11 Division 11 Alleghany Ashe Avery Caldwell Surry Watauga Wilkes Yadkin STATE TRANSPORTATION IMPROVEMENT PROGRAM

Upload: others

Post on 27-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

11

Division 11AlleghanyAsheAveryCaldwellSurryWataugaWilkesYadkin

STATE TRANSPORTATION IMPROVEMENT PROGRAM

Page 2: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

WILKES

CALDWELL

AVERY

YADKIN

WATAUGA

SURRYASHE

ALLEGHANY

421

421

52

321

19

321

64

221

221321

21

601

421

221

74

77

1667

268

194

89

18

93

163268

18

113

90

103

88

105

MountAiry

Boone

Lenoir

AV-5750

B-5830

B-5504

B-5823

B-5835

B-5831

B-5173

B-5527B-5837

B-5832B-5523

B-5834

B-5828

B-4686B-4683

B-5833B-5825

B-5829

B-5386

B-5532

B-4670

B-4676

B-5842

W-5521

R-5525R-5730

U-5776

R-5745

U-4700CA

U-5705R-2566BA

R-5733

EB-5725

U-5715

U-5809

R-4060R-5714

I-5801I-5802

U-5867

R-2915A

U-5810

R-2915B

I-5865

I-5864

U-5603

U-5312

I-5830

R-2603

R-2615

R-2915E

R-2915D

I-5803I-5749

R-2915C

I-5829

I-5862

R-2566B

I-5863R-3101

R-3309

DRAFT STIPFY 2015-2025STI ProjectsDIVISION 11

0 7 143.5Miles

BRIDGES FUNDED THROUGH STI

STATEWIDE AVIATION

REGIONAL AVIATION

DIVISION AVIATION

DIVISION FERRYREGIONAL RAILDIVISION RAILREGIONAL TRANSITDIVISION TRANSITSAFETYTRANSITION *TRANSITION *INTERSTATE MAINTENANCESTATEWIDE HIGHWAYREGIONAL HIGHWAYDIVISON HIGHWAYDIVISION BIKE/PEDESTRIANINTERSTATE ROUTEUS ROUTENC ROUTESECONDARY ROADMUNICIPAL BOUNDARIESMILITARY BASENCDOT DIVISION BOUNDARYCOUNTY BOUNDARYWATER FEATURES

* Note: Reflects 108 of the Major Transition ProjectsNote: FY 2015 projects represent major projects not

let as of November 2014

Page 3: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

COUNTY

FUTURE YEARS

F

NHPB - National Highway Performance Program (Bridge)NHPIM - National Highway Performance Program (Interstate Maintenance)O - OthersRR - Rail-Highway SafetyS (M) - State MatchSRTS - Safe Routes to School

FLPI - Federal Lands Program (Indian Reservation Roads) STP - Surface Transportation ProgramHFB - Highway Fund Bridge Replacement Program STPDA - Surface Transportation Program - Direct AttributableHP - Federal-Aid High Priority STPEB - Surface Transportation Program, Enhancements (Bike)

STPON - Surface Transportation Program Bridge (On System Bridge)STPOFF -Surface Transportation Program (Off System Bridge) PE - Preliminary EngineeringT - State Highway Trust Funds

NHP - National Highway Performance Program TAP - Transportation Alternatives Program RG - Right of Way (GARVEE)

SW - StatewideTRN -Transition Project

S - StructureU - Utilities

I - ImplementationL - LandscapingM - MitigationO - OperationsP - Paving

WAKE

NUMBERLENGTH (MILES)

DIVISION 00

R-0000

IDROUTE/CITY

US or NC RoutesON NEW LOCATION. I - InterstateWITH A BYPASS OF HOMETOWN ROUTE/CITY

Project termini and a general

SW

M1500

A

NHP

4000

FUNDING CATEGORY (1)

used for each project phase.

FUNDING SOURCE (2)

U

B3000R

FY 2017

C

(3) WORK TYPE (ACTIVITY)

A - Acquisition

with proposed work type or activity beginning in the initial scheduled year. (Estimates are in thousand of

For other work types or activities see Work Type (Activity) box below.

dollars.)

of a project segment indicates (Cash-Flow Funding) COMMITMENTSFUTURE

SW CBSW

One or two letter

HIGHWAY PROGRAM

UNFUNDED

NC 3 TO SR 1003SR 1003 TO NC 96

ASW

UNFUNDED

20000CRC 5000C 5000 BC B

WIDEN TO A FOUR-LANE FACILITY

A

NC 00 R7.3 R25063,450I-40 TO NC 96 EAST OF HOMETOWN.

B

FY 2025 FY 2018

700

FY 2019

DEVELOPMENTAL PROGRAMSTATE TRANSPORTATION IMPROVEMENT PROGRAM

FY 2020FY 2015 FY 2016

M

TOTAL PROJECT

COST (THOU)

NHPNHP

FUN

DS

A

PRIOR YEARS COST

(THOU)

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

U 5000NHP

C10000

FY 2021

C

FY 2023 FY 2024

FY 2022

5000

9000

APD - Appalachian Development

NHPNHP

LOCATION / DESCRIPTION NHP

NHP

I-40 TO NC 3

Preliminary engineering, Right of Way, Mitigation, Utilities or Construction. break.

work description.

way, utility, mitigation and construction cost estimates

See Highway Funding Key

any project breaks.Category for the project andIdentifies the "STI" Funding

by funding category in current dollars. Cost may include one or more funding types. Multi-year funding

for an explanation of funding categories

Phases of implementation: ESTIMATED COST Preliminary engineering, right of

(1) FUNDING CATEGORY

PROJECT BREAKS

designation for project

LOCATION / DESCRIPTION

SR - Secondary Road

IDENTIFICATION NUMBER Assigned to each project at conception and remains with

BVarious - multiple routesNEW ROUTE or City

WORK TYPE (ACTIVITY) (3)

BOND (R) - Revenue Bond

HRRR - High Risk Rural Roads

L - LocalHSIP - Highway Safety Improvement Program

project until completion.

DIV - DivisionEX - Exempt

REG - RegionalHF - State Dollars (Non-STI)

F - Feasibility StudyCG - Construction (GARVEE)C - Construction

G - Grading and Structures

R - Right of Way

(2) FUNDING KEY FOR HIGHWAY FUNDING SOURCES

ER - Emergency Relief Funds

CMAQ - Congestion MitigationDP - Discretionary or Demonstration

FED - Federal Rail Funds

Page 4: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS

UNDER CONSTRUCTION

R-3101 28196 18210ROARING GAP TO SPARTA. UPGRADE ROADWAY TO TWENTY-FOUR FEET WITH TWO FOOT PAVED SHOULDERS.

12TRN

STP 9986C ALLEGHANY US 21

PLANNING/DESIGN IN PROGRESS

R-4060 9639 839SR 1172 (GRANDVIEW DRIVE) TO US 21. TWO LANES ON NEW LOCATION.

0.8

DIV

T 2200R T 200U T C 6400

ALLEGHANY US 21SPARTA WESTERNLOOP

FEDERAL BRIDGE PROJECTSB-5388 6491REPLACE BRIDGE NO. 21 OVER LITTLE

RIVER.

HF

HFB R 590 HFB M 1 HFB C 5900

ALLEGHANY NC 18

UNDER CONSTRUCTION

B-4701 1437 1437REPLACE BRIDGE NO. 15 OVER ELK CREEK.

DIV

ALLEGHANY SR 1341(OSBORNEMEMORIAL ROAD)

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-7 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 5: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

RURAL PROJECTS

PLANNING/DESIGN IN PROGRESS

R-2915 180750 28678US 421 IN WATAUGA COUNTY TO US 221 BUSINESS/NC 88 IN JEFFERSON. WIDEN TO FOUR LANES DIVIDED.

