing May 26, 198 1.

Duff, M. C., and C. Amrhein. 1996. Uranium(VI) adsorption on goethite and soil in carbonate

FI

bsolutions. Soil Science Society American Journal9 60: 13 93 - 1400.

ci

Freeze, R.A., and J. A. Cherry. 1979. Groundwater. Prentice-Hall, Englewood Cliffs,

New Jersey.P: Gilbert, R. 0. Statistical Methods for Environmental Pollution Monitoring. Van Nostrand

Reinhold, ISBN o-442-23050-8, New York.

ORNL/GJ 1998a. Tailings Pile Seepage Model of the Atlas Corporation Moab Mill, Moab, Utah.

Prepared for the U.S. Nuclear Regulatory Commission by Oak Ridge National

Laboratory, Environmental Technology Section, Grand Junction, Colorado. January 9,P

[. 1998.

cr ORNL/GJ 1998b. Limited Groundwater Investigation of the Atlas Corporation Moab Mill, Moab,

Utah. Prepared for the U.S. Fish and Wildlife Service by Oak Ridge National Laboratory,

Environmental Technology Section, Grand Junction, Colorado. January 9, 1998.

van Geen, A., A.P. Robertson, and J. 0. Leckie. 1994. Complexation of carbonate species at the

goethite surface: Implications for adsorption of metal ions in natural waters. Geochim.

C’osmochim. Acta, 58:2073-2086.

Waite, T. D., and T. E. Payne. 1993. Uranium transport in the sub-surface environment -

F-ii

Koongarra - A case study. InMetals in Groundwater, Allen, H. E., E. M. Perdue, and D.

S. Brown, eds., Lewis Publishers, Chelsea, Michigan.

p””

F

Supplemental Modeling and Analysis Report 29

Page 32: Supplemental Modeling and Analysis Report

APPENDIX A _

STATISTICAL ANALYSIS OF HISTORICAL WATER QUALITY DATA

Page 33: Supplemental Modeling and Analysis Report

_’

,;: ‘.

I, ,.. . , ,- ,, , . . 2 , I-

File: J:\FOX\GENSTAT\AMM2-NIT.CSV------------------------------------------------------------------

."^ ",_. :. ,., 5, .,I_ _, ."I, r ', ,.-A al. :, _' 'i ,I .<. : ,: _ ,, .c,l,J PROB. OF EXCEEDINGTHE ABSO~iJJTE VALUE

KENDALL OF THE Z STATISTICS Z (TWO-TAILED TEST)

STATION SEASON STATISTIC STATISTXC N IF N > 10

fy 1 1 97.00 1.4308i 34 . 153.

I7tr I

SEN SLOPECONFiDENi3E itiERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMIT

1 1 :050 010 -.667 -.180 :500 500 2.353 1.667100:200

000:ooo

. 500 1.429

. 500 1.136

Page 34: Supplemental Modeling and Analysis Report

m

: ii ,

Page 35: Supplemental Modeling and Analysis Report

30(

26C

2oc

p

8

'1 ,150.s80

1.00

60

0

Nitrate ConcentrationsMonitoring Well AMM-2

P-.--_-_.-i

L

-

S/1.1/87 12/23/88 s/7/90 "* 9/19/91 l/31/93

Dates Sampled

6115194 10128l95 .3

Page 36: Supplemental Modeling and Analysis Report

.

b-u

File: &\FOX\GEN‘kTAT~AMMiJA6.CSV

p------------------------------------------------------------------.,.

@ROB. O F EXCI&DING. d THE ABSOLUTE VALUE

KENDALL OF THE 2 STATISTIC-E s Z

STATION' SEASON STATISTIC STATfsTiC ‘N "(TWO-TAILED TEST)IF, .N," ; ,l‘o ._

F 1 1 1.35320 20 . 176L !v

F!I

SEN SLOPECONFIDENCE“INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMIT1 1 010

:050-.013 013

:013. 057

,000 050.lOO .ooo .013 :050.200 .ooo . 013 . 031

Page 37: Supplemental Modeling and Analysis Report
Page 38: Supplemental Modeling and Analysis Report

