Super Strength Polytunnel Instructions

DR-GARDEN50

Page 2: Super Strength Polytunnel Instructions

2Copyright © NP Structures Ltd

CONTENTS

CONTENTS

INTRODUCTION

PREPARATION

CHOOSING THE RIGHT SITE FOR YOUR POLYTUNNEL GETTING TO KNOW YOUR POLYTUNNELTHE RIGHT TOOLS FOR THE JOB BE SAFE WHEN CONSTRUCTING

GROUND TUBES

ENSURING YOUR GROUND TUBES ARE SQUARED STANDARD GROUND TUBES WITH CONCRETING BAR

FRAMEWORK INSTALLATION

GROUND TUBE FITTINGS HOOP FITTINGS INSTALLING THE HOOP FITTINGSINSTALLING THE HOOPS RIDGE BEAMS CORNER STABILISERS CROP BARS

DOOR FRAME INSTALLATION

TIMBER DOOR FRAME KIT SOFT GROUND TIMBER DOOR FRAME KIT HARD GROUND

TIMBER BASE RAIL INSTALLATION TIMBER BASE RAIL

COVERING INSTALLATION

ANTI HOT SPOT TAPE TIMBER BASE RAIL COVER TENSIONING THE POLYTHENE

DOOR KIT INSTALLATION

TIMBER DOOR KIT CONSTRUCTION TIMBER DOOR KIT INSTALLING A SINGLE SLIDING DOOR

2

3

4-5

4455

7-8

78

9-16

910111213-141516

17-22

17-2021-22

23

23

24-28

2425-2828

29-33

29-31

32-33

Page 3: Super Strength Polytunnel Instructions

3Copyright © NP Structures Ltd

Firstly thank-you for choosing your Polytunnel from Northern Polytunnels. We pride ourselves on the quality of our products combined with our knowledge and experience.

If during the construction of your Poytunnel you feel you need some advice please don’t hesitate to call on 01282 873120.

On first view these instructions may overwhelm and confuse, we advise that you take time to read through these instructions thoroughly, ensuring you have all the right tools for the job BEFORE constructing your new Polytunnel.

INTRODUCTION

Installation Sequence Construct your polytunnel in the following order...

1 GROUND TUBES2 FRAMEWORK3 DOOR FRAME INSTALLATION4 BASE RAIL INSTALLATION6 COVERING THE POLYTUNNEL7 DOOR INSTALLATION

Throughout these instructions we have given Hints and Tips. These bits of advice have been gathered from our constructors’ years of experience.

Thank-you

Hints and Tips

Break the whole process into phases this will make the whole process easier.

Page 4: Super Strength Polytunnel Instructions

4Copyright © NP Structures Ltd

1

3

4

5

6

7

Polytunnel Door and Frame

HoopsRidge Beam

Crop Bar

Corner Stabilisers

Ground tubes

2Base Rail

Choosing the right site for your Polytunnel

Getting to Know Your Polytunnel

PREPARATION

When selecting a site for your new polytun-nel there are a few things to consider. The orientation of the tunnel is not as critical as it would be with a Greenhouse, the tunnel will diffuse the light throughout the day.

Choose a spot sheltered from the wind forinstance next to a hedge, trees or wall, however equally choose a spot that has the maximum amount of sunlight.

During the hottest days we advise keeping the door open to let the air flow through.

Keep an access of approx 1 meter around the Polytunnel for cleaning and maintenance.

Page 5: Super Strength Polytunnel Instructions

5Copyright © NP Structures Ltd

THE RIGHT TOOLS FOR THE JOB

BE SAFE WHEN CONSTRUCTING

8mm Spanner (for M6 Fasteners)13mm Spanner (for M8 Fasteners)17mm Spanner (for M10 Fasteners)Allen bolt (supplied)7mm Timber Drill Bit11mm Masonry Drill Bit4mm HSS Drill Bit11mm HSS Drill BitTimber Hand SawHacksaw (Suitable for cutting Aluminium)Wheel barrow

Spade / Post hole diggerSpirit LevelBuilders String LinesTimber BlockHammerScrew DriverDrillTape MeasureSharp Craft KnifeStep LaddersSetting out pins / pegsCleaning cloth

Always wear gloves when constructing as there may be sharp edges.

Always use the correct tool for the job

Consider other people around the site of your new polytunnel, particularly children and animals.

Take care when using sharp tools.

Keep your work area tidy and organised, a tidy work area is a safe work area.

Do not leave holes open for long periods of time, cover them to reduce the risk of injury.

Tie back any loose hair and wear suitable clothing and shoes.

Take care when lifting heavy items of your kit.

