Starting and Closing Projects Funded by EuropeAid. FoRS 9-10 November 2009 Handout 2. Workshop learning objectives. By the end of the workshop, participants should: Be able to prepare appropriate and quality final narrative and financial reports to EC. Be able to prepare audits. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Starting and Closing Projects Funded by EuropeAid

Starting and Closing Projects Funded by EuropeAid

FoRS9-10 November 2009

Handout 2

1

Page 2: Starting and Closing Projects Funded by EuropeAid

Workshop learning objectives

By the end of the workshop, participants should:• Be able to prepare appropriate and quality final

narrative and financial reports to EC.• Be able to prepare audits.• Understand the requirements of the Standard Contract

and the roles and responsibilities of all stakeholders in managing EU funded contracts.

• Understand the roles and responsibilities of the members of project consortia.

• Be able to learn from previous experience in order to prepare better quality projects.

2

Page 3: Starting and Closing Projects Funded by EuropeAid

Session 1: Preparatory steps for end of project reporting.

Topics covered:

• Why Monitoring and Evaluation (M & E)?

• Information required by EC

• M & E - 3 essential steps

• Key M & E questions

• Types of M & E methods used

• Techniques used to gather information

3

Page 4: Starting and Closing Projects Funded by EuropeAid

The Project Life-cycle

3. Financing .

1. Identification

2. Design and Appraisal

4. Implementation

5. Completion

6. Evaluation

4

Page 5: Starting and Closing Projects Funded by EuropeAid

Logframe Basics

‘... IF results are delivered, AND assumptions hold true, THEN the project purpose will be achieved ...’

Objectively Verifiable Indicators

Intervention Logic

Sources of Verification

Risks & Assumptions

Overall Objectives

Specific objective

Results

Activities Means Cost

Pre-conditionss

5

Page 6: Starting and Closing Projects Funded by EuropeAid

Significance of project logframes• It forms part of the reporting requirements of the EC• It summarizes the project• It states what will be achieved• It shows how the project will be realized• It highlights risks and assumptions• It provides the basis for project planning and

management• It enables comparisons between planned and actual

activities

6

Page 7: Starting and Closing Projects Funded by EuropeAid

Reporting pre-requisites

• A Logical Framework as basis for M & E

• Baseline studies

• A monitoring plan

• Financial reports (minimum quarterly)

• Annual reports

• Case studies

• A final evaluation

7

Page 8: Starting and Closing Projects Funded by EuropeAid

Why M & E?

• To identify the impact and sustainability of the project

• To record and share lessons• To account to stakeholders• To improve your NGO’s future project design• To ensure funds used effectively and efficiently to

deliver results• To enable EC to monitor performance of projects

they have funded

8

Page 9: Starting and Closing Projects Funded by EuropeAid

Information required from M&E • What significant difference/changes have been made to

the lives of those involved? Are these sustainable?

• How have cross-cutting issues been mainstreamed (Human rights, gender equality, democracy, good governance, children’s rights, environmental sustainability, combating HIV/AIDS etc)

• Partnership, management and capacity building

• Participation of beneficiaries in M&E and their feedback

• Learning from the action, how this has been utilised and disseminated.

9

Page 10: Starting and Closing Projects Funded by EuropeAid

M & E - 3 essential steps

• Monitor – to ensure the project activities are on track

• Review – to consider whether the project activities are achieving the intended results

• Evaluate – to assess the overall impact of the project

10

Page 11: Starting and Closing Projects Funded by EuropeAid

Key M & E questions • How does the M & E process encourage

participation?• Does it develop capacity and equity?• How does it empower people?• How does it affect/take account of gender

disparity?• What indicators will you use to measure

participation, improved capacity, accountability, empowerment and sustainability?

