subgrade insulation to prevent soil freezingpublications.iowa.gov/19617/1/iadot_hr87_subgrade... ·...
TRANSCRIPT
\
17-J-fS3/( Cj: Sv.15'
Iowa Highway Research Board
Project HR-87
SUBGRADE INSULATION
TO PREVENT
SOIL FREEZING
Final Report December 1965
Research Department
Iowa State Highway Commission
/ { .. -
IOWA STATE HIGHWAY COMMISSION Ames, Iowa
December 21, 1965
To: All Concerned
From~ Research Department
Subject: Subgrade Insulation to Prevent Soil Freezing
The report noted above .is final for research project HR-87. The automatic temperature recording equipment has been removed from the test site. Observations of the pavement will continue to be made periodically~ you will be informed of any ~ignificant changes.
The basic purpose of this study was to determine if insulating board composed of expanded polystyrene can be used under highway pavement to prevent freezing of the subgr~de soil.
The insulating board was furnished without cost by the manufacturer. The thickness, one and one~half inches, was that recommended by the manufacturer. 1he board was placed on the subgrade composed of a frost-susceptible soil; a nine.inch Portland Cement Concrete slab was placed on top of the board.
The temperature of the air, the concrete, and of the. soil was obtained from thermocouples. This was recorded automatically every two hours. The report contains graphs and· illustrations showing temperature distributions for two years.
The insulation under a PoCo concrete slab and under the shoulders, as used in this experimental project, appears to have adequately protected the subgrade from freezing temperatures and prevented frost heave.
The concrete slab above the insulation, in comparison with the uninsulated control slab, experienced more cycles of freezing and thawing. It also appeared to have a more uniform temperature throughout its thickness.
The conclusions contained in this report do not cons.ti tute a recommendation for any particular brand nor type of thermal insulation. It may be that many suitable materials now exist or will subsequently be deve.loped. While the basic requirement is low thermal conductivity, there are also other properties which should be exhibited by the insulating material. It should absorb little or no moisture, should be unaffected by chemicals and bacteria commonly found in soil and paving materials, and should have structural strength adequate for the intended application.
-2-
This report concerns the use of thermal insulation under rigid pavement. It is recognized that the desirability of preventing soil freezing applies equally to the supporting subgrade for flexible pavement. The exact placement of the insulation under either type of pavement will depend upon individual job requirements and the ingenuity of the designer. It should be kept in mind that the installation method and its compatibility with standard construction procedures is an important factor in the cost of the project. If the installation method is complicated, it will likewise be costly. In this event, the use of thermal insulation may not prove economical in comparison with the conventional practice of replacing the frost-susceptible subgrade soil with granular material.
Te.~:'t Site -----~-,. ___ _ us - 18
[_J
Figure 1: Project Map
ACKNOWLEDGEMENTS
The experimental work described in this report was
accomplished through the cooperation of all concerned with the
design and construction of the pavemento The temperature
recording equipment was installed by personnel from the Materials
Department Laboratoryo Regular inspection of the installation
and profile.measurements of the pavement were provided by
personnel from the Resident Engineer's Office at New Hampton.
We desire to also acknowledge the excellent cooperation of
the paving contractor 0 Fred Carlson, and of the Dow Chemical
Company, which furnished technical assistance as well as the
Styrofoam insulation.
iii
ABSTRACT
The basic purpose of this study was to determine if an
expanded polystyrene insulating board could prevent subgrade
freezing and thereby reduce frost heave.
The insulating board was placed between a nine inch
P. c. concrete slab and a frost-susceptible subgrade. In one
section at the test site, selected backfill material was
placed under the pavement. The P. C. pavement was later
covered by asphalt surfacing. Thermocouples were installed
for obtaining temperature recordings at various locations in
the surfacing, concrete slab, subgrade and shoulders.
This report contains graphs and illustrations showing
temperature distributions for two years, as well as profile
elevations and the results of moisture tests.
iv
TABLE OF CONTENTS
Acknowledgements Abstract Introduction Research Objective Material Construction Testing Results Discussion Conclusions Photographs
Table
1 2 3
Figure
1 2
3-6 7-8 9-10
11-14
15-18
19-20 21-24
List of Tables
Title
Physical Properties of Styrofoam Scorbord SM Centerline Profile Elevations Subgrade Moisture Content
List of Figures
Title
Project Map Test Layout Thermocouple Locations Average Daily Air Temperatures Average Daily Temperatures Above and Below
the Styrofoam Concrete Temperature as Affected by
Styrofoam Temperatures at Various Depths Below the Surf ace
Determination of Freezing Indexes 0 . Depths at Which 32 F Or Less Were Recorded
v
Page
iii iv
1 2 3 3 5 6 7 9
11
16 17 19
ii 22
23-26 27-28
29-30
31-34
35-38 39-40 41-44
INTRODUCTION
Frost heave is a ground-freezing phenomenon which has
always been a problem for highway engineers. When severe
enough, localized areas develop what are commonly called
"frost boils." There is considerable vertical movement of
the road surface during winter freeze and spring thaw.
