steel constraction company

Upload: thomas-k-mathew

Post on 01-Mar-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Steel Constraction Company

    1/61

    To Whom It May Concern

    This is to certify that Md Hachnayen Ahmed, a student of BSCE program at IUBAT -

    International University of Business Agriculture and Technology has successfully completed his

    internship on Construction process of steel building, at I-Mart Engineering Ltd from

    15May, 2013 to 15August, 2013. He has submitted a copy of his project report to the Director of

    the company. He is permitted to submit this practicum report to IUBAT to fulfill the academic

    requirement.

    ..

    Engr. Md. Abu Rayhan

    Managing Director

    I-Mart Engineering Ltd

  • 7/25/2019 Steel Constraction Company

    2/61

    II

    Acknowledgement

    In the process of preparation of my practicum report, I am very thankful to the Almighty who

    made be able to complete my research and the practicum report.

    In this connection I would further like to pay my gratitude and respect to certain personalities for

    their immense help and enormous co-operation herein.

    First of all I would like to pay my gratitude to our respected Prof. Dr. Md. Monirul Islam,

    Chair, Department of Civil Engineering, IUBAT, who gave me the opportunity to do the

    report on Construction process of Steel building.

    Then I would like to pay my gratitude to all the employees of I-Mart Engineering Ltd.who

    helped me immensely, especially, Engr. Abu Rayhan, (Managing Director), who allowed me

    to conduct my practicum work under his company, afterwards, Engr. Morad (Factory

    Engineer)to guide me through my internship period and made me able to understand different

    aspects of Steel Building Fabrication and Erection and prepare this report successfully, and

    Tanzir Rahman (Finance Officer)for Guiding me about project works and construction

    expenditure procedures.

    After that I would like to thank my honorable supervisor Engr. Md. Anisur Rahman (TiTU) ,

    Faculty, Dept. of Civil Engineering, IUBAT, for guiding me entirely, making me able to be

    precise about the report work and be presentable with the required knowledge I have gained

    throughout this practicum period.

    In fine, I would like to thank our respected Vice-chancellor of IUBAT, Prof Dr. M Alimullah

    Miyanbecause of creating such a wonderful environment for learning through which I got the

    opportunity to acquire knowledge under BSCE program, and that will be very helpful for my

    ensuing prospective career.

    .

  • 7/25/2019 Steel Constraction Company

    3/61

    III

    Table of Contents

    Letter of Transmittal...................................................................Error! Bookmark not defined.

    STUDENTS DECLARATION .................................................Error! Bookmark not defined.

    Acknowledgement ....................................................................................................................... II

    Abstract .......................................................................................................................................... V

    Chapter-01: Introduction ................................................................................................................. 1

    1.1

    Synopsis of I-Mart Engineering Ltd................................................................................. 1

    1.2 Company Profile at a Glance ........................................................................................... 2

    1.3 List of Tools & Machineries used in I-Mart Factory ....................................................... 3

    1.4 Materials Specification ..................................................................................................... 3

    1.5 List of Approved Supplier ................................................................................................ 4

    1.6

    Running Project ................................................................................................................ 4

    1.7 Company Director Summary ........................................................................................... 5

    1.8 Valued clients of I-Mart ................................................................................................... 5

    1.9

    Finished Projects .............................................................................................................. 6

    Chapter-02: Metal Building Terminology ...................................................................................... 6

    2.1 Basic Terminology ........................................................................................................... 8

    2.2 Recommended Tools & Equipment ............................................................................... 14

    Chapter-03: Project Pre-Planning ................................................................................................. 15

    3.1

    Project Owner/Managers Responsibility ...................................................................... 15

    3.2 Designers/Engineers Responsibility ............................................................................ 15

    3.3 Prime Contractors Responsibility ................................................................................. 15

    3.4 Steel Fabricators Responsibility ................................................................................... 16

    3.5 Steel Erectors Responsibility ........................................................................................ 16

    3.6 Site-Specific Erection Plan............................................................................................. 17

    Chapter-04: Site and Foundation Preparation ............................................................................... 18

    4.1

    General ........................................................................................................................... 18

    4.2 Procedural Steps ............................................................................................................. 18

    4.3 Squaring the Foundation ............................................................................................... 18

    4.4 Anchor Bolt Settings ...................................................................................................... 19

    Chapter-05: Building Delivery and Storage ................................................................................. 23

    5.1

    Unloading and Preparation of parts for Assembly ......................................................... 23

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/25/2019 Steel Constraction Company

    4/61

    IV

    5.2 Handling and Storage of Materials................................................................................. 23

    5.2.1 Location of Building Parts .......................................................................................... 24

    5.3 Important Notes .............................................................................................................. 27

    5.4 Delivery .......................................................................................................................... 28

    5.5 Wall and Roof Panels ..................................................................................................... 28

    5.5.1 Storage ........................................................................................................................ 29

    Chapter-06: Safety ........................................................................................................................ 31

    6.1 Health and Safety Management System......................................................................... 31

    6.2 Worker Site orientation .................................................................................................. 31

    6.3 Personal Protective Equipment (PPE) ............................................................................ 31

    6.4 Lifting and Handling Loads ........................................................................................... 32

    6.5

    Housekeeping ................................................................................................................. 33

    6.6 Fall Protection ................................................................................................................ 33

    Chapter-06: Structural Steel Assembly ......................................................................................... 36

    6.1 Installing Single Columns .............................................................................................. 36

    6.2

    Installing Columns in a Frame ....................................................................................... 38

    6.3 Installation of Beams ...................................................................................................... 41

    6.4 Structural Stability.......................................................................................................... 45

    6.5 Walking or Walking surfaces ......................................................................................... 45

    6.6 Connections .................................................................................................................... 45

    6.7 Bolting and Torqueing ................................................................................................... 45

    6.8 Field Welding ................................................................................................................. 45

    6.9 Loading and unloading of steel ...................................................................................... 46

    6.10 Decking .......................................................................................................................... 46

    6.11 Roof Opening ................................................................................................................. 48

    6.12 Concrete Slab on Steel Deck .......................................................................................... 48

    Chapter-07: Problems & Solutions ............................................................................................... 53

    7.1 Problems ......................................................................................................................... 53

    7.2 Solutions ......................................................................................................................... 53

    Chapter-08: Conclusion ................................................................................................................ 54

  • 7/25/2019 Steel Constraction Company

    5/61

    V

    Abstract

    The Steel Building Manufacturer produces high quality, pre-engineered metal buildings.