11

Page 12: Starting and Closing Projects Funded by EuropeAid

Types of M & E methods used

• Questionnaires, surveys, checklists• Interviews• Documentation review• Observation• Focus Groups• Case studies

12

Page 13: Starting and Closing Projects Funded by EuropeAid

Some techniques used to gather information

• Case studies: interviews with selected stakeholders using pre-set questions for comparison purposes

• Focus groups: facilitated stakeholder group discussions around specific issues which ensure that all voices are heard

• Individual interviews: in-depth exploration using non-directive questioning

13

Page 14: Starting and Closing Projects Funded by EuropeAid

Session 2: Financial Management Issues

Points covered:• Financial management issues that will be

checked by auditors• Budget changes and reallocations• Audits

14

Page 15: Starting and Closing Projects Funded by EuropeAid

Changes that do not require a budget amendment (reallocations)

The 15% variance rule. (Article 9.2 of EC SC)You can modify the budget and inform the EC in

writing as soon as possible:• Where the financial impact is limited to a transfer

between items within the same main budget heading including cancellation or introduction of an item (this specific wording since SC 2007)

• A transfer between main budget headings involving a variation of 15% or less of the amount originally entered

15

Page 16: Starting and Closing Projects Funded by EuropeAid

Reallocations• You are advised to re-submit the all-years

budget with a set of extra columns showing the re-allocations made.

• Do not continually make re-allocations but do so e.g. at end of year when you are clear about changes that you would like to make. As a general rule, it is good practice to submit the re-allocated budget to your EC desk officer ahead of time for discussion.

16

Page 17: Starting and Closing Projects Funded by EuropeAid

Budget amendments

• Where the change means increasing a Main budget heading by more than 15% you will need to request an amendment to the contract.

• This must be done at least 1 month in advance of making the change.

• Do not leave budget amendment requests until too close to the end of the project: they may be refused.

17

Page 18: Starting and Closing Projects Funded by EuropeAid

EC Audit requirements

Standard Contract Versions August 2006, 2007 and 2008

• Minimum audit requirements. Article 15.6• Any request for payment of the balance in

the case of a grant of more than Euro 100,000.

• Any request for an interim payment for a grant of Euro 750,000 or over

18

Page 19: Starting and Closing Projects Funded by EuropeAid

Annex VII of Standard Contract sets out the terms for audit

The auditor will look at: Eligibility of Direct Costs Accuracy and recordingClassificationReality (Occurrence / existence)Compliance with procurement, nationality and

origin rulesAdministrative (indirect) costsContingencies

19

Page 20: Starting and Closing Projects Funded by EuropeAid

Eligible costs

Only costs that have been approved in the project budget in Annex III are eligible.

Article 14.2. Of SC gives a list of basic eligible costs.

Be careful that you respect the procurement rules in Annex IV.

20

Page 21: Starting and Closing Projects Funded by EuropeAid

Eligible Costs Article 14.1

• Eligible costs are those incurred during the implementation of the action EXCEPT the costs relating to final reports, expenditure verification and evaluation.

21

Page 22: Starting and Closing Projects Funded by EuropeAid

Article 14.1 Contracts for goods/services/works

• You can award a contract for goods/services/works BEFORE the implementation period starts

• These goods/services/works must be used/provided/delivered during the implementation period.

• They must be paid for before the final report is finalised.

• Wording for this is different in SC 2008

22

Page 23: Starting and Closing Projects Funded by EuropeAid

Documentation to keep• Article 16.3 of SC gives a list of the records

to keep.• This is a useful checklist for any donor.• Remember that you, and your partners,

must comply with international auditing standards.

23

Page 24: Starting and Closing Projects Funded by EuropeAid

Taxes & VAT are not eligible costs for most EC budget lines e.g. DCI including all thematic programmes such as NSA

• EC Article 14.6 says• Taxes including VAT are INELIGIBLE unless the

signatory to the contract or his partners cannot reclaim and the applicable regulations authorise coverage of taxes.

• The DCI Regulation does not permit using funds for taxes.

• You and your partners are expected to get exemption.

24

Page 25: Starting and Closing Projects Funded by EuropeAid

Keeping documentation• The EC has a long memory. • Article 16.2. Says that the EC may

inspect your accounts up to 7 years after the payment of the balance of the grant.

• Ensure all your files are kept in order for at least this period of time.

25

Page 26: Starting and Closing Projects Funded by EuropeAid

Session 3: Financial reporting

Points to be covered: • Report formats.• When to report• Coping with delays• Exchange rates• Reporting on unit costs • Recording reallocations

26

Page 27: Starting and Closing Projects Funded by EuropeAid

Interim and Final Reports for the EC

The information on how and when to report is found in Article 2 and Article

15 of Annex II of the Standard Contract

27

Page 28: Starting and Closing Projects Funded by EuropeAid

Final reports

• Final reports must be presented not later than 3 months after end date of implementation. (Art. 2.3.)

