study of bridge project management system in department of road, a review of policy and practice
DESCRIPTION
The Study assess the different aspects (from planning, implementation to operation and maintenance) of Bridge Project Management of Department of Roads, identify the problems in bridge project management faced by the Department of Roads and recommend in action plan for effective bridge management.TRANSCRIPT
CHAPTER 1
Introduction
1.1 Introduction
This report is the outcome of the field study, which is a part of the training course “Road Sector Project Management”
organized by the Nepal Adminstrative Staff College from Shrawan 14 2069 to Bhadra 20 2069. This is a collaborative
effort of 7 partipants of the training.
All the members of the group are from Department of Roads which is mainly involved in construction and maintenance
of infrastructure in road sector. That is why it was decided that a study focused on some vital issue in the department
might be useful for the department itself. Since Bridges are very costly and important structures in road transportation
system, the group has chosen the topic “Bridge Project Management System in Department of Roads a Review of
Policy and Practice”. The study encompasses the management aspect of the bridge from the early stage of planning and
survey/design to the construction as well as maintenance of bridges in DOR.
Study Title: Study of Bridge Project Management System in Department of Road, a
Review of Policy and Practice.
1.2 Objective and scope of the study
Assess the different aspects (from planning, implementation to operation and maintenance) of Bridge Project
Management of Department of Roads
Identify the problems in bridge project management faced by the Department of Roads.
Recommend in action plan for effective bridge management.
The study is based on the experience of concerned DoR engineers through interviews and discussion as far as
practicable. Secondary Information is collected from the Department of Roads at Babarmahal.
1.3 Importance of the study
A bridge is a vital structure which allows uninterrupted
traffic flow in all weather. Collapse of the bridge may
results in traffic obstruction for several days. Therefore
bridges are important structures that contribute with
time value in National economy. On the other had it is
relatively very costly. Design and construction of
bridges require highly technical input as well as sound
management. It is particularly pertinent in our country
where very much unpredictable climate, geology and
nature of the river pose real challenge to the engineers.
According to Nepal Road Statistics, There are 1700
motorable bridges across the country. Out of the 1700
bridges, East West Highway alone consist of the 533
nos of the bridges, other Highway has 427 bridges and
Feeder road contain 578 bridges. The number of
bridges as mentioned are continuously increasing due
to the expansion of the road network within the
country. Hence the effective management of exisiting
By Abhiman Mulmi
31%
51%
5%
7% 6%
Composition of Existing SRN Roads
National HighwayFeeder road Ma-jorFeeder road MinorMid Hill HighwayPostal road
Figure 1.1 Composition of Existing Strategic Road Network
1
bridge as well as those under planning and construction is quite evident. More than 310 bridge are under construction.
Department of Road have also initiated Design and Build Approach to construct the 19 Nos of bridge.
Most of the exiting bridges have been built in conjunction with the development of the road network and, as a result,
many are 35-40 years old and increasingly in need of maintenance and repair. Over 80 percent are reinforced concrete,
with the remainder a mix of steel trusses (including Bailey Bridges), steel plate girder, pre-stressed concrete and stone
or concrete arches in approximate equal numbers of each. There are a limited number (8) of timber bridges.
The longest structures are on the East-West Highway in the Eastern Region: the Koshi Barrage (1.15km with 56 spans)
and the Mahuli Bridge (1.13km with 226 spans). Other significant structures are the Karnali Cable-Stayed Bridge
(500m, with a 325m main span) and three suspension bridges, each of 125m span, across the Narayani at Mugling, the
Marshyandi (Gorka) and the Bheri (Surkhet).
35%
28%
37%
Location of SRN Bridges by Road Type
East West HighwayOther HighwayFeeder roads
Figure 1.2 Location of SRN Bridges by Road Type
One of the major efforts towards efficient management of the bridge was the establishment of the bridge unit under the
Planning and Design Branch in 1994 as the central agency is responsible for coordinating with all Divisions and
Projects in Bridge Management Process. The number and types of problems are increasing each year, hence it is time to
review the present bridge management practice and incorporate necessary changes.
1.4 Methodology of Study
Following methodologies were applied to prepare the field study report.
Visit the DoR, Bridge Project and nearest Division Offices.
Collection of Secondary information and relevant documents.
Discussion with the Engineers.
Observation by Participants.
Analysis of primary and secondary information.
Findings of existing problems and solutions for efficient management in the bridge sector.
Recommendation in action plan
By Abhiman Mulmi 2
Figure 1.3 Structure of Methodology
1.4.1 Theoretical Frame work for Assessment
By Abhiman Mulmi
Field Visit
Conclusions and Recommendations
Data Analysis and Interpretation
Compilation of Data
Secondary DataPrimary Data
Data Collection
Questionnaires DesignStructured Interview
Research Design
Literature Review
Research ScopeResearch ObjectiveProblem Identification
Research Area Identification
3
Figure 1.4 Theoretical Framework for study
Phase of Bridge Project Management
The study is based on the Theoretical framework represented by the figure. The study will review the bridge policy in
each phase of bridge project. Then study and assess the current practices which will help to identify the problems and
constraints of Bridge Project Management. Based on the assessment Recommendation will be drawn in action plan with
role and responsibility for the ensuring the effective bridge project management system to be developed in Department
of Roads.
1.5 Limitation of the study
The following limitations might be observed during the study period:
Simple statistical tools will be used to analyze the data.
Study to be completed within limited time period.
Possible difficulty in the collection of the primary data.
1.6 Organization of the Report
The field study report has been organized in the following chapters
CHAPTER 1: General Introduction
CHAPTER 2: Organizational Background
CHAPTER 3: Bridge Policy, Management Practices and Problems
CHAPTER 4: Data analysis and SWOT Analysis
CHAPTER 5: Conclusions and Recommendations.
Appendices
CHAPTER 2
Organization Structure
By Abhiman Mulmi
Selection and Allocation
Phase
Im plem ention Phase
Hand Over and Docum entation
Phase
Operation and M aintenance
Phase Policy Review
Current Practice
Problem and Constraints
Action Plan for improvement
4
2.1 Organization Background
Department of Road (DOR) is a government agency, established in 1970 splitting from Public Works Department
(PWD), whose main purpose is to translate government policies for the roads sub-sector in terms of provision of service
to the general public of Nepal for the fulfillment of its mission states as “ To contribute Towards the Betterment of
Living Conditions of the People through Effective, Efficient, Safe and Reliable Strategic Road Connectivity”.
During Rana regime, there was a road office named "Bato Kaj Goshwara" and"Chhembhadel Adda" for construction &
maintenance of Civil Engineering works. There were branch offices such as "Banaune Adda" for other parts of the
country. Then "Naya Bato Kaj Goshwara" and "Purano Bato Goshwara" were established for new construction and
maintenance works respectively. An army unit called "Samarjung" used to carry out the routine maintenance under the
"Purano Bato Kaj Goshwara". Later both "Naya Bato Kaj Goshwara" and "Purano Bato Kaj Goshwara" were merged
into a new office as Public Works Department (PWD), which was located in Singh Durbar after the advent of
democracy in 1950.
