subject : reserve provision by non-spinning …
TRANSCRIPT
RCP PAPER NO. : EMC/RCP/120/2021/CP86
SUBJECT : RESERVE PROVISION BY NON-SPINNING GENERATION
FACILITIES
FOR : DECISION
PREPARED BY : JOASH SENG
ECONOMIST
REVIEWED BY : POA TIONG SIAW
SVP, MARKET ADMINISTRATION
DATE OF MEETING : 27 JANUARY 2021
_________________________________________________________________________
Executive Summary
This paper proposes to enhance the modelling of primary and contingency reserve
capabilities of generation registered facilities (GRF). The enhancements will better
represent the reserve capabilities of facilities such as open cycle gas turbine (OCGT) and
battery energy storage systems (BESS) that can meet the reserve performance standards
from a non-spinning start-state. Such facilities can then be scheduled to provide reserve
while being scheduled for energy levels below LowLoad.
The proposal would allow more resources to participate and compete in the reserve
markets, thereby enhancing system security and market efficiency. To mitigate potential
risks to the system security, safeguards are suggested by the PSO to limit the quantity of
contingency reserve that can be scheduled from non-spinning generation facilities.
The EMC recommends for the RCP to:
1. Support the proposal to allow primary and contingency reserves to be provided
from generation facilities with loading below LowLoad point;
2. Support the proposal to subject reserve scheduling of non-spinning generators to
the allowable limit, with an initial value of 100MW for contingency reserve; and
3. Task the EMC to work with the PSO to assess the impacts and costs of
implementation options, and draft relevant modifications to the Market Rules in
order for reserve-capable non-spinning generation facilities to provide primary and
contingency reserves in the SWEM.
The RCP discussed the proposal at its 120th meeting. Upon deliberation, the RCP considered that deeper technical investigation is needed to: (i) ascertain the usefulness of the proposal, as there is uncertainty on whether generators/storage facilities can operate below minimum stable load in a viable manner; and (ii) determine the most appropriate
approach to modify the reserve envelop, given the impact and costs of different implementation options.
The RCP by majority vote supported, in-principle, the proposal to allow primary and contingency reserves to be provided from generation facilities with loading below LowLoad point; and tasked the Technical Working Group (TWG) to conduct the said technical investigation and make its recommendations to the RCP.
EMC/RCP/120/2021/CP86 3
1. Introduction
This paper discusses a proposal raised by Senoko Energy at the 2019/20 mid-year workplan
review exercise. Senoko Energy proposed to allow generation assets that can meet reserve
performance standard from an offline start-state (e.g., open cycle gas turbines), to provide
ancillary services without being scheduled for energy.
2. Background
2.1. Ancillary Services in the SWEM
In the Singapore Wholesale Electricity Market (SWEM), reserves and regulation products are
real-time ancillary services required for the stable functioning of the power system when
contingency events and disturbances occur. These products are largely provided by
Generation Registered Facilities (GRF) that are synchronised to the grid and able to respond
to system frequency changes. In the SWEM, reserves are classified into ‘primary’ and
‘contingency’ reserves. Reserve providers scheduled for these two classes will have to
respond within 9 seconds and 10 minutes respectively.
To ensure that dispatch schedules are feasible, the Market Clearing Engine (MCE) models
reserves and regulation constraints faced by GRFs that provide energy and ancillary services
in the SWEM. Doing so reflects the physical capabilities of the GRFs and enables the MCE to
produce security-constrained economic dispatch schedules for the power system.
2.2. Modelling of Reserve in the SWEM
Reserves can be provided by GRFs, and Load Registered Facilities (LRF) under the
interruptible load scheme.
Every LRF providing reserve is subject to a facility-specific maximum reserve capacity
constraint, which limits the amount of reserve it can be scheduled for. The LRF’s maximum
reserve capacity is verified at the facility registration stage through site tests and reports to
ascertain that LRF has met the performance standards as stipulated in the System Operating
Manual and Transmission Code.
