strengthen hmis in tanzania operation plan
TRANSCRIPT
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
1/25
1
Strengthen HMIS in Tanzania - Operational plan
The MoHSW, with a consortium of partners, in October 2007, developed aProposal to
Strengthen the HMIS in Tanzania. Building on this document, during 2008, an operational
plan has been developed, presented to the MOHSW, revised according to their requirementsof early results, and redeveloped further through an extensive process. This current document
synthesizes the requirements and conclusions reached during this process into an operational
plan.
Key requirements and conclusions emanating from the 2008 process are;
Early national HMIS coverage and effective data flow from all districts to the
MOHSW are required, while at the same time ensuring longer term (5 years)
sustainability, system strengthening and improved data quality and information usage
o A plan for rapid HMIS rollout and system consolidation is now included
Budget needs to be within the limits of what is committed by the Norwegian, Dutchand Canadian Embassies (2.5 mill + 5 mill + 2-3 mill?) and distributed in such a way
that national coverage (Norwegian), system strengthening (Netherland) are included.
The HMIS process needs to be open and inclusive in such a way that other donors
involved in information related interventions are led to contribute into the same
overall process. For example, while JICA is funding the implementation of the
HIV/AIDS information system in Coast region, the Norwegian Embassy is adding to
this contribution in such a way that the Coast region becomes a test region for the
overall HMIS within this operational plan.
The operational plan and budgets need to contain phased and integrated componentsthat will be funded by the above mentioned donors.
A test region will be developed and maintained throughout the 5 years project. Here
the different types of intervention packages (e.g. software, revised data sets, training
manuals, and data use workshops) will be developed, tested and refined for further
rollout to all districts. Through the JICA initiative, the Coast region has now by
default become such a test region. Another test region may later be added (Mtwara
has been suggested).
The operational plan follows the agreed design of two integrated approaches; 1).top-down
National HMIS rollout and 2) bottom-up system strengthening, as illustrated in figure 1.
While the top-down approach ensures national coverage and consolidation of the revised
HMIS, the bottom-up approach ensures continuous system strengthening, further revisions of
data sets and more in-depth capacity building.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
2/25
2
MOH
&SW
Reg
ionReg
ion
Reg
ion
Reg
ion
DistDistDist
Dist Dist DistDist Dist
Bottom-up
System Strengtheningin first one,
then more Regions
-Analysis and use of information
- Regular data-use workshops
- Capacity d evelopment
- Revision of data & indicator sets- Training scheme & guidelines
- District based d ata warehouse
& Information Office
Top-down rapid rollout to all
districts and consolidation of
functional HMIS:- Databases in Districts and Regions
- Integrated National data warehouse
- Training and support
- Data transfer between districts
& MOHSW
Integrated National
Data warehouse
Strengthening
region by region
Test
Region
All Regions
All Districts
Facility reports
National dissemination
Revised HMIS
Training scheme
Tools & methodologies
Figure 1. Complementary combination of top-down rapid National HMIS rollout and consolidation, and bottom-
up system strengthening starting in one test region and gradually includes the other regions.
1. The top-down approach;
Rapid implementation in all districts over 3 years including 6 months initial phase
Overall objectives:
Implement and strengthen the integrated HMIS and DHIS in all districts and regions
and establish effective data flows to the MOHSW.
The aim and indicator of success is to reach level 1 of information usage according
to the TALI tool (see annex),
o Level 1; establish the basic system with quality data at all levels (including
completeness) and with the effective transmission of data between the levels
Develop a national data warehouse integrating all routine reporting and other data
sources and build capacity at the MOHSW. Establish the Coast region as a test region for the development and testing of tools
later to be rolled out to all districts (an additional test region may be added later)
The work is organized in two components called work packages:
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
3/25
3
Work packages (WP):
WP1 National rollout of strengthened HMIS to all districts and regions. The rollout is
labelled top-down because an initial package of the revised HMIS is, first, tested in the
Coast region (WP2), second, rapidly deployed to all districts and regions, and third,
consolidated over the following two years, all in all a three years intervention. The initial
revised HMIS consists of HMIS and routine data sets and data reporting forms that are
currently in use or recently revised, and the DHIS software which is used for managing,
analysing, presenting and transferring the data. The HMIS data sets and reporting form will
be further revised during the process. These revisions will be accommodated when ready.
Rollout approach: Each district region will have two sessions of formal training (initial
training, and repeat training about 8-12 months later) and three sessions of on-the-job training
and support to be carried out by a team of facilitators. While the initial rollout and training
will be rapid, the following technical support and training covered by this WP will be carried
out over about 2.5 years; July, 2009 - December, 2011.
WP2 Coast Region initial test region. Implement DHIS using the existing and revised
HMIS reporting forms in all districts and regional administration in the Coast region.
Establish a first version of the data reporting forms and data sets to be included in the national
roll-out. Including the revised reproductive health and human resources data sets.
Later revisions of data reporting and data sets will be included when they are ready for
implementation. Changes in data sets and data reporting forms are easily accommodated by
the software (which is soft), but more problematic in terms of paper forms (which are
hard copied).
The first phase of this test region is planned for 6 months, until the contracts are formalised.
Thereafter the test region will be used to develop and test all intervention packages of the
overall project (another test region may be added).
The Test region will be used to test all new tools, software customisation, and understand user
needs at facility, district, hospital & regional levels. Adapt support, training & tools
accordingly, and then roll-out to other regions.
