steel catenary risers installation

Upload: seantbt

Post on 04-Jun-2018

275 views

Category:

Documents


4 download

TRANSCRIPT

  • 8/13/2019 Steel catenary risers installation

    1/30

    Deep Water Installation of SteelCatenary Risers

    Subsea Asia

    3rdOctober, 2012

    Kuala Lumpur, Malaysia

    Grant Milne

  • 8/13/2019 Steel catenary risers installation

    2/30

    Safety Moment Abseiling for SCR Installation

    Used On Erha. SCR receptacleslocated above the waterline

    High standard of procedures Early involvement of the abseiling

    supervisor in the project

    -

    2Page2-Oct-12

    department as well assubcontractors.

  • 8/13/2019 Steel catenary risers installation

    3/30

    Agenda

    Introduction

    SCR Configurations

    SCR Welding

    Deepwater SCR Installation

    3Page2-Oct-12

    SCR Hook-upBC-10 Experience

  • 8/13/2019 Steel catenary risers installation

    4/30

    Introduction to Steel Catenary Risers

    Steel Catenary Risers:

    Economically attractive

    Large diameters

    High resistance to internal and externalpressure

    Simple and robust installation methods

    4Page2-Oct-12

    Sensitive to dynamics and morevulnerable to fatigue when they are lightin water

    Challenges: Increasing top tensions due to larger

    diameters and deeper water

    Increase of fatigue due to harsherenvironments, and increasing top tensions

  • 8/13/2019 Steel catenary risers installation

    5/30

    Agenda

    Introduction

    SCR ConfigurationsSCR Welding

    Deepwater SCR Installation

    5Page2-Oct-12 5Page2-Oct-12

    SCR Hook-upBC-10 Experience

  • 8/13/2019 Steel catenary risers installation

    6/30

    SCR Configurations For Minimised Fatigue

    Three configurations to choose from are:

    Free hanging SCR

    Lazy wave SCR

    Buoyancy supported riser

    Influenced by:

    Water depth

    6Page2-Oct-12

    Environmental conditions Installation method

    SCR size and design

    Top tension

    Fatigue allowances Type of production platform

  • 8/13/2019 Steel catenary risers installation

    7/30

    SCR Configurations Free Hanging SCR

    Simple and easy installation

    Often installed VIV strakes

    Economically attractive Can be subject to high

    fatigue damage at top endand TDP

    7Page2-Oct-12

    Sometimes need hold-backanchors:

  • 8/13/2019 Steel catenary risers installation

    8/30

    SCR Configurations Lazy Wave SCR

    Addition of buoyancymodules

    Decreased top tension

    TDP is further away fromproduction facility

    Lower Stress and Fatigue at

    8Page2-Oct-12

    the Top End and TDP byfactors of between 2 and 5

    Completed for BC-10, 2009

  • 8/13/2019 Steel catenary risers installation

    9/30

    SCR Configurations Buoyancy Supported Risers

    De-couple FPSO motionsfrom risers

    Effectively decreased toptension at FPSO or floatingstructure

    Easier SCR installation

    9Page2-Oct-12

    program: De-coupled from FPSO

    Completed without FPSO infield

    Suited to ultra deep water

    Guara Lula project Brazil2013/2014

  • 8/13/2019 Steel catenary risers installation

    10/30

    Agenda

    Introduction

    SCR ConfigurationsSCR Welding

    Deepwater SCR Installation

    10Page2-Oct-12 10Page2-Oct-12

    SCR Hook-upBC-10 Experience

  • 8/13/2019 Steel catenary risers installation

    11/30

    SCR Welding for Improved Fatigue Performance

    Fatigue performance of weld is critical

    Close control of pipe end tolerances and joint misalignment

    High integrity weld procedures Flush grinding of weld caps for better fatigue performance

    Reel lay installation onshore fabrication and testing

    11Page2-Oct-12

  • 8/13/2019 Steel catenary risers installation

    12/30

    SCR Welding Installation of Mechanically Lined

    Clad Pipe for Reel Lay

    Subsea7 has developed a methodology for the installationof mechanically lined pipe by reel lay.

    Qualification gained from DNV and the method will be usedon Guara-Lula, 2013 for the SCR installation

    Methodology adopts reeling on the lined pipe in a floodedcondition with back pressure to mitigate any wrinkling of

    12Page2-Oct-12

    the CRA liner due to plastic bending Method offers significant economic advantages due to the

    reduced cost from using metallurically clad pipe which hasbeen previously reeled

  • 8/13/2019 Steel catenary risers installation

    13/30

    SCR Fabrication Prefabrication Onshore

    Vigra spool base in Norway

    Maximum stalk length of 1520m

    1000m fabrication shed

    13Page2-Oct-12

  • 8/13/2019 Steel catenary risers installation

    14/30

    SCR Fabrication Prefabrication Onshore Pipeline stalks are fabricated first and then spooled onto

    reel lay vessel; Seven Navica

    14Page2-Oct-12

    SCRs can also be installed by offshore fabrication in S-Layand J-Lay

  • 8/13/2019 Steel catenary risers installation

    15/30

    Agenda

    Introduction

    SCR ConfigurationsSCR Fabrication

    Deepwater SCR Installation

    15Page2-Oct-12 15Page2-Oct-12

    SCR Hook-upBC-10 Experience

  • 8/13/2019 Steel catenary risers installation

    16/30

    Deepwater Installation Spread Seven Borealis

    Seven Borealis Size: 182m x 46m

    J-Lay: 937Te, 24

    S-Lay: 600Te, 46

    Crane: 5000Te

    16Page2-Oct-12

    15 gimble capacity allowsvessel to fully weathervanein order to minimise motionsand SCR fatigue.