06/L&

L8/1118

Page 39: Supplemental Modeling and Analysis Report

sr*i ~I 1 .-i

File:. J:\kO%\btiNS~AT\hM2;kA8.C& ..km -------------------------------------------------- ----------m.-____t 'k ; PROB. OF EXCEEDING,. ., MANN- THE ABSOLUTE VALUE

KENDALL10 OF THE Z STATISTICIr.-; S Z (TWO-TAILED TEST)P "STATION ‘StiA&N's ,kkSTIC STATISTIC N IF N > 10

P 1 1 32.00 1.00825 20 -313f ; ."b :

SEN SLOPECONFItiENCE INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMIT1 1 010

:050-.040 038

:038150

-.027 :111.lOO -.019 .038 100. 200 -.009 . 038 :083

Page 40: Supplemental Modeling and Analysis Report

File:J:\FOX\GENSTAT\AMM2-PA8.CSVP&nted:12/31/97 Page: 1

Linear Regression

Minimum Maxinnlm Mean Median Std Dev Slope R-Sqr Num

0.00 3.75 2.52 2.65 0.82 0.13522 0.13 20

i

*.. . 1

Page 41: Supplemental Modeling and Analysis Report

-z

Page 42: Supplemental Modeling and Analysis Report

File: J:\FOX\GENSTAT\AMMZ-URA.CSV---------_----------------------------------------.-------------------

PROB. OF EXCEEDING

89* 8 KENDALL, s *

STATION SEASON STATISTICZ

STATISTIC N

THE ABSOLUTE VALUEOF THE Z STATISTIC(TWO-TAILED TEST)

IF N > 10*I!

1 1I 1 -4"o.oo -1.36919, .,, 19 / 1.71

SEN SLOPE'CONFIDENCE INTERVALS

m STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMIT)i 1 1 :050 010 -113.758 -42.308 60.468_

-95.044 -42.308 17.642P- 100 -89.691 -42.308' 7.143t, . :200 -74.644 -42.308 . 000

Page 43: Supplemental Modeling and Analysis Report

t-7, r

<I” 1 y-j ,-J ,” ‘“J : -yj ::: .“f - 11-3 1: :f *,I .) :I:1 ;‘“-‘j “-IT3 .?I- 3 Y”1

Printed:12/31/97File:J:\FOX\GENSTAT\AMkf2-DR?L.CSV

Page: 1

I Linear Regression IMinimum Maximum Mean Median Std Dev Slope R-Sqr Num

0.00 3900.00 2650.00 2700.00 813.86 0.58730 0.00 19

Page 44: Supplemental Modeling and Analysis Report

S6i8ZlO 1

L8/ L 118

Page 45: Supplemental Modeling and Analysis Report

tm.,’ i

.._ *

File: J:\FOX\GENSTAT\AMM3-MOL.CSV_--_-_-_-__-------------------------------------------------------

PROB. OF EXCEEDING-MANN THE ABSOLUTE VALUEKENDALL OF THE Z STATISTIC

mI S Z (TWO-TAILED TEST)f STATION SEASON STATISTIC STATISTIC N IF N > 10

f?t

1 1 15.00 .49040 19 . 624

T:SEN SLOPE

CONFIDENCE INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMITF4 . 1 1 010

:050-.015 003 028-.OlO :003 . 024

100 -.007 003 :018F :200 -.005 :003 . 014c1 ‘"4

e-5f 1k 3 . . , ,.’ _,_ ,. _. ,.

c;. ‘i&

‘.)_ ,I, ..,<* ,, ,” . . . . _ .‘

rt

Page 46: Supplemental Modeling and Analysis Report

n

.;.; _ .,, _” , ,, _. ,. _,,,,. ‘ ..” .,i. r. I

v-l

r

I”L. /

i i

PI

k~!,

-0-lrl-Wd.0-m&2.0

-WrJ.0

-

2.t-l

f:.T-l

-

.l-l

-z.0

Page 47: Supplemental Modeling and Analysis Report

i ’

