PHILIPPINE RED CROSS Haiyan Operations Leyte Leyte Chapter SUMMARY OF COMPLETION As of November 16, 2015 As of to date, we have 6,376 completed houses in which part of the overall total with an on-going construction of 321 houses. Below will show the figures and the percentage of the completion. PRC in Partners hip with Differen t National Societie s CORE SHELTER COMPLETION MONITORING Municipaliti es Covered T A R G E T S Complete d Houses Percent Complete Ongoing Core Shelter Constructi on SRA Closed Out Target HH per Municipality Overall Target SRA Core SRA Core PRC – AMRC Alang-alang 539 608 3,000 2,300 101 18.30% 19 539 MacArthur 306 144 40 Mayorga 979 377 113 55 961 Tacloban City 165 63 13 AMRC TOTAL 1’518 HH 1’456 HH 421 127 1’500 PRC – DFAT Tacloban City NO SRA 154 154 150 100% DFAT TOTAL 154 HH 150 PRC – ARC Calubian 344 175 3,000 600 49 26.66% 1 339 San Isidro 1,716 282 69 7 1,688 Tabango 925 166 42 4 900 ARC TOTAL 2’985 HH 623 HH 160 12 2’927 PRC – GRC Dulag 1,347 886 2,000 2,100 895 58.05% 1,342 Julita 653 685 324 12 652 GRC TOTAL 2’000 HH 1’571 HH 1,219 12 1’994 PRC – IFRC Barugo 1,795 850 6,232 5,000 693 54.36% 32 1,752 Burauen 828 74 1 8 818 Babatngon 400 100 288 Carigara 395 375 326 13 388 Dagami 1,398 401 401 1,300 La Paz NO SRA 298 240 24 Palo NO SRA 419 1 Pastrana NO SRA 423 124 42 San Miguel 642 252 252 633 Santa Fe NO SRA 91 Tabontabon 1,250 838 639 1’218 Tacloban City NO SRA 826 41 Tunga 96 59 IFRC TOTAL 6’804 HH 5’006 HH 2,718 119 6’490 1

Upload: bryan-soledad

Post on 17-Feb-2017

187 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

As of to date, we have 6,376 completed houses in which part of the overall total with an on-going construction of 321 houses. Below will show the figures and the percentage of the completion.

PRC in Partnership with Different National Societies

CORE SHELTER COMPLETION MONITORING

Municipalities Covered

T A R G E T SComplet

ed Houses

Percent Complete

Ongoing Core

Shelter Constructi

on

SRA Closed

Out

Target HH per Municipality Overall Target

SRA Core SRA Core

PRC – AMRC

Alang-alang 539 608

3,000 2,300

101

18.30%

19 539MacArthur 306 144 40Mayorga 979 377 113 55 961Tacloban City 165 63 13

AMRC TOTAL

1’518 HH

1’456 HH 421 127 1’500

PRC – DFAT

Tacloban City NO SRA 154 154 150 100%DFAT TOTAL 154 HH 150

PRC – ARC

Calubian 344 1753,000 600

49

26.66%

1 339San Isidro 1,716 282 69 7 1,688Tabango 925 166 42 4 900

ARC TOTAL 2’985 HH 623 HH 160 12 2’927

PRC – GRC

Dulag 1,347 8862,000 2,100

895

58.05%

1,342Julita 653 685 324 12 652

GRC TOTAL 2’000 HH

1’571 HH 1,219 12 1’994

PRC – IFRC

Barugo 1,795 850

6,232 5,000

693

54.36%

32 1,752Burauen 828 74 1 8 818Babatngon 400 100 288Carigara 395 375 326 13 388Dagami 1,398 401 401 1,300La Paz NO SRA 298 240 24Palo NO SRA 419 1Pastrana NO SRA 423 124 42San Miguel 642 252 252 633Santa Fe NO SRA 91Tabontabon 1,250 838 639 1’218Tacloban City NO SRA 826 41

Tunga 96 59

IFRC TOTAL 6’804 HH

5’006 HH 2,718 119 6’490

PRC – NLRC

Merida 801 1802,210 400

196

96.22%

14 782Isabel 1,453 227 237 10 1’428

NLRC TOTAL 2’254 HH 407 HH 433 24 2’210

PRC - CitiBank

Tabontabon NO SRA 200 200100%CITIBANK

TOTAL 200

PRC – QRC

Tacloban City NO SRA 638 650 331 50.92%

50

QRC TOTAL 638 HH 331 501

Page 2: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

PRC – SRCTolosa 1,256 750 1,250 750 744 99.2% 6 1’246SRC TOTAL 1’256 HH 750 HH 744 6 1’246

