state farm center: renovation and addition project

46
State Farm Center Renovation and Addition Project

Upload: arakausk

Post on 05-Aug-2015

210 views

Category:

Education


4 download

TRANSCRIPT

Page 1: State Farm Center: Renovation and Addition Project

State Farm Center Renovation and Addition Project

Page 2: State Farm Center: Renovation and Addition Project

Project Leadership Owner

University of Illinois F&S DIA

Construction Manager

Design Team AECOM – Architectural Thorton Tomasetti – Structural Henderson Engineers – Mechanical, Electrical ESD – Plumbing

Page 3: State Farm Center: Renovation and Addition Project

Project Specifics 160 Million Renovations and Addition

New Mechanical Spaces and Systems Reconfiguration of the arena New Luxury Seating New Ramps and Walks

6 phases 1,3,5 – Basketball Phases 2,4,6 – “Construction” Phases

Peak manpower for Phase 2 – 160 Peak manpower for Phase 4 – 250

Page 4: State Farm Center: Renovation and Addition Project

Google Earth

Page 5: State Farm Center: Renovation and Addition Project

State Farm Center12/02/2013 – 02/28/2014

Phase 1 – Site Work

Key

Construction

No Service

Ongoing

In Use

Other

Page 6: State Farm Center: Renovation and Addition Project

State Farm Center12/02/2013 – 02/28/2014

PRV RoomDemo HV-10T/C Offices

Phase 1 – Mechanical Level

Key

Construction

No Service

Ongoing

In Use

Other

Page 7: State Farm Center: Renovation and Addition Project

State Farm CenterState Farm CenterPhase 1 Construction LogisticsDecember 2013 To February 2014

St. Mary’s Road

Four

th S

tree

tFo

urth

Str

eet

St. Mary’s Road

Kirby Avenue Kirby Avenue

Orange LotNo Construction

Parking

Brown LotNo Construction

Parking

Blue LotNo Construction

Parking

N

Relocate Fence As

Work Progresses

Relocate Fence As

Work Progresses

Construction

Deliveries

B

B

B

B

B B

C C

CC

C C

C

C

C

C

C

C

C

C

C

C

C

C

B

B

B

B

B B

P

P

-6’ High chain link fence (with posts in ground)

-6’ High chain link fence, moveable fence supported by bases and sandbags and/or pins

-Primary construction truck ingress and egress

-”B” level entrance into building via stairs (must be maintained for ingress and egress)

-”C” level entrance into building via existing ramps

-Maintain pedestrian access/egress into SFC at “B” level

-Maintain pedestrian access/egress via ramps to “C” level entrance

-Public drop off-30’ Wide Sliding Gate-25’ Wide Swing Gate-25’ Wide Sliding Gate-Masonry Silo-800 AMP 120/208V Service for Trailers

G1

G7

G5

G4

G2

G6

G3

C

B

B

C

P

Relocate Fence As

Work Progresses

Relocate Fence As

Work Progresses

G5G5G5

Trailers - 15 Spaces

300’ x 60’

MM

TETE

Dumpster

Dumpster

Dumpster

Dumpster

Dumpster

Tool Trailers – 34 Spaces340’ x 60’

Storage/StagingArea

Notes: Typical Work of Phase 11) U.G. Utility Contractor shall provide, install, maintain, and reposition moveable chain link fence around all excavations, equipment, and disturbed areas during installations.

2) Any existing roads, sidewalks or pavements shall be restored via 3000 PSI concrete, 4 inches thick after underground installation to allow pedestrian or vehicle traffic.

3) U.G. Utility Contractor to provide and maintain steel road plates over areas where pavement can not be replaced to allow access to SFC.

4) U.G. Utility Contractor to schedule and coordinate work to always provide ingress and egress to the SFC “B” Level entrances and ramps to the “C” Level entrances.

B

BWest Construction Staging Area Construction Road

G8

G9

BC

B

C

Plywood Canopy

Protection

*Trades Men Parking For Phase 1 Only

G11

G11

Service Level Dock Below

B

C

Construction Field Office and Staging

RED PARKING LOT

Temporary Fence Panels

Page 8: State Farm Center: Renovation and Addition Project

Site Utilities Conflicts

Page 9: State Farm Center: Renovation and Addition Project

Site Utilities Conflicts

Page 10: State Farm Center: Renovation and Addition Project

Equipment Selection

Page 11: State Farm Center: Renovation and Addition Project

Equipment Selection

Page 12: State Farm Center: Renovation and Addition Project

State Farm CenterState Farm Center

St. Mary’s Road

Four

th S

tree

t

Kirby Avenue Kirby Avenue

Orange LotNo Construction

Parking

Brown LotConstruction Parking

(Phase 2 Only)

Blue LotNo Construction

Parking-6’ High chain link fence (with posts in ground)

-6’ High chain link fence, moveable fence supported by bases and sandbags and/or pins

-Primary construction truck ingress and egress-Public drop off

-Earth Retention

-30’ Wide Sliding Gate

-25’ Wide Swing Gate

-25’ Wide Sliding Gate

-Masonry Silo

-800 AMP 120/208V Service for Trailers

-30’ Wide Swing Gate

P

Crane Pad

Plywood Canopy

Protection

Crane Pad50’ x 100’

STAGING AREA FOR WEST

STAGING AREA FOR NORTH

STAGING AREA FOR SOUTH

STAGING AREA FOR EAST

Four

th S

tree

t

St. Mary’s Road

Construction

Deliveries

G1

G7

G2

G3

Trailers - 15 Spaces

300’ x 60’

MTE Dumpster

Dumpster

Dumpster

Dumpster

Dumpster

Tool Trailers – 34 Spaces340’ x 60’

Storage/StagingArea

G5

G5

G5

MTE

G5

30’ Wide Road< Ramp <

There will be no ramp to service

level

Contractor must provide their own cranes for hoisting

Construction hoisting access to service level after concrete floor at Level B is poured

West Construction Staging AreaNew Road

Phase 2 Construction LogisticsMarch 2014 To November 2014

Crane Pads to be constructed of CA-A plus 6” of CA-6 with

top elevation @ 749’

G13

G5

G6

G12

G10

G11

G10 G9

G4

G8

G9

*No Construction Parking

East Staging Area50’ x 200’

Crane Pad50’ x 100’

Crane Pad

New U.G. electrical ductbank, water main, and steam

installations in this area.