• However, the final report can be sent at the latest 6 months after the end date of the project if the grant beneficiary does not have its seat in the country of implementation.

28

Page 29: Starting and Closing Projects Funded by EuropeAid

When to report

• There are no fixed dates for submission of interim reports (Art.2.3. Says that an interim report must accompany every request for payment).

• You should have spent 70% of the most recent EC instalment and 100% of any previous instalments in order to report. (Art.15.1.)

• However, Interim reports should normally be presented at the latest by the end of each 12 month period following the start date of the project (Art.2.5.)

29

Page 30: Starting and Closing Projects Funded by EuropeAid

If you have not spent 70%

• Article 15.1. Says that if expenditure is less than the required 70% (and 100% of previous tranches) then the new pre-financing will be reduced by the unused amount.

• This means that you no longer need to delay reporting if you have not spent enough.

30

Page 31: Starting and Closing Projects Funded by EuropeAid

Financial information required

• Statement of income received during reporting period and cumulative since start of project

• Statement of expenditure against agreed budgets during reporting period and cumulative since start of project.

• Report of interest earned• Forecast budget for next phase/year.

31

Page 32: Starting and Closing Projects Funded by EuropeAid

SC August 2006 Article 2.1.Extra Information required

• ‘A list detailing each item of expenditure incurred in the period covered by the report and indicating for each its title, amount, relevant heading in the budget of the project and the reference of the justifying document is annexed to it’(the financial report).

32

Page 33: Starting and Closing Projects Funded by EuropeAid

Delays• If the project is delayed for any reason, the

EC must be informed before the due date of the report.

• GOLDEN RULE. Always keep the EC informed.

• You can delay the first report without having to change the end date of the contract.

33

Page 34: Starting and Closing Projects Funded by EuropeAid

No cost extensions

• If you want to extend the project implementation period, you can ask for a no-cost extension (within the limits of maximum project duration allowed by Call Guidelines).

• However, the EC has become much tighter on granting these.

• DO NOT ASSUME THE EC WILL AGREE TO AN EXTENSION. There must be very good reasons.

• Under-expenditure alone is not considered a good reason.

34

Page 35: Starting and Closing Projects Funded by EuropeAid

Reporting on variances

• Justification of variances between expenditure and approved budget only required in final report.

• See Article 9.2.

35

Page 36: Starting and Closing Projects Funded by EuropeAid

Exchange rate system

• Guidance is found in Article 15.9• Financial reports are now written in the currency

in which local expenditure is made. • You may have to use several currencies in a

report• Expenditure is converted into Euros at the rate

made up by the average of the rates published in InforEuro for the months covered by the relevant report.

36

Page 37: Starting and Closing Projects Funded by EuropeAid

Reporting the holdback

• Remember that to get the 10% holdback, you must pre-finance the EC and claim the money back when you present the final report.

• In the interim reports, you will report the pre-financing under your own income to the project.

• You will calculate any holdback due to you and claim this by filling in an Annex VI to be submitted with the final financial report.

37

Page 38: Starting and Closing Projects Funded by EuropeAid

Interest earned on the EC grant

• Interest earned on both HQ bank accounts and field accounts including those of partners must be reported.

• However you do not have to have an interest bearing account.

38

Page 39: Starting and Closing Projects Funded by EuropeAid

Article 15.9 Interest rules 2007

• SC 2007: Interest accruing from EC pre-financing equal to or below EUR 250,000 need not be paid back and can be invested in the project.

• If pre-financing is more than EUR 250,000, interest shall be paid back by deducting it from the balance due at the end of the contract.

39

Page 40: Starting and Closing Projects Funded by EuropeAid

Interest rules 2006

• These rules do not allow you to keep the interest. It must be recorded but will be deducted at the end of the project from the holdback.

40

Page 41: Starting and Closing Projects Funded by EuropeAid

Session 5: Narrative reports

Points covered:• Information required for final narrative

reports• EC criteria for evaluating the success of a

project.

41

Page 42: Starting and Closing Projects Funded by EuropeAid

New final narrative reports• Report on the last phase of activities (since last

report)• Results of entire project using logframe indicators• Report on outcomes on final beneficiaries• List publications and contracts awarded over EUR

5,000• Sustainability issues.• Report on gender equality, disabilities etc• Monitoring and evaluation methodology used and

feedback from beneficiaries.• Lessons learned and how disseminated.

