stars oasis tech. cont. l.l.c hvac testing and...
TRANSCRIPT
STARS OASIS TECH. CONT. L.L.C
HVAC TESTING AND COMMISSIONING
P.O.Box 47068 *Sharjah* United Arab Emirates* Tel. 06 5740350 * [email protected]
Introduction
Company Introduction
Stars Oasis Tech. Cont. LLC (OTEC) is a leading independent Testing andBalancing company in the Middle East providing the following technicalservices to our Clients. The commissioning team comprises of fully qualified,experienced engineers and specialists dedicated to provide truly independentservices.
Testing and commissioning services are carried out in accordance with thefollowing Commissioning Codes of Practice:Chartered Institute of Building Services Engineers (C.I.B.S.E)
Building Services Research and Information Association (B.S.R.I.A)American Society of Heating, Refrigerating and Air Conditioning Engineers(A.S.H.R.A.E)Associated Air Balancing Council (A.A.B.C)Commissioning Specialist Association (C.S.A)
Our motto to provide top-notch tailor made quality solutions to our clientshelped us reach the pinnacle of success over the past .We take pride in thehistory of our success. The confidence our clients have on us motivates us tocontinue our journey with a passion to deliver the best without anycompromise.Every step forward is a challenge and we are sure that our drive to be thebest will help us deliver value added solutions to every challenge that we facewith integrity and perfection.
Introduction
Company Introduction
Stars Oasis Tech. Cont. LLC (OTEC) is a leading independent Testing andBalancing company in the Middle East providing the following technicalservices to our Clients. The commissioning team comprises of fully qualified,experienced engineers and specialists dedicated to provide truly independentservices.
Testing and commissioning services are carried out in accordance with thefollowing Commissioning Codes of Practice:Chartered Institute of Building Services Engineers (C.I.B.S.E)
Building Services Research and Information Association (B.S.R.I.A)American Society of Heating, Refrigerating and Air Conditioning Engineers(A.S.H.R.A.E)Associated Air Balancing Council (A.A.B.C)Commissioning Specialist Association (C.S.A)
Our motto to provide top-notch tailor made quality solutions to our clientshelped us reach the pinnacle of success over the past .We take pride in thehistory of our success. The confidence our clients have on us motivates us tocontinue our journey with a passion to deliver the best without anycompromise.Every step forward is a challenge and we are sure that our drive to be thebest will help us deliver value added solutions to every challenge that we facewith integrity and perfection.
Introduction
Company Introduction
Stars Oasis Tech. Cont. LLC (OTEC) is a leading independent Testing andBalancing company in the Middle East providing the following technicalservices to our Clients. The commissioning team comprises of fully qualified,experienced engineers and specialists dedicated to provide truly independentservices.
Testing and commissioning services are carried out in accordance with thefollowing Commissioning Codes of Practice:Chartered Institute of Building Services Engineers (C.I.B.S.E)
Building Services Research and Information Association (B.S.R.I.A)American Society of Heating, Refrigerating and Air Conditioning Engineers(A.S.H.R.A.E)Associated Air Balancing Council (A.A.B.C)Commissioning Specialist Association (C.S.A)
Our motto to provide top-notch tailor made quality solutions to our clientshelped us reach the pinnacle of success over the past .We take pride in thehistory of our success. The confidence our clients have on us motivates us tocontinue our journey with a passion to deliver the best without anycompromise.Every step forward is a challenge and we are sure that our drive to be thebest will help us deliver value added solutions to every challenge that we facewith integrity and perfection.
CertificateCertificateCertificate
CertificateCertificateCertificate
CertificateCertificateCertificate
Professional LicenseProfessional LicenseProfessional License
STARS OASIS TECH. CONT. LLC - ORGANISATION CHART
HR &ADMINISTRATION
GENERAL MANAGER
OTEC
ACCOUNTSTECHNICALDOCUMENTATION
PROJECTS MANAGER
HR &ADMINISTRATION
TAB SUPERVISOR TAB SUPERVISOR TAB SUPERVISOR TAB SUPERVISOR TAB TECHNICIAN TAB TECHNICIAN
TAB ENGINEER
TAB TECHNICIAN TAB TECHNICIAN TAB TECHNICIANTAB TECHNICIANTAB TECHNICIANJUNIOR TAB
TECHNICIANS
TAB ENGINEERTAB TENGINEER TAB ENGINEER
TECHNICALDOCUMENTATION
HVAC Testing & Commissioning
H.V.A.C. Testing & Balancing
Independent testing, adjusting and balancing of HVAC system components incompliance with international standards, to the design parameters and to theapproval of the client. OTEC offer a comprehensive service for all HVACsystem including Air Conditioning, Chilled Water and Domestic Hot and ColdWater services, for newly build and refurbishment. In addition, site surveysand troubleshooting can be undertaken, including acoustic and environmentaltesting.
