study of hoist performance during peak hours for tall ... · pdf filestudy of hoist...

58
Study of Hoist Performance during Peak Hours for Tall Building Construction By Yufeng Wei A thesis submitted in conformity with the requirements for the degree of Master of Applied Science Civil Engineering University of Toronto © Copyright by Yufeng Wei 2015

Upload: voxuyen

Post on 17-Mar-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Study of Hoist Performance during Peak Hours for Tall Building Construction

By

Yufeng Wei

A thesis submitted in conformity with the requirements

for the degree of Master of Applied Science

Civil Engineering

University of Toronto

© Copyright by Yufeng Wei 2015

ii

Study of Hoist Performance during Peak Hours for Tall Building Construction

Yufeng Wei

Master of Applied Science

Civil Engineering

University of Toronto

2015

Abstract

The increasing height of urban buildings creates challenges in the vertical delivery of essential

resources during construction phase, which makes the efficient use of construction hoists crucial

in building construction. The inappropriate arrangement of temporary hoists can result in a loss

of productivity, especially during peak-hours when a large number of specialty trades requires

hoists simultaneously. To address this challenge, this paper introduces a discrete-event

simulation model that can assist in examining the impact of different lifting strategies on

workers’ delay during peak-hours. The application of the proposed model in high-rise building

projects shows a potential for minimizing workers’ idle time and increase labour productivity.

iii

Acknowledgments

I would never have been able to finish my thesis without the guidance of my supervisor, help

from friends, and support from my family.

I would like to express my deepest gratitude to my supervisor, Prof. Brenda McCabe, for her

excellent guidance, caring, patience, and providing me with an excellent atmosphere for doing

research. I could not have imagined having a better supervisor and mentor for my graduate study.

In addition, I would like to thank Mohamed Kamleh, who provided lots of help on this project.

I would also like to thank my parents and all my friends for their tremendous support and love.

Their suggestion and encouragement make me stay on track. My research would not have been

possible without them.

Sincere appreciation goes to our industry partners: Sam, Gokul, and Steve at Daniels Group for

their enthusiastic support and time.

Finally, I would like to Thank Jie Zhu, who was always cheering me up and stood by me through

the good times and bad.

iv

Table of Contents

Chapter 1 Introduction .....................................................................................................................1

1.1 Background ..........................................................................................................................2

1.1.1 High-rise Building Construction ..............................................................................4

1.1.2 Challenges in Vertical Transportation .....................................................................5

1.2 Research Objective and Scope .............................................................................................7

1.3 Thesis Organization .............................................................................................................8

Chapter 2 Elevator and Hoist Planning ............................................................................................9

2.1 Elevator Planning .................................................................................................................9

2.2 Hoist Planning ....................................................................................................................12

2.3 Challenges in hoist planning ..............................................................................................14

2.4 Summary ............................................................................................................................16

Chapter 3 Methodology .................................................................................................................17

3.1 Numerical Modeling ..........................................................................................................17

3.1.1 Formulation ............................................................................................................17

3.1.2 Development of Numerical Simulation .................................................................18

3.1.3 Benefits of numerical Simulation ..........................................................................21

3.1.4 Limitations of Numerical Simulation ....................................................................21

3.2 Simulation Modeling .........................................................................................................21

3.2.1 Research Endeavor in DES ....................................................................................22

3.2.2 Application of DES to Construction ......................................................................22

3.3 Simulation Tools ................................................................................................................24

3.3.1 Simphony.NET Interface .......................................................................................24

3.3.2 Simphony.Net Basic Elements...............................................................................26

Chapter 4 Development of the Proposed Model ............................................................................30

v

4.1 Model Description .............................................................................................................30

4.2 Simulation of Worker Movement ......................................................................................31

4.2.1 Creation of Workers ...............................................................................................31

4.2.2 Request for a Hoist.................................................................................................33

4.2.3 Making a Stop ........................................................................................................35

4.3 Operation of Hoists .............................................................................................................36

4.3.1 Creation of Hoists ..................................................................................................37

4.3.2 Hoist Operation ......................................................................................................38

4.4 Model Analysis ..................................................................................................................38

4.4.1 Data Collection ......................................................................................................38

4.4.2 Model Validation ...................................................................................................40

4.5 Case Study .........................................................................................................................41

4.5.1 Model Input ............................................................................................................41

4.5.2 Model Output .........................................................................................................41

4.5.3 Summary ................................................................................................................44

Chapter 5 Conclusion and Further Research .................................................................................47

5.1 Conclusions ........................................................................................................................47

5.2 Limitations and Future Research .......................................................................................48

References ......................................................................................................................................48

1

Chapter 1 Introduction

Construction is one of Canada’s largest and most important industries. From residential buildings

to office buildings, highways and bridges to pipeline systems, the construction industry involves

a variety of engineering projects. The industry contributed $116.7 billion to Canada’s gross

domestic product (GDP) in 2013, which accounts for 7.3% of all industries (Industry Canada

2013). As Figure 1.1 shows, construction has become a strong indicator of the Canada’s

economic strength.

Figure 1.1 Canada’s GDP contribution

As a labour and resource intensive industry, 1.3 million job positions related to construction were

created within Canada in 2014 (Statistics Canada 2015). In Ontario, $32.5 billion was spent on

construction projects, making it an important part of local economy (OMAFRA 2014). Due to

the strong growth of the Ontario construction industry, 21,500 new employment positions were

added during 2013 in Ontario (ESDC 2014). By 2012, there were 128,650 construction

companies throughout Canada and 41,205 across Ontario (CIS 2014). These companies are

consuming 40% of the country’s energy and 50 % of Canada’s primary resources (Zuppa 2014).

Any improvement that can be applied in construction industry could have a tremendous social,

environmental, and economic effect.

2

1.1 Background

Although the Canadian construction industry has been growing steadily during the past few

decades, the increasing labour cost and loss in productivity are putting pressure on the whole

industry, pushing companies’ expenses and resource consumption higher. From 1998 to 2011,

the average hourly wage in the construction sector increased from $22 to $24.16, an increase of

9.8%. In contrast, manufacturing and retail trade experienced an average growth of 5.0% and

3.0% respectively (Morissette et al. 2013). The shortage of skilled workers and increasing

salaries will be a risk to the sustainable growth of the construction industry in Canada.

Another challenge over the past two decades was the declining construction productivity, not just

in Ontario, but across all of the North American construction industry (Dozzi and AbouRizk,

1993; Hewage and Ruwanpura, 2006; Sharpe, 2006).

In general, productivity is the ratio of output to input for a given system. Productivity issues in

the construction industry can be divided into macro and micro levels. At the macro-level,

productivity deals with investment and the economic returns to society. It is affected by

contracting models, labour organization, and the economic environment. While at the micro-

level, it considers the management and operation of a project, mainly at job sites (Dozzi and

AbouRizk 1993).

Over the past decades, there has been a significant shift from on-site work to off-site

manufacturing in the construction industry, which means that a large portion of construction

work is now pre-fabricated in factories and assembled on site. However, the off-site work is not

traditionally considered as a part of the construction industry but a sector under manufacturing.

The impact of new technologies does not necessarily mean that these industries are more

productive from a total productivity point of view. However, they may trade off labor for

automation without overall benefits, or even over expend on technology (Eastman and Sacks

2008). Construction productivity is significantly underestimated, because off-site work is

typically ignored when evaluating productivity.

In Canada, construction productivity largely depends on the performance of construction workers

(Jergeas 2009). The improvement of construction efficiency and productivity can be achieved

3

throughout better management of human resource on job sites. Poor management practices and

the loss of labour productivity can lead to delays, cost overruns, and scope changes.

It was estimated that the average real work time for construction workers is 56%, which means

44% of daily work hours are wasted without contributing to the projects (Dozzi and AbouRizk

1993). Other studies confirm these values. An examination of 32 concrete-placement operations

found that for a general worker, direct work and supporting activities constitute only 61% of the

day. Of the remaining, 23% is idle time and 16% is spent waiting (Christian and Hachey 1995).

Table 1.1 shows the results of several similar productivity studies in North America.

Table 1.1 Average Real Work Time

Breakdown

Dozzi &

AbouRizk

1993

Christian &

Hachey

1995

Choy &

Ruwanpura

2006

Hewage &

Ruwanpura

2006

Hewage &

Gannoruwa

2011

Location Alberta,

Canada

Fredericton,

Canada

Calgary,

Canada

Calgary,

Canada

Alberta,

Canada

Work time 56% 61% 60.4% 50.7% 53.2%

Idle

44%

23% 9.4% 9.3% 12.3%

Moving

16%

7.0% 7.8% 14.0%

Socializing 2.6% 8.6% 3.5%

Retrieving materials,

tools and instruction 5.2% 18.9% 6.7%

Others 15.3% 4.7% 10.4%

Thus, it is obvious that the construction industry is facing certain obstacles to achieving higher

productivity. Competition and high labour costs drive construction companies to seek

management strategies and new tools to reduce workers’ waiting and idle time on construction

sites. If only 5%–10% of the nonproductive activities can be transferred into productive

activities, there could be a tremendous cost savings for projects and for the construction industry

as a whole. For non-productive activities, idle, moving and retrieving materials count for a large

portion. Making vertical transportation more efficient can significantly enhance overall

productivity.

Productivity factors can be classified into three groups: human, external, and management

(Liberda et al. 2003).

4

Human factors include worker motivation, worker boredom and fatigue, worker attitude

and morale, worker’s physical limitations, worker absenteeism, worker learning curve,

worker experience, and worker skills as well as the team spirit of crew.

External factors include union rules and influences, adverse weather conditions, noise,

dust, radiation, congested work area, change in drawings and specifications, changes in

contract, demand for over- quality work, and the nature of project (size and complexity).

Management factors include protective gear, unrealistic schedules, overtime, multiple

shifts, excessive shift length, disrespectful treatment of workers, parking facilities, salary

and benefits, site layout, necessity to re-do work, discontinuity in crew makeup, lack of

detailed planning and non-availability of information, materials, tools and equipment.

