subject: addendum no. 1, cdd13-12, tender for …

81
2013-04-29 TO: ALL BIDDERS SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR MECHANICAL UPGRADES AT PIONEER MANOR The following information, amendments and revisions shall constitute Addendum No. 1 dated April, 29 th , 2013, and shall form an integral part of the Tender Documents and where applicable, shall supersede requirements of other Tender Documents. General Contractors shall bring this addendum to the attention of all sub trades and suppliers from whom they may be receiving quotations. 1.1 Clarification: For natural gas work, contractor will be responsible to paint only the new gas line and branches feed the new equipment on the roof. 1.2 Clarification: Refer to attached sketch. Contractor is responsible to supply and install new gas line and extend 5’ from existing rooftop unit on the roof and cap for phase-1. 1.3 Please refer to spec section 23 74 00 and 23 72 00. Be advised that the tender drawings for RTU and ERV units are based on YORK and GREENHECK. As noted on spec section, Carrier or approved equal such Trane and Aaon will be accepted as long as meet the project specifications. Note: Any changes due to the approved equal product such as dimension, weight affecting structural components will be the mechanical contractor responsibility. 1.4 Contractors are reminded that to include the sprinkler work (Design-build) for phase-2 in their quotation. This was noted in the spec section 21 13 13 as follow: PHASE 2 SPRINKLER WORK: to provide protection in 'L' Wing and 'R' Wing as per drawing M04. Phase 2 shall be quoted as an ADD-On price which the owner may apply if the funding is available. 1.5 Clarification: Please note that all work described in tender documents will be taking place while home areas are occupied with residents. As such access will be limited in duration to specified areas/rooms on a daily basis. 1.6 Clarification: Refer to attached sketches MSK-2 & MSK-3. Contractor will be responsible to supply and install new supervised valves and flow switches for pahse-1 sprinkler work and responsible to supply and installation of the supervised valves for phase-2 sprinkler work for both floors if the funding is not available to proceed the phase-2 fire protection system. …2/

Upload: others

Post on 11-Dec-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

2013-04-29 TO: ALL BIDDERS SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR MECHANICAL UPGRADES AT

PIONEER MANOR The following information, amendments and revisions shall constitute Addendum No. 1 dated April, 29th, 2013, and shall form an integral part of the Tender Documents and where applicable, shall supersede requirements of other Tender Documents. General Contractors shall bring this addendum to the attention of all sub trades and suppliers from whom they may be receiving quotations.

1.1 Clarification: For natural gas work, contractor will be responsible to paint only the new gas line and

branches feed the new equipment on the roof.

1.2 Clarification: Refer to attached sketch. Contractor is responsible to supply and install new gas line and extend 5’ from existing rooftop unit on the roof and cap for phase-1.

1.3 Please refer to spec section 23 74 00 and 23 72 00. Be advised that the tender drawings for RTU and ERV units are based on YORK and GREENHECK. As noted on spec section, Carrier or approved equal such Trane and Aaon will be accepted as long as meet the project specifications. Note: Any changes due to the approved equal product such as dimension, weight affecting structural components will be the mechanical contractor responsibility.

1.4 Contractors are reminded that to include the sprinkler work (Design-build) for phase-2 in their quotation. This was noted in the spec section 21 13 13 as follow:

PHASE 2 SPRINKLER WORK: to provide protection in 'L' Wing and 'R' Wing as per drawing M04. Phase 2 shall be quoted as an ADD-On price which the owner may apply if the funding is available.

1.5 Clarification: Please note that all work described in tender documents will be taking place while home areas are occupied with residents. As such access will be limited in duration to specified areas/rooms on a daily basis.

1.6 Clarification: Refer to attached sketches MSK-2 & MSK-3. Contractor will be responsible to supply and install new supervised valves and flow switches for pahse-1 sprinkler work and responsible to supply and installation of the supervised valves for phase-2 sprinkler work for both floors if the funding is not available to proceed the phase-2 fire protection system.

…2/

Page 2: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Page 2 1.7 Any requests for equals will be accepted as long as meet the project specifications and project

schedule. Note: Any changes due to the approved equal product such as dimension, weight affecting structural components will be the mechanical contractor’s responsibility.

1.8 See tender specifications inadvertently omitted from the tender document.

Please ensure you confirm receipt of this addendum on the Addendum Acknowledgement Form as per Item 14, of Schedule C to By-law 2006-270 and that the form is returned with your tender submission. Further, you are acknowledging that you have received and taken this information into consideration when preparing your bid. Yours truly,

Leigh Lesar Supplies & Services Co-ordinator

Cc: Tony Cardamone, Manager of Building Operations Tony Parmar, Director of Long Term Care, Pioneer Manor

City of Greater Sudbury, Supplies & Services Section, 200 Brady St., Box 5000, Stn. “A”, Sudbury, ON P3A 5P3

Page 3: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Specifications

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades 960 Notre Dame, Sudbury Project No. 131-13878-00

For

City of Greater Sudbury

April 2013

Page 4: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades 960 Notre Dame, Sudbury TABLE OF CONTENTS Project No. 131-13878-00 Page 1

GENIVAR INC .

DIVISION 00 NO. OF PAGES

DIVISION 01 – GENERAL REQUIREMENTS ........................................................................................................ 12

DIVISION 09 - FINISHES .................................................................................................................................... 2

DIVISION 21 – FIRE SUPPRESSION 21 13 13 – WET PIPE SPRINKLER SYSTEMS ..................................................................................................... 8 DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING 23 05 00 – COMMON WORK RESULTS FOR MECHANICAL................................................................................... 5 23 05 54 – MECHANICAL IDENTIFICATION ......................................................................................................... 3 23 05 93 – TESTING, ADJUSTING AND BALANCING FOR HVAC ........................................................................... 5 23 07 13 – THERMAL INSULATION FOR DUCTING ............................................................................................... 4 23 11 23 – FACILITY NATURAL GAS PIPING ...................................................................................................... 3 23 31 14 – METAL DUCTS – LOW PRESSURE TO 500 PA .................................................................................. 5 23 33 00 – DUCT ACCESSORIES ...................................................................................................................... 3 23 33 14 – DAMPERS – BALANCING ................................................................................................................. 2 23 33 16 – DAMPERS – FIRE AND SMOKE ......................................................................................................... 3 23 33 46 – FLEXIBLE DUCTWORK AND SOUND ATTENUATION ............................................................................ 4 23 33 53 – DUCT LINERS ................................................................................................................................. 3 23 37 13 – DIFFUSERS, REGISTERS AND GRILLES............................................................................................. 2 23 72 00 – AIR-TO-AIR ENERGY RECOVERY EQUIPMENT ................................................................................... 4 23 74 00 – PACKAGED OUTDOOR HVAC EQUIPMENT ....................................................................................... 5

END OF TABLE OF CONTENTS

Page 5: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades DIVISION 01

960 Notre Dame, Sudbury GENERAL REQUIREMENTS

Project No. 131-13878-00 Page 1

GENIVAR INC .

DIVISION 01

1.1 GENERAL REQUIREMENTS

.1 Unless specified otherwise, the provisions of this Section shall apply to all Sections of the Specifications.

.2 Conform to the General Conditions of the Canadian Standard Form of Construction Document for a Stipulated Sum (CCDC 2 - 2008) as amended by the Supplementary General Conditions.

.3 Read the balance of Division 01 for instructions regarding general work and services, miscellaneous work and services and temporary work and services.

.4 Study all contract documents to determine additional work required by your Section upon which the work of other Sections depends.

.5 Wherever possible, give preference to local labour and suppliers.

.6 Workmanship shall be of highest quality in accordance with best standard practice for this type of work, except where specified more precisely.

.7 All materials shall be exactly as specified or approved equal. See General Conditions.

1.2 SUMMARY OF WORK

.1 Requirements include:

.1 Title and description of work: Pioneer Manor - Mallard and Scenic Wings Mechanical Upgrades.

.2 Contract method: 2008 Edition of the Canadian Standard Form of Construction Document for a Stipulated Sum (CCDC 2 - 2008) as amended by the Supplementary General Conditions.

.3 Owner's occupancy: upon Substantial Performance.

1.3 ALLOWANCES

.1 Cash Allowances: .1 Refer to GC 4.1.

1.4 SPECIFICATION FORMAT

.1 These Specifications are not intended as a detailed description of installation methods but serve to indicate particular requirements in the completed work.

.2 Conform to Ontario Building Code with latest amendments, hereafter referred to as the "Code". Where Ontario Building Code or the Contract Documents do not cover a particular requirement which is covered by the National Building Code, 2006, conform to the requirements of NBC including its related supplements. Where Drawings and Specifications exceed Code requirements, provide such additional requirements.

.3 Where a material is designated on Drawings or in the Specifications for a certain application, unless otherwise specified, that material shall conform to standards designated in the Ontario Building Code.

Similarly, unless otherwise specified, installation methods and standards of workmanship shall also conform to standards invoked by the aforementioned Code. Where no

Page 6: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

DIVISION 01 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

GENERAL REQUIREMENTS 960 Notre Dame, Sudbury

Page 2 Project No. 131-13878-00

PBK ARCHITECTS INC .

particular material is specified for a certain use, the Contractor shall select from the choice offered in the Code in each case.

.4 Parts of the Specification are written in short form; therefore, it shall be understood that where a component of the work is stated in a heading followed by a material or operation, the words "shall be", "shall consist of" or similar words or phrases are implied which denote complete supply and installation of such materials or operations for the component of work designated by the heading.

.5 Where the aforementioned Code of this Specification does not provide all information necessary for complete installation of an item, then the manufacturer's instructions for first quality workmanship shall be strictly complied with.

.6 Where words in the Contract Documents occur in the singular number, they shall be taken as plural where applicable in accordance with the quantities required to satisfy the requirements of the Contract.

1.5 STANDARDS & DEFINITIONS

.1 Where a reference is made to specification standards produced by various organizations, conform to edition of standards specified or, if not specified, to latest edition as amended and revised to date of contract.

.2 Have a copy of each specified standard which relates to your work available on the site to be produced immediately upon Consultant's request.

.3 Where a standard designates other authorities, these designations shall be taken to mean the Consultant.

.4 Wherever the words "acceptable", "approved", "satisfactory", "selected", "directed", "designated", "permitted", "inspected", "instructed", "required", "submit", or similar words or phrases are used in standards or elsewhere in the Contract documents, it shall be understood that, unless the context provides otherwise, the words "by (to) the Consultant" follow.

1.6 SCAFFOLDING

1. Erect scaffolding independent of walls. Use it in such a manner as to interfere as little as possible with other trades. When not in use, move it as necessary to permit installation of other work. Construct and maintain scaffolding in a rigid, secure and safe manner. Remove it promptly when no longer required.

1.7 PROJECT COORDINATION

.1 Coordinate progress of the Work, progress schedules, submittals, use of site, temporary utilities, construction facilities.

.2 Co-operate with and co-ordinate with other trades as required for the satisfactory and expeditious completion of the work. Take field dimensions relative to this work. Fabricate and erect work to suit field dimensions and field conditions. Provide all forms, templates, anchors, sleeves, inserts and accessories required to be fixed to or inserted in the work and set in place or instruct the related trades as to their location. Pay the cost of extra work caused by and make up time lost as the result of failure to provide the necessary co- operation, information or items to be fixed to or built in, in adequate time.

Page 7: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades DIVISION 01

960 Notre Dame, Sudbury GENERAL REQUIREMENTS

Project No. 131-13878-00 Page 3

GENIVAR INC .

1.8 EXAMINATION

.1 Examine the work upon which your work depends. Report to Consultant in writing, defects in such work. The application of your work or any part of it shall be deemed acceptance of the work upon which your work or that part of it which has been applied depends.

.2 Drawings are, in part, diagrammatic and are intended to convey scope of work and indicate general and approximate location, arrangement and sizes of fixtures and equipment. Obtain more accurate information about locations, arrangement and sizes from study and co-ordination of Drawings, including shop drawings and become familiar with conditions and spaces affecting these matters before proceeding with work. Where job conditions require reasonable changes in indicated locations and arrangements, make changes at no additional cost to the Owner. Similarly, where existing conditions interfere with new installation and require relocation, include such relocation in the work of this Contract. Install and arrange fixtures and equipment in such a way as to conserve as much headroom and space as possible.

1.9 CONCEALMENT OF PIPES, DUCTS, TUBING AND WIRING

.1 Conceal pipes, ducts, tubing and wiring in the floor, wall and ceiling construction of finished areas wherever possible. If any doubt arise as to the means of concealment, or the intention of the Contract documents in this connection, request clarification from the Consultant before proceeding with the portion of the work in question.

.2 Arrange to have mechanical and electrical work laid out well in advance of concrete placement or furring installation so that provisions may be made for proper concealment. All such work shall be tested, inspected and pipe covering applied where applicable before being concealed.

1.10 LINES, LEVELS AND DIMENSIONS

.1 Lay out work in accordance with lines and levels shown on Drawings.

.2 Verify lines, levels and dimensions and report errors or inconsistencies in the Drawings to Consultant before commencing work.

.3 Levels and dimensions necessary to relate work of a Section to the work of other Sections shall be provided under this Section.

1.11 PROTECTION

.1 Adequately protect trowelled sub-floors and finished flooring from damage. Take special measures when moving heavy loads or equipment on them.

.2 Keep floors free of oils, grease or other materials likely to discolour them or affect bond of applied surfaces.

.3 Protect work of other Sections from damage while doing this work.

.4 Damaged work shall be made good by appropriate trades but at the expense of those causing damage.

.5 Attach and fasten fixtures and fittings in place in safe, sturdy, secure manner so that they cannot work loose or fall or shift out of position during the occupancy of Building as a result of vibration or other causes in normal use of Building.

.6 Protect existing buildings, curbs, roads and lanes. If during work, any existing items are damaged, repair or replace them at no extra expense to the Owner.

Page 8: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

DIVISION 01 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

GENERAL REQUIREMENTS 960 Notre Dame, Sudbury

Page 4 Project No. 131-13878-00

PBK ARCHITECTS INC .

1.12 FASTENINGS

.1 Supply all fastenings, anchors and accessories and adhesives required for fabrication and erection of the work.

.2 Exposed metal fastenings and accessories shall be of same texture, colour and finish as base metal on which they occur.

.3 Metal fastenings shall be of the same materials as the metal component they are anchoring or of a metal which will not set up an electrolytic action which would cause damage to the fastening or metal component under moist conditions. Anchors occurring on or in an exterior wall or slab shall be non corrosive or hot dip galvanized steel.

.4 Anchoring and fastening devices or adhesives shall be of appropriate type, use in sufficient quantity and in such a manner as to provide positive, permanent anchorage of the unit to be anchored in position. Install anchors at spacing to provide for required load carrying capacity.

.5 Keep exposed fastenings to a minimum, evenly spaced and neatly laid out.

.6 Supply adequate instructions and templates, and if necessary, supervise installation where fastenings or accessories are required to be built into work of other trades.

.7 Fastenings shall be of permanent type. Do not use wood plugs. Do not use fastenings which cause spalling or cracking of material to which anchorage is being made.

.8 Do not use powder actuated fastening devices which are stressed in withdrawal on any part of this work without approval from the Consultant. Take particularly stringent safety precautions when using powder actuated fastenings. Only low velocity plunger-type devices are permitted.

1.13 CUTTING AND PATCHING

.1 Approvals: .1 Submit written request in advance of cutting or alteration which affects:

.1 Structural integrity of any element of Project.

.2 Integrity of weather-exposed or moisture-resistant elements.

.3 Efficiency, maintenance, or safety of any operational element.

.4 Visual qualities of sight-exposed elements.

.5 Work of Owner or separate contractor. .2 Inspection:

.1 Inspect existing conditions, including elements subject to damage or movement during cutting and patching.

.2 After uncovering, inspect conditions affecting performance of work.

.3 Beginning of cutting or patching means acceptance of existing conditions.

.3 Execution: .1 Perform cutting, fitting, and patching including excavation and fill, to complete the

Work. .2 Remove and replace defective and non-conforming work. .3 Provide openings in non-structural elements of Work for penetrations of

mechanical and electrical work. .4 Perform work to avoid damage to other work. .5 Prepare proper surfaces to receive patching and finishing. .6 Employ original installer to perform cutting and patching for weather-exposed and

moisture-resistant elements, and sight-exposed surfaces. .7 Cut rigid materials using power saw or core drill. Pneumatic or impact tools not

allowed.