HVAC Systems typically use sophisticated, automatic control to supply theproper amount of air for cooling, heating and ventilation in commercialbuildings. Problems encountered during installation, operation andmaintenance of servicing of the HVAC system could prevent it from operatingas designed. There for each system has to be tested to ensure its initial andcontinued performances.
In addition to provide optimal thermal conditions and balanced ventilation, aproperly adjusted and balanced system can also reduce operating cost andincrease equipment life.
Our Testing and Balancing report provides a complete record of the design,preliminary measurements and final test data. The report includes anydiscrepancies between the test data and the design specifications, along withreasons for those discrepancies.
HVAC Testing & Commissioning
H.V.A.C. Testing & Balancing
Independent testing, adjusting and balancing of HVAC system components incompliance with international standards, to the design parameters and to theapproval of the client. OTEC offer a comprehensive service for all HVACsystem including Air Conditioning, Chilled Water and Domestic Hot and ColdWater services, for newly build and refurbishment. In addition, site surveysand troubleshooting can be undertaken, including acoustic and environmentaltesting.
HVAC Systems typically use sophisticated, automatic control to supply theproper amount of air for cooling, heating and ventilation in commercialbuildings. Problems encountered during installation, operation andmaintenance of servicing of the HVAC system could prevent it from operatingas designed. There for each system has to be tested to ensure its initial andcontinued performances.
In addition to provide optimal thermal conditions and balanced ventilation, aproperly adjusted and balanced system can also reduce operating cost andincrease equipment life.
Our Testing and Balancing report provides a complete record of the design,preliminary measurements and final test data. The report includes anydiscrepancies between the test data and the design specifications, along withreasons for those discrepancies.
HVAC Testing & Commissioning
H.V.A.C. Testing & Balancing
Independent testing, adjusting and balancing of HVAC system components incompliance with international standards, to the design parameters and to theapproval of the client. OTEC offer a comprehensive service for all HVACsystem including Air Conditioning, Chilled Water and Domestic Hot and ColdWater services, for newly build and refurbishment. In addition, site surveysand troubleshooting can be undertaken, including acoustic and environmentaltesting.
HVAC Systems typically use sophisticated, automatic control to supply theproper amount of air for cooling, heating and ventilation in commercialbuildings. Problems encountered during installation, operation andmaintenance of servicing of the HVAC system could prevent it from operatingas designed. There for each system has to be tested to ensure its initial andcontinued performances.
In addition to provide optimal thermal conditions and balanced ventilation, aproperly adjusted and balanced system can also reduce operating cost andincrease equipment life.
Our Testing and Balancing report provides a complete record of the design,preliminary measurements and final test data. The report includes anydiscrepancies between the test data and the design specifications, along withreasons for those discrepancies.
HVAC Testing & Commissioning
Commissioning Management
The commissioning company has a major role in any building as theirindependent input helps all concerned focus on the performance of eachsystem. The commissioning manager plays a vital part in bringing allconcerned parties to the table and ensure that the various systems arecoordinated ready for start up and commissioning. The commissioningmanager will schedule the trades so that upon initialization allinterconnections, integration or interfaces with other trades are consideredand incorporated within the start up process. The commissioning managercan be appointed at the design stage to review the commissionability of eachsystem, value engineering and hoe maintainable the actual design solutionwill be.
