state of south dakota board of minerals and … · procedural history of contested case ......

86
STATE OF SOUTH DAKOTA BOARD OF MINERALS AND ENVIRONMENT DEPARTMENT OF ENVIRONMENTAL AND NATURAL RESOURCES IN THE MATTER OF DRAFT TITLE V AIR ) QUALITY PERMIT AND ACID RAIN 1 CONSOLIDATED PERMIT NO. 28-0801-29 FOR THE BIG ) STONE FACILITY AND IN THE MATTER OF ) Permit No. 28.0801-29 DRAFT PSD PERMIT NO. 28-0803-PSD 1 & PERMIT NO. 28-0803-PSD FOR THE BIG ) Permit No. 28.0803-PSD STONE FACILITY ) 1 DENR Draft Permits Issued: 01-08 ) DENR Proposed Permits Issued: 04-08 ) BOARD'S AMENDED FINDINGS OF FACT AND CONCLUSIONS OF LAW April 2 1, 2009

Upload: doannga

Post on 10-May-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

STATE OF SOUTH DAKOTA BOARD OF MINERALS AND ENVIRONMENT

DEPARTMENT OF ENVIRONMENTAL AND NATURAL RESOURCES

IN THE MATTER OF DRAFT TITLE V AIR ) QUALITY PERMIT AND ACID RAIN 1 CONSOLIDATED PERMIT NO. 28-0801-29 FOR THE BIG ) STONE FACILITY AND IN THE MATTER OF ) Permit No. 28.0801-29 DRAFT PSD PERMIT NO. 28-0803-PSD 1 & PERMIT NO. 28-0803-PSD FOR THE BIG ) Permit No. 28.0803-PSD STONE FACILITY )

1 DENR Draft Permits Issued: 01-08 ) DENR Proposed Permits Issued: 04-08 )

BOARD'S AMENDED FINDINGS OF FACT AND CONCLUSIONS OF LAW

April 2 1, 2009

TABLE OF CONTENTS

... ................................................................................................................................. ACRONYMS 111

AMENDED FINDINGS OF FACT ............................................................................................. 6

I . Overview ............................................................................................................................. 6

A . Parties ........................................................................................................................ 7

B . Existing Big Stone I Facility ..................................................................................... 7

C . Proposed Big Stone I1 Project ................................................................................... 8

I1 . Background on DENR Air Quality Program and Requested Permits ............................... 12

111 . DENR Action on Otter Tail's Permit Applications .......................................................... 13

IV . Procedural History of Contested Case Proceedings .......................................................... 22

A . Petitions, Motions and Pre-Hearing Procedures (2008) .................................... 22

B . Evidentiary Contested Case Hearing Before the Board (2008) .............................. 25

C . Evidentiary Contested Case Hearing Before the Board (2009) .............................. 30

D . General Findings Regarding Contested Case Hearings .......................................... 30

V . Facts Supporting the Issuance of the Proposed PSD Permit ............................................. 31

............................................................................................... A . Applicability of PSD 31

....................................................................................................... B . BACT Analysis 32

1 . The BACT Process and Relevant Definitions .......................................... 32

2 . BACT Analysis of Big Stone I1 Emissions ............................................... 37

a . PMlo ............................................................................................. 37

b . CO ................................................................................................. 39

C . v o c s ............................................................................................. 39

d . SAM .............................................................................................. 39

e . Fluorides ........................................................................................ 40

C . Other Applicable Limits (PSD Permit Section 5) ................................................... 41

D . Performance Tests (PSD Permit Section 6) ............................................................ 41

E . Fugitive Dust Controls (PSD Permit Section 7) ..................................................... 41

F . Air Quality Analysis-Air Dispersion Modeling ................................................... 42

G . Modeling for Class I Areas .................................................................................... 43

H . Additional Impacts Analysis ................................................................................... 44

I . Conclusion Regarding PSD Permit ......................................................................... 44

VI . Facts Supporting the Issuance of the Proposed Title V Permit ......................................... 44

A . General .................................................................................................................... 44

B . Netting and Other Conditions Applicable to NO, and SO2 .................................... 45

C . Adequacy of Compliance Provisions for SO2 and NO, .......................................... 47 . . . D Mercury Limits ........................................................................................................ 48

.................................................. E . Limitation on HAPS to Avoid Triggering MACT 48

F . Addition of PSD Requirements ............................................................................... 49

. G Conclusion Regarding Revised Title V and Acid Rain Permit ............................... 50

VII . Findings Relating to Issues Raised by Petitioners (2008 Contested Case) ....................... 50

.................................................................................... A . Plantwide Caps (Issues 1-4) 50

B . IGCC (Issue 8) ........................................................................................................ 52

C . General Findings Regarding Petitioners' Challenges to the BACT Determinations (Issues 1 0- 1 2) ................................................................................ 55

............................................................................. D . PMlo BACT Analysis (Issue 10) 56

E . SAM BACT Analysis (Issue 1 1) ............................................................................ 59

........................................................................ F . Fluoride BACT Analysis (Issue 12) 61

G . BACT During Periods of Startup and Shutdown (Issue 13) ................................... 62

H . Modeling For Periods of Startup and Shutdown (Issue 14) .................................... 65

............................................................... I . PMlo NAAQS and Increments (Issue 15) 65

.................................................. . J SO2 and NOx NAAQS and Increments (Issue 16) 68

...................................................... K . Case-by-Case MACT Requirements (Issue 18) 71

1 . The Permit Limits Ensure That Big Stone I1 is not a Major Source of ......................................................................................................... HAPS 71

2 . The Evidence Proved That Big Stone I1 Can Meet the HAP Limits ........ 72

3 . The HAP Limits Are Enforceable ............................................................. 74

4 . The Public Was Provided Proper and Sufficient Notice ........................... 75

L . Contents of Title V Permit (Issue 19) ..................................................................... 78

VIII . Findings Relating to Questions and Claims Raised in April 2009 Contested ..................................................................................................................... Case Hearing 79

AMENDED CONCLUSIONS OF LAW ................................................................................... 82

I . General .............................................................................................................................. 82

I1 . The Board Should Issue the PSD Permit .......................................................................... 83

I11 . The Board Should Issue the Revised Proposed Title V Permit for EPA's Review ......... 84

...................................................................................... IV . Petitioners' Claims Are Rejected 85

ACRONYMS

AHPC

BACT

Btu

CAA

CAMR

CEMS

CO

DENR

EAB

HAPS

HF

IGCC

MACT

NAAQS

NO,

NSPS

NWS

PAL

PC

PM

PM2.5

PMl0

PSD

SAM

SCR

SIP

so2 VOC

WESP

WFGD

Advanced Hybrid Particulate Collector

Best Available Control Technology

British thermal units

Clean Air Act

Clean Air Mercury Rule

Continuous Emissions Monitoring Systems

Carbon Monoxide

South Dakota Department of Environment and Natural Resources

EPA's Environmental Appeals Board

Hazardous Air Pollutants

Hydrogen Fluoride

Integrated Gasification Combined Cycle

Maximum Achievable Control Technology

National Ambient Air Quality Standards

Nitrogen Oxides

New Source Performance Standard

National Weather Service

Plantwide Applicability Limit

Pulverized Coal

Particulate Matter

Particulate Matter with an Aerodynamic Diameter of or Less than 2.5 Microns

Particulate Matter of or Less than 10 Microns

Prevention of Significant Deterioration

Sulfuric Acid Mist (also known as H2SO4)

Selective Catalytic Reduction Unit

South Dakota Air Quality Program's State Implementation Plan

Sulfur dioxide

Volatile Organic Compounds

Wet Electrostatic Precipitator

Wet Flue Gas Desulfurization system (also known as a "wet scrubber")

This matter came to the attention of the South Dakota Department of Environment

and Natural Resources ("DENR) Board of Minerals & Environment ("Board") for a

contested case hearing on the renewal of a Title V operating permit and the issuance of a

pre-construction permit for the Big Stone facility near Big Stone City, South Dakota. In

addition to other preliminary hearings in this matter, including a public input hearing, the

Board conducted contested case hearings in this matter on Monday, August 18, 2008

through Thursday, August 20,2008; and Tuesday, August 26,2008; and further contested

case hearings on modeling issues on Wednesday, September 24, 2008, through Friday,

September 26 , 2008. At these hearings, Applicant appeared by and through its attorneys

Harry M. Johnson, 111 (pro hac vice), and Penny Shamblin (pro hac vice) of the firm

Hunton & Williams; and Thomas J. Welk and Christopher W. Madsen of Boyce,

Greenfield, Pashby & Welk, LLP. DENR appeared by and through its attorneys, Deputy

Attorney General Roxanne Giedd and Assistant Attorney General Scott Swier.

Petitioners Sierra Club and Clean Water Action appeared by and through William A.

Moore (pro hac vice) and Aaron Emerson. Following the contested case hearings, the

Board received post-hearing briefs and reply briefs from the parties. On November 20,

2008, the Board heard final oral arguments and presentations from the parties. Based on

the testimony of the witnesses, the evidence submitted to the Board at the contested case

hearings, the administrative record, and the arguments of counsel, the Board entered

Findings of Fact and Conclusions of Law to support its Final Decision dated the same

day that authorized and directed DENR to prepare and issue in the Board's name the

Prevention of Significant Deterioration ("PSD") permit for the Big Stone I1 project, and

to prepare and issue the proposed Title V permit for the Big Stone facility for review by

the United States Environmental Protection Agency ("EPA"). The PSD permit and

proposed Title V permit were issued on November 20, 2008, and the Title V permit and

supporting materials were subsequently submitted to EPA for its 45-day review.

On January 22, 2009, DENR received EPA's objections to the proposed Title V

permit. In accordance with federal and South Dakota regulations, DENR may not issue

the Title V permit and must respond to the objections within 90 days thereafter. In

addition, on February 26, 2009 and in connection with the appeal of the PSD permit, the

Circuit Court of Hughes County directed the Board pursuant to SDCL 1-26-34 to take

additional evidence on the limited issue of whether any revisions to the proposed Title V

permit to meet EPA's objections necessitate any changes to the PSD permit and/or

Findings of Fact and Conclusions of Law dated November 20,2008.

In addition to other preliminary hearings in the continuation of this matter, the

Board conducted a combined contested case and evidentiary hearing on Monday, April

20, 2009 and Tuesday, April 21, 2009. At these hearings, Applicant appeared by and

through its attorneys Harry M. Johnson, 111 (pro hac vice), and Penny A. Shamblin (pro

hac vice) of the firm Hunton & Williams; and Thomas J. Welk and Christopher W.

Madsen of Boyce, Greenfield, Pashby & Welk, LLP. DENR appeared by and through its

attorneys, Deputy Attorney General Roxanne Giedd and Assistant Attorney General Scott

Swier. Petitioners Sierra Club and Clean Water Action appeared by and through George

Hays (pro hac vice) and Aaron Emerson.

Based on the testimony of the witnesses, the evidence submitted to the Board at

all the hearings, the administrative record, and the arguments of counsel, the Board enters

the following Amended Findings of Fact and Conclusions of Law:

AMENDED FINDINGS OF FACT

The Board concludes that it is appropriate and lawful to issue the permits at issue

in this contested case proceeding, as amended and clarified, for the reasons stated herein

and in the prior orders of the Board.

I. Overview

1. The proposed Title V permit has been revised to meet EPA's objections,

and these Amended Findings of Fact and Conclusions of Law support the issuance of the

revised proposed Title V permit. The Board concludes that the revisions to the proposed

Title V permit do not necessitate any changes to the PSD permit issued on November 20,

2008. Likewise, the revisions to the Title V permit do not necessitate any changes to the

Findings of Facts and Conclusions of Law as they relate specifically to the PSD permit,

except to conform the general findings and conclusions to the revisions.

2. The Board finds that the revised proposed Title V permit resolves EPA's

objections.

3. Nothing in these Amended Findings of Fact and Conclusions of Law is

intended or shall be deemed to alter or amend the date that the PSD permit was issued

(November 20,2008).

4. To the extent any of the following findings of fact may be determined to

be conclusions of law or mixed findings of fact and conclusions of law, the same are

incorporated by this reference as a conclusion of law as if set forth in detail.

5 . All of these findings of fact have been established by a preponderance of

the evidence introduced or stipulated to at the contested case hearing.

6 . Citations to specific evidence herein are not intended to be exhaustive;

rather, they are representative of the evidence to support the individual findings.

A. Parties

7. Applicant Otter Tail Corporation d/b/a Otter Tail Power Company ("Otter

Tail"), along with Montana-Dakota Utilities Co. ("MDU"), a Division of MDU

Resources Group, and Northwestern Energy are the co-owners of the existing Big Stone I

facility. Otter Tail is the operator of the existing Big Stone I facility. Otter Tail is also

one of the co-owners of the proposed Big Stone I1 facility, along with Central Minnesota

Municipal Power Agency, Heartland Consumers Power District, MDU, and Western

Minnesota Municipal Power Agency d/b/a Missouri River Energy Services. [Tr. 492-93

(Rolfes, 8120108); Ex. 300-Dl.

8. Petitioner Sierra Club is a national non-profit corporation organized and

existing under the non-profit corporation laws of the state of California.

9. Petitioner Clean Water Action, Inc., is a national non-profit corporation

organized and existing under the non-profit corporation laws of the District of Columbia.

B. Existing Big Stone I Facility

10. Big Stone I is an existing pulverized coal-fired plant near Big Stone City

in Grant County, South Dakota. The Big Stone I power plant converts steam to

electricity by burning subbituminous coal and other approved alternative fuels.

11. Big Stone I began construction on January 18, 1971. [Core Ex. 1981.

Because construction commenced prior to August 7, 1977, Big Stone I was not required

to obtain a Prevention of Significant Deterioration ("PSD") permit.

12. On January 22, 1975, DENR issued Otter Tail an operating permit for the

Big Stone I power plant. [Core Ex. 198 at 61.

13. On February 24, 1997, Otter Tail was issued its initial Title V operating

permit for the Big Stone I power plant. The Title V permit was issued for a period of five

years, with an expiration date of February 24, 2002.

Condition 5.2 of Otter Tail's Title V permit provides that, if a renewal application is

submitted six months prior to the expiration of the Title V permit, Otter Tail may

continue to operate under the terms of the expired permit until DENR takes action on the

renewal application. [Core Ex. 217 at 11. On June 4, 2001, Otter Tail, as operator, timely

submitted an application to renew Big Stone I's Title V permit. [Core Ex. 210Al.

Therefore, Otter Tail is authorized to operate under the terms of the February 24, 1997

Title V permit.

14. On October 23, 2006, Otter Tail submitted notification to DENR of

planned projects during the 2007 Maintenance Outage for Big Stone I, including

replacement of the Advanced Hybrid Particulate Collector ("AHPC") with a pulse-jet

fabric filter. [Core Ex. 21 OG].

15. On March 21, 2007, DEIVR issued an Amended Title V permit for Big

Stone I addressing the removal of the AHPC and other projects described in Otter Tail's

October 23,2006 submittal. [Core Ex. 21 lG].

C. Proposed Big Stone I1 Project

16. Big Stone 11 is a proposed super-critical pulverized coal-fired electric

generating unit and associated facilities intended to provide approximately 600 MW of

baseload energy for the participating owners in a low-cost, environmentally responsible

manner. "Baseload" means the power from the proposed Big Stone 11 plant must be

available to meet customer demand on a 24-hour per day, 7 days per week basis except

for times when the plant is off-line for maintenance. The Big Stone I1 Project co-owners

serve customers in South Dakota, North Dakota, Montana, Iowa and Minnesota. The

energy from the facility is intended to serve its co-owners' retail and wholesale native

load customers. The facility is expected to produce 4.6 million megawatt hours of

electricity per year. [Tr. 502, 526 (Rolfes, 8/20/08)].

17. Big Stone I1 will be constructed near Big Stone City, South Dakota, at the

same site as the existing Big Stone I unit. The two units will share a common stack and

wet flue gas desulfurization system ("WFGD" or "Wet FGD"). South Dakota is in

attainment with the National Ambient Air Quality Standards ("NAAQS") for all the

pollutants regulated under the Clean Air Act ("CAW). [Core Ex. 183 at 1 11.

18. The Big Stone I1 Project must obtain a number of permits in order to

construct the proposed plant and has already been subject to substantial scrutiny from

various agencies, including the South Dakota Public Utilities Commission and the South

Dakota Water Management Board. The Big Stone I1 Project has obtained the following

permits: solid waste permit, surface water permit, siting permit, South Dakota route

permit for transmission facilities, and South Dakota groundwater permit. [Tr. 496-99

(Rolfes, 8/20/08)]. These permits are final.