To sum up, the importance of the construction industry and the loss of productivity remain a

concern. Any improvement can contribute to a significant benefit for the whole construction

industry.

1.1.1 High-rise Building Construction

Over the past century, there has been a dramatic shift toward city living (Brown and Newbold,

2012). The rapid population growth in urban areas and expensive land prices have driven the

demand for high-rise buildings.

A high rise building is defined as one whose total height exceeds 36m or approximately 12

floors. Its use can vary between residential, administrative, or commercial (Farouk 2011). City of

Toronto has more high-rise buildings under construction than any other city in North America

(CBC 2014), which makes it a good example to illustrate the trend of urban development and

high-rise building construction. Figure 1.2 shows a comparison of cumulative floors by

neighborhood, from which the incredible growth of Toronto’s high-rise stock in the past decades.

5

Figure 1.2 Floors of buildings existing in 1954 (left) and 2008 (right) (TOBuild 2010)

A great number of high-rise buildings were constructed to meet the demand of dwelling,

business offices, and entertainment facilities. Toronto is projected to have 45 buildings taller

than 150 metres by 2015, about a 3.5 times increase since 2005 (CTBUH 2014), and leading

North America.

1.1.2 Challenges in Vertical Transportation

As buildings continue to be designed much taller than before, the increasing height of buildings

produces problems in the context of constrained urban spaces. One of the problems is the

efficiency, cost, and safety of vertical delivery during construction.

The vertical delivery of materials and labour on construction sites is mainly achieved using

temporary hoists, tower cranes and concrete pumping systems. However, the increasing number

of high-rise building projects worldwide have introduced new challenges in vertical delivery

(Cho et. al. 2011). As the height of buildings grows, the efficiency of vertical transportation

drops exponentially, thus affecting the safety, cost and overall schedule of projects. In particular,

those sites in spatially constrained urban areas are limited in the amount of equipment that can be

installed on site.

6

Construction temporary hoists, shown in Figure 1.3, are the main method of transporting labour.

Unlike materials that can be lifted during the night, workers need to be transported at the time of

executing their assigned tasks (Moonseo 2013). Therefore, the efficiency of hoist use has a big

impact on workers’ productivity.

Figure 1.3 Construction temporary hoist

A construction temporary hoist, also known as a temporary elevator, construction elevator, or

construction lift, is commonly used in building construction projects to lift materials and labour.

For most building projects, hoists are rented by the general contractor. Unlike a permanent

elevator, temporary hoists are operated manually by an on-board operator, allowing direction

changes or stops at any time according to the operator (Hwang 2009).

Hoists commonly have single or double cages per tower with a capacity varying from 25 to 35

people per cage (Chang-Yeon 2009). That capacity is reduced when materials and tools are

carried on with the workers. The growing height of a building, limited number of hoists, and

7

reduced capacity make workers’ movement between floors inefficient, resulting in a significant

amount of time wasted waiting for hoists each day. For example, during the peak of construction

at the Korea Convention and Exhibition Center in Seoul, South Korea, it took approximately 130

minutes to lift 1200 construction workers to their designated working floors (Moonseo 2013).

Hoist operations are also affected by weather and local regulations, which may restrict hours of

operation. Therefore, optimized planning and operation of construction hoists is needed to reduce

worker waiting time and improve overall schedule performance. Furthermore, since workers

typically begin and end their work day simultaneously, the biggest challenge of hoist operation

optimization is to solve peak-hour congestion.

To sum up, the development of high-rise buildings has introduced new challenges in vertical

transportation during construction phase. One of the challenges project managers are facing is

the efficient delivery of workers during peak hours, which will influence the productivity of the

whole project. Given the growth of high-rise building projects and the loss of productivity in

vertical transportation, this research aims to provide contractors with a method to improve the

performance.

1.2 Research Objective and Scope

The primary objective of this study is to improve hoist operation for high-rise building

construction during peak-hours. The scope is limited to the movement of labour during morning

and evening peak hours. The efficiency or productivity of hoist performance is measured by

worker delay. This study provides the following contributions in the field of construction hoist

operation improvement for high-rise building construction:

A general model that can simulate the movement of construction workers that are lifted

by temporary hoists. The model should be applicable for different vertical traffic

conditions.

An examination of the impact of different hoist operation strategies and worker schedule

alternatives, using minimum model inputs.

An estimation of the required delivery time based on user model inputs.

8

1.3 Thesis Organization

This dissertation is organized according to the following sections.

Chapter 1 – Introduction: provides an overview of the background of the study. Firstly, the

important role construction industry plays in Canada’s economy is presented. Secondly, the loss

in productivity for construction industry is reported. Finally, the challenges in vertical

transportation associated with tall building construction is discussed.

Chapter 2 – Elevator and hoist planning: provides recent research effort on hoist planning.

Firstly, research results in elevator planning are presented as a supplement to hoist study.

Secondly, the difference between hoist and elevator operation is listed. Finally, a literature

review of challenges in hoist planning.

Chapter 3 – Methodology: provides the mythology that is used to analyze the problem. Both

numerical and simulation methods are described. A DES method is selected as the analysis

model for the study.

Chapter 4 – Development of the proposed model: provides detailed information on steps building

the proposed model using Simphony.NET.

Chapter 5 – Model analysis: provides a case study that is used to present how the proposed

model can help in improving hoist efficiency by reducing workers’ delay during peak-hours.

Chapter 6 – Conclusion and recommendation: provides a summary of research results and future

research effort.

9

Chapter 2 Elevator and Hoist Planning

Because of the similarity of function and operation between elevators and hoists, a literature

review of elevator operation planning was conducted to supplement the research. However, there

exist significant differences that make it inappropriate to directly implement elevator planning

methods to hoist planning. This chapter will provide a literature review about current methods of

both elevator and hoist planning.

2.1 Elevator Planning

Modern elevator systems in high-rise buildings consist of groups of elevators administrated by

an elevator group control system (EGCS) and a local control system (LCS) on each elevator

(Munoz et al. 2008). The goal in elevator planning is to configure optimal specifications of

elevator group to build and to set up EGCS and LCS that operate elevator with high efficiency

(Tervonen 2008). When designing the elevator system for a high-rise building, decision makers

shall consider the cost, elevator performance and non-performance criteria based on demand

estimation (Tervonen 2008).

Office building traffic patterns change throughout day. Buildings have characteristic traffic

profiles. For an instance, office buildings typically have up-peak traffic in the morning when

employees enter the building, intense two-way or inter-floor traffic during the lunch time, and

down-peak traffic when employees exit the building (Siikonen and Leppälä 1991).

Modern elevator control systems are required to react to different traffic conditions. The system

automatically recognizes a traffic pattern and triggers the appropriate strategy that leads to the

best system performance. Typical traffic patterns (Strakosch 1982) and respective controlling

strategies were proposed to optimize system performance under varying conditions

(Benmakhlouf and Khator 1993), as shown in Table 2.1.

The traffic pattern can also be defined by traffic intensity. Heavy intensity traffic occurs when

the average loading of each elevator exceeds 50% of its capacity. Average loading of less than

10% capacity will be defined as light traffic intensity. Moderate traffic intensity occurs when the

average load is 10% to 50% of capacity.

10

Table 2.1 Traffic Conditions and Controlling Strategies (Benmakhlouf and Khator 1993)

Traffic

Pattern

When Strategies

Two-way

Traffic

Condition

Occurs when

the number of

passengers

going up and

down is about

the same.

Basic strategy: has no preference between different floors and

passenger arrival. (1) If the elevator answers a call at the first

floor, it picks up all the passengers or to its capacity. The

elevator car only stops when a passenger reaches the

destination. (2) If the elevator answers a call from upper floors,

it will first pick up the passenger on the highest floor to its

capacity. The car only answers landing call in its way when the

maximum capacity is not reached. (3) The elevator car has

dwell time at the ground floor and upper floors. Dwell time is

the time an elevator is waiting for coming passengers.

Incoming

Traffic

Condition

Occurs when

most of the

passengers are

going up.

Basic strategy: the difference between model 2 and model 1 is

that model 2 does not have dwell time at upper floors.

Advance strategy: the difference between model 3 and model 1

is that: (1) a call from ground floor has priority over upper floor

calls. (2) When a car returns to the ground floor, it has to wait

for incoming passengers for a period of time, then it will be free

to answer upper landing calls. (3) Once passengers are picked

up from the ground floor, the car travels up and drops off

passengers until the highest destination is reached. After

reversing its direction, the car could stop at a floor if there are at

least one car waiting at the ground floor.

Outgoing

Traffic

Condition

Occurs when

most of the

passengers are

going down.

Basic Strategy: the difference between model 4 and model 1 is

that: (1) landing calls from upper floors are given a priority. (2)

There is no dwell time at the ground floor. (3) If a car drops off

all the passenger at an upper floor, it will answer the highest

landing call instead of returning to the ground floor.

Advanced Strategy: the difference between model 5 and model

1 is that: (1) No dwell time at the ground floor. (2) Higher

priority is given to upper floors. (3) The building might be

divided into zones, which means a car can only response to the

calls registered within the zone.

The performance of a group of elevators is mainly determined by the number of available cars,

capacity, speed, acceleration, door type and controlling algorithm. Performance criteria are the

handling capacity and the interval calculated in the up-peak situation (Barney and Santos 1985).

The handling capacity is the percentage of passengers that can be lifted to upper floors in 5

minutes, and the interval is the time between two starts at the ground floor during up-peak hours.

The up-peak condition is studied because it is the most demanding situation in office buildings

(Barney and Santos 1985). Handling capacity and interval are both related to passenger waiting

11

time (WT), which is a more straightforward expression of system efficiency. Three factors are

used to evaluate the performance of a given elevator system (Benmakhlouf and Khator 1993).

Passenger waiting time is the time between passengers requesting an elevator and its

arrival to serve the call.

Passenger travel time is the time a passenger spends in the elevator. If a passenger’s

objective is to reach their destination as soon as possible, they will give equal weight to

waiting or riding an elevator.

Five-minute system efficiency is the number of passengers that exit the system divided

by the number of passengers that enter the system in 5 minutes.