OTEC provide a fully independent Commissioning Management Serviceswhich offers the following:
HVAC Commissioning Design Assessment
System installation and commissioning-ability assessment and monito
HVAC Commissioning method statement
Coordination and witnessing of Testing and Balancing
Pre-commissioning and Commissioning Test witnessing
Verification of test documents
MEP site coordination
HVAC Testing & Commissioning
Commissioning Management
The commissioning company has a major role in any building as theirindependent input helps all concerned focus on the performance of eachsystem. The commissioning manager plays a vital part in bringing allconcerned parties to the table and ensure that the various systems arecoordinated ready for start up and commissioning. The commissioningmanager will schedule the trades so that upon initialization allinterconnections, integration or interfaces with other trades are consideredand incorporated within the start up process. The commissioning managercan be appointed at the design stage to review the commissionability of eachsystem, value engineering and hoe maintainable the actual design solutionwill be.
OTEC provide a fully independent Commissioning Management Serviceswhich offers the following:
HVAC Commissioning Design Assessment
System installation and commissioning-ability assessment and monito
HVAC Commissioning method statement
Coordination and witnessing of Testing and Balancing
Pre-commissioning and Commissioning Test witnessing
Verification of test documents
MEP site coordination
HVAC Testing & Commissioning
Commissioning Management
The commissioning company has a major role in any building as theirindependent input helps all concerned focus on the performance of eachsystem. The commissioning manager plays a vital part in bringing allconcerned parties to the table and ensure that the various systems arecoordinated ready for start up and commissioning. The commissioningmanager will schedule the trades so that upon initialization allinterconnections, integration or interfaces with other trades are consideredand incorporated within the start up process. The commissioning managercan be appointed at the design stage to review the commissionability of eachsystem, value engineering and hoe maintainable the actual design solutionwill be.
OTEC provide a fully independent Commissioning Management Serviceswhich offers the following:
HVAC Commissioning Design Assessment
System installation and commissioning-ability assessment and monito
HVAC Commissioning method statement
Coordination and witnessing of Testing and Balancing
Pre-commissioning and Commissioning Test witnessing
Verification of test documents
MEP site coordination
HVAC Testing & Commissioning
Sound Level and Environmental Test
Upon completion of Testing and Balancing, we will provide Sound Level Testand Environmental condition monitoring. Sound Level testing comprises ofour engineers using state-of-the-art acoustic equipment that will measure thesound level in all spaces of the building. The study can only be conductedwhen commissioning is complete and all of the buildings fabrics and fittingshave been put in place. The study records all the sound within the space, withplant ON and OFF.
Environmental condition monitoring comprises if our engineers eitherphysically taking readings from each space or setting calibrated electronicdata loggers to record temperature and humidity. During this verification thebuilding management and controls system is modulated and each reading isverified. The data gathered is then provided to the controls specialist enablingexact offsets to be entered into the control system, if necessary. Theindividual space is then retested and signed off.
HVAC Testing & Commissioning
Sound Level and Environmental Test
Upon completion of Testing and Balancing, we will provide Sound Level Testand Environmental condition monitoring. Sound Level testing comprises ofour engineers using state-of-the-art acoustic equipment that will measure thesound level in all spaces of the building. The study can only be conductedwhen commissioning is complete and all of the buildings fabrics and fittingshave been put in place. The study records all the sound within the space, withplant ON and OFF.
Environmental condition monitoring comprises if our engineers eitherphysically taking readings from each space or setting calibrated electronicdata loggers to record temperature and humidity. During this verification thebuilding management and controls system is modulated and each reading isverified. The data gathered is then provided to the controls specialist enablingexact offsets to be entered into the control system, if necessary. Theindividual space is then retested and signed off.
HVAC Testing & Commissioning
Sound Level and Environmental Test
Upon completion of Testing and Balancing, we will provide Sound Level Testand Environmental condition monitoring. Sound Level testing comprises ofour engineers using state-of-the-art acoustic equipment that will measure thesound level in all spaces of the building. The study can only be conductedwhen commissioning is complete and all of the buildings fabrics and fittingshave been put in place. The study records all the sound within the space, withplant ON and OFF.
Environmental condition monitoring comprises if our engineers eitherphysically taking readings from each space or setting calibrated electronicdata loggers to record temperature and humidity. During this verification thebuilding management and controls system is modulated and each reading isverified. The data gathered is then provided to the controls specialist enablingexact offsets to be entered into the control system, if necessary. Theindividual space is then retested and signed off.