19. The Big Stone I1 Project considered and investigated several generation

resources for the Big Stone I1 plant, including (1) atmospheric circulating fluidized bed,

which was determined not to provide sufficient efficiency and economic value; (2)

integrated gasification combined cycle ("IGCC"), which was rejected from a business

standpoint because the technology has not been proven to be reliable and is not generally

commercially available; (3) natural gas-powered turbines, which would be a much more

expensive option; and (4) wind power, which is too intermittent to provide the needed

baseload power. The investigation and analysis of these alternatives was conducted by

Burns & McDonnell, a national engineering firm with extensive experience in power

generation. At the conclusion of the investigation, a super-critical pulverized coal plant

was determined to be the best option for the Project. [Tr. 503-06 (Rolfes, 8120108); Ex.

3221.

20. Burns & McDonnell also investigated potential sites for the location of the

proposed plant. Ultimately, the investigation and analysis revealed the best location for

the new unit was the existing Big Stone I site. [Tr. 508-09 (Rolfes, 8/20/08)].

21. The proposed Big Stone I1 plant is estimated to cost approximately $1.4

billion and the related transmission facilities are estimated to cost approximately another

quarter of a billion dollars. The proposed Big Stone I1 Project will have significant

positive economic impact on the Milbank-Big Stone City area. [Tr. 5 1 1, 5 14-16 (Rolfes,

8/20/08)].

22. The Mid-Continent Area Power Pool, an organization composed of

electrical utilities and other electric industry participants, projects a deficit in generation

capacity, even if Big Stone I1 is constructed. [Tr. 519-20 (Rolfes, 8/20/08)]. Without Big

Stone 11, the utilities will need to find additional generation sources - most likely

combustion turbines which are more expensive than coal on a ~ t u ' basis. [Id.]

23. The proposed Big Stone I1 Project will employ a number of pollution

control devices, including the following:

a. Gases leaving Big Stone 11's super-critical boiler will flow

into a selective catalytic reduction unit ("SCR). The SCR uses catalysts

-

' British thermal units.

to convert nitrogen oxides ("NOx") into nitrogen and water vapor. [Tr.

524 (Rolfes, 8/20/08)].

b. The gases then flow into the "baghouse" where the air

flows through fabric filters. [Tr. 525 (Rolfes, 8/20/08)]. The baghouse

has thousands of fabric filter bags which trap ash and other particulate

matter. [Tr. 530 (Rolfes, 8/20/08)]. Pulses of air directed at the bags

periodically knock the solids off of the bags, and the particulate matter

falls into hoppers where it can be collected. [Tr. 530 (Rolfes, 8/20/08)].

c. Gases then flow into a wet FGD. A wet FGD is also

known as a "wet scrubber." The wet scrubber is a device that will be

shared with Big Stone I, meaning that Big Stone 1's exhaust gases will

also flow into the wet scrubber. A wet scrubber, as compared to a dry

scrubber, will provide for greater reduction of emissions of sulfur dioxide

("S02"). [Tr. 53 1-32 (Rolfes, 8/20/08)].

d. The estimated capital cost of the pollution control

equipment for the proposed Big Stone I1 plant is significant. Rough

approximations are as follows: $300 million for a boiler with the SCR

device; $40 million for the fabric filter baghouse; and $1 50 million for the

wet scrubber. [Tr. 538 (Rolfes, 8/20/08)].

24. The pollution control equipment has not been ordered and final design has

not been completed. Once the permits are issued, the Project will select a vendor to build

the boiler and the pollution control equipment. The emission control efficiencies will be

specified and the equipment will be designed to comply with the permits. [Tr. 552

(Rolfes, 8/20/08)].

11. Background on DENR Air Quality Program and Requested Permits

25. The DENR Air Quality Program administers air quality permitting as

required by the Clean Air Act, and state and federal statutes and regulations.

26. A PSD permit is required for any regulated pollutant prior to construction

of new major stationary sources or major modifications to existing sources in areas

designated as in attainment with the NAAQS under section 107 of the CAA.

27. In January 2008, the EPA approved the South Dakota Air Quality

Program's State Implementation Plan ("SIP") for the PSD Program. Prior to that date,

the PSD Program was considered a "delegated program" which meant that DENR

administered PSD permitting on behalf of EPA. [Tr. 44-46 (Gustafson, 811 8/08)].

28. NAAQS mandated by the CAA are set by EPA. EPA has promulgated

NAAQS for specific criteria pollutants including particulate matter ("PMlo"), SO2, NO,,

and carbon monoxide ("CO"). The Air Quality Program maintains ambient air monitors

throughout the state to determine the level of pollutants in the ambient air to assure

compliance with the NAAQS. South Dakota is in attainment with all the NAAQS. [Tr.

47 (Gustafson, 811 8/08)].

29. A Title V permit is an operating permit required for major sources

pursuant to Title V of the CAA. The Title V permit can also serve as construction

authorization when a PSD permit is not required. ARSD 74:36:05:02. All PSD sources,

among others, are required to have a Title V permit. After construction and within

twelve months of commencing operation, a source is required to apply for a Title V

operating permit, which will incorporate the requirements of the PSD permit, among

others. [Tr. 49-50 (Gustafson, 811 8/08)].

111. DENR Action on Otter Tail's Permit Applications

30. On July 20,2005, Otter Tail submitted an application for a PSD Permit for

Big Stone I1 on behalf of the co-owners of Big Stone 11. [Core Exs. 144 and 183 11.

DENR considered the application complete on August 9,2005. [Core Ex. 183 at :I].

31. In April 2006, DENR issued a "Notice of Prevention of Significant

Deterioration Permit Application and Draft Permit" soliciting public comment on the

initial Draft PSD Permit. [Core Exs. 154, 155, 159, 1601.

32. In May and June 2006, DENR received comments on the initial draft PSD

permit. [Core Exs. 187- 1921.

33. In June 2006, Otter Tail submitted an updated application for the PSD

Permit on behalf of the Co-Owners of Big Stone 11. [Core Ex. 1641. DENR extended the

public comment period until June 26, 2006. [Core Ex. 1611. In August 2006, Otter Tail

submitted further updates to the PSD application. [Core Ex. 1671.

34. In Otter Tail's PSD application for Big Stone 11, Otter Tail requested

emission and operational limits that are associated with both Big Stone I and Big Stone I1

to avoid PSD review for SO2 and NOx emissions. During the public notice period on the

initial PSD draft permit, EPA submitted comments suggesting that the PSD Permit was

not the appropriate place for the SO2 and NOx limitations. DENR agreed and concluded

that the Title V permit was a more appropriate place for those limits. [Core Ex. 217 at :I].

From then on, DENR processed the Big Stone I1 PSD permit application and the Big

Stone I Title V renewal concurrently. [Tr. 242 (Rombough, 8/19/08)].

35. On December 21, 2008, EPA published its approval of the South Dakota

SIP for PSD, effective January 22, 2008. Otter Tail resubmitted its PSD application and

supporting materials on January 22, 2008 to ensure processing of the applications under

the SIP. [Core Ex. 1761.

36. DENR prepared a second draft PSD Permit [Core Ex. 1821 and a revised

Statement of Basis ("PSD RSOB") [Core Ex. 1831. The initial PSD Statement of Basis

[Core Ex. 1601, as revised and supplemented by the PSD RSOB, is adopted and

incorporated herein by reference, as further modified and supplemented by these Findings

of Fact and Conclusions of Law.

37. On January 30, 2008, DENR issued a "Notice of Prevention of Significant

Deterioration Permit Application and Draft Permit" soliciting public comment on the

second draft PSD Permit. [Core Ex. 1781. In accordance with ARSD 74:36:09:03, public

notices were properly published on or about January 25, 2008 in the Watertown Public

Opinion and the Grant County Review. [Tr. 154-55 (Rombough, 8/18/08); Core Ex.

18 I].

38. DENR prepared a draft Title V Air Quality Permit ("Draft Title V

Permit") [Core Ex. 21 61 and associated Statement of Basis ("Title V SOB") based on the

June 4, 2001 application as supplemented. DENR's Title V SOB [Core Ex. 2171 is

adopted and incorporated herein by reference, as modified and supplemented by these

Amended Findings of Fact and Conclusions of Law.

39. On January 30, 2008, DENR issued a "Notice of Title V Air Quality

Permit Application and Draft Permit" soliciting public comment on the Draft Title V

Permit. [Core Ex. 2131. In accordance with ARSD 74:36:05: 17, public notices of the

Title V application and draft permit were properly published on or about January 25,

2008 in the Watertown Public Opinion and the Grant County Review. [Tr. 245-46

(Rombough, 811 9/08); Core Ex 2 151.

40. Following .the February 8, 2008 ruling by the United States Court of

Appeals for the District of Columbia Circuit vacating the Clean Air Mercury Rule, the

applicability of case-by-case MACT to Big Stone I1 was uncertain. New Jersey v. EPA,

5 17 F.3d 574 (D.C. Cir. 2008). In light of this uncertainty, Otter Tail submitted to DENR

on February 25, 2008 a request for a case-by-case Maximum Achievable Control

Technology ("MACT") determination solely for mercury. [Core Ex. 1851. On March 18,

2008, Otter Tail withdrew the request for a case-by-case MACT determination after

further analysis indicating that Big Stone I1 will not be a major source of Hazardous Air

Pollutants ("HAPS"), proposing instead HAP emission limits sufficient to ensure Big

Stone 11's potential HAP emissions are below the major source thresholds. [Core Ex.

1861.

41. In February 2008, DENR received public comments on the second draft

PSD and Title V Permits, which are reflected in the core exhibits. [Core Exs. 187, 188,

193, 1941. Sierra Club requested and received an extension until March 15, 2008 to file

its comments on the draft permits. [Core Exs. 184, 1951.

42. On April 15, 2008, DENR published its responses to the comments

received during the 2006 and 2008 public notice periods regarding the initial draft PSD

permit, the second draft PSD Permit and the draft Title V Permit. [Core Ex. 1981.

DENR's responses to comments were in excess of 90 pages - one of the lengthiest

responses to public comments in DENR's history. [Tr. 277 (Rombough, 8/19/08)]. In its

responses, DENR addressed all comments respecting the draft permits received as of that

time.

43. DENR sent the Final Proposed Permits and its Response to Comments to

all persons who had submitted comments on the Draft Permits. [Tr. 247 (Rombough,

811 9/08>].

44. In particular, DENR addressed all EPA comments on the draft permits and

modified those permits where appropriate. Until January 22, 2009, when it objected to

the proposed Title V permit, EPA neither submitted further written comments nor sought

to intervene in these proceedings.

45. On April 15, 2008, DENR issued its final draft proposed Prevention of

Significant Deterioration Air Quality Preconstruction Permit for Big Stone I1 (Core Ex.

197), and its final draft proposed Title V Air Quality Permit and Acid Rain Permit (Core

Ex. 219).

46. DENR spent thousands of hours investigating and researching the permit

applications in this matter and preparing the draft permits, analyzing comments,

responding to comments and preparing the final proposed permits. That time is

significantly longer than time spent on other PSD or Title V permits. [Tr. 277-78

(Rombough, 8/19/08)]. In performing its review of the permits, Mr. Rombough reviewed

applications and similar permits issued by other states and spoke with his counterparts in

other states' agencies. [Tr. 278-83 (Rombough, 8/19/08); Exs. 327-321.

47. On July 17, 2008, the Board conducted a public input hearing in Milbank,

South Dakota, regarding the proposed permits, the transcript of which is incorporated

herein by reference. Seventy-seven persons, excluding lawyers for the parties, signed in

at the hearing. Twenty-six persons from South Dakota and Minnesota presented

comments regarding the proposed permits. Generally, most commenters expressed

positive comments in support of the Big Stone I1 Project, while a minority of commenters

opposed the Project. Specifically:

a. Many commenters spoke in favor of the project noting that

Otter Tail and Big Stone I have been good neighbors and friends for years.

The project will provide safe, reliable and environmentally responsible

low-cost electricity with less emissions than Big Stone I by itself. A

number of commenters noted that they have raised their families in the

community alongside the Otter Tail employees and have observed no ill

effects among those living close to the power plant.

b. Several commenters expressed concern regarding mercury

emissions from the Big Stone facilities. The evidence is that the

construction of Big Stone I1 will not increase mercury emissions over

existing emissions. Combined mercury emissions from Big Stone I and

Big Stone I1 are capped at Big Stone 1's calculated mercury emissions

from 2004 (189 lbslyear). [Core Ex. 219 at 251. Due to controls that are

added to Big Stone I and Big Stone 11, it is anticipated that mercury

emissions will be approximately 50% below the caps. Hence, mercury

emissions from both Big Stone I and I1 are expected to be less than the

current mercury emissions from Big Stone I.

c. Several commenters expressed concern regarding the effect

of Big Stone I1 on ambient air quality. The Board finds DENR has

conducted extensive air quality monitoring and has determined that air

quality is excellent. Due to controls to be installed as part of the Big Stone

I1 project and based on air dispersion modeling that is accepted by the

Board, all legal requirements regarding air quality are satisfied and there is

no reason to believe that air quality will be degraded.

48. The Board finds that the public was able to reasonably and meaningfully

review and comment in writing and in person on the proposed permits.

49. The Board has considered the public comments received during the 2006,

2008, and 2009 public notice periods, as well as all other public comments received since

that time, when deciding whether to issue the permits. DEhTR's responses to comments

[Core Exs. 198, 8531 are adopted and incorporated herein by reference, as supplemented

herein.

50. During the 2008 contested case hearing, Otter Tail proposed several

changes andlor clarifications of the proposed PSD permit. [Ex. 3241. These included:

clarification of Best Available Control Technology ("BACT") requirements during

startup, shutdown, and malfunction; more stringent material handling PMlo emission

limits consistent with EPA's proposed NSPS and Otter Tail's modeling; the addition of

language in Section 1.1 allowing insignificant changes to the design of the plant so long

as modeling still reflects compliance with air quality standards; and correction of a

typographical error in Unit #35's BACT limit. DENR concurred with all the changes

proposed by Otter Tail except for the proposed language in Section 1.1. DENR proposed

revised language regarding insignificant design changes in Section 1.1 A, and Otter Tail

agreed with DENR's revised language. The final proposed language is shown in Ex. 705,

which the Board accepts and will incorporate into the PSD permit. The Board adopts and

will incorporate the remaining proposed changes in Exhibit 324 for the reasons herein.

51. Otter Tail had originally proposed changes to the 2008 draft Title V

permit. Otter Tail later withdrew those proposed changes. The Board adopted and issued

the 2008 proposed Title V permit [Core Ex. 2 191 without modification.

52. The PSD permit and proposed Title V permit were issued on November

20, 2008, and the proposed Title V permit and supporting materials were subsequently

submitted to EPA for its 45-day review.

53. On January 22, 2009, DENR received EPA's objections to the proposed

Title V permit. [Core Exs. 808-8091. In accordance with federal and South Dakota

regulations, DENR could not issue the Title V permit and was required to respond to the

objections within 90 days thereafter.

54. Generally, EPA objected on the following three areas:

a. Failure to include applicable requirements from the PSD

permit and New Source Performance Standards ("NSPS") for the

proposed Big Stone I1 project in the proposed Title V permit;

b. A lack of a proper PSD applicability analysis for SO2 and

NOx; and

c. Inadequate compliance provisions for SO2 and NO,

emissions to avoid a PSD review and for HAP emissions to avoid a Case-

by-Case MACT review for the Big Stone I1 project in the proposed Title V

permit. EPA also recommended that the HAP provisions in Chapter 11 of

the proposed Title V permit be noticed for public comment.

55. After receiving EPA's objections, DENR and EPA communicated

frequently via telephone and e-mail about revisions to the proposed Title V permit and

the supplemental Statement of Basis. [See, e.g., Core Exs. 8 12-8 15, 8 17-825, 828-8301.

DENR sought to ensure that EPA was satisfied with the revisions before publishing the

public notice of the draft revisions to the proposed Title V permit and the Statement of

Basis.

56. DENR drafted revisions to the proposed Title V air quality permit in

response to EPA's objection to ensure compliance with SDCL 34A-1 and the federal

Clean Air Act. DENR took the following specific actions on the permit:

a. Re-noticingpermitconditions11.1,11.2,11.3,11.4,11.6,

11.7, and 11.9;

b. Revising permit conditions 5.5, 5.9, 7.1 1, 7.12, 8.4, 9.2,

9.5,9.8, and 11.5;

c. Adding permit conditions 5.12,9.3, 9.6, 9.9,9.10, and 1 1.8;

and

d. Adding Chapters 12.0, 13.0, 14.0, 15.0, and 16.0.

57. On February 9, 2009, DENR issued a "Notice of Issuance of Draft

Revisions to Proposed Title V Air Quality Permit in Response to EPA Objections."

[Core Exs. 833, 836-840, 8421. Public notices of the draft revised Title V permit were

properly published on or about February 11, 2009, in the Watertown Public Opinion and

the Grant County Review. [Core Ex. 8411. The notices solicited public comment on the

draft revisions to the Title V Permit, solicited public comment on certain other provisions

in accordance with EPAYs objections, and provided notice of the contested case hearing

on or about April 20,2009. [Id]

58. DENR received public comments from approximately 300 individuals and

environmental groups. [See Core Exs. 844-8481. DENR reviewed and considered the

comments, and where appropriate, incorporated changes into the revised proposed Title

V permit. DEhTR issued responses to the comments on March 18, 2009 [Core Ex. 8531,

and submitted them to EPA and the commenters along with notification of the time and

location of the contested case hearing. [Core Exs. 850-851, 8541.