16.1 STP 13150C A C 13150 A STP 11550C B C 11550 B STP 15000R C STP 720U C STP 2M C STP C 11000 C C 11000 C C 11000 C C 11000 C STP 13300C D C 13300 D STP R 900 E STP U 50 E STP C 15400 E

A US 421 IN WATAUGA COUNTY TO SR 1003 (IDLEWILD ROAD) IN ASHE COUNTY - RIGHT OF WAY IN PROGRESSTRNB SR 1003 (IDLEWILD ROAD) TO NORTH OF SOUTH FORK NEW RIVER - RIGHT OF WAY IN PROGRESSTRNC NORTH OF SOUTH FORK NEW RIVER TO SOUTH OF NC 194DIVD SOUTH OF NC 194 TO US 221 BYPASS - RIGHT OF WAY IN PROGRESSTRNE US 221 BYPASS TO US 221 BUSINESS/NC 88 IN JEFFERSONDIV

ASHEWATAUGA

US 221

URBAN PROJECTS

UNDER CONSTRUCTION

U-3812 10410 10410NC 194 TO US 221 BUSINESS IN JEFFERSON. UPGRADE EXISTING ROADWAY.

1.6ASHE NC 88

FEDERAL BRIDGE PROJECTSB-5821 3520REPLACE BRIDGE NO. 10 OVER SOUTH

FORK NEW RIVER.HF

HFB R 320 HFB 3200C

ASHE US 221

B-4704 2795 100REPLACE BRIDGE NO. 49 OVER BUFFALO CREEK.

HF

HFB R 245 HFB C 2450

ASHE NC 88

B-5823 735REPLACE BRIDGE NO. 355 OVER SOUTH FORK NEW RIVER.

DIV

STPOFF R 35 STPOFF 700C

ASHE SR 1181(HARTSOG FORD ROAD)

B-5830 505REPLACE BRIDGE NO. 177 OVER BEAVER CREEK.

DIV

STPOFF R 25 STPOFF C 480

ASHE SR 1181(HARTSOG FORD ROAD)

11-8 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 6: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS

B-4016 972 312REPLACE BRIDGE NO. 273 OVER BIG HORSE CREEK.

HF

HFB R 60 HFB C 600

ASHE SR 1347(TEABERRY ROAD)

B-3804 4264 59REPLACE BRIDGE NO. 296 OVER NORTH FORK NEW RIVER.

HF

HFB R 380 HFB C 3825

ASHE SR 1351(CAMPBELL ROAD)

UNDER CONSTRUCTION

B-4705 917 917REPLACE BRIDGE NO. 69 OVER LITTLE HELTON CREEK.

DIV

ASHE SR 1376(JOE THOMAS ROAD)

B-5504 1980REPLACE BRIDGE NO. 337 OVER NORTH FORK NEW RIVER.

DIV

STPOFF R 180 STPOFF C 1800

ASHE SR 1503(LOW WATER BRIDGEROAD)

B-5147 725 300REPLACE BRIDGE NO. 327 OVER CREEK.

HF

HFB R 40 HFB C 385

ASHE SR 1509(CLAYBANK ROAD)

B-5838 385REPLACE BRIDGE NO. 309 OVER SILAS CREEK.

HF

HFB 35R HFB 350C

ASHE SR 1523(SILAS CREEK ROAD)

B-4706 685REPLACE BRIDGE NO. 48 OVER BIG HELTON CREEK.

HF

HFB R 60 HFB C 625

ASHE SR 1527(HELTON ROAD)

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-9 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 7: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

RURAL PROJECTS

PLANNING/DESIGN IN PROGRESS

R-2566* 113105 2455US 221 TO SR 1107 (NC 105 BYPASS) IN BOONE. WIDEN TO MULTI-LANES.

14.8 NHP 1000R A NHP 60350C A NHP 1000R B NHP 6800U B NHP 40000C B NHP R 100 BA NHP C 1400 BA

A US 221 IN AVERY COUNTY TO SR 1136 (CLARKS CREEK ROAD) IN WATAUGA COUNTY.B SR 1136 (CLARKS CREEK ROAD) TO SR 1107 (NC 105 BYPASS) IN BOONE.REGBA CONSTRUCT NEW BRIDGE OVER WATAUGA RIVER AND LEFT-TURN LANE AT SR 1112 (BROADSTONE ROAD). - WITHIN THE LIMITS OF R-2566 BDIV

AVERYWATAUGA

NC 105

FEDERAL BRIDGE PROJECTSB-5380 805 200REPLACE BRIDGE NO. 141 OVER CREEK.

HF

HFB R 55 HFB C 550

AVERY SR 1114(BIG PLUMTREECREEK ROAD)

UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BK-5117 765 765REPLACE BRIDGE NO. 16 OVER HORSE CREEK.DIV

AVERY SR 1166

B-5524 440REPLACE BRIDGE NO. 149 OVER HORSE CREEK.

HF

HFB R 40 HFB C 400

AVERY SR 1168(TUCKER HOLLOWROAD)

B-5835 790REPLACE BRIDGE NO. 125 OVER ELK RIVER.

DIV

STPOFF 40R STPOFF 750C

AVERY SR 1306(HICKS HOLLOW ROAD)

B-5383 1020 200REPLACE BRIDGE NO. 143 OVER LINVILLE RIVER.

HF

HFB R 95 HFB C 725

AVERY SR 1536(GREENE ROAD)

11-10 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 8: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

11-11 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 9: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS

R-5745 235INTERSECTION OF US 64/NC 90/NC 18 (WILKESBORO BOULEVARD) AND US 64/NC 90 (TAYLORSVILLE ROAD). CONSTRUCT INTERSECTION IMPROVEMENTS.DIV

T 45R T C 190

CALDWELL US 64/NC 90/NC 18(WILKESBORO BLVD)

R-2237* 254862 237266NORTH OF NC 268 TO MULTI-LANES NORTH OF BLOWING ROCK. WIDEN TO MULTI-LANES.

15.3 T 17596C C

A NORTH OF NC 268 TO SR 1370 (KIRBY MOUNTAIN ROAD) - COMPLETEB SR 1370 (KIRBY MOUNTAIN ROAD) TO SR 1500 (BLACKBERRY ROAD) - COMPLETEC SR 1500 (BLACKBERRY ROAD) TO US 221 AT BLOWING ROCK - UNDER CONSTRUCTIONTRN

CALDWELLWATAUGA

US 321

URBAN PROJECTS

PLANNING/DESIGN IN PROGRESS - INCLUDES B-4450

U-4700 440818 4090US 70 IN HICKORY TO US 64/NC 18/NC 90 IN LENOIR. WIDEN TO SIX LANES.

17.2 NHP R 50750 A R 50750 A NHP M 586 A NHP 17525C A17525C A9175C A C 17525 A HP 8350C A NHP 25400R B NHP 2372M B NHP 41800C B NHP 94400R C NHP 98400C C NHP R 420 CA NHP C 583 CA 583C CA584C CA

A US 70 IN HICKORY TO US 321ASWB US 321A TO SR 1108 (MISSION ROAD)C SR 1108 (MISSION ROAD) TO US 64/NC 18/NC 90 IN LENOIRCA SR 1160 (MOUNT HERMAN ROAD). UPGRADE INTERSECTION TO SUPERSTREET DESIGN. - WITHIN THE LIMITS OF U-4700 C.REG

BURKECALDWELLCATAWBA

US 321

U-2211 39149 39149SR 1933 (SOUTHWEST BOULEVARD) TO SR 1712 (STARCROSS ROAD) EAST OF US 321 IN LENOIR. WIDEN TO MULTILANES WITH CURB AND GUTTER, PART ON NEW LOCATION AND CONSTRUCT AN INTERCHANGE AT US 321.

1.6

A SOUTH OF SR 1933 (SOUTHWEST BOULEVARD) TO NORTH OF US 321A (NORWOOD STREET) - COMPLETEB US 321A (NORWOOD STREET) TO SR 1712 (STARCROSS ROAD) EAST OF US 321 - UNDER CONSTRUCTION

CALDWELL SR 1001 (HIBRITENDRIVE)

UNDER CONSTRUCTION

U-5204 7566 7566GRACE CHAPEL ROAD TO TOWN STREET IN HICKORY. CONSTRUCT A TWO-LANE FACILITY ON NEW LOCATION.