T O T A L 24 Municipalities 16’817 HH 11’440 17’692 12’154 6’376 52.26% 350 16’369Table 1. Summary of the Completed Houses per PNS with the Completion vs. target

PRC in Partnership

with Different National Societies

HEALTH

Target for

Health

Area Covered

Type/Name of Facilities

Intervention RemarksAccomplished % (Complete)Municipality Facility Selected

TARGET Number of Health Facilities

Facility Equipped

PRC - IFRC 6

Tacloban District Health Center

and Barangay Health

Station

2

-District Health Center Suhi – Birthing

-Barangay Health Station Cabalawan – Non-birthing

Reconstruction and Equipping

Rehabilitation and Equipping

Completed the CGIs, trusses and purlins anchoring.- On-going activities:a. Plastering of walls.b. Backfilling of the excavated flooring.c. Completed CHB laying.d. Plastering of septic tank workse. Plumbing worksf. Completed CGIs installation.

Procurement of bidet hose and faucet

51.63%

100%

Palompon Barangay Health

Stations

3

-BHS San Guillermo - Birthing

Reconstruction and Equipping

- On-going activities:a. Ceiling and ceiling joist installation: 83.21% done.b. CHB installation for the delivery room dressing room – on-going.

67.35%

-BHS Tabunok – Birthing

Reconstruction and Equipping

-All punch listing on tile, plumbing and painting works are on-going.-Variation works: On-going with 1 more week allotment for completion.

100%

-BHS Cantuhaon - Birthing

Reconstruction and Equipping

-Concrete, Masonry, Roof, Tiles, Plumbing, Paint and Placenta Vault Works versus punch listing – on-going.-Backfills and Catch basins – completed.-Variation works: On-going with 1 more week allotment for completion.

100%

Dagami Barangay Health

Station 1 1

-BHS Abaca – Non- birthing

Rehabilitation and Equipping

Rehabilitation complete & equipped.-Officially turned over

on July 3 2015.

100%

PRC – NLRC 2 Isabel BHS - Birthing 1 0 -BHS Bantigue Reconstruction 98.58%

2

Page 3: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

Isabel BHS - Birthing 1 0 -BHS Cangag Reconstruction 87.74%

PRC - GRC 3

DulagBarangay Health Centers

2

-BHC Bulod – non birthing

Rehabilitation Completed Technical Designs and BoQ for further review and

approval.

0 %

-BHC Cabatoan – non birthing

Reconstruction Completed construction 100 %

JulitaBarangay Health Center

1 -BHC Tagkip non- birthing

RehabilitationCompleted Rehabilitation

100%

PRC1 Tacloban Marasbaras 1

- -BHS Sitio Ugsad non- birthing

Reconstruction Land survey on going

TOTAL 12 12 1

Table 2. This table will show the summary of the completed REHABILITATED AND RECONSTRUCTED OF HEALTH FACILITIES using number in the identified row for every Participating National Societies.

PRC in Partnership

withBatch Date of

Training

No. of Communities

Covered

Facilitators Mobilized

Target No. of CHVs

No. of CHVs

Trained

Accomplished Percentage

Total Percentage

Accomplished per PNS

IFRC

1 9/1-5/14 1 5 25 25 100%

100.67 %

2 10/6-10/14 3 5 25 23 92%3 10/21-25/14 4 5 25 25 100%4 11/11-15/14 3 5 25 27 108%5 11/24-28/14 4 3 25 24 96%6 12/16-20/14 3 4 25 27 108%

NLRC Isabel 6 35 31 88.57% 88.57%

GRC

AmCROSS1

5 barangays (Mayorga

Municipality

2 17 17 100%

AusRC 127

Total 329 199 60.48%

Table 3. THE TABLE WILL SHOW THE COMMUNITY BASED HEALTH AND FIRST Aid Training

3

Page 4: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

PRC in Partnership with Different

National Societies

R E H A B I L I T A T I O N

Target Classrooms

MunicipalityName of

School/Barangay

NUMBER OF CLASSROOMS

For Rehabilitation

ProgressRemarks

Percent CompletedOngoing Completed

PRC – SRC 35 Tolosa

San Vicente 11CL 11CL

100%

Cantariwis 1CL 1CLCanmogsay 4CL 4CLCapangihan 5CL 5CL

Tanghas 6CL 6CLMalbog 2CL 2CL

San Roque 6CL 6CL

PRC – NLRC 4 IsabelCangag

PutingBato

PRC – JRCS

52 including 1 Function Hall

Tacloban

San Jose Nat’l HS 4 CL 4CLSagkahan Nat’l HS 10 CL including

1 function hall11CL

100%Sagkahan Elementary

Sc.10 CL 10CL

Tanauan

Tanauan Nat’l HS 10 CL 10CL

100%

Tanauan Sc. of CHI 10 CL 10CLTanauan II C.Sc.