    However, these buildings become structures only after erection. This report has been preparedshowing the erection of the buildings. It is a summary of the techniques in use in the metal

    building industry, which is believed to be most representative of good erection practices. These

    procedures and methods are by necessity general in nature. The erector should always,

    especially in special circumstances, use proven and safe erection methods. The objectives of

    this report are to show the civil engineers responsibility in the erection process of steel

    building. Here I have showed the process of steel building erection process maintaining proper

    safety & security. Structural stability is a very important thing of steel construction. I have

    shown the pre erection procedures. While the building is being fabricated, numerous pre-

    erection plans can be made to simplify the buildings erection. Access to the site, Foundation,

    Foundation layout has been discussed briefly in this report. Quality installation is essential to

    complete the structure to the satisfaction of the building stability. This includes the checking

    and success observation during the erection of the metal building also discussed in this report.

  • 7/25/2019 Steel Constraction Company

    6/61

    VI

    COMPANY PROFILE

    OF

    I-MART ENGINEERING LTD.

    HEAD OFFICE: HOUSE # 105 (3RD FLOOR), ROAD # 07, SECTOR # 04, UTTARA,

    DHAKA - 1230, BANGLADESH. www.i-mart.com.bd

    CONTACT NO: +8801612IEL001-10, +88-01714287128.

    E-mail: [email protected],[email protected]

    FACTORY: North Chanpara, Uttarkhan, Dhaka-1230, PHONE: +8801612IEL007.

  • 7/25/2019 Steel Constraction Company

    7/61

    VII

  • 7/25/2019 Steel Constraction Company

    8/61

    1

    Chapter-01: Introduction

    1.1Synopsis of I-Mart Engineering Ltd

    I-Mart Engineering Ltd designs and manufactures each building individually. Our top priority is

    to deliver the most cost effective and highest quality metal building on the market today. Close

    attention is paid to engineering and erection detail. This ensures our customers' complete

    satisfaction in construction of the building and its durability through the years. For cost effective

    reason we can design your pre-engineered building according to any existing standard material

    available in the local market. So we are extremely versatile in engineering aspects.

    I-Mart Engineering Ltd has been launched to design; manufacture, built and marketing pre-

    fabricated steel building in Bangladesh. The building shall consist of all primary and secondary

    structural members, connection bolts, canopies, roof extension, sheeting, trim flashing, doors,

    windows, fasteners, gutters, downspouts and other miscellaneous item and accessories as

    specified, shown or mentioned in this guide. For the premium quality and customized design

    solutions, I-mart Engineering Ltd. Its manufacturing plant located at Uttar khan, Dhaka. Due to

    this location specific convenience, the factory enjoys several external economies of scale such as

    constant supply of industrial energy line, large road transportation hub, availability of physical

    labor for labor intensive tasks and finally the availability of industrial security, which is a large

    factor in the production of any product or service in Bangladesh. Additionally, the I-Mart

    Engineering Ltd beliefs on sustainability have led to a company policy that emphasizes

    environment preservation. I-Mart Engineering Ltd work on projects that include experiencing

    green cover, reducing effluents and emission, maintaining local ecological and improving long

    term coronate sustainability.

  • 7/25/2019 Steel Constraction Company

    9/61

    2

    : I-MART Engineering Ltd.

    : House #105, Road # 07, Sector # 04

    : Uttara, Dhaka-1230

    : +8801612IEL001-10,+8804475007557info@i-

    mart.com.bd,

    : [email protected]

    : www.i-mart.bd.com

    : North Chanpara, Uttarkhan, Dhaka-1230

    : Private Limited Company

    : NCC Bank Ltd.

    : 5021181039

    : 210-201-8931

    : Floor Area-14,000 Sft

    : North Chanpara, Uttarkhan, Dhaka-1230., Cell:

    +8801612435007

    : 18,00 MT/Year

    :

    : Design, Shop Detail, Fabrication & Installation Pre-

    Engineered

    Steel Buildings.

    : Engr. Md. NazmulHasan, Chairman

    : Engr. Md. Abu Rayhan, Managing Director

    : Umme Salma, Director

    : PopyBhowmick, Director

    Company Name

    Address

    Telephone

    E-mail

    WebsiteFactory

    Address

    Type ofCompanyPrincipal

    Bankers

    VAT

    RegistrationNumber

    Income Tax

    File Number

    FactoryAddress

    Production Capacity

    No. of

    Employees

    Scope of Work

    Board of Directors :

    1.2Company Profile at a Glance

  • 7/25/2019 Steel Constraction Company

    10/61

    3

    1.3List of Tools & Machineries used in I-Mart Factory

    SlNo

    Name of Tools and Machine using in I-Mart Factory Quantity

    01 Oxygen 16 Nos.

    02 Pipe Bender 05 Nos.

    03 Weight Machine 02 Nos.

    04 Flaring Vice 10 Nos.

    05 Gauge Meter 10 Nos.

    06 Hammer 20 Nos.

    07 Sly Range 20 Nos.

    08 Dust Blower 05 Nos.

    09 Gas Welding Set 02 Nos.

    10 Tool Box 10 Nos.

    11 Electric Arc (Welding , Set , Heavy duty) 08 Nos.

    12 High Speed (Auto Cutter, Machine) 08 Nos.

    13 Scissors (Heavy Size) 02 Nos.

    14 Sheet Bending Machine 02 Nos.

    15 Drill Press 10 Nos.

    16 Bench Grinder 08 Nos.

    17 Hand Grinder 08 Nos.

    18 Mechanical Auto Saw Machine 01 Nos.

    19 Diesel Generator (60 KVA) 01 Nos.

    20 LP Gas Cylinder 16 Nos.

    1.4Materials Specification

    Sl. No Components Specifications

    01Primary Members :Built-up Section

    M.S. Plate - ASTM A570 50. Minimum yield strength=345 Mpa

    02Secondary Members:

    Purlin & Girt (M. S.)

    Rolled Formed steel. Minimum yield stress 250 mpa.