CALDWELL NEW ROUTE

U-5615 42525STP-DA IN THE GREATER HICKORY METROPOLITAN PLANNING ORGANIZATION (MPO) AREA.

DIV

STPDA 8100C C 2700 C 2700 C 2700 C 2700 C 2700 2700C2700C2700C C 2700 C 1350L 2025C C 675 C 675 C 675 C 675 C 675 675C675C675C C 675 C 675

ALEXANDERBURKECALDWELLCATAWBA

VARIOUS

PLANNING/DESIGN/LET BY DIVISION

U-5776 235INTERSECTION OF SR 1106 (DUKE STREET) AND US 321A. REALIGN INTERSECTION.

REG

T R 45 T C 190

CALDWELL GRANITE FALLS

UNDER CONSTRUCTION

U-3437 1912 1912INTERSECTION OF SR 1160 (MT. HERMAN ROAD) AND ROY E. COFFEY DRIVE IN HUDSON. INTERSECTION IMPROVEMENTS.

CALDWELL HUDSON

FEASIBILITY STUDIES

FEASIBILITY STUDY RE-EVALUATION IN PROGRESS

U-2543 188 188SR 1107 (FALLS AVENUE) IN GRANITE FALLS TO SR 1180 (MCLEAN DRIVE) IN LENOIR. TWO-LANE UPGRADE.

8.6CALDWELL US 321A

FEDERAL BRIDGE PROJECTS

UNDER CONSTRUCTION

B-5138 1269 1269REPLACE BRIDGE NO. 6 OVER LITTLE GUNPOWDER CREEK.REG

CALDWELL US 321A

11-12 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 10: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS

TO BE CONSTRUCTED WITH U-4700

B-4450 17 17REPLACE BRIDGE NO. 367 OVER CATAWBA RIVER.

CALDWELL US 321

UNDER CONSTRUCTION

B-3819 1093 1093REPLACE BRIDGE NO. 184 OVER JOHNS RIVER.

DIV

CALDWELL SR 1356(OLD JOHNS RIVER ROAD)

UNDER CONSTRUCTION

B-4721 687 687REPLACE BRIDGE NO. 57 OVER MIDDLE LITTLE RIVER.

DIV

CALDWELL SR 1732(MILL POND ROAD)

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

B-5385 440REPLACE BRIDGE NO. 123 OVER ESTES MILL CREEK.

HF

HFB R 40 HFB C 400

CALDWELL SR1356(OLD JOHNS RIVERROAD)

MUNICIPAL BRIDGE PROJECTS

UNDER CONSTRUCTION - CITY OF LENOIR - MUNICIPAL PROJECT

B-5011 719 719REPLACE BRIDGE NO. 74 OVER LOWER CREEK.

DIV

CALDWELL LENOIR(FAIRVIEW DRIVE)

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-13 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 11: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

ROADSIDE ENVIRONMENTAL PROJECTS (SCENIC)

UNDER CONSTRUCTION - 2012 NATIONAL SCENIC BYWAYS GRANT

S-5504 57 57UPPER YADKIN WAY SCENIC BYWAY. INSTALL WAYSHOWING SIGNAGE.

CALDWELLWILKES

UPPER YADKINWAY SCENICBYWAY

INTERSTATE PROJECTS

PROJECT COMPLETE - GARVEE BOND FUNDING $4.69 MILLION; PAYBACK FY 2007 - FY 2018

I-5002 12090 10034I-77 TO US 601. PAVEMENT REHABILITATION. 6TRN

NHP 514CG CG 514 CG 514 CG 514 SURRY I-74

I-5862 4000VIRGINIA STATE LINE TO I-77. PAVEMENT REHABILITATION.

4.9SW

NHPIM C 4000 SURRY I-74

I-5863 24000.3 MILE EAST OF SR 2258 (OLD 601) TO 0.6 MILE EAST OF US 52. PAVEMENT REHABILITATION.

5.2SW

NHPIM C 2400 SURRY I-74

I-5830 29930.3 MILE NORTH OF SR 1345 (BEULAH ROAD) TO I-74. PAVEMENT REHABILITATION.

2.2SW

NHPIM C 2993 SURRY I-77

I-5829 3684SR 1122 (DOBBINS MILL ROAD) TO SR 1341 (WHITE DIRT ROAD). PAVEMENT REHABILITATION.

4.4SW

NHPIM C 3684 SURRY I-77

I-5803 2300SR 1341 (WHITE DIRT ROAD) TO 1.3 MILES NORTH OF SR 1345 (BEULAH CHURCH ROAD). PAVEMENT REHABILITATION.

4SW

NHPIM C 2300 SURRY I-77

I-5802 1650SR 1131 (FAX WELBORN ROAD) TO 1 MILE NORTH OF SR 1131 (FAX WELBORN ROAD). PAVEMENT REHABILITATION.

1SW

NHPIM C 1650 SURRY I-77

I-5801 9001.2 MILES NORTH OF US 21 TO 0.4 MILE NORTH OF SR 1136 (EBENEZER CHURCH ROAD). PAVEMENT REHABILITATION.

1SW

NHPIM C 900 SURRY I-77

UNDER CONSTRUCTION

I-5603 3085 3085MILEMARKER 95 TO MILEMARKER 99. PAVEMENT REHABILITATION.

4SURRY I-77

11-14 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 12: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025INTERSTATE PROJECTS

SECTION A - GARVEE BOND FUNDING $35 MILLION; PAYBACK FY 2007 - FY 2018

I-2808 139806 63822SOUTH OF SR 1125 (MILE MARKER 71) IN YADKIN COUNTY TO US 21 BYPASS (MILE MARKER 83.5) IN SURRY COUNTY (EXIT 83). PAVEMENT REHABILITATION.

12 NHP 3746CG A CG 3746 A CG 3746 A CG 3746 A NHP 61000C B

A SOUTH OF SR 1125 (ASHBURY CHURCH ROAD-MILEPOST 71) TO US 21 IN YADKIN COUNTY (EXIT 79) - COMPLETETRNB US 21 IN YADKIN COUNTY (EXIT 79) TO US 21 BYPASS (EXIT 83) IN SURRY COUNTY

SURRYYADKIN

I-77

I-5749 1600SR 1341 (WHITE DIRT ROAD) TO 1.3 MILES NORTH OF SR 1345 (BEULAH ROAD). PAVEMENT REHABILITATION.

4SW

NHPIM C 1600 SURRY I-77

RURAL PROJECTS

SCHEDULED FOR FEASIBILITY STUDY

FS-1511A I-74 TO SR 1104 (CODY TRAIL). WIDEN TO 4-LANES.

7.2SURRY US 601

R-5714 6200US 52 TO SR 1365 (FORREST DRIVE). UPGRADE ROADWAY.

1

REG

T R 850 850R T U 100 100U T 4300C

SURRY US 601

UNDER CONSTRUCTION BY MOUNT AIRY-SURRY COUNTY AIRPORT

R-5309 1000 1000JANICE DRIVE TO COTTAGE DRIVE. RELOCATE ROADWAY FOR MOUNT AIRY-SURRY COUNTY AIRPORT RUNWAY EXTENSION.

1.2

TRN

SURRY SR 1627 (HOLLYSPRINGS ROAD)

FEDERAL BRIDGE PROJECTSB-5831 13000REPLACE BRIDGE NO. 6 OVER NC 268,

SOUTHERN RR, AND YADKIN RIVER.SW

NHPB 600R NHPB 6200C6200C

SURRY I-77 NORTH

B-5527 4550REPLACE BRIDGE NO. 122 OVER TOMS CREEK.

SW

NHPB R 400 NHPB C 2075 2075C

SURRY US 52 (NORTH-BOUND LANE)

B-5836 2640REPLACE BRIDGE NO. 15 OVER MITCHELL RIVER.

HF

HFB 240R HFB 2400C

SURRY SR 1315(ZEPHYR MOUNTAINPARK ROAD)

B-5173 1133 200REPLACE BRIDGE NO. 39 OVER MITCHELL RIVER.