Finally, over a period of years, cracking of the slab and
uneven settlement develop giving the pavement very poor
riding qualities. In extreme conditions complete disinte
gration of the surface can occur.
In order for frost heaving or frost boils to develop,
three basic conditions must exist. These are: (1) freezing
temperatures in the soil; (2) a reservoir of ground water
sufficiently close to the frost line to feed the growing ice
layers; (3) soil material having favorable characteristics
for rapid movement of capillary water upward from the water
table. Since the temperature cannot be controlled, frost
heave areas have generally been corrected by removing the
undesirable material and replacing it with a granular backfill
or by lowering the water table.
1
The conclusions contained in this report do not constitute
a recommendation for any particular brand nor type of thermal
insulation. It may be that many completely adequate materials
now exist or will subsequently be developed. While the basic
requirement is low thermal conductivity, there are also other
properties which should be e.xhibited by the insulating material.
It should absorb little or no moisture, should be unaffected
by chemicals and bacteria commonly found in soil and paving
materials, and should have structural strength adequate for
the intended application.
This report concerns the use of thermal insulation under
rigid pavement. It is recognized that the value of preventing
soil freezing applies equally to the supporting subgrade for
flexible pavement. The exact placement of the insulation
under either type of pavement will depend upon individual
job requirements and the ingenuity of the designer. It should
be kept in mind that the installation method and its compati
bility with standard construction procedures is an important
factor in the cost of the project. If the installation method
is complicated, it will likewise be costly. In this event,
the use of thermal insulation will seldom prove economical in
comparison with the conventional practice of .replacing the
frost-susceptible subgrade soil with granular material.
RESEARCH OBJECTIVE
During the fall of 1963, the Iowa State Highway Commission
constructed a short section of highway where an insulating
material was placed directly below the slab. The objective
of this test was to determine if an insulating material will
2
3
prevent the subgrade from freezing, thereby reducing the frost
heave. If successful, this could eliminate the need to remove
and replace the poor soil with granular material.
The insulating material for this test was furnished with-
out cost by the manufacturer, Dow Chemical Company of Midland,
Michigan. Therefore, no attempt was made to compare the cost
of insulation with that of granular backfill.
MATERIAL
The insulating material used is an expanded polystyrene
with the trade name of Styrofoam. The physical properties of
the type of Styrofoam used in this test are shown in Table 1.
Its mechanical properties decrease slightly as the temperature
is raised. 0 0 At 160 F to 170 F the cellular structure collapses.
The material is not affected adversely at sub-zero temperatures.
Polystyrene, the base plastic, absorbs.a negligible amount
of moisture and the closed cell structure of Styrofoam almost
completely prevents the entrance of water.
CONSTRUCTION
The Iowa test section is located on US 18 about two miles
west of West Union. It is in a 450 foot- section of pavement
having a history of frost heaving.
The original plans were to core out three feet of the
subgrade and backfill with selected granular material. The
excavation and backfilling was eliminated on the east 250 feet
of the section. Instead, one and one-half inches of Styrofoam
was placed directly below the pavement on the subgrade and in
the shoulders at a 2:1 slope.
The 250 foot test area was divided into three sections.
In the east section, 75 feet in length, one layer of Styrofoam
one and one-half inches thick was placed. In the middle
section, 100 feet in length, two layers of Styrofoam, each
three-fourths inch thick, were placed. In the west section,
75 feet in length, one layer of Styrofoam one and one-half
inches thick was placed. In this section the Styrofoam was
covered with a sheet of four mil polyethelene. A layout of
the test area is shown in Figure 2.
The test sections were instrumented to measure the temp
eratures at various locations in the slab, subgrade and
shoulders.
As soon as the pavement forms were in place and the sub
grade cut and compacted, the first group of thermocouples was
installed at various depths in the subgrade. This was followed
by the placing of the Styrofoam between the forms. The Styro
foam was in the form of boards, 2 foot by 8 foot. Very little
trouble was encountered in placing them, however, they were
very light and could easily be blown away by the wind. They
were fastened to the subgrade by wooden peg~.
Nine inches of Portland cement concrete pavement was then
placed directly on the Styrofoam {or polyethelene). The thermo
couples used to measure the temperature of the concrete pave
ment ·\.\ere heJd in position by frames during placing of the
concrete.
The next day, after the paving forms had been removed,
the 2~1 slope was cut on the shoulders. Styrofoam was then
placed along the slope and the shoulder was constructed.
Thermocouples were placed in the shoulder at various depths
in the soil below and above the Styrofoam.
About June 15, 1964, three inches of asphaltic concrete
were placed upon the nine-inch concrete slab. On May 7, 1965,
thermocouples were placed at various positions in the resurfacing.
TESTING
The thermocouple wires terminated in a 5 foot by 5 foot by
6 foot building located near the right of way line. This
building was well insulated and a temperature above 50°F was
easily maintained during the winter months by use of two
electric heaters.
The temperatures obtained by the thermocouples were indi
cated by an automatic recording potentiometer which was capable
of recording, in sequence, the temperatures in 24 separate
locations. It was timed so that the temperatures at the 24
locations were recorded once every two hours. The recorder
contained two instrument boards consisting of 24 terminals
each. Either board could be connected, making it possible to
obtain temperatures from 24 alternate locations if desired.
