start nicmos cooling system activity summary. 1/25/01ken pulkkinen2 start ncs activity applicable...

25
START NICMOS COOLING SYSTEM ACTIVITY SUMMARY

Upload: doris-douglas

Post on 17-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

START NICMOS COOLING SYSTEM

ACTIVITY SUMMARY

LOGO.049

Page 2: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 2

START NCS ACTIVITY

• Applicable SMOV Requirements:

• J.10.4.4.5 NICMOS Cooling System (NCS) Engineering Verification Requirements

– J.10.4.4.5.1 Configure the NCS to re-cool NICMOS detectors. The goal during SMOV is to verify the capability to maintain the NICMOS Cooling Coil temperature less than or equal to 69 +/- 0.1K.

– J.10.4.4.5.2 Verify the capability of the NCS to achieve a NICMOS Cold Well temperature of 75 +/- 3 degrees Kelvin and maintain it within 0.1 K.

LOGO.049

Page 3: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 3

START NCS ACTIVITY

• J.10.4.4.5 NICMOS Cooling System (NCS) Engineering Verification Requirements (cont.)

– J.10.4.4.5.3 Verify the NCS capability to provide adequate level of thermal stability and repeatability for NICMOS science operations. Minimum acceptable levels of performance are thermal stability at the detector baseplate of +/- 0.1 K over one hour and +/- 0.5 K over one month.

LOGO.049

Page 4: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 4

START NCS ACTIVITY

• J.10.4.4.6 NICMOS/NCS Calibration and Performance Requirements

– J.10.4.4.6.1 The temperatures of each NICMOS detector, along with its range of variation and the timescales for variation, shall be determined. Detector temperature stability shall be characterized over periods of 60 sec, 2000 sec, 24 hours, and 30 days.

LOGO.049

Page 5: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 5

START NCS ACTIVITY

• J.10.4.4.6 NICMOS/NCS Calibration and Performance Requirements (cont.)

– J.10.4.4.6.2 The temperature of the VCS (and hence the filter elements), along with its range of variation and the timescales for variation, shall be determined. The thermal stability of the VCS shall be determined to be within +/- 5 K of the nominal operating temperature as determined by models of NCS performance.

LOGO.049

Page 6: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 6

START NCS ACTIVITY

• Purpose:

– Configure the NCS to re-cool the NICMOS detectors, determine the optimal science operating temperature for the NICMOS detectors, and verify stable operation.

• Goals:

– 1) Cool the NICMOS to the coldest possible temperature with HST at a hot attitude and the NCC compressor operating near its maximum allowable speed.

LOGO.049

Page 7: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 7

START NCS ACTIVITY

• Goals (cont.):

– 2) Measure NICMOS detector performance during the cool-down and steady state operation of the NCS.

– 3) Demonstrate stability (+/-0.1K) of the NICMOS detector temperature at the optimal science operating temperature.

– 4) Demonstrate repeatability (+/-0.1 K) of NICMOS detector temperature following changes from the optimal science operating temperature.

LOGO.049

Page 8: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 8

START NCS ACTIVITY

• Methodology:

– 1) Start the NCS CPL (As early as possible in the BEA period)

– 2) Start the NCC circulator.

– 3) Start the NCC compressor.

– 4) With the NCC compressor max speed at its default value (7300 rps.), set the NCC PID control set point to 60 K, controlling off of the weighted average of the neon temperatures. This will result in the fastest cool-down.

LOGO.049

Page 9: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 9

START NCS ACTIVITY

• Methodology (cont.):

– 5) 24 hours after the NCC cool-down is begun, begin taking NICMOS detector internal temperature monitoring observations (30-minute dark, 0-sec bias exposures, FPA temperature, mounting cup temperature) once per orbit until the conclusion of the test [148 hr after start of cooldown (TBR)].

LOGO.049

Page 10: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 10

START NCS ACTIVITY

• Methodology (cont.):

– 6) 76 hours (TBR) after the NCC cool-down is begun, slew HST to the sun angle and roll (consistent with the BEA constraints) that produce the warmest mean NCS radiator temperature. Maintain this attitude for 72 hours (TBR).

LOGO.049

Page 11: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 11

START NCS ACTIVITY

• Methodology (cont.):

– 7) 90 hours after the NCC cool-down is begun, set the NCC compressor max speed to 7250 (TBR) rps (normal max speed is 7300 rps) and keep the NCC PID control set point at 60 K. This will cause the compressor to run at a fixed speed of 7250 rps. and will result in an asymptotic cool-down to the lowest temperature that can be reached at this speed and under these thermal conditions.

LOGO.049

Page 12: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 12

START NCS ACTIVITY

• Methodology (cont.):

• No HST attitude requirements pertain to steps 8-15.

– 8) 148 hours (TBR) after the NCC cool-down is begun, set the NCC PID control set point to 3.0 K (TBR) warmer than the temperature reached and the NCC compressor max speed to 7300 rps. This will put the NCC under active PID control at a controlled operating temperature. Maintain this set point for 48 hours (TBR). (Note: This configuration is a normal operational configuration and can be maintained indefinitely.)

LOGO.049

Page 13: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 13

START NCS ACTIVITY

• Methodology (cont.):

• Steps 9-11 verify the repeatability of the NICMOS detector temperature:

– 9) Increase NCC PID control set point by an amount that corresponds to 0.5 K at the NICMOS detector and maintain this temperature for 48 hours (TBR).