It is also desirable to optimize the elevator configuration in terms of cost, efficiency and

environment effect. Due to safety and feasibility concerns, computer simulation modeling is the

most used technique to determine the best operation strategy while making elevator plans. To

simplify the model, the following assumptions were made when building elevator simulation

models (Leinonen 1999; Hakonen 2003).

When passengers are calling for an elevator, the (up/down) direction that he/she is

heading will be given.

When making a stop, the elevator door will be open, entering people get in, exiting

people get out, and door will close. The time for these activities to occur is taken into

consideration.

The bypass load is less than the maximum load of the elevator, which means if the load

exceeds a percentage of the maximum load (usually 80%), the elevator will stop letting

people in. While elevator still makes stops if on-board passengers need to get off.

The elevator cannot reverse its direction until last onboard call is answered.

The elevator will accelerate and decelerate before and after each stop. When the elevator

reaches its maximum speed, it will travel at a constant speed unless a stop is to be made.

Passengers follow a First-in-First-out rule to enter the elevator.

During peak hour, a passenger can only travel up from the ground floor or go down to the

ground floor. Inter-floor traffic is ignored (Benmakhlouf and Khator 1993).

The above assumptions are made in most elevator simulation models to support making optimal

choices for elevator group based on multiple criteria. Because of the scarcity of hoist study and

12

the similarity between hoist and elevator, the above assumptions can be well implemented in this

hoist study as appropriate.

2.2 Hoist Planning

A hoist system consists of a mast, ties, and one or two cars (cages). The mast tower is tied to the

building structure for stability, and cars travel vertically along the mast. Additional components

required to operate the hoists include machinery equipment, landing platform, access road, and

loading/unloading stations.

Hoists and cranes are the most important equipment for high-rise construction. Hoists usually

serve as the main means of vertical transportation of resources, including labour, materials and

equipment. An effective hoist management plan is vital for the project, because almost every

construction trade depends on hoists to move its workers, tools and materials. Therefore, an

ineffective hoist plan could result in a bad influence on overall performance. Factors that can

lead to significant delay of the project as a consequence of inappropriate hoist planning include

(Hwang 2009):

Failure of coordination between structure and hoist erection schedule.

Late procurement of hoists and resulting in delay of erection of buildings.

Failure to secure enough clearance between hoists and building structure.

Shortage of available hoists and competition between trades.

Redundant hoists and resulting in idle.

Difficulty in loading and unloading materials.

Violation of local codes and restrictions.

Delayed interior finishing and building occupancy due to hoists.

For most building projects, hoists are leased or purchased by the general contractor. The

construction manager has to make careful decisions on selection, operation, erection and

maintenance of their hoists. When making the decision, it is important to consider the number of

hoists (single, double or triple), type of hoists (capacity and speed), rental or purchase of hoists,

and the location of the hoists and landing platform. To determine these variables, decision

makers need to know information about the project and its constraints.

Table 2.2 Input variables of hoist planning (Hwang 2009)

13

Input Variables Introduction

Project data

Basic information of the construction project, including the number of

floors, construction and project schedule, site logistics, potential landing

platform, trades that need hoists frequently, and available hoist models &

specifications.

Resource Schedule

Number of workers on site each day, largest pieces of materials that have

to be lifted by hoists, amount of resources that need to be hoisted to each

floor, and schedule of different trades.

Constraints

Shape of the building (hoist mast has to be vertical and tied to the

building), minimum clearance between hoist cars and building, safety and

maintenance requirements.

Arrangement Delivery, erection and dismantling of hoists, landing floors and contractors.

Among all the factors, hoist type is the most important. Table 2.3 provides examples of hoists,

from which we can see that decision makers have a variety of choices of different types of hoists.

Table 2.3 Hoist types and specifications (Morrow 2015; Metro Elevator 2015)

Model Double or

Single

Max Height

(m)

Load

Capacity

(kg)

Max

Passengers

per car

Max Speed

(m/min)

FC 6200-12 Single 150 2810 30 48

FC 6200-12D Double 150 2810 30 48

FC 6800-12 HS Single 200 3100 30 116

FC 6800-12D HS Double 200 3100 30 116

FC 7100-12 Single 200 3220 29 53

Champion US-60-1R Single 274 2722 30 46

Champion US-6002-1R Single 274 2722 30 92

Champion US-60-2R Double 274 2722 30 46

Champion US-6002-2R Double 274 2722 30 92

Champion US-80-2R Double 274 3600 40 44

The bypass capacity for hoists will be less than the rated capacity when materials and tools are

carried with workers. Considering the function and operation, a temporary hoist is very similar to

a permanent elevator. There are, however, a few notable differences that decision makers have to

pay attention to when hoist planning, as shown in Table 2.4.

14

Table 2.4 Difference between hoist and elevator operation (Leinonen 1999; Hakonen 2003)

Elevator Hoist

Floors have landing buttons. Passengers give a

call with a (up/down) direction where they are

heading.

Workers have interphone. Current floor and

the direction will be given to the operator

when workers use hoists.

The group control algorithm allocates the call

to the most suitable elevator (Tervonon et al.

2008). The control system also has a return

algorithm to determine whether the elevator

shall return the ground floor.

The on-board operator controls the hoists

manually. There is no or little communication

between operators in different hoist cars.

When an elevator makes a stop, the door

opens and closes automatically.

Hoist doors are opened and closed manually

by the operator. The operator is in charge of

making stops.

An elevator can take a number of passengers

up to the bypass capacity, which is about 80%

of the rated load. Elevators still make stops

when the bypass capacity is reached if on-

board passengers need to get off but stop

answering landing calls

As workers tend to carry tools during peak

hours, the bypass load might be much less

than the rated load (Tervonen et al. 2008).

Due to the limited space in hoist car, the

bypass capacity could be 60% of the rated

loading in practice.

An elevator cannot reverse the direction while

passengers are on board.

A hoist can reverse the direction at any time.

Elevators typically only serve passengers. Hoists lift workers as well as materials and

tools.

In terms of traffic patterns, similar to office buildings, construction sites have up-peak and down-

peak hours. Up-peak is when workers’ complete daily safety meeting and start working. Down-

peak hour is when workers get back to ground floor. The demand on hoists depends on the

schedule and varies with trades.

2.3 Challenges in hoist planning

Peak traffic is a temporal surge of lifting demand accumulated during a certain period of time

(Moonseo et al. 2013), resulting in low system efficiency. An on-site observation and interviews

with project managers confirmed the significant productivity loss due to inappropriate hoist

planning. Workers may have to wait to access to the hoists, which might reduce a big portion of

workers’ working time for tall building construction projects.

A questionnaire survey of construction managers was conducted to determine the factors that can

affect hoist system performance (Hwang 2009). The results of the survey show that majority of

15

the respondents (about 80%) pointed the following decision variables: number of hoists,

capacity, location of landing platform, cost (Hwang 2009). This study formed a guideline for

decision makers. But a quantitative mothed is needed for hoist planning.

There has been notable research effort to solve the challenges of optimized hoist planning.

Vertical transportation on construction sites was first interpreted as a cyclic operation (Ioannou

and Martinez 1996), which shows great potential in solving hoist planning problems. Discrete

event simulation method was applied to hoist planning study by helping site managers determine

the required type of hoists and develop operation plans (Ahn 2004). However, these research

focused on hoist productivity and cost of hoists instead of the impact on workers’ delay. To

address the influence of hoist operation on workers, movement of workers during high-rise

building construction was studied, and a discrete-event simulation model was established to

estimate waiting time for workers. What is more, the model considers the change in demand

during the process of construction (Cho et al. 2010). When using simulation method for

planning, all possible alternatives shall be considered to determine the optimal one. The more

input of the simulation model, the more possible alternative plans. It is difficult even impossible

to optimize simulation output when possible alternatives increase explosively without using

artificial intelligence (AI) (Shin et al. 2010). Recent research has proven the feasibility of

applying AI in optimization problems. A discrete event simulation model integrated with genetic

algorithm was applied to assist hoist planning (Shin et al. 2010). The method shows a potential in

increasing planning efficiency. When multiple hoists are available, hoist operation can be

optimized by simplifying it as a Traveling Salesman Problem (TSP). An algorithm derived from

branch and bound (B&B) algorithm was proposed to solve the TSP problem (Cho 2013). The

algorithm has been proven feasible in solving planning optimization problems.

Zoning is a typical management technique in elevator planning. It can also be used in hoist

management by dividing floors onto clusters and assigning a group of lifts for each cluster.

However, it is challenging to derive an optimal zoning configuration for the construction of high-

rise buildings because the lifting demand changes along with the progress of construction

(Moonseo et al. 2013). The zoning configuration determined through a computer simulation

model has shown that lifting-demand based zoning can reduce the vertical lifting of workers by

40% (Moonseo et al. 2013).

16

To sum up, hoist planning needs quantitative simulation method to determine the optimal plan.

Current research fail to establish a general simulation model to study workers’ movement under

a variety of lifting demand. To be more specific, studies have been focused on morning-peak,

while traffic during lunch break and evening peak hours has been neglected. And current studies

tend to seek for the optimal configuration of single strategy (e.g. zoning). A comparison of the

impact of different management on workers’ productivity is needed. This paper will focus on

creating model to simulate hoist operation under different conditions and analyzing impact of

different management strategies on hoist efficiency.

2.4 Summary

There has been notable research effort in the elevator industry to minimize passengers’ waiting

time for different traffic conditions in high-rise office buildings. Due to the similarity of traffic

pattern, function, and operation, research results from elevator studies can be implemented in

hoists research. However, the difference between hoists and elevators make direct application of

elevator tools to hoist planning inappropriate.

To solve the challenges in vertical delivery, simulation methods were proposed to minimize the

waiting times for workers during peak hours for high-rise building construction.

17

Chapter 3 Methodology

This chapter will introduce the analysis methods for hoist planning, including numerical and

simulation methods. The selected method, discrete event simulation, will be described in detail,

including the simulation environment, Simphony.NET, upon which the proposed model is based.

