step by step chp: the pitfalls to avoid between planning and design

34
www.energ-group.com/chp Step by step CHP: The pialls to avoid between planning and design

Upload: energplc

Post on 25-Jun-2015

312 views

Category:

Business


0 download

DESCRIPTION

Discover how you can overcome some of the pitfalls associated with planning cogeneration projects

TRANSCRIPT

Page 1: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

www.energ-group.com/chp

Step by step CHP:The pitfalls to avoid between planning and design

Page 2: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Cogeneration can save money, conserve energy, and reduce emissions - but

specifying the right unit for the site in question has its pitfalls.

Find out how to avoid these common mistakes when taking your CHP project from planning

through to design.

Page 3: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Risks to the viability of a CHP project

Page 4: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Poor site energy efficiency

Mis-sizing plant Site-specific issues

Risks to the viability of a CHP project

Page 5: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Poor site energy efficiency

Mis-sizing plant

The wrong choice of fuel

Site-specific issues

The finance model

Risks to the viability of a CHP project

Page 6: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Poor site energy efficiency

The wrong choice of fuel

None of these problems, however, are insurmountable.

Site-specific issues

Risks to the viability of a CHP project

Mis-sizing plant

The finance model

Page 7: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Greater and longer term benefits are available if energy saving measures are implemented and poor performing plant are improved before sizing a CHP system.

Poor site energy efficiency

Page 8: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Building insulation

Lighting

Power factor

Existing boiler efficiency

Greater and longer term benefits are available if energy saving measures are implemented and poor performing plant are improved before sizing a CHP system.

So check:

Poor site energy efficiency

Page 9: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Building insulation

Lighting

Power factor

Existing boiler efficiency

So check:

Every 1°C of site overheating adds 8% to heating costs

Poor site energy efficiencyGreater and longer term benefits are available if energy saving measures are implemented and

poor performing plant are improved before sizing a CHP system.

Page 10: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Detail is vital when sizing CHP.

Mis-sizing plant

Page 11: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Detail is vital when sizing CHP.

Mis-sizing plant

Calculate hourly consumption of power and gas during the working day, the week and season to season.

Page 12: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Detail is vital when sizing CHP.

Mis-sizing plant

Calculate hourly consumption of power and gas during the working day, the week and season to season.

Economical viability typically requires a heat demand all year of at least 17

hours a day, 5 days a week.

Page 13: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Detail is vital when sizing CHP.

Mis-sizing plant

Calculate hourly consumption of power and gas during the working day, the week and

season to season.

Economical viability typically requires a heat demand all year of at least 17 hours a day, 5 days a week.

The ratio of heat to power should govern the choice of CHP technology and

size. Mismatch could dramatically reduce potential CHP gains.

Page 14: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Future-proofing

Page 15: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Future-proofing

What are the prospects of fuel and electricity cost changes?

Are energy efficiency measures in place?

Page 16: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Future-proofing

What are the prospects of fuel and electricity cost changes?

Does the business have plans to expand?

Are energy efficiency measures in place?

Will the site’s heat and power demands change?

Page 17: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Site-specific issuesOverlooking the detail in the crucial connections of the CHP system can lead to costs over

running during installation.

Page 18: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Site-specific issuesOverlooking the detail in the crucial connections of the CHP system can lead to costs over

running during installation.

The gas network connection

The power network connection

A connection to local heat network where available

A heat rejection outlet where needed

Check the exact siting of:

Page 19: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Site-specific issuesOverlooking the detail in the crucial connections of the CHP system can lead to costs over

running during installation.

Check the exact siting of:Are there planning requirements or noise abatement issues to be

considered?The gas network connection

The power network connection

A connection to local heat network where available

A heat rejection outlet where needed

Page 20: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Site-specific issuesOverlooking the detail in the crucial connections of the CHP system can lead to costs over

running during installation.

Check the exact siting of:Are there planning requirements or noise abatement issues to be

considered?

Can the gas pipework accommodate the increased

volume of gas?

The gas network connection

The power network connection

A connection to local heat network where available

A heat rejection outlet where needed

Page 21: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Site-specific issuesOverlooking the detail in the crucial connections of the CHP system can lead to costs over

running during installation.

Check the exact siting of:Are there planning requirements or noise abatement issues to be

considered?

Can the gas pipework accommodate the increased

volume of gas?

Will the power network support your connection?

The gas network connection

The power network connection

A connection to local heat network where available

A heat rejection outlet where needed

Page 22: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Fuel Selection and Procurement

Page 23: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Fuel Selection and Procurement

Check the duration and volumes in your gas and

electricity supply contract - there could be exit fees.

Page 24: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Fuel Selection and Procurement

Do you have biogas available? Some biogases can contain

corrosive components, so the choice of CHP plant is crucial as is the choice of lubricant.

Check the duration and volumes in your gas and

electricity supply contract - there could be exit fees.

Page 25: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Finance model

Page 26: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Finance model

Invest your own money to get all the cost benefits but take on all

the risk.

Page 27: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Finance model

Invest your own money to get all the cost benefits but take on all

the risk.

Utilise third party financing to share the benefits and minimise

the risks.

Page 28: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Check out the incentives

Page 29: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Check out the incentives

CHP can attract tax and other benefits that can boost the economy...

Page 30: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Check out the incentives

CHP can attract tax and other benefits that can boost the economy...

...especially when specified to meet the requirements of ‘good quality’ CHP under the CHPQA scheme.

Page 31: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

ChecklistTo avoid the pitfalls in cogeneration, detailed design is the only design. Remember to:

Page 32: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Audit energy efficiency measures.

Correctly size the plant based on heat

and power demands.

Manage your fuel selection and cost.

ChecklistTo avoid the pitfalls in cogeneration, detailed design is the only design. Remember to:

Page 33: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

Audit energy efficiency measures.

Correctly size the plant based on heat

and power demands.

Mitigate any site specific issues that might affect

installation.

Manage your fuel selection and cost.

Select a finance model that suits the

project.

ChecklistTo avoid the pitfalls in cogeneration, detailed design is the only design. Remember to:

Page 34: Step by Step CHP: the Pitfalls to Avoid Between Planning and Design

01www.energ.co.uk/chp

CHP Project Planning: How to Plan CHP Equipment Installation