GRFs registered to provide reserves are subject to the following main constraints:
(a) Maximum Reserve Capacity to limit the scheduled reserve to the maximum amount of
reserve that a GRF has offered;
(b) Reserve Generation Max Constraint to limit a GRF’s aggregate scheduled energy,
reserve and regulation to its maximum generation capacity;
(c) Reserve Generation Segments, where reserve provision capability differs depending
on the generation loading level of the GRF. This capability is depicted as 3 reserve
generation line segments spanning from the LowLoad 1 point to
ReserveGenerationMax2 point; and
1 LowLoad is the minimum loading level at which a GRF can provide reserve – this is usually set at the Minimum Stable Load (MSL) registered for the generation facility. 2 ReserveGenerationMax is the maximum combined generation and reserve that can be provided by a GRF.
EMC/RCP/120/2021/CP86 4
(d) Reserve Proportion Constraint such that the amount of scheduled reserve cannot
exceed a proportion of the scheduled energy3.
These constraints are depicted in Figure 1 below, where (a) is represented by the black
horizontal line segment, (b) is represented by the blue line segment, (c) is represented by the
red line segments, and (d) is represented by an orange line segment that starts from the graph
origin. These line segments ‘envelop’ the reserve solution space for a GRF, forming a reserve
(capability) envelope for the GRF.
Figure 1: Existing Modelling of Contingency Reserve Envelope
In addition, considering that typically GRFs operating below LowLoad will be unable to
respond within 9 seconds to provide primary reserve, an additional constraint4 is applied to
disallow a GRF, whose energy scheduled is below LowLoad, from being scheduled for primary
reserve. As a result, the part of the solution space where energy scheduled is below LowLoad
is considered infeasible and removed, as depicted in Figure 2.
3 In addition to Reserve Proportion Constraint, a less restricting constraint (Reserve Proportion Ramp Constraint) would also limit the provision of contingency reserve to a proportion of the ExpectedStartGeneration and/or energy scheduled. This effectively restrict any contingency reserve provision from units which do not provide energy (i.e. ExpectedStartGeneation is 0) during normal times. 4 Mixed Integer Program based reserve constraint.
EMC/RCP/120/2021/CP86 5
Figure 2: Existing Modelling of Primary Reserve Envelope
3. Analysis
3.1. Reserve Capability Differ for Non-spinning Generation Facilities
The proposal centres around the reserve capability of generation facilities that can provide
reserve from an offline start-state. Specifically, generation facilities like OCGTs and BESSs
have relatively higher/more flexible ramp rates. Some OCGTs claim to be able to ramp up
from zero to a significant proportion of its load within a time norm of 8-12 minutes5, while some
BESSs were reported to be able to ramp up to full power within 0.2 seconds6.
OCGTs, due to its low fuel efficiency and therefore higher variable cost, are usually positioned
as peaking capacity that supply energy for a few peak periods during the year. In other words,
OCGTs are not expected to provide energy in normal times. BESSs, being duration-limited
rapid response resources, are also not best utilised when primarily scheduled for providing
energy continuously. Instead, they are better suited to provide load-following/frequency
regulation and fast reserve services. While OCGTs and BESSs are unlikely to be scheduled
5 Some OCGT models were reported to be able to ramp up to full load (260 MW) within 12 minutes. Some GT models from Wartsila (50SG, 34SG) and GE (LMS 100) were noted to have such capabilities. 6 Source: Batteries: Beyond The Spin; Everoze, et. al., (2017) - Queen’s University Belfast (QUB) research at Kilroot Power Station, Northern Ireland demonstrated that with the right controls in place, BESS can ramp to fully power in less than 200ms. Source: Hornsdale Power Reserve: Year 1 Technical and Market Impact Case Study; Aurecon (2018) - Hornsdale Power Reserve (HPR), the world’s largest lithium-ion battery ESS was recorded to be able to discharge up to 100MW in less than 150ms. Under the System Integrity Protection Scheme (SIPS), the HPR is intended to provide a premium service in Fast Frequency Response (FFR) with fast response time of approx. 100ms. During FFR modelling, the HPR’s modelled response based on lab tested characteristics is up to 100 MW with a response time of 100ms.