Page 9: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades DIVISION 01

960 Notre Dame, Sudbury GENERAL REQUIREMENTS

Project No. 131-13878-00 Page 5

GENIVAR INC .

.8 Restore work with new products in accordance with Contract Documents.

.9 Fit work airtight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

.10 At penetration of fire-rated wall, ceiling, or floor construction, completely seal voids with fire-resistant material, full thickness of construction element.

.11 Refinish surfaces to match adjacent finishes; for continuous surfaces refinish to nearest intersection; for an assembly, refinish entire unit.

1.14 INSPECTION AND TESTING COMPANIES

.1 In addition to inspection and testing results specified to be provided as part of the work of various trade sections of the Specifications, inspection and testing companies for various trades may be appointed separately by the Consultant where specifically stated or required. In such cases, the following will apply:

.1 The Owner will pay the costs of such additional inspection and testing except that where test or inspections reveal work not in accordance with the Contract, the Contractor shall bear the cost of such tests as the Consultant requires to verify the acceptability of corrected work.

.2 The Consultant will supply Drawings and Specifications as required for the use of the respective inspection and testing companies and advise the Contractor of the companies appointed for the respective work.

.3 The Contractor shall advise the Consultant and the respective inspection and testing company not less than 5 working days prior to the commencement of any work to be inspected or tested to ensure that proper facilities and co-operation are provided and that no work is carried out without the required inspection and testing.

.4 Proper storage shall be provided for storing concrete specimens at the job site at the required temperature and free from vibration or injury.

.5 Promptly provide Consultant and inspector with safe access to any part of the work requiring inspection.

1.15 PROJECT MEETINGS

.1 Meetings on site will be as the Consultant requires and attended by the Consultant’s representative, Owner's representative, Structural Engineer, Mechanical / Electrical Engineer, Contractor and all sub-contractors or their authorized representatives whose presence is requested by the Consultant.

.2 All representatives must carry the authority of the company they represent and be capable of making decisions. The General Contractor shall record the discussion and contents of meetings. Copies of the minutes of each meeting will be sent to all applicable parties.

1.16 SUBMITTALS

.1 Administrative: .1 Submit to Consultant submittals listed for review. Submit with reasonable

promptness and in an orderly sequence so as to not cause delay in the Work. .2 Work affected by submittal shall not proceed until review is complete. .3 Review submittals prior to submission to Consultant. This review represents that

necessary requirements have been determined and verified, or will be, and that each submittal has been checked and co-ordinated with requirements of the Work and Contract Documents.

.4 Verify field measurements and affected adjacent Work are co-ordinated.

Page 10: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

DIVISION 01 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

GENERAL REQUIREMENTS 960 Notre Dame, Sudbury

Page 6 Project No. 131-13878-00

PBK ARCHITECTS INC .

.2 Shop Drawings and Product Data: .1 Refer to GC 3.10. .2 "Shop drawings" means drawings, diagrams, illustrations, schedules,

performance charts, brochures and other data which are to be provided by Contractor to illustrate details of a portion of the Work.

.3 Indicate materials, methods of construction and attachment or anchorage, erection diagrams, connection, explanatory notes and other information necessary for completion of Work.

.4 Adjustments made on shop drawings by Consultant are not intended to change Contract Price.

.5 Make changes in shop drawings as Consultant may require.

.6 Submit one transparency, and 6 prints of shop drawings for each requirement requested in specification Sections and as Consultant may reasonably request.

.7 Submit 6 copies of product data sheets or brochures for requirements requested in specification Sections and as Consultant may reasonably request where shop drawings will not be prepared due to standardized manufacture of product.

3. Samples: .1 Submit for review, samples in duplicate as requested in respective specification

Sections. .2 Deliver samples prepaid to Consultant's business address.

.4 Colour Selection: .1 Submit duplicate colour charts of all materials or equipment requiring colour

selection in one submission for Consultant's preparation of Colour Schedule. .2 Allow four weeks for Consultant's Colour Schedule preparation and Owner's

approval.

.5 Operating Maintenance Manuals: .1 Two weeks prior to Substantial Performance of the Work, submit to Consultant, 2

copies of operating and maintenance manuals. .2 Manuals to contain operational information on equipment, cleaning and

lubrication schedules, filters, overhaul and adjustment schedules and similar maintenance information.

.3 Bind contents in a three-ring, hard covered, plastic jacketed binder. Organize contents into applicable categories of work, parallel to specifications Sections.

.6 Record Drawings: .1 After award of Contract, Consultant will provide a set of transparency drawings for

purpose of maintaining record drawings. Accurately and neatly record deviations from Contract Documents caused by site conditions and changes ordered by Consultant as the work progresses.

.2 Record locations of concealed components of mechanical and electrical services as the work progresses.

.3 Identify drawings as "Project Record Copy". Maintain in new condition and make available for inspection on site by Consultant.

.4 On completion of Work and prior to final inspection, submit record documents to Consultant.

.7 Guaranties, Warranties and Bonds: .1 Within two weeks of Certification of Substantial Performance, submit original and

two copies of all required guaranties, warranties and bonds, including extended warranties, fully executed and notarized.

Page 11: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades DIVISION 01

960 Notre Dame, Sudbury GENERAL REQUIREMENTS

Project No. 131-13878-00 Page 7

GENIVAR INC .

1.17 SCHEDULES

.1 Schedules Required: .1 Construction Progress Schedule. .2 Submittal Schedule for Shop Drawings, Product Data and Samples. .3 Submittal schedule for Product.

.2 Format: .1 Prepare schedule in form of horizontal bar chart. .2 Provide separate bar for each trade or operation. Identify critical dates. .3 Provide horizontal time scale identifying first work day of each week. .4 Construction Progress Schedule: List items in chronological order of start of each

item. Identify start and finish of each item.

.3 Submission: .1 Submit initial schedules within 15 days after award of Contract. .2 Submit four copies, three copies to be retained by Consultant. .3 Consultant will review schedule and return reviewed copy within 10 days after

receipt. .4 Resubmit finalized schedule within 7 days after return of reviewed copy. .5 Update schedules monthly, and submit with progress claim.

1.18 SITE REVIEW

.1 Refer to GC 2.3.

.2 No review by the Consultant shall relieve the Contractor of any of his obligations under the Contract or shall be interpreted as being an acceptance of defective or improper work or material, which must in every case be removed and replaced properly or otherwise rectified in a satisfactory manner whenever discovered at any time.

1.19 QUALITY CONTROL

.1 Refer to GC 2.3.

.2 Provide a system of quality control to ensure that the minimum standards specified herein are attained.

.3 Bring to the attention of the Consultant any defects in work or departures from the Contract Documents which may occur during construction. The Consultant will decide upon corrective actions and state his recommendations in writing.

.4 The Consultant's general review during construction and inspection and testing by independent inspection and testing agencies reporting to the Consultant are both undertaken to inform the Owner of the Contractor's performance and shall in no way augment the Contractor's quality control or relieve him of contractual responsibility.

1.20 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

.1 Installation / Removal: .1 Provide construction facilities and temporary controls in order to execute work

expeditiously. .2 Remove from site all such work after use.

.2 Fencing and Hoarding: .1 Maintain fencing around perimeter of Work, to protect public from injury or

damage. .2 Install hoarding where required, to protect public from injury or damage.

Page 12: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

DIVISION 01 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

GENERAL REQUIREMENTS 960 Notre Dame, Sudbury

Page 8 Project No. 131-13878-00

PBK ARCHITECTS INC .

.3 Weather Enclosures: .1 Provide weathertight closures to unfinished door and window openings, tops of

shafts and other openings in floors and roofs. .2 Close off floor areas where walls are not finished; seal off other openings;

enclose building interior work area for temporary heat.

.4 Dust Tight Screens: .1 Provide dust tight screens or partitions to localize dust generating activities, and

for protection of workers, finished areas of Work and public. .2 Maintain and relocate protection until such Work is complete.

.5 Dewatering: .1 Provide temporary drainage and pumping facilities to keep excavations and site

free from standing water.

.6 Site Storage/Loading: .1 Refer to GC 3.11. .2 Confine the Work and operations of employees to limits indicated by Contract

Documents. Do not unreasonably encumber premises with Products. .3 Do not load or permit to be loaded any part of the Work with a weight or force that

will endanger the Work.

.7 Sanitary Facilities: .1 Provide sufficient sanitary facilities for workers in accordance with local health

authorities. .2 Maintain in clean condition.

.8 Water Supply: .1 Provide a continuous supply of potable water for construction use. .2 Arrange for connection with appropriate utility company and pay costs for

installation, maintenance and removal.

.9 Temporary Heating: .1 Provide temporary heating required during construction period, including

attendance, maintenance and fuel. .2 Construction heaters used inside building must be vented to outside or be non-

flameless type. Solid fuel salamanders not permitted. .3 Maintain temperatures of minimum 10 deg C in areas where construction is in

progress, unless indicated otherwise in specifications. .4 Ventilate heated areas and keep building free of exhaust or combustion gases.

.10 Temporary Power: .1 Provide and pay for temporary power required during construction for temporary

lighting and operating of power tools, to maximum supply of 230 volts 30 amps. .2 Arrange for connection with appropriate utility company. Pay costs for

installation, maintenance and removal.

.11 Temporary Telephone: .1 Provide and pay for temporary telephones necessary for own use. .2 Maintain telephone in site office.

.12 Temporary Office: .1 Provide, maintain, and remove all necessary temporary site offices. Provide

suitable enclosed area for site meetings.

.13 Equipment / Tool / Materials Storage: .1 Provide and maintain, in clean and orderly condition, lockable weatherproof

sheds for storage of tools, equipment and materials. .2 Locate materials not required to be stored in weatherproof sheds on site in

manner to cause least interference with work activities.

Page 13: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades DIVISION 01

960 Notre Dame, Sudbury GENERAL REQUIREMENTS

Project No. 131-13878-00 Page 9

GENIVAR INC .

.14 Project Cleanliness: .1 Maintain the Work in tidy condition, free from accumulation of waste products and

debris. .2 Remove waste material and debris from site and deposit in waste container at

end of each working day. Remove waste from container as required. Do not burn waste materials on site.

.3 Remove snow and ice from site work area, parking areas, patios and walkways. Do not allow snow or ice build-up. Prevent snow and ice from blocking surface drainage system.

.4 Clean interior areas prior to start of finish work, maintain areas free of dust and other contaminants during finishing operations.

.5 Prevent dust and noise which may affect surrounding properties.

1.21 OVERLOADING

.1 Load no part of structure during construction with load greater than calculated to bear safely when completed. Make every temporary support as strong as permanent support. Place no load on concrete until it has cured as specified in Concrete, Division 3 and has achieved sufficient strength to safely carry such load.

1.22 SUPERINTENDENT

.1 Employ a competent superintendent and necessary assistants who shall be in attendance at the Work site at all times while work is being performed.

.2 The superintendent shall be satisfactory to the Consultant and shall not be changed except for good reason and only then after consultation with, and agreement by, the Consultant.

.3 The superintendent shall represent the Contractor at the work site and directions given to him by the Consultant shall be held to have been given to the Contractor.

.4 Superintendence shall be deemed not satisfactory and changes or additions to superintendence may be demanded when, .1 Control, organization and coordination of the work is not satisfactory, or, .2 The quality of the work does not meet the requirements of the Contract

Documents, or, .3 The directions given in accordance with the Contract Documents are not

followed, or, .4 The progress of the work is behind the agreed schedule.

.5 Superintendent to coordinate work of all trades and ensure prompt and continuous prosecution of work.

.6 Superintendent to be responsible for quality control and Contractor's inspections for incomplete or deficient work.

1.23 MATERIAL AND EQUIPMENT

.1 Product and Material Quality: .1 Refer to GC 3.8. .2 Products, materials, equipment and articles (referred to as Products throughout

specifications) incorporated in Work shall be new, not damaged or defective, and of best quality (compatible with specifications) for purpose intended. If requested, furnish evidence as to type, source and quality of Products provided.

.3 Defective Products, will be rejected, regardless of previous inspections. Inspection does not relieve responsibility, but is precaution against oversight or

Page 14: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

DIVISION 01 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

GENERAL REQUIREMENTS 960 Notre Dame, Sudbury

Page 10 Project No. 131-13878-00

PBK ARCHITECTS INC .

error. Remove and replace defective Products at own expense and be responsible for delays and expenses caused by rejection.

.4 Should any dispute arise as to quality or fitness of Products, decision rests strictly with Consultant based upon requirements of Contract Documents.

.2 Storage, Handling and Protection: .1 Handle and store Products in manner to prevent damage, adulteration,

deterioration and soiling and in accordance with manufacturer's instructions when applicable.

.2 Store packaged or bundled Products in original and undamaged condition with manufacturer's seals and labels intact.

.3 Store products subject to damage from weather in weatherproof enclosures.

.3. Manufacturer's Instructions: .1 Unless otherwise indicated in specifications, install or erect Products in

accordance with manufacturer's instructions. Do not rely on labels or enclosures provided with Products. Obtain written instructions directly from manufacturers.

.2 Notify Consultant in writing, of conflicts between specifications and manufacturer's instructions, so that Consultant may establish course of action.

.3 Improper installation of erection of Products, due to failure in complying with these requirements, authorizes Consultant to require removal and reinstallation at no increase in Contract Price.

.4 Workmanship: .1 Workmanship shall be best quality, executed by workers experienced and skilled

in respective duties for which they are employed. Immediately notify Consultant if required Work is such as to make it impractical to produce required results.

.2 Do not employ any unfit person or anyone unskilled in their required duties.

.3 Decisions as to quality or fitness of workmanship in cases of dispute rest solely with Consultant, whose decision is final.

.5 Concealment: .1 In finished areas, conceal pipes, ducts and wiring in floors, walls and ceilings,

except where indicated otherwise. .2 Before installation, inform Consultant if there is a contradictory situation. Install as

directed by Consultant.

1.24 PROJECT CLOSEOUT

.1 Final Cleaning: .1 Refer to GC 3.13. .2 Prior to Substantially Performance, remove surplus products, tools construction

machinery and equipment not required for performance of remaining Work. .3 Leave work broom clean before inspection process commences. .4 Clean and polish glass, mirrors, hardware, wall tile, stainless steel, chrome,

porcelain enamel, baked enamel, plastic laminate, mechanical and electrical fixtures. Replace broken, scratched or disfigured glass.

.5 Remove stains, spots, marks and dirt from decorative work, electrical and mechanical fixtures, furniture fitments, walls, and finished surfaces.

.6 Vacuum clean and dust building interiors, behind grilles, louvres and screens.

.7 Wax, seal, shampoo or prepare floor finishes, as recommended by manufacturer.

.8 Broom clean and wash exterior walks, steps and surfaces.

.9 Remove dirt and other disfigurations from exterior surfaces.

Page 15: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades DIVISION 01

960 Notre Dame, Sudbury GENERAL REQUIREMENTS

Project No. 131-13878-00 Page 11

GENIVAR INC .

.2 Systems Demonstration: .1 Prior to final inspection, demonstrate operation of each system to Owner. .2 Instruct personnel in operation, adjustment, and maintenance of equipment and

systems, using provided operation and maintenance data as basis for instruction.

.3 Documents: .1 Collect reviewed submittals and assemble documents executed by

Subcontractors, suppliers, and manufacturers. .2 Submit material prior to application for Substantial Performance. .3 Submit operation and maintenance data, record (as-built) drawings. .4 Execute transition of Performance and Labour and Materials Payment Bond to

warranty period requirements. .5 Submit a final statement of accounting giving total adjusted Contract Price,

previous payments, and monies remaining due. .6 Consultant will issue a final change order reflecting approved adjustments to

Contract Price not previously made.

.4 Inspection/Takeover Procedures: .1 Follow procedures in "OAA / OGCA Take-Over Procedures" OAA / OGCA

Document No.100, November 1983. .2 Prior to application for certificate of Substantial Performance, carefully inspect the

Work and ensure it is complete, that major and minor construction deficiencies are complete, defects are corrected and building is clean and in condition for occupancy. Notify Consultant in writing, of satisfactory completion of the Work and request an inspection.

.3 During Consultant inspection, a list of deficiencies and defects will be tabulated. Correct same.

.4 When Consultant considers deficiencies and defects have been corrected and it appears requirements of Contract have been performed, make application for certificate of Substantial Performance. Refer to GC 5.4 for specifics to application.