The layout of the thermocouples at Station 602+00 and at
Station 604+50 is shown in Figures 3 and 4.
Figures 5 and 6 show the thermocouple locations at the
same stations after the asphaltic concrete resurfacing had
been completed. The remaining thermocouples were placed in
the concrete and subgrade at Station 603+50 but were not
installed in the resurfacing at that particular location.
5
RESULTS
Graphs and illustrations of the temperatures at various
locations are shown in Figures 7 through 24.
Figures 7 and 8 show the average daily air temperatures
during the freezing seasons of 1963-1964 and 1964-1965.
Figures 9 and 10 compare the temperatures above and below
the Styrofoam insulation. Figure 9 shows these comparative
temperatures for the 1963-1964 freezing season (before
resurfacing) and Figure 10 shows them for the 1964-1965 freezing
season (after resurfaci~g)~
Figures 11 and 12 compare minimum temperatures in the
concrete one inch above the bottom of the slab, as affected
by insulation below the slab. These graphs are included
primarily to show that while the Styrofoam insulates the sub
grade from freezing temperatures, it also prevents the concrete
from receiving heat from the subgrade. Figures 13 and 14 show
maximum temperatures at the same locations during the warmest
summer months. In this case the Styrofoam reduces the amount
of cooling from the subgrade. The temperatures shown in
Figure 11 are those before the asphaltic concrete was applied
and those in Figuresl2, 13, and 14 are after the three inch
resurfacing.
Figures 15, 16, 17, and 18 show minimum and maximum
temperatures at various depths below the surface with and
without the Styrofoam insulation. It should be noted that
during the winter of 1963-1964 the minimum temperature one inch
above the Styrofoam was -15°F while the minimum temperature
6
one inch below the styrofoam was 34°F. During the winter of
1964-1965, however, the minimum temperature one inch above
0 the Styrofoam was -8 F and the minimum temperature one inch
below the styrofoam dropped to 30°F. During the 1964-1965
winter the subgrade temperature five inches below the styrofoam
0 dropped below 32 F for a period of five days.
DISCUSSION
In order to accurately evaluate the results obtained on
a field installation such as this, it becomes necessary to
determine whether or not the installation was put to a severe
enough test.
A commonly accepted method for determining the severity
of cold weather is to calculate the freezing index for the
winter or winters in question.
Definitions:
Average daily temperature - The average of the maximum and
minimum temperatures for one day or the average of several
temperature readings taken at equal time intervals· during one
day.
Mean daily temperature - The average of the average daily
temperatures for a given day for several years.
Degree-days - The degree-days for any one day equals the dif
o ference between the average daily air temperature and 32 F.
The degree-days are minus when the average daily temperature
is below 32°F (freezing degree-days) and plus when above 32°F
(thawing degree-days).
7
Freezing index - The number of degree-days between the highest
and lowest points on. a curve of cumulative degree-days versus
time for one freezing season. It is a measure of the combined
duration and magnitude of below freezing temperatures occurring
during any given freezing season. The index determined for
air temperatures at 4.5 feet above the ground is commonly
designated as the air freezing index, and that determined for
temperatures immediately below a surface is known as the sur
face freezing index.
Design freezing index - 'I'he average air freezing index of the
three coldest winters in the latest 30 years of record. If
30 years are not available, the air freezing index for the
coldest winter in the latest 10 year period may be used.
Mean Freezing Index - The freezing index determined on the
basis of mean temperatures. The period of record over which
temperatures are averaged is usually a minimum of 10 years
(preferably 30) and should be the latest available.
Figure 19 shows the freezing index to be 1463 degree-days
for the 1963-1964 freezing season. Figure 20 shows the freezing
index for the 1964-1965 freezing season has a value of 2035
degree-days. The mean freezing index for this part of the state
as determined by the U.S. Army Corps of Engineers is 1100
degree-days over a 105 day period and the design freezing index
is 1700 degree-days. From these figures it can be seen that
the 1963-1964 winter was somewhat colder than average for
this area, and the 1964-1965 winter was very severe. Mr. Paul
J. Waite, Weather Bureau State Climatologist, speaking of the
8
1964-1965 winter says it was "the coldest winter (December
through March) since 1935-1936. Subnormal temperatures occurred
throughout all four months."
Figures 21 through 24 show the depth of frost penetration
down to and including 46 inches below the top of the P.C.
concrete in the section containing the granular backfill
material.
Profile elevations of the roadway were taken at various
times during the course of the investigation to determine the
amount of frost heave. Table 2 shows that elevation changes
in the styrofoam sections were much less than those either in
the special backfill section or outside the test sections.
Moisture samples of the subgrade and shoulder were taken
in April, 1964 and May, 1965. These values are listed in
Table 3 and appear to have little significance. The subgrade
in the control section consists of 3 feet of granular backfill
which normally has a much lower moisture content than the fine
grained soil under the Styrofoam.