59. DENR issued its final draft revisions to the Title V permit on March 18,

2009. [Core Ex. 8531

60. At the April 2009 contested case hearing, Otter Tail proposed a slight

wording change to Condition 9.5 of DENRYs March 18, 2009 final draft revision of the

Title V permit to clarify that the Unit #1 and Unit #13 annual nitrogen oxide limits go

into effect the month of the initial startup of Unit #13 consistent with Condition 9.2 for

sulfur dioxide. DENR concurred with the change proposed by Otter Tail. The Board

adopts and will incorporate the proposed change. The first paragraph of Condition 9.5

will read as follows:

9.5 Nitrogen oxide limit. In accordance with ARSD 74:36:05:16:01(8), the owner or operator shall not emit into the ambient air nitrogen oxide emissions in excess of the 12-month rolling emission limit specified in Table 9-2. The 12-month rolling emission limits includes periods of startup, shutdown, and malfunction: The first month of the 12-month rolling total shall begin the month of the initial startup of the Unit #13.

IV. Procedural History of Contested Case Proceedings

A. Petitions, Motions and Pre-Hearing Procedures (2008)

61. On February 20, 2008, Otter Tail timely filed petitions with the Board

requesting contested case hearings regarding the PSD and Title V permits.

62. On May 15, 2008, Petitioners Sierra Club and Clean Water Action, Inc.,

timely filed their "Petitions for Contested Case Hearings on the Big Stone Facility's

Proposed Title V Air Quality Permit and Acid Rain Permit No. 28-0801-29 and the Big

Stone I1 Facility's Proposed PSD Permit No. 28-0803-PSD" (the "Petition"). The

Petition raised the following issues with respect to the proposed permits:

a. Issues 1-4: Challenging the use of plantwide caps for SO2

and NO,.

b. Issue 5: Arguing that prior modifications to Big Stone I

should have triggered PSD Review.

c. Issues 6-7: Arguing that the PSD permit was invalid

because it did not impose BACT limitations on emissions of greenhouse

gases, specifically carbon dioxide ('TO2") and methane.

d. Issue 8: Arguing that DENR should have considered IGCC

in its BACT analysis.

e. Issues 9 and 17: Arguing that DENR should have

separately analyzed emissions of particulate matter with an aerodynamic

diameter less than 2.5 microns ("PM2,3") in the BACT analysis and with

respect to whether Big Stone I1 would violate NAAQS.

f. Issue 10: Challenging DENR's BACT analysis with

respect to PMlo.

g. Issue 11: Challenging DENR's BACT analysis with

respect to sulfuric acid mist ("SAM").

h. Issue 12: Challenging DENR's BACT analysis with

respect to fluorides.

1. Issue 13: Arguing that the Proposed PSD Permit is legally

invalid because it does not require compliance with BACT limits during

periods of startup and shutdown.

j. Issue 14: Arguing that the Proposed PSD Permit is legally

invalid because the modeling was insufficient to demonstrate compliance

with NAAQS and PSD increments during periods of startup and

shutdown.

k. Issue 15: Challenging DENR's conclusion that Big Stone

I1 will not cause or contribute to a violation of PMlo NAAQS and PSD

increments.

1. Issue 16: Challenging DENR's conclusion that Big Stone

I1 will not cause or contribute to a violation of SO2 and NOx NAAQS.

m. Issue 18: Arguing that the Proposed Title V Permit is

invalid because it did not properly address case-by-case MACT

requirements.

n. Issue 19: Arguing that the Proposed Title V Permit does

not include all applicable requirements and impermissibly allows

operation of Big Stone 11.

63. The Board consolidated all the pending petitions into one contested case

hearing.

64. On May 23, 2008, Petitioners moved to voluntarily dismiss Issue 5 of their

Petition. The Board granted the motion by order dated June 16, 2008.

65. On June 4, 2008, Otter Tail filed and served a motion and supporting brief

seeking dismissal of Issues 6 and 7 of the Petition.

66. On July 7, 2008, both Otter Tail and the Petitioners moved for partial

summary judgment. In its motion, Otter Tail sought summary judgment on Issues 9 and

17 regarding DENR's use of PMlo as a surrogate for PM2.5 in its BACT and NAAQS

analyses. In Petitioners' motion, Petitioners sought judgment on Issues 1, 2, 4, 6-8, 13-

14, and 18-19. The parties provided the Board with briefs in support of their respective

positions.

67. On July 17, 2008, the Board heard argument on Otter Tail's Motion to

Dismiss and the parties' respective motions for partial summary judgment.

68. On July 22, 2008, the Board entered an order granting Otter Tail's Motion

to Dismiss Issues 6 and 7 because Petitioners failed to state any claim upon which relief

could be granted with regard to these issues. Accepting the arguments of Otter Tail and

DENR, the Board may not consider control of the emissions of C 0 2 and methane,

because they are not regulated at this time by EPA or the State of South Dakota.

69. On July 22, 2008, the Board also entered an order granting Otter Tail's

Motion for Partial Summary Judgment with respect to Issues 9 and 17 finding there was

no genuine dispute of material fact as to these issues and because Otter Tail was entitled

to judgments on these issues as a matter of law. Accepting the arguments of Otter Tail

and DENR, the Board found that DENR had properly used PMlo as a surrogate for a

BACT analysis of PM2,5 and NAAQS modeling, and therefore, as a matter of law, no

separate BACT analysis or modeling for PM2,5 is required.

70. On July 22, 2008, the Board entered an order denying Petitioners' Motion

for Partial Summary Judgment in its entirety.

B. Evidentiary Contested Case Hearing Before the Board (2008)

71. The Contested Case Hearing was bifurcated to allow Petitioners sufficient

time to analyze all of Otter Tail's and DENR's modeling evidence. The Board set aside

dates in August for the first portion of the hearing and dates in September for the second

portion of the hearing. The first portion was designated for all issues other than

modeling, while the second portion was designated for the modeling issues and rebuttal.

The parties were provided ample time to conduct discovery, present their evidence, and

cross examine the witnesses. A quorum of Board members was present at all times

during the hearings. In addition, any Board members who were not present at any

particular time during the hearing have read the hearing transcript and reviewed the

exhibits admitted.

72. Over the course of the contested case hearings, the Board heard the

testimony of ten witnesses, and accepted into evidence 292 exhibits comprising over

18,200 pages. In addition to the evidence presented at the hearing, the parties engaged in

extensive discovery efforts during which five persons were deposed and more than

46,000 pages of documents were exchanged by the parties pursuant to written discovery

requests. [Tr. 1388-89 (stipulation by parties, 9/26/08)].

73. DENR presented the testimony of the following witnesses:

a. Brian Gustafson, Administrator of DENR's Air Quality

Program. Mr. Gustafson has a Bachelor of Science Degree in geological

engineering from the South Dakota School of Mines & Technology. He

has been employed by DENR in the Air Quality Program since 1998. Mr.

Gustafson's responsibilities as the administrator of DENR's Air Quality

Program include management of the program and assuring the program is

meeting all EPA requirements. [Tr. 4 1 (Gustafson, 811 8/08)].

b. Brad Schultz, Team Leader, DENR Air Quality Program.

Mr. Schultz is an Environmental Senior Scientist with the Air Quality

Program of DENR. Mr. Schultz is a graduate of South Dakota State

University and has a degree in agronomy. Mr. Schultz has been employed

by the State of South Dakota in its environmental programs since 1979 (at

that time within the Department of Health and presently with DENR). Mr.

Schultz, as team leader for the Air Monitoring Program, is responsible for

developing and implementing the air monitoring system for the State of

South Dakota. [Tr. 76-77 (Schultz, 811 8/08)].

c. Kyrik Rombough, Team Leader For Permitting, DENR Air

Quality Program. Mr. Rombough received a Bachelor of Science degree

in chemical engineering from the South Dakota School of Mines &

Technology in May 1999. Following graduation, he started work with

DENR's air quality program. In his job duties, Mr. Rombough is

responsible for processing, reviewing, and making decisions regarding the

relevant permit applications, including the preparation of the Statements of

Basis, the draft permits, the final proposed permits, and DENR's

responses to public comments. Mr. Rombough has worked on most of

South Dakota's Title V permits (approximately 90) and PSD permits

(approximately 7 or 8), and has been the primary permit writer on 40-50 of

the Title V permits and 4 of the PSD permits. [Tr. 123 (Rombough,

811 8/08)],

d. Jim Anderson, Natural Resources Project Engineer, DENR

Air Quality Program. Mr. Anderson graduated from the South Dakota

School of Mines & Technology with a bachelor's degree in chemical

engineering. Mr. Anderson performs ambient air quality modeling.

74. Otter Tail presented the testimony of the following witnesses:

a. Mark Rolfes, Project Manager of Big Stone I1 Project. Mr.

Rolfes has the overall responsibility for the development and

implementation of the Big Stone I1 project. [Tr. 489-90 (Rolfes,

8/20/08)]. He is a Professional Engineer licensed in South Dakota and

Minnesota. He is a 1977 graduate of North Dakota State University,

receiving a Bachelor of Science degree in mechanical engineering. Mr.

Rolfes has been employed with Otter Tail for over 3 1 years. He served as

plant manager of the Big Stone I plant for 14 years and has been the

manager of the Big Stone I1 Project since 200 1.

b. Terry Graumann, Manager of Environmental Services,

Otter Tail. Mr. Graumann is responsible for ensuring that the

documentation and permitting activities associated with Otter Tail's

operations are in compliance with various state and federal environmental

regulations. Mr. Graumann acts as the liaison with DENR to ensure that

Otter Tail receives the appropriate information to complete permitting

applications and that applications are properly filed. Mr. Graumann also

coordinates with plant engineers and outside consultants on data-gathering

projects to ensure that Otter Tail meets its obligations outlined in permit

conditions. Mr. Grawnann has been employed with Otter Tail since 1973

and has remained actively involved in its environmental division for 35

years. Mr. Graumann has served as a team member on the Big Stone I1

Project since 2004. [Tr. 560-66 (Graumann, 8/20/08)].

c. David Gaige, P.E., Project Manager, Environmental

Division, Burns & McDonnell. Mr. Gaige is a licensed professional

engineer in the State of Colorado and is employed as a senior project

manager in the environmental studies and permitting division of Bums &

McDonnell. Mr. Gaige has over 32 years of experience in air quality

permitting. Mr. Gaige has an undergraduate degree in mechanical

engineering from Texas Tech University and a master's degree in

mechanical engineering fiom Colorado State University. Mr. Gaige was

previously employed by the Colorado Health Department, working in air

permitting programs. As a consulting engineer, he has worked on permits

for various power plants, including approximately 20 coal-fired plants.

Mr. Gaige has extensive experience in BACT analysis and air dispersion

modeling. [Tr. 686, 687, 1 142 (Gaige, 812 1/08 & 9/25/08); Ex. 3 191.

d. Robynn Andracsek, P.E., Environmental Engineer, Burns

& McDonnell. Ms. Andracsek is a licensed professional engineer in the

State of Kansas and is employed as an environmental engineer with Bums

& McDonnell in Kansas City, Missouri. Ms. Andracsek has an

undergraduate degree in mechanical engineering and a master's degree in

environmental engineering, both from the University of Kansas. Ms.

Andracsek has worked with air dispersion modeling on a daily basis for

the last 11 years and has extensive experience with air dispersion

modeling for power plants and other industrial facilities. Ms. Andracsek

was the primary modeler for the Big Stone I1 project. [Tr. 984-89

(Andracsek, 9/24/08); Ex. 3781.

75. Petitioners presented the testimony of the following persons:

a. Ranajit "Ron" Sahu, Ph.D., consultant. Dr. Sahu works as

an independent environmental consultant with experience in reviewing

coal-fire power plant applications and air quality emissions calculations.

Dr. Sahu has an undergraduate degree in mechanical engineering from the

Indian Institute of Technology and completed his Ph.D. in the

environmental aspects of coal combustion at Cal Tech in 1988. [Tr. 783-

85 (Sahu, 8/26/08)]. Dr. Sahu has never served as a regulator, nor can he

recall ever preparing an air permit application for a coal-fired power plant.

[Id. at 927-281. He has never prepared a BACT analysis for a coal-fired

power plant. [Id. 1.

b. Patrick Hanrahan, P.E., consultant. Mr. Hanrahan works as

an independent air quality consultant and is a registered professional

engineer in chemical and environmental engineering. He received his

undergraduate degree in chemistry from Portland State University in 1970

and master's degree in biochemistry from the University of Illinois in

Urbana in 1972. [Tr. 1309-10, 1320 (Hanrahan, 9/26/08)]. Mr.

Hanrahan's experience with air quality modeling for coal-fired power

plants, including their haul roads, is very limited. [Id. at 1359-611. Mr.

Hanrahan presented his testimony by telephone at the request of

Petitioners.

C. Evidentiary Contested Case Hearing Before the Board (2009)

76. The Board consolidated the continuation of the contested case on the Title

V permit with the evidentiary hearing ordered by the Circuit Court of Hughes County

pursuant to SDCL 1-26-34 in connection with the PSD appeal.

77. Kyrik Rombough was the only witness who testified.

78. A quorum of Board members was present at all times during the April

2009 hearing.

D. General Findings Regarding Contested Case Hearings

79. Throughout the course of the extensive hearings in this matter, the Board

had ample opportunity to observe the witnesses in person (or to hear their testimony live

via telephone in the case of Mr. Hanrahan). The Board has observed the demeanor of the

witnesses and has considered the testimony they provided under direct and cross

examination. Considering all the evidence presented at the hearing, the Board finds the

testimony of Otter Tail's witnesses and DENR staff to be more credible and convincing

than the testimony by Petitioners' witnesses. In further comparison to Petitioners'

witnesses, the Board finds the witnesses of Otter Tail and DENR have more education,

training, and experience in the field, particularly with regard to air permitting for coal-

fired power plants. In addition, the Board finds the witnesses of Otter Tail and DENR

utilized reasonable, prudent methodologies of analysis whereas Petitioners' witnesses

advocated for speculative or unreasonable methodologies. In many instances,

Petitioners' witnesses offered nothing more than criticisms without offering any

alternatives. Petitioners' witnesses had not spent as much time as DENR's and Otter

Tails's witnesses investigating and evaluating this project and did not display nearly as

much familiarity with the project and its supporting information. The testimony of

Petitioners' witnesses revealed various misunderstandings about the project and about the

supporting information.

80. The Board finds that DENR and its staff persons properly exercised their

judgment in this matter in concluding that the permits should be issued. DENR and its

staff members have substantial education, training, and experience in the field of air

permitting (including PSD and Title V permits) and in the enforcement of federal and

state air quality standards and regulations. The DENR staff spent thousands of hours

reviewing and analyzing Otter Tail's permit applications, preparing draft permits,

analyzing and reviewing comments, working with EPA to address and resolve EPA's

objections, and participating in the contested case hearings.

V. Facts support in^ the Issuance of the Proposed PSD Permit

A. Applicability of PSD

81. Grant County is located in an attainment area, and Big Stone I1 is subject

to PSD review for PMlo, PM2.5, CO, VOC, fluorides and sulfuric acid mist. The main

elements of PSD review are BACT, demonstration of compliance with NAAQS and

increment through air quality modeling, and an analysis of additional impacts.

82. PSD review is not required for SO2 and NOx. Under 40 C.F.R. 3 52.21(b),

Big Stone I and I1 are one stationary source. The 2008 Title V permit established

federally enforceable plantwide emission limits for SO2 and NOx. The limits applied to

all emission units at Big Stone I and I1 that emit SO2 and NOx. With these limits

applicable facility-wide, Big Stone I1 would not cause any increase in SO2 or NO,

emissions for the source. [Core Ex. 198 at 15-17]. To respond to EPA's objection that

individual unit limits are necessary, , DENR conducted a netting analysis as described in

the revised Title V Statement of Basis and established SO2 and NOx limits for each

individual emissions unit such that these pollutants are not subject to PSD Review. [Core

EX. 842A 5-1 51.

83. DENR appropriately used PMlo as a surrogate for PM2 5 in the PSD

review. Therefore, the Board finds that a separate PM2 5 PSD review was not required.

B. BACT Analysis

1. The BACT Process and Relevant Definitions

84. The BACT requirement applies to each individual new or modified

affected emissions unit and pollutant emitting activity at which a net emissions increase

would occur. The BACT analysis consists of determining the best available control

technology and establishing an emissions limit based on the maximum degree of

reduction achievable for each pollutant subject to regulation under the federal Clean Air

Act.