WP3 Software development and Systems Integration. Developing District basedNational data warehouse and building capacity at MOHSW. The first version of the
national data warehouse will be similar to the DHIS used in the Coast region and will be used
to receive data from all over the country as the rollout advances. Gradually additional data
sources will be included and improved functionality such as Geographical Information
Systems and web reporting will be developed.
A key issue is to integrate and include the routine data being collected at facility level and to
remove double reporting and redundant data reporting. The aim is to achieve integration and
unification of all data reporting. This work on data and indicator sets is contributing to, and is
integrated with, the revisions of data sets in WP4.
A software team including the MOHSW will be built and become in charge of the further
development and improving of the DHIS software and related technical aspects at district and
national levels. A program for training and capacity building for MOHSW staff will be
established.
Total budget for WP 1-3 and top-down approach: abut 2.5 mill USD
To be funded by the Royal Norwegian Embassy.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
4/25
4
The attached budget includes additional basic interventions in the Test Region, which is
intended to become a permanent focus-region throughout the project (WP7).
Attached minimum budget 30 months test region: 310,000 USD
National rollout: Institutional base and coordination
The three WPs in the National Rollout are naturally based at the HMIS unit, MOHSW, and
will be located in an office here and managed and coordinated from the HMIS unit. However,UDSM and the University of Oslo will be responsible for the software component (WP3) and
the capacity building at the MOHSW in this regard.
The funds are to be managed in relation to the HMIS unit, MOHSW, with one part of the
budget allocated to UDSM and the University of Oslo for the software component.
2. The Bottom-up approach;
System strengthening, information usage and capacity building;
Objectives:
Develop capacity and ensure that information is analysed and used for informed
decision making and action in all districts and regions.The aim and indicator of achievements is to achieve Level 2 and 3 of information
usage according to the TALI tool (see annex) for 80% of the districts;
o Level 2; Information is analysed, disseminated and used (graphs on the walls,routine district quarterly reports, etc.)
o Level 3; Information is (documented) used for (district) planning and theevaluation of the implementation of these plans
Institutionalise quarterly / regular data-use workshops in all districts and regions;information from the HMIS is presented, analysed, discussed in the workshop and
concrete action plans are made for the improvement of the HMIS and data quality as
well as for the improvements of the services as according to the data.Work packages
WP4 Revisions of data and indicator sets and HMIS procedures - address and includenew data needs as they emerge during the process. Revision of data and indicator sets is an
ongoing process and includes interaction with the health programs. Initially the rollout will be
based on the existing HMIS forms and already revised data sets. Revisions will be included as
they are ready for implementation.
Aim is to arrive at a situation where a national committee is responsible for the harmonisation
of the total array of reporting requirements to the health facilities. Programs and agencies
wanting to introduce new data reporting forms will then have to approach this committee in
order to get acceptance for additional requirements. Requirements when introducing new data
reporting forms will include that they are harmonised within the overall HMIS framework and
that no double reporting is accepted.
WP5 Building district and regional capacity. Establish a HMIS training scheme on analysis
and use of information for management and decision making for program and district
managers at district and regional levels in the entire country.
The training will consist of repeated formal training sessions with individual and group
assignments and support in between.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
5/25
5
WP6 System strengthening; Improving data quality, information usage and healthmanagement. This WP consists of three major set of activities;
1: Institutionalise quarterly /regular data-use workshops in all districts and regions, where data
is analysed and discussed, problems identified (both regarding HMIS and health services),
and action decided upon.
2: Institutionalise the production and dissemination of quality district and regional quarterlyand annual reports based on the HMIS data
3: establish and strengthen the district and regional information office and DHIS data
warehouse as an active and competent information resource centre that is effectively
responding to the needs of the district /region: Create District Information Towers
Approaches to enable these activities in districts and regions are to establish a team of HMIS
facilitators and a support structure covering the country. WP 5 trainers and assignments
will make up an important part of the support structure to WP5
WP7 Establish and use the Test region to develop and test tools and methodologies
including revised datasets. (This WP will be combined with WP1, which has a preliminary
status until the project is formally established).The test region will be used to develop, initially implement and test all the interventions
described in the above WPs; data sets, software, training programs, guidelines for data
workshops, quarterly and annual district reports, strengthening the district information office
and data warehouse, etc.
The test region will be run by hiring additional staff based at the region, conduct particular
investigations and have increased support as compared with the other regions.
Total budget for WP 4-7 and bottom-up approach: about 5 mill USD.
To be funded by the Dutch Embassy.
Some basic components of the test region is included in the roll-out budget to be covered bythe Norwegian Embassy; 2 staff, vehicle, support, training of district and program managers.
This was done because of uncertainty as to when funding and contracts would be available.
Once this is decided the relations between the two budgets may be reworked.
System strengthening bottom-up: Institutional base and coordination
WP 4-7 consist of distinct tasks, such as running and coordinating
Revisions of data and indicator sets and procedures for their collection, management
and use (WP4); a committee of programs and stakeholders will be established (based
on the M&E committee), responsibility, coordination and management, clearly located
to the MOHSW.
Training scheme (WP5); while being coordinated through the MOHSW, clear
responsibilities for the development of programs and the running of the courses are
given Ifakara and UDSM.
test region (WP7); need to be closely linked to the other WPs as a test-bed, but the
responsibility to run it may be delegated Ifakara
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
6/25
6
continuous system strengthening (WP6), which is a further strengthening and after
the first three years the continuation of the National rollout process, should be
managed and coordinated by the HMIS unit, MOHSW.