.5 If project is not Substanially Performed at the time of Contractor's request for inspection, be responsible for Consultant's and Sub-Consultant's cost for inspection and report.

.6 After Certificate of Substantial Performance is issued, arrange and pay for publication of Substantial Performance in acceptable trade publication. Forward proof of publication to Consultant.

.7 Within one week after Cerificate of Substantial Performance is issued, submit schedule for completion of deficiencies for Consultants approval.

.8 Within two weeks after Certificate of Substantial Performance is issued, submit warranties, bonds, and guaranties fully executed and notarized.

.5 The following are required at the project takeover (or prior thereto as specified elsewhere). .1 Statement of completion of work. .2 Two copies of operating manuals as specified elsewhere. .3 Two sets of "as built" drawings showing all changes and modifications. .4 Two copies of Hydro Inspection Certificates. .5 Certificate in good standing from the Workmen's Compensation Board for the

Contractor and all sub-contractors. .6 Documentation for warranty and guarantees. .7 Air balancing reports. .8 All other documentation required including those specified elsewhere. .9 Project keys. .10 Occupancy Permits.

Page 16: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

DIVISION 01 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

GENERAL REQUIREMENTS 960 Notre Dame, Sudbury

Page 12 Project No. 131-13878-00

PBK ARCHITECTS INC .

.11 Fire Department Clearance.

.12 Instructions to Owner on operation of all mechanical and electrical equipment.

.13 List of subtrades who will handle warranty work under the terms of the guarantee.

.14 Arrangement for readings of all meters by public utilites and the changeover of billing.

.15 Maintenance material specified.

1.25 WARRANTY

.1 Warranty Inspection: .1 Approximately one month, before the end of the waranty period, an inspection is

to be carried out. It is to be attended by the Contractor, the Consultant, and the Owner. Rectify all warranty items.

1.26 ENVIRONMENTAL CONDITIONS

.1 Take all necessary precautions to prevent damage to work affected by temperature, water, weather and other environmental conditions in addition to precautions specified in Division 1, as required.

1.27 COLOURS

.1 Consult with Consultant on colours and gloss values. All colours and gloss value selection will be by Consultant. Notify Consultant well in advance of requiring direction on colour and take action, as directed by Consultant, which can be either:

.1 Receiving schedule prepared by Consultant and using colours designated or,

.2 Submitting samples to Consultant for colour selection.

.3 The number of colours selected by the Consultant shall not be limited, unless specifically indicated in other Sections of the Specification. Colours shall be selected from the manufacturer’s full range of colours.

1.28 AWARD / SELECTION OF ALTERNATIVES

.1 Indicate variation of Bid Price for Alternatives described and listed in Tender Form. Note that this form requests a 'difference' in Bid Price by adding to or deducting from the base bid price.

.2 Bids shall be evaluated on ‘base bid’ price. After determination of successful bidder, consideration will be given to Alternatives and Bid Price adjustments.

.3 In accordance with the CCDC Document No. 23 - A Guide to Calling Tenders and Awarding Contracts, the low bid shall be determined on the basis of the lowest tender in accordance with the Contract Documents on which the Project is to be actually constructed, including those alternatives for which prices have been invited and which are to be incorporated in the Work.

END OF DIVISION

Page 17: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades Division 09

960 Notre Dame, Sudbury FINISHES

Project No. 131-13878-00 Page 1

PBK ARCHITECTS INC .

DIVISION 09

9.1 METAL STUD SYSTEM

.1 Non-loadbearing channel stud framing to ASTM C645-83, stud size as shown on drawings.

.2 Floor and ceiling tracks: to ASTM C645-83.

.3 Metal channel stiffener: 40 mm x 40 mm size 1.4mm thick.

9.2 GYPSUM BOARD

.1 Furnish all material and labour necessary to provide finished drywall surfaces in all areas scheduled to receive this finish on the drawings. Tape, spackle and sand surfaces as to receive paint, repeat as required.

.2 All drywall over furring and wood studs shall be to thicknesses shown on drawings in accordance with CSA A82-31-M1980.

9.3 SUSPENDED CEILING SYSTEM

.1 Furnish all materials labour to provide a complete suspended ceiling including ceiling tile, hangers, grid tees and all mouldings.

.2 Install suspension system in accordance with ASTM C636-86.

.3 Suspension system: match existing.

.4 Lay in tile: match existing.

.5 See Reflected Ceiling Plan for the size of panels in locations shown.

9.4 PAINTING - INTERIOR

.1 Formula 1: for concrete block and poured concrete walls apply:

.1 one coat block filler CAN/CGSB-1.188.

.2 one coat primer-sealer CAN/CGSB-1.119.

.3 two coats eggshell enamel CAN/CGSB-1.57.

.2 Formula 2: for plaster and gypsum board ceilings apply:

.1 one coat primer-sealer CAN/CGSB-1.119.

.2 one coat eggshell enamel CAN/CGSB-1.57.

.3 Formula 3: for primed ferrous metal surfaces apply:

.1 one coat spot priming CAN/CGSB-1.40.

.2 one coat enamel undercoat CAN/CGSB-1.38.

.3 two coats semi-gloss enamel CAN/CGSB-1.57.

Page 18: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Division 09 Pioneer Manor – Mallard and Scenic Wings Mechanical Upgrades

FINISHES 960 Notre Dame, Sudbury

Page 2 Project No. 131-13878-00

PBK ARCHITECTS INC .

.4 Formula 4: for woodwork to receive natural finish apply:

.1 one coat paste filler.

.2 one coat shellac.

.3 one coat varnish CAN/CGSB-1.36, Type 1.

.4 one coat varnish CAN/CGSB 1.36, Type 2.

END OF DIVISION

Page 19: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 DESIGN-BUILD SUMMARY

.1 Section Includes:

.1 System design, materials, and installation for wet pipe fire protection and

sprinkler systems for renovation areas. Phase 1 and Phase 2 will be described

below.

.2 Refer to architect's Phase Plans for further information.

.3 The contractor shall assign this work to a sprinkler specialist and carry the final

responsibility for supervision and quality control.

.2 Related Sections:

.1 Existing drawings and reflected ceiling plans can be made available to the

selected company.

.2 Existing fire protection piping.

.3 Pipe painting at areas of 'exposed ceilings'.

.4 Electric power.

.5 Controls/ control wiring/ fire alarm system.

1.2 REFERENCES

.1 American National Standards Institute/National Fire Prevention Association.

.1 NFPA 13. Installation of sprinkler systems.

.2 NFPA 14, Installation of Standpipe and Hose Systems 2007.

.2 Health Canada/Workplace Hazardous Materials Information System (WHMIS)

.1 Material Safety Data Sheets (MSDS).

1.3 SAMPLES

.1 Submit samples of following:

.1 Sprinkler heads on finished ceilings.

1.4 DESIGN REQUIREMENTS

.1 The fire protection company shall design the automatic wet pipe sprinkler systems in

accordance with required provisions of NFPA 13, including hydraulic calculations for

uniform distribution of water over design area.

.2 The building has existing sprinkler systems in place. Design extended piping to ‘M’ Wing

and 'S' Wing designated by the shaded area indicated. This portion will be called

PHASE 1 SPRINKLER WORK.

.3 PHASE 2 SPRINKLER WORK: to provide protection in 'L' Wing and 'R' Wing as per

drawing M04/ M05. Phase 2 shall be quoted as an ADD-On price which the owner may

apply if the funding is available.

Page 20: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 2

.4 The corner Lounge area which is shown on drawing - - is to remain, because it is already

sprinklered.

.5 Submit (stamped) system drawings to local building official and consultant for review.

Make revisions to the design when requested by consultant.

.6 Base plans, in AutoCadd, will be available from the consultant.

.7 Include with each system: selected materials, accessories, and equipment inside and

outside building to provide each system complete and ready for use.

.8 Design and install each system to give full consideration to concealed spaces, piping,

electrical equipment, ducts, and other obstructions in accordance with the project's

drawings. Locate sprinkler heads in a consistent pattern with ceiling grid, lights, and air

diffusers.

.9 Devices and equipment for fire protection service: to be ULC approved for use in wet pipe

sprinkler systems.

.10 The fire protection company shall co-ordinate safety devices with the other trades, for

connection to fire alarm system. Personnel must assist with the alarm testing, before final

acceptance.

.11 Position of Sprinkler Heads:

.1 Locate heads in relation to ceiling and spacing of sprinkler heads not to exceed

that spacing permitted by NFPA 13 for each hazard occupancy. Sidewall

sprinklers may be considered where practical. Sprinkler positions will be subject

to approval by Owner's Representative.

.2 Uniformly space sprinklers on branch.

.3 The sprinkler designer shall schedule design meetings to confirm the basic

requirements from the consultant and to integrate into the building’s ceiling

construction.

.12 Distribution Piping:

.1 Check existing site conditions to determine major obstructions prior to the

design.

.2 Areas of special concern shall be marked on the sprinkler drawings.

.13 Density of Application of Water:

.1 Size pipe to provide specified density when system is discharging specified total

maximum required flow.

.14 Sprinkler Discharge Area:

.1 Area: hydraulically most remote, as defined in NFPA 13.

.15 Outside Hose Allowances:

.1 Include allowance in hydraulic calculations for outside hose streams.

Page 21: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 3

.16 Water Supply:

.1 The sprinkler contractor is required to perform up-to-date flow tests at the site,

unless noted otherwise.

.2 Date of test must be co-ordinated with the owner's representative.

.3 Base the hydraulic calculations on pressures obtained from the flow-testing.

1.5 SUBMITTALS

.1 Product Data:

.1 Submit manufacturer's printed product literature, specifications and datasheet in

accordance with Section – General Requirements.

.2 Shop Drawings:

.1 Submit shop drawings in accordance with Section Submittal Procedures.

.1 Shop drawings: submit drawings stamped and signed by professional

engineer registered or licensed in Province of Ontario.

.2 The system engineer will be asked to sign 'Commitment to Review'

documents as required by the local Building Dept.

.3 Design drawings to indicate:

.1 Materials.

.2 Finishes.

.3 Method of anchorage/ hangers.

.4 Supports.

.5 Pipe layout.

.6 Details of fire-alarm related devices.

.7 Interference/ pipe elevation for the purpose of co-ordination with

other trades.

.3 Quality assurance submittals: During construction, submit the following in accordance

with Section 01 33 00 - Submittal Procedures.

.1 Test reports: as per NFPA 13.

.2 Submit certified test reports for wet pipe fire protection sprinkler systems where

requested by the building officials.

.4 Closeout Submittals:

.1 Manufacturer's Catalog Data, including specific model, type, and size for:

.1 Pipe and fittings.

.2 Valves, including gate, check, and globe.

.3 Sprinkler heads.

.4 Pipe hangers and supports.

.5 Pressure or flow switches; tamper switches.

.6 Mechanical couplings.

.2 Design Data:

.1 Calculations of sprinkler system design.

Page 22: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 4

.2 Indicate type and design of each system.

.3 Field Test Reports: Certif. of AboveGround Piping, as per NFPA code.

.4 Records:

.1 As-built drawings of each system.

.1 After completion, but before final acceptance, submit complete

set of as-built drawings of each system for record purposes. Use

AutoCadd format for electronic files.

.5 Operation and Maintenance Manuals:

.1 Provide maintenance data for incorporation into manual specified in

Section - Closeout Submittals.

1.6 QUALITY ASSURANCE

.1 Qualifications:

.1 Installer: company or person specializing in wet sprinkler systems with

documented experience.

.2 Health and Safety:

.1 Do construction occupational health and safety in accordance with the General

Contractor's Requirements.

1.7 MAINTENANCE

.1 Extra Materials: Provide maintenance materials in accordance with Section - Closeout

Submittals.

.1 Provide spare sprinklers into existing cabinet, and tools as required by

ANSI/NFPA 13.

.2 Indicate, in writing, the annual maintenance requirements for Owner. Refer to

page 3, Part 1.5.4.5, Manuals.

1.8 DELIVERY, STORAGE, AND HANDLING

.1 Packing, shipping, handling and unloading:

.1 Deliver, store and handle in accordance with guidelines set by the Site Supervisor.

.2 Storage and Protection:

.1 Store materials in a dry location.

.2 Store and protect materials from exposure to harmful weather conditions and at

temperature and humidity conditions recommended by manufacturer.

Part 2 Products

2.1 ABOVE GROUND PIPING SYSTEMS

.1 Provide approved fittings for changes in direction of piping and for connections.

.1 Make changes in piping sizes through tapered reducing pipe fittings, bushings will

not be permitted.

Page 23: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 5

.2 Conceal piping in areas with suspended ceiling and in pipe chases where practical.

.1 Confirm that each area of wet sprinkler system is heated.

.2 In suspended ceilings: conserve ceiling space. Future ductwork must be installed,

so the sprinkler lines must permit regular duct construction.

2.2 PIPE, FITTINGS AND VALVES

.1 Pipe:

.1 Steel: to NFPA 13 and NFPA 14.

.2 Copper tube: to NFPA 13.

.2 Fittings and joints to NFPA 13 and NFPA14:

.1 Steel: screwed, flanged or roll grooved.

.2 Copper tube: soldered.

.3 Provide threaded, fittings into which sprinkler heads, sprinkler head riser nipples,

or drop nipples are threaded.

.4 Rubber-gasketted grooved-end pipe and fittings with mechanical couplings are

permitted.

.5 Fittings: ULC approved for use in wet pipe sprinkler systems.

.6 Special flex pipe connectors, for sprinklers in T-bar ceilings.... are acceptable.

.3 Valves:

.1 ULC listed for fire protection service.

.2 Gate valves: open by counterclockwise rotation.

.4 Pipe hangers:

.1 ULC listed for fire protection services in accordance with NFPA.

2.3 SPRINKLER HEADS

.1 General: to ANSI/NFPA 13 and ULC listed for fire services.

.2 Sprinkler Head Type:

.1 Type A: upright bronze.

.2 Type C: pendent chrome glass bulb type.

.3 Type D: semi-recessed polished chrome glass bulb type with ring and cup.

.4 Type E: flush bronze, fully concealed type; with finished cover plate.

.5 Type F: side wall polished chrome type, with chrome escutcheon.

.3 Provide nominal 1.2 cm orifice sprinkler heads. (1/2” nom.)

.1 Release element of each head to be of temperature rating suitable for specific

application.

.2 Provide polished chromium-plated pendent sprinklers below suspended ceilings.

Page 24: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 6

.3 Provide corrosion-resistant sprinkler heads and sprinkler head guards in

accordance with NFPA 13.

.4 Deflector: not more than 75 mm below suspended ceilings.

2.4 EXISTING SYSTEM

.1 The existing sprinkler system shall remain in service at all times during the project.

Contractor shall take all steps necessary to protect the existing system from damage.

.2 The designer shall show all supervised valves and fire alarm devices on the drawing, for

co-ordination with other trades.

2.5 SUPERVISORY SWITCHES

.1 General: to ANSI/NFPA 13 and ULC listed for fire service. Switches are supplied and

installed by sprinkler contractor.

.2 Valves:

.1 Mechanically attached to valve body, with normally open and normally closed

contacts and supervisory capability.

.3 Pressure or flow switch type:

.1 With normally open and normally closed contacts and supervisory capability.

.2 Provide switch with circuit opener or closer for automatic transmittal of alarm

over facility fire alarm system.

.3 Wiring into building fire alarm system- by other trade.

.4 Connection of switch: Section - Fire Alarm Systems (See Electrical).

2.6 PRESSURE GAUGES

.1 ULC listed and to Section - Thermometers and Pressure Gauges - Piping Systems.

.2 Maximum limit of not less than twice normal working pressure at point where installed.

2.7 PIPE SLEEVES

.1 Provide painted steel pipe sleeves where piping passes through masonry walls, slab floors,

and fire-rated assemblies. Refer directly to architect’s Fire Separation Plan.

.2 Secure sleeves in position and location during construction.

.3 Provide sleeves of sufficient length to pass through entire thickness of each building

assembly.

.4 Provide 2.5 cm minimum clearance between exterior of piping and interior of sleeve or

core-drilled hole.

.1 Firmly pack space with mineral wool insulation.

.2 Seal space at both ends of sleeve or core-drilled hole with plastic waterproof

cement which will dry to firm but pliable mass.

Page 25: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 7

.3 In rated walls and fire-rated floors, seal both ends of pipe sleeves or core-drilled

holes with ULC listed sealant material.