Under PWD, construction of Tribhuvan Rajpath, Kanti Rajpath and Hetauda-Narayangadh road has been carried out.
"Bagmati valley Road Project" was set up to carry out the detail survey and construction of Kanti Rajpath. In 1954,
Royal Nepal Army completed its detail survey. In 1960, Rajdal Army Battalion completed the construction of 70 Km of
91 Km long Kanti Rajpath.
The Road Transport Organization (RTO) was also in existence as a Project Office separately representing the
involvement of India and US but could not work satisfactorily and it had been winded up in 1962 transferring all its
activities to DOR. During the year 1970 to 1975, the Road Development Strategy as adopted for the country continued
with Development of National Highways and Feeder Roads. Strategic Road Network (SRN) was developed in year
1975-1981 and PMC was established in 1987. For the continuation in the development of National Highways and
Feeder Roads along with its maintenance, Highway Management and Information System (HMIS), Maintenance and
Rehabilitation Co-Ordination Unit (MRCU) and Strengthened Maintenance Division (SMD) were established during
1988-1991. Transport Policy was first implemented in the year 1999-2001. Within the same year preparation of 20
years Master Plan of DOR was also initiated.
2.2 Vision and Mission
Vision
"Managing Roads for National Integration and Socio-Economic Development" is the vision for development of roads in
Nepal. The overall goal is to contribute in achieving sustainable socio-economic development by providing safe
affordable public road infrastructure services through building of a cost-effective, efficient and reliable road network
system. At the end of its plan period, the 20 year Master Plan for Strategic Road Network envisages the following
outcomes from the implementation of the proposed road program:
Motorable access to all the 75 District Headquarters in the country with Bituminous sealed road to almost all
District HQ;
Doubling of the length of the present Strategic Road Network with a target road density of 15 km per 10,000
populations.
Ensuring more than 95 percent of SRN in a good/fair annual condition;
Substantially reducing the walking distance of 13 days to 3 days in extreme cases to reach the motor-head in
High Himalayas & Mountains; and reducing the walking distance of 4 hours to reach motor-head in Terai and
Hills;
Establishment and functioning of Autonomous Road Agency to manage central road network with increased
level of user's involvement;
By Abhiman Mulmi 5
Establishment and functioning of monitoring system for an effective and efficient service delivery through an
independent annual user's satisfaction survey; and
Substantial reduction in accidents rate.
Mission
The mission statement for the Department of Roads is
"To Contribute Towards the Betterment of Living Conditions of the People through Effective, Efficient, Safe and
Reliable Road Connectivity"
2.3 Human Resources of Department of Roads
Table 2.1 Human Resource of Department of Roads
Class Staff (Number) Remark
Technical Adminstrative Others Total
Gazetted
DG 1 1
Class I 21 21
Class II 94 2 96
Class III 214 37 251
Subtotal 330 39 369
Non Gazetted
Class I 687 103 790
Class II 316 158 474
Class III 243 243
Class IV 287 287
Subtotal 1533 261 1794
Driver 183 183
Typist 91 91
Low Level 581 581
Total 1862 300 856 3018
2.4 Organization of Department of Roads
The department of Roads is headed by a Director-General assisted by 4 deputy directors-general (DDG), one of whom
is responsible for maintenance. The regions (Eastern, Central, Western, Mid-Western and Far-Western) are looked after
by five Regional Directors (RD) who form the link between the Headquarters in Kathmandu and the Divisions (25 in
number at present). The divisions are directly in charge of maintenance operations in their respective jurisdictions. The
organizational chart of DOR is shown in Figure 2.1
2.5 Bridge Project
As a part of the new organizational restructuring for DoR under the institutional strengthening component of World
Bank Project Road Sector Development Project, the earlier Bridge Unit under the Planning and Design Branch was
restructured into Bridge Project headed by the Super tending Engineer. Earlier, Bridge Project was established in 1994
with assistance from ODA (UK). The organization chart of the Bridge Project is shown in the figure 2.2.
By Abhiman Mulmi 6
2.5.1 Objectives of Bridge Project
The objectives of the bridge project are
To develop and establish a system of regular maintenance of bridges in strategic road network.
To standardize the design, construction and maintenance practice.
To develop capability of DoR Personnel, local consultants and contractors in bridge works.
Sectoral objectices of the bridge project are
To establish, develop and update bridge database.
To develop and program a budget for bridge works.
To establish and develop a maintenance management system.
To develop national standards for bridge design and specification.
To develop norms and specifications for bridge design and maintenance.
To undertake bridge design, construction and maintenance pilot projects.
2.5.2 Function of Bridge Project
Bridge Project has carried out bridge design works, maintenance management works and capacity building in the field
of the bridge works.
2.5.2.1 Planning and Design works
The bridge project has carried out design works of more than 500 bridges and feasibility study of more than 200
bridges.
2.5.2.2 Bridge Construction work
Bridge Project initiated the Pilot based Design Build Construction of bridge in 2010.
2.5.2.3 Bride Maintenance Management work
Following works were carried out in the bridge maintenance management works by the bridge project.
Inventory of 1100 bridges in 1996
Condition Survey of those bridges in 1997
Computerized the inventory database of those bridge 1997/98
Bridge Maintenance Manual
Bridge Maintenance works as Demonstration Contracts (Pilot Project)
Recent Maintenance work by Bridge Project
Bridge Project recently launched an extensive project to renovate nine bridges across the country that is in a “most
dilapidated” condition. The project that began in May 2011 aims at repairing the bridges that include the Trishuli
Bridge (Mugling-Tanahun section, Prithvi highway), Marsyangdi Bridge (Khaireni-Gorkha section, Tanahun district),
Seti Bridge (Khaireni-Bhimad section, Prithvi highway), Jharahi Bridge (Mahendra highway, Nawalparasi district),
Kaligandaki Bridge (Siddartha highway, Ramdi), Bheri Bridge (Ratna Highway, Surkhet), Tamakoshi Bridge
(Lamosangu-Jiri section, Dolakha district), Sunkoshi Bridge (Lamosangu-Jiri section, Sindhupalchowk district) and
Tadi Bridge (Nuwakot district). A committee formed under the DoR chose the bridges kept under the renovation project
for repairing. “The nine bridges are extremely important and are all located in core functional sites from the
transportation point of view.
2.5.3.4 Other works
By Abhiman Mulmi 7
Pilot Bridge Construction
Bridge Building Training works
Design Manuals, Bridge Inventory
Assistance to the divisons in bridge related issues.
Special inspection of the blast damaged bridges and remedial measure.
2.6 Bridge Improvement and Maintenance Project
The Government of Nepal has defined a national Strategic Road Network (SRN) consisting of Highways and Feeder
Roads under the auspices of central government. The Department of Roads (DOR) under the Ministry of Physical
Planning and Works is given the mandate of planning, construction and maintenance of the SRN. The SRN currently
suffers from many gaps in continuity and assured access due to non-existent or inadequate bridge structures. Many
existing bridges are 35-40 years old and are in desperate need of rehabilitation and repair. To address this problem, the
DOR has formulated a Priority Investment Plan (PIP) for bridges that aims at achieving year-round accessibility along
the SRN. Under the PIP, the DOR has identified a backlog of bridges for maintenance and refurbishment as well as
about 350 new bridge development projects. To address these needs, a Bridge Improvement and Maintenance Program
Support (BIMPS) is being prepared and is proposed for World Bank financing using the Program for Results (PforR)
lending instrument. Under the financing of World Bank, BIMP Project is initiated in 2012. The Project Development
Objective is to improve uninterrupted movement of traffic along Nepal Strategic Roads Network through support to the
Government of Nepal program of bridge development and maintenance, and strengthened bridge management.