The funds are to be managed in relation to the HMIS unit, MOHSW, with items of the budget
allocated to Ifakara in relation to the training scheme and the Test region..
WP8: Management
& coordination
WP1: National rollout of strengthened HMIS:Rapid deployment, consolidation, strengthening
WP2 & WP7: Test RegionInitially Coast Region (WP2)
Develop & Test,HMIS revisions
WP3: Software Development
& systems Integration
District & NationalData Warehouses
WP5: Capacity development;courses, support & facilitation
Continuous education
Overview Work Packages (WP)
WP4: Revision of HMIS;Data and indicator sets,
procedures & tools
WP6:System StrengtheningImprove USE of information
District Information Tower
Figure 2: Overview work packages (WP)
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
7/25
3. Management and coordination
Facility Information Warehouse
MONITORING AND EVALUATION SECTION
Administration & Logistics
Health Systems
Research and Surveys
Unit
HMIS Unit
InformationCommunication and
Technology(ICT)
Con
Demographic
Surveillance Systems
Unit
HMIS Strengthening Program
Ph
Regional InformationWarehouse
District Information Warehouse
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
8/25
8
Description of a Monitoring and Evaluation Organization chart
Monitoring and Evaluation (M &E) is one of the five sections operating under the Directorate
of Policy and Planning. Its key function is to monitor and evaluate health sector performance.
In this regard its principal function is to supervise data collection, storage data analysis
interpretation and dissemination. Data collection is done through different systems which
are distributed in different ministries, departments and institutions. Some of the systems are
directly managed under this section however; some are run and managed in other
departments of the MoHSW. The plan is to keep such systems continue operating in their
department but coordinated under Health Management Information System (HMIS) which is
one of the units of M & E Section. Detailed explanations are provided under HMIS project.
The M & E section lead by the head of section who report to Directorate of Policy and
Planning. The technical support is provided by M & E Technical Committee which is under
SWAP Technical Committee. The committee has its members from health information
stakeholders like Development partners, National Bureau of Statistics (NBS), Retention
Insolvency Trust ship Agency (RITA), NGOs, Special Programs. M & E section is a secretariat
to this committee.
Administration and logistic: Considering the volume of operations to be managed under
this section, a post of Administrator and Logistic Officer is proposed. The administrator
would report to the head of section. Other staff to operate under this unit will be accountant,
procurement officer, personal secretary, drivers and office attendant. This unit its services
will have cover core units in the section. Job description for the new post with all staff under
him will be developed soon once the M & E structure is approved.
Information Communication Technology Unit (ICT): This unit would provide its services
to all core units in the section. It will be responsible for data management like data storage,
analysis and dissemination using up to date technologies. At the national level, the unit
would perform as Information were-house whereby different health statistics will be kept
and maintained. The unit would be responsible in maintaining hard and soft-wares for
MoHSW.
Health systems Research and survey unit: This is one of the three core units which are
responsible for operation research and surveys. Its main role is to conduct operational
research or to assist other departments to do so. At regional and district levels the unit do
train RHMTs & DHMTS on how to conduct operational research in order to get detailed
information of its locality. Also, the unit has a role to plan and conduct surveys like Service
Availability Mapping (SAM). The unit does work very closely with NBS in conductinghousehold based surveys like Tanzania Demographic and Health Survey (TDHS) Tanzania
HIV/AIDS Malaria Indicator Survey (THMIS) etc.
Demographic and surveillance Systems (DSS) Unit: The unit is responsible for community
based information from selected clusters. Systematically health workers do collect mortality
events as well as conducting population censuses in those clusters. Population censuses are
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
9/25
9
useful in establishing factors linked to cause of deaths. Information from this source is
important in absence of the strong vital registration in the country.
Health Management Information Unit: It is another core unit that is responsible for routine
data systems that are collected from all health facilities. Another responsibility is to up-date
data collection tools as well as to coordinate other sub-systems based in other departments.
More information in regard to this unit is provided under HMIS strengthening program.
Were-houses for regions, districts and health facilities: At regional, district and facility
levels there will be information were-houses to ensure health information is managed at one
point. This would be coordinating centers for sub-systems operated by special programs or
by different departments.
Phone for Health project: This is a special project which will contribute to the strengthening
of HMIS. The system would help to transfer quickly some of the HMIS data into HMIS
system using mobile phones. To start with the project is currently piloting Integrated Disease
Surveillance System in Tabora and Mwanza. Other components to be included are blood
transfusion and PMTCT information.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
10/25
10
HMIS Consortium Team
HMIS Strengthening Program
Assist. Program
Manager
(Reproductive &
Child Health
Statistics)
MODULE 1
Assist. Program
Manager
(Morbidity &
Mortality Statistics)
MDULE 2
Assist. Program
Manager
(Health Systems
Support Statistics)
MDULE 3
Assist. Program
Manager
(Health Related
Statistics)
MDULE 4
- Expanded ProgramFor Immunization(EPI)
- Family Planning (FP)- Safe MotherhoodInitiatives (SMI)
- IntegratedManagementof ChildhoodInitiative (IMCI)
- PMTCT- School HealthProgram
- Nutritional and ChildGrowth
- Outpatient &Inpatient
- NACP- TB & Leprosy- NMCP- IDSSR
- Dental Health- Mental Health- Neglected TropicalDiseases
- Diagnostic Services
- Human Resource- Financial Statistics- Logistics & Supplies- Equipment- Health Facility
Inventories
- Social Welfare Statistics- Environmental and
Sanitation Statistics- Tanzania Food &Drug
Authority- Tanzania Food
Nutritional Center
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
11/25
11
The consortium team behind the HMIS Strengthening program consists of the following
partners:
The Ministry of Health and Social Welfare (MOHSW)
Role: MOHSW is the owner of the HMIS Program and is responsible for its overall
management, financial management and coordination. The HMIS unit within the Monitoring
and Evaluation section in the Directorate of Policy and Planning of the MOHSW is the
operational base of the HMIS Program. The MOHSW regional and district offices are the
operational bases for the HMIS Program at these levels.