CONCLUSIONS
The Styrofoam insulation under a P.C. concrete slab and
under the shoulders, as used in this experimental project,
appears to have adequately protected the subgrade from freezing
temperatures and prevented frost heave.
Because of an insulating layer under the concrete slab
it is known that the slab undergoes more freeze-thaw cycles
than it would if such an insulating layer were not present.
Whether or not this is detrimental remains to be seen.
9
The concrete slab above the Styrofoam appears to maintain
a more uniform temperature throughout its depth than does a
slab resting on the subgra.de. The a.dvantages gained from this
due to a reduction in curling of the slab is beyond the scope
of this report.
10
first thermocou0le
Photo !, .~
Pooden pegs QSed to fasten the r
I ,
P11.c>~tc> Dn the
Photo 5. :on~ret~ bein p11L::ec. on the Styrofoam.
Photo s~ CuttLns- the 2~1 Shoulder Slope :Eor
Photo 7~ Styrof'::>a~r1 'Jein~' placecl on the 2~1 Slope in the Shoulclero
I;''
Ph=ito T.-Iousin9 £or the temperature recording device.
Photo 9~ Interior of temperature recording installation. Recording potentio;:neter above, two electrical heaters below.
Table 1 16
Physical Properties of Styrofoam Scorbord SM
ASTM Test Method l" Thick 2" Thick
Density a #/fto 3 2o7 2o3 Tensile Strength o pSio Dl623-59T 56 52 Ultimate Elongationo % Dl623-59T 2o3 2o5 Tensile Modulus, psio Dl~23=59T 2490 1990 Compressive Strength D 621~59T 31 48
at 5% Deformation 0 psio Compressive Moduluso psio Dl621~59T 876 1900 Flexural Strengtho psio C203~58 96 114 Deflection at Break 0 inc C203-58 Oo 57 Oo62 Flexural.Modulus 0 psio C203-58 3830 2750 Shear Strangtho psio C273-53 42 25 Shear Modulus, psio C273~53 652
1 0 Tensile properties were obtained at a crosshead spe.ed of Oo05"/ mine for 1 11 specimens and at Ool"/mino for 2°' specimens, using respectively l" and 2 °' jaw spano
2o Compressive properties were obtained at a crosshead speed of Ool 1Jfuino/ l'" of specimen thicknesso
3o Flexural properties obtained at a crosshead speed of Oo5n/mino for 1 11 specimens and loO"/mino for 2" specimens using a 10" spano
4o ·Shear properties obtained at Oa05"/mino crosshead speedo
TABLE 2
CENTERLINE PROFILE ELEVATION
Before Resurfacing After Resurfacing
Sta. Dec. '63 Feb. "64 May '64 'Dec. '64 Apr. '65 May '65
600+00 99.87
+33 B e g i n
+40 99.99
+60 100.15
+80 100.32
601+00 100.49
+20 100.63
+40 100.79
+60 +oo.93
+80 101.09
602+00 101.23
99.93 99.83
G r a n u 1 a r
100.05
100.17
100.35
100.51
100.64
100.80
100.95
101.13
101.27
101.39
99.97
100.12
100.31
100.48
100.62
100.78
100.92
101. 08
101.24
101. 36
100.08 100.15
B a c k f i 1 1
100.21
100.36
100.55
100.71
100.88
101.02
101.18
101.34
101.50
101.62
100.32
100.43
100.60
100.76
100.90
101.06
101. 21
101.36
101. 51
101. 64
100.07
100.23
100.38
100.57
100.73
100.88
101.03
101.27
101. 33
101. 48
101.62 +20 101.36
+33 tE n d
+40 101.47
G r a n u 1 a r - I e g i n S t y r c f o a m
+60 101.62
+80 101.76
603+00 101.92
+20 102.12
+40 102. 28 '
+60 102.44
+80 102.58
101.48
101.64
101. 78
101.95
102.14
102.30
102.46
101.47
101.62
101. 77
101. 93
102.11
102.28
102.44
101. 75
101.90
102.04
102.22
102.38
102.54
102.70
101. 75
101. 90
102.04
102.21
102.40
102.56
102.72
~02.60 ~02.58 102.85 to2.87 '--~--~+-~~~~L--~~~--''--
(Tab I e Continued On Next Page)
101.73
101. 88
102.03
102.21
102.38
102.55
102.71
102.85
17
., \,.