EMC/RCP/120/2021/CP86 6
for energy in most periods, they are still able to provide reserves from an offline start-state due
to their ‘fast ramping’ capability.
Offline vs. Non-Spinning Start State
Discussions with the PSO suggest that calling on offline(/non-synchronised) generators to
provide reserves pose considerable risk to the power system, in part due to the need for plant
start-up. Generators should be minimally synchronised to the grid and generating to be eligible
for reserves provision. While BESSs may be connected/synchronised to the grid at 0MW
output, this is unlikely the case for OCGTs that need to be generating above 0MW in order to
be synchronised and ready to provide contingency reserve.
For avoidance of doubt, the PSO refers to instances where generators are synchronised to
the grid at loading levels below LowLoad(/MSL) as “non-spinning”.7 The PSO is of the view
that it is valuable to extend reserve provision eligibility to reserve capable non-spinning
generators. Performance testing can be conducted to ascertain the lowest output level (0MW
inclusive) that non-spinning generators are able to provide reserves reliably. Eligibility of offline
generators to provide reserve can be revisited when there is adequate track record to assure
the system operator that they can meet reserve performance standards.
Restrictive Parameters for Reserve Capable Non-Spinning Assets
Currently, all GRFs are subject to the same set of parameters determining their reserve
envelopes. As illustrated in Figure 1, GRFs are subject to a Reserve Proportion Constraint,
where the amount of scheduled reserve cannot exceed a proportion of the scheduled energy.
This Reserve Proportion Constraint implies that GRFs must be scheduled for energy (and
consequently be synchronised and generating during the dispatch period) in order to be
scheduled for contingency reserve. While the current formulation ensures that conventional
GRFs, e.g., combined cycle gas turbines (CCGT), can provide scheduled reserves in a stable
and sustained manner, it is not reflective of the ability of certain generation facilities to ramp
up steadily from a non-spinning state (i.e., not scheduled for energy) when called upon. The
current model, when applied to such facilities, places an unnecessary constraint on the
feasible solution space. As a result, in meeting the reserve requirements, the MCE may have
to: (a) schedule less efficient units to generate; and (b) restrain the generation level of more
efficient units. This can result in less than optimal dispatch schedules.
The proposal seeks to distinguish reserve-capable non-spinning generation facilities
from conventional GRF reserve providers, so that the former can be scheduled for
contingency reserves without being concurrently scheduled for energy levels at/above
LowLoad. Doing so can potentially improve the utilisation of spinning GRFs, since a
proportion of the reserve requirement can be met by non-spinning generation facilities.
7 This is opposed to ‘spinning’ generators that are generators synchronised to the grid at load levels at or above MSL.
EMC/RCP/120/2021/CP86 7
3.2. Modifications to Reserve Envelope for Reserve-capable Non-spinning Generation Facilities
In order for non-spinning generation facilities to provide contingency reserve, the following
modifications to the reserve envelope are required to represent such generation facilities:
(a) Introduce additional parameter to represent generation facilities’ reserve
capability below LowLoad level. This parameter (i.e., non-spin reserve point)
should indicate the maximum MW quantity a unit can ramp up to from its lowest reserve
capable “non-spinning” loading level within 10 minutes. It should be determined based
on actual testing results approved by the PSO. For BESS, the non-spin reserve point
could potentially be set at 0MW (as represented by the y-intercept point highlighted in
green in Figure 3), subject to future testing results from ongoing BESS testbeds.
By connecting the non-spin reserve point and LowLoad reserve point, a new reserve
generation segment (represented by ‘line segment 4’) is created to limit the solution
space for reserve-capable non-spinning GRFs whose energy schedule are below
LowLoad. For GRFs that are not capable of fast ramping from a non-spinning start
state, its non-spin reserve point should be set at 0 or invalidated.
(b) Remove Reserve Proportion Constraint and Reserve Proportion Ramp
Constraint. The next step is to remove these two constraints for GRFs that are
approved to provide non-spinning reserves. This would allow reserve-capable non-
spinning GRFs to be scheduled for contingency reserve from an energy level below
the conventional LowLoad point for conventional generators (i.e., Minimum Stable
Load).
