Status of LS1 collimator maintenance
O. Aberle – 03/03/14
With input from P. Bestmann, S. De Man and J. Lendaro
O. Aberle – CWC2
Main activities during the LS1
Collimator exchange (TCTP vs TCT, IR 1, 2, 5 and 8)
Collimator installation (TCLP, TCL6 in IR1 and 5)
New TCAPD (IR 3) New installation commissioning Collimator standard maintenance Special maintenance TIM / Robot intervention/observations Alignment Outlook
March 03rd 2014
O. Aberle – CWC3
Collimator exchange New production of 16 + 4 TCTP New production of 2 + 1 TCSP New production of 2 + 1 TCAPD Preparation of 2 spare TCLP Preparation of 1 spare TCP Layout modification in Pt. 8, removal of 2 TCTVB, shifting TCLIA Pt. 1: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP and 2 TCT Pt. 2: Replacement of 2 TCT + 2 TCLP by 4 TCTP Pt. 3: Installation of 2 new TCAPD Pt. 5: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP and 2 TCT Pt. 6: Replacement of 2 TCS by 2 TCSP Pt. 7: Remove first TCP on the right side and the three TCP on the left side
during ventilation door installation (to prevent damage) and exchange the skewed TCP of IR7L (water cooling)
Pt. 8: Replacement of 2 TCT + 2 TCTVB by 4 TCTP
March 03rd 2014
O. Aberle – CWC4
New installation commissioning
Check each collimator mechanics and electronics. Full check of controll system Slot and infrastructure (support, cabling, cooling
water) Installation and alignment Vacuum connection and bake-out Collimator standard maintenance
March 03rd 2014
O. Aberle – CWC5
Collimator standard maintenance
Check each collimator mechanics and electronics. Cycle from out to in, to anti-collision and back to
out. Check 5th axis for clearance Check water cooling flow Check temperature sensors Check switches, LVDT’s, resolvers, motors and
drivers Map sound profile for each collimator Check rails Check roller screws
March 03rd 2014
O. Aberle – CWC6
Collimator roller screw replacement (2011-12)
March 03rd 2014
Dust and debris in the end cap and the housing
Some dry screws regreased
Up to date 3 rollers screws have been exchanged.-No linear bearing-2 LVDT‘s-1 motor-2 switches
O. Aberle – CWC7
TIM and Robot intervention
March 03rd 2014
Sound inspection of the collimators done with the TIM in S34 (23/24 April 2012).
Visual and acoustic inspections with camera can be useful in the future (TIM automatically, Telemax robot more flexible).
Vacuum disconnection testing with the Telemax robot on-going.
Use of robot for visual inspections/leak tests (He spray).
Profit from the long shutdown to verify the integration and do some hardware tests to confirm the procedures.
O. Aberle – CWC8
Alignment
March 03rd 2014
Survey is working in the whole machine. During smoothing, magnets will be aligned
and collimators checked (and adjusted if needed).
IR 3 and IR 7 are equipped with additional targets for remote verification with the stretched wire.
New collimators (TCTP, TCSP, TCLP, TCT (TCL6) and TCAPD) will be aligned.
The TCP’s removed during the installation of the ventilation doors + the skewed TCP in IR7L to be checked (high radiation levels, how much deviation can be tolerated?).
O. Aberle – CWC9
Schedule – linked to LS1 LHC planning
March 03rd 2014
Number of systems Network Installation
230V power supply cabling 230V powered R2E cabling works Other works Control System
InstallationSystems ready for
commissioningCollimator added
or replaced during LS1
Collimator not modified during
LS1Sector Cooldown L Sector Cooldown R Powering
Tests SeqControls
Commissioning starting date
Controls Commissioning
end dateNew collimators Installation date
New collimators Commissioning/calibration
starting date
New Collimators Commissioning/Calibration end
dateCalibration
starting dateCalibration end
date
US15 4 + 1 for TCL-6 OK OK OK OK OK YES 6 + 2 TCL6 2 2 June 30 June 3 10. Mrz 14. Mrz1L TCTP 14/04/20141R TCTP 5/03/2014TCL-6 ?
