suny canton facilities project update

8
SUNY Canton SUNY Canton Facilities Project Update Facilities Project Update Residential Residential

Upload: ksena

Post on 11-Jan-2016

41 views

Category:

Documents


0 download

DESCRIPTION

SUNY Canton Facilities Project Update. Residential. Facilities Project Update Residential. DASNY PN 254430 - Electrical Modifications at Mohawk & Smith - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SUNY Canton Facilities Project Update

SUNY CantonSUNY CantonFacilities Project UpdateFacilities Project Update

ResidentialResidential

Page 2: SUNY Canton Facilities Project Update

22

Facilities Project UpdateFacilities Project UpdateResidentialResidential

DASNY PN 254430 - Electrical Modifications at DASNY PN 254430 - Electrical Modifications at Mohawk & SmithMohawk & Smith

o Description - Replacement of existing electrical panels, Description - Replacement of existing electrical panels, breakers, wiring, outlets and switches in student wings. breakers, wiring, outlets and switches in student wings. The project will separate various circuits providing The project will separate various circuits providing each student room with a dedicated circuit as well as a each student room with a dedicated circuit as well as a shared surge protected circuit (surge protected outlet) shared surge protected circuit (surge protected outlet) for computer equipment use.for computer equipment use.

o Status - Complete.Status - Complete.

Page 3: SUNY Canton Facilities Project Update

33

Facilities Project UpdateFacilities Project UpdateResidentialResidential

DASNY PN 254440 - Entrance Canopies, Lobby DASNY PN 254440 - Entrance Canopies, Lobby Upgrades & Site at Mohawk & SmithUpgrades & Site at Mohawk & Smith

o Description - Improved pedestrian and vehicular Description - Improved pedestrian and vehicular access to Smith and Mohawk including site access to Smith and Mohawk including site landscape, lighting, blue lights, canopy and entrance landscape, lighting, blue lights, canopy and entrance vestibules. Renovations to the entrance lobbies vestibules. Renovations to the entrance lobbies including floor finishes, walls, railings and windows.including floor finishes, walls, railings and windows.

o Status - Approximately 90% complete. Entrance Status - Approximately 90% complete. Entrance canopies expected to be complete mid to late canopies expected to be complete mid to late September. Delivery of permanent exterior lighting September. Delivery of permanent exterior lighting expected October 1expected October 1stst followed by installation. Delivery followed by installation. Delivery of permanent store fronts, doors and windows of permanent store fronts, doors and windows expected November 1expected November 1stst followed by installation. followed by installation.

Page 4: SUNY Canton Facilities Project Update

44

Page 5: SUNY Canton Facilities Project Update

55

Page 6: SUNY Canton Facilities Project Update

66

Page 7: SUNY Canton Facilities Project Update

77

Page 8: SUNY Canton Facilities Project Update

88

Facilities Project UpdateFacilities Project UpdateResidentialResidential

New York Power Authority’s (NYPA) Energy New York Power Authority’s (NYPA) Energy Services Program - Replace Boilers, Smith, Services Program - Replace Boilers, Smith, Mohawk, Heritage & RushtonMohawk, Heritage & Rushton

o Description - Replacement of existing hot water boiler Description - Replacement of existing hot water boiler in each residence building with two high efficiency in each residence building with two high efficiency boilers. One boiler will be used to provide domestic boilers. One boiler will be used to provide domestic hot water and the other will be used to heat the hot water and the other will be used to heat the building. A third boiler will be installed to provide heat building. A third boiler will be installed to provide heat and domestic hot water for each of the residence and domestic hot water for each of the residence buildings directors living space.buildings directors living space.

o Status - Approximately 85% complete. Substantial Status - Approximately 85% complete. Substantial completion expected late September.completion expected late September.