(c) Convexity Test for Reserve Envelope. Tests to validate the convexity of the reserve
envelope will still apply as part of the pre-processing of the GRF’s standing capability
data, to ensure the MCE receives inputs that will produce valid results. With the
introduction of the new parameter: “non-spin reserve point”, the convexity test should
be conducted based on the new solution space which consists of four segments (as
illustrated in Figure 3).
The proposed modifications produce a better representation of the reserve capability of non-
spinning generation facilities that are capable of meeting reserve performance standards and
provide more assurance from a security standpoint.
EMC/RCP/120/2021/CP86 8
Figure 3: Sample Modified Contingency Reserve Envelope
3.3. Other Considerations
EMC also assessed the proposal against ongoing developments in the SWEM and the
associated risks and benefits of enabling fast start units to provide non-spinning reserves.
(a) Risks of Non-spinning Resources Providing Reserves. As LRFs are not ‘steel in
the ground’ and not on Automatic Governor Control, the PSO has instituted maximum
allowable limits to safeguard power system reliability. As the performance of non-
spinning reserve providers have not been proven over time, the PSO has thus
suggested an initial limit of 100 MW for contingency reserve scheduled from reserve-
capable non-spinning GRFs. The allowable limit for non-spinning reserves can be
subject to review. (Please refer to Annex A for a comparison with non-spinning reserve
treatment in the PJM).
(b) Applicability to Provision of Primary Reserve. The EMC notes that the proposal
elaborated through sections 3.1 and 3.2 was to allow for contingency reserve to be
scheduled without energy. However, we assessed that the proposed remodelling could
also apply to primary reserve provision by BESSs, which are able to respond within 9
seconds with their rapid response capability.
With Singapore’s national deployment target of 200 MW of BESS beyond 2025,
several BESS projects are slated for commissioning by 2021, with the intention of
providing ancillary services in the SWEM. The current reserve constraints modelled for
GRFs are not applicable to BESS units and could hinder their provision of valuable
services to the SWEM.
EMC proposes for the modified reserve envelope in section 3.2 apply to primary
reserve for primary reserve-capable non-spinning generation facilities (e.g., BESS).
Like in the case of contingency reserve, such generation facilities that wish to provide
primary reserve from a non-spinning start-state would need to undergo capability
EMC/RCP/120/2021/CP86 9
testing with the PSO to ascertain the non-spin reserve point. For such resources, the
solution space for primary reserve should be the similar to the one illustrated in Figure
3 instead of that in Figure 2.
4. Consultation
The concept paper was published for consultation on 15 October 2020. Comments were
received from 5 stakeholders, namely Senoko, Sembcorp, PacificLight, Keppel, and the Power
System Operator.
Comments
from Comments EMC’s Response
Senoko
We are fully supportive of this proposal as it not only
better utilizes OCGTs and BESSs, it also frees up
‘spinning capacity’ which could flow into the energy
market. Inclusion of non-spinning GRFs in the reserve
market might not only result in units generating at a
higher efficiency level (less instances of running at part
load) but it also enhances system security in the
SWEM.
While we understand PSO’s concerns on LRFs
providing reserves beyond 30% of the total system
requirement, non-spinning GRFs (I.E., OCGTs) have
consistently proven over time of its ability to ramp
up to levels above 100MW in under 10 minutes.
Hence, we disagree with the proposed 100MW
aggregate cap on non-spinning GRFs.
As a suggestion to alleviate reliability concerns, PSO
could conduct periodic ‘reserve tests’ on these
non-spinning GRFs and place unit specific caps or
ratings based on actual test results.
EMC notes Senoko’s comments.
Concerning Senoko’s suggestions,
unannounced periodic reserve tests
could be helpful to review and update
the reserve provider group and
specific cap that a non-spinning GRF
is subject to.
For avoidance of doubt, the PSO
clarified that non-spinning GRFs are
synchronised (see sect 3.1), and
hence not synonymous with GRFs
that are offline.
Sembcorp
Sembcorp is supportive of the proposal to allow
primary and contingency reserves to be provided from
reserve-capable non-spinning generation facilities as
OCGTs and BESSs.