When using ladders ensure they are on level ground

PREPARATION

When starting each phase of the construction lay out all materials close to hand. This will ensure you have the right parts and don’t forget to fit the right parts.

Always wear suitable personal protective equiptment

Page 6: Super Strength Polytunnel Instructions

6Copyright © NP Structures Ltd

ENSURING YOUR GROUND TUBES ARE SQUARED

PLEASE NOTE: Regardless of which ground tube option you have chosen the same method of squaring will apply.

It is essential that the ground tubes are fitted accurately to ensure the polytunnel is constructed to a satisfactory standard

Make sure the ground tubes are in line and set to a constant height with their opposite ground tube.

Install each corner and run a builders string around the perimeter to aid with installing the inner ground tubes

Check that the ground tubes are at 90º to each other by measuring 3m down the length, 4m along the width and checking the resulting measurement between the two points is 5m.

The diagonal measurements should be equal to each other

EQUAL TO OPPOSITE DIAGONALEQUAL TO OPPOSITE DIAGONAL

5m

3m

4m

TOOLS: Tape measure, Tape, Setting out pins / pegs, Spirit level

Page 7: Super Strength Polytunnel Instructions

7Copyright © NP Structures Ltd

ENSURING YOUR GROUND TUBES ARE SQUARED

X= 10ft 12ft 14ft

Y = 5ft or 6ft see order details

Your Polytunnel should be level side to side,but can have a slope on the length (within reason). Measure corner to corner to double check the foundations are square

Page 8: Super Strength Polytunnel Instructions

8Copyright © NP Structures Ltd

GROUND TUBES

STANDARD GROUND TUBES WITH CONCRETING BAR

Dig holes for each ground tube ensuring they are square to each other.

Insert the concreting bar into the ground tube, then drop the tube assembly into the ground.

Using a hammer, drive ground tube into the ground, using a timber block to protect the end of the tube.

Pour concrete mixture into holes to completely cover concrete bar and ensuring the ground tube is straight.

Once concrete has set, back fill the holes with earth.

PARTS: FR-SGLGT125, MP-CONCBAR

TOOLS: Spade, Hammer, Timber block, String line, spirit level, tape, wheel barrow, setting out pins / pegs

Use a spirit level to ensure ground tubes are squared.

Page 9: Super Strength Polytunnel Instructions

9Copyright © NP Structures Ltd

FRAMEWORK INSTALLATION

GROUND TUBE FITTINGS

PARTS: 1 FIT-A45, 2 FIT-MSC45, 3 FIT-HSC45

TOOLS: Spirit level, String line, Tape measure, Drill, Concrete drill bit, Hammer, 17mm and 13mm spanner

1 2 3

PLEASE NOTE: The inner hoop is set to 120mm and the end hoop to 190mm to allow for tensioning at the covering stage.

Page 10: Super Strength Polytunnel Instructions

10Copyright © NP Structures Ltd

HOOP FITTINGS

FRAMEWORK INSTALLATION

PLEASE NOTE: take the time to read this section throughly before beginning the construction of hoops and attaching any fittings

Copyright © NP Structures Ltd

FR-HHP10PL50FR-HHP12PL50FRHHP14PL50

FR-HHP10SW50FR-HHP12SW50FR-HHP14SW50

Swaged Half Hoop

Plain Half HoopThe following codes relate to the width of your polytunnel

The following codes relate to the width of your polytunnel

Corner Stabiliser Bar Fitting FIT-B50

Door Frame Fitting FIT-D50

Ridge Beam Fitting FIT-E50

Used with Single ridge beam fitting

Joining The Hoops Together

Page 11: Super Strength Polytunnel Instructions

11Copyright © NP Structures Ltd

HOOP FITTINGS

FRAMEWORK INSTALLATION

Securing Hoops With Single Ridge Beam Option

TOOLS: 17mm spanner

Page 12: Super Strength Polytunnel Instructions

12Copyright © NP Structures Ltd

INSTALLING THE HOOPS

FRAMEWORK INSTALLATION

Now you have attached all the correct fit-tings for your polytunnel option, you are ready to install the hoops to your ground tubes.

Page 13: Super Strength Polytunnel Instructions

13Copyright © NP Structures Ltd

RIDGE BEAMS

FRAMEWORK INSTALLATION

Ridge Tube Swaged End Ridge Tube Plain end

TOOLS: Hammer, 10mm spanner, 17mm spanner, Hack Saw, Step ladders

55mm Tube Plug MP-PLUG55mm

PARTS: 1 RIDGE TUBE SWAGED END 2 RIDGE TUBE PLAIN END 3 MP-PLUG50MM

Installing First and Inner Ridge Beam

Page 14: Super Strength Polytunnel Instructions

14Copyright © NP Structures Ltd

RIDGE BEAMS

FRAMEWORK INSTALLATION

Installing The Last Ridge Beam

Securing the Ridge Beams

Put one end hoop and one inner hoop at at each end then fit the diagonal bracing. This will ensure your polytunnel is square and will help with measurements.