85. The BACT analysis is determined

on a case-by-case basis, taking into account energy, environmental, and economic impacts and other costs, [and] is achievable . . . through application of production processes or available methods, systems, and techniques, including fuel cleaning or treatment or innovative fuel combustion techniques for control of [the] pollutant. In no event shall application of [BACT] result in emissions of any pollutant which would exceed the emissions allowed by any applicable standard under [the New Source Performance Standards]. If the Administrator determines that technological or economic limitations on the application of measurement methodology to a particular emissions unit would make the imposition of an emissions standard infeasible, a design, equipment, work practice, operational standard, or combination thereof, may be prescribed instead to satisfy the requirement for the application of [BACT]. Such standard shall, to the degree possible, set forth the emissions reduction achievable by implementation of such design, equipment, work practice or operation, and shall provide for compliance by means which achieve equivalent results.

40 CFR 5 52.21(b)(12), incorporated by ARSD 74:36:09:02.

86. In determining BACT, a permitting authority should recognize that BACT

must be met at all times under worst case conditions and that overall system performance

degrades over time. Thus, setting an unrealistically low BACT limit in the hope that the

facility will somehow meet it is not good regulatory practice.

87. A high degree of technical judgment also must be exercised in any BACT

analysis for coal-fired plants, because of the wide variety of coals and coal-fired

facilities. The Board agrees with EPAYs Environmental Appeal Board ("EAB") that

BACT decisions are highly site-specific:

We note, however, that PSD permit decisions depend heavily on site-specific analysis, and this kind of case-by- case decision making inevitably results in substantive differences from permit to permit. See, e.g., In re Cardinal FG Co., 12 E.A.D. 154, 16 1 (EAB 2005) (explaining that "BACT is a site-specific determination"); In re Old Dominion Elec. Coop., 3 E.A.D. 779,788-89 (Adm'r 1992)

("PSD permit determinations are made individually under the Act on a case-by-case basis . . . .").

In re BP Cherry Point, 12 E.A.D. 209, 223 n.37 (EAB 2005); see also In re Prairie State

Generating Co., PSD Appeal No. 05-05, slip op. at 71 (EAB August 24,2006), aff'd sub

nom. Sierra Club v. EPA, 499 F.3d 653,655 (7th Cir. 2007).

88. In the context of BACT, "available" and "achievable" are not exact terms

and do not have explicit regulatory definitions. Therefore, they are subject to reasonable

interpretation and judgment.

89. According to the definition of BACT, a control technology must be

"available" and "applicable" to be considered BACT. 40 CFR § 52.21(b)(12),

incorporated by ARSD 74:36:09:02. It is reasonable to interpret "available" as follows:

[A] technology is considered "available" if it can be obtained by the applicant through commercial channels or is otherwise available within the common sense meaning of the term. An available technology is "applicable" if it can reasonably be installed and operated on the source type under consideration.

Prairie State, slip. op. at 45 (citation omitted).

90. Feasible technology means technology that is commercially available and

has been demonstrated (i.e., proven) on the type of source being permitted. This means

that the technology has progressed beyond the conceptual stage and beyond the pilot

testing phase. See Cardinal, 12 E.A.D. at 166 ("Technologies in the testing stage

generally are not considered technically feasible."). The technology must have been

demonstrated successfully on full-scale operations for a sufficient time to be considered

proven. Id. at 166-67 (upholding permitting agency's rationale that 2 to 3 years operating

history of a technology "is insufficient to satisfy the concept of demonstrated

technology").

91. According to the definition of BACT, a BACT limit must also be

"achievable." 40 CFR $ 52.21(b)(12), incorporated by ARSD 74:36:09:02. To

determine whether a limit is achievable, a high degree of technical judgment and

expertise must be used.

92. "Achievable" in the context of BACT means an emission limit that the

source can meet on a continual basis over each averaging period for the lifetime of the

facility. To establish limits based on unproven supposition or on short-term expectations

is to virtually ensure repeated and unavoidable permit violations. BACT limits should be

set at levels the source can meet under all reasonably foreseeable worst-case conditions

because exceeding a BACT limit is a serious violation and the penalties are severe.

BACT limits are therefore not established based on what a source can achieve on its best

possible day or on an average day. BACT is not established based on speculation or what

may theoretically be possible on a short-term basis. Accordingly, a BACT analysis does

not require an applicant or the permitting agency to speculate about what a technology

might be able to achieve in the future. See, e.g., Cardinal, 12 E.A.D. at 166-67.

93. It is appropriate to include "safety factors" or "cushions" to ensure that

BACT limits are achievable at all times. [Tr. 690-91 (Gaige, 08/21/08); see also In re

Masonite Corp., 5 E.A.D. 551, 560-61 (EAB 1994); In re Knauf Fiber Glass, GmbH, 9

E.A.D. 1, 15 (EAB 2000) ("There is nothing inherently wrong with setting an emission

limitation that takes into account a reasonable safety factor."); id. ("The inclusion of a

reasonable safety factor in the emission limitation calculation is a legitimate method of

deriving a specific emission limitation that may not be exceeded."); accord Three

Mountain Power, LLC, 10 E.A.D. 39,53 (EAB 2001)l.

94. This Board agrees that, while BACT is forward looking, "the word

'achievable'. . . constrains the permit issuer's discretion by prohibiting BACT limits that

would require pollution reductions greater than what can be achieved with available

methods." In re Newmont Nev. Energy Investment, LLC, 12 E.A.D. 429, 441 (EAB

2005); accord Prairie State, slip op. at 70. We recognize that "the permit issuer may take

into account the absence of long-term data, or the unproven long-term effectiveness of

the technology, in setting the emissions limitation that is BACT for the facility."

Newmont, 12 E.A.D. at 442; see also Cardinal, 12 E.A.D. at 166-67. The BACT analysis

"must be solidly grounded on what is presently known about the selected technology's

effectiveness" and "emissions limitations achieved by other facilities and corresponding

control technologies used at other facilities are an important source of information in

determining" BACT. Newmont, 12 E.A.D. at 44 1 (emphasis added).

95. To determine BACT, recent permits for similar sources with the selected

technologies are important. See In re New Century Development, 1 1 E.A.D. 40, 52-53

(EAB 2003; see Cardinal, 12 E.A.D. at 170 ("PSD permit limits are not necessarily a

direct translation of the lowest emission rate that has been achieved by a particular

technology at another facility."). Information from vendors based on the source and fuel

characteristics are also an important source of information.

96. The Board will not use BACT to redefine the source. BACT does not

require an applicant to build a fundamentally different type of facility from the one it has

proposed to build. The BACT determination must have as its starting point the

"proposed facility." 42 U.S.C. 5 7475(a)(4); ARSD 74:36:09:02 (incorporating 40

C.F.R. 3 52.21(b) (12), which requires that BACT be applied to a "proposed major

stationary source"). Based on the statutory language requiring application of BACT to

the "proposed facility," EPA has long recognized, in a consistent line of adjudicatory

precedent and guidance, that the BACT process is not "a means to redefine the design of

the source when considering available control alternatives." [Ex. 502 at 88; Ex. 321 at

10-201.~ The Seventh Circuit has upheld EPA's interpretation as consistent with the

statutory text of the CAA. Sierra Club v. EPA, 499 F.3d 653, 655 (7" Cir. 2007).

Accordingly, the Board rejects Petitioners' contention that the PSD permit should be

denied because DENR did not consider IGCC.

2. BACT Analysis of Big Stone I1 Emissions

a. PMIO

97. The baghouses proposed by Otter Tail and approved by DENR for

material handling Units #7a-7d, #17, #20, #21, #23a and b, #24, #22, #26, #27, #29, #30,

#34, and #35 are the top control for those emissions units. [Core Exs. 160 at 16, 183 at

11-21.

98. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the 0.0005% drift eliminator

proposed by Otter Tail and approved by DENR is BACT to control PMlo emissions from

the cooling tower (Unit #16). [Core Ex. 160 at 191.

99. The baghouse proposed by Otter Tail and approved by DENR to limit

emissions from the pulverized coal-fired boiler (Unit #13) is the top control for this type

of operation. [Core Ex. 160 at 201.

2 See, e.g., In re SEI Birchwood Inc., 5 E.A.D. 25,28-29 (EAB 1994); In re Old Dominion Elec. Coop., 3 E.A.D. 779,793-94 (EAB 1992).

100. The catalyzed diesel particulate filter in conjunction with ultra low sulfur

diesel fuel are the top controls for PMlo emissions from the fire pump (Unit #14), the

generator (Unit #15), the boiler booster pump (Unit #25), and the silo booster pump (Unit

#33). Baghouses or electrostatic precipitators are not technically feasible because exit

gas temperatures for these units prohibit the use of a baghouse or electrostatic precipitator

for controlling PMlo emissions. [Core Ex. 160 at 15-1 61.

101. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the work practices in Section 7 of

the PSD permit for fugitive dust sources are BACT. [Core Ex. 160 at 271. The Board

also finds that the requirement to pave all haul roads and parking lots within Big Stone's

boundaries is BACT. [Core Ex. 197 at 131.

102. Since the issuance of DENR's final draft permit, a new NSPS has been

proposed for material handling that applies to PMlo emissions from Units #7a-d, #17,

#22, #26, #27, and #30. In accordance with the new NSPS, it is appropriate to reduce the

limits for those units as reflected in Table 4-1 of Exhibit 324 at 9-10. In addition, there is

a typographical error in the BACT limit for Unit #35, which shall also be amended to

conform to the correct number, as reflected in Exhibit 324.

103. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the PMlo emission limits for Big

Stone I1 set forth in Table 4-1 of the Proposed PSD Permit (Core Ex. 197 at 10-1 I), as

revised downward in Otter Tail's Exhibit 324, are BACT.

104. The Board further concludes that the approach described in the PSD

permit with respect to the total PMlo limit is reasonable in light of the uncertainties about

total PMlo emissions, data, and reliability of approved test methods. The total PMlo limit

is subject to testing once operation has commenced and can be reduced as low as 0.018

pounds per million Btu. [Core Ex. 197 at 111.

b. CO

105. Combustion control, as proposed by Otter Tail and approved by DENR, is

the top technology for controlling CO emissions from Units #13, #14, #15, #25 and #33.

[Core Ex. 1 83 at 1 51.

106. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the CO emission limits for Big

Stone I1 set forth in the Proposed PSD Permit at Table 4-2 are BACT. They are

appropriate and are consistent with limits imposed at similar facilities. [Core Ex. 198 at

67-68].

C. v o c s

107. Combustion control, as proposed by Otter Tail and approved by DENR, is

the top technology for controlling VOC emissions from Units #13, #14, #15, #25 and

#33. [Core Ex. 160 at 23; Core Ex. 183 at 15-16].

108. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the VOC emission limits for Big

Stone I1 set forth in Table 4-3 of the Proposed PSD Permit are BACT. [Core Ex. 197 at

121. They are appropriate and are consistent with limits imposed at similar facilities.

[Core Ex. 198 at 691.

d. SAM

109. The baghouse coupled with WFGD, as proposed by Otter Tail and

approved by DENR, is the best technology for controlling emissions of SAM from Unit

#13. A wet electrostatic precipitator ("WESP") is cost-prohibitive at approximately

$147,000 per ton of sulfuric acid mist reduced. [Core Ex. 160 at 24-25]. Likewise,

sorbent injection (such as injection of hydrated lime) does not represent BACT for Big

Stone 11. Big Stone I1 will burn subbituminous coal that is relatively high in calcium

content. Hence, the fly ash will be alkaline in nature, and the addition of hydrated lime or

other sorbents would not be expected to achieve significant additional removal of SAM.

It has not been used in any Powder River Basin ("PRB") coal plant for SAM control.

[Tr. 7 1 1 - 12 (Gaige, 812 1/08)].

110. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the sulfuric acid mist emission

limit for Big Stone I1 set forth in Table 4-4 of the Proposed PSD Permit is BACT. [Core

Ex. 197 at 131. It is appropriate and consistent with limits imposed at similar facilities.

[Core Ex. 198 at 46-47]. Most of the permits with lower limits are distinguishable due to

different type of boiler, different fuel, or different control technologies for other

pollutants. Many of the plants are not yet operating, so the limits are not yet

demonstrated in practice to be achievable. [Tr. 712-1 3 (Gaige, 8/21/08); Core Ex. 160 at

23; Core Ex. 198 at 46-47].

e. Fluorides

11 1. A baghouse coupled with WFGD, as proposed by Otter Tail and approved

by DENR, is the best technology for reducing emissions of fluorides from Unit #13.

[Core Ex. 160 at 261. As noted above for SAM, WESP is not cost-effective and sorbent

injection would be redundant due to the high alkalinity of the PRB ash.

112. Taking into account all the relevant factors and recognizing the technical

judgment and expertise involved, the Board finds that the total fluoride emission limit for

Big Stone I1 set forth in Table 4-5 of the Proposed PSD Permit is BACT. [Core Ex. 197

at 131. It is appropriate and consistent with limits imposed at similar facilities. [Core Ex.

198 at 68-69]. Most of the permits with lower limits are limits only for hydrogen fluoride

("HF"), not total fluorides. [Tr. 714-17 (Gaige, 8/21/08)]. Thus, they are not directly

applicable to Big Stone 11. Others burn a different fuel, which affects fluoride emissions.

[Core Ex. 198 at 681. In addition, most of the plants with lower limits are not yet

operating, and therefore the limits are not demonstrated. [Tr. 7 13- 1 8 (Gaige, 812 1/08);

Core Ex. 160 at 231.

C. Other Applicable Limits (PSD Permit Section 5)

113. The limits and conditions in Sections 5.1 through 5.8 of the draft PSD

permit are appropriate and in compliance with all applicable laws and requirements.

[Core Ex. 197 at 14-16].

D. Performance Tests (PSD Permit Section 6)

1 14. The testing and conditions in Sections 6.1 through 6.10 of the draft PSD

permit are appropriate and in compliance with all applicable laws and requirements.

[Core Ex. 197 at 16-18]. In conjunction with other conditions, the PSD permit is

enforceable as a practical matter.

E. Fugitive Dust Controls (PSD Permit Section 7)

115. The terms and conditions in Sections 7.1 through 7.5 of the PSD permit

are appropriate and in compliance with all applicable laws and requirements. [Core Ex.

197 at 1 8-20].

F. Air Quality Analysis-Air Dispersion Modeling

116. Otter Tail submitted ambient air quality analyses to demonstrate

compliance with the NAAQS and PSD increments. The Board agrees with DENR that

Otter Tail has submitted an adequate demonstration of compliance with NAAQS and

PSD increments.

117. The Big Stone I1 project triggered ambient air quality analyses for PMlo

and CO.

118. Preconstruction ambient monitoring was required for PMlo to determine

background PMlo concentrations. Preconstruction ambient monitoring was not required

for CO. [Core Ex. 183 at 231.

119. Otter Tail performed preconstruction SOz, NO,, and PMlo monitoring in

2001 and 2002. Data was collected for one year and was determined to be valid by

DENR. That monitoring data was accepted by DENR for use in the Big Stone I1 ambient

air quality analyses to reflect background concentrations. [Tr. 97, 103-04, 107 (Schultz,

81 1 8/08)].

120. Otter Tail consulted with DENR regarding the modeling protocol. [Ex.

3091. Otter Tail also provided a protocol describing the methodology used to calculate

fugitive emissions. [Core Ex. 167 at 1961.

121. In accordance with Appendix W of 40 C.F.R. Part 51, five years of

representative meteorological data from 2001 to 2005 were used to estimate

concentrations with an air quality model. The data were obtained from the National

Weather Service ("NWS") Stations located at Huron, South Dakota (#14936) for surface

air and Aberdeen, South Dakota (#14929) for upper air. [Core Ex. 183 at 201. The

permitting authority has a choice between specifying the use of limited one-year on-site

surface meteorological data or five years of meteorological data from representative

NWS. Long term data from the NWS was ultimately selected by DENR. The more

extensive data from the NWS stations at Huron and Aberdeen are not only representative

of the weather conditions at the proposed Big Stone I1 site, but are also more reliable than

the limited one-year on-site data. [Tr. 1063-64 (Andracsek, 9/24/08); Tr. 1162-63

(Gaige, 9/25/08)]. The Board finds the meteorological data used for the modeling is

reasonable, appropriate, and representative of the proposed Big Stone I1 site.

122. In 2005 as part of the application, Otter Tail submitted modeling

consistent with the protocol. In 2006, Otter Tail updated the modeling to reflect proposed

changes in the design of the facility. Otter Tail performed additional air dispersion

modeling analyses in 2007 using the preferred, current regulatory model.

123. The air dispersion modeling on behalf of Big Stone I1 used appropriate

methodologies and reasonable, reliable, conservative assumptions. It was consistent with

methodologies and assumptions approved by other states and by EPA in other air

permitting proceedings. [Tr. 1 144 (Gaige, 9/25/08)].