    03

    Roof, wall Sheeting &

    Fascia Sheet.(Pre-Painted)

    Hi-Tensile 0.47 mm thick Steel Profile Sheets with

    min. yield strength of 550 N/mm2 coated with an alloy of55% aluminum, 45% Zinc, coating mass shall be 150gm/m2. ZincAlume Steel ASTM A 792M Grade 345B,

    AZM 150 Fy = 34.5 kN/cm2

    04Fastener Imported heavy duty Hex head self-taping screws with

    new prime seal washer

    05 Standard Anchor Bolts JIS G3101 SS 400, Fy = 25.00 KN/cm2

    06 High Strength Bolts A325 M Type 1 Hot Dip Galvanized

  • 7/25/2019 Steel Constraction Company

    11/61

    4

    1.5List of Approved Supplier

    1.6Running Project

    Sl. NoProject Area (Sft)

    Location

    01 New Stair for TM Textiles & Garments Ltd. 3000 VALUKA

    02 New Mezzanine Floor for RADIAL

    INTERNATIONAL LTD6000 ZIRANI

    BAZAR

    03 New Mezzanine Floor RADIANT Pharmaceuticals 2000 Tongi, BSCIC

    Si No.Name Of Supplier

    Address Type of Supplied

    1. BOC Bangladesh Ltd. Tejgaon I/A,Dhaka. Oxygen

    2. Kleenheat GasKawran Bazar C/A,

    Dhaka- 1215.Gas

    3.Steel Treams Taiwan

    Ltd.Gulshan-2, Dhaka. Steel Profile Sheets

    4. M/S Steel Bond Ltd

    746, west

    shewrapara,Rokeya

    Sharani Dhaka-1216.

    Steel Profile Sheets,

    Fastener, Purlin & Girt

    (M. S.), Standard Anchor

    Bolts, High Strength

    Bolts.

    5. Lee Tsai Steel Ltd.

    Walsow Tower, level-1, 21

    KaziNazrul Islam avenue,

    Pariba h, Dhaka-1215.

    Steel Profile Sheets

    6.M/S Haque Engineering

    Works

    40/Q-1, Jigatola New

    Sarak,West

    Dhanmondi, Dhaka-1209.

    Steel Profile Sheets,

    Fastener, Purlin & Girt

    (M. S.), Standard Anchor

    Bolts, High Strength

    7.M/S R. Rahman

    HardwareSaidabad, Jatrabari,Dhaka

    Standard Anchor Bolts,

    High Strength Bolts

    8. Khan Filling Station Ltd. Abdullahpur,TongiDiversion Road.

    Diesel

    9. DESCO Banani, Dhaka Electrical Energy

  • 7/25/2019 Steel Constraction Company

    12/61

    5

    1.7Company Director Summary

    1.8Valued clients of I-Mart

    Sl. No. Name of Directors Designation QualificationYear of

    Experience

    01Engr. Md. NazmulHasan, Chairman B.Sc. in Electricaland Electronics

    Engineering10 Years

    02Engr. Md. AbuRayhan

    ManagingDirector

    B.Sc. in CivilEngineering

    11 Years

    03

    Umme Salma Director- Finance& Admin

    B.A (Hons) inEnglish 04 Years

    04Popy Bhowmick Director- Supply

    ChainM.B.B.S

    03 Years

    Sl. No Name of ClientsContact Person with Designation

    01 Linde Bangladesh (BOC)Engr. Md. Khalilur Rahman

    Area Manager

    02 Confidence Group

    Kh. Moallem Abdul Malek

    General Manager (Planning &

    development)

    03 TM Textiles & Garments Ltd. Valuka,

    Mymenshingha

    Engr. Md. Abdul LatifSenior Manager (Maintenance)

    04 Nitol Motors Ltd, Mohakhali, Dhaka.Md. Sultan Mahmud

    Manager, Nitol Construction

    05 Jahangirnagar UniversityEngr. AhsanHabib

    Asst. Engineer

    06Radiance Group

    Engr. Shahidul Islam

    Project Engineer

    07 Radiant Pharmaceuticals Ltd.

    Engr. MdNewajHossain

    Incharge, Plant Maintenance

    08Gemcon Food & Agricultural Product Ltd. Engr. Md Kamrul Islam

    Project Manager

  • 7/25/2019 Steel Constraction Company

    13/61

    6

    1.9Finished Projects

    Sl.

    NoProject Area (Sft) Location

    01 Extension of BOC, Bangladesh at Dhaka 2515 Tejgoan, Dhaka

    02Consultation for two Storied Steel Building forDisha Engineering Ltd. 38000 Baro Bari, Gazipur

    03Consultation for 80 ft Span Foot Over Bridge atChittagong for Multi space Steel Structures Ltd.

    Chittagong

    04

    Consultation for Play Ground over 3-storied

    building for Scholastica School at Dhaka for Multispace Steel Structures Ltd. 4500 Dhaka

    05 Inspection Room for TM Textiles & Garments Ltd. 3500 Bogra

    07 Roof System for Pacific Button at Tongi 9000 Tongi, BISIC

    08Renovation Work for TM TEXTILES &GARMENTS LTD 44621 Valuka

    09 Renovation work for BOC 7000 Tejgoan , Dhaka

    10 Extension Work for NITOL MOTORs LTD. 6500 Tongi

    11Partition Wall for TM TEXTILES & GARMENTSLTD

    VALUKA

    12Roof System of Old Microbiology Lab for Jahangir

    Nagar University 2500 Savar, Dhaka

    13Steel Building of Container molding Shop for

    Confidence Electric Ltd 15500 Narayanganj

    1410.60 , HT Water Tank Tower for TM TEXTILES& GARMENTS LTD VALUKA

    15 Steel Partition wall for Confidence Electric Ltd 4500 Narayangonj

  • 7/25/2019 Steel Constraction Company

    14/61

    7

    Recently Finished Project

    Sl.

    NoProject

    Area (sft)Location

    1New Mosque Building By Steel Structure For Linde

    Bangladesh Ltd.

    2000Tejgoan, Dhaka

    2

    Roof Renovation Work of AJKER KAGOJ

    BHABON at Mohammadpur for Gemcon Food &

    Agriculture Products Ltd.

    13000Mohammadpur,

    Gaptholi

    3Steel Structure of Lift Core Area for RADIANT

    Pharmaceuticals.

    Tongi, Gazipur-

    17105 New mezzanine floor for Radial International Ltd. Jirani,Savar

    6Pre-fabricated Steel Structure (Mezzanine) at

    Screw Shed of Confidence Steel Ltd.

    7Supply & installation of 1.80 km surface water

    drainage system of tm textiles & garments limited

    Habirbari,Bhaluk

    a, Mymensingh

    8Canopy on Sewing Entrance of Iron Section

    (Canopy 03)for TM Textiles & Garments Ltd.

    Valuka,

    Mymenshinh

    9Canopy (01) of Sewing Building for TM Textiles &

    Garments Ltd.