- --

PaloPhilippine Science HS

1 CL1CL 100%

PHASE 2

42CL

Alang - Alang

Alang – Alang I Central School

For Alang Alang, PRC already conducted Preconsturction Meeting with both Principals,

contractor, and consultant team.

For Tolosa, preconstruction meeting will be scheduled on November 13, 2015.

Contract already signed by all parties and have been notarized. (Waiting for 20% down payment to

contractors before implementation.)

Alang – Alang National High School

6 CL

Tolosa

DZR Memorial Elementary School

23 CL

QRCS 7 Burauen,LeyteBurauen North

Elementary SchoolWaiting for the certified true copy of Land title

Lowest and responsive bidder identified by BAC

GRC 11 Dulag Camitoc 1CL 1CL completed 100%Combis 1CL 1CL completed 100%Victory

Salvacion

4

Page 5: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

Rizal 1CL1CL

Ongoing Purchase of

MaterialsJulita Hindang 4CL 4CL completed 100%

TOTAL 151 116 87 Table 4. The table will show the update of the ongoing Rehabilitation of the selected schools within Leyte

PRC in Partnership with Different

National Societies

R E C O N S T R U C T I O N

Target Classrooms

MunicipalityName of

School/Barangay

NUMBER OF CLASSROOMS

For Reconstruction

ProgressRemarks

Percent CompletedOngoing Completed

PRC – SRC 35 Tolosa

San VicenteCantariwisCanmogsayCapangihan

TanghasMalbog

San Roque

PRC – NLRC 4 IsabelCangag 2CL 2 96.58%

PutingBato 2CL 2 100%

PRC – JRCS

52 including 1 Function Hall

Tacloban

San Jose Nat’l HS

Sagkahan Nat’l HS

Sagkahan Elementary Sc.

Tanauan

Tanauan Nat’l HS 1 CL 1 CL

95%

Tanauan Sc. of CHI

Tanauan II C.Sc. 6CL 6 CL

PaloPhilippine Science

HSPHASE 2

42CL

Alang - Alang

Alang – Alang I Central School

10 CL For Alang Alang, PRC already conducted Preconsturction Meeting with both Principals,

contractor, and consultant team.

For Tolosa, preconstruction meeting will be scheduled on November 13, 2015.

Contract already signed by all parties and have been notarized. (Waiting for 20% down payment to

contractors before implementation.)

Alang – Alang National High School

3 CL

Tolosa

DZR Memorial Elementary School

QRCS 7 Burauen,LeyteBurauen North

Elementary School7CL(for

CONSTRUCTION)GRC 11 Dulag Camitoc

CombisVictory 2CL

Salvacion 1CL

5

Page 6: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

Rizal

Julita Hindang 1CL

TOTAL 151 35 10 1 Table 5. The table will show the update of the ongoing Reconstruction of the selected schools within Leyte

As of to date, the Participating National Societies who are doing the Water and Sanitation interventions and completing latrines in schools and associated with core shelter is now increasing the number of completion. Below, we have now 5,385 toilets associated with core shelter completed with an ongoing of 353 units, and 8 Latrine in School completed.

PRC in Partnership with Different

National Societies

LATRINES COMPLETION MONITORING

Municipalities Covered

T A R G E T SCompleted LATRINES

Percent Completion

OngoingLATRINES

ConstructionTarget HH per Municipality

Overall Target

PRC – AMRC

Alang-alang 608

2,300

50

12.65%

34MacArthur 306 116 17Mayorga 377 76 14Tacloban City 165 49 10AMRC TOTAL 1’456 HH 291 75