2.6.1 Project Description
The proposed project is a US$60 million Specific Investment Credit that uses a programmatic approach to support the
bridge maintenance and improvement program of the Strategic Road Network (SRN) over a four-year period. The
project is structured around two components:
Component A - Support to the bridge construction and maintenance program (US$56.1 million) - this component will
contribute to the finance of the overall bridge maintenance and construction program of the SRN based on a prioritized
maintenance and investment program. Given the poor quality of the existing stock of bridges backlog periodic
maintenance and rehabilitation/replacement works will be prioritized as well as scaling up the existing routine
maintenance activities. Where technically and economically feasible the project may also finance bridge strengthening,
widening and new bridge construction. Large bridge works (potentially bridge lengths exceed 100 metres, but will be
decided once the bridge inventory and condition surveys are completed) will be not be eligible for financing under the
project. The Government of Nepal (GON) has also asked for support in the procurement of Bailey bridges. These
bridges will be kept in stock to allow a rapid response to natural disasters. The GON proposal includes the procurement
1,000m length of bailey bridges.
Component B - Institutional strengthening (US$3.9 million) supports a technical assistance program designed to
strengthen the capacity of the DOR to manage and implement a prioritized bridge improvement and maintenance
program. The component will focus heavily on human resource development at the national and regional level. The
tools and skills required to undertake bridge inspections, plan and execute maintenance activities and to plan and design
bridge works (particularly for large bridges) will be developed. The existing bridge policy and maintenance inspection
manuals will be reviewed and revised to reflect current international best practice and to support the roll out of the
Bridge Management System (BMS).
By Abhiman Mulmi 8
Nepal Government
DEPARTMENT OF ROADS
By Abhiman Mulmi
Figure 2.1 Organization Chart of DORHMIS Unit
Human Resource Development &
Computer Documentation Center
Central Laboratory
Quality Test Unit
Road & Traffic Unit
Bridge Unit
Geo-Environmental Unit
Planning, Monitoring & Evaluation Unit
RMDP (World Bank)
Dhulikhel-Bardibas Project
Hile-Bhojpur Project (RAP)
Feeder Road Co-Ordination Unit
Dispute Resolution Unit
Multi-Lateral Co-Operation Unit
Bi-Lateral Co-Operation Unit
Administrative Section Under
Secretary(Adm.)-1
ADB Project Directorate
Financial Administrative Section
Under Secretary (ACC.)-1
Mechanical Branch
DDG-1(Mech.)
Foreign Cooperation Branch DDG-1
Planning and Design Branch DDG-1
Maintenance Branch
DDG-1
DIRECTOR
Sub-Regional Transport
Facilitation Project
Road Network
Development Project
Legal & Compensation
Unit
Internal Administration
Unit
Personnel Administration
Unit
Central Store Mechanical Office -9nos
Mechanical Training Center
Heavy Equipment Division Offices-6 nos
Equipment Procurement & Training Unit
Equipment Maintenance & Management Unit
Operational Unit
Central Level Auditing Unit
Khodpe-Bajhang Project
Regional Directorate
Offices-5 nos
Contract Document Unit
Gaighat-Diktel Project
Divisional Road Offices-25 nos
Development Unit/SMD
General Unit
Units under Branches
Legend
Offices under Units
Director of DoR
Branches under DoR
9
DEPARTMENT OF ROADS
Bridge Project
By Abhiman Mulmi
Project Manager (DDG)
Technical
Senior Divisional Engineer (3Nos)
Engineer (4Nos)
Sub Engineer (2Nos)
Draught Persons (3Nos)
Adminstration
Nayab Subba 1
Kharidar (1No)
Peon
AccountDivision Road
Office (25 Division)
Figure 2.2 Organization Chart of Bridge Project
10
CHAPTER 3
Bridge Policy, Management Practices and Problems
3.1 The DoR Bridge Policy
In order to institutionalize the bridge works, the department published its Bridge Policy in 2004.
The Policy Statement is “The Bridge Policy of DoR is to provide safe, reliable and cost effective bridges.”
It states the following strategies
Strategy 1 Strengthening the existing institutional capacity
Strategy 2 Establishing economic and financial norms
Strategy 3 Institutional bridge maintenance and emergency works.
Strategy 4 Incorporating environmental and social aspects in the management of bridges.
Strategy 5 Establishing Project management cycles
Strategy 6 Technical Support and standardizing bridge definitions with other organizations.
Strategy 1 Strengthening the existing institutional capacity
The implementation of any technical or economic activity will not be effective unless there is a committed institutional
arrangement. So, strengthening the existing institutional arrangement has been the first thrust of the strategy. It aims to
strengthen exisiting DoR institutional capacity through
Strengthening of the Bridge Unit
Continuous Human Resource development
Introduction and consolidation of codes of practices, standards and working manuals and guidelines for design,
construction and maintenance of bridges.
Establishing elements of good governance in management practices
Adopting affordable appropriate technology and working jointly with private sector for capacity improvement..
Strategy 2 Establishing economic and financial norms
Development and maintenance of bridges demand adequate investment. It requires a rational procedure in investment and
financial management. Therefore the second strategy emphasises to establish economic and financial norms through Total
Life Cycle Costs considering introducing value engineering and creating an appropriate environment for private sector
investment and management.
Strategy 3 Institutional bridge maintenance and emergency works.
Many bridges are suffering premature loss of strength resulting reduced functional life due to inadequate maintenance.
Hence the third strategy is to institutionalize bridge maintenance and emergency response through adoption of planned
maintenance Specific maintenance strategies for special bridges, prioritising maintenance over new construction, imporoving
capacity for dealing with emergencies and setting operable BMMS.
Strategy 4 Incorporating environmental and social aspects in the management of bridges.
As bridges bring changes to the environment and society within their vicinity, the fourth strategy aims to reduce any adverse
effects of bridges to their environment and nearby communities by means of implementing legal measures, encouraging
community participation in river cooridor protection and introducing effective water management.
Strategy 5 Establishing Project management cycles
The main problems of the most of the bridge projects are
By Abhiman Mulmi 11
Adhoc planning
Long construction periods due to insufficient annual funds.
An increasing number of contractural disputes
Unclear ownership
Insufficient annual maintenance budget and
Poor maintenance practice
In order to overcome these problems, the fifty strategy aims to establish a bridge project management cycle having a four
specific stages.
a) Selection and approval of projects
b) Project implementation phase
c) A formal hand over process and
d) Operation and maintenance
Strategy 6 Technical Support and standardizing bridge definitions with other organizations.