    Valuka,

    Mymenshinh

    10Canopy (02) of Sewing Building for TM Textiles &

    Garments Ltd.

    Valuka,

    Mymenshinh

    11Stair (01 and 2) Renovation Materials for TM

    Textiles & Garments Ltd

    Valuka,

    Mymenshinh

    12

    Generator Room For Tm Textiles & Garments Ltd. Valuka,

    Mymenshinh

    13Making new stair (1 & 2) including, railing & rain

    protective shed for TM Textiles & Garments Ltd

    Valuka,

    Mymenshinh

  • 7/25/2019 Steel Constraction Company

    15/61

    8

    Chapter-02: Metal Building Terminology

    2.1Basic Terminology

    Accessory

    An extra building component added to a basic Kirby building, such as a door, window vent, etc.

    Aluminized

    Aluminum coated steel

    Anchor Bolts

    Bolts set in concrete, used to anchor structural members to concrete foundation.

    Base Angle

    A continuous angle secured to foundation to support wall panels.

    Base Plate

    A shop-welded, pre-punched plate on that portion of a beam or column which rests on the

    supporting surface.

    Base Channel

    A light gauge cold formed channel which replaces the base angle when liner or double sheeted

    partitions are required.

    Bay End

    The Distance between the centerline to the first interior frame to the inside of the end wall panel.

    Bay - Interior

    The distance from centerline to centerline of two interior columns.

    Beam

    A structural member who is ordinarily subject to bending and is usually a horizontal member

    carrying vertical loads.

    Bearing Frame End wall

  • 7/25/2019 Steel Constraction Company

    16/61

    9

    Frame composed of corner columns, wind columns, flush girts and rafter sections, which is

    designed to carry one-half bay loading, also referred to as Light End wall.

    Brace Angles/Rods

    Angles or rods primarily on Roof and sidewalls or RF (Rigid Frame) or BC (Beam & Column)buildings for transferring wind force to foundation and aiding in plumbing the structure.

    Bridge Crane

    A material handling system usually within a building which moves longitudinally on a runway

    constructed of rails and beams.

    Bridging

    Structural members used to give weak axis stability to joists or purlins.

    Built-Up Member or Section

    A structural member, usually an I section, made from individual web, flange and

    base plates by welding them together.

    Built-Up Roof

    A roof composed of layered felt or jute, saturated with tar, with each layer set by mopping a hot

    tar or asphalt.

    Butt Plate (or Splice Plate)

    The pre-punched end plate of a structural member which usually rests against a matching plate of

    another member in forming a bolted connection.

    By-Framed Girts

    Girts which overlap at outside column flange to form a continuous member. C Section A

    member cold-formed from steel coil in the shape of C used primarily in bearing frame end

    walls and framed openings.

    Camber

    A predetermined curvature designed into a structural member to offset the anticipated deflection

    when load is applied.

  • 7/25/2019 Steel Constraction Company

    17/61

    10

    Canopy

    Any overhanging or projecting structure with extreme end usually unsupported.

    Cantilever

    A projecting beam that is supported and restrained at one end only.

    Caulk

    To seal and make weather tight joints, seams or voids by filling with a waterproofing compound

    or material.

    Channel

    An open-ended C shape with no return lips, which may be either cold-formed or hot-rolled

    Clip

    A plate used for fastening several members together.

    Clip Angle

    An angle used for fastening various members together.

    Closure Strip

    Sealant material formed to match either inside or outside wall or roof panel configuration used at

    base, eave, rake or accessory locations to provide closure against the elements.

    Cold-Formed

    Various shapes such as angles, channels, girts and purlins, formed from steel at room

    temperature.

    Column

    A vertical structural member

    Continuous Gift or Purlin

    Gift or purlin that overlaps at columns or frames to form a continuous member. Continuous

    Ridge Vent Series of roof ventilators connected to each other located along roof peak line.

    Corner Column

    Corner column (usually a C shape) located at the corner of a bearing frame end wall.

    Corner Trim

  • 7/25/2019 Steel Constraction Company

    18/61

    11

    Preformed sheet metal trim used to close the junction of side and end wallsheets.

    Curtain Wall

    Perimeter wall panels which carry only their own weight..

    Eave Height

    The vertical dimension from finished floor to top of eave strut.

    Eave Strut

    Structural member at the eave to support roof and wall panels; also transmits forces due to wind

    on end wall from roof brace rods to wall brace rods.

    Erection

    The on-site assembly of pre-engineered components to form complete structure.

    Erection Drawings

    Drawings prepared specifically for each building, showing piece mark, and location of all

    components.

    Expansion Joint

    A break of space in construction to allow for thermal expansion and contraction.

    Fixed Base

    A vertical structural member, bolted to and positioned at 900 to a sidewall column to provide

    additional base fastening and to prevent column rotation.

    Flange

    The projecting edge of a structural member.

    Footing

    A pad or mat, usually concrete, located under a column, wall, or other structural member, used to

    distribute loads from the member into supporting soil.

    Foundation

    The substructure on which a building rests.

    Frame

  • 7/25/2019 Steel Constraction Company

    19/61

    12

    Primary structural members, made up of columns and rafters, which support the secondary

    framing.

    Framed Opening

    Opening in a wall, roof or floor that is framed with secondary members.

    Gauge

    Thickness range of steel (24, 26 etc). Distance between holes punched in flanges, base or splice

    plates.

    Galvanized

    Zinc-coated steel.

    Girder

    A main horizontal or near horizontal structural member that supports vertical loads.

    Girt

    A secondary horizontal structural member attached to sidewall or end wall columns to which

    wall covering is attached and supported horizontally: usually a cold-formed Z shape.

    Gutter

    The member used to collect and carry rain water off the roof.

    High Strength Bolts

    Any bolt made from steel having a tensile strength in excess of 100,00 pounds per square inch

    (PSI). Some examples are ASTM A-325, JIS 11.86.

    High Tensile Steel

    Structural steel having a yield stress in excess of 36,000 pounds per square inch.

    Hot Rolled Shapes

    Steel sections (angles, channels, I-Beams, etc.) which are formed by rolling mills while the steel

    is in a semi-molten state.

    Insulation

    Any material used in building construction to reduce heat transfer.

  • 7/25/2019 Steel Constraction Company

    20/61

    13

    Intermediate Bay

    A Distance between two main frames within a building.Other than end frames.

    Joist

    Beam for supporting the floor or roof.

