Greater Mekong Subregion Economic Cooperation Program14th Meeting of the GMS Subregional Transport Forum
Country Report on Priority Transport
Projects between 2008 and 2012
The Peoples Republic of China
Nanning, Guangxi Zhuang Autonomous Region, thePeoples Republic of China
2-3 December 2010
Projects included in the Vientiane Plan of Action
. Roads
. Ports/Airports
The views expressed in this paper/presentation are the views of the author and do not necessarily reflect the views or
policies of the Asian Development Bank (ADB), or its Board of Governors, or the governments they represent. ADB does
not guarantee the accuracy of the data included in this paper and accepts no responsibility for any consequence of their
use. Terminology used may not necessarily be consistent with ADB official terms.
-
8/8/2019 STF-14 Appendix 5B PRC
2/13
2
. Roads
1North-South Economic CorridorInternational Mekong River Bridge
MOU among PRC, Lao PDR and Thailand
A 50-50 cost sharing between PRC and Thailand
Detailed design Completed in June 2008
A grant from Thailand of about $1.2M
ADB assisting in procurement of process for civil
works
Commenced in February 2010 & expected to be
completed by 2012
-
8/8/2019 STF-14 Appendix 5B PRC
3/13
3
2. Western Yunnan Roads
Development Project II (longling-ruili)
Longling
Ruili
Estimated cost: 1,426 million USD
Included in the ADB RCOBP for GMS (for aloan of $ 250 M under the 2010 pipeline) and
COBP for PRCNegotiating meeting on ADB loan ended&Agreement on loan expected to sign in April,2011
Feasibility study approved in Oct. 2010, and theconstruction will commence by the end of 2010.
-
8/8/2019 STF-14 Appendix 5B PRC
4/13
4
3Dali-Lijiang Road Upgrading
Estimated cost: 2,400 million USD
Financed by PRC government
Commenced by the end of 2009
4 years period
15% investment finished by Oct 2010
Lijiang
Dali
4Baise-Debao-Longbang Expressway
Estimated cost: 1,016 million USD
Financed by PRC government
To be implemented by two sections: Baise-Debao-
Jingxi section started on September 25, 2009; Jingxito Longbang to be started in 2010
-
8/8/2019 STF-14 Appendix 5B PRC
5/13
5
5Hechi-Baise Expressway
Estimated cost: 2,012 million USDFinanced by PRC government.
Feasibility study report completed
To be started in 2010
Hechi
Baise
6Preparation for signing the tripartiteMOU among PRC, Lao PDR and Thailand
for the exchange of traffic rights along the
north-south economic corridor
-
8/8/2019 STF-14 Appendix 5B PRC
6/13
6
MOU Discussion held in August 2010 among
PRC, Lao PDR and Thailand for the exchangeof traffic rights along the North-South
Economic Corridor with the assistance of ADB
The MOU expected to be signed in 2011
7Preparation for convening of the Third JointMeeting of GMS National Facilitation Transport
Committee
The Third Joint Meeting of GMS National Facilitation
Transport Committee held in Vientiane on June 17,
2010
-
8/8/2019 STF-14 Appendix 5B PRC
7/13
7
8
Fangcheng
Dongxing (54km)
To be completed by 2013
To be financed by PRC government
Estimated cost: 376.5 million USD
Preliminary design approved
Construction started in April, 2010
9Nanning-Baise (188 km)
Started in June 2005 and completed in Dec. 2007
between Greater Nanning (Tanlou City) and Baise City
Assisted by ADB under the Guangxi Roads
Development II project (Loan No. 2094
Baise
Nanning
-
8/8/2019 STF-14 Appendix 5B PRC
8/13
8
. Ports/Airports
1Mengzi Airport Upgrading
Estimated cost: 40.3 million USD
Project application submitted to State Council
for approval
Project Assessment in progress
-
8/8/2019 STF-14 Appendix 5B PRC
9/13
9
2
Nanning InternationalAirport Improvement
Estimated cost: 126 million USD
Financed by the PRC government
Upgrading project for flight area completed inSeptember, 2009 with budgetary estimate of 94million USD
Project proposal for the new main airportbuilding and its necessary accessories approvedin August, 2010
3Guilin International AirportImprovement
Estimated cost: 90 million USD
Financed by the PRC government.
Upgrading project for A380 type airplane started in September, 2008
56% investment completed
Upgrading project for the new main building to be completed in 2020
-
8/8/2019 STF-14 Appendix 5B PRC
10/13
10
4Improvement and Maintenance ofNavigation Channels along the
Lancang-Mekong River
Myanmar
Yunnan
VietnamLaos
Thailand
Cambodia
Quadripartite Agreement on Commercial
Navigation signed by PRC, Lao PDR, Myanmar
and Thailand in April 2000
-
8/8/2019 STF-14 Appendix 5B PRC
11/13
11
the Upper MeKong River Navigation Channel
Improvement Project with a grant of $5M by
PRC government
Needing financial assistance for further improvement
and maintenance
At the 13th GMS MinistersMeeting held in Dali, China
proposed that ADB work out a strategic planning for
water transport.
ADB requested to expedite this process
-
8/8/2019 STF-14 Appendix 5B PRC
12/13
12
5
Technical Investigation of RedRiver for Subregional Transport
A technical investigation in 2011 proposed by
concerned provinces in PRC (Yunnan province)
and VietnamLao Cai Province
6The second bridge on the RedRiver beween Hekou and Lao Cai
Completed in Sept.2009 and Co-financed by
PRC and Vietnam
-
8/8/2019 STF-14 Appendix 5B PRC
13/13
13
7Preparation of CBTA implementationManuals for the pilot border crossing of
Mohan to Boten
MOU on the initial implementation of CBTA at Mohan-
Boten signed by PRC and Lao PDR in September 9, 2009ADB requested to assist PRC and Lao PDR to draft aCBTA implementation manual for the border crossing ofMohan-Boten