    Suited for the installation ofthe biggest SCRs in ultra-deepwater environments

  • 8/13/2019 Steel catenary risers installation

    17/30

    Deep Water Installation Spread Sapura 3000

    Sapura 3000

    Size: 151m x 38m

    J-lay: 400Te, 20

    S-lay: 240Te, 60

    17Page2-Oct-12

    Class leading heavy lift andpipelay vessel operating in

    water depths of up to3000m

  • 8/13/2019 Steel catenary risers installation

    18/30

    Deepwater Installation Spread Seven Oceans

    Seven Oceans

    Size: 157m x 28m

    Reel Lay: 3500Te

    Pipe Size: 6-16

    18Page2-Oct-12

    Efficient reel lay vessel withSCR experience

  • 8/13/2019 Steel catenary risers installation

    19/30

    Deepwater Installation Spread

    Seven Seas

    Construction and flex-lay

    vessel with J-lay capabilitiesthrough the moonpool

    Top tension: 400Te

    19Page2-Oct-12

  • 8/13/2019 Steel catenary risers installation

    20/30

    Deepwater Installation Spread Weather Mitigation J-Lay: 15 gimble to allow 360 heading changes

    Larger vessels: smaller motions

    Reel lay: small installation window needed due to quick layspeeds

    Moonpool lay decreases vessel motions seen by SCR.

    20Page2-Oct-12

  • 8/13/2019 Steel catenary risers installation

    21/30

    Agenda

    Introduction

    SCR ConfigurationsSCR Welding

    Deepwater SCR Installation

    21Page2-Oct-12 21Page2-Oct-12

    SCR Hook-up

    BC-10 Experience

  • 8/13/2019 Steel catenary risers installation

    22/30

    SCR Hook-up SCR Wet Store De-couple SCR fabrication

    and installation with FPSOdelivery

    Tight corridors

    Additional vessel to recoverand transfer SCR to FPSO

    22Page2-Oct-12

    Pull-in head and laydowntool installation

  • 8/13/2019 Steel catenary risers installation

    23/30

    SCR Hook-up Direct Transfer From pipelay vessel to FPSO

    Historically preferred method

    Deploy SCR on A&R winchfrom pipelay vessel andhandover subsea to FPSOpull-in wire

    23Page2-Oct-12

  • 8/13/2019 Steel catenary risers installation

    24/30

    SCR Hook-up Riser Pull-in Equipment (RPE) Located on FPSO to

    complete final pull-in of SCR

    Up to 450Te has been

    completed, 600Te in thefuture

    Slides between riser

    24Page2-Oct-12

    recep ac es

    De-mobilised off FPSO afterhook-up.

  • 8/13/2019 Steel catenary risers installation

    25/30

    Agenda

    Introduction

    SCR ConfigurationsSCR Welding

    Deepwater SCR Installation

    25Page2-Oct-12 25Page2-Oct-12

    SCR Hook-up

    BC-10 Experience

  • 8/13/2019 Steel catenary risers installation

    26/30

    Shell BC-10 Overview Brazil Campos Basin

    Harsh environmental conditions

    1190-1940m WD

    2009

    Reel lay Seven Oceans Ubu spool base

    26Page2-Oct-12

    Lazy Wave SCR Improved fatigue life

    Reduced top tension andreduced loads on FPSO turret

    FPSO motions affect the SCR

    less.

    3 SCRs were wet stored and2 were directly transferred.

  • 8/13/2019 Steel catenary risers installation

    27/30

    Shell BC-10 Buoyancy Modules Installed after the initiation

    of the PLET.

    Installed under lay spread

    on Seven Oceans.

    Half shells of buoyancy wereheavy and large.

    27Page2-Oct-12

    Operation completed withoutincident.

    Fatigue performance for SCRare very good.

  • 8/13/2019 Steel catenary risers installation

    28/30

    Shell BC-10 Flexjoint Weld SCR hung off in worktable.

    Flexjoint lifted into layspread by vessel crane.

    Flexjoint section manuallywelded onto SCR.

    J-lay methodology

    28Page2-Oct-12

  • 8/13/2019 Steel catenary risers installation

    29/30

    Conclusion Selection of the best SCR configuration

    Lazy Wave for decreased top tension and lower fatigue

    Free hanging for simplicity

    Buoyancy supported riser for ultra deep water

    Selection of a vessel to minimise installation fatigue loads

    Reel lay for minimal installation time

    29Page2-Oct-12

    J-lay for high top tension and 360 heading changes

    S-lay

    Wet-store or direct transfer

    De-couple installation schedule from FPSO delivery

    Pull-in and landing of SCR into receptacle on floatingstructure

  • 8/13/2019 Steel catenary risers installation

    30/30

    10.01.11 30Page

    seabed-to-surface

    www.subsea7.com