2.8 ESCUTCHEON PLATES

.1 Provide one piece or split hinge type metal plates for piping passing through walls, floors,

and ceilings in exposed spaces.

.2 Provide polished chromium-plated finish on plates in finished areas.

2.9 SIGNS

.1 Attach properly lettered Bilingual and approved metal signs to each valve and alarm

device to ANSI/NFPA 13.

.2 Permanently fix hydraulic design data nameplates to riser of each system.

2.10 SPARE PARTS CABINET

.1 Provide metal cabinet with extra sprinkler heads and sprinkler head wrench adjacent to

each alarm valve. Number and types of extra sprinkler heads as specified in NFPA 13.

Part 3 Execution

3.1 GENERAL

.1 Install, inspect and test in accordance with ANSI/NFPA 13.

.2 The building will be occupied at all times. The contractor shall include for schedule and

work practices which will comply with the owner's directions.

.3 Minimize the interruption of the water supply in the building. When the fire protection

water must be temporarily shut down, co-ordinate the actions with Owner and with local

Fire Dept. Shut-down dates must be scheduled in advance so that life safety measures are

in place for the building.

3.2 PIPE INSTALLATION

.1 Install piping straight and true to bear evenly on hangers and supports. Use the building

structure for support. Do not hang piping from plaster ceilings.

.2 Co-ordinate pipe route with other trades to avoid interference.

.3 Route branch lines around mechanical obstructions where needed.

.4 Identify sprinkler piping and valves according to good practice. Apply red lettered labels

on 6 m spacing. For concealed items, use ID labels on nearest T-bar ceiling track. For

pipe painting, see below.

Page 26: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 8

.5 Keep interior of piping systems clean during installation by means of plugs or other

approved methods. When work is not in progress, securely close open ends of piping to

prevent entry of water and foreign matter.

.6 Inspect piping before placing into position.

3.3 ELECTRICAL CONNECTIONS (by Electrical Trade)

.1 Electrical work associated with this section under Section - Common Work Results - for

Electrical.

.2 Fire alarm system connections as per electrical section.

.3 Control and fire alarm wiring, including connections to fire alarm systems, in accordance

with Electrical Code.

.4 Power wiring in rigid metal conduit or intermediate metal conduit.

3.4 PAINTING OF PIPE SYSTEM (by Sprinkler Co.)

.1 On new systems including exposed piping, hangers, supports, miscellaneous metalwork,

and accessories. Exception: painting not required for concealed piping.

.2 Apply coatings to clean, dry surfaces, using clean brushes. Colour: fire engine 'red'.

.3 Shield sprinkler heads with protective covering while painting is in progress.

.4 Upon completion of painting, remove protective covering from sprinkler heads.

.5 Remove sprinkler heads which have been painted and replace with new sprinkler heads.

.6 Piping in Unfinished Areas (such as Service Rooms/ Mech Rooms).

.7 General methods:

.1 Prepare primed steel surfaces with 2 coats of red alkyd gloss enamel

applied to piping.

3.5 FIELD QUALITY CONTROL

.1 Site Test, Inspection:

.1 Perform test to determine compliance with specified requirements.

.2 Test, inspect, and approve piping before covering or concealing. Install auxialiary

fittings on main piping to permit convenient flushing and testing of new systems.

Be responsible for protecting the existing finishes as this building is OCCUPIED

at all times.

.3 Preliminary Tests:

.1 Unless otherwise directed, hydrostatically test each system at 150 psig for

a 2 hour period with no leakage or reduction in pressure.

.2 Flush piping with potable water in accordance with NFPA 13.

Page 27: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 21 13 13

Sudbury, Ont. WET PIPE SPRINKLER SYSTEMS

GENIVAR #131-13878-00

April 2013 Page 9

.3 Arrange for safe disposal of discharge water after flushing, without

damage to building.

.4 Piping above suspended ceilings: to be tested, inspected, and approved

before installation of ceilings.

.5 Test alarms and other devices.

.6 Test water flow alarms by flowing water through test connection or test

valve. When tests have been completed and corrections made, submit

signed and dated certificate in accordance with NFPA 13.

.4 Formal Tests and Inspections:

.1 Do not submit request for formal test and inspection until preliminary test

and corrections are completed and approved.

.2 Repeat required tests as directed.

.3 Correct defects and make additional tests until systems comply with local

authorities.

.4 Furnish appliances, equipment, instruments, connecting devices, and

personnel for tests.

.5 Local Authority Having Jurisdiction will witness formal tests and approve

systems before they are accepted.

.2 Proceed in accordance with General Specs Section - Cleaning.

.3 Upon completion and verification of installation, remove surplus materials, excess

materials, rubbish, tools and equipment. Leave work area broom clean.

.4 Prepare Certificate of Above Ground Piping, for inclusion in owner’s manuals.

.5 Submit close-out documents, and as-built drawings according to part 1 of this spec

section.

END OF SECTION

Page 28: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 00

Sudbury, Ontario COMMON WORK RESULTS FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 RELATED SECTIONS

.1 Testing, Adjusting, and Balancing of Mechanical Systems.

1.2 MAINTENANCE

.1 Furnish spare parts in accordance with Section - Closeout Submittals and as follows:

.1 One spare filter cartridge or set of filters for each filter or filter bank on the

project, in addition to final operating set.

.2 Provide one set of special tools required to service equipment as recommended by

manufacturers.

1.3 CO-ORDINATION WORK.

.1 The contractor shall review drawings in the tender documents. Each trade shall be aware

of the work being shown in the full set of drawings. Where errors or discrepancies exist,

notify consultant at least 3 days before closing date.

.2 Review your quote with the General Contractor to co-ordinate your on-site

responsibilities.

.3 Mechanical trade shall supply roof curb for ERV unit and RTU which penetrate the roof

with ducts. The minimum curb height is 450mm. Where air intakes hood on the units are

low the height of intake hood shall be modified and increased to ensure the air intake will

remain above the snow-line.

.4 On duct penetrations through roof: prepare proper flashing and duct curb to allow roof

materials to be sealed water-tight. If methods are not set by the roofing co. then request

diagrams to show flashing installation.

.5 These specs must be read by the installers. This is to supplement the information on the

drawings.

.6 MAKING HOLES: Mech. Trade is responsible for making holes up-to and including 200

mm in size (for small duct penetrations.) For 201 mm and larger, Mech. Trade shall mark

the openings and co-ordinate with the general contractor.

.7 Coordinate work with general contractor where ducts must be concealed inside the duct

chase and new bulkhead in both floors.

.8 Mechanical Division shall carry the total controls cost, air balancing and co-ordinate the

work of the Controls personnel.

.9 Mechanical Division shall carry the total fire protection cost and co-ordinate the work of

the sprinkler installation.

Page 29: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 00

Sudbury, Ontario COMMON WORK RESULTS FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 2

1.4 CLOSEOUT SUBMITTALS

.1 Provide operation and maintenance data for incorporation into manual specified in specs.

.2 Present the instructions in an indexed three ring hard cover binders, with spine label

project indicator. Include all shop drawings, permits and warrantee certificates in the

manual.

.3 Operation and maintenance manual to be approved by, and final copies deposited with,

consultants before final inspection.

.4 Operation data to include:

.1 Control schematics for each system including environmental controls.

.2 Description of each system and its controls.

.3 Description of operation of each system at various loads together with reset

schedules and seasonal variances.

.4 Operation instruction for each system and each component.

.5 Description of actions to be taken in event of equipment failure. .Maintenance

data shall include:

.6 Servicing, maintenance, operation and trouble-shooting instructions for each item

of equipment.

.7 Data to include schedules of tasks, frequency, tools required and task time.

.5 Performance data to include:

.1 Equipment manufacturer's performance data sheets with point of operation as left

after commissioning is complete.

.2 Testing, adjusting and balancing reports.

.6 Approvals:

.1 Submit 3 copies of draft Operation and Maintenance Manual to Consultant for

approval before the final inspection times.

.2 Make changes as required and re-submit as directed by Consultant.

.7 Additional data:

.1 Prepare and insert into operation and maintenance manual when need for same

becomes apparent during demonstrations and instructions specified above.

1.5 SHOP DRAWINGS AND PRODUCT DATA

.1 Submit shop drawings and product data in accordance with General Sections.

Page 30: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 00

Sudbury, Ontario COMMON WORK RESULTS FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 3

.2 The Contractor shall check/ review the technical pages of the shop drawings, before

submission. Documents will be returned when supplier errors are found. Replace shop

drawings as directed.

.3 Shop drawings and product data shall show:

.1 Mounting arrangements.

.2 Operating and maintenance clearances. eg. access door swing spaces.

.4 Shop drawings and product data shall be accompanied by:

.1 Detailed drawings of bases, supports, and anchor bolts.

.2 Acoustical sound power data, where applicable.

.3 Points of operation on performance curves.

.4 Manufacturer to certify as to current model production.

.5 Certification of compliance to applicable codes.

1.6 AS-BUILT DRAWINGS

.1 Site records:

.1 Consultant will provide 1 set of mechanical drawings. Mark there-on all changes

as work progresses and as changes occur. This shall include changes to gas

piping, mechanical systems, control systems and low voltage control wiring.

.2 On a weekly basis, transfer information to show all work as actually installed.

.3 Use different colour waterproof ink for each service.

.4 Make available (on-site) for reference purposes and inspection at all times.

.2 As-built drawings:

.1 Prior to start of Testing, Adjusting and Balancing (TAB), finalize production of

as-built drawings.

.2 Identify each drawing in lower right hand corner in letters at least 12 mm high as

follows: - "AS BUILT DRAWINGS: THIS DRAWING HAS BEEN REVISED

TO SHOW MECHANICAL SYSTEMS AS INSTALLED" (Signature of

Contractor) (date).

.3 Submit to Consultant for approval and make corrections as directed.

.4 TAB to be performed using as-built drawings.

.3 Submit copies of as-built drawings for inclusion in final TAB report.

Page 31: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 00

Sudbury, Ontario COMMON WORK RESULTS FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 4

Part 2 Products

2.1 Reserved

Part 3 Execution

3.1 PAINTING REPAIRS AND RESTORATION

.1 During construction, some finishes on new equipment may become damaged. Prime and

touch up marred finished paintwork to match original.

.2 Restore to new condition, finishes which have been damaged.

.3 Where finishes alone will not restore the product, replace the component with a new one.

3.2 FIELD QUALITY CONTROL

.1 Before inspection times, the mechanical supervisor shall check the work and make

corrections where the work does not comply with the project documents. This is the first

level of quality control.

.2 After the quality has met the supervisor’s standards, then notify the consultant for

construction review/ site visit.

3.3 DEMONSTRATION/ OPERATING AND MAINTENANCE INSTRUCTIONS

.1 Supply tools, equipment and personnel to demonstrate and instruct operating and

maintenance personnel in operating, controlling, adjusting, trouble-shooting and servicing

of all systems and equipment during regular work hours, prior to acceptance.

.2 Use operation and maintenance manual, as-built drawings, audio visual aids, etc. as part of

instruction materials.

3.4 PROTECTION

.1 Protect all work and materials before and after erection from weather and other hazards

and keep in a clean and orderly manner. Seal ductwork during construction to prevent

dust contamination.

.2 Use plastic and tape where practical. Cap all openings during construction to prevent

contamination.

.3 Protect mechanical equipment having a baked enamel finish by covering with

polyethylene sheet securely held in place.

3.5 ELECTRICAL WORK.

.1 Electrical work (related to mechanical systems) shall conform to the electrical drawing,

and include the following:

Page 32: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 00

Sudbury, Ontario COMMON WORK RESULTS FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 5

.2 Transformers (for mech. systems and controls) shall be sized and supplied by mechanical

trade.

.3 Wiring above 50 V shall be done by Electrical trade. And, on power supply to the Control

Panels/ control devices: wiring to be arranged by mech. trade.

.4 Control wiring, 50 V and lower, is the responsibility of the mech. trade.

.5 Mech. trade shall supply mechanical-related controls, motors, starters, isolation switches,

relays, thermostats, transformers, and required disconnect switches. Co-ordinate the

responsibilities with the Controls trade.

.6 HVAC items requiring line voltage above 50 V will be installed by Elec. trade.

END OF SECTION

Page 33: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 54

Sudbury, Ontario MECHANICAL IDENTIFICATION

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 Section Includes:

.1 Materials and requirements for the identification of piping systems, duct work,

valves and controllers, including the installation and location of identification

systems.

1.2 REFERENCES

.1 Canadian General Standards Board (CGSB)

.1 CAN/CGSB-1.60-[97], Interior Alkyd Gloss Enamel.

.2 CAN/CGSB-24.3-[92], Identification of Piping Systems.

1.3 QUALITY ASSURANCE

.1 Quality assurance submittals: submit following in accordance with Section - Submittal

Procedures.

Part 2 Products

2.1 MANUFACTURER'S EQUIPMENT NAMEPLATES

.1 Metal or plastic laminate nameplate mechanically fastened to each piece of equipment by

manufacturer.

.2 Information to include, as appropriate:

.1 Equipment: manufacturer's name, model, size, serial number, capacity.

.2 Motor: voltage, Hz, phase, power factor, duty, frame size.

2.2 SYSTEM NAMEPLATES

.1 Colours:

.1 Hazardous: red letters, white background.

.2 Elsewhere: black letters, white background (except where required otherwise by

applicable codes).

.2 System names to be clearly visible and legible.

2.3 PIPING SYSTEMS GOVERNED BY CODES

.1 Identification:

.1 Natural gas piping systems: to CSA B149 the gas code.

2.4 IDENTIFICATION OF PIPING SYSTEMS (not used)

.1 Identify contents by background colour marking, pictogram (as necessary), legend;

direction of flow by arrows.

Page 34: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 54

Sudbury, Ontario MECHANICAL IDENTIFICATION

GENIVAR #131-13878-00

April 2013 Page 2

.2 Legend:

.1 Block capitals to sizes and colours listed in CAN/CGSB 24.3.

.3 Arrows showing direction of flow:

.1 Outside diameter of pipe or insulation less than 75 mm: 100 mm long x 50 mm

high.

.2 Outside diameter of pipe or insulation 75 mm and greater: 150 mm long x 50 mm

high.

.3 Use double-headed arrows where flow is reversible.

.4 Extent of background colour marking:

.1 To full circumference of pipe or insulation.

.2 Length to accommodate pictogram, full length of legend and arrows.

.5 Materials for background colour marking, legend, arrows:

.1 Pipes and tubing 20 mm and smaller: waterproof and heat-resistant pressure

sensitive plastic marker tags.

.2 Other pipes: pressure sensitive vinyl with protective overcoating, waterproof

contact adhesive undercoating, suitable for ambient of 100% RH and continuous

operating temperature of 150 degrees C and intermittent temperature of 200

degrees C.

.3 Colours for legends, arrows: to following table:

.4

Background colour: Legend, arrows:

Yellow BLACK

Green WHITE

Red WHITE

2.5 CONTROLS COMPONENTS IDENTIFICATION

.1 Identify all systems, equipment, components, controls, sensors with system nameplates

specified in this section.

.2 Inscriptions to include function and (where appropriate) fail-safe position.

Part 3 Execution

3.1 MANUFACTURER'S INSTRUCTIONS

.1 Compliance: comply with manufacturer's written recommendations or specifications,

including product technical bulletins, handling, storage and installation instructions, and

datasheet.

3.2 INSTALLATION

.1 Perform work in accordance with CAN/CGSB-24.3 except as specified otherwise.

.2 Provide ULC or CSA registration plates as required by respective agency.

Page 35: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 54

Sudbury, Ontario MECHANICAL IDENTIFICATION

GENIVAR #131-13878-00

April 2013 Page 3

.3 Identify systems, piping, controls, and equipment to allow future maintenance work to be

accomplished without confusion.

3.3 NAMEPLATES

.1 Locations: In conspicuous location to facilitate easy reading and identification from

operating floor.

.2 Standoffs: Provide for nameplates on hot and/or insulated surfaces.

.3 Protection:

.1 Do not paint, insulate or cover.

3.4 LOCATION OF IDENTIFICATION ON DUCTWORK SYSTEMS

.1 At point immediately upstream of major manually operated or automatically controlled

valves, and dampers. Where this is not possible, place identification as close as possible,

preferably on upstream side.

.2 Identification easily and accurately readable from usual operating areas and from access

points.