A financial entity will be put in place in order to manage the finances as in accordance with
the specifications for reporting and management given by the donors.
Ifakara Health Research Institute (IHRI)
Role: responsible for the health professional components of the HMIS Program, including
epidemiology, M&E, using information for health action and operational health research.
Furthermore, IHRCD is responsible for the development of training manuals and guidelinesand for assisting in the running of the training scheme (WP5) and the test region (WP7).
IHRD is also taking part in the System Strengthening (WP6) and overall management.
University of Dar es Salaam (UDSM)
Role: UDSM is responsible for the Information Technology, software and implementation
components of the HMIS Program (WP1, WP2, WP3) as well as for the training programs in
WP5. The training program will use the NORAD funded Masters in Health Informatics as an
institutional base. The Muhimbili University of Health and Allied Sciences (MUHAS) is a
partner in this Masters Program.
University of Oslo (UiO)Role: UiO represents the international expertise and advisory role on HMIS/HIS and Open
Source software in the HMIS Program. UiO will work closely with UDSM and the HMIS unit
on the software, implementation and system strengthening issues.
MOHSW the operational base and responsibilities
The MOHSW is the owner of the HMIS and the HMIS unit of the Health Information and
Research (HIR) section of the MOHSW is the operational base of the HMIS Program. In order
to render the HMIS sustainable, the HMIS Program will focus on developing capacity within
the MOHSW in all aspects of the management of the HMIS and data analysis and
dissemination. In order for this to be possible, it is the responsibility of the MOHSW to
prioritise the HMIS and give it high level support, which will entail the allocation of
sufficient resources. For the HMIS Program to succeed the following actions are needed:
Health Information and Research section & HMIS unit need to be strengthened in theareas of database management and epidemiology
Regions and districts need information officers responsible for the HMIS and datareporting, analysis and dissemination across programs and staff responsible for thedatabase. The district information officer needs to be member of the DHMT
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
12/25
12
All facilities need identified person responsible for the HMIS.
The identification and allocation of HMIS staff is the responsibility of the MOHSW. Trainingand supporting these HMIS staff is the responsibility of the HMIS Program.
Project management and reporting overview
The HMIS Program is managed by a joint management team consisting of all consortium
members and is headed by a program manager from the HMIS unit. The program team, withthe program manager as responsible, will report on the progress of the HMIS Program every6 month. The responsibility for tasks and deliverables related to the various Work Packages,such as particular training manuals, software or implementation components, are distributedbetween the partners and given to individuals, who are then responsible for reportingprogress to the joint management team.
Financial Management
The MOHSW is responsible for establishing a financial entity able to manage the budget andthe funds, and report on expenditures as according to the requirements of the donors.
Particular budget items related to tasks and responsibility are to be allocated to particularpartners and consortium members who will then report on the utilisation of these funds asaccording to the requirements to the financial entity at the MOHSW and on work done anddeliverables achieved to the joint management team.
Implementing the top-down approach; National rollout and software component
Specification of the operational plan for the National rollout (WP1) and the building of theNational, District and Regional data warehouses (WP3).
This specification is following the attached budget.
4. Specification of the top-down National HMIS rollout
The rollout process will start with a one week training session for MOHSW and nationalhealth program staff.
The top-down rollout consists of 3 interlinked work packages;
WP1; National rollout
WP2; Coast region as initial test region. Budgeted separately.
WP3; Software development and systems integration, building the data warehouses
These three WPs are directly interlinked as follows; the data from the national rollout will
become the content of the data warehouse, and the data warehouse is the software applicationthat will be implemented during the rollout. The Coast region is where the rollout strategy,
tools and data sets are initially tested.
The team that will carry out these components is composed as follows:
6 MOHSW staff,
6 DHIS /HMIS facilitators, from UDSM and the HISP group
International and regional consultants
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
13/25
13
4.1. The Coast region (WP2)
In collaboration with JICA and funded by JICA and the Norwegian Embassy, the team
is
identifying the HMIS data reporting forms and other data sets that are to be included
the initial phase
customizing the DHIS database according to these requirements; data entry forms and
data analysis and reporting functionality
testing out software and the technical configuration to be used in the districts, regions
and national level; which is based on the Linux operating system and which enable the
data to be accessed by all computers in the district offices via wifi.
Training users in technical aspects as well as in HMIS management and developing
training guidelines
The output of the Coast region work Package, as well as the initial output of the software
work package to be explained later, will be the initial HMIS package to be rolled out
nationally.