DIV

STPOFF 85R STPOFF 23U STPOFF C 825

SURRY SR 1328(HAYSTACK ROAD)

B-5841 1870REPLACE BRIDGE NO. 62 OVER STEWARTS CREEK.

HF

HFB 170R HFB 1700C

SURRY SR 1350(RED BRUSH ROAD)

UNDER CONSTRUCTION

B-4821 1624 1624REPLACE BRIDGE NO. 88 OVER PAUL'S CREEK.

DIV

SURRY SR 1621(SPARGER ROAD)

B-5824 1870REPLACE BRIDGE NO. 92 OVER PAULS CREEK.

HF

HFB R 170 HFB 1700C

SURRY SR 1624(DON BARE ROAD)

B-5837 1160REPLACE BRIDGE NO. 129 OVER FLAT SHOAL CREEK.

DIV

STPOFF R 60 STPOFF C 1100

SURRY SR 2017(ARARAT ROAD)

B-5832 3800REPLACE BRIDGE NO. 152 OVER ARARAT RIVER.

DIV

STPOFF 200R STPOFF 1800C1800C

SURRY SR 2080(QUAKER CHURCHROAD)

11-15 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 13: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

UNDER CONSTRUCTION - PURCHASE ORDER CONTRACT (POC)

SF-4911E 50 50US 52, STOKES COUNTY LINE TO US 52 BUSINESS. INSTALL SHOULDER RUMBLE STRIPS.

12.5SURRY US 52

UNDER CONSTRUCTION

W-5307 2074 2074SOUTH OF NC 18 TO SOUTH OF NC 18. CURVE RE-ALIGNMENT, PAVEMENT WIDENING, AND PAVED SHOULDERS.

0.2SURRY NC 89

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-16 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 14: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

ROADSIDE ENVIRONMENTAL PROJECTS (SCENIC)

IN PROGRESS - 2012 NATIONAL SCENIC BYWAYS GRANT

S-5503 68 68YADKIN VALLEY SCENIC BYWAY WAYFINDING PROGRAM.

SURRYYADKIN

YADKIN VALLEYSCENIC BYWAY

RURAL PROJECTS

PLANNING/DESIGN IN PROGRESS

R-2915 180750 28678US 421 IN WATAUGA COUNTY TO US 221 BUSINESS/NC 88 IN JEFFERSON. WIDEN TO FOUR LANES DIVIDED.

16.1 STP 13150C A C 13150 A STP 11550C B C 11550 B STP 15000R C STP 720U C STP 2M C STP C 11000 C C 11000 C C 11000 C C 11000 C STP 13300C D C 13300 D STP R 900 E STP U 50 E STP C 15400 E

A US 421 IN WATAUGA COUNTY TO SR 1003 (IDLEWILD ROAD) IN ASHE COUNTY - RIGHT OF WAY IN PROGRESSTRNB SR 1003 (IDLEWILD ROAD) TO NORTH OF SOUTH FORK NEW RIVER - RIGHT OF WAY IN PROGRESSTRNC NORTH OF SOUTH FORK NEW RIVER TO SOUTH OF NC 194DIVD SOUTH OF NC 194 TO US 221 BYPASS - RIGHT OF WAY IN PROGRESSTRNE US 221 BYPASS TO US 221 BUSINESS/NC 88 IN JEFFERSONDIV

ASHEWATAUGA

US 221

R-2237* 254862 237266NORTH OF NC 268 TO MULTI-LANES NORTH OF BLOWING ROCK. WIDEN TO MULTI-LANES.

15.3 T 17596C C

A NORTH OF NC 268 TO SR 1370 (KIRBY MOUNTAIN ROAD) - COMPLETEB SR 1370 (KIRBY MOUNTAIN ROAD) TO SR 1500 (BLACKBERRY ROAD) - COMPLETEC SR 1500 (BLACKBERRY ROAD) TO US 221 AT BLOWING ROCK - UNDER CONSTRUCTIONTRN

CALDWELLWATAUGA

US 321

R-2615* 58400US 321/US 421 JUNCTION NEAR VILAS TO SR 1107 (105 BYPASS) - TERMINI OF PROPOSED BOONE BYPASS (U-2703). WIDEN TO MULTI-LANES.

3.5

REG

T 26500R T 3200U T 21525C C 7175

WATAUGA US 421/US 321

11-17 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 15: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025RURAL PROJECTS

PLANNING/DESIGN IN PROGRESS

R-2566* 113105 2455US 221 TO SR 1107 (NC 105 BYPASS) IN BOONE. WIDEN TO MULTI-LANES.

14.8 NHP 1000R A NHP 60350C A NHP 1000R B NHP 6800U B NHP 40000C B NHP R 100 BA NHP C 1400 BA

A US 221 IN AVERY COUNTY TO SR 1136 (CLARKS CREEK ROAD) IN WATAUGA COUNTY.B SR 1136 (CLARKS CREEK ROAD) TO SR 1107 (NC 105 BYPASS) IN BOONE.REGBA CONSTRUCT NEW BRIDGE OVER WATAUGA RIVER AND LEFT-TURN LANE AT SR 1112 (BROADSTONE ROAD). - WITHIN THE LIMITS OF R-2566 BDIV

AVERYWATAUGA

NC 105

UNDER CONSTRUCTION. ARC PROJECT NO. 17476

R-5525 2476 2476BLOWING ROCK POST ACUTE CARE FACILITY. CONSTRUCT ACCESS ROAD.

0.25TRN

WATAUGA BLOWING ROCK

URBAN PROJECTSU-5705 2350NC 105 INTERSECTION. CONSTRUCT

UPGRADES.SW

NHP R 450 NHP 1900C

WATAUGA US 221/321

PLANNING/DESIGN/LET BY DIVISION

U-5715 235COLLEGE STREET INTERSECTION. CONSTRUCT IMPROVEMENTS.

SW

NHP R 45 NHP C 190

WATAUGA US 321/421, NC 194(KING STREET)

U-5603 6500US 321 (BLOWING ROCK ROAD) TO NC 105 BYPASS. UPGRADE ROADWAY.

2.1

DIV

NHP R 1100 NHP 5400C

WATAUGA NC 105

U-5867 17200US 421 (KING STREET) TO SR 1306 (HOWARDS CREEK ROAD). WIDEN TO MULTI-LANES.

1.6

DIV

T 4000R T 500U T 6350C C 6350

WATAUGA NC 194

U-5810 3100US 421/US 221 TO SR 1522 (DEERFIELD ROAD). WIDEN ROADWAY TO 12-FEET LANES WITH 4-FEET PAVED SHOULDERS.

1.9

DIV

T R 100 T C 3000

WATAUGA SR 1514 (BAMBOOROAD); SR 1523(WILSON RIDGE)

FEDERAL BRIDGE PROJECTSB-5829 4100REPLACE BRIDGE NO. 5 OVER WATAUGA

RIVER.SW

NHPB R 200 NHPB 1950C1950C

WATAUGA NC 105

B-4670 390 5REPLACE BRIDGE NO. 200 OVER CREEK.

DIV

STPOFF 35R STPOFF C 350

WATAUGA SR 1130(WORLEY ROAD)

BRIDGE PURCHASE ORDER CONTRACT (BPOC) - UNDER CONSTRUCTION

BK-5119 469 469REPLACE BRIDGE NO. 25 OVER CREEK.DIV

WATAUGA SR 1225

B-5386 440REPLACE BRIDGE NO. 87 OVER NORTH FORK CREEK.

DIV

STPOFF R 40 STPOFF C 400

WATAUGA SR 1227(NORTH FORK ROAD)

UNDER CONSTRUCTION

B-4836 2008 2008REPLACE BRIDGE NO. 59 OVER SOUTH FORK NEW RIVER.

DIV

WATAUGA SR 1331(ROBY GREENE ROAD)

B-5532 355REPLACE BRIDGE NO. 142 OVER CREEK.

DIV

STPOFF R 30 STPOFF C 325

WATAUGA SR 1359(BROWNWOOD ROAD)

11-18 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 16: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS

B-5177 3100 100REPLACE BRIDGE NO. 278 OVER MIDDLE FORK CREEK AND REALIGN INTERSECTIONS OF US 321 WITH SR 1540 AND SR 1531.