42

Page 43: Starting and Closing Projects Funded by EuropeAid

Final reports…. continued

• Section 3 of format requires information on relationships with partners and others.

• Section 4. Requires a report on Visibility actions undertaken.• Proof of transfer of ownership of equipment.

Ensure at project planning stage that good monitoring plans are prepared to collect all this information.

43

Page 44: Starting and Closing Projects Funded by EuropeAid

EC criteria

• Efficiency• Effectiveness• Sustainability• Replicability

Does the information in your report provide evidence for the above?

44

Page 45: Starting and Closing Projects Funded by EuropeAid

Session 6: Partnerships

Points covered:• The importance of relationships• Principles for partnership• Capacity building• Practical partnership issues• First steps• Formalised agreements with partners• Project management structures

45

Page 46: Starting and Closing Projects Funded by EuropeAid

Why build relationships?

• To deliver the overall objectives of the project

• To build capacity of partners for sustainable participatory development

• For mutual enrichment between civil society north-north, north-south and and south-south.

46

Page 47: Starting and Closing Projects Funded by EuropeAid

Principles for partnership

• Develop relationships of trust

• Develop shared common values – e.g. Participatory approaches

• Take joint responsibility for delivering the project

• Establish collaborative working

relationships 47

Page 48: Starting and Closing Projects Funded by EuropeAid

Capacity building • EC says: All NSA projects must contain

some elements of capacity building and empowerment of civil society actors.

• Need to analyse partner/stakeholder capacities at outset to define skill training needs and other types of support (mentoring, management support etc)

• Ensure support included in plans, budgets, M&E, project protocols etc.

48

Page 49: Starting and Closing Projects Funded by EuropeAid

Practical partnership issues

• Lines of responsibility• Protocols for communication• Ensuring implementation takes place

according to agreed plans • Ensuring donor requirements are met • Measuring project outcomes and impact• Money management issues

49

Page 50: Starting and Closing Projects Funded by EuropeAid

Formalised agreements with partners

• You and your partners have joint responsibility for project delivery and reporting.

• How will you ensure that all parties fulfil their obligations towards each other and the donor?

• Contracts, MOUs

50

Page 51: Starting and Closing Projects Funded by EuropeAid

EC Standard Contract and partnership issues

• The grant beneficiary (signatory to the contract) is responsible for ensuring that their named partners respect all the rules and regulations of the standard contract.

• This includes procurement rules, eligibility of expenditure, documentation and record keeping etc.

• Consortium members have same status as partners with regard to contractual obligations.

51

Page 52: Starting and Closing Projects Funded by EuropeAid

Obligations of partners

• They sign the partnership agreement at time of submitting the funding proposal

• They are registered on PADOR• They do not have any other formalized

agreement with the EC• Important that Grant beneficiary and partners

sign formalized agreements between themselves. EC do not normally ask to see these.

52

Page 53: Starting and Closing Projects Funded by EuropeAid

Partners &EC reporting requirements

• EC require an assessment of the relationship between the formal partners of the action.

• Remember that where the project is submitted by a European NGO, the project should emanate from an idea of the partner(s) involved.

• Partners should be involved at every stage of the project (design, implementation, monitoring and evaluation). Reporting must provide evidence to show this.

53

Page 54: Starting and Closing Projects Funded by EuropeAid

Money management issues

• If partners received project funds they must manage them according to the regulations of the Standard Contract.

• They will be included in audit arrangements.

54

Page 55: Starting and Closing Projects Funded by EuropeAid

Session 7: Lesson learning and dissemination

Points covered:• What to include in lesson learning

• Means of dissemination of lessons learnt

55

Page 56: Starting and Closing Projects Funded by EuropeAid

Lessons learnt

These will include:

• The project/sector/theme

• General development issues

• Working with partners

• Best practice, innovation

• Programme management

• Capacity building

56

Page 57: Starting and Closing Projects Funded by EuropeAid

Means of dissemination and audiences

Share information with: • Czech partners, other partners from EU

Member States• Local partners, other NGOs, donors,

government, other local CSOs. Means of dissemination: • Reports, broadcast and print media,

internet, through seminars, conferences etc.

57

Page 58: Starting and Closing Projects Funded by EuropeAid

EC Visibility requirements

• You must report on how the visibility of the EU contribution is being ensured in the action.

• For new contracts you must provide the EC with a Visibility and Communication strategy.

58