    Nibbler

    Al electric hand tool used to cut steel roof or wall sheet openings.

    Parapet

    That portion of the wall which extends vertically above the roof line to form a fascia-type

    appearance to hide roof slope.

    Purlin

    A secondary member, usually cold-formed horizontal structural member located in the roof to

    support roof panels, that is itself supported by the primary structural framing. Generally, purlins

    in Kirby Buildings overlap at frames to form a continuous design.

    Rafter

    A fabricated primary structural member with parallel flanges that extends from haunch to apex.

    Any beam used in a primary frame to support purlins.

    (RF)-Rigid Frame

    A clearspan structure. Characterized by tapered columns, tapered haunches and rafter beams.

  • 7/25/2019 Steel Constraction Company

    21/61

    14

    2.2Recommended Tools & Equipment

    The following list of tools and equipment is considered adequate for erection of most I-Mart

    buildings. Actual Equipment requirement may vary due to differences in building type and size,

    jobsite conditions and erection personnel. The list is intended to serve as a recommendation only

    and should not be used as a limitation to your inventory of erection equipment.

    Sl.No Name Qut. Description

    1 Screw Guns 2 With magnetic hex socket heads and replacement

    2 Sheet Metal Nibbler 1 Electric sheet cutting tool with replacement Bits

    3 Power Impact Wrench 2 With assorted impact sockets 12mm to 36mm

    4 Electric Drill 2 Heavy Duty, 12mm

    5 Electric Drill 2 Heavy Duty, 6mm

    6 Electric Screw Gun 4 Heavy Duty with hex sockets

    7 Electric Power Saw 1 Heavy Duty with metal & carbide blades

    8 Electric Extension Cords 2 Sufficient for maximum number of tools used at once

    9 Electric Arc Welder 1 With leads and extra welding head

    10 Portable Generator 1 Gas driven for electric power at jobsite

    11 Gas Cutting Outfit 1 With hose, gauges, torch & replacement heads

    12 Socket Wrenches 2 Sets 12mm drive with assorted sockets and ratchet

    13 Spud Wrenches 6 Assorted sizes 12mm to 36mm

    14 Box End Wrenches 2 Sets - assorted sizes 12mm to 36mm

    15 Open End Wrenches 2 Sets - assorted sizes 12mm to 36mm

    16 Vice Grip Pliers 2

    17 Pop Rivet Tool 2 Manual and Electric

    18 Stapler Gun 4 With staples

    19 Hammers 2 Shop, Sledge, Rubber

    20 Sheet Metal Cutters 2 Left, Right, Straight

    21 Drift Pins 4 Heavy Duty

    22 Hack Saw 4 With assorted blades

    23 Chokers 4 3/8

  • 7/25/2019 Steel Constraction Company

    22/61

    15

    Chapter-03: Project Pre-Planning

    Pre-planning must consider the structures design and constructability as well as the application

    of various fall protection systems. Project pre-planning is the responsibility of the:

    Project Owner/Manager

    Design Engineer

    Prime Contractor

    Steel Fabricator

    Steel Erector

    3.1Project Owner/Managers Responsibility

    The project owner/manager is:

    A key player in the overall shared responsibility of public and worker safety.

    Responsible for ensuring that all organizations involved in any erection.

    Projects are fulfilling their safety responsibilities.

    3.2Designers/Engineers Responsibility

    The design engineer is responsible for:

    Ensuring that the structural design and integrity is consistent with the structures intended

    use and that the structure can be erected safely.

    The foundation supporting the structure.

    Considering the safety of both workers and the public.

    Considering the site-specific soil and atmospheric conditions.

    Ensuring that a minimum of 4 anchor bolts are on each main structural column.

    3.3Prime Contractors Responsibility

    Before erection starts, the prime contractor must provide the following information and

    communicate it to the steel erector:

    Notice of any repair, replacement, or modification of the anchor bolts for a column

    (required before the column is erected) as well as documentation to confirm that the

    changes were done in accordance with CSA standards.

  • 7/25/2019 Steel Constraction Company

    23/61

    16

    Site Layout Testing Requirements.

    An overall project schedule that includes coordinating the various building trades.

    Adequate access roads into and through the site for the safe delivery and movement of

    equipment and workers.

    A firm, properly graded, drained area that is readily accessible to the workers and with

    adequate space for the safe storage of materials and the safe operation of the steel

    erection equipment.

    3.4Steel Fabricators Responsibility

    The steel fabricator is responsible for:

    Providing detailed connection information to ensure that the structure can be safely

    erected.

    Providing, where required, safety attachments or anchor points as outlined in project

    specification/design documents.

    3.5Steel Erectors Responsibility

    The steel erector is responsible for:

    Ensuring workers are adequately qualified, suitably trained, and with sufficient

    experience to safely perform the assigned work.

    Informing the prime contractor about access needs to the site and specific work areas.

    Pre-planning work activities to ensure that workers are not required to work under unsafe

    or suspended loads. If workers must work beneath a load (e.g., connectors), they must be

    informed about the danger.

    Developing site-specific work instructions and procedures that identify access and area

    needs.

    Ensuring that requirements for moving loads over working areas are met. The steel

    erector and crane operator must comply with the general and specific requirements oflifting and handling loads.

    Ensuring the prime contractor has provided a report verifying concrete strength.

  • 7/25/2019 Steel Constraction Company

    24/61

    17

    3.6Site-Specific Erection Plan

    Prior to starting erection activities, every worker have involved in the erection review the site

    erection plan. The following things were included in the Site Erection Plan.

    Site-specific hazard assessment.

    Making the better understanding of erection drawing and erection procedures for

    connecting the structural parts of a skeleton structure

    Erection drawings and erection procedures for connection the structural parts of a skeleton

    structure were:

    Prepared and certified by a professional engineer.

    Checked by BRTC.

    Made available to and reviewed by all workers before work begins.

    Fig: Erection Plan checked by BRTC, BUET

  • 7/25/2019 Steel Constraction Company

    25/61

    18

    Chapter-04: Site and Foundation Preparation

    4.1General

    Before the prefabricated steel building arrives, the site and foundation should be prepared. This

    includes leveling the terrain and constructing the foundation. Steel buildings are typically

    designed to be placed on a permanent slab. A concrete contractor is highly recommended for this

    phase of the construction.

    4.2Procedural Steps

    Trees , rubbish and other items has been removed from site location

    Smooth and leveling the ground is done

    Constructing the foundation using the recommended materials is made

    4.3Squaring the Foundation

    For proper building erection, it is critical the foundation is square. The following examples are

    practiced to ensure square foundation.