3.1 Numerical Modeling

Numerical method is a simplified way of estimating hoist performance by directly calculating a

worker’s waiting time. It significantly reduces the complexity of modeling and provides results

with the fewer variable inputs.

3.1.1 Formulation

Vertical transportation of workers is a cyclic operation. The cycle time can be divided into two

parts: one is the travel time and the other is the time required for each stop. So the calculation of

cyclic time for each trip can be expressed by:

T=Tt + Ts [Eq. 1]

T---Cycle time for each round trip.

Tt---Lifting time. Time that a hoist spends traveling between floors at full operation speed.

Ts---Time spent loading/unloading acceleration/deceleration, and door opening/closing time.

Assume that in one round trip, the hoist runs from the ground floor to the Nth floor with k stops.

The cycle time can be described by:

Tt=2*h*(N-1)/s [Eq. 2]

Ts= Tl* (k+1) [Eq. 3]

So that:

T=2*h*(N-1)/s + Tl* (k+1) [Eq. 4]

h---The height of each floor.

18

s---The rated speed of the hoists.

Tl---Time loss in loading/unloading, acceleration/deceleration, and door opening/closing time for

each stop,

The total time loss related to making stops is k+1, because ground floor must be included.

By simplifying hoist operation as cyclic actives, the calculation of time required for each trip

only needs the input of number of stops to make, the highest floor for up-peak traffic, operation

speed of the hoist and floor height.

Waiting time is the time between worker arrival and hoist arrival to serve the request. Therefore,

waiting time for workers in the same hoist car (same cycle) should be the same.

[Eq. 5]

Wn---Waiting time for cycle n.

T(i)---Cycle time of ith cycle.

For example, waiting time for the third cycle will be the sum of cycle time of the first two cycles:

W3=T0+T1+T2, where T0=0.

3.1.2 Development of Numerical Simulation

The goal of numerical simulation for hoist planning is to evaluate workers’ delay based on user

inputs. Two user inputs will affect the output:

Working floors is the number of floors that hoists serve. Workers will follow the plan and

go to their designated floors. If the floor plan is not given, workers will choose a random

destination floor in the simulation.

Number of workers: is the amount of workers that need to be lifted during peak-hours.

Hoist type: is the information about the hoists on site, including the speed, capacity and

how many hoists are available.

19

From section 3.1.1, the required time for lifting all workers depends on number of cycles and

time spent on each cycle. Using above three input variables, the number of cycles and number of

stops for each cycle can be determined. For an instance, number of workers along with hoist

capacity can determine the number of cycles. Working floors determine the number of stops to

make for each cycle. Hoist speed is used to calculate travel time between floors.

When conducting the numerical simulation, there are some assumption to make. First, workers

arrive simultaneously at the ground floor and queue to go to their destination floors. Second, all

workers are going the same direction in peak-hours. Finally, inter-floor traffic is not allowed

during peak-hours. Table 3.1 shows the steps of calculating waiting time using the numerical

method. The output the model will be the total waiting time or average waiting time for each

worker.

Table 3.1 Numerical Model Framework

Level 1: Worker

Arrival Level 2: Cycle Time Calculation

Level 3: Waiting Time

Calculation

Generate workers,

and assign each

worker with a

designated floor

Step1: Calculation the number of cycles that

is needed based on the number of workers

and the capacity of hoists.

Calculate average waiting

time based on number of

trips and cycle time of

each trip.

Step2: Group workers such that they

represent the workers that are lifted each

cycle.

Step3: Calculated number of stops, and find

out the highest floor for each trip.

Step4: Calculate cycle time for each trip.

An example is provided to show how waiting time is calculated through the numerical model.

The following assumptions have been made:

1. Workers’ destination floors depend on floor plan. Each worker randomly chooses a floor

within his working floors.

20

2. Numerical model will use input from table 3.2 and table 3.3. Time loss per stop is estimated

from the data collected, which will be discussed in section 4.3.1. The time loss for each stop

is the mean of the data collected from construction sites.

3. All workers reach the hoist at the same time in the morning.

Level One:

Table 3.2 Floor plan

Working Floors Number of Workers

2-15 30

16-30 15

Table 3.3 Building and hoist information

Hoist Information Building Information Operation Information

Capacity Speed (s) Type Floor Height (h) Time loss per stop (Tl)

15workers/car 90m/min Single 3 m 0.6 min

Cycles needed : (30+15)/15=3 cycles

Level Two: Steps Two and Three

In the simulation, workers will be assigned a random designated floor if no specific schedule is

given. Every 15 workers (hoist capacity) will be lifted together. For each trip, the highest floor

determines from the workers in the hoist highest floor.

Table 3.4 Model level 2, step 1-3

Cycle One Cycle Two Cycle Three

Number of

Stops (k1)

Highest floor

(N1)

Number of

Stops (k2)

Highest floor

(N2)

Number of

Stops (k3)

Highest floor

(N3)

12 27 11 30 13 25

Level Two: Step Four

Using Equation 4: T=2*h*(N-1)/s + Tl* (k+1)

With equation 4 and table 3.4, cycle time of each group can be calculated. Based on the

calculation of cycle time, waiting time can also be calculated using Equation 5.

21

Table 3.5 Numerical simulation results

Cycle one Cycle two Cycle three

Cycle Time (T) 9.5 min 9.1 min 10 min

Waiting Time (Tw) 0 min 9.5 min 9.1 min

3.1.3 Benefits of numerical Simulation

Numerical model provides decision makers a simple and fast way to calculate cycle time

and waiting time for hoist operation in peak hours.

The model minimizes the input parameters which can be easily retrieved from project

schedule and hoist manufacturing information.

3.1.4 Limitations of Numerical Simulation

Numerical modeling is a simplified way of estimating waiting time for peak-hour traffic;

however, it has several limitations.

The model has little flexibility to adapt to down-peak or lunch break scenarios, because

of the different traffic conditions. The model is a numerical and simplified method to

calculate up-peak congestion, adaption to other scenarios requires a redesign of the model

framework.

The method cannot consider the impact of management strategies regarding workers’

arrival or hoist operation, such as, staggered arrivals or building zoning.

Inter-floor traffic in the model is not allowed, which means the origin of each trip has to

be the ground floor.

3.2 Simulation Modeling

Simulation technology is a powerful tool that can be used for resource planning, design and

analysis of construction methods, site planning, and risk assessment (Sawhney et al. 1998). The

development of construction simulation was motivated by the need to solve stochastic problems

encountered during construction, such as establishing cost range, evaluation of project

completion time, and various production of construction processes (AbouRizk et al. 1992).

Because construction is dynamic, complex, cyclic, and involves uncertainties, the discrete-event

22

simulation (DES) is well suited as an alternative to solve interactive construction planning

problems.

Discrete event simulation (DES) models the operation of a system as a discrete sequence of

events in time. Each event occurs at a particular instant in time and lasts for a certain period,

marking a change of status in the system (Robinson 2004). An event in the context of discrete

event simulation can be defined as an instant of time at which a significant state change occurs in

the system (Pidd 1989).

3.2.1 Research Endeavor in DES

Discrete-event simulation was described as “the modeling of a system as it evolves over time by

a presentation in which the state variables change only at a countable number of points in time”

(Law and Kelton 1982). Since the application of CYCLONE technology in construction industry

(Halpin 1977), computer aided DES modeling has become a powerful tool for engineers, which

eventually leads to productive and efficient field operations.

Modelers, however, are required to be familiar with specific terminology and modeling

schematics to simulate with an acceptable degree of accuracy and confidence (Lu 2003). Recent

effort was spent on making simulation methods easier for users. There are two approaches that

can simplify the construction modeling by using activity-based approaches (Shi 1999) or event-

based approaches to develop application frameworks (Hajjar and AbouRizk 2000). A new

simplified discrete-event simulation approach (SDESA) was developed by combining the

advanced features of event and activity based simulation methods (Lu 2003). The methodology

was outlined for conducting DES studies of construction operations (Martinez 2010). A practical

approach was proposed for handling the complicity in off-site construction planning using a DES

model (Alvanchi et al. 2012).

3.2.2 Application of DES to Construction

A key issue while developing a model is to balance the complexity of the real system with the

simplifications and assumptions necessary to create a model without making it trivial or

misleading (Shannon 1999). Typically, problems that are well-suited to discrete-event simulation

have (Martinez 2010):

23

Significant uncertainty in the time required for tasks, or the amount of resources and

materials;

Logical complexity with dynamic decision making rules;

Interdependent components, such as, many resources that must collaborate to complete

tasks, or activities that have compulsory precedent or succeeding activities; or,

Data that can be collected to support building the models.

Hoist planning problem well fits the above criteria. Firstly, lifting operation involves uncertainty

in worker decision and hoist operation. Workers’ designated floors and the number of workers

might change from time to time, and hoist type varies from case to case. Secondly, operation

activities, such as loading/unloading and traveling among floors, need a complex and logical

strategy. Finally, site observation can prove the accuracy of model estimation.

Steps used in DES modeling for construction studies (Martinez 2010) are provided.

Table 3.6 Steps of building DES model

Steps General steps of building DES model Development of hoist simulation

model

1 Determine the extent to which a DES

model can lead to a better solution to

the problem or a better understanding

of current situation.

Hoist operation involves complex

cyclic activities, which makes it more

efficient to solve using DES model.

2 Establish the scope of the model and

the specific questions or problem the

model should answer and solve.

Section 1.2

3 Define the model for the operation by

selecting the elements that will be used

to present the real system (e.g.,

resources, tasks and waiting queuing).

Section 4.2 and Section 4.3

4 Collect data to determine the type of

probabilistic distribution to suit the

model. Independence assumptions

among activities have to be made and

tested.

Section 4.4.1

5

Validate model and data to ensure they

match the understanding of the system.

Design and execute a simulation

experiment to validate the model to

ensure the output matches the real

Section 4.4.2

24

Steps General steps of building DES model Development of hoist simulation

model

system.

6 Analyze input of the model to select

sets of input to ensure the model can

represent the situation that are needed

to study.