The rapid injection of power by BESSs in the system
would help provide initial stabilisation of the grid as
other technologies such as OCGTs and CCGTs ramp
up and dispatch power to recover grid frequency back
to stable levels prevent sector or system-wide
blackouts. To ensure system security, EMC may
consider modelling the aggregate primary and
contingency reserve capacity required by each
form of technology on a time scale. The intent is to
determine the required amount of reserve from BESSs
and OCGT needed to maintain the system while the
larger capacity of reserves providers can ramp up to
restabilise the system in a sustainable manner.
Modelling primary/contingency
reserve capabilities and setting the
requirements for each reserve class
falls out of the EMC’s purview. We
understand that the current
primary/contingency reserve classes
and requirements are designed
based on the current reserve
operation strategy of the PSO; and
that the power system’s reserve
capability is technology neutral. EMA
will share more insights on modelling
implications from the EMA-ESS
testbeds and Industry Working Group
2 workstream.
EMC/RCP/120/2021/CP86 10
By establishing the aggregate capacity required from
each technology, EMC could set limitations on the
amount of reserve provided by different
technologies by creating new tiers (e.g. fast
response reserve) to ensure that the system has a
balanced supply of different reserve products to amply
support reserve events and prevent oversupply and
dependence from one particular technology.
On top of the participation in the reserves market,
additional incentive payments to BESSs for the
provision for fast response and flexible reserve
options would encourage higher participation from
existing distributed energy storage as well as the
attraction of new investments on ESS.
The prospect of Fast Frequency
Response product(s) is currently
being studied under EMA’s
“Consultancy Studies to Develop
Technical and Market Based
Solutions to Address Intermittency at
Higher Solar PV Penetrations”. EMC
will work with PSO following the
conclusion of the study to effect the
recommended changes in the
market.
Notwithstanding the above, EMC’s
view is that reserve classes,
requirements and performance
standards, should be designed based
on system need rather than targeting
certain technology.
All BESS systems should not be allowed to charge
back immediately after each event of reserve
provision. This would ensure that grid stability would
be not be affected. Battery energy storage systems at
lower SOC states have a very low impedance
compared to an LRF or a GRF asset. High
concentration of BESS systems drawing power from the
grid at >3C rate might create a nodal voltage sag effect.
The PSO could explore imposing limits on the charge curve of the reserve providing BESSs. This would have to be studied further.
Unlike OCGTs and CCGTs, BESSs cannot offer both
reserve and regulation simultaneously as the
activation for discharge may conflict with an AGC
signal to lower frequency.
In order to have BESSs as a reliable source of
reserve, BESSs have to be on 100% standby and
readily available to be activated and hence will not
be able to offer other grid ancillary services. In
addition, the provision of multiple services will hinder
the storage of renewable energy into batteries. More
accurate stand by times and scheduling are necessary
for using BESS for multiple gird disturbances.
EMC’s view is that BESS can offer
and be scheduled for reserve and
regulation simultaneously. During
actual operations, the BESS
scheduled for reserve and/or
regulation will respond to the AGC
depending on system needs.
How BESS should be apportioned
and timed for different services is the
prerogative of the BESS owner and
his operating strategy. A BESS MP
should offer into the market according
to the unit’s practical capabilities.
Gate closure exemptions could be
considered so that BESS MPs can
submit timely offer variations to
reflect a unit’s actual capability.
PacificLight
Consistent with the principles the NEMS operates
under, all reserve providers should stand an equal
chance of being activated, up to the volume of their
scheduled quantity.
When OCGTs are called upon to provide
contingency reserve, they will be dispatched at
energy prices that they are not willing to offer in the
first place (otherwise they would have been dispatched
This proposal’s intent is to open
opportunities for non-spinning GRFs
to offer and compete in the reserves
market. MPs have full autonomy over
their reserve offer and would have to
assess for themselves, the reserve
offer price needed to recover start-up
cost, energy cost, and other possible
expenses to be on reserve stand-by.