PRC – DFAT Tacloban City 150150

150100%

3DFAT TOTAL 154 HH 150 3

PRC – ARC

Calubian 175

600

50

26.66%

15

San Isidro 282 69 8Tabango 166 41 19ARC TOTAL 623 HH 160 42

PRC – GRCDulag 886

2,100442

32.38%36

Julita 685 238 8GRC TOTAL 1’571 HH 680 44

PRC – IFRC

Barugo 850

5,000

693

57.54%

Burauen 74 1Babatngon 100Carigara 375 326 1Dagami 401 401La Paz 298 240 40Palo 419 1Pastrana 423 124 37San Miguel 252 252Santa Fe 91Tabontabon 838 839Tacloban City 826Tunga 59IFRC TOTAL 5’006 HH 2’877 78

PRC – NLRCMerida 180

450196

96.22%15

Isabel 227 237 9NLRC TOTAL 407 HH 433 24Tabontabon 200 41 20.5%

6

Page 7: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

PRC - CitiBank CITIBANK TOTAL 41

PRC – QRC Tacloban City 638650

33150.92%

66QRC TOTAL 638 HH 331 66

PRC – SRC Tolosa 750750

42256.26%

21SRC TOTAL 750 HH 422 21

T O T A L 24 Municipalities 11’440 12’200 5,385 44.13% 353 Table 6. The table will show the summary of the completed latrines associated with core shelter construction

Water Supply

Rehabilitation activities on water supply facilities in the province of Leyte continue to be done in various communities through the support of teams in the field. Table below shows the summary of the completed and ongoing facilities:

Partner Municipality Barangay Type of FacilityTotal # of

Units Completed

Status/Remarks

American Red Cross

Alang-alang Penalosa, Santiago, Astorga

Hand pumps 5 No report received

Water tank 1

MacArthur Danao Hand pumps 4

German Red Cross

DulagBarbo, Buntay, Candao, Combis, Luan, Sungi

Hand pumps 30

Completed rehabilitation of water facilities in Hindang Elementary School.

Conducted assessment for water facilities at Calipayan Health Center, Dulag

Conducted consolidation of assessment data’s for water points

On-going procurement and delivery of materials for 2nd retrofitting and repair of Batch 2 & 3 hand-pump.

On-going delivery for provision of water facilities in Rizal community center, Dulag, Leyte

Approved CBA for the 5th batch (15) units handpumps in Brgy. Cabatoan, Tabu, Highway & San Rafael, Dulag, Leyte

Barangays in Dulag, Leyte to be covered for the upcoming water supply installations are: (1) Cabatoan, (2) Tabu, (3) Highway and (4) San Rafael.

Julita

Bongdo, Hindang, Inawangan,Bongdo, Villa Hermosa, Anibong, San Pablo

Hand pumps 20

Netherlands Red Cross

Isabel San Francisco, Cangag

Hand pumps, pipeline system 2

Ongoing installation of 1 hand pump in barangay San Francisco, Isabel.

PO for the pipe rehabilitation in Antipolo and has been approved by Headquarters

Merida Calunasan Pipe line system CBA for the spring box rehabilitation

7

Page 8: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

in Calunasan has been approved by Tacloban, and is now in the Admin-level for processing.

Request for quotation for the piping fixtures for the spring box has been given to the prospective suppliers.

2 quotations for the piping fixtures have been received already and CBA will be submitted as soon as the 3rd

quotation will be received.

IFRC Babatngon

Magcasuang

Connection of New Water supply and Rehabilitation of old water source

No update Team is still waiting for the result of

the technical validation conducted by Architect Michael ColisVilla Magsaysay Connection of New

Water supply

San Agustin Connection of New Water supply

Australian Red Cross Tabango Manlawaan Rain water

harvesting unit

1 A pilot installation of rainwater harvesting units has been done in the barangay last Nov 9, 2015 with 3 skilled workers mobilized.

Table 7. The table show the updates for the water supply we have in the different Municipalities in Leyte

For the hardware interventions in the schools targeted in the municipality of Babatngon, the following structures have been proposed by the technical team:

Partner Municipality # of Schools Schools Catered Type of Facility Status

IFRC

Barugo 5Abango ES, Amahit ES, Bukid ES, Can-isak ES, Pikas ES

Construction activities completed

No steel plate yet Still for turn over Letters of refusal of

installation of bidet hose still has not been turned over

Babatngon 4

Bagong Silang Elementary School

Construction of 1 Sanitary Block (1 Male, 1 Female, 1 Urinal)

Construction of new Dug well

Pre-bidding has been conducted

A site visit was done with the potential contractors of the project.