I”) !f

?i

sll

3

S6/8ZIOl

P6lS LIQ

88/82/Z 1

L8/ 1118“! 0

0

Page 48: Supplemental Modeling and Analysis Report

mi iI 2

File: J:\FOX\GENSTAT\AMM3-RA8.CSVw _---____------^---------------------------------------------------

t:PROB. OF EXCEEDINGTHE ABSOLUTE VALUE

KENDALL OF THE Z STATISTICPb S Z (TWO-TAILED TEST)

STATION SEASON STATISTIC STATISTIC N IF N > 10

P 1 1 29.00 . 96605 19 . 324I /

,

SEN SLOPECONFIDENCE INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMIT1 1 010 -.035

:050 -.019039:039

.llO086

100 -.014 039 :082:200 -.002 :039 . 078

I-i i

Page 49: Supplemental Modeling and Analysis Report

8-4

i

m

i? !

r

Page 50: Supplemental Modeling and Analysis Report

0.5

0

RA228 ConcentrationsMonitoring Well AMM3

8/l 1187 12123188 517190 9119191 l/3 l/93 6/15/94 10128195 3/l l/97t

Dates Sampled

Page 51: Supplemental Modeling and Analysis Report

cci i

File: J:\FOX\GENSTAT\AMM3-URA.CSV:

_________________-_------------------------------------~------~~~-.--

F”I

PROB. OF EXCEEDING/ , THE ABSOLUTE'-VALUB

KENDALL OF THE Z STATISTICF S Zb (TWO-TAILED TEST)

STATION SEASON STATISTIC STATISTIC .N ". -'IF"‘N"> 10" "

E” 1 1 82.00 2.83902 19

i

SEN SLOPECONFIDENCE INTERVALS

,.

STATION SEASON ALPHA LOWER LIMIT SLOPEp 1 1 010

:050000

L : 16:66765.38565.3-85I

ioo

:20025.380 65.385

cr 33.769 65.385

. 004

UPPER LIMIT141.152112.500104.54596.913

Page 52: Supplemental Modeling and Analysis Report

1

Page 53: Supplemental Modeling and Analysis Report

m

: ”

88iEZfZ 1

L8/ 11180

Page 54: Supplemental Modeling and Analysis Report

m: It /

File: J:\FOX\GENSTAT\ATPlS_RG.CSV------_-----------------------------------------------------------

PROB. OF EXCEEDINGTHE ABSOLUTE VALUE

KENDALL OF THE Z STATISTICS Z (TWO-TAILED TEST)

STATION SEASON STATISTIC STATISTIC N IF N > 10

r? 1 1 -44.00 -.8d743 29 -420

SEN SLOPECONFIDENCE INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMIT1 1

.010 -.088 -.019 043

:loo' 050 -.065 - YO53~ -.019 -.019:02502-o

P . 200 -.047 -.019 :on:

Page 55: Supplemental Modeling and Analysis Report

__. ,.

File:J:\FOX\GENSTAT\ATPlSwR6.CSVPrinted:12/31/97 Page: 1

: ~" ', ,' Linear RegressionMinimum Maximum Mean Median Std Dev Slope R-Sqr Num

0.00 7.30 1.52 1.20 1.44 -0.09141 0.03 29.

p .

F

fI 1

Page 56: Supplemental Modeling and Analysis Report

p (‘.:_.

f-

i a

c ‘

F””

t

Page 57: Supplemental Modeling and Analysis Report

File: J:\FbX\GENSTA‘f\ATPlS;UR.CSV-------------------------------------------~-------,---------------~--

fy

,,,IPROB. OF EXCEEDING

. _I MANN - THE P;BSOLU?E VALUEKENDALL OF THE Z STATISTIC

FI I ') s Z (TWO-TAILED TEST)k. j, ., STATION SEASON STATISTIC STATI$TIC Ia IF N > 10

1 1 -141.00," -2.77477 28 .006

SEN SLOPEr 7 'CONtiIDENCE“INTERVALSL ,"

STATION SEASON ALPHA LOWER LIMIT SLiJPE UPPER LIMITkl. 1 1 010 -.300

:050 -.278-.170 000-.170 -:045

. 100 -.265 -.170 -.065F .2po -.250 -.170 -.082

y

_1 .*

n \ ,. >_ , :. ‘ (. . .: ./

m: 1i j

Page 58: Supplemental Modeling and Analysis Report
Page 59: Supplemental Modeling and Analysis Report