HF

HFB R 500 HFB C 2500

WATAUGA SR 1540(TWEETSIERAILROAD)

B-5118 881 250REPLACE BRIDGE NO. 55 OVER CREEK.

DIV

STPOFF 40R STPOFF 116U STPOFF C 475

WATAUGA SR 1557(SHULL'S MILL ROAD)

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-19 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 17: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

UNDER CONSTRUCTION

E-4955 287 287PHASE I: WILSON DRIVE IN BOONE. CONSTRUCT FOUR-FOOT PAVED SHOULDERS.

WATAUGA BOONE

RURAL PROJECTS

UNDER CONSTRUCTION

R-3405 23879 23879SR 1002 (MOUNTAIN VIEW ROAD) TO SR 1717. WIDEN TO THREE LANES.

3.5WILKES NC 18

RIGHT OF WAY IN PROGRESS

R-2603 35569 10369NC 18 TO SR 1966 (AIRPORT ROAD). CONSTRUCT SIDEWALK FROM NC 18 TO SHAVER STREET. WIDEN TO FIVE-LANES FROM SHAVER STREET TO FAIRPLAINS ROAD. WIDEN TO FOUR-LANES DIVIDED FROM FAIRPLAINS ROAD TO SR 1966 (AIRPORT ROAD).

3.6TRN

STP 8400C C 8400 C 8400 WILKES NC 268

R-3309 125200SR 1966 TO THE ELKIN BYPASS. UPGRADE ROADWAY.

13.5

DIV

STP 1000R STP 41400C C 41400 C 41400

WILKES NC 268

UNDER CONSTRUCTION

R-5186 756 756WILKES INDUSTRIAL PARK. EAST OF INTERSECTION OF RIVER ROAD, LIBERTY GROVE ROAD AND COLONIAL DRIVE NORTHEAST TO LIBERTY GROVE ROAD. CONSTRUCT ACCESS ROAD TO PARK.

WILKES NEW ROUTE

URBAN PROJECTSU-5312 22200 1000NC 16 TO US 421 BUSINESS. CONVERT

EXISTING ROADWAY TO SUPER STREET AND ADD SERVICE ROADS.

2.6

REG

NHP R 2600 NHP U 4500 NHP 7050C7050C

WILKES US 421

FEDERAL BRIDGE PROJECTS

RIGHT OF WAY IN PROGRESS

B-4676 2100 250REPLACE BRIDGE NO. 29 OVER CUB CREEK.

DIV

STPOFF 1850C WILKES SR 1001(OAKWOODS ROAD)

11-20 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 18: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025FEDERAL BRIDGE PROJECTS

B-5826 715REPLACE BRIDGE NO. 136 OVER MULBERRY CREEK.

HF

HFB R 65 HFB 650C

WILKES SR 1002(MOUNTAIN VIEW ROAD)

B-4978 1640 100REPLACE BRIDGE NO. 82 OVER SOUTH PRONG LEWIS FORK CREEK.

HF

HFB R 140 HFB C 1400

WILKES SR 1154(MT PLEASANT ROAD)

DIVISION PURCHASE ORDER CONTRACT (DPOC)

B-4977 650 100REPLACE BRIDGE NO. 75 OVER FISH DAM CREEK.

HF

HFB R 50 HFB C 500

WILKES SR 1313(CONGO ROAD)

B-5828 420REPLACE BRIDGE NO. 340 OVER SOUTH FORK REDDIES RIVER.

DIV

STPOFF 20R STPOFF 400C

WILKES SR 1355(WHITE OAK ROAD)

B-5842 370REPLACE BRIDGE NO. 110 OVER NORTH PRONG LEWIS FORK CREEK.

DIV

STPOFF R 20 STPOFF C 350

WILKES SR 1363(BIG IVY ROAD)

UNDER CONSTRUCTION

B-5146 1564 1564REPLACE BRIDGE NO. 302 OVER MIDDLE FORK OF REDDIES RIVER.

DIV

WILKES SR 1562(OLD NC 16)

UNDER CONSTRUCTION

B-4325 1232 1232REPLACE BRIDGE NO. 718 OVER MIDDLE FORK REDDIES RIVER.

DIV

WILKES SR 1580(KUENZEL ELLER DRIVE)

B-5523 385REPLACE BRIDGE NO. 168 OVER CREEK.

DIV

STPOFF R 35 STPOFF C 350

WILKES SR 1725(CANE CREEKCHURCH ROAD)

B-5834 210REPLACE BRIDGE NO. 235 OVER CREEK.

DIV

STPOFF 10R STPOFF 200C

WILKES SR 1753(ROARING GAPCHURCH)

B-5525 1320REPLACE BRIDGE NO. 436 OVER EAST PRONG ROARING RIVER.

HF

HFB R 120 HFB C 1200

WILKES SR 1943(BREWER HILL ROAD)

UNDER CONSTRUCTION

B-4846 1192 1192REPLACE BRIDGE NO. 5 OVER LITTLE HUNTING CREEK.

DIV

WILKES SR 2418(MITCHELL MILLROAD)

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-21 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 19: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTSW-5521 3220US 421 NEAR SR 1301 (FALL CREEK ROAD).

REALIGNMENT, MEDIAN BARRIER INSTALLATION, AND RUMBLE STRIPS.SW

HSIP 320R HSIP C 1450 C 1450

WILKES US 421

UNDER CONSTRUCTION - PURCHASE ORDER CONTRACT (POC)

SF-4911D 825 825INTERSECTION OF NC 16 AND 18 NORTH TO SR 2545 (PLAZA DRIVE). CONSTRUCT A TWO-WAY LEFT TURN LANE AND INSTALL A SOUTHBOUND LEFT TURN LANE ON NC 16/NC 18 AT SR 2545.

WILKES NC 16/NC 18

W-5503 6650 600NC 268 EAST OF NORTH WILKESBORO. WIDEN MULTIPLE SECTIONS AND IMPROVE SHOULDERS.REG

HSIP 3125R HSIP 2925C

WILKES NC 268

RIGHT OF WAY IN PROGRESS

W-5511 1600 225SR 2324 (RED, WHITE, AND BLUE ROAD) NEAR SR 2326 (RUTH LINNEY ROAD). IMPROVE HORIZONTAL AND VERTICAL ALIGNMENTS ON SR 2324 NEAR SR 2326 AND REPLACE BRIDGE NO. 193.

DIV

HSIP 1375C WILKES SR 2324

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-22 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 20: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ENHANCEMENT (CALL PROJECTS)

UNDER CONSTRUCTION

E-4975 576 576BLUE RIDGE NATIONAL HERITAGE SITES. INTERPRETATIVE AND GATEWAY MARKERS.

ALLEGHANYASHEAVERYBUNCOMBEBURKECALDWELLCHEROKEECLAYGRAHAMHAYWOODHENDERSONJACKSONMACONMADISONMcDOWELLMITCHELLPOLKRUTHERFORDSURRYSWAINTRANSYLVANIAWATAUGAWILKESYANCEY

VARIOUS

ROADSIDE ENVIRONMENTAL PROJECTS (SCENIC)

UNDER CONSTRUCTION - 2012 NATIONAL SCENIC BYWAYS GRANT

S-5504 57 57UPPER YADKIN WAY SCENIC BYWAY. INSTALL WAYSHOWING SIGNAGE.

CALDWELLWILKES

UPPER YADKINWAY SCENICBYWAY

INTERSTATE PROJECTSI-5865 17000.6 MILE NORTH OF SR 1103 (MARIER RD) TO

0.9 MILE NORTH OF SR 1316 (RENA RD). PAVEMENT REHABILITATION.

2SW

NHPIM C 1700 YADKIN I-77

I-5864 21000.8 MILE NORTH OF SR 1125 (ASBURY CHURCH) TO 0.8 MILE NORTH OF SR 1314 (OLD US 421). PAVEMENT REHABILITATION.

