Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013, in Press) Wei Zheng Department of Computer Science, Xiamen University, Xiamen, China Rizos Sakellariou SchoolofComputerScience,TheUniversityofManchester,UK

Upload: sabina-cameron

Post on 02-Jan-2016

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Stochastic DAG Scheduling using

Monte Carlo ApproachHeterogeneous Computing Workshop (at IPDPS) 2012

Extended version: Elsevier JPDC (accepted July 2013, in Press)

Wei ZhengDepartment of Computer Science, Xiamen University, Xiamen, China

Rizos SakellariouSchoolofComputerScience,TheUniversityofManchester,UK

Page 2: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Previous Presentation (9/06/13)

• Research Area: Scheduling workflows under heterogeneous environment with variable performance.

DAG Scheduling

Static (full-ahead) Just In time Dynamic Rescheduling (runtime)

Page 3: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

This Presentation

DAG Scheduling

Static (full-ahead) Just In time Dynamic Rescheduling (runtime)

Page 4: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Introduction

• General DAG Scheduling assumption:• Estimated Execution time for each task is known in advance.

• Several techniques of estimation: e.g. average over several runs• Similarly, estimated data transfer time is known in advance.

• A study* has shown, there might be significant deviations in observed performance in Grids.• To address this deviations, Two approaches are prevalent• Just-In-Time (high overhead)• RunTime (static schedule + runtime changes) (hypothesis**: might waste

resources and increase makespan if static schedule is not very good) • * A. Lastovetsky, J. Twamley, Towards a realistic performance model for networks of heterogeneous computers, in:M.Ng,A.Doncescu,L.Yang,T.Leng (Eds.), High

Performance Computational Science and Engineering, in: IFIP InternationalFederationforInformationProcessing,vol.172,Springer,Boston, 2005,pp.39–57. • ** R.Sakellariou,H.Zhao,A low-cost rescheduling policy for efficient mapping of workflows on grid systems, Sci. Program. 12(4) (2004) 253–262

Page 5: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Problem Addressed

• Generating a better (minimize makespan) “Static” schedule based on the stochastic model of the variations in the performance (execution time) of individual tasks in the graph.

Page 6: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Background and Related Work

• Heterogeneous Earliest Finish Time heuristic (discussed in the previous presentation)• List based scheduling.• Prioritize tasks based on the “bLevel” (essentially, tasks on the critical path get

higher priority)

• Once task is chosen, map it to “best” available resource.

bLevel(i) = wi + max j Succ(i)wi→j +bLevel(j)∈

Page 7: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Problem Description

• G = (N, E) -> DAG with one entry, one exit node.• R -> set of heterogeneous resources• Et

i,p -> Random variable for execution time

• Assumption: Network bandwidth is constant.• M -> Makespan = finish time of exit node.

Goal: Find schedule Ω to minimize makespan (assign N to R, no overlap, no preemption, no migration)

Page 8: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Methodology

• Assumption: Analytical methods that solve the probabilistic optimization problem are too expensive.• Use Monte Carlo Sampling (MCS) method.

• Define a space comprising possible input values• IG =ETi,p :i N,p R.∈ ∈

• Take an independent sample randomly from the space• PG =fsmp(IG) =ti,p :i N,p R∈ ∈

• Perform deterministic computation using the sample input (store the result)• ΩG =Static_SchedulingHEFT(G,PG)

• Repeat 2 and 3 till some exit condition (no. of repetitions)• Aggregate the stored results of the individual computations into the final result.

Page 9: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

MCS Based SchedulingComplexity:• Depends on the deterministic

scheduling algorithm• For HEFT it is O(v + e * r) = O(e*r)• First loop: O(e*r*m)• Second loop: O(e * n * k)• Total = O(e*r*m + e*n*k)

Page 10: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Example

Page 11: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Example

10,000 iterations - production phase (Gaussian Distribution)

200 iterations - selection phase

20% reduction in makespan

Absolute increase in algorithm time: 1.2s

Page 12: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Evaluation

• Graphs

Page 13: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Threshold Calculation

Page 14: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Convergence (no. of repetitions)

Page 15: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Convergence

Page 16: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Makespan performance evaluation

• Static HEFT (baseline) with Mean ET values• Autopsy – Static HEFT With known ET values• MCS - Static• ReStatic • ReMCS

• Graph Generation (random generator of given type)• Task Execution Time for different runs

• Select “Mean” for each task.• Use a probability distribution to select actual execution time. The variation is bounded by Quality

of Estimation (QoE) (0<QoE<1)

Page 17: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Makespan performance evaluation

Page 18: Stochastic DAG Scheduling using Monte Carlo Approach Heterogeneous Computing Workshop (at IPDPS) 2012 Extended version: Elsevier JPDC (accepted July 2013,

Summary

• It is possible to obtain a good full-ahead static schedule that performs well under prediction inaccuracy, without too much overhead.• MCS, which has a more robust procedure for selecting an initial

schedule, generally results in better performance when rescheduling is applied