3.5 CLEANING

.1 Upon completion and verification of performance of installation, remove surplus

materials, excess materials, rubbish, tools and equipment.

END OF SECTION

Page 36: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 93

Sudbury, Ontario TESTING, ADJUSTING AND BALANCING FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 TAB is used throughout this Section to describe the process, methods and requirements of

testing, adjusting and balancing for HVAC.

.2 TAB means to test, adjust and balance to perform in accordance with requirements of

Contract Documents and to do other work as specified in this section.

.3 The contractor shall include the costs for all expenses related to TAB, including travel and

follow-up site visits to correct comfort problems and to adjust the system operation.

.4 For sequence of operation refer to mechanical drawing M05.

1.2 QUALIFICATIONS OF TAB PERSONNEL

.1 Submit names of personnel to perform TAB to Consultant within 30 days of award of

contract.

.2 Provide documentation confirming qualifications, successful experience.

.3 TAB: performed in accordance with the requirements of standard under which TAB

Firm's qualifications are approved:

.1 Sheet Metal and Air Conditioning Contractors' National Association (SMACNA),

HVAC TAB HVAC Systems - Testing, Adjusting and Balancing-2002.

.4 Use TAB Standard provisions, including checklists, and report forms.

1.3 PURPOSE OF TAB

.1 Test to verify proper and safe operation, determine actual point of performance, evaluate

qualitative and quantitative performance of equipment, systems and controls at design,

average and low loads using actual or simulated loads

.2 Adjust and regulate equipment and systems to meet specified performance requirements

and to achieve specified interaction with other related systems under normal and

emergency loads and operating conditions.

.3 Balance systems and equipment to regulate air flow rates to match load requirements over

full operating ranges.

1.4 EXCEPTIONS

.1 TAB of systems and equipment regulated by codes, standards to satisfaction of authority

having jurisdiction.

Page 37: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 93

Sudbury, Ontario TESTING, ADJUSTING AND BALANCING FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 2

1.5 CO-ORDINATION

.1 Schedule time required for TAB (including repairs, re-testing) into project construction

and completion schedule to ensure completion before acceptance of project.

.2 Do TAB of each system independently and subsequently, where interlocked with other

systems, in unison with those systems.

1.6 PRE-TAB REVIEW

.1 Review contract documents before project construction is started and confirm in writing to

Consultant to confirm the adequate provisions for TAB and other aspects of design and

installation pertinent to success of TAB.

.2 During construction, co-ordinate location and installation of TAB devices, equipment,

accessories, measurement test ports and fittings to match requirements of the balancing

company.

1.7 START-UP

.1 Follow start-up procedures as recommended by equipment manufacturer unless specified

otherwise.

1.8 OPERATION OF SYSTEMS DURING TAB

.1 Operate systems for length of time required for TAB and as required by Consultant for

verification of TAB reports.

1.9 START OF TAB

.1 Notify Consultant 7 days prior to start of TAB.

.2 Start TAB when building is essentially completed, including:

.3 Installation of ceilings affecting TAB.

.4 Application of weather-stripping, sealing, and caulking.

.5 Pressure, leakage, other tests specified elsewhere Division 23.

.6 Provisions for TAB installed and operational.

.7 Start-up, verification for proper, normal and safe operation of mechanical and associated

electrical and control systems affecting TAB including but not limited to:

.1 Proper thermal overload protection in place for electrical equipment.

.2 Air systems:

.1 Filters in place, clean.

.2 Duct systems clean.

.3 Ducts, ceiling plenums are airtight to within specified tolerances.

.4 Correct fan rotation.

Page 38: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 93

Sudbury, Ontario TESTING, ADJUSTING AND BALANCING FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 3

.5 Fire dampers, volume control dampers installed and open.

.6 Coil fins combed, clean.

.7 Access doors, installed, closed.

.8 Outlets installed volume control dampers open.

1.10 ACCURACY TOLERANCES

.1 Measured values accurate to within plus or minus 5 % of actual values.

1.11 INSTRUMENTS

.1 Calibrate within 3 months of TAB. Provide certificate of calibration to Consultant if

requested.

1.12 SUBMITTALS

.1 Submit, prior to commencement of TAB:

.2 Proposed methodology and procedures for performing TAB if different from referenced

standard.

1.13 TAB REPORT

.1 TAB report to show results in units similar to the drawings, and to include:

.1 Project record drawings.

.2 System schematics.

.2 Submit 3 copies of TAB Report to Consultant for verification and approval, in English; in

D-ring binders, complete with index tabs.

1.14 VERIFICATION

.1 Reported results subject to verification by Consultant.

.2 Provide personnel and instrumentation to verify up to 30 % of reported results.

.3 Number and location of verified results as directed by Consultant.

.4 Pay costs to repeat TAB as required to satisfaction of Consultant.

1.15 SETTINGS

.1 After TAB is completed to satisfaction of Consultant, replace drive guards, close access

doors, lock devices in set positions, and ensure sensors are at required settings.

.2 Permanently mark settings to allow restoration at any time during life of facility. Do not

eradicate or cover markings.

Page 39: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 93

Sudbury, Ontario TESTING, ADJUSTING AND BALANCING FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 4

1.16 COMPLETION OF TAB

.1 TAB considered complete when final TAB Report is received and approved by the

Consultant.

1.17 AIR SYSTEMS

.1 Standard: TAB to most stringent of this section or SMACNA.

.2 Do TAB of systems, equipment, components, controls specified in the mechanical

sections.

.3 Qualifications: personnel performing TAB to have minimum 5 years experience in this

type of building project.

.4 Quality assurance: perform TAB under direction of a qualified supervisor.

.5 Measurements: to include equipment, components, controls: air velocity, static pressure,

flow rate, pressure drop (or loss), temperatures (dry bulb, wet bulb, dewpoint), duct

cross-sectional area, RPM, electrical power, voltage, vibration.

.6 Locations of equipment measurements: to include as appropriate:

.1 Inlet and outlet of dampers, filter, coil, fan, other equipment causing changes in

conditions.

.2 At controllers, controlled device.

.7 Locations of systems measurements to include (as a minimum): main ducts, main branch,

sub-branch, run-out (or grille, register or diffuser).

1.18 OTHER TAB REQUIREMENTS

.1 Zone pressure differences:

.1 Adjust new HVAC systems, equipment, controls to establish slightly positive air

pressure differentials in related to outside air, with systems in each combination of

normal operating modes.

1.19 POST-OCCUPANCY TAB

.1 Participate in systems checks twice during Warranty Period. Check - #1 approximately 3

months after acceptance and Check #2 within 1 month before the end of Warranty Period.

Page 40: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 05 93

Sudbury, Ontario TESTING, ADJUSTING AND BALANCING FOR HVAC

GENIVAR #131-13878-00

April 2013 Page 5

Part 2 Products

2.1 NOT USED

Part 3 Execution

3.1 NOT USED

END OF SECTION

Page 41: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 07 13

Sudbury, Ontario THERMAL INSULATION FOR DUCTING

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 RELATED SECTIONS

.1 Section- Submittal Procedures.

1.2 REFERENCES

.1 American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE)

.1 ANSI/ASHRAE/IESNA 90.1-01, SI; Energy Standard for Buildings Except

Low-Rise Residential Buildings.

.2 American Society for Testing and Materials International, (ASTM)

.1 ASTM C449/C449M-00, Standard Specification for Mineral

Fiber-Hydraulic-Setting Thermal Insulating and Finishing Cement.

.2 ASTM C553-00, Specification for Mineral Fiber Blanket Thermal Insulation for

Commercial and Industrial Applications.

.3 ASTM C612-00a, Specification for Mineral Fiber Block and Board Thermal

Insulation.

.3 Canadian General Standards Board (CGSB)

.1 CGSB 51-GP-52Ma-89, Vapour Barrier, Jacket and Facing Material for Pipe,

Duct and Equipment Thermal Insulation.

.4 Thermal Insulation Association of Canada (TIAC): National Insulation Standards

(R1999).

.5 Underwriters Laboratories of Canada (ULC)

.1 CAN/ULC-S102-M88(R2000), Surface Burning Characteristics of Building

Materials and Assemblies.

1.3 DEFINITIONS

.1 For purposes of this section:

.1 "CONCEALED" - insulated mechanical services and equipment in suspended

ceilings and non-accessible chases and furred-in spaces.

.2 "EXPOSED" - will mean "not concealed" as defined herein.

.3 Insulation systems - insulation material, fasteners, jackets, and other accessories.

.2 TIAC Codes:

.1 CRD: Code Round Ductwork,

.2 CRF: Code Rectangular Finish.

Page 42: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 07 13

Sudbury, Ontario THERMAL INSULATION FOR DUCTING

GENIVAR #131-13878-00

April 2013 Page 2

1.4 SHOP DRAWINGS

.1 Submit for approval: insulation products, material description, manufacturer’s catalogue

literature related to installation, fabrication for duct jointing recommendations.

1.5 MANUFACTURERS' INSTRUCTIONS

.1 Installation instructions to include procedures used and installation standards achieved.

1.6 QUALIFICATIONS

.1 Installer: specialist in performing work of this section, and have at least 3 years successful

experience in this size and type of project.

1.7 DELIVERY, STORAGE AND HANDLING

.1 Deliver materials to site in original factory packaging, labelled with manufacturer's name,

address.

.2 Protect from weather and construction traffic.

.3 Protect against damage from any source.

1.8 WASTE MANAGEMENT AND DISPOSAL

.1 Separate and recycle waste materials.

.2 Remove from site and dispose of packaging materials at appropriate recycling facilities.

Part 2 Products

2.1 FIRE AND SMOKE RATING

.1 In accordance with CAN/ULC-S102:

.1 Maximum flame spread rating: 25.

.2 Maximum smoke developed rating: 50.

2.2 INSULATION

.1 Mineral fibre: as specified includes glass fibre, rock wool.

.2 Thermal conductivity ("k" factor) not to exceed specified values at 24oC mean

temperature when tested in accordance with ASTM C335.

.3 TIAC Code C-1: Rigid mineral fibre board to CAN/CGSB 51.10, with factory applied

vapour retarder jacket to CGSB 51-GP-52Ma (as scheduled in PART 3 of this Section).

.4 TIAC Code C-2: Mineral fibre blanket to CAN/CGSB 51.11 faced with factory applied

vapour retarder jacket to CGSB 51-GP-52Ma (as scheduled in PART 3 of this section).

Page 43: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 07 13

Sudbury, Ontario THERMAL INSULATION FOR DUCTING

GENIVAR #131-13878-00

April 2013 Page 3

.1 Mineral fibre: to ASTM C553.

.2 Jacket: to CGSB 51-GP-52Ma.

.3 Maximum "k" factor: to CAN/CGSB 51.11

2.3 JACKETS

.1 Canvas:

.1 220 gm/m2 cotton, plain weave, treated with dilute fire retardant lagging adhesive

to ASTM C921.

.2 Lagging adhesive: Compatible with insulation.

2.4 ACCESSORIES

.1 Vapour retarder lap adhesive:

.1 Water based, fire retardant type, compatible with insulation.

.2 Indoor Vapour Retarder Finish:

.1 Vinyl emulsion type acrylic, compatible with insulation.

.3 Tape: self-adhesive, aluminum, reinforced, 50 mm wide minimum.

.4 Canvas adhesive: washable.

.5 Fasteners: 2 mm diameter pins with 35 mm square clips, length to suit thickness of

insulation.

Part 3 Execution

3.1 PRE-INSTALLATION REQUIREMENTS

.1 Pressure testing of ductwork systems complete, witnessed and certified.

.2 Surfaces clean, dry, free from foreign material.

3.2 INSTALLATION

.1 SCOPE: Insulate supply air (cooling) ductwork, mains and branches, and where

indicated.

.2 Apply materials in accordance with manufacturers instructions and as indicated.

.3 Use two layers with staggered joints when required nominal thickness exceeds 75 mm.

.4 Maintain uninterrupted continuity and integrity of vapour barrier and finishes.

.1 Hangers, supports to be outside vapour barrier jacket.

.2 Avoid un-necessary holes in the vapour barrier.

.5 Supports, Hangers:

Page 44: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 07 13

Sudbury, Ontario THERMAL INSULATION FOR DUCTING

GENIVAR #131-13878-00

April 2013 Page 4

.1 Apply high compressive strength insulation where insulation may be compressed

by weight of ductwork.

.6 Fasteners: At 300 mm oc in horizontal and vertical directions, minimum two rows each

side.

.7 Use stand-off brackets for duct-mounted control accessories.

3.3 DUCTWORK INSULATION SCHEDULE

.1 Insulation types and thicknesses: Conform to following table:

TIAC Code Vapour Retarder Thickness (mm)

Rectangular cold and

dual temperature supply

air ducts

C-1 yes 25

Round cold and dual

temperature supply air

ducts

C-2 yes 25

Rectangular warm air

ducts

C-1 no 25

Round warm air ducts C-1 no 25

Supply, return and

exhaust ducts exposed

in space being served

none

Outside air ducts to

mixing plenum

C-1 yes 50

Mixing plenums C-1 yes 25

Exhaust duct between

fan and outdoors

C-1 yes 25

Rectangular ducts

outside

C-1 special 50

Round ducts outside C-1 special 50

Acoustically lined ducts none

END OF SECTION

Page 45: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 11 23

Sudbury, Ontario FACILITY NATURAL GAS PIPING

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 Section Includes:

.1 Materials and installation for piping, valves and fittings for gas fired equipment.

.2 Related Sections:

.1 Section – Common Work Result Work for HVAC.

1.2 REFERENCES

.1 American Society for Testing and Materials International (ASTM)

.1 ASTM A47/A47M-[99(2004)], Standard Specification for Ferritic Malleable Iron

Castings.

.2 ASTM A53/A53M-[04], Standard Specification for Pipe, Steel, Black and

Hot-Dipped, Zinc Coated, Welded and Seamless.

.2 Canadian Standards Association (CSA International)

.1 CSA W47.1-[03], Certification of Companies for Fusion Welding of Steel.

.3 Canadian Standards Association (CSA)/Canadian Gas Association (CGA)

.1 CAN/CSA B149.1HB, Natural Gas and Propane Installation Code Handbook.

.4 Health Canada/Workplace Hazardous Materials Information System (WHMIS)

.1 Material Safety Data Sheets (MSDS).

1.3 SUBMITTALS

.1 Product Data:

.1 Submit manufacturer's printed product literature, specifications and datasheet for

piping, fittings and equipment.

.2 Test Reports: submit signed test reports from licensed personnel, to show that the gas

piping system is free of leaks before connection to roof top units. Follow test requirements

of the Gas Code.

1.4 QUALITY ASSURANCE

.1 Pre-Installation Meeting:

.1 Verify project requirements.

.2 Review installation .

.3 Co-ordination with other building sub trades.

.4 Review equipment manufacturer's installation instructions and warranty

requirements.

.2 Health and Safety:

Page 46: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 11 23

Sudbury, Ontario FACILITY NATURAL GAS PIPING

GENIVAR #131-13878-00

April 2013 Page 2

.1 Do construction occupational health and safety in accordance with local

regulations.

Part 2 Products

2.1 PIPE

.1 Steel pipe: to ASTM A53/A53M, Schedule 40, seamless as follows:

.1 NPS 1/2 to 2, screwed.

.2 NPS2 1/2 and over, plain end welded.

2.2 JOINTING MATERIAL

.1 Screwed fittings: industry-approved paste.

.2 Welded fittings: to CSA W47.1.

2.3 FITTINGS

.1 Steel pipe fittings, screwed, or welded:

.1 Malleable iron: screwed, banded, Class 150.

.2 Welding: butt-welding fittings.

.3 Unions: malleable iron, brass to iron, ground seat, to ASTM A47/A47M.

.4 Nipples: schedule 40, to ASTM A53/A53M.

2.4 VALVES

.1 Provincial Code approved, lubricated [ball] type.

Part 3 Execution

3.1 MANUFACTURER'S INSTRUCTIONS

.1 Compliance: For connection to equipment, comply with manufacturer's written

recommendations or specifications, including product technical bulletins, handling,

storage and installation instructions, and datasheet.

3.2 PIPING

.1 Paint new gas piping and fittings.

.2 Install drip points:

.1 At low points in piping system.

.2 At connections to equipment.

3.3 VALVES

.1 Install valves with stems upright or horizontal unless otherwise approved by Consultant.