  • 7/25/2019 Steel Constraction Company

    26/61

    19

    Measurement: A same as B C same as D E same as F G same as H

    4.4Anchor Bolt Settings

    It is extremely important that anchor bolts be placed accurately in accordance with the anchor

    bolt setting plan. All anchor bolts should be held in place with a template or similar means, so

    they will remain plumb and in the correct location during placing of the concrete. Check the

    concrete forms and anchor bolt locations prior to the pouring of the concrete. A final check

    should be made after the completion of the concrete work and prior to the steel erection. This

    will allow any necessary corrections to be made before the costly erection labor and equipment

    arrives. The following things were insured prior to starting erection:

    Anchor bolts were checked according to plan.

    Stand columns in place and tighten anchor bolt nuts.

    Girts are attached and temporary bracing were installed.

    Size, type and position of the anchor bolt were checked.

  • 7/25/2019 Steel Constraction Company

    27/61

    20

    Fig: Basic principles of anchor bolts

  • 7/25/2019 Steel Constraction Company

    28/61

    21

    Fig: Checking of anchor bolts as per drawing (using tape & slide calipers)

  • 7/25/2019 Steel Constraction Company

    29/61

    22

    Fig: Anchor bolt checking before casting (center to center)

  • 7/25/2019 Steel Constraction Company

    30/61

    23

    Chapter-05: Building Delivery and Storage

    5.1Unloading and Preparation of parts for Assembly

    The vehicle transporting of building parts must gain access to the building site from the adjacent

    highway or road. Such access should be studied and prepared in advance of arrival. All

    obstructions, overhead and otherwise, must be removed and the access route graveled or planked

    if the soil will not sustain the heavy wheel loads

    After unloading the truck and before the driver leaves, ensure that all parts have been delivered.

    The following things have been ensured

    Each part against the delivery receipt is checked

    Each part is marked for identification.

    Delivered receipt is signed after successful delivery of each part.

    Missing parts are identified with the sales person

    5.2Handling and Storage of Materials

    A great amount of time and trouble can be saved if the building parts are unloaded at the building

    site according to a pre-arranged plan. Proper location and handling of components will eliminate

    unnecessary handling

    Blocking under the columns and rafters protects the splice plates and the slab from damage

    during the unloading process. It also facilitates the placing of slings or cables around the

    members for later lifting and allows members to be bolted together into sub-assemblies while on

    the ground. Extra care should always be exercised in the unloading operation to prevent injuries

    from handling the steel and to prevent damage to materials and the concrete slab.

    If water is allowed to remain for extended periods in bundles of primed parts such as girts,

    purlins, etc., the pigment will fade and the paint will gradually soften reducing its bond to the

    steel. Therefore, upon receipt of a job, all bundles of primed parts should be stored at an angle to

  • 7/25/2019 Steel Constraction Company

    31/61

    24

    allow any trapped water to drain away and permit air circulation for drying. Puddles of water

    should not be allowed to collect and remain on columns or rafters for the same reason.

    5.2.1 Location of Building Parts

    While the building material is unloaded, it should be placed in and around the building site near

    the place where it will be used. This is referred to as Shaking Out. While each job will vary

    according to the size or site conditions.Placed the parts around the Foundation.

    End wall materials were laid out for each end (end column & rafters).

    Main columns and rafter at the sides

    Nuts and bolts are placed in suitable place (ensuring the easy access)

    Purlins and girts, depending on the number of bundles, are usually stored near the

    sidewalls clear of other packages or parts.

    Sheet packages are usually located along one or both sidewalls off the ground and slopingto one end to encourage drainage in case of rain.

    Accessories are usually unloaded on a corner of the slab or off the slab near one end of

    the building to keep them as much out of the way as possible from the active area during

    steel erection.

    Wall and roof paneling and other components which will not be used in the initial stage

    of erecting the steel are placed to the outside of the work area and properly stored and

    protected from weather.

    Each part is numbered for quick identification

    Fig: Planning Map for the location of Building Parts

  • 7/25/2019 Steel Constraction Company

    32/61

    25

    Fig: Placing of Secondary beams

  • 7/25/2019 Steel Constraction Company

    33/61

    26

    Fig: Placing of Angle and other secondary members

  • 7/25/2019 Steel Constraction Company

    34/61

    27

    5.3Important Notes

    During working with the materials unloading or placing I have found some claim. And I have

    generated some questions regarding those claims:

    The bundle or container in question (if any)

    The actual quantity received.

    The quantity which should have been received or that which was damaged.

    This is important for quickly retrieving the necessary information. Also, the other information

    such as numbers, names and addresses should be indicated on claims as well as invoice numbers.

    These procedures are primarily for your protection, a shortage discovered later can be caused by

    theft, misplacement or other causes and neither the carrier nor building provider can accept

    responsibility.

  • 7/25/2019 Steel Constraction Company

    35/61

    28

    5.4Delivery

    Company takes every precaution to ensure that material is delivered to the customer damage free

    and fully protected from the elements during shipment. When the material is delivered to the

    customer it then becomes the customer's responsibility to protect the material from the elements,

    possible theft, and other damage. The following guidelines are practiced:

    1. Ensure the band of Bundles during the unloading process.

    2. Lifting of bundles by banding material is strictly prohibited

    3. Lifting is done maintaining the closing distance to its center of gravity

    4. After panel bundles are opened, individual sheets have been handled carefully to prevent

    panel buckling or damage to the panel coating.

    5. When removing a sheet from a bundle, rolled off the bundle to prevent scratching of the

    next sheet.

    6. Never drag or slide one sheet over another sheet was strictly prohibited.

    7. Lifting of sheets is done along its longitudinal edge and carries in a vertical position.

    8. Instead, lift the sheet along its longitudinal edge and carry in a vertical position.

    9. For 10 long, 3 to 4 people were worked.

    5.5Wall and Roof Panels

    Wall and roof panels including color coated, galvalume, and galvanized provide excellent service

    under widely varied conditions. All unloading and erection personnel should fully understand

    that these panels are quality merchandise which merit cautious care in handling.

    Under no circumstances should panels be handled roughly. Packages of sheets were lifted off the

    truck with extreme care to ensure that no damage occurs to ends of the sheets or to side ribs.