Section 4.5

7 Analyze output of the model to

determine the performance of various

system configurations and select the

best alternative for decision making.

Section 4.5

These steps work as a guideline for building the proposed model.

3.3 Simulation Tools

Based on the idea of discrete-event simulation, computer simulation environments were

developed, such as CYCLONE and Visual SLAM. Based on CYCLONE, different versions of

simulation environments were developed to meet specific need of construction operation, like

INSIGHT. RESQUE and Simphony.NET (Lu 2003). The simulation environment that is used in

this research is Simphony.NET which simulates construction systems by analyzing the flow of

entities. Entities pass through a sequence of activities in a process and interact with resources at

each activity for a certain duration. Each entity carries its attributes, so that statistical analysis

can be conducted on status of entities.

3.3.1 Simphony.NET Interface

Simphony.NET is one of the offspring of CYCLONE. Simphony.NET makes DES modeling

much easier with its graphic user interface, shown in Figure 3.1.

25

Figure 3.1 Simphony.NET user interface

The function of each section is provided.

Template Area: displays elements available in the modeling element library to construct

new projects. Elements are categorized by the templates to which they belong and by

folders within the templates.

Model Explorer: has navigation tree of current simulation project structure, including

Scenarios and Composite elements belonging to each scenario

Property Grid: displays property of each scenario or modeling elements. Users can

specify name and input parameters of scenarios or modeling elements by selecting or

writing VB code.

Modeling Space: is the main workspace for building simulations. Users can drag and

drop modeling elements from Template area. Each Scenario contains an independent

simulation model, which can represent either the entire project, or several instances of the

same project with different settings for comparison purposes.

Modeling

Space

Template Area

Model Explorer

Property Grid

Trace

Window

Menu

Bar

26

Trace Window: displays trace messages defined in the Trace modeling element or in user

code during a simulation. It also shows feedback regarding errors that occur during

modeling.

3.3.2 Simphony.Net Basic Elements

Simphony simulation environment is activity-orientated, in which all the activities are expressed

by nodes and activated by passing entities. Once entities are created, they will pass through the

network’s nodes and links. Table 3.4 provides a description of primary nodes.

Table 3.7 Primary Elements of Simphony.NET

Node Symbol Description Input

Parameters

Output

Parameters

Create

Creates entities at different

quantities.

Quantity

First

Interval

Total number of

entity created

Task

Used to represent an

activity. There are two

types of task: constrained

and unconstrained.

Duration

Severs

N/A

Counter

Counting the number of

entities passed.

Initial

Limit

Count

Time

Set

Attribute

Allows the user to assign

attributes to the passing

entities.

Floats; Ints;

Strings

N/A

Destroy

Deletes any entities that

arrive at the element.

N/A N/A

27

Node Symbol Description Input

Parameters

Output

Parameters

Execute

Executes an expression

customized by user.

Expression N/A

Trace

Allows the user to track the

progress of the model by

outputting user-specified

text.

Expression N/A

Branch

Directs the entity to a

different path based on

either a user –specified

probability or condition.

Expression or

Probabilistic

N/A

Resource

Creates a resource in the

model.

Severs Available

File

Creates a waiting file for

accessing resources.

IsBlocking:

whether entity

can change

queueing for the

same resource.

N/A

Capture

Allows the entities to

capture resources.

File; Sever;

Resource;

Priority

N/A

Release

Allows the entities to

release resources. Usually

in pairs with Capture.

Resource; Sever N/A

28

Node Symbol Description Input

Parameters

Output

Parameters

Statistic

Shows the results of

selected variables.

N/A N/A

StatisticCo

llect

Adds observations to a

statistic element.

Statistic; Value N/A

Valve

Stop or allow the entities to

pass.

AutoClose;

Initial State

Current length;

state

Activator

Open or close a Valve Action; Valve N/A

Figure 3.3 Sample Model

Figure 3.3 shows a sample model created with the help of Simphony.NET, in which different

elements are connected with links. Nodes will be activated when an entity passes and the system

will automatically track all of the activities. Workers, as entities, are created at the start of

simulation, representing their arrival. The conditional branch will decide whether a worker can

29

get on the hoist based on the availability of hoists. After workers spend time on the hoist, they

are destroyed, which means they arrive the designated floor and are deleted from system.

30

Chapter 4 Development of the Proposed Model

This chapter will introduce the simulation model built in Simphony.NET to study the

performance of the hoist. To be more specific, the framework, input and output of the model. A

case study will be used to demonstrate the impact of different management strategies on the

efficiency of hoist performance.

4.1 Model Description

To ensure that the proposed model can fulfill the objective of this study, several elements have

been considered.

The simulated process can represent the movement of worker and operation of hoists in

practice.

The model can be adapted for different projects or phases of the construction. This allows

users to easily change the inputs of the model.

The model should be able to simulate hoist operations for both up-peak (morning peak)

and down-peak (evening peak) scenarios. This requires the model to develop a general

mechanism to answer calls.

The model should be able to provide feedback on different operation strategies so that

project managers can find the optimal strategy for a specific project. This requires that the

decision tree built in the model, shown in Figure 4.1, can be changed to meet different

requirements.

The model shall enable decision makers to compare worker delay for different model

inputs. This requires more flexibility of the model to generate outputs.

The structure of the proposed model can be divided into two parts: the movement of workers and

the operation of hoists. These two parts work collaboratively and simultaneously, as shown in

Figures 4.1 and 4.2.

31

Creation of

workers

Request for a

hoist

Hoist

Available

Wait

No

Stay in

hoist carYes

Make a

stop

No

Reach

designated floor

Yes

Creation of

workers

Idling at

ground floor

Receive Call

Answer call

Hoist

operation

Yes

Finish

trip

Yes

No

Figure 4.1 Worker Movement Figure 4.2 Hoist Operation

4.2 Simulation of Worker Movement

4.2.1 Creation of Workers

Worker entities will be created and assigned an ID and other attributes, shown in Table 4.1.

Table 4.1 Worker attributes

Attributes Type Description

Worker ID Integer Every worker is assigned a unique ID so that the system can track

individuals. The system performance analysis is achieved through

statistically analyzing the delay of each worker.

Current

floor

Integer Current floor information is the current location of each worker. For the

morning peak scenario, the current floor is the ground floor. For the

evening peak scenario, current floor is the floor where workers finish

their work at the end of the day, which is determined by the floor

schedule.

Designated

floor

Integer This attribution describes the destination of workers’ trip. For the

morning scenario, it will be workers’ designated floor. And for the

evening scenario, it will be the ground floor. If internal trips are

allowed during peak hours, this attribute can be any floor in the

building.

32

Hoist

number

Integer If there are more than one hoists on site, each of them will be assigned

an ID number. When a worker chooses a hoist to take, this information

will be added to the log.

Request

time

Float This attribute is the time (according to system clock) a worker ask for

the hoist. It does not have to be zero, if workers arrive/leave stagger.

Get on time Float This attribute is the time (according to system clock) that the hoist is

going to pick up the worker arrives at that floor. Therefore, the time for

workers on the same floor to get on hoists the same.

Get off time Float This attribute is the time (according to system clock) that the hoist

reaches the designated floor and opens the door.

Figure 4.3 the creation of workers

Table 4.2 Sample coding to set attributes to each entity

Element: SetAttributes

imports Simphony.Mathematics

Public Partial Class Formulas

Public Shared Function Formula(ByVal context As

Simphony.Modeling.Element(Of Simphony.Simulation.GeneralEntity)) As

System.String

context.CurrentEntity.Ints(1) =1

context.CurrentEntity.Ints(2)=1

context.CurrentEntity.Ints(3)= cint (uniform.sample(2,10))

context.CurrentEntity.Floats(2)=context.Engine.TimeNow

Return Nothing

End Function

End Class

33

Because trades may require different start times, the workers can be created in groups with a

defined inter-arrival time. Then the information of each worker can be initialized, including

worker ID, current floor, designated floor and time of arrival.

4.2.2 Request for a Hoist

When a worker needs to access a hoist, a request will be sent to the system with the worker’s

current floor and the destination floor. The information is updated in the hoist operation part.

Workers have to wait at their current floor until a hoist arrives to pick them up. Workers stay in

the hoist car and travel with the hoist until the hoist reaches the worker’s destination floor and

stops at that floor.

Available Hoist

Launch One

Update call

waiting list

No

Yes

Wait for

hoistsWorker

ArrivalHoist Arrive

No

Yes

Figure 4.4 Flow chart of requesting a hoist

34

Figure 4.5 Hoist Request Mechanism

After workers request a hoist, the model will decide which hoist will answer the call based on the

status of the hoists.

Figure 4.4 and 4.5 show the mechanism that decides whether to launch a hoist in idle to pick up

waiting workers. If there are available hoists at the ground floor and workers are currently at the

ground floor, then one of those hoists will respond to their call. If none of the hoists is available,

the request call list will be updated and the hoist will answer the call when the landing calls are

answered. Workers will wait on their current floor until a hoist comes to pick them up. If the

35

hoist is full when reaching the floor, workers will make a request again. If there are more than

one hoists at the floor, workers will be assigned to each hoist with equal possibility.

4.2.3 Making a Stop

While workers are traveling in the hoist car, the hoist will stop if the workers on the hoist have

reached their destination floor and let workers get off.

After workers arrive at their destination floors, the attributes they carry will be collected and

used as indicators of system performance. Data that are collected from each entity are worker ID,

original floor, destination floor, arrival time, request time, get-off/on time. These data can be

used to calculate average waiting time and system efficiency. Table 4.4 shows the coding used to

summarize results.