Page 47: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 11 23

Sudbury, Ontario FACILITY NATURAL GAS PIPING

GENIVAR #131-13878-00

April 2013 Page 3

.2 Install valves at branch take-offs to isolate pieces of equipment, and as indicated.

3.4 FIELD QUALITY CONTROL

.1 Perform pressure test on new gas lines from main gas to new RTU to check for gas

integrity. Follow pressure test procedure from Natural Gas and Propane Installation Code

6.22.2. Submit report to Consultant following test.

.2 Confirm if there is gas required in the building, where other gas-fired equipment is

installed. Restore operation of those systems as necessary.

.3 Site Tests/Inspection:

.1 Test system in accordance with CAN/CSA B149.1 and requirements of authorities

having jurisdiction. This is to be done before final connections to equipment.

.2 Before tests, isolate and make safe the other equipment which is connected to the

gas piping. Then restore regular operation after test period.

.4 Obtain reports within 3 days of testing and submit immediately to Consultant.

3.5 ADJUSTING

.1 Purging: purge after pressure test in accordance with CAN/CSA B149.1.

.2 Pre-Start-Up Inspections:

.1 Check gas trains, entire installation is approved by authority having jurisdiction.

3.6 CLEANING

.1 Cleaning: in accordance with CAN/CSA B149.1.

.2 Perform cleaning operations in accordance with manufacturer's recommendations.

.3 Upon completion and verification of performance of installation, remove surplus

materials, excess materials, rubbish, tools and equipment.

END OF SECTION

Page 48: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 31 14

Sudbury, Ontario METAL DUCTS - LOW PRESSURE TO 500 PA

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 Section Includes:

.1 Materials and installation of low-pressure metallic ductwork, joints and

accessories.

.2 Related Sections:

.1 Section - Firestopping.

1.2 REFERENCES

.1 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.

(ASHRAE).

.2 American Society for Testing and Materials International, (ASTM).

.1 ASTM A653/A653M-03, Standard Specification for Steel Sheet, Zinc Coated

(Galvanized) or Zinc-Iron Alloy Coated (Galvannealed) by the Hot-Dip Process.

.3 National Fire Protection Association (NFPA).

.1 NFPA 90A-02, Standard for the Installation of Air-Conditioning and Ventilating

Systems.

.4 Sheet Metal and Air Conditioning Contractors' National Association (SMACNA).

.1 SMACNA HVAC Duct Construction Standards - Metal and Flexible, 2nd Edition

1995 and Addendum No. 1, 1997.

1.3 SUBMITTALS

.1 Submit shop drawings and product data in accordance with Section - Submittal

Procedures.

.2 Product Data: submit documents for the following:

.1 Sealants.

.2 Test port.

.3 Proprietary Joints.

.4 Flexible duct connections

1.4 QUALITY ASSURANCE

.1 Certification of Ratings:

.1 Catalogue or published ratings shall be those obtained from tests carried out by

manufacturer or independent testing agency signifying adherence to codes and

standards.

.2 Health and Safety:

Page 49: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 31 14

Sudbury, Ontario METAL DUCTS - LOW PRESSURE TO 500 PA

GENIVAR #131-13878-00

April 2013 Page 2

.1 Do construction occupational health and safety in accordance with the site Health

and Safety Requirements.

Part 2 Products

2.1 SEAL CLASSIFICATION

.1 Classification as follows:

Maximum Pressure Pa SMACNA Seal Class

500 C

250 C

125 C

125 Unsealed

.2 Seal classification: THIS PROJECT WILL ADHERE TO ‘CLASS C’.

.1 Class A: longitudinal seams, transverse joints, duct wall penetrations and

connections made airtight with sealant and tape.

.2 Class B: longitudinal seams, transverse joints and connections made airtight with

sealant tape or combination thereof.

.3 Class C: transverse joints and connections made air tight with sealant and tape,

with longitudinal seams unsealed.

.4 Unsealed seams and joints.

2.2 SEALANT

.1 Sealant: oil resistant, polymer type flame resistant duct sealant. Temperature range of

minus 30 degrees C to plus 93 degrees C.

2.3 TAPE

.1 Tape: polyvinyl treated, aluminum tape, 50 mm wide.

2.4 DUCT LEAKAGE

.1 Allowable leakage to be strictly controlled in accordance with SMACNA Manual, and

controlled by mech. project supervisor.

.2 Follow good practice on sealing methods.

2.5 FITTINGS

.1 Fabrication: to SMACNA.

.2 Radiused elbows.

.1 Rectangular: standard radius: 1.5 times width of duct.

.2 Round: five-piece. Centreline radius: 1.5 times the duct diameter.

.3 Mitred elbows, rectangular:

.1 To 400 mm: with double thickness turning vanes.

Page 50: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 31 14

Sudbury, Ontario METAL DUCTS - LOW PRESSURE TO 500 PA

GENIVAR #131-13878-00

April 2013 Page 3

.2 Over 400 mm: with double thickness turning vanes.

.4 Branches:

.1 Rectangular main and branch: with radius on branch 1.5 times width of duct 45

degrees entry on branch.

.2 Round main and branch: enter main duct at 45 degrees with conical connection.

.3 Provide volume control damper in branch duct near connection to main duct.

.5 Transitions:

.1 Diverging: 20 degrees maximum included angle.

.2 Converging: 30 degrees maximum included angle.

.6 Offsets:

.1 radiused elbows.

.7 Obstruction deflectors: maintain full cross-sectional area of duct.

2.6 FIRE STOPPING

.1 Retaining angles around duct, on both sides of fire separation where is necessary in

accordance with Section - Fire stopping.

.2 Fire stopping material and installation must not distort duct.

2.7 GALVANIZED STEEL

.1 Lock forming quality: to ASTM A653/A653M, Z90 zinc coating.

.2 Thickness, fabrication and reinforcement: to SMACNA.

.3 Joints: to SMACNA proprietary manufactured duct joint. Proprietary manufactured

flanged duct joint to be considered to be a class A seal.

2.8 HANGERS AND SUPPORTS (where is necessary)

.1 Hangers and Supports:

.1 Strap hangers: of same material as duct but next sheet metal thickness heavier

than duct.

.1 Maximum size duct supported by strap hanger: 500 mm.

.2 Hanger configuration: to ASHRAE and SMACNA.

.3 Hangers: black steel angle with galvanized steel rods to SMACNA and the

following table:

Duct Size Angle Size Rod Size

(mm) (mm) (mm)

up to 750 25 x 25 x 3 6

751 to 1050 40 x 40 x 3 6

1051 to 1500 40 x 40 x 3 10

1501 to 2100 50 x 50 x 3 10

2101 to 2400 50 x 50 x 5 10

Page 51: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 31 14

Sudbury, Ontario METAL DUCTS - LOW PRESSURE TO 500 PA

GENIVAR #131-13878-00

April 2013 Page 4

Duct Size Angle Size Rod Size

2401 and over 50 x 50 x 6 10

.4 Upper hanger attachments:

.1 For concrete: manufactured concrete inserts.

.2 For steel joist:manufactured joist clamp steel plate washer.

.3 For steel beams: manufactured beam clamps:

Part 3 Execution

3.1 GENERAL

.1 Do work in accordance with NFPA 90A and SMACNA.

.2 Do not break continuity of insulation vapour barrier with hangers or rods.

.1 Insulate strap hangers 100 mm beyond insulated duct.

.3 Support risers in accordance with SMACNA guidelines.

.4 Install breakaway joints in ductwork on both sides of fire separation.

.5 Manufacture duct in lengths and diameter to accommodate installation of acoustic duct

lining, where necessary.

.6 Install test ports around ductwork, to permit easy progress of TAB work; and for

verification of system performance.

3.2 HANGERS

.1 Strap hangers: install in accordance with SMACNA.

.2 Angle hangers: complete with locking nuts and washers.

.3 Hanger spacing: in accordance with the following:

Duct Size Spacing

(mm) (mm)

to 1500 3000

1501 and over 2500

3.3 WATERTIGHT DUCT

.1 Provide watertight duct for:

.1 Fresh air intakes.

.2 Duct risers at the new RTU ports.

3.4 SEALING AND TAPING

.1 Apply sealant to outside of joint to manufacturer's recommendations.

.2 Bed tape in sealant and recoat with minimum of one coat of sealant to manufacturers

recommendations.

Page 52: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 31 14

Sudbury, Ontario METAL DUCTS - LOW PRESSURE TO 500 PA

GENIVAR #131-13878-00

April 2013 Page 5

3.5 LEAKAGE TESTS

.1 Do leakage tests in main duct risers where ducts are connected to the new rooftop package

and ERV unit.

.2 Make trial leakage tests as instructed to demonstrate workmanship.

.3 Complete test starting or concealment Work.

3.6 FIELD QUALITY CONTROL

.1 Contractor's responsibility to include:

.1 Field supervision.

.2 List of valid experience for duct installers.

.3 Demonstration of good practice during all phases of the project.

.4 Remove and replace new duct sections which show poor quality and improper

seals.

END OF SECTION

Page 53: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 00

Sudbury, Ontario DUCT ACCESSORIES

GENIVAR #131-13878-00

April 2013 Page 1

PART 1 General

1.1 RELATED SECTIONS

.1 Section - Submittal Procedures.

1.2 REFERENCES

.1 Sheet Metal and Air Conditioning Contractors' National Association (SMACNA)

.1 SMACNA - HVAC Duct Construction Standards - Metal and Flexible.

1.3 PRODUCT DATA

.1 Submit product data for review by consultants.

.2 Indicate the following:

.1 Flexible connections.

.2 Duct access doors.

.3 Turning vanes.

.4 Instrument test ports.

PART 2 Products

2.1 GENERAL

.1 Manufacture in accordance with SMACNA - HVAC Duct Construction Standards.

.2 Standard of Acceptance: DuctMate, DuroDyne.

2.2 FLEXIBLE CONNECTIONS

.1 Frame: galvanized sheet metal frame 1.6 mm thick with fabric clenched by means of

double locked seams.

.2 Flex Material:

.1 Fire resistant, self extinguishing, neoprene coated glass fabric, temperature rated

at minus 40 deg C to plus 90 deg C, density of 1.3 kg/m2.

2.3 ACCESS DOORS IN DUCTS (where required)

.1 Non-insulated ducts: sandwich construction of same material as duct, one sheet metal

thickness heavier, minimum 0.6 mm thick complete with sheet metal angle frame.

.2 Insulated ducts: sandwich construction of same material as duct, one sheet metal

thickness heavier, minimum 0.6 mm thick complete with sheet metal angle frame and 25

mm thick rigid glass fibre insulation.

.3 Gaskets: neoprene.

Page 54: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 00

Sudbury, Ontario DUCT ACCESSORIES

GENIVAR #131-13878-00

April 2013 Page 2

.4 Hardware:

.1 Doors up to 300 x 300 mm: two sash locks.

.2 301 to 450 mm: four sash locks complete with safety chain.

.3 451 to 1000 mm: piano hinge and minimum two sash locks.

2.4 TURNING VANES

.1 Factory or shop fabricated double thickness with trailing edge, to recommendations of

SMACNA and as indicated.

2.5 INSTRUMENT TEST PORTS

.1 1.6 mm thick steel, zinc plated after manufacture.

.2 Cam lock handles with neoprene expansion plug and handle chain.

.3 28 mm minimum inside diameter. Length to suit insulation thickness.

.4 Neoprene mounting gasket.

PART 3 Execution

3.1 INSTALLATION

.1 Flexible duct connections:

.1 Install in following locations:

.1 Inlets and outlets to supply air units and main fans.

.2 Inlets and outlets of exhaust and return air fans.

.3 As indicated.

.2 Length of connection: 100 mm.

.3 Minimum distance between metal parts when system in operation: 75 mm.

.4 When fan is running:

.1 Ducting on sides of flexible connection to be in alignment.

.2 Ensure slack material in flexible connection.

.2 Access doors (where required):

.1 Size:

.1 Access door to be sized to fit according to the duct size to ensure that

access is not restricted for servicing entry.

.2 250 x 250 mm for viewing.

.3 Other dimensions may be required to suit each access situation.

.2 Locations:

.1 Fire dampers.

.2 Control dampers.

.3 Devices requiring maintenance.

.4 Elsewhere as indicated.

Page 55: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 00

Sudbury, Ontario DUCT ACCESSORIES

GENIVAR #131-13878-00

April 2013 Page 3

.3 Instrument test ports.

.1 Locate to permit easy manipulation of instruments.

.2 Install insulation port extensions as required.

.3 Locations.

.1 For traverse readings:

.1 Ducted inlets to roof and wall exhausters.

.2 Inlets and outlets of other fan systems.

.2 For temperature readings:

.1 At outside air intakes.

.2 In mixed air applications in locations as approved by Consultant.

.3 At inlet and outlet of burners/ heat exchangers.

.4 And as indicated.

.4 Turning vanes:

.1 Install in accordance with recommendations of SMACNA and where indicated.

.2 Use when reduced radius elbows or mitred elbows are fabricated.

END OF SECTION

Page 56: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 14

Sudbury, Ontario DAMPERS - BALANCING

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 Section Includes:

.1 Balancing dampers for mechanical forced air ventilation and heating systems.

1.2 REFERENCES

.1 Sheet Metal and Air Conditioning National Association (SMACNA)

.1 SMACNA HVAC Duct Construction Standards, Metal and Flexible-1985.

1.3 SUBMITTALS

.1 Product Data:

.1 Submit manufacturer's printed product literature, specifications and datasheet in

accordance with Section - Submittal Procedures. Include product characteristics,

performance criteria, and limitations.

Part 2 Products

2.1 GENERAL

.1 Manufacture to SMACNA standards.

2.2 DISC TYPE DAMPERS

.1 Frame: formed, welded, 1.6 mm thick, galvanized steel.

.2 Disc: spin formed, 1.6 mm thick, galvanized steel.

.3 Gasket: extruded neoprene, field replaceable, with 10 year warranty.

.4 Bearings: self-lubricated.

.5 Operator: compatible with damper, linear stroke operator. Position must be lockable with

set-screw.

.6 Performance:

.1 Leakage: in closed position less than 0.001 % of rated air flow.

Page 57: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 14

Sudbury, Ontario DAMPERS - BALANCING

GENIVAR #131-13878-00

April 2013 Page 2

2.3 MULTI-BLADED DAMPERS

.1 Factory manufactured of material compatible with duct.

.2 Opposed blade: configuration, metal thickness and construction to recommendations of

SMACNA.

.3 Maximum blade height: 100 mm.

.4 Bearings: self-lubricating nylon.

.5 Linkage: shaft extension with locking quadrant.

.6 Channel frame of same material as adjacent duct, complete with angle stop.

Part 3 Execution

3.1 MANUFACTURER'S INSTRUCTIONS

.1 Compliance: comply with manufacturer's written recommendations or specifications,

including product technical bulletins, handling, storage and installation instructions, and

datasheet.

3.2 INSTALLATION

.1 Install where required for air balancing systems.

.2 Install in accordance with recommendations of SMACNA and in accordance with

manufacturer's instructions.

.3 Locate balancing dampers in each branch duct, for supply, return and exhaust systems

may require for balancing.

.4 Runouts to registers and diffusers: install disc type damper located as close as possible to

main ducts. .

.5 Dampers: vibration free.

.6 Ensure damper operators are observable and accessible. In final position, lock set-screw

in securely.

3.3 FIELD QUALITY CONTROL

.1 Tests:

.1 Tests to be done before final acceptance, demonstrate that system is functioning as

specified. See Testing, Adjustment and Balancing.

END OF SECTION

Page 58: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 16

Sudbury, Ontario DAMPERS - FIRE AND SMOKE

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 REFERENCES

.1 American National Standards Institute/National Fire Protection Association (ANSI/NFPA)

.1 ANSI/NFPA 90A-2002, Standard for the Installation of Air Conditioning and

Ventilating Systems.

.2 Underwriters Laboratories of Canada (ULC)

.1 CAN4-S112-M1990, Fire Test of Fire Damper Assemblies.

.2 ULC-S505, Fusible Links for Fire Protection Service.

1.2 SUBMITTALS

.1 Product Data:

.1 Submit manufacturer's printed product literature, specifications and datasheet in

accordance with Section - Submittal Procedures. Include product characteristics,

performance criteria, and limitations.

.2 Indicate the following:

.1 Fire dampers.

.2 Fire stop flaps.

.3 Fusible links.

.4 Manufacturer's details of FD installation. Supplier to include this

information with the submission of shop drawings.