16

T

Uranium ConcentrationMonitoring Well ATP-1-S

2118182 11114l84 8/11187, t. sl7190

Dates Sampled

1131193 10128195 7124198

Page 60: Supplemental Modeling and Analysis Report

File: J:\FOx\GENSTAT\ATPZS-MO.CSV_______-----------------------------------------------------------'

_. _. , PROB. OF EXCEEDING_. ITHE ABSOLUT'E -VAbl%

f-KENDALL OF THE Z STATISTIC

b S Z (TWO-TAILED TEST)c ‘. STATION SEASON S+ATI'STIC STATISTIC N IF N > 10

em

;1 1 46.00 1.8'5999 17 . 063

k;

SEN SLOPECONFIDENCE INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPEr

UPPER LIMIT1 1 .OlO -.012 020 061

. 050 .ooo :020 :054

. 100 . 020Fk * .200 . Ol<O . 020 . 049i '

‘ ...

Page 61: Supplemental Modeling and Analysis Report

<

Page 62: Supplemental Modeling and Analysis Report

t

”L ;

mi :: ,i ;

z-l

: !

L6lL LIE

P6lS 119

li

1616 116

Page 63: Supplemental Modeling and Analysis Report

File: &\FOk\tiENSTAT\ATPZS-NI.CSV_i_____--_--------------------------------------------------------

PROB. OF EXCEEDINGTHE ABSOLUTE VALUE

KENDALL OF THE Z STATISTICS Z (TWO-TAILED TEST)

STATION SEASON STATISTIC STATISTIC N IF N > 10

lrrl 1 1 -610.00 -3.88537 60 . 000

dSEN SLOPE

CONFIDENCE INTERVALS

STATION SEASON ALPHA LOWER LIMIT SLoPE UPPER LIMIT1 1 010 '

:050-4.513 -2.739 -1.059-4.032 -2.739 -1.500

. 100 -3.765 -2.739 -1.719- .200 -3.500 -2.739 -2.055L

Page 64: Supplemental Modeling and Analysis Report
Page 65: Supplemental Modeling and Analysis Report

l-

c

Page 66: Supplemental Modeling and Analysis Report

File: J:\FOX\GENSTAT\ATP2S_RG.CSV____-_------------------------------------------------------------

PROB. OF EXCEEDINGTHti ABSbLtiE VALUE

STATION

STATION1

KENDALL OF THE Z STATISTICS Z (TWO-TAILED TEST)

SEASON STATISTIC STATISTIC N IF N > 10

1 -194.00 -2.09965 42 . 036

SEN SLOPECONFIDENCE INTERVALS

SEASON ALPHA LOWER LIMIT1 .OlO -.050

,050 -.040

:200 100 -.033 -.030

SLOPE-.020-.0207.020-.020

UPPER LIMIT002:ooo. 000

-.007

Page 67: Supplemental Modeling and Analysis Report

Printed:12/31/97 Page: 1File:J:\FO~\GEXSTAT\ATP2S_R6.CSV

Linear Regression

Minimum Maxinnlm Mean Median Std Dev Slope R-Sqr Num

0.00 lg.80 1.23 0.60 1.94 -0.05548 0.12 42

Page 68: Supplemental Modeling and Analysis Report

li

10

8

6

4

2

0

RA226 ConcentrationsMonitoring Well ATP-2-S

-- _. 1 -- -” ‘1

,

.---..- ---.--____-_

0- -_- -._

t -

-.---._____ _._______..._._____I___

2/18/82 lll14l84 8/11/87 WI90 1131193 1 O/28/95 7124198I

Dates Sampled

Page 69: Supplemental Modeling and Analysis Report

. ̂ ,.( I __., j ./.l,r”,

“1

File: J:\FOX\GENSTAT\ATPZS_R8.CSVn -------_----_-_---------------------------------------------------" 1L ,

MANN-PROB. OF-EXCEEDINGTHE ABSOLUTE VALUE

KENDALL OF THE Z STATISTICp S Z (TWO-TAILED TEST)