4.2. The National HMIS rollout and consolidation (WP1)
It involves getting HMIS working, based on existing registers and books, with monthly return,
and use DHIS as tool to collate, analyse and report. Train at least 2 people in every district
& region, plus follow-up visits to sites.
The national rollout and following consolidation will be carried out over two and a half years
following the initial 6 months of testing in the Coast Region. It will consist of 2 formaltraining sessions and three support missions in each region which will cover all districts. The
first initial deployment will be carried out by a rapid training scheme, where (if computers
may be purchased), district and regional information staff do their training on the new
computers with the software installed, and bring them with them back to the districts.
Training will be followed by a first support mission to each region and district. Support
missions to the districts will be carried out together with the regional information officer, with
the aim to enable him/her to carry out the first level of system support as an institutional new
practice. Budget (travel) will later be allocated for such support. During the first 6-8 months,
the first basic coverage of the country will be completed, and during the following 2 years the
district HMIS and the reporting structure from the districts to the MOHSW will beconsolidated.
The objective is to achieve Level 1 of Information usage for 80% of facilities and 90% of the
districts by the end of this period.
During the two and a half years basic training and support will be carried out as follows:
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
14/25
14
For each Region:
Formal training. Two sessions of one week (5 full days of) training will be carried out in all
regions, first the initial training at the start of the implementation. 7-10 months later a second
one full week training session will be conducted.
District support and HMIS facilitation missions. 3 interventions of an average of 20 days
will be carried out in all districts in each region, by a team of 3 from MOHSW /HISP and 1
from the regional office (information officer). On the job training, facilitation and support will
be carried out. In order to save travel cost, the first two of these interventions per region are
sought carried out after the formal training sessions.
After the first 30 months further strengthening of the HMIS
After 30 months this rapid rollout and consolidation process will merge with the more in-
depth regional (bottom-up) approaches; training of health managers in WP5 (capacity
building) and the strengthening of the district HMIS in WP6 (system strengthening). WP6,
System strengthening and use of information, will represent the continuation of the on-site
support and facilitation in the rollout WP, but with increased sophistication in terms of
information use.
The data-use workshops to be organized in WP6 will be of particular importance as a way to
institutionalize the use of data for management, and thus the HMIS.
4.3. Software and system integration. Strengthening the MOHSW HMIS unit and
building the integrated district and national data warehouses
4.3.1 General training of MOHSW staff
Develop Software team
A dedicated software team is being built consisting of
4 MOHSW staff,
4 UDSM /HISP staff
This team is partly overlapping with the technical rollout team described above
The software teams main tasks are to develop the national and district data warehouses and to
customize DHIS and additional software tools as according to the needs of the MOHSW,Furthermore, to integrate the data warehouse with other data sources by extracting the needed
data. GIS functionality will be developed as part of the collaboration with WHO on the
OpenHealth project.
The software team will work with, and be part of, the global network of DHIS developers and
work closely with the WHO and HMN on the developing of appropriate Open Source tools.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
15/25
15
This work has already started as three members of the software team (one of them form the
MOHSW) took part in a two weeks DHIS workshop in New Delhi, India, in March.
Regional and international experts will assist the MOHSW in the development of the data
warehouse, at national, regional and district levels, as well as in the rollout of the system.
Capacity building MOHSW; data management, DHIS data warehouse and open sourcetechnologies
Capacity will be developed in the MOHSW through the activities of the software team
described above but also through the building of a solid base for managing the overall
National HMIS.
All staff in the HMIS and ICT units will be part of this effort.
As the building of the National data warehouse and the National HMIS will take place in the
HMIS unit, capacity building will be part of every step of the process.
In order to achieve capacity development in the MOHSW, the project needs to recruit
additional regular MOHSW staff, train existing staff, allocate skilled project staff to the HIR
section and engage them fully in the development of the system and its rollout.
Based at the UDSM and the NOMA Masters Programme, which is running courses on these
issues, the project will engage in a wider national capacity development in this area, as well as
targeting individual HMIS and ICT staff for training (several are already included).
Training of regional and zonal HMIS staff will also be part of this effort.
4.3.2. Software development and systems integration
The software development and integration work package will be a continuous activity and will
be handled by the UDSM-MOHSW software team. The team will be responsible to;
Design database and software for rapid rollout based on existing HMIS.
Update software and data warehouse design based on revised tools.
Integrate DHIS with other related applications (e.g. LGMD)
Revise database & software once new registers & tools finalised
The customization and further development of the DHIS software and its integration with the
WHO OpenHealth application for web based Geographical Information System (GIS), is
specified in a separate document. The DHIS-OpenHealth development is in cooperation with
WHO and Health Metrics Network. The WHO-OpenHealth is the new web-based application
developed by WHO to replace the HealthMapper (see figure).
The DHIS-OpenHealth is a scalable district and web-based data warehouse, which may work
as a stand alone application without internet connection in a district, or as a web based
national repository at MOHSW.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
16/25
16
Integration with other computer based application such as Electronic Patient Record systems
in hospitals and other facilities is handled through a standardised data interchange platform.
This, of course, is depending on the use of open standards also by other computer
applications, which will be ensured through the strategic planning process. and other
computerised data sources; establishing web-based data warehouse, electronic reporting etc.
The basic principle underlying the various software applications involved in this workpackage is that first a first customised, stable and useful application is implemented, and
thereafter it is continuously further developed and integrated with the patient record systems
such as the Care2X, and other systems in place.