.2 Quality assurance submittals: submit following in accordance with Section - Submittal

Procedures.

.1 Certificates: submit certificates signed by manufacturer certifying that materials

comply with specified performance characteristics and physical properties.

.2 Instructions: submit manufacturer's installation instructions.

.3 Closeout Submittals:

.1 Provide maintenance data for incorporation into manual specified in Section -

Closeout Submittals.

Part 2 Products

2.1 FIRE DAMPERS

.1 Fire dampers: arrangement Type B and C, listed and bear label of ULC or Warnock

Hersey, meet requirements of provincial fire authority and authorities having jurisdiction.

Fire damper assemblies must be fire tested in accordance with CAN4-S112.

.2 Mild steel, factory fabricated for fire rating requirement to maintain integrity of fire wall

and/or fire separation.

Page 59: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 16

Sudbury, Ontario DAMPERS - FIRE AND SMOKE

GENIVAR #131-13878-00

April 2013 Page 2

.3 Fusible link actuated, weighted to close and lock in closed position when released or

having spring-closing operator for multi-leaf type or roll door type in horizontal position

with vertical air flow.

.4 Install to complete the 40 x 40 x 1.6 mm retaining angle iron frame, on full perimeter of

fire damper, on both sides of fire separation being pierced. Follow approved details and

manufacturer instructions for damper installation.

.5 Equip fire dampers with steel sleeve or frame installed without disruption to ductwork. Do

not impair damper operation.

.6 Equip sleeves or frames with perimeter mounting angles attached on both sides of wall or

floor opening.

.7 Design and select dampers to not reduce duct or air transfer opening cross-sectional area.

.8 Dampers shall be installed so that the centerline of the damper depth or thickness is

located in the centerline of the wall, partition of floor slab depth or thickness.

.9 Unless otherwise indicated, the installation details given in SMACNA Installation of Fire

Dampers and in manufacturer's instructions for fire dampers shall be followed.

2.2 FIRE STOP FLAPS

.1 Fire flaps: ULC listed and labelled and fire tested in accordance with CAN4-S112.2.

.2 Construct of minimum 1.5 mm thick sheet steel with 1.6 mm thick non-asbestos ULC

listed insulation and corrosion-resistant pins and hinges.

.3 Flaps held open with fusible link conforming to ULC-S505.

Part 3 Execution

3.1 MANUFACTURER'S INSTRUCTIONS

.1 Compliance: comply with manufacturer's written recommendations or specifications,

including product technical bulletins, handling, storage and installation instructions, and

datasheet.

3.2 INSTALLATION

.1 Install in accordance with ANSI/NFPA 90A and in accordance with conditions of ULC

listing.

.2 Maintain integrity of fire separation.

.3 After completion and prior to concealment obtain approvals of complete installation from

authority having jurisdiction.

.4 Install access door adjacent to each damper, unless access is gained directly through a

grille.

Page 60: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 16

Sudbury, Ontario DAMPERS - FIRE AND SMOKE

GENIVAR #131-13878-00

April 2013 Page 3

.5 Co-ordinate with installer of firestopping.

.6 Ensure access doors/panels, fusible links, damper operators are easily observed and

accessible.

.7 Fasten steel retaining angles on both sides of fire separation. Install break-away joints of

approved design on each side of separation.

3.3 FIELD QUALITY CONTROL

.1 Arrange for a detailed inspection of the first one or two FD installations, to establish the

proper Materials and Methods. After the quality of work is accepted, the other FD

locations can proceed.

.2 During final inspections, remove access doors to prove and show that dampers are opened

and properly framed.

3.4 CLEANING

.1 Upon completion and verification of performance of installation, remove surplus

materials, excess materials, rubbish, tools and equipment.

END OF SECTION

Page 61: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 46

Sudbury, Ontario FLEXIBLE DUCTWORK AND SOUND ATTENUATION

GENIVAR #131-13878-00

April 2013 Page 1

PART 1 General

1.1 RELATED SECTIONS

.1 Section - Submittal Procedures.

1.2 REFERENCES

.1 National Fire Protection Association (NFPA)

.1 NFPA 90A-99, Installation of Air Conditioning and Ventilating Systems.

.2 Sheet Metal and Air Conditioning Contractors' National Association (SMACNA)

.1 SMACNA HVAC Duct Construction Standards - Metal and Flexible, and

Addendum No.1 1997.

.3 Underwriter's Laboratories of Canada (ULC)

.1 CAN/ULC-S110-, Fire Tests for Air Ducts.

.2 UL 181-96, Factory Made Air Ducts and Connectors.

1.3 PRODUCT DATA

.1 Submit product data for review by consultant.

.2 Indicate the following:

.1 Thermal properties.

.2 Friction loss.

.3 Acoustical loss.

.4 Leakage.

.5 Fire rating.

1.4 CERTIFICATION OF RATINGS

.1 Catalogue or published ratings to be those obtained from tests carried out by

manufacturer or independent testing agency signifying adherence to codes and standards.

PART 2 Products

2.1 GENERAL

.1 Factory fabricated to CAN/ULC S110.

.2 Pressure drop coefficients listed below are based on relative sheet metal duct pressure

drop coefficient of 1.00.

.3 Flame spread rating not to exceed 25. Smoke developed rating not to exceed 50.

Page 62: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 46

Sudbury, Ontario FLEXIBLE DUCTWORK AND SOUND ATTENUATION

GENIVAR #131-13878-00

April 2013 Page 2

2.2 METALLIC – UNINSULATED (type 1)

.1 Type 1: spiral wound, flexible aluminum.

.2 Performance:

.1 Factory tested to 2.5 kPa without leakage.

.2 Maximum relative pressure drop coefficient: 3.

.3 Acceptable material: Flexmaster, Dundas-Jafine.

2.3 METALLIC – INSULATED (type 2)

.1 Type 2: spiral wound, flexible aluminum with factory applied, 37 mm thick flexible

glass fibre thermal insulation with vapour barrier and vinyl jacket.

.2 Performance:

.1 Factory tested to 2.5 kPa without leakage.

.2 Maximum relative pressure drop coefficient: 3.

2.4 METALLIC, ACOUSTIC INSULATED MEDIUM PRESSURE (type 5)

.1 Type 5: Spiral wound, flexible perforated aluminum with factory applied 37 mm thick

flexible glass fibre thermal insulation and sleeved by aluminum foil and mylar laminate

vapour barrier.

.2 Performance:

.1 Factory tested to 2.5 kPa without leakage.

.2 Maximum relative pressure drop coefficient: 3.

.3 Acoustical performance: Minimum attenuation (dB/m) to following table:

Frequency (Hz)

Duct Diam: 125 250 500 1000 2000

100 0.6 3 12 27 0

150 1.2 3 12 22 27

200 2.0 5 12 19 20

300 2.4 5 12 16 15

2.5 SILENCERS (Not used)

.1 Silencers shall be of the size, configuration, capacity and acoustic performance as

scheduled on the drawings. All silencers shall be factory fabricated and supplied by the

same manufacturer.

.2 Silencer inlet and outlet connection dimensions must be equal to the duct sizes shown on

the drawings. Duct transitions at silencers are not permitted unless shown on the contract

drawings.

.3 Acceptable material: Vibro-Acoustics, or equal.

Page 63: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 46

Sudbury, Ontario FLEXIBLE DUCTWORK AND SOUND ATTENUATION

GENIVAR #131-13878-00

April 2013 Page 3

PART 3 Execution

3.1 FLEXIBLE DUCT INSTALLATION

.1 Install in accordance with: CAN/ULC-S110, NFPA 90A.

.2 Type1: maximum 1800 mm (6 ft) length permitted. May be used for concealed branch

connections of exhaust grilles/ registers.

.3 Type 2: maximum 1800 mm (6 ft) length permitted. May be used for concealed branch

connections of diffusers in cooling systems.

.4 Type 5: use for sound reduction in branch connections to Supply Air grilles on rooms

which are close to the Air Handling/Roof Top Package Equipment. Follow manuf.

recommendations for limits of length, as the minimum flex length may be 3 m. If

locations are not indicated, then notify consultant for a list of room numbers which

require this sound-reduction product.

.5 Type 5 shall be used when branches are within 10 m of the main plenum, and the system

involved is larger than 900 CFM. (Exception: Not used for exposed duct branches.)

.6 Contractor to seal ends of flex duct sections with sealant and tape to prevent condensation

and air leakage.

3.2 INSTALLATION

.1 Install in accordance with manufacturer's instructions.

.2 Noise flanking: where indicated, install in wall sleeve with uniform clearance around to

ensure no contact of silencer with wall sleeve. Pack with flexible, non hardening caulking

on both sides of sleeves.

.3 Instrument test ports: install at inlet and outlet to permit measurement of insertion loss

and pressure loss.

.4 Suspension: to manufacturer's instructions.

3.3 TESTING

.1 Contractor to obtain sound measurements after start up and testing, adjusting and

balancing of systems to Section 15950 - Testing Adjusting and Balancing (TAB) of

Mechanical Systems.

.2 Sound measurements will be for general ambient noise level, with systems ‘ON’ just to

ensure the rooms involved will not be subject to system noise.

.1 downstream of each plenum.

.2 In areas adjacent to mechanical equipment rooms, duct and pipe shafts.

.3 At 1800 mm above floor adjacent to first and second air terminal.

Page 64: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 46

Sudbury, Ontario FLEXIBLE DUCTWORK AND SOUND ATTENUATION

GENIVAR #131-13878-00

April 2013 Page 4

.3 BEFORE CONSTRUCTION: Establish adequacy of equipment isolation, acceptability of

noise levels in occupied areas, other conditions affecting acoustics and, where

appropriate, recommendation for remedial measures and costs.

END OF SECTION

Page 65: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 53

Sudbury, Ontario DUCT LINERS

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SECTION INCLUDES

.1 Materials and installation for acoustic duct lining.

1.2 REFERENCES

.1 Canadian General Standards Board (CGSB)

.1 CGSB 51-GP-10M-76, Thermal Insulation, Mineral Fiber, Block or Board for

Ducting.

.2 National Fire Protection Association (NFPA).

.1 NFPA 90A-02, Standard for the Installation of Air Conditioning and Ventilating

Systems.

.3 Sheet Metal and Air Conditioning Contractor's National Association (SMACNA).

.1 SMACNA, HVAC DCS, HVAC, Duct Construction Standards, Metal and

Flexible-95 (Addendum No.1, Nov. 97).

.4 Underwriter's Laboratories of Canada (ULC).

.1 CAN/ULC-S102-03-EN, Methods of Test for Surface Burning Characteristics of

Building Materials and Assemblies.

1.3 SUBMITTALS

.1 Submit product data in accordance with Section- General Requirements.

1.4 DELIVERY, STORAGE AND HANDLING

.1 Protect on site stored or installed absorptive material from moisture damage.

1.5 WASTE MANAGEMENT AND DISPOSAL

.1 Separate waste materials for recycling.

.2 Ensure emptied containers are sealed and stored safely.

Part 2 Products

2.1 DUCT LINER

.1 Mineral Fibre duct liner: air surface coated mat facing.

.2 Flame spread rating shall not exceed 25. Smoke development rating shall not

exceed 50 when tested in accordance with CAN/ULC-S102 and NFPA 90A

NFPA 90B.

.3 Recycled Content: EcoLogo certified with minimum 35 % by weight recycled

content .

Page 66: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 53

Sudbury, Ontario DUCT LINERS

GENIVAR #131-13878-00

April 2013 Page 2

.4 Product to be resistant to bacteria and contamination.

.2 Rigid:

.1 Use on flat surfaces where indicated .

.2 25 mm thick, to CGSB.51-GP-10M , fibrous glass rigid board duct liner.

.3 Density: 48 kg/m3minimum.

2.2 ADHESIVE

.1 Adhesive: Meet requirements of NFPA 90A and NFPA 90B.

.2 Flame spread rating shall not exceed 25. Smoke development rating shall not exceed 50.

Temperature range minus 29 degreesC to plus 93 degreesC.

.3 Water-based fire retardant type.

2.3 FASTENERS

.1 Weld pins 2.0 mm diameter, length to suit thickness of insulation. Metal retaining clips,

32 mm square.

2.4 JOINT TAPE

.1 Poly-Vinyl treated open weave fiberglass membrane 50 mm wide.

2.5 SEALER

.1 Meet requirements of NFPA 90A and NFPA 90B.

.2 Flame spread rating shall not exceed 25. Smoke development rating shall not exceed 50.

Temperature range minus 68 degrees C to plus 93 degrees C.

Part 3 Execution

3.1 GENERAL

.1 Do work in accordance with recommendations of SMACNA HVAC DCS.

.2 Line inside of ducts where indicated.

.3 All duct sizes shown on plans are based on clear inside duct dimension. Contractor shall

consider lining thickness for each duct dimension.

.4 Ducts to be accessible for future inspection to check the integrity of the lining. Add 300 x

300 mm minimum (1) one access panel on main plenum where necessary for inspection.

3.2 DUCT LINER

.1 Install in accordance with manufacturer's recommendations, and as follows:

.1 Fasten to interior sheet metal surface with 100 % coverage of adhesive.

Page 67: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 33 53

Sudbury, Ontario DUCT LINERS

GENIVAR #131-13878-00

April 2013 Page 3

.2 In addition to adhesive, install weld pins not less than 2 rows per surface and not

more than 425 mm on centres.

3.3 JOINTS

.1 Seal butt joints, exposed edges, weld pin and clip penetrations and damaged areas of

liner with joint tape and sealer. Install joint tape in accordance with manufacturer's written

recommendations, and as follows:

.1 Bed tape in sealer.

.2 Apply two coats of sealer over tape.

.2 Replace damaged areas of liner at discretion of Consultant.

.3 Protect leading and trailing edges of duct sections with sheet metal nosing having 15 mm

overlap and fastened to duct.

END OF SECTION

Page 68: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 37 13

Sudbury, Ontario DIFFUSERS, REGISTERS AND GRILLES

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 Section Includes:

.1 Supply, return and exhaust grilles and registers, diffusers for commercial.

.2 Related Work:

.1 Reflected ceiling plan; lighting plan.

1.2 SYSTEM DESCRIPTION

.1 Performance Requirements:

.1 Catalogued or published ratings for manufactured items: obtained from tests

carried out by manufacturer or those ordered by manufacturer from independent

testing agency signifying adherence to codes and standards.

1.3 SUBMITTALS

.1 Product Data:

.1 Submit manufacturer's printed product literature, specifications and datasheet in

accordance with Section - Submittal Procedures. Include product characteristics,

performance criteria, and limitations.

.2 Indicate following:

.1 Capacity.

.2 Throw and terminal velocity.

.3 Noise criteria.

.4 Pressure drop.

.5 Neck velocity.

.6 Finishes.

1.4 DELIVERY, STORAGE, AND HANDLING

.1 Packing, shipping, handling and unloading:

.1 Deliver, store and handle materials in accordance with the instructions from site

supervisor.

1.5 MAINTENANCE

.1 Extra Materials:

.1 Provide maintenance materials in accordance with Section - Closeout Submittals.

.2 Include:

.1 Keys for volume control adjustment.

Page 69: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 37 13

Sudbury, Ontario DIFFUSERS, REGISTERS AND GRILLES

GENIVAR #131-13878-00

April 2013 Page 2

Part 2 Products

2.1 GENERAL

.1 To meet capacity, pressure drop, terminal velocity, throw, noise level, neck velocity as

indicated.

.2 Frames:

.1 Standard style, unless noted otherwise.

.2 T-bar mount, gyproc ceiling, duct mounted and vertical wall mounting.

.3 Duct adaptors: To be fabricated by contractor to suit the sizing of branch

ductwork and to suit the building material involved.

.3 Concealed manual volume control damper operators, where noted.

.4 Colour: standard white.

2.2 MANUFACTURED UNITS

.1 Grilles, registers and diffusers of same generic type, to be products of one manufacturer.

2.3 DIFFUSERS/ RETURN AIR GRILLE

.1 See schedule on mechanical drawings for various types.

Part 3 Execution

3.1 INSTALLATION

.1 Install according to good practice. Fasten duct to diffusers using screws.

.2 Bolt grilles, registers and diffusers, in place where public safety is concerned.

.3 Where interior of ducts are visible behind grilles, paint interior of duct with 1 coat flat

black to hide sheet metal.

.4 Dampers in grilles to remain fully-open until final balancing is required.