UA23 6 + TDI OK OK Planned 28/02/2014 - OK No 3 (including TDI) 7 30 June - 4 17. Mrz 21. Mrz TCTP 12/05/2014TDI 28/04/2014
UA27 2 OK OK Planned 28/02/2014 - OK No 2 2 - 11 August 5 24. Mrz 28. Mrz TCTP 12/05/2014
UJ33 7 - OK OK - Ok YES 0 18 11 August 15 September 2 25. Feb 07. Mrz TCAPD 14/02/2014
USC55 4 + 1 for TCL-6 No No. End of March End of MarchCables available around 20th March. TCL-6 cables : L 15/04
, R 30/05 No No 6 + 2 TCL6 2 22 September 28 July 10 12. Mai 16. Mai
5L TCTP 14/07/20145R TCTP 9/06/2014TCL-6 ?
US65 1 - OK OK - OK System to switch ON 2 0 28 July 5 May 6 31. Mrz 02. Apr 6L TCSP 13/03/20146R TCSP 18/02/2014
TZ76 21 OK In progress Planned end of MarchIn progress. Cables
reconnection in TZ76: date to confirm
OK No 4 (TCP) 34 5 May 11 August 9 22. Apr 09. Mai 7R TCP 18/02/20147L TCP 10/03/2014
UA83 2 OK In progress Planned 3/03/2014 - TCTVB Cabling in progress OK No 3 1 11 August - 8 14. Apr 18. Apr TCTP 9/06/2014
UA87 5 + TDI OK In progress Planned 3/03/2014 -TCTVB Cabling. Finished: To check
OK No 3 (including TDI) 6 - 2 June 7 02. Apr 11. Apr TCTP 14/04/2014
BA7 1 OK OK OK - OK YES 0 1 - - 1 24. Feb 24. Feb -
Frame given by LHC planning, Julie is coordinating with Vacuum, transport, powering etc…
Cabling and control system availability Installation readiness of new collimators
O. Aberle – CWC10
Schedule – details by Jerome
March 03rd 2014
Number of systems Control System Installation
Systems ready for commissioning
Collimator added or replaced during LS1
Collimator not modified during
LS1Seq
Controls Commissioning
starting date
Controls Commissioning
end dateNew collimators Installation date
US15 4 + 1 for TCL-6 OK YES 6 + 2 TCL6 2 3 10. Mrz 14. Mrz1L TCTP 14/04/20141R TCTP 5/03/2014TCL-6 ?
UA23 6 + TDI OK No 3 (including TDI) 7 4 17. Mrz 21. Mrz TCTP 12/05/2014TDI 28/04/2014
UA27 2 OK No 2 2 5 24. Mrz 28. Mrz TCTP 12/05/2014
UJ33 7 Ok YES 0 18 2 25. Feb 07. Mrz TCAPD 14/02/2014
USC55 4 + 1 for TCL-6 No No 6 + 2 TCL6 2 10 12. Mai 16. Mai5L TCTP 14/07/20145R TCTP 9/06/2014TCL-6 ?
US65 1 OK System to switch ON 2 0 6 31. Mrz 02. Apr 6L TCSP 13/03/20146R TCSP 18/02/2014
TZ76 21 OK No 4 (TCP) 34 9 22. Apr 09. Mai 7R TCP 18/02/20147L TCP 10/03/2014
UA83 2 OK No 3 1 8 14. Apr 18. Apr TCTP 9/06/2014
UA87 5 + TDI OK No 3 (including TDI) 6 7 02. Apr 11. Apr TCTP 14/04/2014
BA7 1 OK YES 0 1 1 24. Feb 24. Feb -
O. Aberle – CWC11
Schedule – linked to LS1 LHC planning
March 03rd 2014
Work has just started First ring collimators put back into operational
statusTCLA.7L3.B2, TCP.6L3.B1, TCSG.5L3.B1
A lot of work in parallel with surface preparation and installation activities.
J. Finelle from the vacuum team will take pictures when ever a collimator will be disconnected from the vacuum system.
All collimators will be checked for alignment errors, re-alignement has already started in several points.
O. Aberle – CWC12
Outlook
March 03rd 2014
Improve the sound and image quality for the TIM, very powerful tool for the future.
Investigate on the capabilities of the Telemax or similar robots for inspections and interventions.
Reference sound recording of all collimators? Improve the accessibility to the screw (cap)
(Phase 2!) A regular check during long breaks and shut-
downs with re-lubrication of the screw. Check every slot for 5th axis motion
limitations. Sven De Man is the new reference person for
the LHC tunnel situation concerning collimators