G11

G11

G8

G9

Access to loading dock at event level

Service Level Dock Below

N

Page 13: State Farm Center: Renovation and Addition Project

03/01/2014 – 10/31/2014

BTN Work RoomLoading Dock WalkShopsSecurity

Phase 2 – Service Level

Key

Construction

No Service

Ongoing

In Use

Other

East MechanicalWest MechanicalMicro Piles from Above

Page 14: State Farm Center: Renovation and Addition Project

Earth Retention - Arena

Page 15: State Farm Center: Renovation and Addition Project

03/01/2014 – 10/31/2014

Operations OfficesSubstation A & BTunnel Abatement

Phase 2 – Mechanical Level

Key

Construction

No Service

Ongoing

In Use

Abatement

Chilled Water Main to AHU 18Demo Chiller

Generator Base

PRV RoomEast Mechanical TunnelWest Mechanical TunnelMicro Piles from Above

Page 16: State Farm Center: Renovation and Addition Project

Earth Retention – Additions

Page 17: State Farm Center: Renovation and Addition Project

Earth Retention/ Excavation - Additions

Page 18: State Farm Center: Renovation and Addition Project

Earth Retention – Soil Nail Wall

Page 19: State Farm Center: Renovation and Addition Project

Earth Retention – Soil Nail Wall

Page 20: State Farm Center: Renovation and Addition Project

Earth Retention – Soil Nail Wall

Page 21: State Farm Center: Renovation and Addition Project

Earth Retention – Soil Nail Wall

Page 22: State Farm Center: Renovation and Addition Project

Earth Retention – Soil Nail Wall

Page 23: State Farm Center: Renovation and Addition Project

Remove InsulrockEast Addition

03/01/2014 – 10/31/2014

Phase 2 – B Level Concourse

Key

Construction

No Service

Ongoing

In Use

Other

Abate Office AreasDemo Office AreasDemo Toilet LidsDomestic Water Loop

West AdditionFit Out (No Service)

South Ramps and PlazaDemo Stair Over Substation A & B

Page 24: State Farm Center: Renovation and Addition Project

Excavation – Link Tunnels

Page 25: State Farm Center: Renovation and Addition Project

Excavation – Link Tunnels

Page 26: State Farm Center: Renovation and Addition Project

Crane Usage

Page 27: State Farm Center: Renovation and Addition Project

Single Sided Forms

Page 28: State Farm Center: Renovation and Addition Project

03/01/2014 – 10/31/2014

Bowl Retention PilesNew Tunnel PilesRaker Duct Lining

Phase 2 – Event Bowl

Key

Construction

No Service

Ongoing

In Use

Preparation

Booth ExteriorVom. InfillsC-Level SeatingProvide Raker Access

Prepare Catwalk for Phase 6

Page 29: State Farm Center: Renovation and Addition Project

Raker Openings

Page 30: State Farm Center: Renovation and Addition Project

Seating Infills

Page 31: State Farm Center: Renovation and Addition Project

Seating Installation

Page 32: State Farm Center: Renovation and Addition Project

03/01/2014 – 10/31/2014

Temporary StairsDemolition of Stairs at Substation

5 Portables2 ADA RampsEast Addition

Phase 2 – C Level Concourse

Key

Construction

No Service

Ongoing

In Use

Temporary

South Ramps & PlazaWest Addition

Page 33: State Farm Center: Renovation and Addition Project

Dust Protection Tent

Page 34: State Farm Center: Renovation and Addition Project

Phase 3 Egress Plan

Page 35: State Farm Center: Renovation and Addition Project

Phase 3 – Basketball Season• Work continues on the East and West Addition

Service Level Fitout• Closeout of the Bid Package 1 Contractors• EXTENSIVE scheduling and pre-planning session

for Phase 4

Page 36: State Farm Center: Renovation and Addition Project
Page 37: State Farm Center: Renovation and Addition Project
Page 38: State Farm Center: Renovation and Addition Project
Page 39: State Farm Center: Renovation and Addition Project

Phase 4 Arena Bowl Demolition

Day 1

Page 40: State Farm Center: Renovation and Addition Project

Phase 4 Arena Bowl Demolition

Day 6

Page 41: State Farm Center: Renovation and Addition Project

NE Tunnel Excavation

Page 42: State Farm Center: Renovation and Addition Project

Tie Backs for the NE Tunnel

Page 43: State Farm Center: Renovation and Addition Project

Load Transfer Beam Placement

Page 44: State Farm Center: Renovation and Addition Project

“”Other” Work

Page 45: State Farm Center: Renovation and Addition Project

Project Challenges

Aggressive design schedule and even more aggressive construction schedule

Public client with state procurement limitations Renovation of a 50 year old building Finding qualified local manpower to be able to

support a project of this magnitude Despite all the challenges so far the project

remains on schedule and within budget.

Page 46: State Farm Center: Renovation and Addition Project

Questions ?