3.2 CLEANING

.1 Protect grilles, diffusers with a combination of plastic and tape. Prevent dust

contamination until the building is free of construction dirt.

.2 Upon completion and verification of performance of installation, remove surplus

materials, excess materials, rubbish, tools and equipment.

END OF SECTION

Page 70: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 72 00

Sudbury, Ontario AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 REFERENCES

.1 American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE)

.1 ASHRAE 84-1991, Method of Testing Air-to-Air Heat Exchangers.

1.2 SHOP DRAWINGS

.1 Submit shop drawings and product data in accordance with Section 23 05 00.

.2 Indicate following: dimensions, wiring diagrams, controls, remote panels, capacities,

performance, and accessories.

1.3 CLOSEOUT SUBMITTALS

.1 Provide operation and maintenance data for incorporation into manual specified in

Common Work Specifications.

1.4 CERTIFICATION

.1 Catalogued or published ratings shall be those obtained from tests carried out by

manufacturer or those ordered from independent testing agency signifying adherence to

codes and standards in force.

.2 Provide confirmation of testing.

Part 2 Products

2.1 GENERAL

.1 Energy Recovery Ventilator shall be as manufactured by "Greenheck" or approved equal

provided all specifications are met. Greenheck Model ERH is used as the basis of design.

Units shall be listed per ANSI/UL 1995, Heating and Cooling Equipment. Energy transfer

ratings of the energy recovery wheel shall be ARI Certified. Ventilators shall bear the

AMCA Certified Rating Seals for Air Performance. Performance shall be as scheduled on

plans. Exhaust discharge and outside air intake shall not be located on the same side on

the unit.

.2 Comply with ASHRAE 84.

.3 Electrical: per schedule.

2.2 ENTHALPY TYPE AIR TO AIR ROTARY HEAT EXCHANGER

.1 Pre-Packaged ERV-1 equipment, factory assembled; ready for connection to power supply

and ductwork. Capac: as indicated.

.2 Casing:

Page 71: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 72 00

Sudbury, Ontario AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 2

Unit shall be of internal frame type construction of galvanized steel. Frame and panels

shall be G90 galvanized steel. Unit shall be internally lined with galvanized sheet metal

creating a double wall. Where top panels are joined there shall be an overlapping, standing

seam to insure positive weather protection. All metal-to-metal seams shall be factory

sealed, requiring no caulking at job site.

Unit casing to be insulated with 1 inch fiberglass. Insulation shall meet requirements of

NFPA 90A and tested to meet UL 181 erosion requirements. Insulation to be enclosed in

double wall construction.

.3 Unit is OUTOOR mounted: ERV-1 for general ventilation.

.4 Seals: adjustable at periphery of rotor, on duct divider and on purge sections.

.5 Motors:

Motors shall be energy efficient, complying with EPACT standards, for single speed ODP

and TE enclosures. Motors shall be permanently lubricated, heavy-duty type, matched to

the fan load and furnished at the specified voltage, phase, and enclosure. Drives shall be

sized for a minimum of 150% of driven horsepower. Pulleys shall be of the fully machined

cast type, keyed and securely attached to the fan wheel and motor shafts; 10 horsepower

and less shall be supplied with an adjustable drive pulley. Energy wheel motors shall have

integral overload protection.

.6 Electrical Requirement:

All internal electrical components shall be factory wired for single point power

connection. Units with electric reheat will be wired with independent power supply. All

electrical components shall be UL Listed, Approved, or Classified where applicable and

wired in compliance with the National Electrical Code.

Weatherproof, integral door interlocking disconnect switch, motor starters, control circuit

fusing, control transformer for 24 VAC circuit, and terminal strip shall be supplied as

standard components in the control center. Motor starters consist of a contactor and Class

20 electronic adjustable overload protection and shall be provided for all motors in the

unit.

.7 Enthalpy Wheel:

Wheel shall be of the enthalpy type for both sensible and latent heat recovery and be

designed to insure laminar flow. Energy transfer ratings must be ARI Certified to Standard

1060 and bear the ARI certification symbol for ARI Air-to-Air Energy Recovery

Ventilation Equipment Certification Program based on ARI 1060. Ratings "in accordance

with 1060" without certification are not acceptable. Desiccant shall be silica gel for

maximum latent energy transfer. Wheel shall be constructed of lightweight polymer media

to minimize shaft and bearing loads. Polymer media shall be mounted in a stainless steel

rotor for corrosion resistance.

Page 72: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 72 00

Sudbury, Ontario AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 3

Wheel design shall consist of removable segments for ease of service and/or cleaning.

Silica gel desiccant shall be permanently bonded to wheel media to retain latent heat

capability after cleaning. Wheels with sprayed on desiccant coatings are not acceptable.

Wheels with desiccant applied after wheel formation are not acceptable. Energy recovery

device shall transfer moisture entirely in the vapor phase.

Energy recovery drive belt material shall be high strength urethane and shall be factory

installed in a pre-stretched state, eliminating the need for field belt tension adjustment.

Link style belts are not acceptable.

.8 Access Doors:

All components shall be easily accessible through removable doors for exhaust, supply,

filter, and damper compartments.

.9 Filteration:

Supply and exhaust air filters shall be 2-inch thick pleated fiberglass, 30% efficient and

tested to meet UL Class 2. Filter racks shall be die-formed galvanized steel.

.10 Media: bacteriostatic with desiccant and coated with silicate.

.11 Fan isolation: spring and flex. Duct section

.12 Performance characteristics: Minimum 70% ave. heat recovery.

.13 Include Free-Cooling control where heat wheel is stopped for any time that the outdoor

temperature is between 50F to 70F. This wheel-stop shall be commanded by the existing

BAS.

.14 Accessories:

.1 Defrost mode: modulating wheel (energy wheel modulates to lower speed when

frosting is indicated). Unit shall be equipped with the necessary sensors and

controls using 0-10 VDC to vary the energy wheel speed down to 2 RPM to

maintain continuous ventilation and to prevent frost from forming on the enthalpy

wheel and to allow for continuous ventilation.

.2 Insulated motorized low leakage fresh air damper and exhaust damper and Spring-

Return damper operators to be included in package.

.3 Dampers to be insulated sandwich design and with spring return operators.

.4 Provide disconnect switch.

.5 Sensor Contacts:

- Control device and contacts shall be included to provide a 24 VAC signal when

filters require replacing.

- Unit shall come equipped with a wheel rotation sensor. A 24 VAC signal will be

provided if the enthalpy wheel fails.

.6 External Finish:

- Unit shall include white, baked on, polyester pre-painted galvanized steel

package. Cabinet shall withstand 10 years without cracking, chipping, peeling,

brazing or spotting.

Page 73: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 72 00

Sudbury, Ontario AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 4

.9 Control sequences must be clearly defined during shop drawings stage.

.15 Acceptable material: Greenheck ERV, or approved alternates. The base design is

Greenheck. Any changes to the based design due to the alternate products will be the

responsibility of mechanical contractor.

Part 3 Execution

3.1 INSTALLATION

.1 Install in accordance with manufacturers recommendations.

.2 Support independently of adjacent ductwork with flexible connections.

.3 Arrange with other trade for correct power supply to equipment.

3.2 CLEANING

.1 Vacuum interior and exterior of unit and ducts before acceptance from Owners.

.2 Upon completion and verification of performance of installation, remove surplus

materials, excess material, rubbish, tools and equipment.

3.3 TESTING

.1 Manufacturer’s rep shall start-up and test the equipment in advance of final inspection

times. Allow 2 days testing for each package.

.2 Measure and record temperature performance under normal operating conditions;

including cold weather testing. Submit results to consultants. Include cost for repeat site

visits when cold weather will permit proper tests.

.3 Remove and replace equipment which is not functioning properly.

.4 Adjust operations for owner, during the warrantee period, according to TAB section.

3.4 WARRANTY

.1 The energy recovery ventilator shall be warranted to be free from defects in

material and workmanship for a period of one year from the purchase date. The

energy recovery wheel shall be warranted to be free from defects in material and

workmanship for a period of five years from the purchase date. Motors shall be

warranted by the motor manufacturer for a period of one year from the purchase

date.

END OF SECTION

Page 74: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 74 00

Sudbury, ON PACKAGED OUTDOOR HVAC EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 1

Part 1 General

1.1 SUMMARY

.1 Section Includes:

.1 Materials and installation for self-contained single zone, gas-fired, packaged

rooftop HVAC units.

.2 Related Sections:

.1 Section- Submittal Procedures.

.2 Section - Quality Control.

1.2 REFERENCES

.1 American National Standards Institute (ANSI)/Air Conditioning and Refrigeration

Institute (ARI)

.1 ANSI/ARI 210/240-03, Unitary Air-Conditioning and Air-Source Heat Pump

Equipment.

.2 Canadian Standards Association (CSA International)

.1 CSA B52-99, Mechanical Refrigeration Code.

.2 CSA C22.1 HB-02, Canadian Electrical Code Handbook.

.3 National Fire Protection Association

.1 NFPA 90A-02, Standard for the Installation of Air Conditioning and Ventilating

Systems.

1.3 SUBMITTALS

.1 Submittals in accordance with Section - Submittal Procedures.

.2 Shop Drawings:

.1 Submit shop drawings to indicate project layout and dimensions; indicate:

.1 Equipment, piping, and connections, together with valves, strainers,

control assemblies, thermostatic controls, auxiliaries and hardware, and

recommended ancillaries which are mounted, wired and piped ready for

final connection to building system.

.2 Piping, valves, fitting shipped loose showing final location in assembly.

.3 Control equipment shipped loose, showing final location in assembly.

.4 Dimensions, internal and external construction details, recommended

method of installation with proposed structural steel support, mounting

curb details, sizes and location of mounting bolt holes.

.5 Detailed composite wiring diagrams for control systems showing factory

installed wiring and field wiring.

.6 Pump and fan performance curves.

Page 75: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 74 00

Sudbury, ON PACKAGED OUTDOOR HVAC EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 2

.7 Estimate of sound levels to be expected across individual octave bands in

dB referred to A rating.

.8 Type of refrigerant used.

.3 Instructions: submit manufacturer's installation instructions.

.4 Closeout submittals: submit maintenance data for incorporation into manual specified in

Section - Closeout Submittals:

.1 Indicate: brief description of unit, indexed, with details of function, operation,

control, and service for components.

.2 Provide for units, manufacturer's name, type, model no., year, number of units,

and capacity.

1.4 QUALITY ASSURANCE

.1 Health and Safety:

.1 Do construction occupational health and safety in accordance with Section -

Health and Safety Requirements.

1.5 WARRANTY

.1 Special Case: Contractor hereby warrants that the packaged rooftop refrigeration

compressors will function and operate for 60 months.

Part 2 Products

2.1 GENERAL

.1 Roof mounted, self-contained, single zone unit with gas burner and DX refrigeration and

bear label of CSA, CGA.

.2 Unit to consist of cabinet and frame, supply fan, heat exchanger, burner with integral

induced draft fan, heater control, air filter, refrigerant cooling coil, compressors, condenser

coil and fans, motorized outside air damper, return damper, power exhaust damper.

.3 Provide economizer option, with built-in enthalpy controls.

.4 Standard of Acceptance: York, Carrier or approved equal. Note: base design is based on

YORK. Any changes due to the dimension, weight affecting structural components will be

the mechanical contractor responsibility.

.5 Supply weather-proof disconnects to meet Electrical Safety requirements.

.6 450mm high full perimeter insulated roof curb required for RTU-1.

2.2 CABINET

.1 Single wall construction.

Page 76: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 74 00

Sudbury, ON PACKAGED OUTDOOR HVAC EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 3

.2 Framing and supports: 2 mm thick welded steel, galvanized after manufacture, with lifting

lugs at top of unit.

.3 Outer casing: weathertight galvanized steel with baked enamel finish, complete with

flashing.

.4 Access: hinged gasketted doors, or panels with quick operated flush cam type fasteners.

.5 Insulation: neoprene coated glass fiber on surfaces where conditioned air is handled.

2.3 FANS

.1 Centrifugal, forward curved impellers, statically and dynamically balanced. V-belt drive

with adjustable variable pitch motor pulley, rubber isolated hinge mounted motor fan and

motor integrally mounted on isolation base.

2.4 AIR FILTERS

.1 50 mm thick, 30% efficiency, metal framed filter rack, throwaway, standard to unit

manufacturer.

.2 Pre-filter on economizer hood, for pest control.

2.5 HEAT EXCHANGERS AND BURNERS

.1 Gas fired, multiple flue passes, with primary heating surface of stainless steel; secondary

heating surface.

.1 Gas burner: factory mounted, wired and fire tested complete with operating and

safety controls.

.2 Induced draft blower.

.3 Spark ignited pilot with pilot flame safety shut-off.

2.6 REFRIGERATION

.1 Conform to CSA B52 and ANSI/UL 1995 requirements.

.2 Compressor/Condenser Section:

.1 compressors, vibration isolated with flexible suction and discharge connections,

oil sight glass, oil pressure switch, crankcase heater, with control to liquid line

solenoid valve.

.2 Fans: propeller type with single piece spun venturi outlets and zinc plated guards.

Motors: sequenced for head pressure control.

.3 Electrical system: complete with operating controls, oil and refrigerant pressure

protection, motor overload protection, weatherproof electrical wiring with

weatherproof disconnect.

.4 Condenser: staggered copper tube aluminum fin coil assembly.

.5 Refrigerant: Puron refrigerant charge (R-410A) or approved equivalent.

.3 Evaporator:

Page 77: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 74 00

Sudbury, ON PACKAGED OUTDOOR HVAC EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 4

.1 Thermostatic expansion valve.

.2 Coil: staggered seamless copper tubes expanded into aluminum fins, and

insulated condensation pan.

.3 Cooling coil condensate drain pans: designed to avoid standing water, easily

cleaned or removable for cleaning. Drain connection: deep seal trap to be fitted in

the field, by contractor. Drain to roof (RTU-1).

2.7 CONTROLS

.1 Factory-wired: combustion safety controls.

.2 Economizer: factory designed to provide free cooling with fresh air, in the desired range

of outside air temp. (ie. 60 deg.F to 70 deg.F only).

.3 See the note on drawing for the sequence of operation.

2.8 CAPACITY

.1 As indicated on drawings.

Part 3 Execution

3.1 MANUFACTURER'S INSTRUCTIONS

.1 Compliance: comply with manufacturer's written recommendations or specifications,

including product technical bulletins, handling, storage and installation instructions, and

datasheet.

3.2 INSTALLATION

.1 Install roof curb as indicated. Co-ordinate the rough opening and the flashing, with the

general contractor and other trades.

.2 Manufacturer's rep to supervise start-up and commission unit.

.3 Run drain line from cooling coil condensate drain pan to discharge over roof and where

indicated .

3.3 FIELD QUALITY CONTROL

.1 Verify accessibility, serviceability of components including motorized dampers, filters

coils, fans, motors, operators, sensors, electrical disconnects.

.2 Performance Verification:

.1 Rooftop Air Package Unit:

.1 Set outside air and return air dampers for minimum outside air.

.2 Check for smooth, rotation of supply fan impeller.

.3 Adjust impeller speed as necessary and repeat measurement of fan

capacity.

Page 78: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …

Pioneer Manor, Mallard and Scenic Wings Mechanical Upgrades Section 23 74 00

Sudbury, ON PACKAGED OUTDOOR HVAC EQUIPMENT

GENIVAR #131-13878-00

April 2013 Page 5

.4 OAD: verify for proper stroking, interlock with RAD.

.5 Simulate maximum heating load and:

.1 Verify temperature rise across heat exchanger.

.2 Simulate minimum heating load and repeat measurements.

.6 Verify operating control strategies, including:

.1 Heat exchanger operating and high limit.

.2 Early morning warm-up cycle.

.3 Economizer cycle operation, temperature of change-over.

.7 Measure DX refrigeration system performance.

3.4 DEMONSTRATION

.1 Training: in accordance with Section- control: Training of O&M Personnel, as specified in

general requirement spec.

3.5 CLEANING

.1 Perform cleaning operations as specified and in accordance with manufacturer's

recommendations.

.2 On completion and verification of performance of installation, remove surplus materials,

excess materials, rubbish, tools and equipment.

END OF SECTION

Page 79: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …
Page 80: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …
Page 81: SUBJECT: ADDENDUM NO. 1, CDD13-12, TENDER FOR …