Until now a DoR is the prime public sector institution for development of bridges in the central level road network (SRN) as
well as local (district, village, urban) roads in Nepal. Recently other organization, particularly, DoLIDAR in liason with the
DDCs, VDCs and Municipalities, have increasingly involved in design and construction of motorable bridges in the non
SRN roads. However, future improvement in the economic conditions of the country may bridge some of local roads into the
SRN. As the functional life of bridges is more than roads, it woul be rational and economically sensible to build bridges as
per national standards in the first instance. The last strategy, therefore, aims to support other organizations through the
development of national standards, assistance to their human resource development programmes.
DoR is also committed to the development of appropriate and realistic modalities for each strategy, and to continue
monitoring their implementation for continous improvement as per the transport sector’s needs.
3.2 Bridge Policy in Project Management Cycle and Current Practices and problems
3.2.1 Selection and approval of the project
3.2.1.1 Policy review; very decentralized
The DoR Bridge Policy has clearly stipulated the process of selection and approval of bridge projects. According to the
policy, investment in a bridge project through DoR is recommended after several steps which mainly include prefeasibility
study, feasibility study, priority ranking after discussions among the stakeholders. The policy aims at very careful scrutiny
before investing in a bridge project. Only after discussion DoR get the formal approval of the rolling plan from concerned
authority. And Detailed engineering design of the bridge selected in rolling plan was conducted in order of the priority.
There is a formal design acceptance process, where greater role has been proposed for RD, DRO regarding field verification,
which is followed by the design check by the Bridge Unit and design acceptance by the concerned authority. Finally on the
basis of priority bridge project is selected in the annual programme.
3.2.1.2 Practice; centralized and politicized
The selection and approval process of bridge project in reality is highly centralized and politicized.
By Abhiman Mulmi 12
Figure 3.1 Project Selection Process in Practice
Each year National Planning Commission decides ultimately which bridge is to be constructed and includes in the RED
book. But the procedure and criteria for selection is not clear. Red book allocates budget for construction in an adhoc basis
without knowing whether he bridge is technically or economically feasible or not. There are large numbers of cases where
the budgets have been allocated on the basis of demand of politician. There are cases where Division staff could not find
where a particular crossing lies in their territory. It indicates that bridge planning is centralized, there is little relevant input
from the divisions of the local level.
3.2.1.3 Practice; Feasibility Study
The feasibility study is done through Bridge Unit. The engineer complains that it is very difficult to monitor the study from
the central bodies. The engineer complains that is is very difficult to monitor the study from the central office due to the lack
of manpower and other logistics facilities. The format of feasibility study reports were found inconsistent. The above
observation leaves an impression that the pre-feasibility and feasibility studies are done merely to fulfil some unnecessary
formalities. The results are neither used for planning and budgeting nor for detailed design and construction.
Figure 3.2 Project relation
3.2.1.4 Practice; Detailed Design of bridge
Construction of bridge is possible only after its design which consists of engineering survey, hydrological study, soil
investigation, study of environmental aspects and structural design of its various components. Thus the design process of a
bridge is closely associated with the natural condition surrounding the bridge site.
By Abhiman Mulmi
Nepali Congress
Maoist
UMLRastriya
Prajatantra Party
Terai Party
National Planning Commission
Department of Roads
People
FeasibilityDetailed Design
Construction
13
A few year back the Division offices themselves used to hire consultants for the design of bridges in their jurisdiction. It
saved time but arouse problem like improper design contracts, inconsistent and inappropriate designs, non uniformity of
design formats etc. To solve these problems the department ruled that the all the design works should be done only through
the bridge unit. The policy of design at centre helped to solve the above problems but again other types of problems began to
emerge.
Figure3.3 Typical Design Problems
The cause of such problems is again lack of supervision of the survey and design works. The engineers at the bridge unit
complain that they are not familiar with the bridge site and there is no provision for constant supervision throughout the
survey works. The division offices have very limited role in the design process hence much input cannot be expected from
them. The bridge unit is limited to check the technical content but they are unaware of the possible construction problems.
Figure 3.4 Adhoc Design Approval Process
By Abhiman Mulmi
Division Report Search for the design report
Design report and drawing forward by DRO to Bridge
Project
3 Engineers of Bridge Project
Check
Concerned Authority
approved it
Adhoc planning (Bridge Project inform DoR of
Procurement of Bridge) normally Baisakh, Jestha
Common design
problem
Soil starta not conform to
design
Wrong Hydrological
data
Inapprpriate design of river training and
approach road
Un economical
design
Trend of copying design
Insufficient free board
More than 100 bridges goes to procurement
Time Period 2 to 3 Months at the end of Year
Manpower in Bridge Project 3 Engineers to check
14
3.2.1.5 Practice; Lack of Standard Guidelines and format and expertise
The bridge unit is considered as a central expert unit. So whenever any problem arises at the site, DRO send it to the Bridge
Unit. But can it really solve the problems? Are the engineers in the Bridge Unit specially trained and have expertise. The
engineers in the DoR are randomly transferred to the bridge unit. No special training is provided to them. So, there is
virtually no difference between the engineers. The Bridge Standard 2067 is inadequate beside there is lack of standard
designs, guidelines to carry bridge design work. Majority of the bridges locally based on simple RCC technology or simple
truss. There was not effort made in the research and development of new bridge like cable stayed, pre stressed bridge etc.
3.2.1.6 Practice; why Bridge Unit is procuring and supervising so many bridges
As per Policy Bridge unit is more of an expert panel which is more focus on bridge design. It is good that it can procure and
supervise any bridge project in pilot phase. But Today Practice shown that it is more concerned in contract as well as
supervising a number of bridge based on Design and Build. It shows the centralized practice of bridge unit executing the
maintenance contract of 9 periodic maintenance of bridge under the decentralized network of Department of Roads. Such
Practice has to be made clear.
3.2.2 Implementation Phase
3.2.2.1 Policy review
Implementation phase start with the procurement management. Division Road Office and Project Office prepare the bid
document and carried out the procurement process and award the contract for the execution of the work. Construction
Supervision was carried out the Division Road Office in technical support of Bridge Unit and Design Consultants. Division
identifies any changes and reports to the regional Director and to the Department. Bridge Project conducts discussion with
the project stakeholder and assists to revise the initial design or resolves the site problems and concerned office forwards for
approval as per regulations.
Figure 3.5 Technical Support identified by Bridge Unit in Implementation Phase
3.2.2.2 Practice; Procurement Stage
The bridge unit have the standard bidding document for the Bridge work of medium contract published in the year 2067 BS.
All the Division Road Office and Project office prepare the bid document on the basis of the standard bid document and
there is now more or less uniformity in the bid document which was not in the past. The major problem burden to the
procurement of bridge is that Bridge Project needs to select only those projects which were designed by it. The Database of
Bridge Project regarding Design report is very poor, that it is very difficult to get the design report from the Bridge Project.
Bridge Project at the last hour of fiscal year informs the Division and Project about the list of bridge to procure, sometimes,
their design was not even happen. Bridge Project has to shortlist only that project whose design have been approved by
early. So, that Division and Project would more focus on Procurement management.
By Abhiman Mulmi
Laying out of the bridge axis.