EMC/RCP/120/2021/CP86 11
and are “spinning”) and it is at odd with how the energy
prices are cleared. Factor in the potential losses in
margin (if activated) and the high heat rate of OCGT
and the high amount of carbon emissions, it is not
justifiable to assume that their entrance in the reserve
market improves market efficiency. Increased cost
effectiveness of OCGT’s reserve provisions is therefore
implausible. As such, it would be more cost effective for
the online units to continue providing reserves.
The MCE in-turn decides whether to
schedule reserve from such units
based on its reserve offer price.
Furthermore, we would seek clarification on factors
the PSO will consider in choosing which GRF to
activate, given that now there are two groups of
providers, the online and offline units. Considering the
lead time required to start up the unit, it might not be
efficient to dispatch the offline OCGT for
contingency, especially if the scheduled reserve
volume is small and can be easily met by the online
units. If the chances of being activated is not equal
across providers, this creates an imbalanced playing
field.
We also would like to highlight that BESS should
undergo the frequency injection test, like the one
that Gencos underwent, to determine the primary
reserve envelope.
Lastly, please also advise how OCGT and BESS will
be classified and assessed for the Reserve Provider
Group.
Priority ranking of all generation
registered facilities (computed using
offer prices for energy, regulation and
reserve of all Generation Licensees)
shall be used by the PSO to call on
contingency reserve. As offline units
may require a longer “warm-up” time,
the PSO discussed possibilities to
activate offline units ahead of online
units if scheduled for contingency
reserve.
EMC agrees that BESS should be
subject to the same testing
requirements as current reserve
providers to determine the reserve
envelope. Non-spinning generation
facilities can adhere to the current
standing procedures for defining
reserve provider group for GRFs and
LRFs. For initial verification testing,
non-spinning GRFs could be subject
to unannounced reserve test(s)
across a specified period to mimic
real-life activation scenarios.
Keppel
Keppel is of the view that the providers of spinning
reserves are more reliable than non-spinning reserves
as the former does not suffer from start-up issues.
Replacing a portion of spinning reserves with non-
spinning reserves without considering the unique risks
from different types of providers will reduce the
reliability of the reserve class leading to reduced system
security. Furthermore, there can be additional
concentration risk, where a single non-spinning reserve
provider dispatched a relatively large reserve fails to
deliver, leading to a large shortfall. Keppel does not
support allowing contingency reserves to be provided
by non-spinning generation facilities.
Non-spinning reserves are currently procured as a
distinct market reserve product in other jurisdictions (i.e.
CAISO, PJM). Can EMC perform a study if such a
reserve product could be beneficial in SWEM?
The reliability of non-spinning GRFs
for providing contingency reserves
should be assessed using the same
performance test procedures PSO
administers for other GRFs.
Performance risks of non-spinning
GRFs should have been accounted
for by the PSO, before determining
each GRF’s eligibility, reserve
capacity and reserve effectiveness.
We agree with Keppel that there are
additional risks involved with non-
spinning reserves compared with
online spinning reserves. An
allowable limit on reserves scheduled
from non-spinning units, subject to
regular review, can further safeguard
the system.
EMC/RCP/120/2021/CP86 12
Keppel has no objection for Primary Reserves to be
provided by BESS should they meet the reserve
capability standards.
A recent study on real-time reserves
was concluded in 2017 and
recommended that 2 classes of
reserves, instead of 3, was sufficient
to meet the risk requirements of the
SWEM. The recency of the study and
limited non-spinning GRFs in the
market may not justify a detailed
assessment of a separate non-
spinning reserve class. We can revisit
this possibility as part of future wider
ancillary services studies.
PSO
Currently, the proposal of non-spinning reserve
(offline unit) is already cater for under AS Contract
which covers Fast Start, Black Start, Reliability Must-
Run services. The current NEMS market is designed
for all online units to provide spinning reserve.
Thus, this proposal is basically to allow registered
facility with very low load point (online and non-zero
energy output) to register and participate in the ancillary
services market under NEMS. The registered facility
can carry out testing to validate their characteristics and
registered in NEMS accordingly as well as complying
with MR/SOM/Transmission Code requirements.