18
TABLE 2 (Continued)
CENTERLINE PROFILE ELEVATION
Before Resurfacing After Resurfacing
Sta. Dec. '63 Feb. '64 May '64 Dec '64 Apr. '65 May '65
604+00 102.73 102.74 102.73 102.98 103.02 102.99
+20 102.85 102,87 102.86 103.12 103.15 103.11
+40 103.00 103.02 103.00 103.25 103.30 103.26
+60 103.16 103.18 103.17 103.41 103.45 103.42
+80 103.34 103.37 103.34 103,60 103.65 103.63
+85 E n d s t y r o f o a m
605+00 103.56 103.66 103.55 103.80 103,88 103.80
+20 103.73 103.83 103.72 103.99 104.06 103.99
+40 103.92 103.99 103.90 104.18 104.24 104.18
606+00 104.50 104.58 104.49 104~76 104.81 104.78
Average Change Per Section
Dec. '63 Feb. '64 Dec "64 Apr" '65 to to to to
Section Feb. "64 May '64 Apr '65 May '65
Granblar +0.028' -0.038' +0.030' -0.029'
Styrofoam +0.020' -0.018' +0.019' -0,018'
Outside Test Section +0.082' -0.096' +0. 065 ! -0.059'
19 TABLE 3
SUBGRADE MOISTURE CONTENT
..
s t' a t i d h 6 0 1 + 0 0 ( N 0 s t y r 0 f 0 a m }
6 Ft. Lt. of CL 6 Ft. Rt. of CL 14 Ft~ Rt. of CL -· Under Slab Under Slab f n
-· Shoulder
Depth % Moisture % Moisture % Moisture
Inches Apr. "64 May '65 Apr. "64 May "65 Apr. '64 May '65
0- 6 5.7 6.9 4.7 7.0 21.0 17.7
6-12 4.6 4.1 5.1 5.8 10.0 13.4
12-18 4.5 3.5 4.2 4.2 6.0 5.9
18-24 5.1 4.9 --- 4.8 5.9 5.3
24-30 --- --- --- --- 6.7 6.6
30-36 --- --- ,,_,,_...., --- 7.9 7.6
s t a i i 0 n ( 0 2 + 0 0 ( N 0 s t y \,,
0 f 0 a rr )
0- 6 ,, ~ 7 1 6.2 5.8 5.9 14.0 12.6 _, . ,
I i 6-12 5.7 5.4 5.9 5.6 8.0 11.2 '
12-18 4.9 4.1 5.4 5.4 5.6 10.9
18-24 4.9 4.7 --- 5.6 5.3 5.2
24-30 --- --- --- --- 5.6 13.9
30-36 --- --- --- --- 7.1 9.4 ..
36--42 ·---- --- --- --- 11.2 6.6
-· I s t a t i 0 n 6 0 3 + ~~ . !
...,,J .I .... { s t y r 0 f ,:I> a m 0 n 1 y }
0- 6 10.0 13.5 ' 17.3 17.7 --- ---6-12 --- --- 15.0 14.7 18.5 20.5
12-19 --- --- 16.2 15.0 11. 9 15.5
(Table Continued On Next Page) . .
20
TABLE 3 (Continued)
SUBGRADE MOISTURE CONTENT
s t a t i 0 n 6 0 3 + 5 0 (S t y r 0 f 0 a m 0 n 1 y) (Cont.)
6 Ft. Lt. of CL 6 Ft. Rt. of CL 14 Ft. Rt. of CL Under Slab Under Slab ln Shoulder
-
Depth % Moisture % Moisture % Moisture
Inches Apr. '64 May "65 Apr. "64 May "65 Apr. '64 May "65
19-25 14.1 19.0 --- --- --- ---
25-31 --- --- --- --- 17.1 24.0
31-37 --- --- --- --- 20.4 21.9
37-43 --- --- --- --- 18.5 19.3
''
s t a t i 0 n 6 0 4 + 5 0 ( s t y r 0 f 0 a m 0 ri 1 y )
6 Ft. Rt. of CL 14 Ft. Rt. of CL Under Styrofoam In Shoulder
Depth % Moisture % Moist ure
U:nches Apr. "64 May "65 Apr. '64 May '65
\ 12.9 18.9 19.2 17.7 0- 6
! 6-12 17 ;9 17.8 16.9 17.5
k2-18 19.5 17.6 16.9 17.3 ' 1 I
'.18-24 17.3 --- 15.0 16.8 ''
,l
i24-30 --- --- 13.6 13.9
' ~0-36 . 13.4 13.2 --- ---. s t a i 0 n 6 0 2 + 5 0 (Styro:t: 8am and 4 mil pol ye hylene)
0- 6 10.4 14.4 --- ---
'6-12 14.4 14.4 --- ---
~2-18 15.2 14.7 --- ---(Table Continued On Next Page)
21
TABLE 3 (Continued)
SUB'GRADE MOISTURE CONTENT
s t a t i 0 n 6 0 2 + 9 0 (Styrofoam and 4 mil polyethylene)
6 Ft. Rt. of CL 14 Ft. Rt. of CL Under Styrofoam In Shoulder
Depth % Moisture % Moisture
Inches Apr. "64 May "65 Apr. "64 May "65
0- 6 14.6 15.0 --- ---6-12 16.7 16.2 --- ---
12-18 16.4 15.0 --- ---
s t a i 0 n 6 0 3 + 9 0 { s t y r 0 f 0 a m 0 r 1 y )
0- 6 14.6 15.5 --- ---
6-12 17.2 16.3 --- ---
12-18 15.7 14.7 --- ---
s t a i 0 n 6 0 4 + 2 0 ( s t y r 0 f 0 a m 0 r 1 y)
0- 6 14.8 19.2 --- ---6-12 19.2 17.5 --- ---
12-18 18.7 19.9 --- ---
N
l
C"l C"l + ' 0 0 l.O . tlj .µ
450'
0
ROW . . .