STATION SEASON STATISTIC STATISTIC N IF N > 10

631 1 1 26.00 1.03392 17 . 301I iI

SEN SLOPECtitiFI'D"titiC!ti' ItiTERVALS

STATION SEASON ALPHA LOWER LIMIT SLOPE1 1 010 -.071 037

:050 -.048 :037. 100 -.024 037. 200 -.009 :037

UPPER LIMIT158:121. 106.083

6-7j /

: :

Page 70: Supplemental Modeling and Analysis Report

Printed:12/31/97 Page: 1

Linear Regression

Minimum Maximum Mean Median Std Dev Slope R-Sqr Num0.00 3.00 1.97 2.00 0.73 0.05612 0.12 17

-3

Page 71: Supplemental Modeling and Analysis Report

L6ILLIB

P6l5 LIS

1616 116

06lLl9

1 88/EZIZ L0

Page 72: Supplemental Modeling and Analysis Report

File: J:\FOX\GENSTAT\ATPZS-UR.CSV----------------------------------------- -------------------------

I-i 1

MANi'PROB. OF EXCEEDINGTHE ABSOLUTE VALUE

KENDALL OF THE Z STATISTICm S Z (TWO-TAILED TEST)I ; STATION SEASON STATIQTIC SY!&TfST~IC N IF N > 10

P-4 1 1 -143.00 -1.38991 .165:

L7SEN SLOPE.CoN;F‘TBgHcE" .‘INTGRvAL's

STATION SEASON ALPHA LOWER LIMIT SLOPE UPPER LIMITrclll

,

1 1 . 010 -163.169 -56.696 57.143

:100 050 -141.301 -125.989 -56.696 -56.696 29.763 x2.158r* .200 -115.074 -56.696 -2.769:k;

“I:

h !. d

Page 73: Supplemental Modeling and Analysis Report

Printed:12/31/97 Page: 1File:J:\FOX\GENSTAT\ATP2S_UR.CSV

Linear Regression

Minimum Maximum Mean Median Std Dev Slope R-Sqr Num

0.00 9800.00 4999.33 5400.00 2717.74 -'32.59795 0.02 45b

Page 74: Supplemental Modeling and Analysis Report

86/m L

.-

96l8210 L,

*Ict

I. E6lLlll

I

i f

f-88

a

LSI 1 118

c”iI

P8lt II 11--

j

--Yh

8 Ii2 ,

*7

I :

Page 75: Supplemental Modeling and Analysis Report

APPENDIX B

h.

r-4I

: /

Page 76: Supplemental Modeling and Analysis Report

-

*6/Q 118P6/ 1Ell&6/Ll/LL&6/0Z/86612219C6/9Z/P86/9ZlZBG/ZZ/ 1ZG/BZ/ 11

zz ZG/ZZ/O 1Z6/6 l/8Z6fL l/L2611 LZ/QZ6lt l/PZGILZIZZ6/ I/ 116/9Z/ll16/8 L/O 1

0

0

1

O9

0

0

0’

0

D

e-0

a

2a88

I’ t8

0

-.CL,

8

c8

873

0

83

08

80

Ia I

dI

8op

8a

0

aC

0

r”4

8

a

‘L

;8

0

a8 0

C

P-

aC

8 00”

ry

0 1-

8>Ba53t

16lPZi816/QZ/L1 G/Et/Q16/OZ/P16ILZIZ16/Ql/l06/6Z/ 1061 IZIO06/L l/806/ZZ/Q06/9Zrt7

0

L1

06/L l/C06/oz/ 168/lZ/ll68/ 1 L/O 168/ZZ/868/8/f6816 L/Q68/Q LIP.68/ZZ/Z68/P I/ 1+

Page 77: Supplemental Modeling and Analysis Report

&Jtr6/QZfZtr6/5Zf 1

$M.