OpenHealth-
DHIS SuiteMultiple Views (e.g. M&E,
surveillance) free combination of
components(e.g. only data dictionary or
web presentation)
Data
Quality &Validation
Data
Dictionary
Data
processing
DHIS
DHIS-Integrated
Data repository
GIS
Pivot
Tables Charts
OpenHealthWeb
Presentationplatform
Data Exchange and Integration Platform
Data Exchange and Integration Platform
Data
Entry
Other systems;e.g. Patient
recordshospitals, DHS,vital registration
Figure: The DHIS-OpenHealth data repository. The integration of DHIS and OpenHealth is
part of a global project managed by WHO.
Budget for top-down national HMIS rollout specified in attached Excel
National rollout: 2,043,000 USD
International technical support 280,000 USDTotal 2,323,000 USD
5. Specification of the Bottom-up approach
- System strengthening, information usage and capacity building
The bottom-up approach consists of 3 interlinked work packages:
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
17/25
17
WP4; Revisions of data and indicator sets and HMIS procedures (continuous, but with initial
baseline revision)
WP5; Building district and regional capacity training scheme
WP6; System strengthening; Improving data quality, information usage and health
management
WP7; Establish and use the Test region to develop and test tools, methodologies and revisions
Work Package 4; Revisions of data and indicator sets and HMIS
procedures (continuous, but with initial baseline revision)
Background
An indicator set has existed in Tanzania since the 1990s, but this is now seen as being out of
date, fragmented and inadequate and needs to be reviewed in conjunction with all relevant
stakeholders. Numerous additional program specific data collection tools and routines are in
use. There is a need for international best practice standards to be applied to indicatorselection as well as to the harmonization of the routine data collection system.
There is a perceived need for harmonized set of indicators and corresponding data sets and
data collection tools and routines, clearly acknowledged by MoH&SW top management,
M&E chapter of HSSP III, donors and programs.
Objectives
First phase (first 2 months)
Review existing data collection tools and indicators being used by MOHSW and the
relevant programs
Identify key performance indicators for the health sector in Tanzania
Identify data sets and data collection tools and HMIS procedures to be part of the
initial phase. Make sure indicator numerator and denominator, with clear definitions of
all components, are covered (when possible)
Identify sources and frequency of all data and indicators
Hospitals; same procedure for hospitals. The first phase approach is to assess current
forms and effectively harmonize and use what is there.
Define and establish the data sets that are going to be part of the first rollout:
o The current book 2, together with data sets from
o Vertical programs: HIV, and subsequently EPI, Leprosy/TB, Malaria.
o Handle the overlaps: same data collected by several programs and data
collection tools: These data will as a start be harmonized within the DHIS
database (while one single data item might be collected in many forms, such as
e.g. First ANC visit, it will only be captured and registered once in the
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
18/25
18
database /DHIS). During phase 2, they will also be harmonized in the data
collection tools.
Second phase (first 18 months timeline depending on time it takes to physically print,
distribute and replace book 2)
Replace current book 2: Harmonize all relevant data collection tools and routines to
be used at facility and district levels, and design, produce and distribute new forms
that will be the primary monthly manual return from facility to district.
Given the slower process to print and replace existing paper based data collection
tools, this process will go on beyond the initial phase.
Establish a permanent national committee to oversee ongoing revisions of data and
indicator sets.
The aim is to arrive at a situation where programs needing more data and reports will
have to present their new data demands for this national committee and arrive at anagreement on whether the new demands are justified, whether the needed data are
already collected, how, eventually, the new data needs may be incorporated in the
existing routine data collection system, or whether new data collection tools, provided
they are not overlapping any existing tool, are needed. This measure is to stop the
process of fragmentation.
Special focus on hospitals. Harmonize all relevant data collection tools, data sets and
indicator sets.
Scope of Work
Review existing data collection tools, indicator set and data definitions Conduct consultation meeting with all key HIS stakeholders and their implementation
teams
o MOHSW Policy makers, cooperating partners
o Relevant vertical program managers,
o HMIS managers, District, provincial managers
Develop draft national indicator set with defined numerator and denominator and
source, in accordance with international norms and HMN framework
Circulate indicators with numerator, denominator, data source, rationale, use, related
indicators Organize and facilitate consensus meeting on indicators with each program
Design, print and distribute new paper forms which are shared between MOHSW and
all relevant health programs. There will be no duplication and overlapping data
collection (paper) forms. HMIS, RCH, EPI, etc, will all be based on a shared set of
forms the new book 2.
This new book may be conceptualized as a set of forms based on programs and
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
19/25
19
services areas; a paper sheet for each of the following (or several combined in one
sheet), e.g. OPD/morbidity, EPI, RCH, Leprosy/TB, HIV, PMTCT, Malaria.
A key design objective for the new, inclusive and extended book 2, which is a
compilation of program specific official forms, is to design and establish a way
whereby new data requirements in the future will be captured by official additions to
book 2, by e.g. replacing the HIV sheet when this is being revised, etc.THIS IS IMPORTANT. The inability to continuously being able to update book 2
over time is the root cause to many of the current problems of fragmentation.
Continuously incorporate revised forms and definitions of data, data forms and
indicators into DHIS database /data warehouse
Revise the entire package of paper based data registration tools used at the facility
level; design, print, distribute the new tools. IMPORTANT; design a strategy for their
continuous update and revision over time, i.e. design for addendums according to the
future updates of book 2.