1.8SW

NHPIM C 2100 YADKIN I-77

SECTION A - GARVEE BOND FUNDING $35 MILLION; PAYBACK FY 2007 - FY 2018

I-2808 139806 63822SOUTH OF SR 1125 (MILE MARKER 71) IN YADKIN COUNTY TO US 21 BYPASS (MILE MARKER 83.5) IN SURRY COUNTY (EXIT 83). PAVEMENT REHABILITATION.

12 NHP 3746CG A CG 3746 A CG 3746 A CG 3746 A NHP 61000C B

A SOUTH OF SR 1125 (ASHBURY CHURCH ROAD-MILEPOST 71) TO US 21 IN YADKIN COUNTY (EXIT 79) - COMPLETETRNB US 21 IN YADKIN COUNTY (EXIT 79) TO US 21 BYPASS (EXIT 83) IN SURRY COUNTY

SURRYYADKIN

I-77

RURAL PROJECTSR-5733 12900CONSTRUCT NEW INTERCHANGE ON US 421

BETWEEN EXISTING EXITS 257 AND 259.

DIV

T 100R T 100U T 12700C

YADKIN US 421

R-5730 31400SR 1146 (SHACKTOWN ROAD) TO SR 1711 (SPEER BRIDGE ROAD). CONSTRUCT NEW ROADWAY TO REALIGN SR 1605 WITH SR 1711 AND CONSTRUCT A ROUNDABOUT AT THE INTERSECTION WITH SR 1146.

0.2

DIV

T R 5200 T U 600 T 12800C12800C

YADKIN SR 1605 (OLD US 421)

11-23 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 21: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025URBAN PROJECTS

U-5809 10300US 421 TO SR 1146 (LEE AVENUE). CONSTRUCT MEDIAN AND ROUNDABOUTS.

0.6

DIV

T R 1500 T U 200 T 8600C

YADKIN US 601 (STATESTREET)

FEDERAL BRIDGE PROJECTSB-5833 6400REPLACE BRIDGE NO. 29 OVER I-77.

REG

NHPB 300R NHPB 3050C3050C

YADKIN US 21 BUSINESS

B-4979 1395REPLACE BRIDGE NO. 59 OVER JONESVILLE CREEK.

HF

HFB R 120 HFB C 1275

YADKIN US 21 BUSINESS

B-5389 7480REPLACE BRIDGE NO. 105 OVER YADKIN RIVER OVERFLOW.

HF

HFB R 580 HFB C 6900

YADKIN US 421 NBL

B-5825 17330REPLACE BRIDGE NO. 35 OVER YADKIN RIVER.

REG

T R 830 T 5500C5500C5500C

YADKIN NC 67

B-4683 751 66REPLACE BRIDGE NO. 20 OVER SOUTH DEEP CREEK.

DIV

STPOFF R 135 STPOFF C 550

YADKIN SR 1152(NEELIE ROAD)

B-4686 1500 140REPLACE BRIDGE NO. 10 OVER SOUTH DEEP CREEK.

DIV

STPOFF R 110 STPOFF C 1250

YADKIN SR 1710(WATKINS ROAD)

PART UNDER CONSTRUCTION - BRIDGE PURCHASE ORDER CONTRACT (BPOC)

BD-5111 18656 16656DIVISION 11 PURCHASE ORDER CONTRACT BRIDGE REPLACEMENT PROJECTS AT SELECTED LOCATIONS.

DIV

STPOFF 200R STPOFF 1800C

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

MITIGATION PROJECTS

IN PROGRESS

EE-4911 17405 17405ECOSYSTEM ENHANCEMENT PROGRAM FOR DIVISION 11 PROJECT MITIGATION.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

HAZARD ELIMINATION PROJECTS

DIVISION PURCHASE ORDER CONTRACT (DPOC) - IN PROGRESS

W-5211 450 450DIVISION 11 RUMBLE STRIPS, GUARDRAIL, SAFETY AND LIGHTING IMPROVEMENTS AT SELECTED LOCATIONS.

ALLEGHANYASHEAVERYCALDWELLSURRYWATAUGAWILKESYADKIN

VARIOUS

11-24 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 22: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025ROADSIDE ENVIRONMENTAL PROJECTS (SCENIC)

IN PROGRESS - 2012 NATIONAL SCENIC BYWAYS GRANT

S-5503 68 68YADKIN VALLEY SCENIC BYWAY WAYFINDING PROGRAM.

SURRYYADKIN

YADKIN VALLEYSCENIC BYWAY

11-25 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 23: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

COUNTY ID

FUTURE YEARS

F

RR - Rail-Highway SafetyRTAP - Rural Transit Assistance ProgramS - State I - ImpementationS (M) - State Match O - OperationsSMAP - Operating Assistance and State Maintenance Oc - OPS Funded CapitalSRTS - Safe Routes to School PE - Preliminary EngineeringSTAT - State PL - Planning / DesignSTHSR - Stimulus High Speed Rail R - Right-of-WaySTPDA - Surface Transportation Program - Direct AttributableSTPE - Surface Transportation Program, EnhancementsSTPEB - Surface Transportation Program, Enhancements (Bike)T - State Highway Trust FundsT2001 - State Rail FundsTAP - Transportation Alternatives ProgramTIGER DISC - TIGER Discretionary Grants

HP - Federal-Aid High PriorityJARC - Job Assistance and Reverse Commute (3037)

(1) FUNDING CATEGORY

DURHAM AREA

SR - Secondary Road

TRANSIT PARTNERROUTE / CITY /

NUMBER

TA-4738

LOCATION / DESCRIPTION

PASSENGER AMENITIES - BUS STOP TRANSIT AUTHORITY

DIV

SHELTERS, BENCHES, SHOP EQUIPMENTSPARE PARTS, ENGINES, SERVICE VEHICLES, ETC.

CP

BUS STOP SHELTER AND BENCHES LOCATED AT HOLLOWAY STREET

ESTIMATED COST Preliminary engineering, right of

C10000

dollars.)

of a project segment indicates (Cash-Flow Funding)Mitigation, Utilities or Construction.

way, utility, mitigation and construction cost estimates

(2) FUNDING SOURCES KEY

O - OtherL - Local

initial scheduled year. (Estimates are in thousand of

For other work types or activities see Work Type (Activity) box below.

work description. CPProject termini and a general

conception and remains with

9000

PROJECT BREAKS

CP

Various - multiple routes

A

5000

FY 2022

C

CP 3000CP

BCP 5000 B

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FY 2023 FY 2024FY 2021

STATE TRANSPORTATION IMPROVEMENT PROGRAM

FY 2020

TOTAL PROJECT

COST (THOU)

FUZFUZ

FUN

DS

A

PRIOR YEARS COST

(THOU)

ACP 700

FY 2015 FY 2016

4000CP

FY 2025

5000

BB

CP CP 5000B

UNFUNDED

NON HIGHWAY PROGRAM

ADIV

FY 2017 FY 2018

BSHOP EQUIPMENT, SPARE PARTS, ENGINES, SERVICE VEHICLES, ETC.

WORK TYPE (ACTIVITY) (3)Phases of implementation:

DIV C

20000

COMMITMENTSFUTURE

by funding category in current dollars. Cost may include one or more funding types. Multi-year funding

Preliminary engineering, Right of Way, UNFUNDED

BUS STOP SHELTER AND BENCHES LOCATED AT GREGSON AVENUE

with proposed work type or activity beginning in the

break.

One or two letter

CP

A

for an explanation of funding categories

FUNDING CATEGORY (1)

DIV

DIVISION 00

DEVELOPMENTAL PROGRAM

DURHAM

FY 2019

TRANSIT PARTNERROUTE / CITY /

NEW ROUTE or CityTRANSIT PARTNER

IDENTIFICATION NUMBER Assigned to each project at

US or NC RoutesI - Interstate

project until completion.

C - City

FEPD - Elderly and Persons with Disablity (5310)

FMOD - Fixed Guideway Modifications

designation for project

any project breaks.Category for the project and

LOCATION / DESCRIPTION

used for each project phase.