Figure 4.6 making a stop Table 4.3 Coding for making a stop

Element: Hoist Info -1

Public Partial Class Formulas

Public Shared Function

Formula(ByVal context As

Simphony.Modeling.Element(Of

Simphony.Simulation.GeneralEn

tity)) As System.String

context.Scenario.Ints(9

)= context.Scenario.Ints(9) -

1

context.Scenario.Ints(1

3)=1

context.CurrentEntity.F

loats(3)=context.Engine.TimeN

ow

Return Nothing

End Function

End Class

36

Table 4.4 Coding for result return

Element: RReport

Public Partial Class Formulas

Public Shared Function Formula(ByVal context As

Simphony.General.Trace) As System.String

Return "Hoist#" & cstr (context.CurrentEntity.Ints(4))& "

Request Time " &Cstr(context.CurrentEntity.Floats(0)) &" GetOnTime "&

Cstr(Context.CurrentEntity.Floats(1))& " GetOff "&

Cstr(context.CurrentEntity.floats(3))&" From " & cstr

(context.CurrentEntity.Ints(2)) & "to" & cstr

(context.CurrentEntity.Ints(3)) &" "& "1---"&

cstr(context.Scenario.Ints(3)) &"peole"&cstr(context.Scenario.Ints(9))&"D"&

cstr(context.Scenario.Ints(5))&","& "2---"

&cstr(context.Scenario.Ints(4))&"peole"&cstr(context.Scenario.Ints(10))&"D"&

cstr(context.Scenario.Ints(6))

End Function

End Class

4.3 Operation of Hoists

As opposed to the worker movement model whose attributes are all local and can be only read by

each entity, hoist attributes are global, and all the information about hoists can be read at any

point in the system. All these attribute and variables are shown in table 4.5.

Table 4.5 Hoist attributes and variables

Attributes Type Description

Hoist ID Integer ID is the unique and only local attribute of hoists

Number of

Hoists

Integer The number of hoists available on the construction site

Capacity Integer The maximum number of passengers for a single hoist car

Number of

available hoists

Integer The number of hoists that are idling at the ground floor. This

number add one if one hoist returns to the ground floor, and

minus one if one hoist is launched

Hoist current

floor

Integer This is the current location for each hoist car

Direction Status Integer This attribute can be -1, 0, 1 or 2, where -1 means going towards

ground floor, and 0 means idling, and 1 means going up, and 2

means the hoist stops at that floor.

People on hoists Integer How many people are currently in hoist cars? The number

changes with each stop

Hoists return and idle at the ground floor when they are not needed. When a request call is sent

to the system, it launches one available hoist. The launched hoist will go up and check each floor

37

(this does not take any time in the simulation environment) if there are workers waiting, and pick

up any waiting workers. When the hoist returns to the ground floor, it again idles. If the hoist is

at capacity, it won’t stop even though there are workers waiting for it. If more than one hoist

stops at a floor, workers randomly choose which one to take. The flowchart of hoist operation is

shown in Figure 4.7.

Figure 4.7 Hoist operation

4.3.1 Creation of Hoists

Hoist entities are created with the attributes in Table 4.5. The number of hoist entities is equal to

the number of available hoists on site. The initial status of hoists is “available” and turn

“occupied” after it is requested. Then the status becomes “available” again after the hoists return

to the ground floor and release all of the workers on-board.

As shown in Figure 4.7 and Table 4.3, “valves” are used in the model to control the operation of

hoists. Hoist entities are blocked by a “Requested Valve” (Figure 4.7) when they are idling at the

ground floor. These valve nodes in the model connect hoist operation worker movement, making

two parts work cooperatively.

Table 4.6 Valve elements

Element: Requested Type: Valve Element: Check Workers Type: Activator

38

Initial State: Close; Auto-close: 1

Description: This valve is activated by Activator

“ReqeuStOne” in 4.2.2, The function of this element

is to allow one hoist to going into the system when

there is a request from worker.

Action: Open; Valve: Check on & Check off

Description: This activator works with valves in

4.2. The function of this element is to update

information that if there are workers or workers

are getting off waiting at current floor.

4.3.2 Hoist Operation

In the proposed model, hoist operations are characterized as cyclical activities. Decisions made

by on-board operators will reflect direction status (Table 4.5) in the simulation. In other words,

the way direction status changes when the way hoists are operated.

Answer a call from the ground floor (from 0 to 1): 1. Hoists are idling at ground floor and

workers request from ground floor. This situation is common during up-peak hours when

workers access hoists from ground. 2. Hoists are idling at ground floor, and other hoists

are occupied.

Change direction (from 1 to -1, or from -1 to 1): 1. Hoist can change direction when it is

empty or reaches highest request floor. 2. Hoists can pick up workers near the destination

floor.

Make a stop (From 1 to 2, or from -1 to 2): 1. Hoist stops when on-board workers reach

their designated floor. 2. Hoists can answer landing calls when the bypass capacity is now

reached.

4.4 Model Analysis

Data needed to be collected in order to determine the variables in the model and validate the

output of the proposed model.

4.4.1 Data Collection

Loading/unloading and door opening/closing time needs a case to case study, because hoist doors

are manually operated by the on board operators. Characteristics of the operator and the hoists

can significantly influence this time. In this case study, a data collection was conducted to

39

determine the probabilistic distribution of hoist operation time. Table 4.7 shows a sample of data

collected from the site, from which we can analyze the distribution of time every stop and the

relationship between travel time and floors passed. Figure 4.8 and Figure 4.9 shows the statistical

results of the data collection.

Table 4.7 Sample data collected from the site

Cycle

Trip

start

Trip

ends

Stopping

Floor

Door

opens

Door

closes

Workers

on/off

Time per

stop

(seconds)

Travel

time

(seconds)

Floors

passed

1 6:52:42 6:56:49

G

6:52:42 2

4 6:53:02 6:53:16 1 14 20 3

5 6:53:23 6:53:40 6 17 7 1

14 6:54:18 6:54:28 2 10 38 9

16 6:54:48 6:54:57 2 9 20 2

17 6:55:07 6:55:22 2 15 10 1

19 6:55:38 6:55:43 1 5 16 2

G 6:56:49

66 18

2 6:57:32 7:03:39

G

7:03:39 7

5 6:57:51 6:58:03 1 12 19 4

13 6:58:35 6:58:48 1 13 32 8

16 6:59:05 6:59:26 1 21 17 3

17 6:59:38 6:59:54 1 16 12 1

26 7:00:27 7:00:48 5 21 33 9

27 7:00:55 7:01:20 1 25 7 1

18 7:02:01 7:02:21 1 20 41 9

5 7:03:01 7:03:15 1 14 40 13

G 7:03:39

24 4

In the collection, time of each activity was monitored: the floors hoist stops at, when the door

opens/closes, how many workers get on/off. Based on these information, the time taken for each

stoop and the time for traveling between two stops can be calculated. To be more specific, the

time per stop is the time between door opening and closing. The travel time is the time between

door openings.

40

Figure 4.8 lifting time (Tm), and Figure 4.9 loading time (Tl)

Figure 4.8 and Figure 4.9 indicates a linear relationship between time spent on traveling between

two stops and the number of floors between two stops. From the distribution of time for each

stop, the probabilistic distribution can be fit. In the simulation model, the probabilistic

distribution of time delay for each stop is a triangular distribution (0.24,1.15,0.37).

4.4.2 Model Validation

A simulation model can be regarded as valid and credible when its results can reproduce the

actual situation (Law and Kelton 2007). To validate the proposed model, an experiment was

conducted to compare the difference between simulation results and observations. Hoist

information and worker movement was recorded to work as an input of the proposed model. In

table 4.8, the difference in cycle time is compared. As we can see, the simulation results are very

close to the observation results, which proves the validation of the proposed model.

Table 4.8 Comparison between simulation results and observations

Observation

Results (min:sec)

Simulation

Results (min:sec)

Difference

(seconds)

Difference

Percentage

3:12 3:18 6 3%

4:26 4:26 0 0

5:02 5:14 12 4%

5:48 5:12 36 10%

7:24 7:32 8 2%

5:48 5:55 7 2%

4:51 4:53 2 1%

41

4:47 4:49 2 1%

6:07 6:13 6 2%

5:36 5:47 11 3%

4.5 Case Study

A case study was conducted to validate the proposed model and demonstrate the impact of

different management strategies on hoist performance. The site is a 31-floor high-rise residential

project, located in downtown Toronto, Ontario, Canada.

4.5.1 Model Input

The site and hoist information is given in Table 4.9 as the input of the model.

Table 4.9 Construction worker layout and hoist information of the case study

Group1 Group2 Group3

Working Floors 2-10 11-20 21-31

Number of Workers 40 35 25

Practical Hoist Capacity 15 people/Hoist car

Hoist Travel Speed 90m/min

Hoist Type Double

The following assumptions have been made to simplify the model:

1. Workers’ destination floors depend on floor plan. Each worker randomly choose a floor

within his working floors.

2. Probabilistic distributions of time delay related to stops is using the results from section

4.3.1.

4.5.2 Model Output

Figure 4.10 shows an example result that is retrieved from the simulation model. Waiting time

and journey time for each individual worker is pictured.

42

Figure 4.10 Delays for up-peak

To measure the impact of different operation strategies on workers’ delay, different scenarios

ware simulated. The result of each scenario is shown below.

Table 4.10 Simulation results for different scenarios

Scenario

Delay (Minutes)

Average Waiting

Time

Max Waiting

Time

Average Journey

Time

Max Journey

Time

Up-

peak

Simulation Numerical Simulation Numerical Simulation Simulation Numerical

Scenario 1 12.2 11.8 29.0 29.0 16.5 35.0 34.5

Scenario 2 8.8 8.3 23.5 20.3 12.7 29.4 24.9

Scenario 3 10.1 9.6 23.3 21.9 13.8 28.2 26.9

Scenario 4 0.7 N/A 7.8 N/A 2.1 8.1 N/A

Scenario 5 10.4 N/A 24.8 N/A 13.6 29.5 N/A

Scenario 6 10.5 10.2 26.2 25.5 14.0 30.6 31.6

Down-

Peak

Scenario 7 9.8 N/A 18.2 N/A 11.3 20.2 N/A

Scenario 8 7.7 N/A 17.1 N/A 9.4 15.5 N/A

Scenario 9 3.6 N/A 7.5 N/A 5.0 8.7 N/A

Table 4.10 Simulation results for different scenarios

Scenario 1: This scenario is common in construction sites. The workers on site start to

arrive at the same time with random sequence. The hoists serve workers that arrive earlier.

