structural condition assessment of sans souci … · sans souci bathers pavilion 80818250 16...
TRANSCRIPT
![Page 1: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/1.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 1
STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI BATHERS PAVILION
Sans Souci Bathers Pavilion 80818250
Prepared for Georges River Council 16th February 2018
![Page 2: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/2.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 2
Contact Information
Cardno (NSW/ACT) Pty Ltd
ABN 95 001 145 035
Level 9, The Forum
203 Pacific Highway
St Leonards NSW 2065
Telephone: 02 9496 7700
Facsimile: 02 9439 5170
International: +61 2 9496 7700
www.cardno.com
Author(s):
Vesal Torabi (VT)
Remedial Engineer
Approved By:
Leo Meng (LM)
Remedial Team Leader
Document Information
Prepared for Georges River Council
Project Name Sans Souci Bathers Pavilion
80818250
File Reference 80818250_Structural Condition
Assessment of Sans Souci
Bathers Pavilion
Job Reference 80818250
Date 16 February 2018
Version Number 1
Effective Date 16th February 2018
Date Approved: 16th February 2018
Document History
Version Effective Date
Description of Revision Prepared by:
1 16.02.2018 Review Vesal Torabi
![Page 3: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/3.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 3
Table of Contents
1 Executive Summary 4
2 Introduction 6
3 Site Observations 7
4 Desktop Study and Recommendations 17
5 Risk and Conformance Issues 19
5.1 Risk Assessment 19
5.1.1 Consequence Criteria 19
19
5.1.2 Likelihood Criteria 20
20
5.1.3 Risk Matrix (combine Likelihood Vs Consequence) 20
5.1.4 Risk Assessment based on Existing Condition 21
6 Conclusion 22
![Page 4: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/4.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 4
1 Executive Summary
Cardno has been engaged to undertake a structural assessment of the bathers pavilion at Sans Souci. The
purpose of the structural assessment is to identify the structural risks and make suitable recommendations on
the required remedial works in order to maintain the longevity of the structure if possible. 3D imaging was
captured to better portray the condition of the existing building. This can be seen on the following link
https://my.matterport.com/show/?m=f7gTNgDihyA.
Suspended Concrete Roof Slab
The structural assessment on the suspended concrete roof was noted to have signs of concrete spalling and
moisture staining to the soffit. In general, the slab soffit was found to be in reasonably good condition in most
areas, however upon the completion of desktop study of the existing roof slab, it was noted that the current
design is not sufficient in withstanding a 5kPa live load as required by the Australian Standards for ‘areas
which are susceptible to overcrowding’. The followings observations were noted during our structural
assessment:
Condition/Risks
Structural strength review based on the calculations finds that the suspended concrete roof slab is
structurally inadequate to support the current requirements as stated by the Australian Standards. It
is our understanding that access onto the roof slab has been barricaded off to prevent human entry
into the area.
Concrete spalling was noted within some sections of the slab soffit as mentioned in Section 3 of this
report.
Moisture Staining was noted within some sections of the slab soffit as mentioned in Section 3 of this
report.
Overall, current the risk level is high for the suspended concrete roof slab. Our recommendations on the roof
slab are as summarised below:
Recommendations
Access onto the roof slab to be barricaded off immediately. (Which we believe has already occurred)
In order for the existing concrete roof slab to be accessible, significant strengthening is required.
Other Structural Elements Throughout Bathers Pavilion
The frame of Sans Souci Bathers Pavilion is in very poor condition, with significant signs of concrete spalling
within the entire structure. The following observations were noted during our structural assessment:
Condition/Risks
Significant concrete spalling was noted to all aspects of the building, including the concrete columns
and beams.
Internal non-load bearing walls were heavily dilapidated
Cracking was noted to areas of the slab on ground and tiled areas.
Significant concrete spalling was noted to the reinforced concrete lintels.
Overall, the current risk level is high for the structural frame of the building. Our recommendations are as
summarised below:
![Page 5: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/5.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 5
Recommendations
Due to the degree of severity of concrete spalling within the façade, it is possible that conventional
concrete spalling repair would deem more expensive than to demolish and rebuilding sections within
the façade.