Page 15: Super Strength Polytunnel Instructions

15Copyright © NP Structures Ltd

CORNER STABILISERS

FRAMEWORK INSTALLATION

PARTS: FR-DIAST2X32 or FR-DIAST2.2X32, BFA-H8X20HN

TOOLS: Two 17mm spanners

On the last inner hoop at either end, securing the corner stabiliser at ground tube level. Using the long hex screws attach your corner stabiliser to part B50 which was fitted to the hoops on page 11. B50fitting

Corner Stabiliser

Attach the other end of the corner stabiliser to the B50 fitting on last hoop.

Last hoop High level

B50 fitting

Corner Stabiliser

When attaching your corner stabiliser, ensure the bolt head is to the outside of the tunnel.

BFA-M8X20MN

INSIDE

Page 16: Super Strength Polytunnel Instructions

16Copyright © NP Structures Ltd

CROP BARS

FRAMEWORK INSTALLATION

PARTS: 1 FR-CB2521 or FR-CB3228 or FR-CB3231, 2 KH50, 3 BFA-H8X20NY, 4 FR-CB25X0.6

TOOLS: Two 13mm spanners, Spirit level

Place a spirit level on the crop bar and check for level. When crop bars are all in place we advise you stand back and visually check they line up.

Page 17: Super Strength Polytunnel Instructions

17Copyright © NP Structures Ltd

TIMBER DOOR FRAME KIT

TIMBER DOOR FRAME KIT SOFT GROUND

PARTS:1 TIM-75402.55, 2 = TIM-7540.9 3 = TIM-4040.9 4 = FIT-CJP, 5 = BS-NAIL40, 6 = BF-TS15063, 7 = BF-TSBIT, 8 = BFA-R10X60HN, 9= BF-WASH10

TOOLS: Hammer, Nails, Tape measure, Drill, Allen bolt, Spade, 13mm spanner, Wood drill, 11mm drill bit, Wood saw

WIDTH T W

10’ 150mm 900mm

12/14’ 300mm 900mm

Door Frame Dimensions

Page 18: Super Strength Polytunnel Instructions

18Copyright © NP Structures Ltd

TIMBER DOOR FRAME KIT

TIMBER DOOR FRAME KIT SOFT GROUND

Fixing Corner Joining Plate

Securing The Frame

Page 19: Super Strength Polytunnel Instructions

19Copyright © NP Structures Ltd

TIMBER DOOR FRAME KIT SOFT GROUND

To secure your door frame into soft ground, dig out two holes 1150mm apart.

TIMBER DOOR FRAME KIT

Page 20: Super Strength Polytunnel Instructions

20Copyright © NP Structures Ltd

Line up post to the edge of each hole, mark approx 10mm under posts and cut.

To attach the frame to the hoops, use fitting D32 attached on page 13 to secure the door. Next back fill holes with compacted earth leaving approx 10mm of thresher showing.

TIMBER DOOR FRAME KIT

TIMBER DOOR FRAME KIT SOFT GROUND

Page 21: Super Strength Polytunnel Instructions

21Copyright © NP Structures Ltd

TIMBER DOOR FRAME KIT

TIMBER DOOR FRAME KIT HARD GROUND

Door Frame Dimensions

WIDTH T W

10’ 150mm 900mm

12/14’ 300mm 900mm

Page 22: Super Strength Polytunnel Instructions

22Copyright © NP Structures Ltd

TIMBER DOOR FRAME KIT

TIMBER DOOR FRAME KIT HARD GROUND

Page 23: Super Strength Polytunnel Instructions

23Copyright © NP Structures Ltd

TIMBER BASE RAIL INSTALLATION

TIMBER BASE RAIL

PARTS:1 TIM-75401.525 or TIM-75401830, 2 TIM-75401.2, 3 FIT-CJP, 4 BS-NAIL30, 5 BFA-R8X50HN, 6 BF-WASH8X15

TOOLS:13mm spanner, 17mm spanner

1 TIM-75401.525 or TIM-75401830, 2 TIM-75401.2, 3 FIT-CJP, 4 BS-NAIL30, 5 BFA-R8X50HN, 6 BF-WASH8X15

TOOLS:13mm spanner, 17mm spanner

23

Page 24: Super Strength Polytunnel Instructions

24Copyright © NP Structures Ltd

ANTI HOT SPOT TAPE

ANTI HOT SPOT TAPE

PARTS:1 SU-AHST30MM + SU-AHST60MM

TOOLS: Stanley knife, cloth

24Copyright © NP Structures Ltd

Anti Hot Spot Tape on Inner Hoops

Anti Hot Spot Tape on End Hoops

60mm Tape

30mm Tape

Before applying the anti hot spot tape clean any oil or resedue off the hoops ensuring they are dry.