After the hoists are launched, the direction will be reversed after lifting all the workers

and return the ground floor.

Scenario 2: In this scenario, the workers arrive at the same time, but priority is given to

workers who are going to lower floors. The hoists return to the ground floor to pick up

43

other workers after the hoists become empty. This strategy can reduce 28% of waiting

time for each worker.

Scenario 3: In this scenario, the workers arrive at the same time, but priority is given to

workers who are going to upper floors. The hoists return to the ground floor to pick up

other workers after hoists become empty. 17% of average waiting time can be reduced.

Scenario 4: In this scenario, workers are grouped by the floor they are working. Each

group arrives with a 15-minute delay. Workers working on 1-10 floors are the first group

to arrive, then 11-20 floors, finally 21-31 floors.

Scenario 5: In this scenario, working floors are divided into two zones, and each zone is

assigned one hoist. Hence, one hoist will only lift workers whose designated floors are

above 15th floor, while the other hoist will lift the rest of workers to floors below 15th

floor.

Scenario 6: In this scenario, a new technology, jump-lift, is tested. Jump-lift is an

alternative to exterior hoists, which operates in the building’s permanent elevator well.

The biggest difference between hoists and jump-lift is that the operation speed of jump-

lift can be up to 240 metre/minute (KONE 2014). To better compare the difference

between strategies, the capacity of jump-lift is set the same as hoists, which is 15 people

per car. Other assumptions of worker movement will be the same as scenario 1. If we

assume that time delay of making a stop is the same with hoists, it is shown a potential of

reducing 14% of workers’ average waiting time. Because time of making a stop (door

opening and closing, workers getting on and off) is assumed the same as hoists, the

reduction on waiting time is less than expectation.

Scenario 7: This scenario is mostly used on construction sites during down-peak hours.

After hoists leave the ground floor, they will lift to the top floor without stops, then hoists

pick up worker that are waiting when hoists are traveling downwards. Assumptions of

hoist operation and floor plan will be the same as scenario 1. Workers reach the hoists at

the same time after work.

Scenario 8: In this scenario, hoists pick up workers that are waiting while traveling

upwards and reverse the direction when reaching the capacity or reaching the highest

floor. The rest assumptions are the same as scenario 7.

44

Scenario 9: Similar to Scenario 4, workers end their shift in a staggered fashion. The

group that starts the earliest will end their work earliest in the evening. The rest

assumption will be the same as scenario 7.

Scenario 1 and scenario 7 represent normal lifting strategies on construction sites. Combining

these two simulation results, we can discover that, for a medium construction site, workers spend

approximately 22 minutes every day waiting for the hoists during peak hours, and about 28-

minute journey time every day during peak hours. This occupies a large portion of working time

without contribution to the projects. The delay will increase significantly when the building is

designed higher and when there are more workers working in the building.

The results from numerical simulation can verify the output of DES models. Compared with

DES model, it shows that numerical model has more optimistic results, because it does not

consider random activities. DES can take random activities into consideration, which may lead to

more realistic results.

4.5.3 Summary

Management strategies can have a significate effect on worker delays. In morning peak hours,

for example, by giving priority to workers that are going to lower floors, average waiting time

can reduce by 28% every day. Also by dividing the building into zones that can be reached by

two hoists, average waiting time can be reduced by 15%. The zoning management strategies are

usually applied when high-rise buildings are equipped with multiple hoists.

A new technology, Jump-lift, is also tested and compared to traditional exterior hoists. The

biggest advantage is reliability and speed. It reduces the possibility of shutting-down by extreme

weather. This new technology also shows a potential in delay reduction. However, the

disadvantages of this technology is that the elevator will shut down when moving up this floors

for 2 days. The huge cost of applying jump-lift will also be a challenge. (KONE 2014)

In the down peak hours, it has been shown that current hoist operations are not efficient. It could

be better if hoists pick up workers that are waiting while traveling upwards and reverse the

direction when reaching the capacity or reaching the highest floor. In addition, staggered use of

hoists also presents a potential in delay reduction.

45

The most efficient strategy is to stagger workers’ shift by the areas they are working in, by which

we can guarantee the fairness among workers to have the same length of shift hours but

significantly reduce non-productive time associated with hoists use during peak hours. In the

case study, for a 15-minute stagger use of hoists, 17.7 minutes of waiting time can be saved for

each worker each working day, if scenario 4 and scenario 9 are combined for both up and down

peak hours . Assuming the average wage of workers is 30 dollars per hour (labour 2011) and 20

working days per month, 17,700 dollars could be saved each month for the situation in the case

study. Considering larger construction projects, a significant amount of money can be reduced

from budget by applying more efficient hoist management strategies.

To determine the stagger time, project manager should have a good estimation of how long is

needed to lift a certain number of workers to a certain area of floors. Table 4.11 shows the

estimated required time for lifting a certain number of workers based on their destination floors.

Lifting time is the time between hoist serving first worker and lifting the last worker to his

destination floor (excluding empty hoist coming back to ground floor in the last cycle). Data in

Table 4.11 is the average lifting time of 100 simulation runs. It is also assumed that all data

inputs and model parameters are the same as it in the case study (scenario 1).

Table 4.12 Assumptions for estimation

Practical Hoist Capacity 15 people/Hoist car

Hoist Travel Speed 90m/min

Hoist Type Double

Floor Height 3m

Worker Arrival No stagger

Lifting Priority None

Table 4.12 Estimated required time for lifting

Required Time (Minutes)

Floors to go 2 - 10 11 - 20 21 - 30 31 - 40 41 - 50 51 - 60 61 - 70 71 - 80 81 - 90

Number 10 4.1 4.5 4.8 5.1 5.4 5.8 6.1 6.5 6.8

46

of

Workers

20 5.1 5.6 6.0 6.2 6.6 7.0 7.3 7.5 7.8

30 5.7 6.1 6.4 6.6 7.0 7.4 7.6 7.9 8.3

40 10.2 11.2 12.1 13.0 14.0 15.1 15.9 16.8 17.9

50 11.7 13.2 14.1 15.0 15.9 16.8 17.9 18.9 19.8

60 11.9 13.3 14.3 15.2 16.3 17.1 18.2 19.1 20.0

70 16.3 18.1 19.5 20.8 22.1 23.5 24.8 26.2 27.6

80 17.9 20.3 21.6 23.3 25.0 26.5 27.9 29.3 31.2

90 18.2 20.6 22.0 23.6 25.3 26.8 28.3 29.8 31.5

47

Chapter 5 Conclusion and Further Research

This chapter will summarize the results and contribution of the research. This section will also

provide the limitation of the study. Finally, recommendations on future study based on current

research will be presented.

5.1 Conclusions

The increase height of buildings introduces challenges in efficient use of vertical transportation

during construction phase. As the height of buildings grows, the efficiency of vertical

transportation drops exponentially, thus affecting the safety, cost and overall schedule of

projects. As the most important means of vertical resource delivery, temporary construction

hoists have a significant impact on overall performance of tall building projects.

Because of the scarcity of studies on construction hoists, research on elevator is reviewed as

supplement. A general DES model was developed in Simphony.NET to analyze the influence of

different lifting management strategies.

The primary objective of the study is to develop numerical and simulation models that can be

used to simulate worker movement under different conditions, examining the influence of

different management strategies have on worker waiting time and estimating the time needed to

lift a certain number of workers to a certain floors. The goals of the study have been met by

establishing numerical model and developing a DES model. A case study has shown that

management strategies can make a significate change on worker delays. It was shown that

changing the start time schedule of different trades can reduce workers’ average waiting time by

11.5 minutes (or 94%) with a 15-minute interval between groups. Also, it has been shown that

dividing building into two zones (15 floors each) that can be served by different hoists can save

the time wasted waiting for hoists. By serving workers in the order of their designated floor, it

also could reduce average waiting time by 2.1 to 3.4 minutes (from 12.2 minutes to 10.1 minutes

and 8.8 minutes).

48

5.2 Limitations and Future Research

Provided the scope and assumptions of this study, a few limitations arise. The limitations of this

study are as follows:

The study is limited to the lift of workers during peak hours, during which time hoists are

only used to deliver labour. However, material is also lifted by hoists on construction site

and cannot be reflected by the proposed model without modification.

Inter-floor traffic was ignored in the study. However, materials and tools are stored at

certain floors, and workers pick up those tools first in the morning then heading to their

designated floors. In this way, inter-floor traffic might significantly impact the results.

Hoist operation data has to be collected from construction site to determine cycle time

that is used to calculate delay.

The research has shown great potential in solving worker productivity loss associated with

vertical transportation. Future research will be focusing on hoist performance study during the

whole process of construction. The model should be more integrated with project schedule, with

the help of building information modeling technique. The future model should be able to

simulate hoist operation, worker and material movement for a whole day in different phases of

construction.

References

AbouRizk, S.M., Halpin, D.W., and Lutz, J. 1992. State of the art in Construction Simulation.

Proceedings of the Winter Simulation Conference, Washington, D.C., 1:1271-1277.

Ahn, B. 2004. A Vertical Movement Plan for Labors in High-Rise Building Construction Using

Discrete-Event Simulation. Korean Journal of Construction Engineering and

Management, KICEM, 5(2):47-54.

49

Alvanchi, A., Azimi, R., Lee, S., AbouRizk, S.M., Zubick, P. 2012. Off-site construction

planning using discrete event simulation. Journal of Architecture Engineering, ASCE,

18:114-122.

Barney, G.C. and Santos, S.M. 1985. Elevator Traffic Analysis Design and Control. London, UK,

Peter Peregrinus Ltd.

Benmakhlouf, S.M., Khator, S. 1993. Smart Lifts: Control Design and Performance Evaluation.

Computers and Industrial Engineering, Pergamon Press Ltd, 25: 175-178.

Brown, W.M., and Newbold, K. B. 2012. Cities and Growth: Moving to Toronto –Income Gains

Associated with Large Metropolitan Labour Markets. Statistics Canada-Economic

Analysis Division.