It would also be good for EMC to share how other
jurisdictions treat offline OCGTs that provide
contingency reserve and ESS that provide both
contingency and primary reserve. Our understanding is
other jurisdictions classified it as non-spinning reserve
which in our NEMS designed is under AS contract.
While it is true offline units can be
signed under AS Contracts, this does
not necessarily mean that offline units
should be limited to AS Contracts.
EMC did an initial survey and found
that markets like PJM and CAISO
schedule non-spinning reserves as
part of real-time ancillary services. In
the PJM, both spinning and non-
spinning units that can respond within
10 mins and maintain for the duration
of the event or 30 mins from the start
of the event, can participate in the
primary reserve market as part of the
economic dispatch process.
This is broadly similar to the SWEM’s
contingency reserve product.
In addition, EMC to provide reference on ‘BESSs were
reported to be able to ramp up to full power within 0.1
seconds. On the modelling of the contingency reserve
envelope, EMC should consider shifting the low-load to
zero-load in the reserve envelope (Figure 3), in effect,
reverting back to the original reserve envelope (Figure
1) as the gradient seems identical. The existing facility
registration form can still be used and may not require
any additional testing requirement since it is not
necessary to introduce a new ‘zero-load reserve’
parameter in the model.
EMC agrees that modelling the zero-load reserve point using the current low-load reserve mould could be the more expedient approach. We would study this further during the rule change paper drafting stage.
The limit is necessary as a substantial amount of
contingency reserve could be provided by offline
resources. Suggest a jurisdictions scanning be
conducted.
There is no specific limit placed on
offline units that offer into PJM’s 10-
minute response Primary Reserve
product. We can consider adapting
PJM’s operating reserve
methodology for the treatment of
contingency reserve offers by non-
spinning OCGTs in the SWEM
(Annex A).
EMC/RCP/120/2021/CP86 13
5. Conclusion and Recommendations
The proposed modifications to the primary and contingency reserve modelling would allow for
better representation of non-spinning generation facilities that can meet the reserve
performance standards. Safeguards are also proposed to mitigate potential risk to the system
security that could arise from non-performance of these facilities.
With Singapore on track to meeting its 2 GWp solar target by 2030, solar intermittency during
peak periods and consequently the risk of contingency events is expected to increase.
Enabling reserve-capable non-spinning generation facilities to provide primary and
contingency reserves increases the available sources of reserve to address the increasing
risk. In periods where reserve requirement is moderate, scheduling non-spinning units for
reserve frees up stand-by capacity of conventional generators to supply energy at better heat
rates.
EMC concludes that the proposal to remodel the reserve envelope for GRFs is timely and
should be considered to promote added system security and market efficiency.
EMC recommends for the RCP to:
1. Support the proposal to allow primary and contingency reserves to be provided
from generation facilities with loading below LowLoad point;
2. Support the proposal to subject reserve scheduling of non-spinning generators to
the allowable limit, with an initial value of 100MW for contingency reserve; and
3. Task the EMC to work with PSO to assess the impacts and costs of implementation
options, and draft relevant modifications to the Market Rules in order for reserve-
capable non-spinning generation facilities to provide primary and contingency
reserves in the SWEM.
6. Decision at the 120th RCP Meeting
The concept paper was discussed at the 120th RCP meeting.
Upon deliberation, the RCP considered that deeper technical investigation is needed to: (i) ascertain the usefulness of the proposal, as there is uncertainty on whether generators/storage facilities can operate below minimum stable load in a viable manner; and (ii) determine the most appropriate approach to modify the reserve envelop, given the impact and costs of different implementation options.
The RCP by majority vote supported, in-principle, the proposal to allow primary and contingency reserves to be provided from generation facilities with loading below LowLoad point; and tasked the Technical Working Group (TWG) to conduct the said technical investigation and make its recommendations to the RCP.