-0 l.O
Specie 1 ~
Backfill
-~
Thermocouple Group Thermocouple Wire
Line
Temperatu~a-----------~l ,,.-- I
Recorder · / I t // I I
/ I I /
I I / / I I
/ I / I / f
/ f I / f I
/ I I '. /
/ I I
/ I / q ___ -- _,/f /
/ */ d -- / ·~ ii -- _....,_-<_ - - - I ---- - ----4 Itl..il - - - - I ....... ' ..............
- -Polyethylene , ...... .......
0 .......
- ··-I--- -
..... "O
No Styrc
us #18_1~-bfoam l~" Styrofoam
I 2-3/4" f tyrofoam l~" Sty '"'ofoarn
0 0 + N 0
. \.0 . ro .µ CJ)
9" P.C. Concrete Pavement
Scale l"= 20' Vert. l"= 50' Horiz.
C"l co C"l 0 + -1 N C"l 0 0 l.O l.O . . ro nl .µ .µ CJ) CJ)
Figure 2
0 00 0 M 1..n 0 LO co + -L + + (""') ~ 'tj' 'tj' 0 0 0 0 l.O \.0 l.O l.O
. . . . ro nl fl:I m .µ .µ .µ ,·P·· CJ) CJ) CJ) CJ)
..
. ' ~
N N
0 Thermocouple (Regular Recording)
ag Thermocouple (Alternate Recording)
Scale
l" = 4' horiz.
l" = 10 11 vert.
/O '
3'
~ ~ e '11\J
'\f-~ Ci
0
" "9 0+ I
" @·
\:J ........
@l_
Thermocouple Locations
Sta. 602+00
/Z; >I //; I
9 II P.C. Cone. Pav't. ~
0)
0
0 ~
"ti-
~ 0
• Q)
t 0
'9 ~ "'!-~
0
~
(\j ........
J_ 0
Figure 3
0 'rli.ermocouple (Regular Recording}
~ Thermocouple (Alternate Recording)
Scale
l" = 4' horizo
l" = 10" verto
12.'
1 9 11 PoCo
0 ~-+---
'------+- l~ '' Styrofoam
<!>--- t
Thermocouple Locations
Stao 604+50
Figure 4
Thermocouple (Regular Recording)
Scale:
1" = 4 1 Horizontal 1" = 10" Vertical
/2. I
11'1 J 11 A. C. Surfacing
911 P. C. Concrete ~ ......
0
0
I 10 ~
'-0
+0 '> (\} ......
+0 ,,,. (\j .......
__L~
Figure 5: Thermocouple Locations Sta. 602 + 00 - Effective 5-7-65
ct
~
°" '\}-
e T!1ermocouple (Regular Recording)
Scale:
111 = 4 1 Horizontal 1" = 1011 Vertical
.. ~,__ _____ / 0 / /2. I
'6'/ 14----- 7- --~E------
311 A. C. Surfacing
9 11 P. Co Concrete
Styrofoam
Figure 6~ Thermoeouple Locations Sta. 604 + 50 = Effe-, ':-ive 5=7=65
__j_ --0
0
l I
<P
I
rt
~ '\;)-.. .........
4 """ ~ ;:,
~ "' (X)
~
-t '>
[\j .....__
60
50
.µ ·r-1 40. Q)
.g (]}
H 30 ~ Iii
(I) 20 Q) Q) H tJ"I Q) 10 Cl
0
10
10 20 NOVo
30
1963
Average Daily Air Temperature
___ _]~--------
10 20 30 Dec.
9 19 Jana
Figure 7
29 8 18 Febo
28
1964
9 19 Mare
29 8 18 April
60
50 +> •rl Q)
..c ~ Li-O (!)
~I _,_~
' " ClJ
µ,. -- -UJ '30 Q) Q)
H b0 O,l :? 'J ~
10
']
-10
1 () 2.0 'I 1' ..l..•.'
Nev. 20 Q 1~
Jan.
{\/
8 lO ::i:i Feb.
1of,r: "" ....
10 20 JO ·Lar.
9 10 ~,,
-t'Lpr ...
{\) (;J
J
60
50
40
30
20
10
0
10
Average Daily Temperature
8" below the Surface l" above the Styrofoam
..'..___ --- _Q':._ - --
10 20 30 10 20 30 Novo Deco
1963
9 19 Jan.
Figure
--------------------
29 8
9
11~ 11 below the Surface l" below the Styrofoam
18 28 9 19 29 Febo Maro
1964
I 8 18 April
N
'°
Average Da4ly Temperature
50 14t" Below A~ C~ Surface (1" Below Styrofoc")
Below A. C. Surface ( 11! Above Styrofoam)
40
/
-f -- - - - --,
30 ::
( +:> ·rl Q)
..c:
\ s:: (!)
