structural survey - whatdotheyknow · for health and safety reasons, the two loose finials have ......
TRANSCRIPT
O:\_misc projects\_STRUCTURAL DSA REPORTS\Harborneclock1REV.1.0.doc
Structural Survey
Of
Harborne Clock Tower Centre,
High Street, Harborne,
Birmingham. B17 9NJ
Ref: 72069/SE/BK/V1 10th August 2010
O:\_misc projects\_STRUCTURAL DSA REPORTS\Harborneclock1REV.1.0.doc
CONTENTS
1. Introduction
2. Description
3. Procedure
4. Observations
5. Discussion
6. Recommendations
7. Photographs
1.0 INTRODUCTION
The Structural Section of Urban Design was requested by Iain Pay (Building
Surveyor, Urban Design) on 17th
March 2010, to undertake a survey of the
building known as Harborne Clock Tower Centre on Harborne High Street,
Harborne, Birmingham, due to reports of debris falling from high levels of the
building on to the public highway.
In particular, it is understood that due to some elements of the building being
severely deteriorated, one reasonably large piece of feature stone had become
loose and fell onto the public pavement along High St; Harborne.
2.0 DESCRIPTION
The listed building predominantly comprises traditional brickwork, terracotta
and natural stonework all covered in plain clay tiling onto traditional timber
roof. It is understood the building was built in late 1800's.
3.0 PROCEDURE
An initial visit to site was made on 8th
April 2010 when it quickly became
apparent that a protective scaffold was necessary to safeguard members of the
public from further falling debris and an access scaffold to facilitate the
inspection of all high level elements of the structure. Due to the urgency of the
situation, the protective scaffold was already being erected under the guidance
of Iain Pay of Urban Design.
Further visits were made on 29th
April , 2nd
June 16th
July, 20th
July and 4th
August 2010 to carry out various structural inspections and to identify areas that
required to be opened up including identifying positions of access scaffold.
4.0 OBSERVATIONS
The weather was generally dry on many occasions, slightly raining on one day
and a light to moderate wind on the day of high level inspection of the outside
elevations of the clock tower itself.
External
Roof
Generally, the roofs to the building, including the clock tower, are in a
dilapidated state and numerous past repairs are evident. Roofs to the building in
general are noted to be slightly sagging. However, the clock tower roof is very
steep and sagging to this is not visible.
There are numerous areas of the roof where:
• a leaded crest over the roof facing York Street can be swayed by
reasonable hand force. This will need to be taken down and re-fixed
• relatively heavy terracotta finials to the ridges to some of the gablets are
loose that can be moved by hand whilst applying a reasonable amount of
force
• the ridge tiles are sitting loose in position under their own self weight
and these can be moved by hand
• opened joints amongst slipped and missing verge tiles
• loose mortar or missing under-cloak at verges
• missing and broken roof tiles in the expanse of the roof over various
rooms to the building
• the above ground drainage system including gutters, down pipes and soil
stacks, is in dire state; cracked or broken where leaking or over-spilling
water is causing damp to walls and foliage growth in the walls
• lead flashings to the roof are severely breaking away and may require to
be re-bedding or total replacement
• valleys showing signs of past water penetration and lead work requiring
to be at least re-bedded. The valleys require to be substantially repaired
or reconstructed where the timber at the base of any of the valleys is
likely to be rotting
• Ironwork or steelwork where noted including to areas in the clock tower,
has corroded significantly and in such cases is affecting the brickwork by
the expansion caused by the rusting of as such.
• Timber fascias or soffits are rotting
More specifically, the following observations relating to the clock tower were
made:
• There were four iron finials above the clock level which appeared to be
fixed into the masonry. One of these finials was just held in position by a
pin and was easily removed by the scaffolding or roofing team. Another
was tested by me and was easily removed by a hand turn. The other two
remaining finials are suspect, one of which is held by some pressure
from the scaffolding board wedging it. The finials would seem to weigh
approx. 5 kg. For health and safety reasons, the two loose finials have
been taken down and stored away by the contractor.
• The removed finials could have potentially caused a fatality to members
of the public should these have fallen off due to wind etc. As the
remaining finials are suspect, these should be taken down, refurbished
and re-fixed.
• The steep roof to the tower has had limited patch repairs carried out in
the past. However, some missing plain clay tiles are evident in various
locations. Amongst these, quite a few of the hip tiles are missing and in
numerous other roof areas they are loose and their fixity suspect.
• There are large areas of perished brickwork with delaminating surfaces
and loose mortar joints. The brickwork and terracotta around the clock
is particularly badly affected.
• There are four GRP finials - probably replacing old terracotta. These are
fixed onto the ridge tile to a gablet in each face. One of these finials on
its base can be moved by hand with a reasonable force applied.
• Iron gutters and down pipes (some of the down pipes are of asbestos
construction) are corroded including their fixings into the wall. There is
evidence of missing or broken tiles landing into the gutters and they are
remaining there even today.
Elevations
There are numerous areas of perished to all elevations including a total area of
walling over the entrance to the building from York Street, feature brickwork
surrounding the louvre openings to the clock tower, whereby it will be necessary
to carefully remove and re-build such affected brickwork. Some in-significant
bowing of walls or tall piers is noted.
Much of the perished brickwork is delaminating and, evidently the facing layers
can be easily removed by hand. Some of those layers are noted to be fairly thick
and should they fall from a height, may cause injury to members of the public
below.
Similarly, much of the stonework noted to window and door heads and sills,
louvres to the clock tower, elemental features including at eaves, parapets or
coping stones; string courses etc. is significantly eroded and will need specialist
attention in cutting out and re-bonded with new or careful replacement.
Slight cracking to brick work is evident in the rear elevation including just
below verges to gable ends and over a lintelled opening to the rear.