124. After considering all the evidence presented, the Board finds that the July

2007 modeling for PMlo and CO, as accepted by and relied upon by DENR, represents an

adequate, reliable, and appropriate demonstration of compliance with NAAQS and PSD

increments. Big Stone I1 will not cause or contribute to a violation of any applicable

NAAQS or PSD increment. [Core Ex. 183 at 241.

G. Modeling for Class I Areas

125. Because the Big Stone I1 project is located near Big Stone City, South

Dakota, which is greater than 300 kilometers away from any Class I area, Class I

modeling was not required. [Core Ex. 183 at 251. Nevertheless, DENR did provide

notice of the applications to the IVational Park Service pursuant to an agreement to keep

the National Park Service informed of certain applications in South Dakota. The

National Park Service agreed that no Class I area analysis was required, but did request a

visibility analysis at the Pipestone National Monument, which analysis Otter Tail agreed

to perform and did perform. [Tr. 130-33 (Rombough, 8/18/08); Core Ex. 1351. The

analysis showed that no adverse visibility impacts will occur. [Core Ex. 160 at 371.

H. Additional Impacts Analysis

126. The evidence established that Big Stone I1 complied in all respects with

the requirement for an additional impacts analysis. [Core Ex. 160 at 37-38]. No adverse

impacts are expected to air quality, visibility, or soils and vegetation as a result of the

facility and associated commercial, residential, and industrial growth.

I. Conclusion Regarding PSD Permit

127. After consideration of the record, the evidence and testimony received at

the contested case hearing and the technical expertise involved, the Board finds that the

proposed PSD permit is appropriate and complies with all applicable laws and

regulations. [Core Ex. 1971.

VI. Facts Supporting the Issuance of the Proposed Title V Permit

A. General

128. For the reasons stated in the Title V Statement of Basis, as revised and

supplemented by the revised Title V Statement of Basis (Core Exs. 217, 842A) and

DENR's Responses to Comments (Core Exs. 198, 853), the revised Title V permit with

Otter Tail's suggested change is appropriate and complies with all applicable laws and

requirements.

B. Netting and Other Conditions Applicable to NO, and SO2

129. Units #13, #14, #15, #25 and #33 emit SO2 and NOx and will be permitted

under the Title V Air Quality Permit for Big Stone I. Existing Units #5 and #6 will be

removed from the Title V permit once the Big Stone I1 project is constructed and begins

operation. [Core Ex. 2 17 at 5-61.

130. Otter Tail requested and DENR has proposed operational and emission

limits that will maintain actual emissions of SO2 and NOx at levels that will allow the Big

Stone I1 project to avoid a PSD review for these two air pollutants. As noted in Otter

Tail's PSD application for the Big Stone I1 project, Otter Tail proposes to install

equipment that will control the SO2 and NOx emissions from Unit #13 and has made an

agreement with Big Stone I owners to reduce Big Stone I's SO2 and NOx emissions. This

will result in a zero emission increase for both air pollutants. [Core Ex. 2 17 at 151.

13 1. In response to EPA's objections on PSD applicability to SO2 and NOx, the

Title V permit has been revised to incorporate EPA's option for PSD netting. [Core Ex.

842A at 51.

132. The revised proposed Title V permit imposes unit-specific limits for SO2

and NO, to resolve EPA's objections. The limits for establishing emission decreases at

Big Stone I are specific to Big Stone I, ensure actual emission decreases at least as great

as .the emission increases expected from the Big Stone I1 project, and ensure the

decreases in actual emissions are enforceable as a practical matter, at and after the

construction date of the Big Stone I1 project. The permit also establishes SO2 and NOx

limits that are specific to the emission units associated with the Big Stone I1 project and

when summed together are no greater than the actual emission decreases required from

Big Stone I .

133. For purposes of setting the baseline for the netting analysis, the period of

January 2003 through December 2004, is appropriate and is selected as representative of

baseline actual emissions in accordance with 40 CFR 5 52.21(b)(48)(i). [See Core Ex.

853 at 6-81. In selecting this baseline period as representative, the Board has considered

the timelines of the permitting process, the projects and uncontrollable plant

circumstances that affected normal operations, and the existing requirements under the

Title V air quality permit.

134. The Board finds the unit-specific SO2 and NO, limits in the revised permit

appropriate, as are the calculations upon which those unit-specific limits are based. [See

Core Ex. 842A at 6- 151.

135. The Board finds that DENR's rationale for deleting sentences in

Conditions 9.2 and 9.4 from the previously-proposed Title V permit is persuasive and the

Board accepts it. [See Core Ex. 842A at 151.

136. SO2 emissions from Unit #13 will be controlled by a WFGD. Unit #13 is

not allowed to operate when the WFGD is not operational. Otter Tail will connect the

baghouse exhaust from Unit #1 to the WFGD being installed on Unit #13 before Unit #13

goes into operation. NOx emissions from Unit #13 will be controlled by a SCR. NOx

emissions from Unit # 1 will be controlled further by implementing operational changes at

Big Stone I before Unit # 1 3 goes operational. [Core Ex. 2 17 at 161.

137. Units #1 and #13 will be required to install, maintain, and operate

Continuous Emissions Monitoring Systems ("CEMS") for SOz and NOx by the

requirements under the Acid Rain Program and the NSPS for electric utility steam

generators. Since the CEMS will be able to provide quantifiable data on an hourly,

monthly, and yearly basis, a short term or hourly emission limit is not warranted for

demonstrating compliance with the SOz and NOx 12-month rolling limitation to forego

PSD. [Core Ex. 217 at 161.

138. The short term SO2 limit for Unit #2, #3, and #4 is based on using low

sulhr distillate oil or biodiesel with a sulfur content less than 0.05 percent by weight

sulfur. The short term limits for Unit #14, #15, #25, and #33 will be based on using ultra

low sulfur distillate oil or biodiesel with a sulfur content less than 0.0015 percent by

weight sulfur. Compliance with the sulfur content limit will be based on fuel supplier

certification and/or grab samples from the liquid fuel storage tanks. [Core Ex. 217 at 171.

139. The short term NOx emission limit for Unit #2, #3, and #4 is 0.17 pounds

per million Btu heat input, 0.14 pounds per million Btu heat input, and 0.024 pounds per

horsepower hour, respectively, derived from emission rates used in the Otter Tail

application for Big Stone 11. The NSPS for stationary compression ignition internal

combustion engines contains a NOx plus non-methane organic compound short term

emission limit for Unit #14, #15, #25 and #33. [Core Ex. 217 at 171.

C. Adequacy of Compliance Provisions for SOt and NOx

140. EPA objected because the proposed Title V permit did not specify where

the CEMS were to be located and how compliance with the SO2 and NOx emission limits 'L.

would be demonstrated. EPA also commented that the data substitution methods should

be identified.

141. The revised Title V Statement of Basis responds to the objection and

comment at paragraph 139. Attachment A thereto identifies the locations of the CEMS.

DENR also proposed revisions to the Title V permit describing the location of the CEMS

and the methodology for determining emissions to assure compliance with unit specific

emission limits. The Board finds the response to be appropriate and hereby adopts it.

D. Mercury Limits

142. On March 3 1, 2006, Otter Tail proposed a voluntary facility-wide cap on

mercury emissions from Big Stone I and Big Stone 11. The cap is reflected in the revised

Title V permit Section 1 1.1. Otter Tail also proposed a specific mercury limit for Unit 13

that is reflected in Section 1 1.2.

143. During the application process, DENR anticipated that Big Stone I1 would

be subject to the NSPS of the Clean Air Mercury Rule ("CAMR). Shortly before DENR

issued its final draft of the proposed Title V permit, the United States Court of Appeals

for the D.C. Circuit vacated CAMR. New Jersey v. EPA, 517 F.3d 574 (D.C. Cir. 2008).

Nevertheless, Otter Tail has agreed to maintain the mercury limits in the Title V permit.

144. The plantwide mercury cap, reflective of estimated mercury emissions

prior to the installation of Big Stone 11, is appropriate. Emissions will be monitored by

CEMS per section 11.6 of the draft Title V permit. Based on the evidence submitted at

the contested case hearing and the technical expertise required, the Board finds that the

mercury limits in Sections 1 1.1 and 1 1.2 should be included in the Title V permit.

E. Limitation on HAPS to Avoid Triggering MACT

145. A case-by-case MACT review is required when an owner or operator

constructs a major source of HAP. A source is "major" if its potential emissions equal or

exceed 10 tons per year of a single HAP or 25 tons per year of total HAPS. 40 C.F.R.

5 63.2. For construction of a new unit at an existing source, only the emissions from the

new unit are compared to the major source thresholds. 40 C.F.R. tj 63.41. Big Stone I1 is

a new unit at an existing source.

146. Big Stone 11's potential HAP emissions do not meet either of the

thresholds. Otter Tail requested and DENR has proposed permit limits in the Title V

permit (Sections 1 1.3-1 1.5, 11.7, and 11.8) that are below the thresholds to ensure that

Big Stone I1 is not a major source by limiting Big Stone 11's potential to emit. [Core Ex.

2 19 at 3 1-32; 40 C.F.R. tj 63.2 (defining "potential to emit")].

147. EPA objected that the compliance provisions were inadequate for the

HAPS limits in the 2008 proposed Title V permit. As explained in the revised Title V

Statement of Basis (Core Ex. 842A) at pages 17-20 and in DENR's 2009 responses to

comments (Core Ex. 853) at pages 13-14, the revised Title V permit has been modified in

several specific respects to respond to EPA's objection and to public comments. The

Board finds that the revisions are proper responses to EPA's objection and to public

comments and hereby adopts the revisions.

148. The HAP limits are enforceable. The evidence proved that the conditions

of the revised Title V permit are sufficient to render the HAP limits enforceable as a

practical matter.

149. Based on the evidence submitted, the record, and the technical expertise

required, the Board finds that a case-by-case MACT review is not required for the

addition of Big Stone 11. [Core Exs. 186; Core Ex. 198 at 71-75; Core Ex. 842A; Core

Ex. 8-53].

F. Addition of PSD Requirements

150. EPA objected on grounds that the Title V permit should include the Big

Stone I1 PSD requirements. Although DENR continues to disagree with EPA's

objection, the specific PSD requirements are being incorporated into the revised Title V

permit to address EPA's objection.

15 1. Pages 3 and 4 of Core Exhibit 842A list the specific conditions from the

PSD permit that are being incorporated into the revised Title V.

152. Additionally, EPA questioned whether the BACT limits in the PSD permit

applied during startup, shutdown and malfunction. As this Board previously found and

concluded, the numeric BACT limits for Big Stone I1 apply at all times, including periods

of startup, shutdown and malfunction.

153. Under all the circumstances, the Board finds that the decision to

incorporate the PSD conditions into the revised Title V permit is reasonable and

appropriate.

G. Conclusion Regarding Revised Title V and Acid Rain Permit

154. After consideration of the record, the evidence and testimony received at

the contested case hearing, and the technical expertise involved, the Board finds that the

revised Title V and Acid Rain permit is appropriate and complies with all applicable laws

and regulations.

VII. Findings Relating to Issues Raised by Petitioners (2008 Contested Case)

A. Plantwide Caps (Issues 1-4)

155. In Issues 1-4, Petitioners attempted to challenge the use of facility-wide

caps restricting SO2 and NOx emissions by questioning the legality and sufficiency of the

annual caps on SO2 and NOx in the Title V permit. The Board found Otter Tail had

satisfied its burden of proof on these claims.

156. The owners of Big Stone I and I1 requested facility-wide emission caps be

imposed on SO2 and NOx so that PSD review would be unnecessary for those pollutants.

PSD is triggered at an existing source if there is a "major modification," which is defined

as "any physical change in or change in the method of operation of a major stationary

source that would result in a significant emissions increase . . . and a significant net

emissions increase of that pollutant from the major stationary source." ARSD

74:36:09:03, incorporating 40 C.F.R. tj 52.21(b)(2)(i). While the construction of Big

Stone I1 is a "physical change" in a "major stationary source," the requested facility-wide

annual emissions caps impose federally enforceable limitations on the potential of Big

Stone I and I1 to emit SO2 and NOx and prevent any increase in emissions.

157. DENR has the authority under ARSD 74:36:05:16 to establish plantwide

caps (i.e., synthetic minor permit limits) in a Title V permit. Such permit limits are

federally enforceable per ARSD 74:3 6:01:0 l(29).

158. DENR included carefully crafted language in the 2008 proposed Title V

permit to impose facility-wide annual emissions caps on SO2 (Section 9.2) and NOx

(Section 9.4). The permit required CEMS for SO2 and NOx for Unit # 1 and #13 and SOz

and NO, emissions verification via emissions tests and fuel data for Unit #14, #15, #25,

and #33. The permit also imposes substantive penalties (including the need for PSD

review) if the SO2 or NOx caps are exceeded.

159. For the 2008 proposed Title V permit, DENR did not rely on the PSD

netting or Plantwide Applicability Limit ("PAL") regulations as the basis for establishing

the plantwide caps for SO2 and NOx. Contrary to Petitioners' claims, the emissions caps

do not and need not rely on the "netting" or PAL provisions of the PSD regulations. See

40 C.F.R. 9 52.21(b)(3)(i) (netting); 40 C.F.R. tj52.21(aa) (PALS). Synthetic minor

limits in Title V permits are an acceptable alternative authorized by both South Dakota

and EPA regulations.

160. Petitioners' expert, Dr. Sahu, offered no testimony regarding the SO2 and

NOx plantwide caps.

161. The Board found the plantwide caps to be federally enforceable synthetic

minor pennit limits. Because the caps prevent any emissions increase of SO2 or NOx,

there is no major modification, and PSD requirements, such as BACT and ambient air

modeling, are not applicable for those pollutants.

162. The Board agreed with DENR and found that the plantwide annual caps

on SO2 and NOx emissions are appropriate and comply with all applicable laws and

requirements. The Board found the evidence presented by Otter Tail and DENR satisfied

the burden of proof on issues 1-4.

163. Notwithstanding the above findings, these claims are now moot based on

EPA's objection to the plantwide caps for SO2 and NOx. To resolve EPA's objection,

DENR performed a PSD netting analysis as described in the revised Statement of Basis

and established limits for SO2 and NOx on the individual emissions units in the revised

Title V permit.

B. IGCC (Issue 8)

164. Petitioners claim that the BACT analysis for Big Stone I1 failed to

consider IGCC, an alternative method of generating electricity, and is therefore defective.

165. Owners are not required to construct a fundamentally different type of

facility from the one proposed. [Tr. 371-72 (Rombough, 8/20/08)]. Under the CAA, a

major emitting facility may not be constructed unless the "proposed facility is subject to

[BACT] for each pollutant [from] such facility." 42 U.S.C. $ 7475(a)(4) (emphasis

added). ARSD 74:36:09:02. As other agencies and courts have agreed, the BACT

determination must have as its starting point the bbproposed facility" as defined by the

applicant. Consequently, the BACT determination cannot be used to "redefine" (i.e.,

change the fundamental characteristics of) the proposed facility. [Tr. 37 1-72

(Rombough, 8/20/08); Core Ex. 198 at 40-431.

166. IGCC is a completely different technology for producing electricity, and

permitting agencies are not required to consider it in the BACT analysis for a pulverized

coal ("PC") plant. [Ex. 318; Tr. 371 (Rombough, 8/20/08); Tr. 694-95 (Gaige, 8/21/08);

Ex. 322; Core Ex. 198 at 421. EPA and the vast majority of permitting agencies have

agreed that IGCC need not be considered. [Ex. 3211.

167. Even though IGCC need not be considered in the BACT analysis, the

evidence demonstrated that it would not represent BACT in any event for Big Stone 11.

IGCC is still a developing technology unsuited for the PRB coal available at Big Stone,

and IGCC is not sufficiently reliable or cost-effective for a baseload plant. [Tr. 698

(Gaige, 8/21/08)]. Burns & McDonnell prepared a report analyzing alternative

generation options for Big Stone 11. [See Ex. 3221. That report concluded: (1) no IGCC

had successfully generated electricity with subbituminous coal (as proposed for Big

Stone 11) and without natural gas back-up (which is not available on the Big Stone I1

site); (2) IGCC has not achieved a high capacity factor required for baseload units; and

(3) IGCC would cost 40 to 50 percent more than the equipment proposed for Big Stone

11. [Tr. 506 (Rolfes, 8/20/08) (IGCC risky, unproven, and not cost effective); Tr. 698,

724, 765-66 (Gaige, 8/21/08) (same)]. The South Dakota PUC determined that IGCC

would cost between 43% and 50% more than the proposed pulverized-coal plant. [See In

re the Application by Otter Tail Power Company on Behalf of Big Stone II Co-Owners

for an Energy Conversion Facility Permit for the Construction of the Big Stone 11

Project, No. EL05-022 (S.D. Public Utilities Comm'n July 21, 2006) at 281. Finally, the

small number of IGCC units in actual operation have not shown any better emissions

performance than PC boilers. [Tr. 728-29 (Gaige, 812 1/08)].