Foundation preparation including the bottom plugging of wells, well capping, pile testing, installation of bearings or any foundation problems.
At the time of preparing shop drawing, the preparation of steel superstructures, fabrication, material testing, erection methodology preparation, the field erection period and during the handing over period.
Deflection monitoring for steel bridges and load test.
Any specific issues or events.
15
3.2.2.3 Practice; Construction Technology and Quality Assurance Mechanism
The construction supervision is primarily the responsibility of the Division Road Office. Division Road Office and Project
Office have the role of quality control of the construction work and have to supervise the work to ensure the construction
work carried out as per design and specification. There is lack of systematic quality control. It is usually done in an adhoc
basis as per the supervising engineers own understanding and does not always reflect the quality of the works. No standard
formats, checklist, guidelines and procedure are available and the engineers are not trained enough for quality control
measure. Currently about 310 bridges are under construction under the Department of Road. Each Division Road Office has
at least 10 bridges or more bridge to construct. Bridge construction need a knowledge and skill, and Engineer have to work
hard to construct the bridge. The bridge like Steel Truss Bridge needs a expertise. Most of bridge construction contractor are
incompetent, in this situation a regular supervision from Engineer is needed. The construction technology adopted by the
Contractor is also traditional and labour based, even the construction like steel truss bridge.
Figure 3.6 Constraints during construction
3.2.2.4 Practice; Feedback and Problem Solving Mechanism
Most of the problems are encountered at the site condition. Logically, the best practice would be to solve it there as far as
possible. Although most of the problems are related to the site conditions and could be effectively solved locally. There is a
general tendency to send it to the centre. Such tendency is due to lack of confidence and training. No guidelines are available
to solve common types of problems and there is a confusion whether the divisions are empowered to solve them on their
own, or should they get approval from the Bridge Project. Bridge Project is not always capable to solve the problem because
it has no decision making tools, no expert engineer and no logistics, making the files returned back with some ambiguous
solution or no solution causing delay.
Another common problem is the lack of systematic lateral communication within the department. Information on any
problem and its solution is not shared by the wide mass. It hinders the development of expertise. This problem exists not
only in the bridge sector but in all the systems.
By Abhiman Mulmi
Constraints
Incompetent contractor
Traditional Labour based
technology
One engineer might have to
look after 5 bridge at time
Lack of monitoring
Poor quality control
mechanism
16
3.2.3 Handover Process and Documentation Phase
3.2.3.1 Policy Review
Policy gives a importance on joint inspection of Bridge by the Bridge Unit, Division Road Office, Project Office along with
the Contractor and Design Consultant one month before issue of completion certificate. Followed by the rectification
measures it necessary by the contractor. After rectification, Division Road Office Project Office issues the completion
certificate. Bridge Unit then conduct the Principal Inspection by BU and Handover of SRN bridges to DRO. DRO then
disseminate the information on construction and maintenance problems and shortcoming to DoR, BU and HMIS.
3.2.3 2 Practice; Start up and Commissioning
Start up and commissioning of the at least Bridge other than the RCC bridge should be done, load test, start up and
commissioning provision should be compulsorily incorporated in the Contract of Bridge Construction.
3.2.3.3 Practice; Hand Over of the Non SRN bridges
Many Non SRN bridges are constructed and under construction under DoR. Bridges located in the non SRN road should be
handed over to the Local body after the construction.
3.2.3.4 Practice; Database of as built drawing
Division Road office should maintain the as built drawing of bridge and send a copy of as built drawing of the bridge to the
Bridge Project, which it should maintain.
3.2.4 Operation and Maintenance Phase
3.2.4.1 Policy Review
The four class of the maintenance activity is defined by the bridge policy they are routine maintenance, recurrent
maintenance and minor repairs, periodic maintenance and the emergency maintenance. All DROs prepare conduct annual
bridge inspection as per the routine maintenance inspection guidelines and also carry annual inspection of river corridors to
identify the requirement for strengthening of river training work and bank protection. Bridge Project conduct periodic
inspection survey five to seven year as per principal inspection guidelines. Bridge Project also conduct special inspection of
the bridge in case of any major accident or events. All DROs assess minor repair works on the basis of routine inspection
and prepare recurrent budgets. Concerend DRO or PD assess the periodic maintenance need on the basis of periodic
inspection and condition survey. Bridge Project, DRO, PO assess emergency damage immediately after it occurred. Bridge
Project coordinates with all relevant authorities. All DROs prepare Annual Road Maintenance Plan for the routine, recurrent
and emergency maintenance of the bridge. All DROs or PO carried out the routine, recurrent, emergency and periodic
maintenance of the bridge. All DROs maintain the physical progress reporting and update bridge register and disseminate
information to Bridge Project and Highway Management Information System.
Bridge Condition of Nepal
The Bridge Inventory Study also undertook a condition survey of a sample of 96 bridges – from within the total of 1056 –
which were identified as being in need of repair or rehabilitation. The selected bridges included 34 bridges on the East-West
Highway, 38 on other Highways and 24 on Feeder Roads. The damage and defects notes ranged from ‘complete collapse’,
‘scour & siltation’, ‘corrosion of bearings’, ‘ageing’ to ‘poor condition’: 15 cases of damage due to ‘rebels attack’ were
noted.
A total of 10 elements of each bridge were inspected and ranked, including: the approach roads, bridge deck surface,
parapets, expansion joints, superstructure, bearings, abutments, piers, protection works, and river training works. The
By Abhiman Mulmi 17
condition of each element was ranked on a scale of 0-4, with the extent of damage and degree of urgency also scored on a
scale of 0-4. Details of the recommended remedial works are included in the draft Study Reports: the results of the condition
survey are presented so as to enable DoR prioritisation of the remedial works.
A specific recommendation is made regarding the widening of the bridges on the Pathlaiya-Dhalkebar section of the East-
West Highway. There are approximately 60 bridges on this section most of which have a carriageway width of only 5.5m:
this is below the minimum for Asian Highway Standards and is insufficient for two commercial vehicles to pass in comfort.
Furthermore 10 of these bridges are in excess of 100m in length, which adds to difficulties for opposing vehicles to pass. A
detailed study of how best to resolve the issue is recommended.
Bridge Inventory Survey 2005
Figure 3.7 Bridge condition of Nepal
A latest estimate by DOR suggests that SRN bridge program’s capital expenditures will need to support major repairs of 514
SRN bridges. Of them 60 bridges require urgent attention. Minor repairs of a further 841 SRN bridges will also be required.
The per-bridge cost of major maintenance of these bridges is small relative to many infrastructure investments. The average
cost of 85% of SRN bridges requiring major maintenance is estimated to be less than USD 100,000. DOR’s bridge inventory
has also identified 296 gaps on SRN, which will require new bridges in order to facilitate all-weather access. 82% of these
new SRN bridges are estimated to costs less than USD 1 m per bridge. The most expensive new SRN bridges will be in the
region of USD 10 - 15m. Costs of engineering designs, feasibility studies, and quality management are estimated to be
approximately 5% of capital spending.