FUNDING SOURCE (2)

Identifies the "STI" Funding

See Highway Funding Key

FSPR - State Planning and Research

FNF - New Freedom ProgramFNS - New Starts - Capital (5309)

FMPL - Metropolitan Planning (5303)

FED - Federal Rail Funds

FLAP - Federal Lands Access Program

FUZ - Urbanized Area Formula Program (5307)

CMAQ - Congestion Mitigation

FF - Federal Ferry

FNU - Non Urbanized Area Formula Program (5311)

(3) WORK TYPE (ACTIVITY)

C - ConstructionAD - Administrative

CP - Capital

A - AcquisitionHF - State Dollars (Non-STI)REG - RegionalSW - Statewide

DIV - Division

DP - Discretionary or DemonstrationFBUS - Capital Program - Bus Earmark (5309)

Page 24: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

NON HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS

TA-6169 220 56CAPITALHF

FNU 164CP ALLEGHANY ALLEGHANY COUNTY

TA-6527 9CAPITAL

HF

FEPD 7CP L 1CP S 1CP

ALLEGHANY ALLEGHANY COUNTY

TK-6105 2163 615ADMINISTRATION

HF

FNU 308O O 155 O 155 O 155 O 155 O 155 155O155O155O FNU

ALLEGHANY ALLEGHANY COUNTY

TQ-6174 84OPERATING ASSISTANCEHF

FEPD 84O ALLEGHANY ALLEGHANY COUNTY

AVIATION PROJECTSAV-5750 350ACQUIRE LAND AND EXISTING HANGARS

NORTH OF RUNWAY 10 THRESHOLD AND ADJACENT TO AIRPORT PROPERTY.DIV

T R 315 O R 35

ASHE ASHE COUNTY AIRPORT(GEV)

PUBLIC TRANSPORTATION PROJECTSTQ-6803 90OPERATING

HF

FEPD 45O L 45O

ASHE ASHE COUNTYTRANSPORTATION

TA-6171 587 330CAPITAL

HF

FNU 257CP ASHE ASHE COUNTYTRANSPORTATION

TK-6108 2739 781ADMINISTRATION

HF

FNU 390O O 196 O 196 O 196 O 196 O 196 196O196O196O FNU

ASHE ASHE COUNTYTRANSPORTATION

PUBLIC TRANSPORTATION PROJECTSTA-6161 87 28CAPITAL

HF

FNU 59CP AVERY AVERY COUNTYTRANSPORTATION

TK-6109 1130 678ADMINISTRATION

HF

FNU 452AD AVERY AVERY COUNTYTRANSPORTATION

BICYCLE AND PEDESTRIAN PROJECTSU-5546 3575GREATER HICKORY MPO TRANSPORTATION

ALTERNATIVES (TA) PROGRAM.

DIV

TAP 60R R 20 R 20 R 20 R 20 R 20 20R20R20R R 20 R 20L 15R R 5 R 5 R 5 R 5 R 5 5R5R5R R 5 R 5TAP 600C C 200 C 200 C 200 C 200 C 200 200C200C200C C 200 C 200L 150C C 50 C 50 C 50 C 50 C 50 50C50C50C C 50 C 50

ALEXANDERBURKECALDWELLCATAWBA

VARIOUS

PUBLIC TRANSPORTATION PROJECTSTI-6101 8823 2512INTERCITY BUS - BOONE TO CHARLOTTE

HF

FNU 1543O O 596 O 596 O 596 O 596 O 596 596O596O596O CALDWELLCATAWBALINCOLNMECKLENBURGWATAUGA

COACH AMERICA

TA-6501 908 402REPLACEMENT VAN

HF

FNU 46CP CP 138 CP 92 CP 46 CP 46 46CP46CP46CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

11-29 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 25: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

NON HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS

TA-6556 339CAPITAL

HF

FNU 271CP L 34CP S 34CP

ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TG-6159 392 192ROUTINE CAPITAL - BUS STOP SHELTERS, BENCHES, SHOP EQUIPMENT, SPARE PARTS, ENGINES, FAREBOX, SERVICE VEHICLES, ETC

HF

FNU 40CP CP 20 CP 20 CP 20 CP 20 CP 20 20CP20CP20CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TG-4774 738 238ROUTINE CAPITAL - BUS STOP SHELTERS, BENCHES, SHOP EQUIPMENT, SPARE PARTS, ENGINES, FAREBOX, SERVICE VEHICLES, ETC

HF

FUZ 100CP CP 50 CP 50 CP 50 CP 50 CP 50 50CP50CP50CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TG-6142A 121 43ROUTINE CAPITAL - SERVICE VEHICLE

HF

FNU CP 39 39CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

see amendment #2 to 2012-2018 STIP apv'd by BOT in March 2012

TG-4774A 5925 925PREVENTIVE MAINTENANCE

HF

FUZ 1000Oc Oc 500 Oc 500 Oc 500 Oc 500 Oc 500 500Oc500Oc500Oc ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

see amendment #2 to 2012-2018 STIP apv'd by BOT in March 2012

TG-4774B 1463 353OPERATING ASSISTANCE - ADA PARATRANSIT SERVICE

HF

FUZ 222Oc Oc 111 Oc 111 Oc 111 Oc 111 Oc 111 111Oc111Oc111Oc ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TK-5181 4976 1426ADMINISTRATION

HF

FNU 710O O 355 O 355 O 355 O 355 O 355 355O355O355O FNU

ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TM-6108 2638 798OPERATING ASSISTANCE - NON-URBAN

HF

JARC 368O O 184 O 184 O 184 O 184 O 184 184O184O184O ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TA-6507 2934 634REPLACEMENT - LIGHT TRANSIT VEHICLE

HF

FNU 460CP CP 230 CP 230 CP 230 CP 230 CP 230 230CP230CP230CP ALEXANDERBURKECALDWELLCATAWBA

TRANSPORTATION ADMIN.

see March 2012-2018 BOT approval

TA-4927 1434 157REPLACEMENT BUS

HF

FUZ 557CP CP 180 CP 180 CP 180 180CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

11-30 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 26: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

NON HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS

TA-4928 1086EXPANSION BUS

HF

FUZ 362CP CP 362 362CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TA-4929 812 164REPLACEMENT VAN

HF

FUZ 108CP CP 108 CP 108 108CP108CP108CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TA-4928B 122EXPANSION - LIGHT TRANSIT VEHICLE - CMAQ APP#HU5

HF

CMAQ 122CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TN-6109 390 90OPERATING ASSISTANCE - SMALL-URBAN

HF

FNF 60O O 30 O 30 O 30 O 30 O 30 30O30O30O ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

see amendment #2 of 2012-2018 STIP BOT apvd March 2012

TO-4733 26830 6254OPERATING ASSISTANCE

HF

FUZ 4964O O 2796 O 2796 O 2796 O 1046 O 1046 1046O1000O1046O SMAP 408O O 204 O 204 O 204 O 204 O 204 204O204O204O

ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TO-6109 2586 626OPERATING ASSISTANCE

HF

FNU 392O O 196 O 196 O 196 O 196 O 196 196O196O196O ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TP-5106 553 157PLANNING ASSISTANCE - 5303

HF

FMPL 84CP CP 42 CP 42 CP 42 CP 42 CP 42 34CP34CP34CP ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTCOUNCILOF GOVERNMENTS

TP-4733A 2281 811PLANNING ASSISTANCE

HF

FUZ 420CP CP 210 CP 210 CP 210 CP 210 CP 210 ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TP-4733B 681 331PLANNING ASSISTANCE

HF

FUZ 100CP CP 50 CP 50 CP 50 CP 50 CP 50 ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TQ-6503 137 33PREVENTIVE MAINTENANCE - PARATRANSIT

HF

FEPD 22Oc Oc 11 Oc 11 Oc 11 Oc 11 Oc 11 9Oc9Oc9Oc ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

11-31 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 27: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

NON HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS

TQ-6507 792 207OPERATING ASSISTANCE - ELDERLY AND DISABLED PERSONS

HF

FEPD 138O O 69 O 69 O 69 O 69 O 69 34O34O34O ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

TS-5128 279 107SAFETY & SECURITY

HF

FUZ 54CP CP 24 CP 24 CP 23 CP 23 CP 24 ALEXANDERBURKECALDWELLCATAWBA

WESTERN PIEDMONTREGIONAL TRANSPORTATION

AVIATION PROJECTSAV-5757 2800RUNWAY SAFETY AREA EXTENSION FOR

RUNWAY 7

DIV

T 2520C O 280C

SURRY ELKIN MUNICIPALAIRPORT (ZEF)

AV-5759 2360RUNWAY 25. CONSTRUCT 500 FEET EXTENSION AND TAXIWAY TURNAROUND

DIV

T 2124C O 236C

SURRY ELKIN MUNICIPALAIRPORT (ZEF)

AV-5751 2400EXTEND RUNWAY AND PARALLEL TAXIWAY.