168. Like DENR, the Board "disagrees that IGCC has been proven to be ready

and commercially available to produce approximately 600 megawatts of base load

electricity by burning subbituminous coal." [Core Ex. 198 at 431.

169. Petitioners presented no witnesses regarding IGCC at the evidentiary

hearing, but Otter Tail submitted evidence of Petitioner Sierra Club's position on IGCC

in a separate ongoing permitting proceeding. Sierra Club recently submitted comments

to DENR criticizing the proposed Hyperion oil refinery project in South Dakota that

includes an IGCC unit. In those comments, Sierra Club called IGCC an "experimental

process" that "has only operated at an experimental level, not at a commercial level."

[Ex. 333 at 11. Sierra Club also recognized the exorbitant cost of IGCC, noting "the

financial burdens that would jeopardize the financial viability of this proposed

operation." [Id.; see also Tr. 476 (Rombough, 8/20/08)]. While the Board makes no

finding about the appropriateness of IGCC for that unrelated project, we are persuaded by

the evidence that IGCC is not BACT for Big Stone I1 in light of the unique characteristics

of the Big Stone I1 project.

170. Based on the evidence presented at the contested case hearing, the Board

finds that IGCC would impermissibly redefine the source. Even if IGCC were properly a

consideration in the BACT analysis, the Board finds that IGCC would not represent

BACT for the pollutants at issue in this proceeding. IGCC is not demonstrated to be

sufficiently reliable, cost-effective, or commercially available for Big Stone 11. The

Board finds Otter Tail and DENR have submitted reliable, persuasive evidence on Issue 8

and have satisfied the burden of proof.

C. General Findings Regarding Petitioners' Challenges to the BACT Determinations (Issues 10-12)

17 1. Before addressing Petitioners' specific challenges to the BACT

determinations for the PSD permit, the Board makes the following general findings.

Petitioners presented an expert witness, Dr. Sahu, to criticize DENR's BACT analysis for

PMlo, SAM, and fluorides. Dr. Sahu admitted he did not conduct an independent BACT

analysis for the Big Stone I1 Project. [Tr. 864-65 (Sahu, 8/26/08)]. Dr. Sahu has never

conducted a BACT analysis for any coal-fired power plant and has never submitted an air

quality permit application for a coal-fired power plant. [Tr. 927-28 (Sahu, 8/26/08)].

Although Dr. Sahu criticized DENR's BACT analysis as lacking sufficient

documentation, he admitted that the definition of BACT does not say how much support

or documentation an agency needs to provide for any particular application of its

judgment in conducting a BACT review. [Tr. 946 (Sahu, 8/26/08)].

172. In his capacity as an expert witness, Dr. Sahu regularly criticizes various

agencies' BACT analyses around the country. [Id. at 93 11. He could not identify a single

instance where he agreed that a permitting agency had conducted a proper BACT

analysis in all respects. [Id. at 93 1-32]. There was no evidence that Dr. Sahu's testimony

or opinions in other cases have ever been accepted. [Id. at 935-431.

173. Dr. Sahu's testimony regarding DENR's BACT determination procedure

is mistaken and directly conflicts with DENR's witness Mr. Rombough, who testified

that he did not simply pick his BACT numbers from the range of emissions limits in

other permits. [Tr. 1250-5 1 (Rombough, 9/25/08)].

174. Dr. Sahu questioned and criticized various aspects of the BACT analysis

done by Otter Tail and DENR, yet he never identified any fundamental flaws, errors, or

actual shortcomings in the analysis. By contrast, DENR and Otter Tail presented

compelling evidence in support of the BACT determinations.

D. PMlo BACT Analysis (Issue 10)

175. Petitioners argue that DENR erred in setting the BACT limit for PMlo

emissions by failing to consider the AHPC, a more efficient fabric filter baghouse, a wet

electrostatic precipitator, and more efficient SO2 controls as control devices. Petitioners

suggest that, had these other alternatives been considered, DENR would have set lower

BACT limits for PMlo.

176. Based on the use of a fabric filter and WFGD, the permit contains a limit

of 0.012 1bImmBtu for filterable PMlo and an initial limit of 0.03 lb/mrnBtu on total PMlo

(filterable and condensable combined). [Core Ex. 197 $4.1, Table 4-11. The total PMlo

limit will be lowered if actual operating data demonstrates that a lower limit is

achievable, with a target of lowering it to 0.01 8 lb/mmBtu. [Id. $ 4.1, Table 4-11.

177. The evidence at the hearing proved that these PMlo limits are appropriate

and BACT. DENR established the limits based on a thorough examination of available

technologies, a comparison of emission limits in recent permits, consideration of the ash

and moisture content of the fuel to be burned at Big Stone 11, and recognition of the

uncertainty in the measurement of condensables using current approved test methods.

[Tr. 201-06 (Rombough, 8/19/08); Ex. 198 at 43-46; Ex. 160 at 19-24]. Mr. Rombough

did not restrict himself to EPA's database of recent permit limits (the "RBLC" database);

he identified and used other sources of information during his investigation. [Tr. 394-95

(Rombough, 8/20/08)]. As the BACT regulation contemplates, he then applied his

technical judgment, which the Board accepts as reasonable and appropriate.

178. In carrying out its duties, DENR did not simply "rubber stamp" Otter

Tail's proposed limits. DENR has recommended limits to this Board that are lower than

Otter Tail had proposed in its application. [Tr. 297 (Rombough, 8/19/08); Tr. 393-94

(Rombough, 8/20/08)]. The Board is adopting the lower limits proposed by DENR.

179. The undisputed evidence is that the proposed PMlo filterable limit is the

lowest of any final permit for a coal-fired plant burning subbituminous coal. [Tr. 704

(Gaige, 8/21/08)]. Petitioners point to one final permit (Desert Rock) and to permit

applications with slightly lower limits, but 0.012 lb/mmBtu remains the lowest filterable

PMlo limit of any final permit for PRB coal. BACT is a case-by-case analysis, and the

Board finds that Petitioners' evidence did not provide any reason to believe the PMlo

limits are unreasonable. Otter Tail satisfied its burden of proof.

180. The Board rejects Petitioners' suggestion that the AHPC is the best

available control technology for Big Stone I1 to control PMlo. The evidence established

that the AHPC was a complete failure in its trial at Big Stone I. [See, e.g., Tr. 572-79

(Graurnann, 8/20/08)]. The Big Stone I co-owners invested millions in an attempt to

make this experimental technology work (in addition to millions spent by the Department

of Energy and W.H. Gore & Associates). [Id. at 575-76, 578-791. The Department of

Energy provided funding to the project in an attempt to demonstrate AHPC as a viable

technology. The demonstration project failed. DENR was well-aware that the

experiment did not succeed, and Big Stone I finally was forced to replace the AHPC in

2007. [Id. at 5791. It would make no sense now to require Big Stone I1 to install the

flawed AHPC technology as BACT.

18 1. The Board hrther rejects Petitioners' arguments that "better" bag material

or "differently-designed" baghouses should have been considered. Likewise, the Board

rejects the argument that other control devices should have been given greater

consideration. A baghouse was proven to be the best control device for this application,

as numerous permitting agencies have found. This Board is not required to dictate the

specific design or specific vendor of the baghouse or bag material, especially when this

Board has found that the proposed PMlo emissions limit represents BACT. The evidence

established that all necessary and appropriate factors and control devices have been

considered in establishing the emissions limit. [See Tr. 961-62 (Sahu, 8/26/08) (Dr. Sahu

unable to recall any other permit application where the applicant discusses specific types

of bags or the specific design of the baghouses)].

182. Petitioners' expert, Dr. Sahu, tried to use an estimate of uncontrolled PMlo

emissions and controlled emissions to calculate a "removal efficiency" (i.e., percent

reduction) for the baghouse. Considering all the evidence on this point, the Board finds

the evidence of Otter Tail and DENR to be more persuasive and credible on the proper

approach for evaluating a BACT emissions limit.

183. Petitioners also presented evidence from other facilities' source tests to

suggest that Big Stone I1 can achieve lower emissions. [Exs. 504-5061. These same

source tests have recently been reviewed in detail and rejected by both DENR and EPA

as valid for a PMlo BACT determination, and the Board agrees with the reasons cited by

DENR and EPA. [Tr. 1253-54 (Rombough, 9/25/08) (Mr. Rombough personally

reviewed the source test data and found them inapplicable to the BACT analysis in this

case); Ex. 321 at 79-82].

184. The Board finds that DENR's and Otter Tail's evidence satisfied the

burden of proof on Issue 10 and that the PMlo BACT limit is appropriate.

E. SAM BACT Analysis (Issue 11)

185. Petitioners argued that DENR erred in setting the BACT limit for SAM

emissions by failing to consider various control options, including WESP; a low SO2 to

SO3 conversion SCR catalyst; lowering the temperature across the SCR catalyst using

more frequent soot blowing, a more efficient SO2 scrubber (such as the Chiyoda jet

bubbling reactor), regenerating the SCR catalyst rather than replacing it, and

combinations of control options.

186. The proposed PSD permit contains a SAM limit of 0.005 lb/mmBtu based

on the use of a fabric filter and WFGD system. [Core Ex. 197 at 131.

187. The evidence established that DENR's analysis was thorough and resulted

in a reasonable BACT limit. Mr. Rombough explained his approach in detail. [Tr. 207-

09 (Rombough, 811 9/08)]. Otter Tail's application and DENR's draft Statement of Basis

provide additional justification for the limit. [Core Ex. 144 at 46-48; Core Ex. 160 at 27-

281.

188. The evidence further proved the SAM emission limit is well within the

range in recently-issued permits, and is appropriate for Big Stone 11. [Tr. 712 (Gaige,

8/21/08)]. Mr. Rombough reviewed other permits for plants burning PRB coal, and

"agreed in my judgment that the proposed limit was the maximum reduction achievable."

[Tr. 208 (Rombough, 8/19/08); see also Table 10-12 of Core Ex. 160 at 281. Although

one permit limit (Hastings Utilities) appears to be significantly lower than Big Stone's, it

is based on a typographical error in EPA's database. [Tr. 713 (Gaige, 8/21/08); Tr. 402-

03 (Rombough, 8/20/08)].

189. Other control options do not represent BACT for Big Stone 11. The

evidence established that all necessary and appropriate factors and relevant control

options have been properly considered in establishing the emissions limit. [See, e.g., Tr.

12 56 (Rombough, 9/25/08)].

190. WESP may be able to reduce emissions, but it is not cost-effective for Big

Stone 11. [Tr. 207-08 (Rombough, 8/19/08); Tr. 706, 7 1 1- 12 (Gaige, 812 1/08)]. The cost

estimate was explained in detail, and the supporting documentation was offered into

evidence. [Tr. 707- 1 1 (Gaige, 812 1/08); Exs. 302-3061. Petitioners offered no alternative

estimate of the cost. In addition, Petitioners' expert was unable to identify any power

plant in the country burning low sulfur coal that uses WESP to control SAM. [Tr. 966-67

(Sahu, 8/26/08)].

191. Likewise, the evidence established that "sorbent injection" (i.e., injection

of an alkaline substance such as lime) is not BACT for Big Stone 11. Sorbent injection

would be superfluous. Big Stone will bum PRB coal, whose ash is already high in

calcium. [Tr. 7 12 (Gaige, 812 1/08)]. Adding another alkaline material would have little,

if any, effect on SAM. [Id.; Tr. 1255 (Rombough, 9/25/08)]. Accordingly, no coal-fired

power plant in the nation uses sorbent injection to control SAM when burning PRB coal

[Tr. 712 (Gaige, 8/21/08)], and no permitting agency has found it to be BACT under

those circumstances. [Tr. 967 (Sahu, 8/26/08)]. For these reasons, Otter Tail had ruled

out sorbent injection in its application, and DENR agreed. [Core Ex. 144 at 47; Tr. 207,

1255 (Rombough, 811 9/08 & 9/25/08)].

192. The Board finds that DENR's and Otter Tail's evidence satisfied the

burden of proof on Issue 11 and that the SAM BACT limit is appropriate.

F. Fluoride BACT Analysis (Issue 12)

193. Petitioners argued that DENR erred in setting the BACT limit for fluoride

emissions by failing to consider sorbent injection, a more efficient SO2 scrubber, and

more efficient particulate matter control.

194. The permit contains a limit of 0.0006 Ibs/mrnBtu on total fluoride

emissions (includes HF and other fluoride compounds). [Core Ex. 197 at 131.

195. Mr. Rombough explained his review of Otter Tail's application and the

potential control technologies for fluorides. [Tr. 209- 10 (Rombough, 811 9/08)]. He

agreed that, for Big Stone 11, a combination of WFGD and a baghouse was the best

control for fluorides. [Id. at 209; see also Core Ex. 144 at 48-49]. To confirm this

conclusion, he reviewed permits for other plants burning subbituminous coal. [Tr. 209

(Rombough, 811 9/08)]. Mr. Rombough concluded that 0.0006 lbs/mmBtu is "the

maximum reduction achievable and I proposed or recommended that for the draft

permit." [Id. at 2 10.1 The Board agrees.

196. The evidence established that other controls for fluoride were not BACT

for Big Stone 11. As with SAM, sorbent injection provides little additional control

because Big Stone will bum calcium-rich PRB coal. [Tr. 714 (Gaige, 8/21/08)].

Petitioners offered no testimony at the hearing about other potential controls. The other

suggested options such as a "more efficient" wet FGD ignore the fact that the control

technology has not yet been designed or purchased. [Tr. 600-01, 603 (Graumann,

8/20/08)].

197. Moreover, the evidence contradicted Petitioners7 assertion that the

proposed permit limit for fluorides is unreasonably high. The permit is well within the

range of recently-issued permits. [Tr. 209-10 (Rombough, 8/19/08); Ex. 160 at 29; Tr.

714 (Gaige, 8/21/08)]. Some agencies have imposed slightly lower limits and others

have imposed higher limits. The evidence explained why the lower limits are not

comparable. [Tr. 7 14-1 8 (Gaige, 812 1 /08)]. Many apply only to the HF fraction of total

fluorides, while others are for units burning different coal. [Id.] None of the units with

lower limits has started operating, so it is unproven whether they will be able to meet

those limits. In short, the fluoride limit is BACT for Big Stone 11.

198. The Board finds that DENRYs and Otter Tail's evidence satisfied the

burden of proof on Issue 12 and that the fluoride BACT limit is appropriate.

G. BACT During Periods of Startup and Shutdown (Issue 13)

199. Petitioners assert that the proposed PSD permit is legally invalid because

it does not require continuous compliance with BACT during periods of startup,

shutdown, and malfunction. In addition to Petitioners' claim, Otter Tail has asked that

the Board clarify the meaning of Conditions 4.1-4.5.

200. Contrary to Petitioners' assertions, BACT expressly applies to Big Stone

I1 at all times, including startup, shutdown and malfunction. [Tr. 210 (Rombough,

8/19/08) ("BACT requirements do apply during startup, shutdown, and malfunction")].

The January 2008 draft PSD Permit had stated that BACT applied except during startup,

shutdown, and malfunction. But, after receiving comments on this exception, DENR

deleted it and added references to Section 4.8, which establishes a work practice designed

to minimize emissions during startup, shutdown, or malfunction. [See, e.g., Core Ex. 197

at 10-1 1 ("Compliance with the PMlo BACT emission limits in Table 4.1 ... during

periods of startup, shutdown, and malfunction shall be based on permit condition 4.8.")].

The Board finds that Section 4.8 provides a reasonable process for developing the most

effective plan for minimizing emissions after Big Stone I1 has selected equipment and

vendors. [See Tr. 603 (Graumann, 8/20/08)].

201. DENR's proposed BACT requirements for Big Stone I1 are consistent

with the definition of BACT. BACT is ordinarily a numeric emission limit, but it may be

a work practice if there are "technological or economic limitations on the application of

measurement methodology to a particular emissions unit that would make the imposition

of an emissions standard infeasible." 40 C.F.R. 5 52.2 1 (b)(12) (definition of BACT

incorporated by reference at ARSD 74:36:09:02). Thus, when a measurement

methodology, such as the performance tests required by the PSD permit, is

technologically infeasible, a permitting authority may substitute a work practice as

BACT. [Tr. 199 (Rombough, 81 1 9/08)].

202. Compliance with numeric limits for PMlo, SAM, VOC and fluorides is

determined by periodic performance testing (i.e., stack testing) using EPA approved test

methods. DENR correctly determined that it is technologically infeasible to measure

PMlo, SAM, VOC and fluoride emissions during startup, shutdown and malfunction

using EPA-approved performance test methods. [Core Ex. 198 at 511. As Mr. Gaige

testified, stack testing cannot be performed during startup and shutdown periods because

the conditions are too transient, so stack testing cannot demonstrate compliance with a

numeric limit. [Tr. 72 1 (Gaige, 812 1 /08)].

203. The numeric BACT limit for CO emissions from the Big Stone I1 boiler

apply at all times, including startup, shutdown and malfunction. Compliance with the

numeric BACT limits for CO are determined by a CEMS, which is capable of monitoring

emissions during such periods. [Core Ex. 197 at 1 1 - 131.