– 10) Decrease NCC PID control set point by an amount that corresponds to 1.0 K at the NICMOS detector and maintain this temperature for 48 hours (TBR).

LOGO.049

Page 14: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 14

START NCS ACTIVITY

• Methodology (cont.):

– 11) Increase NCC PID control set point by an amount that corresponds to 0.5 K at the NICMOS detector and maintain this temperature for 48 hours (TBR).

– 12) Two weeks after the end of the BEA period, set the NCC PID control set point to the temperature that corresponds to the NICMOS detector optimal science operating temperature as determined from analysis of the data taken in step 7. This temperature will depend on NCS and NICMOS detector performance. Maintain this set point for 48 hours (TBR).

LOGO.049

Page 15: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 15

START NCS ACTIVITY

• Methodology (cont.):

– 13) Concurrent with steps 8-12, take NICMOS detector internal temperature monitoring observations once per orbit.

– 14) At the end of the 48-hr stabilization interval, take continuous NICMOS detector internal temperature monitoring observations for 1 orbit to demonstrate +/-0.1K stability at the science operating temperature (known as rapid monitor data takes).

LOGO.049

Page 16: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 16

START NCS ACTIVITY

• Methodology (cont.):

– 15) Continue NICMOS detector internal temperature monitoring observations once every three orbits for 1 month (150 samples) to demonstrate +/-0.5K stability at the science operating temperature.

• Implementation Method:

– Real-time commanding for NCS operations.

– Proposal for NICMOS measurements.

LOGO.049

Page 17: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 17

START NCS ACTIVITY

• Dependencies:

– 1) Fill NCS circulator neon loop (done in command plan after release)

– 2) Perform STIS baseline measurements.

– 3) A Vehicle Disturbance Test (VDT) is planned in regards to NCC startup. The following are the requirements in conjunction with NCC startup:

• a) At least 1 full orbit at +V3 sunpoint prior to NCC operation while moving the ACS Filter Wheel

LOGO.049

Page 18: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 18

START NCS ACTIVITY

• Dependencies (cont.):

• b) At least 5 full orbits at +V3 sunpoint prior to NCC operation with no filter wheel motion

• c) At least 1 full orbit at +V3 sunpoint during NCC startup

• d) At least 5 full orbits at +V3 sunpoint while NCC is operating at steady-state

• e) At least 5 full orbits at -V1 sunpoint while NCC is operating at steady-state

LOGO.049

Page 19: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 19

START NCS ACTIVITY

• Duration:

– Starting the NCS CPL requires approximately 3 hours of sparse real-time commanding.

– Starting the NCC circulator and compressor requires approximately 1 hour of real-time commanding.

– The NCC cool-down during the BEA requires approximately 148 hours. The final 76 hours of this is at a specified attitude.

LOGO.049

Page 20: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 20

START NCS ACTIVITY

• Duration (cont.):

– The NCS stability and repeatability steps require approximately 15 days. There are no related HST attitude requirements and these steps can be done in parallel with other activities.

• Data requirements:

– Several (TBD) NCS history buffer dumps for NCS start-up (8 Kbytes/dump)

LOGO.049

Page 21: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 21

START NCS ACTIVITY

• Data requirements (cont.):

– NICMOS detector data:

• Once-per-orbit internal temperature monitor: DARK = 30-min dark 3 detectors = 12.5 MB. BIAS = 2 x 100 0-sec exposures 1 detector = 32 MB. There is no additional data volume for FPA and mounting cup temperature.

LOGO.049

Page 22: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 22

START NCS ACTIVITY

• Data requirements (cont.):

– NICMOS detector data (cont.):

• Daily data volume = 15 orbits of 3-detector DARK + 15 orbits of 1-detector BIAS + 1 orbit of 2-detector BIAS = 15*12.5 + 15*32 + 2*32 = 731.5 MB.

• One orbit rapid monitor: 88 MB (TBD)

LOGO.049

Page 23: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 23

START NCS ACTIVITY

• Analyses & Results:

– The CHAMP Thermal group will analyze NCS thermal performance. The BEA NCS cool-down and steady state data will be used to determine the coldest NCC Cold Load Interface temperature that the NCS can maintain under active PID control in all expected thermal environments. Analysis is expected to require two weeks (TBR). Results of this analysis are required for the stability and repeatability parts of this activity, which begin after the BEA period.

LOGO.049

Page 24: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 24

START NCS ACTIVITY

• Analyses & Results (cont.):

– The STScI NICMOS team will analyze NICMOS detector performance. NICMOS detector data from the BEA cool-down period will be used to determine the detector temperature that will provide the optimal science data by trading detector quantum efficiency and dark current and considering the minimum sustainable NICMOS temperature. Analysis is expected to require two week (TBR). Results of this analysis are required for the stability and repeatability parts of this activity, which begin after the BEA period.

LOGO.049

Page 25: START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J.10.4.4.5 NICMOS Cooling System

1/25/01 Ken Pulkkinen 25

START NCS ACTIVITY

• Analyses & Results (cont.):

– NICMOS detector data from the post-BEA period will be used to determine detector temperature stability and repeatability. Analysis is expected to require one week (TBR). Results of this analysis are required prior to beginning NICMOS calibration and science observations.

LOGO.049