3.2.4.2 Bridge Maintenance Practice
There are standard bridge inspection guidelines for the carrying of bridge inspection and maintenance. Division Road Office
rarely carried out the bridge inspection annually as defined in the Bridge Policy of Department of Roads. Bridge Project
should make the Annual Bridge Inspection Mechanism mandatory for all the concerned office with necessary facility and
budget for the work. All the Division should rate as defined in the Bridge inspection and Maintenance guidelines. Condition
rating, Extent rating and urgency rating should be mandatorily incorporate in the Annual Road Maintenance Plan. Currently
Division adhocly put the bridge maintenance budget in the Annual Road Maintenance Plan.
Table 3.1 Bridge Maintenance condition rating Nepal
Condition rating Extent rating
4 Serious condition with severe damage. The element or
component is not functioning as designed.
4 Extensive, most or all of the element affected.
3 Poor condition The element or component shows
numerous defects of structural significance which may
soon prevent it from functioning as designed.
3 Major , highly significant, more than 20% of the
element affected
2 Below average. The element or component shows local
defects of structural significance but functions as
designed.
2 Significant, 5% to 20% of length or area of the
element affected
1 Fair condition. The element or component shows a few
nonstructural defects.
1 Minor, less than 5% of length or area of the element
affected
0 Good condition with no significant defects 0 No defect or insignificant length or area of the element
affected
N Not applicable, or element not accessible for inspection
Urgency rating
4 Immediate action required
By Abhiman Mulmi 18
3 Attention required within 6 months
2 Attention required within year
1 Non urgent; attention required within 2 years
0 No time limit for action
Source: Guideline for Inspection and Maintenance of bridge Volume I
3.2.4.2 Practice; Bridge Inspection Equipment
Following equipments are listed in the Bridge inspection and maintenance guidelines for the inspection of the bridge. They
are
1) Safety jackets 2) Gloves 3) Safety helmet 4) Rain coat 5)Bicycle 6) Ladders 7) Other tools
such as First aid kit, Axe, Hasiaya, Knife, Hammer, Gainti, Saw, Traffic cones. It is very dangerous to inspect the work with
such equipments, it will be better to procure at least one inspection vehicle at each regional office for the bridge inspection
work.
Figure 3.8 Bridge Inspection Vehicle
3.2.4.3 Practice; Budget Constraints
Major constraints to the bridge poor condition is the budget constraints. Like in road maintenance work there is no
sustainable funding for the bridge maintenance and Donor too have least interest in the sector. Each year Government
allocates average of 2 million in the bridge maintenance in each division road office which was not sufficient. Sustainable
funding for the bridge maintenance is the needed for good condition of the bridge. World Bank initiated Bridge improvement
and maintenance project for the improvement and maintenance of bridge in Nepal in 2012.
By Abhiman Mulmi 19
3.2.4.4 Practice; Database of as built drawing
Bridge Project must develop the database of as built drawing of existing bridge. As they play a major role in the maintenance
of the bridge. Department of Road is finding difficulty in assessing the bridge vulnerability in the absence of the as built
drawing.
3.2.4.5 Practice; Training
Many Engineers does not have adequate knowledge in Bridge inspection, condition rating, extent rating, urgency rating.
They should be trained in the various aspects of the bridge inspection and maintenance.
3.3 Existing Policy, Guidelines, Standards regarding Bridge Management
1. The DoR Bridge Policy and Strategies 2004
2. Guidelines for Inspection of bridge and maintenance Volume I and II
3. Standard Specification for Road Bridges 2001
4. Nepal Bridge Standards 2067
5. Standard Bidding Document for bridge construction Medium Contract
6. Initiation of Bridge Management Information System
7. Incorporation of Bridge Maintenance in Annual Road Maintenance Plan.
8. Standard Design of Superstructure (Modified to Two lanes)
9. Restructuring of Bridge Unit into Bridge Project
10. Initiation of Design Build Concept of Bridge Construction
3.4 Recent Development Bridge Management Information System
A bridge management system or BMS is a means for managing bridges throughout design, construction, operation and
maintenance of the bridges. As funds available become tighter, road authorities around the world are facing challenges
related to bridge management and the escalating maintenance requirements of large infrastructure assets. Bridge
management systems help agencies to meet their objectives, such as building inventories and inspection databases, planning
for maintenance, repair and rehabilitation (MR&R) interventions in a systematic way, optimizing the allocation of financial
resources, and increasing the safety of bridge users.
The major tasks in bridge management are: collection of inventory data; inspection; assessment of condition and strength;
repair, strengthening or replacement of components; and prioritizing the allocation of funds. A BMS is a means of managing
bridge information to formulate maintenance programs within cost limitations. A BMS includes four basic components: data
storage, cost and deterioration models, optimization and analysis models, and updating functions.
It can be used for following measures
1. Storing Bridge data
2. Making Maintenance of bridge
3. Making Improvement of bridge
4. Making replacement of bridge
5. Allocating fund
6. Projecting future construction of bridge
7. Tracking Projects
8. Tracking Performance
By Abhiman Mulmi 20
Figure 3.9 Bridge Management system
By Abhiman Mulmi
Bridge Management
System
Planning
Budgeting
Scheduling
Performing
Reporting and
Evaluating
Inspecting
21
CHAPTER 4
4.0 Data Analysis and SWOT analysis
This Data analysis logically presents the analytical results acquired from the intensive review and study. Primary data were
collected from questionnaire survey discussion where as the secondary data were collected through the desk study of various
reports published by DoR and Project documents. This chapter deals with the findings of the study in relation with exploring
Bridge management practices in Nepal. It analyses and presents the results from each section of the questionnaire in different
forms e.g. tables, pie charts bar charts, histograms etc.
4.1 Human Resource Assessment
Main Organization Unit that are involved in the Bridge project management are
1. Department of Roads
2. Bridge Unit
3. Regional Directorate
4. Division Road Office
The Human resource assessment for the bridge project management is carried out in the matrix format.
Table 4.1 Human Resource Assessment for bridge management in Department of Roads
Institution Total Human Resource
Technical
Non Technical
Work Load Remark
Department of Roads (including Regional Directorate and Road Division)
2610 2300 310 All works and function of the DOR including road and bridge development initiated by DOR
Bridge Unit at the DOR
24 15 9 Pre-feasibility, feasibility study of the bridge (35 new bridges are under design; 350 bridges are under construction now; 50 to 60 bridges construction is completed each year; 70 to 80 new bridges are taken up for construction each year, 12 to 1300 bridges currently require maintenance), model contract documents (for all bridge projects), and implementation supervision/monitoring of centrally implemented projects (3 projects). Supervision and monitoring of the projects implemented by Regional Directorate and Road Divisions (more than 350 under construction bridges)
Considering the workload in the bridge unit, the working technical staff in the project is inadequate. Further lack of special training related to bridge design to the staffs of the unit, the unit has to entirely depend on outsourcing of the consultants for design as well as review of the design.
As the unit also directly supervise the central level projects (3), supervisory functions of the uit for the bridge construction and maintenance projects at road division level is grossly inadequate for the quality construction and maintenance.
Regional Directorate *
8 3 5 Many staff on the lists, but hardly few are present in the office. There is not much workload to the regional
By Abhiman Mulmi 22
directorate. Most of the time staffs of the regional directorate are at the central office.