The following RCP members supported the proposal:
1. Mr. Soh Yap Choon (Representative of the PSO) 2. Mr. Henry Gan (Representative of EMC) 3. Mr. Calvin Quek (Representative of Generation Licensee) 4. Mr. Cheong Zhen Siong (Representative of Wholesale Electricity Trader) 5. Mr. Sean Chan (Representative of Retail Electricity Licensee) 6. Mr. Terence Ang (Representative of the Retail Electricity Licensee)
EMC/RCP/120/2021/CP86 14
7. Mr. Song Jian En (Representative of the Retail Electricity Licensee) 8. Dr. Toh Mun Heng (Representative of Consumers of Electricity in Singapore) 9. Mr. Fong Yeng Keong (Representative of Consumers of Electricity in Singapore) 10. Ms. Ho Yin Shan (Representative of the Market Support Services Licensee) 11. Mr. Tan Chian Khong (Person experienced in Financial Matters in Singapore)
The following RCP member abstained from voting:
1. Mr. Tony Tan (Representative of Generation Licensee)
EMC/RCP/120/2021/CP86 15
Annex A: Allowable Limits for Non-Spinning Reserve in PJM
Industry consultations suggest that performance risks can be minimised through proper
reserve verification testing. To address concerns over perceived risks from offline and/or non-
spinning reserves, EMC studied a possible adaptation of non-spinning reserve treatment
from the PJM.
In the PJM, spinning and non-spinning units that can respond within 10 minutes can offer into
the real-time Primary Reserve product. PJM’s latest proposal8 is for Primary Reserve demand
to be modelled using an Operating Reserve Demand Curve (ORDC) made of two line
segments: (i) minimum reserve requirement (MRR) quantified as 150% of “N-1” contingency
(~2,100MW) priced at a reserve shortage penalty factor of $2000/MWh; and (ii) a downward
sloping segment modelled using LOLP multiplied by the penalty factor across reserve quantity
procured.
In determining the PJM’s Primary Reserves schedule, spinning units scheduled for the higher
quality Synchronised Reserve9 product (10-minute response) is prioritised for clearing. The
balance can be met by the most economic combination of additional online and offline
reserves. As the Synchronised Reserve’s MRR of 100% of “N-1” contingency (~1,400MW) is
nested within Primary Reserve MRR, spinning reserves will be sufficiently scheduled against
the PJM’s single largest contingency in the Primary Reserve market (provided no reserve
shortage). Hence, there is no numerical allowable limit (e.g., XMW) that non-spinning reserves
can only be scheduled within.
There are similarities in the operating reserve structure between the PJM and the SWEM. The
SWEM’s Primary Reserve requirement is similar to the PJM’s Synchronised Reserve in that
the scheduled Primary Reserve and presence of power system response is set to cover the
loss of the largest on-line generation unit. Correspondingly, the SWEM’s Contingency Reserve
requirement is akin to the PJM’s Primary Reserve where the risk requirement is scaled to
150% of the largest contingency.
Reserve Type Reserve Requirement Response Time
SWEM
Primary Reserve
(Online/BESS)
(100% “N-1” Contingency)
x (Power System
Response),
Up to 9 seconds
Contingency Reserve
(Online/Offline) 150% “N-1” Contingency10 Up to 10 minutes
8 As of July 2020. https://www.aepenergy.com/2020/07/01/ferc-approves-pjm-reserve-pricing-reforms/ 9 Synchronised Reserves (SR) is a 10-minute response time real-time product that can only be met by online spinning units. SR has a separate ORDC with MRR set at 100% of “N-1” contingency. As SR is a higher quality product, the scheduled SR MW quantity will also be used to meet the Primary Reserve requirement. 10 In the SWEM, a Risk Adjustment Factor (RAF) is used to scale the risk requirement for Contingency Reserve since the termination of fast start ancillary service contract in 2004. Barring extraneous events, the RAF for Contingency Reserves is 1.5 times the “N-1” contingency.
EMC/RCP/120/2021/CP86 16
PJM
Synchronised Reserve
(Online) 100% “N-1” Contingency Up to 10 minutes
Primary Reserve
(Online/Offline) 150% “N-1” Contingency Up to 10 minutes
Referencing the PJM, a possible option is for eligible non-spinning units to compete with LRFs
within the allowable limit of 30% (~one-third) Contingency Reserve requirement. Doing so
ensures that there will be enough spinning reserves to at least cater for the loss of the single
largest online generation unit.