204. In weighing and balancing all the evidence presented, the Board finds that

Otter Tail and DENR have presented credible and persuasive evidence on Issue 13, and

the burden of proof has been satisfied.

205. While it is clear that BACT applies at all times, Otter Tail has asked for

clarification from this Board as to whether the new language - "Compliance with the

PMlO BACT emission limits in Table 4. ... during periods of startup, shutdown, and

malfunction shall be based on permit condition 4.8" - requires compliance with the

numeric BACT limits in the Tables during startup and shutdown (to be demonstrated by

compliance with the work practices in Section 4.8) or requires compliance only with the

work practices themselves. Otter Tail believes the language literally requires Big Stone

I1 to meet the numeric limits in the Tables, whereas DENR has stated that only

compliance with the work practices are required. Otter Tail seeks clarification from the

Board to avoid any future misunderstandings when the plant begins to operate. Otter Tail

has no objection to the numeric limits applying during startup and shutdown, provided

that Section 4.8 is the means of demonstrating compliance with those limits.

206. The numeric BACT limits for PMlo, VOC, SAM, and fluorides emissions

from the Big Stone I1 boiler apply at all times including periods of startup, shutdown and

malfunction. Because stack testing is not feasible during startup, shutdown and

malfunction, compliance with the numeric limits during such periods shall be

demonstrated by compliance with the work practice provision in Condition 4.8.

H. Modeling For Periods of Startup and Shutdown (Issue 14)

207. Petitioners argue that Otter Tail's air dispersion modeling is legally invalid

because startup and shutdown emissions from the Big Stone I1 boiler were not included.

After reviewing the evidence, the Board finds Otter Tail and DENR's evidence more

persuasive.

208. As discussed above, the numeric PMlo and CO BACT limits in the permit

apply at all times including during periods of startup and shutdown. The numeric BACT

emissions rates were used in the modeling.

209. Otter Tail used the maximum CO and PMlo emission rates for the Big

Stone I1 boiler in the ambient air modeling. Therefore, the evidence has established that

the CO and the PMlo NAAQS and PSD increment modeling are not flawed.

I. PMlo NAAQS and Increments (Issue 15)

210. Petitioners alleged that the NAAQS and PSD increment modeling for

PMlo was technically and legally invalid for three reasons: (1) the Huron meteorological

data did not reflect worst-case meteorological conditions at Big Stone; (2) the emissions

estimates for the haul roads were based on unjustified assumptions of the silt loading and

control efficiency leading to an underestimation of emissions; and (3) all increment

consuming sources were not included in the increment modeling.

21 1. Otter Tail's July 2007 modeling demonstrates that PMlo emissions from

Big Stone I1 will not cause or contribute to a violation of the NAAQS or PSD increments.

DENR's review of the modeling submitted by Otter Tail in support of its application was

sufficient to conclude that there had been an adequate demonstration.

212. As previously found, the Huron airport surface meteorological data used

in the modeling is representative of meteorology at the Big Stone site. DENR carefully

considered the appropriateness of the data to be used in the Big Stone modeling and

reasonably determined that Huron was representative.

2 13. Petitioner's expert modeling witness, Patrick Hanrahan, expressed various

criticisms of Applicant's air dispersion modeling. The Board finds Mr. Hanrahan's

criticisms are not credible or reliable, because, among other reasons, the criticisms are

based on erroneous interpretations and assumptions as to the modeling performed by

Otter Tail.

214. Mr. Hanrahan has never been to the Big Stone I1 project site and has never

performed haul road calculations for a coal-fired power plant. [Tr. 1353-57 (Hanrahan,

9/26/08)]. Mr. Hanrahan's opinions amounted to little more than speculation.

215. One of Petitioner's chief criticisms of the modeling performed by Otter

Tail involves the methodology and input data for emissions of dust from haul roads. In

comparing and weighing the modeling offered by DENR and Otter Tail compared to the

analysis offered by Petitioners, the Board finds the assumptions as to emission reductions

from fugitive dust controls and the silt loading factor for haul road emission calculations

of DENR and Otter Tail more reliable, reasonable, and persuasive. Otter Tail will be

required to implement fugitive dust controls to minimize emissions from haul roads. An

assumption of a 50% reduction based on those controls was reasonable in estimating

emissions. [Tr. 106 1-63 (Andracsek, 9/24/08); Ex. 3 86 at 1301. Use of a silt loading of

0.6 g/m2 in calculating emissions from paved haul roads was reasonable for a coal-fired

power plant. The assumptions used in the haul road calculations are consistent with those

accepted by EPA and other state agencies in permitting power plants. See, e.g., Ex. 390

at 201. In addition, Otter Tail presented persuasive evidence that the current models

overstate actual impacts of haul road emissions [Tr. 1151-54 (Gaige, 9/25/08); Ex. 3891,

and Petitioners offered no evidence to the contrary. Otter Tail also offered evidence that

some states do not even require emissions from haul roads to be included in power plant

air modeling. [See, e.g., Exs. 387-388; Tr. 1154-58 (Gaige, 9/25/08)].

216. Haul roads at the Big Stone site are currently unpaved. All haul roads will

be paved as part of the construction of Big Stone 11, potentially resulting in a decrease in

haul road emissions as compared to current emissions from just Big Stone I activities.

[Tr. 1 183 (Gaige, 9/25/08)]. This change from unpaved to paved was not considered in

estimating emissions for the modeling.

217. DENR determines the PSD PMlo increment minor source baseline date on

a county-by-county basis. The Big Stone I1 PSD application set the minor source

baseline date for Grant County. Thus, Big Stone I1 was the only source that consumes

the PMlo increment. The July 2007 modeling confirms that emissions from Big Stone I1

will not result in a violation of the increment.

21 8. Petitioners disagree with DENR and argue that the PMlo increment minor

source baseline should be determined on a statewide basis, excluding the Rapid City area.

To address Petitioners' argument, Otter Tail performed additional increment modeling in

July 2008 assuming that the minor source baseline date was set in 1991 by a source

located in the Sioux Falls area. [Exs. 3 1 1-3 141. The purpose of this supplemental

modeling was to show that, even if Petitioners' interpretations of the PSD increment

regulations are adopted, Big Stone I1 still will not cause or contribute to any violation of

the PSD increment regulations. Otter Tail included in the modeling emissions from other

sources that would consume increment if the baseline date was set in 1991. Otter Tail's

July 2008 increment modeling demonstrates that emissions from Big Stone I1 will not

result in a violation of the increment even if the baseline date was set in 1991. The Board

accepts the supplemental modeling for the reasons herein as confirming that air quality

standards are protected regardless of when baseline was triggered.

2 19. After weighing and balancing all the highly technical evidence presented,

the Board finds that Otter Tail and DENR have satisfied the burden of proof on Issue 15

with credible and persuasive evidence. The Board further finds that the modeling

adequately demonstrates that PMlo emissions from Big Stone I1 will not cause or

contribute to a violation of the NAAQS or PSD increment.

J. SO2 and NOx NAAQS and Increments (Issue 16)

220. Petitioners argued that the NAAQS modeling for NOx and SO2 was

technically and legally invalid. Petitioners base their claim on two alleged flaws: (1)

unrepresentative meteorological data; and (2) the modeling did not reflect the allowable

SO2 or NOx emission rates from Big Stone I and Big Stone 11.

221. DENR maintains that SO2 and NO, modeling is not required for the

issuance of either the PSD permit or the Title V permit. The Board agrees with DENR.

222. As previously discussed, PSD requirements are not triggered for SO2 or

NO,. Thus, a demonstration of compliance with the SO2 or NOx NAAQS is not required

for issuance of the PSD permit. [Tr. 1232 (Rombough, 9/25/08)]. DENR performed SOz

and NO, modeling to respond to comments from EPA. [Core Ex. 1501. DENR used the

same meteorological data used by Otter Tail in its modeling. As previously found, the

Huron airport surface meteorological data and the Aberdeen airport upper air

meteorological data used in the modeling is representative of meteorology at the Big

Stone site.

223. The Title V regulations require a showing "that the operation of the new

source or permit modification will not prevent or interfere with the attainment or

maintenance of an applicable ambient air quality standard" before the Title V permit may

be issued. [ARSD 74:36:05:06]. The regulations do not specify that modeling is the only

method available for making the required showing.

224. In this case, modeling is not required to show that Big Stone I1 will not

prevent or interfere with attainment of the SO2 and NOx NAAQS. South Dakota is in

attainment for all pollutants, including SO2 and NOx. [Tr. 47 (Gustafson, 8/18/08)]. Big

Stone I1 construction and operation will not result in an increase in SO2 and NOx

emissions because of the plant-wide caps. Generally, emissions from Big Stone I and I1

will be routed through a common stack, which is the same height as the existing Big

Stone I stack. [Core Ex. 160 at 311. There will be differences in stack characteristics

such as temperature and velocity, but those differences are not sufficient to prevent or

interfere with attainment of the SOz and NOx NAAQS. Monitoring in South Dakota

indicates that current ambient concentrations are approximately 3% of the SO2 NAAQS

and approximately 9% of the NOx NAAQS. [Ex. 700 at 16- 181.

225. Nonetheless, to the extent the Title V regulations (ARSD 74:36:05:06)

require modeling to show that operation of a new or modified source will not prevent or

interfere with attainment of any NAAQS, DENR's modeling satisfies that requirement.

DENR's SO2 and NOx modeling show that operation of Big Stone I1 will not prevent or

interfere with attainment of the NAAQS. DENR's modeling confirms that the

differences in the stack parameters for Big Stone I and Big Stone I1 do not significantly

change the modeled ambient air impacts.

226. Based on the evidence and the technical expertise required, the Board

finds that SO2 and NO, NAAQS modeling is not required for the issuance of the permits.

While not required, the Board further finds that the SO2 and NOx modeling performed by

DENR confirms that operation of Big Stone I1 will not prevent or interfere with

attainment of the NAAQS. On Issue 16, the Board finds the evidence to favor issuance

of the permits by a preponderance of the evidence.

227. Petitioners have also raised collateral issues about prior DENR modeling

for SOz and NO,. DENR had initially performed SO2 and NO, modeling before the first

draft PSD permit was public noticed. The results were reported in the first PSD

Statement of Basis in 2006. Although Sierra Club and Clean Water Action submitted

extensive comments on the modeling, neither they nor any other member of the public

requested the underlying modeling files until this contested case proceeding. At that

time, it was discovered that the SO2 and NOx modeling files had been discarded when

former DENR employee Jason Knapp, who performed the modeling, had left the

employment of DENR. [Tr. 218, 461 (Rombough, 8/19/08 & 8/20/08)]. This occurred

before the second draft PSD permit was public noticed and before any contested case

proceeding was filed. The Board finds that the deletion is not material to its decision

whether to issue the permits in this case. Even assuming modeling is required, no party

suffered any prejudice here. DENR performed new modeling to confirm the results of

the prior modeling, and Petitioners were provided ample time to review and present

evidence and argument and to cross examine witnesses on the new modeling before this

Board's decision. In addition, the deletion of the initial modeling files was not

intentional, and occurred before any contested case proceeding was filed or threatened.

[Tr. 1 192-94 (Anderson, 9/25/08)].

228. In 2008, Mr. Anderson of DENR performed new SOz and NOx modeling

to verify the prior modeling results. [Tr. 21 8 (Rombough, 811 9/08); Tr. 1 186-9 1

(Anderson, 9/25/08)]. The 2008 modeling used appropriate methodologies and

meteorological data representative of the Big Stone site. To the extent that any modeling

was even required, the modeling performed by DENR in 2008 confirms that Big Stone's

SO2 and NOx emissions will not prevent or interfere with attainment of any applicable air

quality standards.

K. Case-by-Case MACT Requirements (Issue 18)

229. Petitioners contend that Section 112(g) of the Clean Air Act (i.e., MACT)

should apply to Big Stone I1 in spite of the HAP limits in the Title V permit that require

Big Stone I1 to remain below the statutory thresholds for triggering MACT. Petitioners

also attack the HAP limits by arguing that Big Stone I1 might not meet those limits and

by asserting that the limits are not enforceable. Finally, Petitioners suggest that the HAP

provisions in the Title V Permit were not subject to public comment.

1. The Permit Limits Ensure That Big Stone I1 is not a Major Source of HAPs.

230. The Board finds that the case-by-case MACT requirements do not apply to

Big Stone I1 because it is not a major source of HAPs.

23 1. Case-by-case MACT applies only to "major sources" of hazardous air

pollutants. CAA 5 112(g)(2)(B). As noted above, a major source of HAPs is defined as

one that emits 10 tons per year of any single HAP or 25 tons per year of any combination

of HAPs. CAA 5 112(a)(l). The limits in the Title V permit ensure that Big Stone I1 will

not exceed the statutory thresholds to be deemed a major source of HAPs. [Tr. 258-60,

272-74 (Rombough, 811 8/08 & 8/19/08)]. DENR has proposed limits (9.5 tons and 23.8

tons, respectively) that are approximately five percent below the MACT thresholds to

provide additional assurance that the thresholds will not be exceeded. [Core Ex. 219 at

3 1 ; Tr. 273-74 (Rombough, 8/19/08)]. The Title V permit also contains short-term HAP

emission limits to provide further assurance that Big Stone I1 will not be a major source

of HAPs.

232. Petitioners do not challenge this Board's legal authority to use permit

limits to keep facilities below regulatory thresholds. In PSD permitting, this is often

called a "synthetic minor." All parties agree that the approach is conceptually valid and

commonly used. See, e.g., Tr. 259-60, 369-70 (Rombough, 8/19/08 & 8/20/08); Tr. 859-

60 (Sahu, 8/26/08) ("[ilt's entirely within the prerogative of the source to say they will

limit [emissions] to a certain level and stay within or out of the certain program")].

Petitioners' expert witness has used this approach on behalf of his own clients. [Tr. 805

(Sahu, 8/26/08)]. The Board agrees with DENR and finds that the HAP limits here are an

effective means to require Big Stone I1 to stay below the MACT threshold.

2. The Evidence Proved That Big Stone I1 Can Meet the HAP Limits.

233. While Petitioners acknowledge that synthetic minor limits are viable in

concept, they argue that Big Stone I1 cannot meet the HAP limits in this case. The Board

disagrees.

234. Big Stone I1 is required by law to meet the HAP limits. There are severe

consequences if Big Stone I1 violates those limits. The Board is not required to speculate

today whether Big Stone I1 will comply with its obligations under the law. If Big Stone

I1 were to violate these limits, DENR and the Board (not to mention EPA and the public)

would have ample enforcement powers. [See, e.g., Tr. 124.1 -42 (Rombough, 9/25/08)].

In addition to enforcement, the permit provides that a case-by-case MACT is required if

Big Stone I1 emissions exceed any of the MACT thresholds. [Id. at 1243; Tr. 433

(Rombough, 8120108); Ex. 219 at 321. In short, speculation about Big Stone 11's future

compliance is not a reason to deny the permit today.

235. The evidence also refuted Petitioners' allegation that Big Stone I1 cannot

meet the limits. Otter Tail estimated HAP emissions using conservative assumptions,

such as operating at full capacity for every hour of the year. [Tr. 591-92 (Graumann,

8/20/08)]. Mr. Rombough himself verified that the estimates were reasonable, based on

his independent research. [Tr. 432-33, 1246-50 (Rombough, 8120108 & 9/25/08)]. In

light of these conservative assumptions, Otter Tail is confident that Big Stone I1 will meet

the HAP limits. [Tr. 591-92 (Graumann, 8120/08)]. If Otter Tail were not confident in its

emissions estimates, it would not have proposed and accepted those limits. [See id. at

590-91 (Mr. Graumann stands by his certification under oath that his calculations are

accurate to the best of his knowledge); Tr. 434 (Rombough, 8120108) (risk is on Big

Stone that it can meet its limits)].

236. Petitioners spent hours at the hearing challenging minute details of Otter

Tail's HAP emissions estimates in Exhibit 187 (e.g., arguing that Otter Tail should have

used maximum fluorine and chlorine content of coal instead of average content). Each of

their criticisms was refuted in turn by either Mr. Graumann, Mr. Gaige, or Mr.

Rombough. [See, e.g., Tr. 591-98 (Graumann, 8120108); Tr. 718-19 (Gaige, 8/21/08); Tr.

435, 1246-50 (Rombough, 8120108 & 9/25/08); Exs. 315-171. In addition, Big Stone I1

has not yet picked a vendor for its control equipment. It will have the ability to specify

equipment to meet the needs of the project, including meeting the HAP limits. [Tr. 55 1-

52 (Rolfes, 8/20/08)]. Even Petitioners' own expert conceded that technology is

currently available in the marketplace that will enable Big Stone to meet the limits. [Tr.

968-69 (Sahu, 8/26/08)].

237. At the 2009 contested case hearing, DENR offered additional evidence

regarding HAP emissions estimates demonstrating that Otter Tail should be able to meet

the HAP limits.