DIV

T 2160C O 240C

SURRY MOUNT AIRY/SURRYCOUNTY AIRPORT (MWK)

AV-5758 1400RUNWAY AND TAXIWAY EXTENSION - PAVING AND LIGHTING

DIV

T 1260C O 140C

SURRY MOUNT AIRY/SURRYCOUNTY AIRPORT (MWK)

BICYCLE AND PEDESTRIAN PROJECTSEB-5014 2200 300MOUNT AIRY GREENWAY LOOP. 2.2

TRN

STPEB 56R S(M) 14R STPEB 1464C S(M) 366C

SURRY MOUNT AIRY

EB-5725 193HAMBURG STREET FROM SOUTH MAIN STREET TO MOUNT AIRY MIDDLE SCHOOL. CONSTRUCT SIDEWALK. HAMBURG STREET TO MOUNT AIRY MIDDLE SCHOOL. CONSTRUCT GREENWAY.

0.5

DIV

TAP 46PE L 12PE TAP 108C L 27C

SURRY MOUNT AIRY

PUBLIC TRANSPORTATION PROJECTSTA-6139 1973 899CAPITAL

HF

FNU 1074CP DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TK-6174 6002 1742ADMINISTRATION

HF

FNU 852O O 426 O 426 O 426 O 426 O 426 426O426O426O FNU

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TN-6122 12OPERATING

HF

FNF 12O DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TO-6113 356OPERATING ASSISTANCE

HF

FNU 267O L 89O

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

11-32 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 28: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

NON HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS

TQ-8004 44CAPITAL - MOBILITY MANAGEMENT

HF

FNF 36CP L 4CP S 4CP

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TQ-6798 100OPERATING

HF

FEPD 50O L 50O

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

BICYCLE AND PEDESTRIAN PROJECTS

UNDER CONSTRUCTION

EB-5527 375 375MIDDLE FORK GREENWAY, PHASE I. TWEETSIE RAILROAD TO STERLING CREEK PARK. CONSTRUCT 10 FEET WIDE MULTI-USE PATH ALONG MIDDLE FORK NEW RIVER.

TRNWATAUGA BLOWING ROCK

PLANNING, DESIGN, RIGHT OF WAY, AND CONSTRUCTION BY TOWN OF BOONE

EB-5612 600SOUTH SIDE OF US 421 TO NORTH SIDE OF US 421 AT THE NEW RIVER. CONSTRUCT UNDERPASS ALONG THE WESTERN BANK OF RIVER.

0.1TRN

STPEB 600C WATAUGA BOONE GREENWAY

PUBLIC TRANSPORTATION PROJECTSTA-6101 5015 1585CAPITALHF

FNU 3430CP WATAUGA APPALCART

TK-6107 6558 1878ADMINISTRATION

HF

FNU 936O O 468 O 468 O 468 O 468 O 468 468O468O468O FNU

WATAUGA APPALCART

TM-6149 672OPERATING

HF

JARC 336O L 336O

WATAUGA APPALCART

TM-6133 450OPERATING ASSISTANCE

HF

JARC 225O L 225O

WATAUGA APPALCART

TO-6101 33212 9352OPERATING ASSISTANCEHF

FNU 4772O O 2386 O 2386 O 2386 O 2386 O 2386 2386O2386O2386O WATAUGA APPALCART

TO-6104 9212 2632OPERATING ASSISTANCEHF

SMAP 1316O O 658 O 658 O 658 O 658 O 658 658O658O658O WATAUGA APPALCART

TI-6103 12802 3566INTERCITY BUS - GREENSBORO TO BOONE

HF

FNU 2196O O 880 O 880 O 880 O 880 O 880 880O880O880O FORSYTHGUILFORDWATAUGAWILKESYADKIN

COACH AMERICA

TI-6101 8823 2512INTERCITY BUS - BOONE TO CHARLOTTE

HF

FNU 1543O O 596 O 596 O 596 O 596 O 596 596O596O596O CALDWELLCATAWBALINCOLNMECKLENBURGWATAUGA

COACH AMERICA

PUBLIC TRANSPORTATION PROJECTSTA-6138 648 207CAPITAL

HF

FNU 441CP WILKES WILKES TRANSPORTATIONAUTHORITY

TK-6172 3192 912ADMINISTRATION

HF

FNU 456O O 228 O 228 O 228 O 228 O 228 228O228O228O FNU

WILKES WILKES TRANSPORTATIONAUTHORITY

11-33 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project

Page 29: STATE TRANSPORTATION IMPROVEMENT PROGRAM 11.pdfdivision 11 project mitigation. alleghany ashe avery caldwell surry watauga wilkes yadkin various hazard elimination projects division

NON HIGHWAY PROGRAMDIVISION 11

ROUTE/CITYCOUNTYID

LOCATION / DESCRIPTION (THOU) (THOU)NUMBER

PRIORYEARSCOST

TOTALPROJCOST

LENGTH

TYPE OF WORK / ESTIMATED COST IN THOUSANDS / PROJECT BREAKS

FUNDS FY 2016

UNFUNDED

FY 2015 FUTURE YEARSFY 2017 FY 2019FY 2018 FY 2020

STATE TRANSPORTATION PROGRAM DEVELOPMENTAL PROGRAM

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025PUBLIC TRANSPORTATION PROJECTS

TI-6103 12802 3566INTERCITY BUS - GREENSBORO TO BOONE

HF

FNU 2196O O 880 O 880 O 880 O 880 O 880 880O880O880O FORSYTHGUILFORDWATAUGAWILKESYADKIN

COACH AMERICA

BICYCLE AND PEDESTRIAN PROJECTSEB-5529 495NORTH LEE AVENUE, MAIN STREET TO US

601 IN YADKINVILLE. CONSTRUCT SIDEWALK ON NORTH SIDE OF ROAD.TRN

STPEB 495C YADKIN YADKINVILLE

PUBLIC TRANSPORTATION PROJECTSTI-6103 12802 3566INTERCITY BUS - GREENSBORO TO BOONE

HF

FNU 2196O O 880 O 880 O 880 O 880 O 880 880O880O880O FORSYTHGUILFORDWATAUGAWILKESYADKIN

COACH AMERICA

TA-6139 1973 899CAPITAL

HF

FNU 1074CP DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TK-6174 6002 1742ADMINISTRATION

HF

FNU 852O O 426 O 426 O 426 O 426 O 426 426O426O426O FNU

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TN-6122 12OPERATING

HF

FNF 12O DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TO-6113 356OPERATING ASSISTANCE

HF

FNU 267O L 89O

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TQ-6798 100OPERATING

HF

FEPD 50O L 50O

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

TQ-8004 44CAPITAL - MOBILITY MANAGEMENT

HF

FNF 36CP L 4CP S 4CP

DAVIESTOKESSURRYYADKIN

YADKIN VALLEY ECONOMIC DEVELOPMENT DISTRICT

11-34 COST AND SCHEDULES ARE PRELIMINARY AND SUBJECT TO SIGNIFICANT CHANGE AS MORE INFORMATION BECOMES

AVAILABLE

DIV - Division Category EX - Exempt CategoryHF - State Dollars (Non STI) REG - Regional Category SW - Statewide Category TRN - Transition Project