Devise a mechanism to revise data and indicator sets annually (i.e. phase 2)Hospitals:
Similar scope of work, but in a different context. Many hospitals are introducing
computer based systems. The program needs to take this into account and plan for a
gradual integration of these systems based on electronic patient records.
The scope of work includes
o the aggregated data flows within the hospitals (wards), to be managed within
DHIS at each hospital (gradually)
o reporting from all hospitals to the HMIS/DHIS
o integration of the electronic patient based systems being implemented in the
hospitals with the system for aggregated statistical data reporting; HMIS and
DHIS
Establish a sub-group within the program for the revision of the hospital HMIS
Develop hospital indicators and data sets
Develop revised reporting forms for hospitals
Incorporate revisions in the DHIS
Implement DHIS in selected hospitals
Plan for implementation of computerized HMIS and DHIS at all 200 hospitals. Make
this part of the strategy to integrate electronic patient records with the DHIS and
HMIS
Develop a strategic plan for the Hospital Information Systems in Tanzania, where the
process of introducing electronic patient based record systems in hospitals are
coordinated and integrated within the wider M&E framework as according to the
HMN technical framework
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
20/25
20
Work
To establish a national team responsible for co-ordination, consultation, and finalizing new
registers, tools, indicators. Each member of the consortium (MoHSW, Ifakara, UDSM, UiO)
will assign a staff member full time for this national team
Phase 1 the first 2 months; establishing the initial data and indicator setsThis task, in Dar es Salaam, will start together with the initial phase in the test region and go
on for about 2 months.
During the two months, one staff (equivalent) from MOHSW, Ifakara, UDSM and UiO will
each work 6 weeks; 3X30 days= 90 days @ 100.000 = 9.000.000 Tshs
Phase 2 revision and replacements of book 2 and other needed tools. Month 7 - 12
The same/equivalent task force will continue and work on the more radical revision of the
paper based tools used in all facilities. This work will start 4 months after the initial data sets
are implemented (in order to gain some experience), go on for 6 months, with slightly less
intensively; 250 days = 25.000.000.
Important will be to be realistic in designing the additional tools and books supporting book
2; paper based books/registers/forms are difficult to replace once printed. They need to
adhere to certain flexibility, i.e. include blank columns.
Printing and distribution need to be budgeted separately.
The timeframe for the total replacement of book 2 and other paper based tools will depend
on logistics.
Hospitals Phase 1 and 2
A task force from the same partners and of the same size and intensity as for Phase 2 (250
days, 25.0000.000) will carry out this work over the first year of the project. While the first
phase, reporting from district hospitals will be part of Phase 1, referral hospitals need
additional attention. Plans for further computerization and the electronic integration of
patient record systems such as Care2X, and the collaboration with projects of this type, will
make up an important part of this work.
The task force will also develop a strategic plan and framework for the development of the
overall Hospital information system in Tanzania, and its integration within the M&E
framework, beyond the initial 18 months.
Printing and distribution need to be budgeted separately.
Budget: 250 days, 25.0000.000 Tsh
For all phases above: UiO is covered through the international consultancy budget.
WP5; Building district and regional capacity training scheme
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
21/25
21
Objectives:
Run courses and develop capacity in HMIS and data use at
Regional and national levels (training of trainers of district staff)
District level staff (training of trainers of facility level staff)
Facility level staff
Develop training materials and guidelines for the above training scheme
This capacity development scheme will have to be carried out in stages starting with the
regional and national levels, and about 3 months later, also with the district level staff in the
test region(s)
The first objective and stage for this work package is to establish a training program for
the training of trainers; regional and national staff.
Three staff from each region, including the HMIS focal person, totalling 63, and about 12
from national and zonal level, totalling about 75. Four training sessions of 2 weeks will beconducted over 2 years. The topics of the training will address HMIS and management,
analysis and use of information for health management and health services delivery.
Assignments to be completed between the training sessions will include; use HMIS and other
information for situation analysis, planning and target setting, as well as the organisation of
data use workshops at district and regional (i.e. for all districts in the region) levels.
The training will be conducted using the zonal training centres where appropriate.
The second objective is to devolve an adapted part of this training program to the district
level, starting in the test region(s).
Three times one week training over about 1.5-2 years will be carried out at the regional level
for 3-4 staff from each district. With about 25 persons per training session, some regions may
be combined.
The training will include the same issues as for the regional staff, but with an additional
emphasise on facility supervision and the training of facility level staff. Assignments to be
completed between training sessions will include, as for the regional level staff; use HMIS
and other information for situation analysis, planning and target setting, as well as the
organisation of data use workshops at district level for district and facility staff.
Regional level staff will be responsible for conducting the training, but with support from
national level, in particular during the first session.
The third objective is to devolve the training scheme to the facility level. The test region(s)
will be used to develop cost effective methods to train facility level staff (data use workshops
may be the primary methodology, linked to supervision an additional one). Details will be
developed later.
For long term HMIS sustainability, an HMIS module will be designed and integrated into pre-
service training. In addition, a diploma in Health Informatics programme will be established
for HMIS cadre.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
22/25
22
Development of training materials
The regional training program:
One staff equivalent from each of the consortium members; MOHSW, Ifakara, UDSM and
UiO, will each work 4 weeks up to and including the first 2 weeks training session forregional and national staff.