238. Weighing all the evidence, the Board finds Otter Tail's and DENR's HAP

emissions estimates to be reasonable, reliable, and persuasive.

3. The HAP Limits Are Enforceable.

239. Petitioners further argue that the HAP limits are not enforceable (i.e., the

permit does not provide adequate measures for demonstrating that Big Stone is in

compliance with the limits). Petitioners contend that more sampling, testing, and/or

monitoring is necessary. The Board does not agree. As the evidence proved, the Title V

permit contains ample terms and conditions to be enforceable as a practical matter.

240. The Title V permit provides for an initial performance test, quarterly

reporting of HAP emissions, weekly composite coal analysis of fluorine and chlorine

content, and calculations of emissions "based on the most recent stack test, mass balance,

emissions factors, or other approved method." [Core Ex. 2 19 at 16, 25, 3 1 and 32; Tr.

273 (Rombough, 8/19/08) (explaining conditions)]. These are standard conditions for

demonstrating compliance with HF and HC1 limits, and they are consistent with what

other agencies typically insert into their permits. [Tr. 1165 (Gaige, 9/25/08)]. DENR

considers compliance with the HAP limits "an important issue" and "something [it] will

be watching for." [Tr. 1243 (Rombough, 9/25/08)]. DENR also retains the express

authority to demand a stack test at any time. [Id. at 1244; Tr. 437 (Rombough, 8/20/08)].

It is clear, then, that the HAP limits are enforceable.

241. The synthetic minor provisions for the HAPS are not "blanket restrictions

on actual emissions" as that term is used in United States v. Louisiana Pacific Corp., 682

F. Supp. 1122 (D. Colo. 1987). To the extent that the reasoning of that case even applies

here, the proposed Title V permit contains sufficient terms and provisions to render the

caps enforceable as a practical matter. [See 58 Fed. Reg. 37778, 37789 (July 19, 1993)l.

242. While the Board believes that its 2008 findings and conclusions regarding

the enforceability of the HAP provisions were correct, this issue as raised during the 2008

contested case is now moot given EPA's objection. To respond to EPA's objection and

Petitioners' comments, DENR included additional testing and monitoring provisions

along with a more detailed explanation as to how compliance is continuously

demonstrated. The Board agrees with DENR's revisions to the Title V permit and finds

they address EPA's objection and Petitioners' 2009 comments.

4. The Public Was Provided Proper and Sufficient Notice.

243. Petitioners also argued that the HAP provisions in the draft Title V permit

were not subject to public comment. The Board found that a new public notice was not

required for several reasons. First, the HAP limits were added as a direct result of

comments they filed. Consequently, DENR was not legally required to conduct a second

round of public notice and comment on those limits. Second, the public notice provisions

of the MACT program cannot require public notice in this case because Big Stone I1 has

not triggered MACT review. Finally, the public had the opportunity to comment on the

draft Title V permit in contested case proceedings.

244. The evidence established that the HAP limits were a response to public

comments. Petitioner Sierra Club had commented on an earlier draft permit, arguing that

a case-by-case MACT analysis was required for Big Stone I1 pursuant to Section 112 of

the CAA. [Core Ex. 195 at 481. In response to those and other comments, DENR revised

the draft Title V permit to include a condition limiting emission of HAPS from Big Stone

I1 below the threshold that triggers MACT. [Core Ex. 198 at 71-75 (explaining HAP

provisions in DENR's formal responses to comments)]. In making the revisions, DENR

expressly considered and rejected the need to reopen the draft permits for further

comment: "The proposed additional limits will be equivalent to or more stringent than the

requirements already existing in the draft permits. Therefore, these changes do not need

to be public noticed again." [Id. at 75.1

245. The Board agreed with DENR and found that a new public notice was not

required. It is a well settled principle of administrative law that changes may be made to

a permit in response to comments without subjecting those changes to additional public

notice and comment. See Sierra Club v. Costle, 657 F.2d 298, 352 (D.C. Cir. 1981). As

the EPA Administrator concluded in response to a similar claim, neither the CAA nor 40

C.F.R. Part 70 "require permitting authorities to conduct a second round of comments."

In the Matter of NYCDEP North River Water Pollution Control Plant, Petition No.: 11-

2002-1 1, 2004 EPA CAA Title V LEXIS 11 at *9-10 (Sept. 24, 2004). The CAA

requires that there be "[aldequate, streamlined, and reasonable procedures for . . . public

notice, including offering an opportunity for public comment and a hearing . ..." CAA

502(b)(6). Multiple rounds of public comment on provisions revised to address such

comments would not qualify as streamlined or reasonable. South Dakota's regulations

mirror 40 C.F.R. Part 70, and, likewise, did not require DENR to conduct another round

of public notice and comment.

246. Notice and comment for the new provisions also is not required by MACT

(Section 112 of the CAA) or its implementing regulations. As noted above, case-by-case

MACT applies only to major sources of HAPS, and Big Stone I1 is not a major source.

Thus, Section 112 requirements, including the notice and comment requirements, do not

apply to Big Stone 11.

247. Finally, even assuming for the sake of argument that there is a requirement

for a second round of public notice and comment, interested parties have had the

opportunity to comment on the proposed revisions in the contested case proceedings.

Pursuant to ARSD 74:36:05 : 17, DENR "provide[d] to the interested parties a 30-day

notice of any hearing to contest a draft permit." Thus, anyone wishing to comment on the

HAP provisions could have done so in this contested case before the Board will make its

determination. Petitioners themselves elected to "comment" on the HAP provisions with

their extensive challenge in this case. In addition, Petitioners offered no evidence at the

hearing that anyone wishing to comment on the HAP provisions was somehow deprived

of the opportunity to do so.

248. The Board found that the Title V public notice in this matter was

reasonable and sufficient and in compliance with applicable requirements.

249. The Board further found that Otter Tail and DENR satisfied the burden of

proof with credible and persuasive evidence on Issue 18.

250. While the Board believes that its 2008 findings and conclusions were

correct, this issue is moot as a result of EPA's objection. To address EPA's objection,

DENR specifically requested comments on the HAP provisions in its February 2009

public notice.

L. Contents of Title V Permit (Issue 19)

25 1. Petitioners asserted that DENR's proposed final Title V Permit is legally

invalid because it authorizes operation of the Big Stone I1 modification without including

all applicable requirements for Big Stone 11, specifically the requirements contained in

the proposed PSD permit. Petitioners presented no evidence on this issue during the

hearing. The Board accepted DENR's and Otter Tails arguments and found as follows

based on the evidence:

252. The Title V permit contains all the applicable requirements necessary at

this time. PSD permit conditions do not become applicable requirements to be included

in the Title V permit until after the PSD permit has been issued (ARSD 74:36:01:05(2);

Tr. 473 (Rombough, 8/20/08)), the source has been constructed, and operation of the

source begins. ARSD 74:36:05:03.01. Otter Tail would have 12 months after operation

of Big Stone I1 commences to submit a Title V application to incorporate the Big Stone I1

PSD permit conditions into the Title V permit. [Id.]

253. The original inclusion of plantwide caps in the previously-proposed Title

V permit for SO2 and NO,, which are applicable to Big Stone 11, does not change the

regulatory requirements with respect to the incorporation of the Big Stone I1 PSD permit

requirements into the Title V.

254. While the Board believes that its 2008 findings and conclusions were

correct, this claim is now moot as a result of EPA's objection. DEhTR has included the

PSD provisions for Big Stone I1 in the revised Title V permit, and the Board adopts this

revision as satisfying EPA's objection.

VIII. Findings Relating; to Questions and Claims Raised in April 2009 Contested Case Hearing

255. Petitioners commented on the revised Title V permit during the public

comment period. DENR made several revisions to the Title V permit in response to those

comments. [See generally Core Ex. 853.1

256. Although they offered no witnesses, Petitioners raised a number of

questions and claims during the April 2009 contested case hearing concerning the revised

Title V permit. Petitioners' questions and claims were addressed in DENR's responses

to comments and by Mr. Rombough's testimony at the contested case hearing, and the

Board accepts and adopts the reasoning of the responses to comments and Mr.

Rombough's testimony. [See Core Ex. 853.1 The Board finds that Petitioners' claims

have no merit and that Otter Tail met its burden of proof. Selected questions and claims

are discussed in more detail below.

257. Petitioners allege that the Title V operating permit is not the appropriate

place to create the SO2 and NO, emission limits. Further, Petitioners argue that Title V

permits are meant only to consolidate pre-existing requirements into a single,

comprehensive document, and then assure compliance with those requirements. This

claim has no merit here. EPA commented in 2006 that the Title V permit is an

appropriate place for such conditions. Moreover, South Dakota regulations expressly

provide the Title V as the appropriate place for such conditions. [See Core Ex. 853 at 4-

51.

258. Petitioners also allege that the SO2 and NOx limits on Big Stone I must be

in place well before Big Stone I1 is constructed. DENR discussed this issue with EPA,

which agreed with the approach in the revised Title V permit during a verbal

conversation, but refused to indicate agreement with this approach in writing. Permit

conditions 9.2 and 9.5 provide that the 12-month rolling limits begin when the Big Stone

I1 project commences operation. In addition, permit condition 9.8 was revised to require

the emissions from Big Stone I be routed to the wet scrubber prior to commencing

operation of Big Stone 11. These conditions make the emission reductions from the

existing Big Stone I facility occur prior to the operation of the Big Stone I1 facility in

accordance with 40 CFR tj 52.21(b)(3). [See Core Ex. 853 at 5-61.

259. Petitioners further allege that the netting analysis is based on an improper

timeline for baseline actual emissions for the Big Stone I1 project. They indicated the

baseline date should be based on the time period starting in May 2004 through September

2008. As explained by DENR, the appropriate representative baseline time period is

January 2003 through December 2004 due to the timelines of the permitting process, the

projects and uncontrollable plant circumstances that affected normal operations, and the

existing requirements under the revised Title V permit. [See Core Ex. 853 at 6-81. The

record reflects persuasive reasons why periods subsequent to December 2004 are not

representative. [Id.] The Board agrees with DENR's analysis, which is consistent with

the applicable regulations.

260. Petitioners allege that the netting analysis is flawed because there was an

increase of emissions associated with Poet Biorefining's ethanol expansion project. Big

Stone I provides steam to the ethanol plant and, Petitioners allege, the expansion would

have required additional steam production which would generate additional emissions.

Petitioners offered no evidence to support this allegation. In fact, the record reflects that

Poet's expansion did not require any additional steam from Big Stone I above the amount

already permitted. Therefore, Big Stone I did not have to make a physical change or

change its method of operation as defined in 40 CFR 5 52.2 1 (b)(2)(iii)(t) to accommodate

Poet's increase in ethanol production. Thus, the Board finds that the netting analysis is

not flawed. [See Core Ex. 853 at 81.

261. Petitioners further allege that the emission estimates for the HAPs,

excluding HF, HCl, and mercury, are underestimated and that Big Stone I1 should be

deemed a major source of HAPs subject to CAA 112(g). DENR's responses to

comments and the evidence at the contested case hearing demonstrate that Petitioners'

attack on the HAP estimates is not well-founded. Instead, the record as a whole reflects

that Otter Tail's and DENR's estimates of HAP emissions persuasively establish that Big

Stone I1 will not be a major source of HAPs. [See Core Ex. 853 at 10- 121.

262. Petitioners raise a number of arguments about the adequacy of the

compliance demonstrations for HAPs and periodic monitoring for the PSD emission

limits. DENR's responses to comments and the evidence at the contested case hearing

demonstrate conclusively that Petitioners' attack is not well-founded. [See Core Ex. 853

at 14- 181. Otter Tail has met its burden of proof.

263. Petitioners have also argued that the Board should not issue the revised

Title V permit at this time and should revoke or stay the PSD permit as a result of the

Order of the Minnesota Public Utilities Commission ("Minnesota PUC Order") dated

March 17, 2009. For the reasons stated in DENR's and Otter Tail's filings on this issue,

the Board finds that no changes or delays are necessary or appropriate for either the PSD

permit issued on November 20,2008, or the revised Title V permit.

AMENDED CONCLUSIONS OF LAW

Based on the foregoing amended findings of fact, the Board enters the following

amended conclusions of law:

I. General

1. The Board has jurisdiction over the parties to this administrative

proceeding and over the subject matter.

2. To the extent any of the following conclusions of law may be determined

to be findings of fact or mixed findings of fact and conclusions of law, the same are

incorporated by this reference as a finding of fact as if set forth in detail.

3. Administrative rules have the force of law and are presumed valid.

Feltrop v. Department of Social Svcs,. 559 N.W.2d 883, 884 (S.D. 1997). An

administrative agency is bound by its own rules. Mulder v. Department of Social Svcs.,

675 N.W.2d 212,216 (S.D. 2004).

4. The burden of proof as to an issue on which a party bears the burden is the

preponderance of the evidence.

5. The Board concludes that it needs no other information to assess the

proposed permits or to determine if any party has met its burden of proof as to any issue

on which the party bears the burden of proof.

6. The Board concludes that the hearings in this matter have been properly

conducted pursuant to SDCL Ch. 1-26.

7. The Board concludes that the applications, draft permits and all required

filings are in conformity with South Dakota law. All procedural requirements required

under South Dakota law have been met. All data and exhibits have been filed.

8. The Board concludes that the applications, draft permits and notices are

legally and procedurally appropriate and complete. All formatting and timing

requirements have been complied with. All public hearing requirements have been met.

9. A full and fair opportunity to litigate the issues involved in this matter, as

required by law including SDCL Ch. 1-26, was given to all parties and those in privity

with the parties prior to the Board's decision.

10. The Board concludes that the draft permits are supported by the testimony

of the witnesses and documentary evidence, and that DENR and Otter Tail have met their

burden of proof by a preponderance of the evidence to establish that the Board should

issue the permits.

11. Through a combination of periodic testing, monitoring and recordkeeping,

the permits will require Big Stone to demonstrate compliance with the permit conditions

and emissions limitations.

12. The Board concludes that no changes are necessary to the PSD permit

issued on November 20,2008 or the Revised Title V permit as a result of the Minnesota

PUC Order dated March 17, 2009.

11. The Board Should Issue the PSD Permit

13. The Board concludes that the proposed PSD permit, with the changes

proposed by Otter Tail and DENR, complies with all applicable laws and regulations,

including 42 U.S.C. $$ 7470-7479; SDCL Chapter 34A-1; and ARSD 74:36:09

incorporating by reference 40 C.F.R. $ 52.21. Issuance of the PSD permit is consistent

with the policies expressed in SDCL 34A-1-1 "to achieve and maintain reasonable levels

of air quality which will protect human health and safety, prevent injury to plant and

animal life and property, foster the comfort and convenience of its inhabitants, promote

the economic and social development of the state and, to the greatest degree practicable,

facilitate the enjoyment of the natural attractions of the state." The Board will issue the

PSD permit as proposed by DENR with the following changes and clarifications:

a. Lowering certain limits in Table 4.1 of Section 4.1, as

reflected in Exhibit 324; and

b. Adding Section l. lA, as reflected in Exhibit 705.

14. The Board concludes that no changes are necessary to the PSD permit

issued on November 20,2008 as a result of EPA's objection to the 2008 proposed Title V

permit.

111. The Board Should Issue the Revised Proposed Title V Permit for EPA's Review

15. The Board concludes that the revised Title V permit, with the change

proposed by Otter Tail, complies with all applicable laws and regulations, including CAA

Title V (42 U.S.C. $ 5 7661-77661f); Acid Rain (42 U.S.C. $ 5 7651-76510); SDCL

Chapter 34A-1; and ARSD 74:36:05. Issuance of the revised Title V permit is consistent

with the policies expressed in SDCL 34A-1-1 "to achieve and maintain reasonable levels

of air quality which will protect human health and safety, prevent injury to plant and

animal life and property, foster the comfort and convenience of its inhabitants, promote

the economic and social development of the state and, to the greatest degree practicable,

facilitate the enjoyment of the natural attractions of the state." The Board will direct the

issuance of the revised Title V permit for EPA's review. The Board hereby adopts the

draft Statement of Basis for the Title V permit, as supplemented and modified by

DENR's Revised Statement of Basis [Core Ex. 8291, and Responses to Comments dated

April 15,2008, and March 18,2009 [Core Ex. 8-53].

16. The Board concludes that the revised proposed Title V permit responds to

EPA's objections.

IV. Petitioners' Claims Are Rejected

17. After carefully considering the record, the evidence presented at the

contested case hearing, written and oral arguments of counsel, and applicable laws and

requirements, the Board concludes that a preponderance of the evidence favors issuing

the permits and further concludes that all of Petitioners' claims lack merit and should be

rejected.

Dated this 21 st day of April, 2009.

SOUTH DAKOTA BOARD OF MINERALS AND ENVIRONMENT

+---

J

BY Lee M. McCahren

L

Hearing Chairman of the Board of Minerals and Environment