H 20 ..c: I ell J::r_,
Cl)
~ <D Q)
H till 10 Q)
~
v~ 0 OQ _,_,_. __ - - - - -·--- -- - - - - --
-201----1------'--------'-------'-------1"------.L-----L------L.-----1..----1-----..J_------1 1 11 21 31 10 20 JO 9 19 - 11
December 1964 January 1965 Fetc•1~~ry March
Fig1J.re 10 \._;. ~
40
30
20
10 +' ·rl Q)
·c§ Q)
11 C1}
i:r..
--~
_,.,q_ / \ /
-10_
=20
'
\
\ \
\
\
\
Qf-------"'O
0---- - -0
\_ - ---z1
"-.._
Minimum Air Temperature
Minimum Concrete Temperature 8" Below P. C. Surface (No Styrofoam)
Minimum Concrete Temperature 8 11 Below P. C. Surface (1 11 Above Styrofoam)
(P. C. Concrete is 9 in. thick)
;A, I \ \
1 ', ~ \ ''\
~-~ _j ' ~-~,
I I
b-_ -~
\
'
' \ \
\ \
~ " ' '
=30 ~1Q~.~~~--:-1~2~~-t--~~1~4~~+-~-1~6~~1--~-1~2~~-'--~-2~0~~1-~-2L2~~l-~-2~4~~1--~-2~6~~'--~-2~8~~1-~J~0
December 1963 Figure 11: Concrete temperatures as J.ffe-· L':'!d cw ins'.J.lation - Winter 1963
.,_, ·rl Q)
40
JO
20
"§ JO Q)
.E CIS
fr.. U) (1) Q)
~
Il' o n
=10
~20
=30 12
'
\ \
O'------__,o
o--------0
\
\ '\ /
\/ f
I
14 J.6
Minimum Air Temperature
Minimum Concrete Tem.perd.ure 11 n Below A. C. Surface (No Styrofoam)
Minimim Concrete 'I'ernpe~~ature 11" Below A. C. Surface (1n Above Styrofoam)
(P. Co Concrete is 9 in. thick= Asphalt overlay is Jin.)
'
\
18 20 22 24 26 28 JO January 1965
/ \
/
1
\ \ o.---er-
J 5 F'ebrucry 1965
Figcre 12: ConcreL0 - ci,lJr_"':''c "' affected by in~3U1ation - Winter 1964 - 1965
6
120
110
-P100 ·rl GJ
.. r:::..'
§ ~~I
..d cu
""-· {/)
CJ) 90 CJ)
H OD Q)
~
e.o
70
60
v
15
/ /
o a
er -- - - - --o
ff
17
/ /
I 19
\
Maximum Air Temperature
Maximum Concrete Temperature 11 11 Below A. C. Surface (No Styrofoam)
Maximum Concrete Temperature 11 11 Below A. C. Surface (1" Above Styrofoam)
(P. C. ConcPete is 9 in. thick - Asphalt overlay is J in.)
I
I 21 23 25 27 29 J1
.July 1964
Figure 1J: Concrete temperatures as affected by insulation - Summer 1964 ----
/ /
/
2 August
/ /
'\ /
'd
1964 I....) I....)
4
110
/
100
o----~o
0-------o
' '
Maximum Air Temperature
Maximum Concrete Temperature 11 rt Below A. C, Surface (No Styrofoam)
Maximum Concrete Temperature 11'1 Below A. C. Surface (1 11 Above Styrofoam)
(P. C. Concrete is 9 in. thick - Asphalt overlay is J in.)
9
o---.(f I
11
Figure 14: Concrete temperatures as affeeted by insulation - Sv":mer 1965
P- -/
/ f'
/ /
13
35
~ 11 ~ Air (-26) -.,.j 11 ~ 0
0
(-19) I
5 - 9"· P. C. Concrete c-f7) I P. C. Concrete 911
! l 0 Cl
(-15 -1) 10 - 11-11 Styrofoam 2 0
t 0 ' (J) (34)
15 -0
( 7) . 0 >:: (35) .,;
Q) 0 20 -<U
'+-i H ;::S
Cl) 0
' (13) 0 0 . 25 - (37) A.+
::;: 0 rl
Q) µ::)
Q) 0 ~o >:: ) -cU
+> (/)
.,; A
35 0
0 (24) (38)
40
0
(27)
50_
Figure 15: Minimum Temperatures OF - November 1963 - June 1964
,-.~ , ~' ,/ .•...