![Page 6: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/6.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 6
2 Introduction
Cardno was commissioned to carry out the structural condition assessment of the bathers pavilion located at
Sans Souci. The purpose of the structural assessment is to identify the structural risk and making suitable
recommendations on the required remedial works in order to maintain the longevity of the structure if possible.
A visual site inspection was carried out by two suitably qualified structural engineers on the 6th February 2018.
Cardno carried out a slab scan to locate the existing steel reinforcement within the concrete members for our
desktop study. Cardno also carried out a 3D scan of the building to ensure that no defects were missed during
the inspection as well as providing the ability to present the overall condition of the structure in a
comprehensive manner to any persons of interest.
An aerial view of Sans Souci Bathers Pavilion is shown in Figure 2-1 below.
Figure 2-1 Aerial View of Sans Souci Bathers Pavilion (Google Images)
![Page 7: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/7.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 7
3 Site Observations
Based on our visual inspection on 7th February 2018, the main issues noted at The Bathers Pavilion includes severe concrete spalling, extremely corroded/deteriorated reinforcement and staining to both the internal and external walls. A selection of photos are shown below:
ITEM
Bathers Pavilion
Suspended Concrete Roof Slab Soffit
Extensive concrete spalling and severe corrosion to the reinforcing bars
Photo 1
Suspended Concrete Roof Slab Soffit
Typical extensive spalling to roof slab
Photo 2
![Page 8: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/8.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 8
Concrete Beams
Significant concrete spalling and corrosion to the concrete beams.
Photo 3
Concrete Beams
Typical extensive concrete spalling to the concrete beams.
Photo 4
![Page 9: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/9.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 9
Concrete Columns
Significant concrete spalling and loss of cross-sectional area to the concrete columns.
Photo 5
Concrete Columns
Further evidence of extensive deterioration to concrete columns as well as exposed and corroded reinforcement.
Photo 6
![Page 10: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/10.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 10
Concrete Lintels Extensive concrete spalling was noted to the lintels as shown below.
Photo 7
Concrete Lintels Typical concrete spalling to lintels. Large cracks were also noted throughout the entirety of the building.
Photo 8
![Page 11: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/11.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 11
Cantilevered Concrete Roof Slab
Extensive concrete spalling to the cantilevered sections of the concrete roof slab as shown below. Substantial flaking of paint and bubbling was also noted across the entire building.
Photo 9
Cantilevered Concrete Roof Slab
Further evidence of the concrete spalling to the slab soffit.
Photo 10
![Page 12: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/12.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 12
Brick Walls
Large cracks exceeding 3mm in width were noted to several walls within the building.
Photo 11
Brick Walls
The photo below shows a general overview photo the current condition of the walls.
Photo 12
![Page 13: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/13.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 13
Brick Walls
Large cracks within the brick walls of the building.
Photo 13
Brick Walls
Significant cracking to internal walls.
Photo 14
![Page 14: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/14.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 14
Façade
Significant cracking and staining to the southern façade.
Photo 15
Facade
Extensive concrete spalling to the southern façade. Large amounts of flaking paint was also noted to all facades.
Photo 16
![Page 15: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/15.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 15
Electrical Switch Room
Significant cracking and concrete spalling was noted to the brick walls and concrete lintels.
Photo 17
Electrical Switch Room
Typical cracking throughout the building facades.
Photo 18
![Page 16: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/16.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 16
Electrical Switch Room
Severe cracking to roof slab of electrical switch room
Photo 19
Electrical Switch Room
Further evidence of cracking to the concrete roof.
Photo 20
![Page 17: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/17.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 17
4 Desktop Study and Recommendations
Desktop Study on Suspended Concrete Roof Slab Cardno carried out detailed measurements of the structural components of the building to determine whether the suspended concrete roof slab was capable of withstanding a live load of 5kPa as stated in AS 1170.1 -2002 (Permanent, imposed and other actions) . In the desktop study, 100% steel utilisation was assumed for the purpose of this report. Analysis of the design showed that the roof slab is structurally inadequate to support the current requirements and that this area should be immediately barricaded off to prevent human entry as this area serves as a potential of serious injury. We believe this area has already been closed off. Below shows the typical layout structure of the building frame which was used for the desktop study of the suspended concrete roof slab.