Victory Elementary School

Provision of Elevated water tank with pump and pipe connections to the latrines

Construction of Septic Tank.

Repair of Dental Through (for hand wash and tootbrush)

Taguite Elementary School

Construction of 1 Sanitary block (1Male, 1 Female, 1 Urinal)

Proposed Rehabilitation of 1 unit hand pump

Guintigi-an Elementary Construction of 1 Sanitary

8

Page 9: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

School

Block (2 Male, 2 Female, 1 Urinal)

Construction of one elevated water tank with electric pump

Table 8. This is the construction of toilets in school

Hygiene Promotion Activities

Partner Municipality # of Communities

Communities Catered Status Remarks

IFRC

Tabon-tabon, Barugo, Dagami, San Miguel (La Paz) 3

69

See shelter latrine matrix for complete list of communities per municipality

Ongoing implementation of simplified HP

Facilitation of Hygiene Promotion Sessions continue in Santa Fe, Leyte catered for the facilitation of HP 1-5: A total of 68 individual attended the sessions. For Gender aggregation 37% of these participants were female and the remaining 63% were male, while for the Age Group 0% of the total participants were Below 16 years old, 66% were 17 to 49 years old, and 34% were above 50 years old.

Spanish Red Cross Tolosa 10

San Roque, Telegrafo, Canmogsay, Doña Brigida, Quilao, Olot, Tanghas Opong, Burak, Cantariwis

Training phase of implementation will commence

See section on PHAST for additional updates.

German Red Cross

Dulag 4Salvacion, Cabacungan, San Rafael, and Rizal

Ongoing implementation

Julita 1 Hindang

Australian Red Cross San Isidro 14

Paril, Crossing, Dajadiot, Hacienda Maria, Linao, San Jose, Capinahan, San Miguel, Daja daku, Banat-I, Basud, Busay, Cabungaan, Bunacan

Initial implementation has not yet resumed

Conducted an Orientation with the CO and Shelter Volunteers with regards to the baseline survey as well as the hygiene promotion to the beneficiaries.

Conducted a Baseline survey at Brgy Omaganhan, Brgy Poblacion and Brgy. Manlawaan, Tabango

9

Page 10: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

American Red Cross

MacArthur, Alang-alang, Tacloban City, Mayorga

23

See shelter latrine matrix for complete list of communities per municipality

Ongoing implementation of HP activities

No report received

Netherlands Red Cross

Isabel 8

Antipolo, Bantigue, San Francisco, Putting Bato, Monte Alegre, Can-andan, Cangag, Consolacion

Implementation ongoing

No update for this activity received for this week.

Merida 8

Calunasan, Cambalong, Mat-e, Mahalit, Tubod, San Jose, Lundag, Can-unzo

Table 9. Hygiene promotion sessions targeting the core shelter beneficiaries continue to be facilitated throughout the province. The table below shows the status of the implementation per partner.

Participatory Hygiene and Sanitation Transformation (PHAST) Activities

Partner Municipality # of Communities Communities Catered Status

IFRC Barugo 6Balire (Dropped), Bulod, Cabarasan, Hiagsam, Hinugayan, Pitogo

Facilitation of Participatory Hygiene and Sanitation Transformation (PHAST) continue in five (5) communities of Barugo, Leyte catered for the facilitation of Step 6: Planning for Monitoring and Evaluation; Activity 1: (Preparing to check our Progress).A total of 15 individual attended the sessions. For Gender aggregation 93% of these participants were female and the remaining 7% were male, while for the Age Group 0% of the total participants were Below 16 years old, 47% were 17 to 49 years old, and 53% were above 50 years old.

Spanish Red Cross Tolosa 3 Imelda, San Vicente, Capangihan

First batch of PHAST training for Community Health Volunteers (CHVs) has been facilitated last November 4-6, 2015. A total of 24 individuals participated in the activity.

