supercritical technology in boilers
TRANSCRIPT
SUPER CRITICAL TECHNOLOGY
Presented By:Amit Joshi
UPES Dehradun,India
Introduction"Supercritical" is a thermodynamic
expression describing the state of a substance where there is no clear distinction between the liquid and the gaseous phase.
Supercritical Power plants operate at higher temperatures & higher pressure resulting in higher efficiencies i.e., up to 46 percent for supercritical plants and lower emissions than traditional (subcritical) coal-fired plants.
WHAT IS A SUPERCRITICAL BOILER?Supercritical steam generators (also known as Benson
boilers) are frequently used for the production of electric power.
In contrast to a "subcritical boiler", a supercritical steam generator operates at such a high pressure (over 3,200 psi/22.06 MPa 3,200 psi/220.6 bar that actual boiling ceases to occur, and the boiler has no water - steam separation.
There is no generation of steam bubbles within the water, because the pressure is above the "critical pressure" at which steam bubbles can form.
It passes below the critical point as it does work in the high pressure turbine and enters the generator's condenser.
This is more efficient, resulting in slightly less fuel use. The term "boiler" should not be used for a supercritical pressure steam generator, as no "boiling" actually occurs in this device.
WHAT IS SUPERCRITICAL TECHNOLOGY?Above 221 bars, two phase mixtures of water and steam
cease to existThey are replaced by a single supercritical fluid. This eliminates the need for water/steam separation in
drums during operationThus allowing a simpler separator to be employed during
start-up conditions.The transition to steam temperatures of 600°C and higher
is now a further major development step, which decisively affects many aspects of the design of the power plant, especially of the boiler
Critical Point
22.1MPa-373ºC
Special feature of supercritical boilersCapacity to operate under low load. Suitability for continuous variable loads. Suitability for cyclic operations. Suitability for two shift operations. Quicker start up and shut down capability. Larger unit size.
Advantages of Supercritical technology Today supercritical units can achieve thermal
efficiency of more than 45 percent, compared with a typical subcritical plants 30-38 percent.
Higher firing temperatures and pressures translate into better efficiency, defined as more electricity generated per BTU of coal consumed.
super critical technology will result in saving of about 4% of fuel and correspondingly less emission.
The Benson design offers a number of advantages, including simplified start up and the ability to operate in sliding pressure mode.
“LIMITATIONS” Economy of scale.
Problem with the metallurgical limit .
An increase in steam temperature (>700 C) is possible but without NICKEL based materials it is not possible to obtain more than 10K to 20K.
Double reheating is required to prevent Inlet pressure turbine exhaust wetness
Extremely high initial build cost. More complicated to operate. Much higher O&M costs. Not very flexible, generation changes are
slow and minimal, usually only for "base-load" generation.
Environmental considerations.
1960s 1970s 1980s 1990s 2000s 2010s
MatureTechnology
R&D- Advance USC
Subcritical 170/540oC/540o
Super critical 245/540/540
245/540/565
245-580/600
285-600-620
285-630/650
382-700/720
ULTRA SUPERCRITICAL
Par
a met
e rs
Year
SUPERCRITICALSUB- CRITICAL
Und
er
Indu
ctio
n
Alr
eady
In
duct
ed
International Scenario of Supercritical Technology
CO2 Reduction Scenarios
0
200
400
600
800
1000
1200
1400
30 35 40 45 50 55 60
Plant Net Efficiency
CO
2
Em
issi
on
s(
kg
/MW
h)
USCA-USC
Super Critical
Capacity addition based on Supercritical technology
11 number supercritical units totaling to 7,540 MW under construction during 11th Plan.
20 number supercritical units totaling to 14,000 MW ordered so far for 12th Plan
13 number UMPP, each of about 4,000 MW capacity, based on supercritical technology planned. Four UMPP already awarded
About 62 number supercritical units totaling to 44,000 MW likely to be added during 12th Plan.
Super Critical Technology in NTPC UPCOMING PLANTS
North Karanpura, Jharkhand – 3x660 MW Darlipali, Orissa – 4x800 MW Lara, Chattisgarh – 5x800 MW Marakanam, Tamilnadu – 4x800 MW Tanda-II, Uttar Pradesh - 2x660 MW Meja, Uttar Pradesh - 2x660 MW Sholapur – 2x660 MW New Nabinagar-3x660 MW Many more projects including 800 MW ultra super critical
units under consideration