Cracking or opened up joints and in brick perps is evident to the terracotta
arches to the external elevations.
The elevations that are worst affected by the above noted defects in brickwork
and stone or terracotta appear to be those facing High Street, York Street and
sections of the rear elevations when viewed from the rear courtyard serving the
building.
More specifically, the following observations relating to the Clock Tower were
made:
• an area of brickwork contained a fairly substantial but rusting fixing -
possibly a fixing to a former down pipe
• Brickwork including the terracotta around the clock tower including at
the corners of the tower and around the louvres is badly perished and
missing in places. There is evidence of surface de-lamination to these
bricks. Also, mortar joints are loose in these affected areas of walls.
• stone sills to the openings in the walls to the tower are badly perished
and some of the sections of the sills are missing
Chimneys
There are chimneys serving the main building and those at the rear of the
building near the car park that are either bowing, cracking or that their
brickwork is loose and will need to be either reduced in height or re-built.
One particular chimney stack to the rear is very tall and slender. To this chimney
stack, there is evidence of opened joints including perps, perished and missing
bricks. Iron strapping and rods designed to stabilise the stack are corroded to a
degree requiring remedial attention or replacement. The stack itself will need to
be reduced in height.
Another but smaller chimney stack is dangerously crumbling, whereby bricks
can be moved or even picked up by hand. This has already been temporarily
secured by scaffold and netted around to prevent any fall out.
Drainage
The underground drainage system appears to be of an age such that it requires to
be surveyed and tested by a specialist and may require repairs to be carried out
to the system as may be necessary. This is to avoid any leaking drains affecting
ground conditions and causing building settlement problems.
Internal
All rooms were inspected that contained high ceilings. The roof structure
comprises timber jack rafters supported of timber purlins which are in turn
supported off principle timber trusses. Most of the ceilings are lath and plaster
fixed to the underside of the jack rafters. Evidence of water penetration is noted
and such areas have been be opened up including those areas where it was
essential to determine certain structural elements and their condition including
brick walls, roof structure, ceilings and floors.
Upon viewing the opened up areas, such as the roof valley positions from below,
there do not appear to be any major implications. Some of the fixings in the
joints have slipped and thereby allowing the principle timber members to also
slip in turn.
Some of the walls and timber floors, particularly to the narrow store and the
section of building occupied by the caretaker at first floor located at the end of
the building - are noted to be affected by lateral and rising damp.
Some of the external walls to the part of the building occupied by the caretaker
are showing severe damp conditions and foliage growing on the inside faces -
behind the plastered finishes. It appears that water ingress had been abundant
and some may still be present for the above to occur.
Severe dry rot has been identified in at least one section of the building where
the timber floor and brick walls have been affected. Floor to that area has been
temporarily made safe.
Upon inspection of the internal masonry cross walls, there do not appear to be
any significant structural problems or to the overall stability of the building.
5.0 DISCUSSION
Presently, there generally appears to be no fundamental overall stability issues
with the structure, the exception being the high level chimneys. However, there
are extensive and significant material defects, throughout the building,
predominantly at high level. These defects need to be addressed in the near
future to ensure no consequential damage to the structure occurs.
The main problems with this building are the roof and perished/weathered
masonry and terracotta.
Debris has been reported to have fallen on a number of occasions and from
observations this situation would have continued with potentially fatal
consequences. Such examples would include the approximately 700mm high
metal finials that were removed by hand from the tower roof and the hip and
ridge tiles that were held by their self weight. There are further components to
the building that have been identified to be loose or corroded embedded and
require attention. These defects have vindicated the decision to erect the
protective scaffold.
There is some age related cracking to the building. However, nothing that would
not be expected in view of the age of the building.
Dry rot has been identified in a section of the building. This would require
immediate attention as this type of rot has the potential to spread quite quickly if
not remedied.
6.0 RECOMMENDATIONS:
Roof covering is likely to require major work including replacement in many of
these areas. The integrity and fixing of the tiles and battens needs to be checked
by specialist roofing contractor.
As noted above, cracking, bowing or loose brickwork to chimneys will need to
be addressed by either reducing their height, repairing or rebuilding.
The various finials and crests including those that have been identified to be
either suspect or loose require to be removed and refurbished, and then
satisfactorily re-fixed into position. Any embedded iron work that has corroded
needs to be removed and suitably replaced where necessary.
Timber fascias and soffits will need to be replaced.
Perished brickwork or stonework will need repairing or replacement including
to the clock tower. Any replacing will obviously need to be sympathetic with the
existing building and to match including mortar mix. Large areas of brickwork
will require pointing in particular those at high level. A nominal amount of
brickwork stitching will be required to deal with localised cracking in the
masonry. More immediately, loose or delaminating masonry should be removed
or appropriate netting carried out around the scaffold to prevent any fall out onto
members of the public.
The above ground drainage needs to be replaced.
The underground drainage needs to be surveyed and tested and any identified
defects addressed.
A timber and damp specialist should be consulted to consider the noted areas
observed to be damp or rot affected. Any noted defects should be rectified in
accordance with their recommendations.
Author: Bob Kumar, BSc (Eng); Str. Eng; DSS, Urban Design
0121 303 6574
Reviewed: S L Bates; C.Eng; MICE, Group Eng; DSS, Urban Design
7.0 PHOTOGRAPHS.
Tall chimney Close up of tall chimney showing cracking
Dangerous chimney with loose bricks evident
Clock Tower
Loose ridge, broken, slipped and missing tiles
Moveable crest on ridge
Leaking drainage with foliage growing in walls
Foliage growing
behind internal
finishes to external
wall
Perished and cracked arches over openings
Perished and weathered brickwork and stone copings/string coursing
Uncovered dry rot from timber floor
De-laminating brickwork easily removed by hand (including at high level)