HVAC Testing & Commissioning
Vibration Test
We provide vibration testing for both predictive maintenance and reactivemaintenance. With our predictive maintenance technique we utilize a vibrationmeasuring device that records a blue print of your piece of plant. Thismeasurement can be trended to ensure that each item of the plant is workingto its optimum performance. By utilizing this service as part of the regularmaintenance plant optimization can be guaranteed. The vibration test iscarried out on equipment suspected of excessive vibration and unusual noise.Any unusual noise should be dealt with immediately, this is often the tell tailsign that the plant is failing or working inefficiently. Vibration test can also becarried out on the plant with intermittent faults, often vibration can trace theroot of the problem quickly, accurately without any down time.
HVAC Testing & Commissioning
Vibration Test
We provide vibration testing for both predictive maintenance and reactivemaintenance. With our predictive maintenance technique we utilize a vibrationmeasuring device that records a blue print of your piece of plant. Thismeasurement can be trended to ensure that each item of the plant is workingto its optimum performance. By utilizing this service as part of the regularmaintenance plant optimization can be guaranteed. The vibration test iscarried out on equipment suspected of excessive vibration and unusual noise.Any unusual noise should be dealt with immediately, this is often the tell tailsign that the plant is failing or working inefficiently. Vibration test can also becarried out on the plant with intermittent faults, often vibration can trace theroot of the problem quickly, accurately without any down time.
HVAC Testing & Commissioning
Vibration Test
We provide vibration testing for both predictive maintenance and reactivemaintenance. With our predictive maintenance technique we utilize a vibrationmeasuring device that records a blue print of your piece of plant. Thismeasurement can be trended to ensure that each item of the plant is workingto its optimum performance. By utilizing this service as part of the regularmaintenance plant optimization can be guaranteed. The vibration test iscarried out on equipment suspected of excessive vibration and unusual noise.Any unusual noise should be dealt with immediately, this is often the tell tailsign that the plant is failing or working inefficiently. Vibration test can also becarried out on the plant with intermittent faults, often vibration can trace theroot of the problem quickly, accurately without any down time.
HVAC Testing & Commissioning
Duct Leak / Pressure Test
A duct leakage tester is a diagnostic tool designed to measure the airtightness of forced air heating, ventilating and air-conditioning (HVAC)ductwork. A duct leakage tester consists of a calibrated fan for measuring anair flow rate and a pressure sensing device to measure the pressure createdby the fan flow. The combination of pressure and fan flow measurements areused to determine the ductwork air tightness.
During the construction process, when the duct is accessible before the grillesand equipment is installed, each intentional opening in the duct system issealed air tight with plastic and tape. The duct system is then placed underhigh pressure, and the airflow through the fan is measured. The fan airflow isinterpreted as duct leakage. If the level of leakage is out of spec, the leakyduct is repaired and then the test is repeated. The process continues untilacceptable results are achieved.
Higher pressure is critical to assure the pressure at the fan is equal to thepressure throughout the entire duct system. Only then can the pressure at thefan be interpreted to represent accurate airflow leakage throughout thesystem.
Since air is the fluid that carries the heating or cooling throughout the building,its flow, temperatures, velocities, losses, gains, and enthalpy must be verifiedat many points throughout the system so it can be effectively diagnosed andperformance rated.
Airflow is the life-blood of a system upon which all the other components andcircuits depend. Air is as essential to the system as power is to the fan.Without verification of airflow throughout the entire system, it’s impossible toeffectively test the heating and refrigeration performance.
HVAC Testing & Commissioning
Duct Leak / Pressure Test
A duct leakage tester is a diagnostic tool designed to measure the airtightness of forced air heating, ventilating and air-conditioning (HVAC)ductwork. A duct leakage tester consists of a calibrated fan for measuring anair flow rate and a pressure sensing device to measure the pressure createdby the fan flow. The combination of pressure and fan flow measurements areused to determine the ductwork air tightness.
During the construction process, when the duct is accessible before the grillesand equipment is installed, each intentional opening in the duct system issealed air tight with plastic and tape. The duct system is then placed underhigh pressure, and the airflow through the fan is measured. The fan airflow isinterpreted as duct leakage. If the level of leakage is out of spec, the leakyduct is repaired and then the test is repeated. The process continues untilacceptable results are achieved.
Higher pressure is critical to assure the pressure at the fan is equal to thepressure throughout the entire duct system. Only then can the pressure at thefan be interpreted to represent accurate airflow leakage throughout thesystem.