PHAST training schedule for 2nd batch will be on November 17, 18 & 19, 2015

PHAST training schedule for 3rd batch will be on November 23, 24, & 25 2015

German Red Cross Dulag 4 Arado, Highway, San Rafael, San Vicente

Ongoing facilitation of Step 2 activities 3 (Investigating community practices) and 4 (How diseases spread) and

10

Page 11: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

hygiene promotion key message 3 (use of safe drinking water and proper food handling). A total of 1,303 participants attended the sessions in the communities covered:o Dulag: 1,089o Julita: 214

Julita 5 Aslum, Calbasag, Dita, Gitabla, Sta. Cruz

Australian Red Cross San Isidro 3 Hacienda Maria, Linao,

San Jose Implementation completed

American Red Cross

MacArthur 9

San Isidro, Burabod,Kiling, Sta Isabel, San Antonio, Lanawan, Danao, Villa Imelda, Oguisan

No report received

Mayorga 5 San Roque, Talisay, Burgos, Union, Wilson

Alang-alang 5Astorga, Hubang, Peñalosa, Santiago, Alsum

Tacloban City 4 83C, 79, Paglaum, Palanog

Netherlands Red Cross

Isabel 8

Can-andan, Cangag, Putting bato, Antipolo, Bantigue, Monte Alegre, San Francisco, Consolacion

Implementation completed. Consolidation of the endline

assessment is ongoing.

Merida 8Calunasan, Cambalong, San Jose, Tubod, Lundag, Mahalit, Mat-e, Caunzo

Table 10. Participatory hygiene and Sanitation Transformation (PHAST) continue to be conducted in various municipalities in the province. Updates on the status of the implementation per partner is indicated in the table above.

Children Hygiene and Sanitation Transformation (CHAST) Activities

Partner Municipality # of Schools Schools Catered Status

American Red Cross

MacArthur 5Lanawan ES, Burabod ES, San Isidro ES, San Antonio ES, Kiling ES

No report received

Mayorga 5 Union ES, Burgos ES, Wilson ES, San Roque ES, Talisay ES

Alang-alang 5Aslum ES, Hubang ES, Sanitiago ES, Astorga ES, Peñalosa ES

Tacloban City 3 Lorenzo Daang ES, Palanog ES, Marasbaras ES

Netherlands Red Cross

Isabel 3 Can-andan ES, Consolacion ES, Puting Bato ES

MoA signing has been completed during the Stakeholders’ orientation.

Orientation of stakeholders has been completed in both Isabel and Merida.

School-based WASH training for Merida 3 Calunasan ES, Cambalong ES

Can-unzo ES

11

Page 12: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

WASH committee will be conducted on 16-19 November 2015. Preparations are ongoing.

Spanish Red Cross Tolosa 8

Canmogsay ES, Capangihan ES, Opong ES, San Roque ES, San Vicente ES , Tanghas ES, DZR ES, Malbog ES

Training for School-based WASH for adult members (Principal, PTAs, & Teachers) of the WASH committee is scheduled to be conducted on November 13-14, 2015 in JICA (located in barangay Poblacion, Tolosa).

Communication letters have already been disseminated and a total of 31 participants are expected to attend.

CHAST training for 2nd batch (1st

batch of students) November 19 & 20

CHAST training for 3rd batch (2nd

batch of students) November 26 & 27

German Red Cross

Dulag 18

Alegre ES, Arado ES, Barbo ES, Batug ES, Camitoc ES, Cabacungan ES, Cabacungan NHS, Cabatoan ES, Cabatoan NHS, Francisco Dumaguit Memorial ES, Luan ES, Rawis ES, Rizal ES, Rizal NHS, Salvacion ES, San Rafael ES, Tabu ES, Victory ES

Ongoing assessment on target schools. (Anibong, Batug, Bongdo, Cabacungan, Cuya-e, Dita, Hindang, Inawangan, Sta. Cruz, Salvacion, and Villa Hermosa.

Ongoing scheduling of stakeholders on target schools.

Ongoing recruitment of School-Based WatSan Committee on target schools. See table below for the status of the recruitment.

Drafting of activity proposal for training of WatSan Committee.

Revising of work plan for CHAST Activity.

Julita 12

Alegria ES, Alegria NHS, Anibong ES, Bongdo ES, Calbasag ES, Cuya-e ES, Dita ES, Hindang ES, Inawangan PS, San Andres ES, Sto Niño ES, Villa Hermosa ES

Australian Red Cross

Tabango 1Tabango North Central School The team conducted an orientation

with the stakeholders at the following schools:

a. Banat-I Elementary Schoolb. Hugpa Elementary Schoolc. Uson Elementary Schoold. Petrolio Elementary Schoole. Dulao Elementary School

San Isidro 2Hugpa ES, Banat-I ES

Calubian 3Petrolio ES, Uson ES, Dulao ES

IFRC

Barugo 5 Abango ES, Amahit ES, Bukid ES, Can-isak ES, Pikas ES

Implementation completed

Babatngon 4 Bagong Silang ES, Victory ES, Taguite ES, Guintigi-an ES

Communication letters regarding the upcoming orientation of stakeholders have been disseminated to the DepEd Division office and the school heads of the target schools

Total 0

74 Schools under DepEd Leyte Division

3 Schools under DepEd Tacloban City Division

12

Page 13: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

Table 11. Implementation of school-based WASH in the province has already started. With the scaling up of interventions, preliminary activities have already started for the initiation of the implementation. The table above shows the schools targeted.