Page 25: Super Strength Polytunnel Instructions

25Copyright © NP Structures Ltd

COVERING INSTALLATION FOR ORDERS WITH BASE RAILS

TIMBER BASE RAIL COVER

Door Frame Battening

Laying Out Polythene

PARTS:1 Polythene cover code varies, 2 TIM-38192.2, 3 TIM-38192, 4 TIM-38191.828 or TIM-38191.524, 5 TIM-38191.2, 6 TIM-3819.97, 7 TIM-3819.9, 8 BF-NAIL50

TOOLS: Hammer, Tape measure, Step ladders, Saw, Two 17mm spanners

Before covering with main sheet make sure everyting looks square and all bolts are tight. Ensure there are no bolts sticking out or sharp edges, if there are cover them with anti hot spot tape.

Page 26: Super Strength Polytunnel Instructions

26Copyright © NP Structures Ltd

Securing the Polythene

Pulling Polythene Over Framework

TIMBER BASE RAIL COVER

COVERING INSTALLATION FOR ORDERS WITH BASE RAILS

Page 27: Super Strength Polytunnel Instructions

27Copyright © NP Structures Ltd

COVERING INSTALLATION FOR ORDERS WITH BASE RAILS

TIMBER BASE RAIL COVER

Always have someone else to hold the cover while you fasten the sheet so it does not blow away.

Page 28: Super Strength Polytunnel Instructions

28Copyright © NP Structures Ltd

Tensioning the Polythene

TENSIONING THE POLYTHENE

RELEASE THE CORNER STABI-LISER FITTINGS B50 ON THE END AND SECOND HOOPS PRIOR TO TENSIONING.

CORNER STABILISER

SLIDE INNER HOOPS UPWARDS ON THE GROUND TUBE APPROX. 70MM TO TENSION THE POLYTHENE.

RE-POSITION THE A45 FITTING ON THE GROUND TUBE AFTER TENSIONING TO SUPPORT THE INNER HOOPS.

TIMBER BASE RAIL COVER

Page 29: Super Strength Polytunnel Instructions

29Copyright © NP Structures Ltd

TIMBER DOOR KIT INSTALLATION

TIMBER DOOR KIT

PARTS:Door Parts1 TIM-4040.950, 2 TIM-40401945, 3 TIM-4040.870, 4 TIM-4040950D, 5 FIT-CJP, 6 BF-NAIL40, 7 CO-DOORPOLY, 8 TIM-381922, 9 TIM-3819.870, 10 DO-SROLL, 11 DO-DBOLT, 12 BF-TS3855, 13 BF-NAIL50, 14 SU-NET1.5M, Sliding Track Parts12 BF-TS3855, 15 AL-SDTRACK1.8 17 D0-HBOLTTUBE, 19 BF-COACH38MM, 20 BFA-H8X16HN

TOOLS: Hammer, Timber block, Spanner, Drill, Two 13mm spanners, Tape measure, Wood saw, Allen bolt, 9mm drill bit

Setting out the door

Fixing Together

Page 30: Super Strength Polytunnel Instructions

30Copyright © NP Structures Ltd

Securing the Polythene

Applying the Polythene

TIMBER DOOR KIT

TIMBER DOOR KIT INSTALLATION

Page 31: Super Strength Polytunnel Instructions

31Copyright © NP Structures Ltd

TIMBER DOOR KIT INSTALLATION

TIMBER DOOR KIT

Net Option

Installing the Drop Bolt

Page 32: Super Strength Polytunnel Instructions

32Copyright © NP Structures Ltd

TIMBER DOOR KIT INSTALLATION

TIMBER DOOR KIT Installing a SINGLE Sliding Door

Door Track Drillings

Fitting Door Track Support Sliding Door Onto Track

Door Guide

Page 33: Super Strength Polytunnel Instructions

33Copyright © NP Structures Ltd

TIMBER DOOR KIT INSTALLATION

TIMBER DOOR KIT Installing a SINGLE Sliding Door

Fix Door into Position

Door Stop

Drop Bolt Holes

Page 34: Super Strength Polytunnel Instructions