State of Kuwait Ministry of Defence Military Engineering Projects Project : Ali Al-Sabah Military Academy Transmittal No. : To : Gulf Consult Rev. No. : Contract No. : 1412812 Date : Contractor : O&G Engineering W.L.L. Company WE ARE SENDING SUBMITTED FOR SUBMITTAL STATUS CODE SD- Shop Drawing Approval A - Approved MD- Manufacturer’s Data Information B – Approved as Noted SM- Sample B / R – Revise and Resubmit GT- Guarantee / Warranties C - Rejected CT- Certificates D – For Information / Others TT - Test OT- Others Item No. Dwgs, Specs, BOQ Ref. Description Copies Action We certify that the materials submitted herewith have been reviewed and are in conformance with the contract drawings and specifications except as otherwise stated Contractor’s Representative : Yasser Al Aazab Al Basyoni Received By: Date : 29 April 2015 Date Review Comments : Action by : Gulf Consult Rep.:______________ Date : ________________________ Gulf Consult: RE : ____________________ Date : ___________________ Received By: Contractor :______________ Date : ___________________ Distribution : Owner’s Representative Gulf Consult Contractor Submittal Form

Upload: fred-anthony-a-uera

Post on 16-Dec-2015

6 views

Category:

Documents


2 download

DESCRIPTION

SF

TRANSCRIPT

  • State of Kuwait Ministry of Defence

    Military Engineering Projects

    Project : Ali Al-Sabah Military Academy Transmittal No. : To : Gulf Consult Rev. No. :

    Contract No. : 1412812 Date :

    Contractor : O&G Engineering W.L.L. Company

    WE ARE SENDING SUBMITTED FOR SUBMITTAL STATUS CODE

    SD- Shop Drawing Approval A - Approved

    MD- Manufacturers Data Information B Approved as Noted

    SM- Sample B / R Revise and Resubmit

    GT- Guarantee / Warranties C - Rejected

    CT- Certificates D For Information / Others

    TT - Test

    OT- Others

    Item No.

    Dwgs, Specs, BOQ Ref.

    Description Copies Action

    We certify that the materials submitted herewith have been reviewed and are in conformance with the contract drawings and specifications except as otherwise stated

    Contractors Representative : Yasser Al Aazab Al Basyoni

    Received By:

    Date : 29 April 2015 Date

    Review Comments :

    Action by :

    Gulf Consult Rep.:______________

    Date : ________________________

    Gulf Consult:

    RE : ____________________

    Date : ___________________

    Received By:

    Contractor :______________

    Date : ___________________

    Distribution : Owners Representative Gulf Consult Contractor