The district training program
The team of about 4 persons develops a down-scaled version of the regional training program
for the district level. This work will be conducted in the test region(s) and will include the
practical development of a methodology and guidelines for data use workshops both at the
regional level (for the districts) and at the district level (for district managers and facility
staff).
The practical development of data workshop methodology and guidelines will also feed into
the regional training program.Four staff equivalents will work 8 weeks on this task.
Annex Assessing levels of information usage
Table 1: Criteria for Assessing Levels of Information Use General, All Levels
Level Broad description Detailed description of criteria
Level 1 The information system is working
according to its specification: timely
and accurate data is submitted to the
district; district manages data indatabase, reports to region and
feedback to facility. Similar at
regional and central levels.
Clearly defined Essential datasets for all
compulsory reporting have been defined?
Has an information manager been identified?
Have all the expected routine reports beensubmitted?
Have feedback reports been issued?
User friendly guideline including information
handling at that level is available?
Level 2 Summary reports of data produced
and disseminated regularly
Indicators are being assessed against
performance / targets on a regular
basis.
Are summary reports available
Are indicators graphed?
Are indicators discussed in management
meetings?
Level 3 Indicators and information are used
by managers to inform their action
plans.
Indicators and information used to
document performance in all written
reports
Are indicators interpreted and understood?
Are problems identified based on available
information?
Have any problems been addressed, and can
these steps be documented, and an improvement
shown using indicators and data?
Table 2: Criteria for Assessing Levels of Information Use for District level
Criteria to be met for District Level 1:
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
23/25
23
Criteria 1.1:
District has clearly defined Datasets for which they are responsible to collect, manage and report
data.
Criteria 1.2:
Information handling (data collection, management and reporting), including all programs, is
coordinated and integrated. AND The district has identified an information officer responsible
for information management.
Criteria 1.3:
All data for which the district is responsible to report is captured and managed in the district
database
Criteria 1.4:
Up-to-date and user friendly Guideline for collecting, managing, reporting and using
information in the district is available (encompassing all data requirements, such as from
different health programs). A detailed Guideline for managing the district database software is
also available.
Criteria 1.5:
The district has staff with sufficient skills responsible for managing the computer based district
database.
Criteria 1.6:
The district database contains 90% of the expected reports from the facilities for the last year.
75% of the reports from the facilities are received within the period set for the submission of
reports (for monthly reports; within the 15th
the following month).
Criteria 1.7:
The district has produced and submitted feedback reports to the facilities within the defined
time frames.
Criteria 1.8:
The district has a plan for capacity development related to HMIS (at both district and facility
levels) and the district database
Criteria to be met for District Level 2:
Criteria 2.1:
District monthly/quarterly reports: Summary report on data collected (from all programs)
including key indicators compiled and made available for staff and managers at least each
quarter
Criteria 2.1:
Feedback reports to the facilities (including a summary of data reported and key indicators) and
other information from the HMIS actively used in the supervision of the facilities
Criteria 2.2:
At least 8 indicators (and at least one for each program) are graphed for the year and up to date
for the year and up to last reported month.
Criteria 2.3:
At least 1 meeting each quarter designated to evaluate the data elements/ indicators. District
meetings with facility representatives routinely using indicators and data from the HMIS
assessing and discussing performance
Criteria to be met for District Level 3:
Criteria 3.1:
At least four problems have been identified and addressed through an action plan, with data and
indicators specified for assessing achievements towards targets.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
24/25
24
Criteria 3.2:
The effect of the action has been monitored using indicators & information from the HMIS and
can be shown.
Criteria 3.3:
The actions and achievements are documented using data and indicators in a written report to
the district management team and/or in the annual report.
-
8/6/2019 Strengthen HMIS in Tanzania Operation Plan
25/25
Table 3: Criteria for Assessing Levels of Information Use at Facility level
Criteria to be met for Facility Level 1:
Criteria 1.1:
Facility has an Essential Dataset defined; a clear set of data to be collected, compiled and reported.
AND; the needed and specified tools (e.g. registers, forms) are in sufficient stock
Criteria 1.2:
Up-to-date and user friendly Guideline for collecting, managing, reporting and usinginformation in the facility is available (encompassing all data requirements, such as from different
health programs).
Criteria 1.3:
The facility has identified an information officer responsible for information management.
Criteria 1.4:
The facility has submitted all (100%) of the expected reports in the last year within the period set
for the submission of reports.
Criteria 1.5:
The facility information manager has validated 80% of the feedback reports from the district
(checked, signed, and sent back to district if any errors were noted).
Criteria to be met for Facility Level 2:
Criteria 2.1:
Summary report on data collected and reported (from all programs) compiled and made available
for staff at least each quarter
Criteria 2.2:
At least 4 indicators are graphed for the year and up to date for the year and up to last reported
month.
Criteria 2.3:
At least 1 meeting each quarter (assessed over the last two quarters) to evaluate the data elements/
indicators (i.e. at least one meeting each quarter)
Criteria to be met for Facility Level 3:
Criteria 3.1:
At least one problem has been identified and addressed through an action plan, with data and
indicators specified for assessing achievements towards targets.
Criteria 3.2:
The effect of the action has been monitored using indicators & information from the HMIS and
can be shown.
Criteria 3.3:
The actions and achievements are documented using data and indicators in a written report to the
district, the facility committee, or the annual report.