~1'r Air (-25) ~1·~ 0 t
Y' A. C. Surf acing A. c. Surfacing " ( 0
5- (-11)
911 P. c. Concrete 0 P. ,., Concrete 911 v,
t !- \
l l \ _,,-, ,:
10_
0 0
(-8) 2) 1t11 Styrofoam 0
15_ 0 (5)
(JO)
0
0 (7)
d 20.._ (Ji) ·rl
(}) u C1l
4-1
~ 25- 0 Cf)
(12) • 0
0 ( 33)
' <.'~
~ 0 30_ r-~ Q)
(ll
<]) ()
r.:: m ~ 35_ ·rl A
0
0 ( 19)
L~O _ (36)
50_ 0 (26)
Figure 16: JVIinimum Temperatures °F November 1964 - May 1965
37
~1i~ Air (99) ~1~~
0 <t:. rt. 1'
I 3" A, Co Surfacing A. C" Surfacing Y'
5 0 - (117)
Po Co Concrete Po Co Concrete 9" 0 911 ( 114) I 10
0 0
11-11 Styrofoam 0
1 c: 0 ( 100)
_; . ( 71_~) s:: ·rl
0
CD 0 (97)
0 (72) ~ 20
s U)
0
0
0
< 25 - 0
6 (94) r--1 0
CD (70) co
CD C.J s:: 30 -m
+> U)
·rl i::i
35 -
0
0 (87)
40 (67)
45 _
0 50 - (84)
Figure 17~ Maximum Temperatures CF - June 1964 - November 1964
38
~1u~ Air (96) ~1u!< 7u~6RU >I 0
<f t 0 0
311 A. C. Surfacing (128)1 Ao Co Surfacing (12J) 3 11
I (1j5)1 5_
(113) ( 110)
9" P. Co Concrete P, C. Concrete Q II /
10-0 0
11-n 2 Styrofoam 0
15_ 0 (92)
. (69) >::: ·rl
0
(lJ 0 (89)
{)
(69) ctj 20_ 4-1 s U)
0
0
0
c::i: 25_ 0 :;: (86) 0 rl Q Q) (67) p.:; Q) u
JO_ >::: Cl)_
+:> [I)
·rl ~
35
0
0 (81)
40 (65)
0 50_ (78)
Figure 18: Maximum Temperatures PF - May 1965 =August 1965
+400
l't.i 0 N ("\
CJ) :> =400 0
..0 <
(/)
» -600 ~
Q) =800 Q)
~ b.D CJ)
~ =1000 CJ)
:> orl .+-) C\l
r-1 =1200 § ;:j ()
-1400
=1600 I< 1JO Days
-18QO 10 20 30 10 20 30 9 19 29
Deco Jana
Figure 19~ Determination of Freezing Index
8 18 28 Feb~
1964
9 19 Mar.
~I
29 8 18 Apro
l:!:...1
0 N (""'\
Q)
:> 0
~ Ul p., m
Q
(j) <D ~. hO Q)
~
Q)
::> or/ +) rn rl § :::l
0
+400
+200
0 -
=200
=400 -
-600
=800
-1000 -
=1200
=1400
=1600
10 20 Nov.
30
1964
10 20 JO Deco
Figure 20~ Determination of Freezing Index
133 Days
9 19 Jano
29 8 18 Febo
28 10 20 Maro
1965
30 9 19 Apr.
o II
10 ....
50 -
II
111111
or Less
I
I ' I I
~ 1 I I I I Pi i I
l I Above J2° F
I
10 20 JO
1963
Figure 21:. Depth at ,fbich avei
I
9 i9 _. ;_.:~ '. i r;>
I I I I ?O ~/ 18 28 9 19
Feb~ Maro 1964
/ I
. I
I
29
I I ~
- I -
-I
8 18 Apro
0 ii II I I
II l Ill II I II I I I I
'"- ~ e ( Ir ~~e -
I ..... ii-ii Styrofoam -10
- --- -
15 ~ ~
- -
'"-- -
~ -
- -
L- -
45 1-- 11111 l I I -32° F Above
or 32° F Less -~ 50
I r I I I i ! ! I I l l I I . I I 10 20 30 10 20 :w
Nov. 1963 Dec" ·.
9 :l.9 29 8 18 ~'.~ar., A.pr~
Figure 22: Depth at ·:-v11J_c1:1 avero.ge temy.H::.:···~1
,_l 5~ § 8 ID
~ JO~ fl.
;s 0
'6 J5~ p::i
QJ
u @ r-0 -~~
+> !fl
•rl i::'.l
45_
50 _
111111 J2<l' F
or Less
I I
I I Above 32° F
I I I I
10 20 JO iC 20 JO Nov~ Dec.
-I ' I i I I l I
9 19 29 8 18 28 10 20 30 9 19 Jan. F~eb~ Mar .. l Apr~
1965
F~~c6ure 23 ~ Depth at which average tem:r)eratures of J2° F or less were recorded
J
" II I II I
c: '-
LO " s::
- 11 ·rl
(!) 15 .__
0 ctl ~ H 20 ;j
U) '-
+:> s:: Q)
s 25 Q) '-p. Qj
p..
~ 30 ,_ rl
Q)
r:r:l Q) 35 0 -c cU
+:> (/)
·rl 40 Q -111111 I I
45 J2° F Above '---
J2° F or Less
50 -I I I I I
10 20 30 10 20 Nov. Dec.
1964
Figure Depth at which av,o;::·s.gc
II I I Ii r ~ hg .J
~ ~
i. t:; I>
'11 :i.t11 Styrofoam
I I I I I ':. (! q ·, ,,
...... ;i q ·~-
l.farl.,.
I 1 p .J.. '~)
I II
I
}i'eb~
I 28
1111 11111
I
10 I
20 Mar.
1111 II
-
-
-
-
-
-
-
-
-
-
I I 30 9 19
Apr.
J