Road Division** 24 18 6 Total project handled by the division is 50 (district road 16, urban road 14, Toourist road 4, Regional level roads 3, bridges 12, Chepang Marga 1) excluding the regular maintenance and rehabilitation works of roads and bridges.
With the current level of staff it appears that one technical person has to supervise nearly 3 projects at a time. Further the projects are located at wide apart areas. Obviously, the supervision of the works by the appointed technical staff is inadequate to maintain the quality works.
** DRO Bharatpur
Source World Bank Project Appraisal Document of Bridge Improvement and Maintenance Project
It indicate that the lack adequate human resource in the implementation of bridge management.
4.2 Financial Assessment
4.2.1 Bridge Construction work
Table 4.2 Budget Allocation and Expenditure in Bridge construction in DoR (Amount in, 000)
Fiscal Year Budget Allocation Plan Budget Spent Achievement
FY 2068/69 3,523,631 Plan to complete 75 bridges , procurement of 6 additional bridge through design build approach totalling to 19 bridge and continuation of bridge construction work
3,339,865 Completion of 46 bridge construction work
FY 2067/68 3,15,52,03 45 Nos of bridge construction to be completed, Intiation of Design Build Contract of 5 bridges
2,95,29,13 87% Physical Progress
FY 2066/67 2,33,72,36 2,16,17,57 96.38% Physical Progress
FY 2065/66 1,39,57,48 1,29,94,91 91.46% Physical Progress
FY 2064/65 77,49,45 75,04,43 74.95 Physical Progress
FY 2063/64 74,33,77 52,19,83 72.35% Physical Progress
FY 2062/63 51,45,53 37,04,35 69.67% Physical Progress 35 bridge completed
FY 2061/62 76,70,00 45,21,37 78% Physical Progress
FY 2060/61 46,55,00 32,25,51 78% Physical Progress
FY 2059/60 24, 73,04 14,57,28 71% Physical Progress
By Abhiman Mulmi 23
FY 2059/
60
FY 2060/
61
FY 2061/
62
FY 2062/
63
FY 2063/
64
FY 2064/
65
FY 2065/
66
FY 2066/
67
FY 2067/
68
FY 2068/
69
0
500000
1000000
1500000
2000000
2500000
3000000
3500000
4000000
Budget AllocationBudget Spent
Figure 4.1 Budget Allocation and Budget Expenditure in Bridge Construction in DoR (Amount in thousands)
Budget Allocation data show that the budget allocation has been double in FY 2065/66 in comparison to FY 2064/65 and
afterward it continuously increased in the next years. The progress also good with the present organization structure as there
has not been significant addition of human resource today back some ten years ago. The work load comparing today is more
than 1000% greater than some ten year back. Budget allocation for FY 2059/60 is 24,32,04,000 in comparison to allocation
for FY 2068/69 3,52,36,31,000. Which shows how the work is going today and this indicate the immediate need of
organization restricting. HOW much input of Human resource is needed for bridge construction work?
4.2.2 Bridge Maintenance work
Table 4.3 Budget Allocation and Expenditure in Bridge Maintenance in DoR (Amount in, 000)
Fiscal Year Budget Allocation Plan Budget Spent Achievement
FY 2068/69 24,42,70 Plan to Maintenance the bridges of strategic road network.
19,82,95 85% Physical Progress. Trishuli Bridge Periodic Maintenance of (Mugling-Tanahun section, Prithvi highway), Marsyangdi Bridge (Khaireni-Gorkha section, Tanahun district), Seti Bridge (Khaireni-Bhimad section, Prithvi highway), Jharahi Bridge (Mahendra highway, Nawalparasi district), Kaligandaki Bridge (Siddartha highway, Ramdi), Bheri Bridge (Ratna Highway, Surkhet), Tamakoshi Bridge (Lamosangu-Jiri section, Dolakha district), Sunkoshi Bridge (Lamosangu-Jiri section, Sindhupalchowk district) and Tadi Bridge
By Abhiman Mulmi 24
(Nuwakot district)
FY 2067/68 30,42,71 Plan to Maintenance the bridges of strategic road network.
15,04,08 76% Physical Progress
FY 2066/67 4,24,57 Plan to Maintenance the bridges of strategic road network.
3,70,33 96% Physical Progress
FY 2065/66 3,77,90 Plan to Maintenance the bridges of strategic road network.
3,44,68 95.20% Physical Progress
FY 2064/65 3,94,55 Plan to Maintenance the bridges of strategic road network.
3,51,90 90.79 Physical Progress
FY 2063/64 3,01,00 Plan to Maintenance the bridges of strategic road network.
2,25,61 89.79% Physical Progress
FY 2062/63 2,70,00 Plan to Maintenance the bridges of strategic road network.
2,20,97 87.52% Physical Progress
FY 2061/62 2,60,00 Plan to Maintenance the bridges of strategic road network.
1,56,68 82% Physical Progress
FY 2060/61 2,60,00 Plan to Maintenance the bridges of strategic road network.
1,58,28 91% Physical Progress
FY 2059/60 2,70,00 Plan to Maintenance the bridges of strategic road network.
1,32,41 17.6 % Physical Progress
By Abhiman Mulmi 25
FY 2059/
60
FY 2060/
61
FY 2061/
62
FY 2062/
63
FY 2063/
64
FY 2064/
65
FY 2065/
66
FY 2066/
67
FY 2067/
68
FY 2068/
69
0
50000
100000
150000
200000
250000
300000
350000
400000
450000
Budget AllocationBudget Spent
Figure 4.2 Budget Allocation and Budget Expenditure in BridgeMaintenance in DoR (Amount in thousands)
Budget allocation for the Bridge maintenance is inadequate, which show Government is not serious on the preservation of
the bridge. Budget Allocation data show that the budget allocation has been increase significantly in FY 2067/68 in
comparision to FY 2059/60 and afterward it continuously increased in the next years. However, it is still is inadequate to the
requirement of bridge maintenance.
4.3 SWOT analysis of Bridge Management Practice in DoR
The Successful Implementation of the proposed plan depends upon various factors. The Strength, Weakness, Opportunity
and Threats (SWOT) are identified and analysed as follows.
Based on the review of the documents on the performance based maintenance and management contracts. Certain points
have been listed as in Table No 6-1 below:
Table 4.4 SWOT analysis of Bridge Management System
Strength
Good structured strategic network and Division within a
geographic area.
Well equipped and experienced Employer, Contractor and
Consultant.
Good Procurement Management and e procurement
Strong Logistic Support
Well Formulated Policies and Guidelines
Fast Developing Private Sector
Systematic Bridge Inspection Manual
Web Based Bridge Management System
Weakness
Lack of clearly defined process and procedure for its
implementation of Maintenance Management.
Budget Constraints.
Inadequate Human Resource and expertise.
Poor documentation and record management
Inappropriate Job Description
Lack of motivation
Higher dependency in donor
Poor Implementation of policy
High Political influence.
Opportunities
Potential Expansion of road network-Large number of bridge
projects.
Increasing interest of donor in bridge sector.