    Then the packages stored off the ground sufficiently high to allow air circulation underneath the

    packages. This avoids ground moisture and deters people from walking on the packages. One

    end of the package should always be elevated to encourage drainage in case of rain.

    All stacked metal panels are subject, to some degree, to localized discoloration or stain when

    water is trapped between their closely nested surfaces. We exercise extreme caution during

    fabricating and shipping operations to ensure that all panel stock is kept dry. However, due to

    climatic conditions, water formed by condensation of humid air can become trapped between

    stacked sheets. Water can also be trapped between the stacked sheets when exposed to rain. This

    discoloration caused by trapped moisture is often called wet storage stain.

    The stain is usually superficial and has little effect on the appearance or service life of the panels

    as long as it is not permitted to remain on the panels. However, moisture in contact with the

  • 7/25/2019 Steel Constraction Company

    36/61

    29

    surface of the panels over an extended period can severely attack the finish and reduce the

    effective service life. Therefore, it is imperative that all panels be inspected for moisture upon

    receipt of the order. If moisture is present, dry the panels at once and store in a dry, warm place.

    5.5.1 Storage

    It was recommended that sheets be stored under roof if at all possible. As sheets were to be

    stored outside, the following precautions was observed:

    Leveling and location of storied area so as to minimize handling.

    In case of bare ground, placing of plastic ground cover under the bundles to minimize

    condensation on the sheets from ground moisture.

    Marinating at least 12 inches above ground level to allow air circulation beneath the

    bundle and to prevent damage from rising water. Waterproof cover was placed over the bundles to allow for air circulation under the

    cover.

    Inspecting stored bundles daily and repair any tears or punctures in the water proof cover.

    Re-cover opened bundles at the end of each workday to prevent subsequent moisture

    damage.

    Fig: Storage System of Metal Sheet

  • 7/25/2019 Steel Constraction Company

    37/61

    30

    Fig: Placing of Sheet Metal in the site

  • 7/25/2019 Steel Constraction Company

    38/61

    31

    Chapter-06: Safety

    6.1Health and Safety Management System

    The purpose of a Safety Management System is to identify, assess, and control workplace

    hazards. To be effective, the following essential components were done:

    Health and safety hazards at the work site were analyzed.

    Control measures to eliminate or reduce risks from hazards were taken.

    Clearly stated company policy and management commitment

    Worker competency and training was done

    An checkup program was established

    Prior to starting work, all workers have attended a structural steel erection best practices review

    for the project. A review document was understood and signed as accepted.

    Weekly safety meetings was continued to held and the prime contractor always be kept

    informed, in writing, about discussions and issues that may affect safe erection of steel (e.g.,

    weather conditions [such as wind], access, site conditions).

    6.2Worker Site orientation

    Prior to starting work, every worker attended a site orientation to be informed of and become

    familiar with:

    Site rules and regulations

    Erection plan and procedures

    Equipment to be used

    Hazard assessment

    Work area and emergency procedures (including the rescue plan)

    Work areas of other trades and the need to communicate planned work

    Activities to them when working in close proximity

    6.3Personal Protective Equipment (PPE)

    Personal protective equipment (PPE) refers to protective clothing, helmets, goggles, or other

    garments or equipment designed to protect the wearer's body from injury.

    The purpose of personal protective equipment is to reduce employee exposure to hazards when

    engineering and administrative controls are not feasible or effective to reduce these risks to

    acceptable levels.

  • 7/25/2019 Steel Constraction Company

    39/61

    32

    Employers and workers must ensure that this equipment is used whenever a worker is

    exposed to the relevant hazard.

    All PPE complied with standards referenced in the OSHA.

    Additional PPE is supplied as required for various tasks.

    Pant legs and laces must be tied or taped to avoid tripping hazards.

    Fig: Shearing ideas of safety & security with the workers

    6.4Lifting and Handling Loads

    Manual handling of loads or materials by workers was minimized.

    Worker lift were provided

    Push and pull method was practiced

    Proper care taken to carry or handle or transportation of heavy or awkward loads.

  • 7/25/2019 Steel Constraction Company

    40/61

    33

    Fig: Lifting & Handling of Building parts

    6.5Housekeeping

    All supplies, such as bolts, shims, Dunn age and debris storied in proper containers and

    set away from areas where they can pose tripping hazards.

    No loose bolt and nuts were leave lying on steel or on ground.

    Ongoing cleanup was performed

    6.6Fall Protection

    Fall protection was ensured in case of unusual possibility of injury if a worker falls from

    above 3m.

    Fall protection plan specify the following things.

    Fall hazards at work site

  • 7/25/2019 Steel Constraction Company

    41/61

    34

    Fall protection system to be used at the work site

    Procedures used to assemble, maintain, inspect, use, and disassemble the fall protection system.

    Fig: Safety hamlet & belt

    Fig: Worker with the safety equipment

  • 7/25/2019 Steel Constraction Company

    42/61

    35

  • 7/25/2019 Steel Constraction Company

    43/61

    36

    Fig: Workers with the safety equipmentChapter-06: Structural Steel Assembly

    6.1Installing Single Columns

    All main structural columns were anchored by a minimum of 4 anchor bolts.

    Columns were set on the leveling plates, nuts.

    No repair or Modifications were allowed.

    Column rigging were attached through a bolt hole in the top of the column in the web or a

    beam clip.

    Some places choker has been used.

  • 7/25/2019 Steel Constraction Company

    44/61

    37

    Fig: Layout of Column

  • 7/25/2019 Steel Constraction Company

    45/61

    38

    Lower the Column

    Placing column on anchor bolts:

    Watch for pinch point.

    Once the base plate of the column touches the slim, put the washers and nuts on theanchor bolts.

    Plumb the column by tightening the anchor bots.

    Check the column for the stability

    Placing column on to a steel column or beam:

    Watch for pinch point.

    Once the base plate of the column touches the connection point, bolt down.

    Plumb the column by tightening the connection bolts.

    Minimum four bolt were used

    Column were checked for stability

    Unstable columns were braced necessarily.

    6.2Installing Columns in a Frame

    Frames are often referred to as bents.

    Lower the frame onto the anchor bolts. Watch for pinch points

    Placed the beams, bracing according to the plan to make the large frame.

    Always maintain lift capacity

    Maintain the good signal to the crane operator

    Once the frame is lifted off the ground and the crane has the complete weight, provide the

    signal to the operator not to stop the lift until the load settles. Once the load settles,

    proceed to signal the crane operator to move the frame into position.

    After the base plate of the column touches the shims, put the washers and nuts on the

    anchor bolts.