Partner Municipality Name of Barangay School No. of WatSan

Committee Members

German Red Cross

Julita

Cuya-e Cuya-e Elem. School Ongoing recruitmentHindang Hindang Elem. School 10

Inawangan Inawangan Primary School

5

Anibong Anibong Elem. School 9

Villa Hermosa Villa Hermosa Primary School

Ongoing recruitment

Bongdo Bongdo Elem. School 10Sta. Cruz Sta. Cruz Elem. School Ongoing recruitmentDita Dita Elem. School 10

DulagCabacungan

Cabacungan Elem. School Ongoing recruitmentCabacungan National High School

Ongoing recruitment

Salvacion Salvacion Elem. School Ongoing recruitmentBatug Batug Elem. School Ongoing recruitment

Table 12. As mentioned in the table above, recruitment of the members of the WASH committee in the schools covered

by the PRC-GRC is ongoing. Status of the target schools for the 2015 implementation of school-based WASH are as follows

13

Page 14: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

PRC In Partnership With Different National

SocietiesLivelihood Activities as November 13, 2015

PRC – American Red Cross

Phase II- Rolled out Retrospective Examination for 1st Batch STED scholars.- Followed-up and collected requirements of 2nd Batch STED scholars.

Phase III- Conducted 4-day training on Entrepreneurship and Management. 3 associations joined

the training with a total of 50 participants.

Agriculture Activity:- Completed Rice production & management training in Mac Arthur. A total of 38

beneficiaries participated in the training.

PRC – Australian Red Cross Phase I

- Impact assessments: House to house survey done. To date, team is now inputting data to the ODK.

Phase II Skills Training

- On-going hands-on training on community-based food processing at San Isidro and silk-screen printing at Calubian.

- Interviewed and identified additional beneficiaries for the training on motorcycle servicing at Brgy. Gimarco.

Enterprise Development- Meeting with the beneficiaries at Brgy. Inangatan for their proposals.- 5 proposals were approved by the PARC (Project Appraisals and Review

Committee) at Calubian.

Phase III- Coordinated with the LGU for a site visit at Brgy. Villanueva, Calubian. Visited

one site at Brgy. Inangatan, Tabango.- Meeting with beneficiaries at Brgy. Abanilla, Calubian regarding phase 3

14

Page 15: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

implementation and next week the group will have an orientation.

Other Activities- The team together with some of the trainees went to Tacloban to celebrate the

2nd Haiyan commemoration at Robinsons Place. They were able to showcase their outputs of what they have learned in the training like atchara, alimango, cinnamon bread, salvaro, vegetable products, peanut butter, peanuts and ketchup.

PRC – German Red Cross

Phase I (Short Term Trainings)- Continued focus group discussion with beneficiaries to ask updates of their livelihood

activity. This is to finalize the potential list of benficiaries for the short term livelihood trainings.

- Completed short term livelihood training Basic Business Skills for Association in Villahermosa, Julita

- Conducted orientation for the upcoming short term livelihood trainings Basic Business Skills and Root Crop-Based Food Processing, Bongdo of Julita and brgy,Tigabao, Dulag

- Follow up coordination in Department of Trade and Industry (DTI), Office of the Provincial Agriculturist (OPA), Philippine Coconut Authority (PCA) for the short term livelihood trainings, and Department of Education for school gardening.

Other Activities- Took part in the Inauguration of Cabatoan Health Center and TESDA Carpentry and

Masonry NCII training Graduation Ceremonies- Meeting with the Inclusion Adviser of Handicap International for the upcoming kick off

activity for Persons with Disabilities.

PRC – International Federation of Red

Cross & Red Crescent Societies

Phase II: Weekly monitoring for sholars- All of the scholars are done with their OJT. There are still 9 scholars who are

neither done with their OJT nor employed. This is due to: 1. Financial constraints as they used their allowance for their family2. Problem in the partner companies like students were there but not doing

anything so they opted to go home and not continue their OJT3. Pregnant

- Employement coaching done facilitated by PESO. PESO informed the students that they are allowed to visit the office to seek validation in their resume.