C6f LZIO 1 f=

86/OC/L %

B6ILZlQ66fZZfBE6fZZfZZ6fZZf Z 1Z6fL I/ 1126/61/6Z6fL L/8z6/QZ/9Z6/6 115Z6ILZIEZ6f LZIZ16/L t/Z 116/0Z/ 1116/zz/6 E1612218 2.16/Q l/Q d

16/81/Q g16/EZ/&

.-

;,W

Q)ILe

P

B

C

!

r16fCZfZ0616 LIZ 106/L If 11061 lZf6

.-

8’0

06/P l/806/ZZ/j306fQZft06/f LIE06fOW 1681 lZ/ 1168/l L/O 168/zz/868/8/L6816 If Q68/Q l/P

Page 78: Supplemental Modeling and Analysis Report

GRAPH B-3WATER LEVEL COMPARISON BETWEEN WELL AMM-3 AND COLORADO RIVER

3 9 6 3 . 0 0 7 0

n

xsECTA.XLS NM’tiB3.XLC 16/2@/941

Page 79: Supplemental Modeling and Analysis Report

: c.

I

%

3

0

I

3

A

0

J

‘9

I

0

0

0

e"

0

‘0

I

0

0

a

-. .+ . .

n:

lrwszfztrW5Zll8WlZlOL&6/OC/Lg&&&y&

E6fzZf EE6fzZfzZwzZ/ zZ6fL If 1ZWEW6Z6fL l/8Z6f QZ/Q

c8

J

-

t.

8

#

-0

I c

I

II

03

Is

c II

.cl

I0

1

o-I

m88 l 86l c

kI

I8

�La

8

tL-

00

l~/ZZ/6 .g16/ZZ/8 z16/Q L/Q 5

9’LW8WQ’ i 216/&Z/C 2

3*

coc! Io I

o--r!

8 Y!

16/&Z!Z0616 l/Z 106fLLf 11061 lZf6OWV 118owzw~OS/&Ytr

OWL LIE06fOW 168flWt 168/L l/O1

68/zZf8

68/8/L68f6LlQ

6819 LIP

68/ZZ/Z

mc f3. >

5fF”r

c

t ,

Page 80: Supplemental Modeling and Analysis Report

.3tr6fQZf Z -@

E6f6Zf6P-e

E6fOCflL p

4 BGILZI 9

66fZZfC

E6fZZf 1

~Z6/L1/11

Z6/ lZf6

Z6fL l/L

Z6/6 l/Q

Z6ILZl E

i5WQ,Irn

B.e

8

n*

m

: ! Iaxss00

sa

iii5mJ E>

z

1,0H

t

Z6ltr l/l

l6/9Zfll

16/Zz/6 5

16ILZIL 2

16/81lQ 8

iS/SZ/S

16&Z/ 1

06/f If 11

0616 l/6p?f. -

B$ 06/Z l/L.-,06/l I&

06/L 11 c:

06/0Z/ 1

68/lzfll

68/Z/6

68/8/L

68/V l/Q

6818 lf&

68/P If 1

Page 81: Supplemental Modeling and Analysis Report

t6/4Z/ZE6/6Z/6

BGIOEIL

EGILZIB2P ”.

- - EG/ZZ/l

- - 26/f l/l 1

- - Z6fL 1/L

- - ZGILZIB

- - Z6/Pl/l

- - 16/9Z/ 11

- - LGILZIL

- - 16/91/9

- - 16/81/E

- - I6/9Z/l

- - 06/Ll/ll

- - 06/6 l/6

06/z l/L

06/ 1 l/9

06/L l/C

061OZI 1

69f lZ/ 1

69/Z/6

69/9/f

1pn

:

69/t l/9

6919 l/E

69/t I/ 1

mI i

Page 82: Supplemental Modeling and Analysis Report

aP6/9Z/ZO

C6/62/60

86lOCllLO

EGILZI90

EGIZZIEO

CSIZZ! 10

Z6/Ll/ll

261 lZl60

Z6lL l/LO

Z616 l&O

. Z6lLZlCO

Z6ltrlIlO

16/9Z/ll

16/~z/60 3

l6ILZlfO 5

16/91/90 4a

16lCZlCO

16&Z/ 10

06/f l/l 1

0616 l/60

oyz l/f 0

06/l l/90

06/f l/80

06/OZ/ 10

68/lZ/ll

68lZO160

68/80/f 0

68/P l/90

6818 l/E0

68/t l/10

m..* ?:

nL ,.mib;.