Figure 4-1
Upon inspection of the structural components of the building, significant concrete spalling was noted throughout the entire building. This concrete spalling was evident within the concrete beams, columns and roof slab. Significant amounts of concrete spalling leads to a loss of steel utilisation as well as a decrease in the cross sectional area of the concrete columns and beams, leading to a loss of strength and possibility of sudden collapse. To adhere to the Australian Standards, significant strengthening is required and taking into consideration the overall condition of the building, this exercise would deem very expensive and impractical
![Page 18: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/18.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 18
Recommendations: Conventional concrete spalling repair comprises of wire brushing cleaning corroded reinforcing bars. If a bar is found to have lost at least 20% of its cross-sectional area, new bars are to be lapped with the existing to provide the sufficient strength required. Considering the significant amount of corroded steel throughout the entire building it is highly likely that this corrosion has extended even further than what can be inspected visually alone. It is possible that the steel has corroded in areas which the concrete has not been displaced. Therefore, it is very difficult to control the extent of the repair and the repair cost. The roof slab requires significant strengthening, structural components within the building require large quantities of concrete spalling repair and sections within the façade need to be rebuilt. Due to these reason, it is our opinion that demolishing and rebuilding would be the more cost-effective solution.
![Page 19: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/19.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 19
5 Risk and Conformance Issues
5.1 Risk Assessment
A risk assessment has been performed based on the current condition of Bather Pavilion. The risk
assessment criteria is shown 5.1.1 to 5.1.3 below.
5.1.1 Consequence Criteria
Figure 5-1
![Page 20: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/20.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 20
5.1.2 Likelihood Criteria
Figure 5-2
5.1.3 Risk Matrix (combine Likelihood Vs Consequence)
Consequence
L
ike
lih
oo
d
Insignificant Minor Moderate Major Catastrophic Almost Certain
Medium (11)
High (16)
Extreme (20)
Extreme (23)
Extreme (25) A
Likely Medium (7)
High (12)
High (17)
Extreme (21)
Extreme (24) B
Possible Low (4)
Medium (8)
High (13)
High (18)
Extreme (22) C
Unlikely Low (2)
Low (5)
Medium (9)
High (14)
High (19) D
Rare Low (1)
Low (3)
Low (6)
Medium (10)
High (15) E
1 2 3 4 5
Figure 5-3
![Page 21: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/21.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 21
5.1.4 Risk Assessment based on Existing Condition
The outcome of the risk assessment based on current condition is shown in the table below.
Risk Assessment – Current Condition
Component Element Likelihood Consequence Risk
rating
Bathers Pavilion
Electrical Switch Room Possible Moderate High
Suspended Concrete Slab Likely Major Extreme
Concrete Beams Possible Moderate High
Concrete Columns Possible Moderate High
Concrete Lintels Possible Moderate High
![Page 22: STRUCTURAL CONDITION ASSESSMENT OF SANS SOUCI … · Sans Souci Bathers Pavilion 80818250 16 February 2018 Cardno 4 1 Executive Summary Cardno has been engaged to undertake a structural](https://reader035.vdocuments.site/reader035/viewer/2022062415/5fdc5ce46233cd0d570bd2da/html5/thumbnails/22.jpg)
Structural Condition Assessment Sans Souci Bathers Pavilion 80818250
16 February 2018 Cardno 22
6 Conclusion
Based on our inspection and desktop study, Bathers Pavilion is in very poor condition overall and has a high level of risk due to its current condition. Significant concrete spalling is apparent throughout the concrete beams, columns and roof slab. The roof slab requires significant strengthening, structural components within the building require large quantities of concrete spalling repair and sections within the façade need to be rebuilt. Due to these reason, it is our opinion that demolishing and rebuilding would be the more cost-effective solution.
A detailed 3D walk through of the building can be seen on the following link -https://my.matterport.com/show/?m=f7gTNgDihyA.