Threats
Political instability (frequently happening bands)
Lack of commitment and adhoc selection of bridge
construction and maintenance.
By Abhiman Mulmi 26
Potential development of expertise.
Expansion of other mode of transportation like railway
bridge, flyover.
Opportunity to transfer the significant amount of risk to the
private sector through Design Build, BOT modality.
Improvement of service quality level of the Bridge, Improve
condition of Bridge.
Involvement of private sector in maintenance activities
reduces the burden to public sector.
Increased investment and funding opportunities, potentially
more opportunity to obtain funding on bridge
maintenance.
Greater market appetite for larger contracts, qualified and
experienced contractors will be attracted more
competition.
Opportunities to cope with the global trend.
High level of political influence.
Inefficient accessibility in planning of the BMMS.
Long term market instability and uncertainty may damage
the opportunities.
Conflicting interest and unnecessary condition of donor.
Change in government policy and intervention.
Unforeseen natural phenomenon leads to emergency works
like earthquake, landslides, floods etc.
CHAPTER 5
Conclusion and Recommendation
5.1 Finding and Conclusion
Department of Road Bridge Policy is very good document and can be the good guidelines for the effective bridge
management of the country. There is good unbalanced related to advanced policy framework but weak implementation
capacity. Following conclusions are drawn up.
1. Centralized project planning, Higher Political and Interest Group interference in the project selection and budget
allocation process.
2. Poor Database management and rare use of technology like Bridge Management Information System in all phase
of project.
3. Nepal Bridge Standard only focuses on theoretical term and it is very basic. Lack of standard quality assurance
plan and standard construction technology for bridge construction resulting weak quality.
4. Lack of proper coordination, Weak Monitoring and Feedback Mechanism and Problem solving mechanism.
5. Lack of expertise among the Engineer of Department of Roads regarding the design and supervision of mainly
steel truss and other than RCC bridges. Likewise Poor knowledge among the Engineer of Division Road Office
regarding bridge inspection and management.
6. Budget Constraints hindering the progress of construction and maintenance of bridge.
7. Traditional Bridge inspection equipment, Weak bridge inspection and no execution of condition rating, extent
rating and urgency rating of plan. Bridge Maintenance Part in Annual road maintenance plan is unreliable.
8. Lack of motivation among the Engineers of Bridge Project.
5.2 Recommendation
The following measures are recommended for the effective management of bridge to strengthen weak implementation
capacity.
Table 5.1 Recommendation in the action plan
Phase of Project
Activity to perform Time to Perform
Responsible Authority
M& E Authority
Remark
Project Institulisation of Bridge Within 1 month Bridge Project (Main Ministry of Workshop
By Abhiman Mulmi 27
Selection and Allocation Phased
Management through developing and introducing decision support systems such as BMMS.
Leader), Regional Director, Division Road Office, Project Office
Physical Planning and Works Transport Management
need to be conduct
Project Selection
Need assessment of Bridge requirement and Prioritize the bridge
Each Fiscal Year
Division Road Office, Project Office
Bridge Project DoR should make it mandatory and decentralized.
Prioritize the Bridge on basis of need assessment of bridge for project selection for feasibility and detailed study
Each Fiscal Year
Bridge Project Ministry of Physical Planning and Works Transport Management
Systematic Database management of the feasibility and detailed study of bridge
Each Fiscal Year
Bridge Project Ministry of Physical Planning and Works Transport Management
Manage the Space Constraints of Bridge Project and Adopt Computer based Database
Allocation Project selection for construction procurement of only those project whose feasibility and detailed survey was conducted on ranking basis
Each Fiscal Year
Bridge Project Ministry of Physical Planning and Works Transport Management
Design Review and Update of Bridge Policy, Bridge Standards, Development of Standard and Guidelines for Complicated bridge, Bridge Design Manual, Standardization of design document, guidelines, manual
Each Fiscal Year
Bridge Project, Department of Road
Ministry of Physical Planning and Works Transport Management
Standardization in design with reduce complication and save time
Strict regulation for Consultants Bridge Project Trend of copying the design has been high
Implementation Phase
Review of current qualification criteria of bidder
Bridge Project This is needed that many bridge project handle by in competent contractor
Development of Standard Quality Assurance Plan and Construction Technology Plan and mandatorily implementation during the construction of bridge.
Bridge Project, Division Road Office, Project Office
To address poor quality control mechanism and weak traditional construction technology
Mandatory Monitoring of the construction work of bridge with standard checklist and guidelines
Each three month
Regional Director Bridge Unit/Director General
Development of Feedback and Problem Solving mechanism with the pool of experts or outsourcing External Consultant for the solving complicated bridge case annually across the Division
Hiring Pool of External Expert annually on fixed contract basis annually
Bridge Unit
Handover and Make the Provision of Start up Before handover Bridge
By Abhiman Mulmi 28
Documentation Phase
and Commissioning work mandatory in the bridge construction contract execution of start up and commissioning work before hand over
Unit/Contractor/Design Consultant, Division Road Office, Project Office
Handover of the SRN bridge to Division Road Office, Project Office and Non SRN to Local Body.
Maintain Digital Database of as built drawing of constructed bridge.
Bridge Project, Division Road Office, Project Office
Bridge Project
Operation and Maintenance Phase
Institutionalising Sustainable Bridge Management through developing and introducing various decision support system like BMMS and BRMS in maintaining bridge
Bridge Project
Effective adoption of planned bridge maintenance making the annual bridge inspection and urgency rating for maintenance mandatory
Division Road Office, Project Office
Regional Director, Bridge Project
A separate workshop like Annual Bridge Maintenance Plan can be held
Procurement of Bridge Inspection Vehicle
Mechanical Branch, Department of Road
Training to the Engineers of Department of Roads on Bridge Inspection and Maintenance
Consultants Bridge Project Human resource Development
Separate Maintenance Strategy for special type of bridge like Karnali Bridge, Mugling bridge should be developed.
Maintain Digital Database of as built drawing of all existing bridge.
Bridge Project, Division Road Office, Project Office
Bridge Project
Human Resource Development
Provide different type of training on bridge planning to maintenance to Engineers of Department of Road.
Road Sector Skill Development Unit, Bridge Unit
Restructuring of Bridge Project
Bridge Project should incorporate the separate team of Bridge Management Support Unit
Bridge Project
By Abhiman Mulmi 29
References
DoR, 1994; DoR Strategy, Department of Roads, Kathmandu
DoR,2001; Standard Specification for Road Bridges, Department of Roads, Kathmandu
DoR, 2004; The DoR Bridge Policy and Strategies, Department of Roads, Kathmandu
DoR, 2004; Guidelines for Inspection of bridge and maintenance Volume I and II, Department of Roads, Kathmandu
DoR 2005; Bridge Condition Survey Report, Department of Roads, Kathmandu
DoR, 2009; Nepal Road Statistics, Department of Roads, Kathmandu
DoR, 2010; Nepal Bridge Standards 2067, Department of Roads, Kathmandu
DoR 2011; Standard Bidding Document for bridge construction Medium Contract
World Bank 2012; Project Appraisal Document Bridge Improvement and Maintenance Project, Washington DC
By Abhiman Mulmi 30