CBC. 2014. 130 high-rise building projects in Toronto lead North America. Retrieved from:

http://www.cbc.ca/news/business/130-highrise-building-projects-in-toronto-lead-north-

america-1.2504776. (Feb 17, 2015)

Chang-Yeon, C., Soon-Wook, K., Junbok, L., Suk-Jun,Y., Sang, Y.C. and Yea-Sang, K. 2009.

Basic Study of Smart Robotic Construction Lift for Increasing Resource Lifting

Efficiency in High-Rise Building Construction. International Symposium on Automation

and Robotics in Construction, ISARC, Austin, Texas, U.S, 1:266-277.

Cho, C.Y. and Kim, J.Y. 2010. Simulation Method of Construction Hoist Operating Plan for

High Rise Buildings Considering Lifting Heights and Loads. 27th International

Symposium on Automation and Robotics in Construction, ISARC, Bratislava, Slovakia,

1:22-28.

Cho, C.Y., Kwon, S., Shin, T,. Chin, S., Kim, Y. 2011. A Development of Next Generation

Intelligent Construction Liftcar Toolkit for Vertical Material Movement Management.

Automation in Construction, ASCE, 20:14-27.

Choy, E. and Ruwanpura, J. Y. 2006. Predicting Construction Productivity Using Situation-

based Simulation Models, Canadian Journal of Civil Engineering, NRC Canada, 33:

1585–1600.

Christian, J., and Hachey, D. 1995. Effects of Delay Times on Production Rates in Construction.

Journal of Construction Engineering and Management, ASCE, 121(1): 20–26.

CIS - Canadian Industry Statistics. 2014. Retrieved from:

https://www.ic.gc.ca/app/scr/sbms/sbb/cis/search.html?lang=eng (Feb 15, 2015)

50

CTBUH - Council on Tall Buildings and Urban Habitat.2014. CTBUH Height Criteria.

Retrieved from:

http://www.ctbuh.org/TallBuildings/HeightStatistics/Criteria/tabid/446/language/en-

US/Default.aspx. (Feb 16, 2015).

Dantzig, G., Fulkerson, R., Johnson, S. 1954. Solution of a Large-scale Traveling-salesman

Problem, Journal of the Operations Research Society of America, Palgrave Macmillan,

2(4):393–410.

Dozzi, S., and AbouRizk, S. M. 1993. Productivity in Construction. National Research Council

Canada: Ottawa.

Eastman, C.M. and Sacks, R. 2008. Relative Productivity in the AEC Industries in the United

States for On-Site and Off-Site Activities. Journal of Construction Engineering and

Management, ASCE, 134:517-526.

ESDC - Employment and Social Development Canada. 2014. Retrieved from:

http://www.esdc.gc.ca/eng/jobs/lmi/publications/bulletins/on/apr2014.shtml (Feb 15

2015).

Farouk, A. 2011. High Rise Buildings and How They Affect Countries Progression. Ain Shams

University, Egypt.

Hajjar, D., and AbouRizk, S. 2000. Application Framework for Development of Simulation

Tools. Journal of Computing in Civil Engineering, ASCE , 14(3): 160–167.

Hakonen, H. 2003. Simulation of Building Traffic and Evacuation by Elevators, Licentiate thesis,

System Analysis Laboratory, Helsinki University of Technology, Otaniem, Finland.

Halpin, D. and Riggs, L. 1992. Planning and Analysis of Construction Operations, Wiley, New

York.

Halpin, D. W. 1977. CYCLONE—method for modeling job site processes. Journal of

Construction Division, ASCE, 103(3): 489–499.

Hewage, K.N. and Ruwanpura, J.Y. 2006. Carpentry Workers Issues and Efficiencies Related to

Construction Productivity in Commercial Construction Projects in Alberta. Canadian

Journal of Civil Engineering, NRC Canada, 33(8): 1075-1089.

Hewage, K., Gannoruwa, A. and Ruwanpura J. 2011. Current status of factors leading to team

performance of on-site construction professionals in Alberta building construction

projects. Canadian Jornal of Civil Engineering, NRC Canada, 38:679-689.

51

Hwang, S. 2009. Planning Temporary Hoists for Building Construction. Construction Research

Congress 2009, ASCE, Seattle, Washington, USA, 1:1300-1307.

Industry Canada. 2013. Retrieved from: http://www.statcan.gc.ca/tables-tableaux/sum-

som/l01/cst01/manuf10-eng.htm. (Feb 15, 2015).

Ioannou, P.G, Martinez, J.C. 1996. Scalable Simulation Models for Construction Operations,

1996 Winter Simulation Conference (28th), Washington, DC, USA, 1:1329–1336.

KONE. 2014. KONE Jumplift, available at http://major-projects.kone.com/our-

solutions/complete-solutions/build/construction-solutions/kone-jumplift/ (May 10, 2015)

Labour. 2011. Ontario - Toronto Zone: Schedule of Wage Rates, available at

http://www.labour.gc.ca/eng/standards_equity/contracts/schedules/ontario/toronto_zone/s

chedule.shtml (Aug 5, 2015)

Law, A. and Kelton, D. 1982. Simulation modeling and analysis, McGraw-Hill, New York.

Law, A.W. and Kelton, W.D. 2007. Simulation Modeling & Analysis, 4th edition, McGraw-Hill,

New York, 1: 1-59.

Leinonen, R. 1999. Building traffic simulator. Master’s degree thesis, Helsinki University of

Technology, Otaniem, Finland.

Liberda, M., Ruwanpura, J.Y., and Jergeas, G. 2003. Construction Productivity Improvement: A

Study of Human, Managerial and External Factors. Proceedings of ASCE Construction

Research Congress, Hawaii, USA.

Lu, M. 2003. Simplified Discrete-event Simulation Approach for Construction Simulation.

Journal of Construction Engineering and Management, ASCE, 129:537-546.

Martinez, J.C. 2010. Methodology for Conducting Discrete-Event Simulation Studies in

Construction Engineering and Management, Journal of Construction Engineering and

Management, ASCE, 136:3-16.

Metro Eleevator. 2015. Construction Hoists. Retrieved from :

http://metroelevator.com/construction-hoists/ (Feb 14, 2015)

Moonseo, P., Sungbong, H. and Hyun-Soo, L. 2013. Lifting Demand-Based Zoning for

Minimizing Worker Vertical Transportation Time in High-Rise Building Construction.

Automation in Construction, ASCE, 32: 88–95.

Morissette, R., Picot, G. and Lu, Y. 2013. The Evolution of Canadian Wages over the Last Three

Decades. Analytical Studies Branch Research Paper Series, Social Analysis Division,

Ottawa, Ontario, Canada.

52

Morrow. 2015. Construction hoists. Retrieved from: http://www.morrow.com/equipment/hoists

(Feb 15, 2015)

Munoz, D., Llanos, C., Mauricio, A., Els, R. 2008. Distributed approach to group control of

elevator systems using fuzzy logic and FPGA implementation of dispatching algorithms.

Engineering Applications of Artificial Intelligence, Elsevier, 21: 1309– 1320.

Newell, G.F. 1998. Strategies for serving peak elevator traffic. Transportation Research,

Eksvieer Science Ltd, 32(8): 583-588.

OMAFRA - Ontario Ministry of Agriculture, Food and Rural Affairs. 2014. Retrieved from:

http://www.omafra.gov.on.ca/english/stats/economy/gdp_all.htm (Feb 15, 2015)

Pidd, M. 1989. Computer simulation in management science, 2nd Edition, Wiley, New York

Robinson, S. 2004. Simulation – The practice of model development and use, John Wiley &

Sons Ltd, The Atrium, England.

Sawhney, A., AbouRizk, S.M., Halpin, D.W. 1998. Construction project simulation using

CYCLONE. Canadian Journal of Civil Engineering, NRC Canada, 25(1): 16-25.

Shannon, R. E. 1999. Introduction to the art and science of simulation, Winter Simulation

Conference, IEEE, Piscataway, N.J.

Sharpe, A. 2006. Lessons for Canada from International Productivity Experience. Ottawa, ON,

Canada: Centre for the Study of Living Standards: page 5. Retrieved from:

http://site.ebrary.com.ezproxy.lib.ucalgary.ca/lib/calgarypubpolicy/docDetail.action?docI

D=10146026 (Feb 17, 2015).

Shi, J. 1999. Activity-based construction (ABC) modeling and simulation method. Journal of

Construction Engineering and Management, ASCE, 125(5): 354–360.

Shin, Y., Cho, H., Kang, K. 2010. Simulation model incorporating genetic algorithms for

optimal temporary hoist planning in high-rise building construction, Automation in

Construction, Elsevier, 20(5):550–558.

Siikonen, ML and Leppälä, J. 1991. Elevator traffic pattern recognition. Proceedings of the

fourth world congress of the international fuzzy systems association, Brussels, Belgium.

1: 195–198.

So, A.P.T., Yu, J.K.L. 2001. Intelligent supervisory control for lifts: dynamic zoning. Building

Services Engineering Research and Technology, 22(1): 14–33.

Statistics Canada. 2015. Retrieved from: http://www.statcan.gc.ca/tables-tableaux/sum-

som/l01/cst01/econ40-eng.htm (Feb 15 2015)

53

Strakosch, G.R. 1982. Vertical Transportation: Elevators and Escalators, 2nd Edition.

Tervonen, T., Hakonen, H. and Lahdelm, R. 2008. Elevator planning with stochastic multi-

criteria acceptability analysis. The international Journal of Management Science, Omega,

36: 352-362.

TOBuild. 2010. Retrieved from: http://www.tobuilt.ca/NeighbourhoodsWeb.html (Feb 15 2015)

Yang, S., Tai, J., Shao, C. 2009. Dynamic partition of elevator group control system with

destination floor guidance in up-peak traffic. Journal of Computers, SAGE, 4(1):45–52.

Zuppa, D. 2014. Construction. Retrieved from National Research Council Canada:

http://www.nrc-cnrc.gc.ca/eng/rd/construction/index.html (Feb 10, 2015)