    Plumbed the frame by tightening the anchor bolts.

    Weight of the frame was released

    Plumbing work of anchor bolts was checked.

  • 7/25/2019 Steel Constraction Company

    46/61

    39

    Fig: Check the security of the column before releasing the rigging.

  • 7/25/2019 Steel Constraction Company

    47/61

    40

    Fig: Placing of Column by Crane

  • 7/25/2019 Steel Constraction Company

    48/61

    41

    6.3Installation of Beams

    Beams generally includes purlins and girts

    Rigging were attached in the center of load using the appropriate chocker

    Signal the crane operator to lift beam

    Adjust the crane line (by signaling the operator) to remain above the rigging point of the

    lift as the beam is being raised.

    After the beam is lifted off the ground and the crane has completed the weight, lift was

    stopped until the load settled.

    After the settlement of the load, lift operator were signaled to move the crane into

    position.

    Beams were attached to the supporting structural members (columns) using sufficient

    number of bolts

    To ensure the structural integrity before weight of load is placed on the connection plates,

    sufficient numbers of welding were confirmed.

    Columns sufficient load were ensured before installing members.

    After checking the structural stability of the member, chocker was released from the

    member.

  • 7/25/2019 Steel Constraction Company

    49/61

    42

    Fig: Lifting process of beams

  • 7/25/2019 Steel Constraction Company

    50/61

    43

    Fig: Lifting of beams

  • 7/25/2019 Steel Constraction Company

    51/61

    44

    Fig: Sufficient Welding before releasing the rigging

  • 7/25/2019 Steel Constraction Company

    52/61

    45

    6.4Structural Stability

    Ensure that structural stability is maintained at all times.

    No Construction loads were not placed on any steel before framework is safely bolted, welded, or

    otherwise adequately secure.

    When used, temporary bracing was used and properly installed in conjunction with the steel

    erection plan to ensure the structural stability.

    6.5Walking or Walking surfaces

    Walking on the coated structural steel were strictly prohibited as it is slipper then the

    normal primed steel.

    Tried to avoid the shear connector, where possible as that create tripping hazards.

    6.6Connections

    During the final placing of solid web structural members, the load should not be released from

    the hoisting line until the member is secured with at least two bolts per connection, wrench tight.

    Secondary members must have one bolt wrench tight.

    Ensure more than two bolts to stability of a connection

    During erection, diagonal bracing was secured by at least one bolt per connection.

    Wrenched tightened, before releasing load.

    Where two beams, framing from opposite sides of a supporting member, share the same

    bolts, a clipped connection should be used unless a seated connection is used to facilitate

    safe erection.

    6.7Bolting and Torqueing

    Always followed the bolting instructions

    Inspect bolt bags daily for damage.

    Do not leave unsecured objects (e.g., bolt bags, tools, loose steel) at elevations

    6.8Field Welding

    Welder was certified, qualified and experienced to perform the work involved.

    Welder was employed by the I-Mart

    All welding is performed by two experienced persons.

  • 7/25/2019 Steel Constraction Company

    53/61

    46

    6.9Loading and unloading of steel

    Worker always told to stay out of the danger zone whenever moving equipment.

    All good, materials and equipment were stacked, storied and secured such a way they do

    not flow, move, roll or collapse.

    Worker responsibility for stacking, storing or securing goods, materials and equipment

    was indicated before.

    6.10 Decking

    No bundle was packaged or strapping designed for hoisting without any special design.

    Loose items always on top of the bundles.

    All decking were secured against displacement. No decking loads were allowed on the steel joist until erectors has confirmed that bridging is

    installed and anchored and all joist bearing ends are attached.

  • 7/25/2019 Steel Constraction Company

    54/61

    47

    Fig: Decking Layout Plan

  • 7/25/2019 Steel Constraction Company

    55/61

    48

    6.11 Roof Opening

    Metal decks must be installed to meet these requirements:

    Roof and floor openings were covered during the decking

    process.

    All cover was secured.

    All holes and opening were immediately covered.

    Skylight openings must meet these same requirements.

    6.12 Concrete Slab on Steel Deck

    Composite Steel Deck Floor System consists of a high strength structural steel deck and a

    structural concrete slab with welded wire fabric and additional reinforcing when specified.This

    floor system provides economy and efficiency, taking advantage of the composite design of the

    steel deck and concrete.

    Construction Process

    Place all the accordingly.

    After placement of metal sheet, shear bolts were welded

    with the sheet.

    Placing of rods was done.

    Then concrete pouring was done.

  • 7/25/2019 Steel Constraction Company

    56/61

    49

    Fig: Check the additional decking

  • 7/25/2019 Steel Constraction Company

    57/61

    50

    Fig: Placing of Steel deck & shear bolts

  • 7/25/2019 Steel Constraction Company

    58/61

    51

    Fig: Placing of reinforcement bar.

  • 7/25/2019 Steel Constraction Company

    59/61

    52

    Fig: Placing of Concrete

  • 7/25/2019 Steel Constraction Company

    60/61

    53

    Chapter-07: Problems & Solutions

    7.1Problems

    I have detected some problem during my training period and learnt how to solve those problems.

    Two columns were less than their design height up to 1.5 ft.

    Problem occurred with the alignment of RCC works.

    One sheet was shorter than its original length.

    7.2Solutions

    Solutions to the problems discussed above are discussed below:

    After discussing with the client we have decided to provide pc (purlin cleat) to increase the

    height.

    For maintaining the alignment of the Column we have some cutting of RCC works and then

    recast.

    For sheeting problem, it was not possible to make a new sheet immediately, and we have just

    change the sheeting alignment. Providing long sheet where necessary and without cutting or

    trimming we just use the whole sheets accordingly. And finally the problem was solved.

  • 7/25/2019 Steel Constraction Company

    61/61

    Chapter-08: Conclusion

    Steel construction is considered as a process that involves many related activities. The basics of

    metal building erection, from the primary structures to the secondary structures, have been

    covered in this report. I have briefly encapsulated the basic sequence of events from construction

    site planning through erecting a Metal Building. Many other phases, such as mechanical,

    electrical, interior finishing and landscaping need to be done to finish and complete most

    projects. Although there are many other events, procedures, and essentials that are involved in

    the erection of a metal building. Responsible personnel, experienced in rigging and handling

    light steel members in a safe manner should complete the layout, assembly, and erection of the

    metal building. Improper handling can easily result in injury, delays and unexpected added costs.