- There are a total of 56 scholars who are currently employed in different areas of Tacloban. Up to date, students are complying with their needed requirements for job application

Phase III: 1st batch of proposals

- Procurement of construction materials done. Materials have been delivered to the construction site. Repair of storage has started.

15

Page 16: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

2nd batch of proposals- 3 proposals have been approved by NHQ as per advice. Associations are currently

working on the attachements needed, signatories from LGU and endorsement letter from Mayor.

- Trainings and procurement of materials will be scheduled next week. 3rd batch of proposals

- 5 proposals have been reviewed and validated by the LGU. Revisions were made with the assistance of relative agencies.

- Submission of 3rd batch proposals will be scheduled next week.

PRC – International Federation of Red

Cross & Red Crescent Societies -

Babatngon

Phase I- Finalization of monitoring report.

Phase II- To avoid increase numbers of trained but unemployed scholars, team conducted FGD to

the possible barangays that will be covered for Phase II. Agenda were:1. Mapped out their market connections in Tacloban2. Possible courses that are marketable3. Possible challenges in employing scholars

- Team discussed the possible program with the focal person of Health and Education. He said that they have a lot of NCII passers in Babatngon that are still unemployed. He suggested that team will talk to possible companies that are in need of employers.

- Team has identified 31 possible youth for interview and validation.

Phase III- Proposal preparation in Barangay Planza. Review and validation of proposal with

relative LGU partners will be scheduled next week.

PRC – Netherlands Red Cross Promoting Composting and Natural Farming System in Backyard Gardening

- A total of 17 weeks has been used for the training. There will be one week of training before the graduation. Below shows the attendance of participants per week. Attendance of participants was an issue in the 1st batch and one factor that they saw is the age and willingness thus the team intervene through focus group discussion and included some factors like age and willingness as one of the criteria selection. As per observation, attendance has improved.

16

Page 17: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

Sloping Agricultural Land Technology- In Puting Bato, Isabel, beneficiaries have started to harvest and earned money from

pechay, mongo beans and okra. Constant monitoring has been done for the update and status of the activity.

Farmers Business School- Last November 10, 2015, 25 beneficiaries celebrated the culmination ceremony of the

Farmers Business School in Merida. They were awarded with certificates.

PRC – Spanish Red Cross Phase I: Micro Enterprise Development

- A request for quotation is needed for the professional fees of the trainers. UP has already filled-up the quotation form but St. Pauls is still waiting for the logical framework of the micro-enterprise development.

- Monitored the 420 livelihood beneficiaries. This is to check the status of their livelihood and to update the Phase I masterlist. Results will be shared in the next report.

Phase II: Skills Training

- Up to date, 24 scholars are already having their OJTs. 5 F&B scholars have an assignment already but will start on Nov. 16, 2015. 2 housekeeping scholars started having their OJT at Asia Stars Hotel while 1 scholar did not continue due to family problems. Team will discuss the situation with CWMFI and will suggest that the scholar will be accommodated at the hotel in Tolosa

- Employment coaching was held last November 10, 2015. 29 scholars attended, one scholar was not able to attend due to some family problem.

Enterprise Development- Will meet with the associations to explain the status of the program. Minutes of

the meeting will be shared in the next report.

Advocacy on Illegal Fishing and Overfishing - The following are the proposed activities for the advocacy:

1. Documentary screening and information dissemination in the 8 barangays of

17

Page 18: Summary of WBR as of November 16, 2015

PHILIPPINE RED CROSSHaiyan Operations Leyte

Leyte Chapter

SUMMARY OF COMPLETIONAs of November 16, 2015

Tolosa.2. Different contests like; Jingle making, slogan, mural and story writing will be

held which will involve the different schools from elementary to college.3. Information Dissemination through radio program.4. Distribution of IEC Materials

- A stakeholders’ meeting will be held to discuss the appropriateness of the different activities for the advocacy. The tentative schedule is on the 3rd week of November.

Other Activities:- The BRC members from the 15 barangays were invited for a meeting to share the

updates of the different projects in Tolosa. A self-evaluation was conducted for the BRC members to evaluate their performance and also for PRC to know the needs of the BRC.

Prepared by:

BRYAN SOLEDADReporting and Monitoring Officer

Noted by:

LEO HANIFF C. KOField Operation Head

18