Since air is the fluid that carries the heating or cooling throughout the building,its flow, temperatures, velocities, losses, gains, and enthalpy must be verifiedat many points throughout the system so it can be effectively diagnosed andperformance rated.
Airflow is the life-blood of a system upon which all the other components andcircuits depend. Air is as essential to the system as power is to the fan.Without verification of airflow throughout the entire system, it’s impossible toeffectively test the heating and refrigeration performance.
HVAC Testing & Commissioning
Duct Leak / Pressure Test
A duct leakage tester is a diagnostic tool designed to measure the airtightness of forced air heating, ventilating and air-conditioning (HVAC)ductwork. A duct leakage tester consists of a calibrated fan for measuring anair flow rate and a pressure sensing device to measure the pressure createdby the fan flow. The combination of pressure and fan flow measurements areused to determine the ductwork air tightness.
During the construction process, when the duct is accessible before the grillesand equipment is installed, each intentional opening in the duct system issealed air tight with plastic and tape. The duct system is then placed underhigh pressure, and the airflow through the fan is measured. The fan airflow isinterpreted as duct leakage. If the level of leakage is out of spec, the leakyduct is repaired and then the test is repeated. The process continues untilacceptable results are achieved.
Higher pressure is critical to assure the pressure at the fan is equal to thepressure throughout the entire duct system. Only then can the pressure at thefan be interpreted to represent accurate airflow leakage throughout thesystem.
Since air is the fluid that carries the heating or cooling throughout the building,its flow, temperatures, velocities, losses, gains, and enthalpy must be verifiedat many points throughout the system so it can be effectively diagnosed andperformance rated.
Airflow is the life-blood of a system upon which all the other components andcircuits depend. Air is as essential to the system as power is to the fan.Without verification of airflow throughout the entire system, it’s impossible toeffectively test the heating and refrigeration performance.
HVAC Testing & Commissioning
Plant Surveys
We provide a combination of observations and physical measurements in aconcise tabulated format to enable you to appreciate the condition andperformance against design. We also estimate the life expectancy of yourplant.
We record the physical details, design data and the dynamic measurement ofvolumetric flow rates, static pressures, speed and absorbed current. In orderto provide an extremely cost effective service, we focus on plant rooms andspecifically nominated areas. However, we would be happy to record andcompare air and water flow rates throughout the network. We can also inspectthe condition and operation of the HVAC system with regard to Life SafetyEquipments such as fire dampers and duct smoke detectors.
Our quality controlled documents record both static and dynamic plant data.Our team measures all relevant plant data with latest calibrated and certifiedtest equipment.
HVAC Testing & Commissioning
Plant Surveys
We provide a combination of observations and physical measurements in aconcise tabulated format to enable you to appreciate the condition andperformance against design. We also estimate the life expectancy of yourplant.
We record the physical details, design data and the dynamic measurement ofvolumetric flow rates, static pressures, speed and absorbed current. In orderto provide an extremely cost effective service, we focus on plant rooms andspecifically nominated areas. However, we would be happy to record andcompare air and water flow rates throughout the network. We can also inspectthe condition and operation of the HVAC system with regard to Life SafetyEquipments such as fire dampers and duct smoke detectors.
Our quality controlled documents record both static and dynamic plant data.Our team measures all relevant plant data with latest calibrated and certifiedtest equipment.
HVAC Testing & Commissioning
Plant Surveys
We provide a combination of observations and physical measurements in aconcise tabulated format to enable you to appreciate the condition andperformance against design. We also estimate the life expectancy of yourplant.
We record the physical details, design data and the dynamic measurement ofvolumetric flow rates, static pressures, speed and absorbed current. In orderto provide an extremely cost effective service, we focus on plant rooms andspecifically nominated areas. However, we would be happy to record andcompare air and water flow rates throughout the network. We can also inspectthe condition and operation of the HVAC system with regard to Life SafetyEquipments such as fire dampers and duct smoke detectors.
Our quality controlled documents record both static and dynamic plant data.Our team measures all relevant plant data with latest calibrated and certifiedtest equipment.
HVAC Testing & Commissioning
Indoor Air Quality Test
The quality of air within our working environment is extremely importantASHRAE following an extensive survey concluded that productivity can beimproved by 10 - 25% by improving air quality. We provide air qualityinspections to determine whether the property is suffering from Sick BuildingSyndrome (SBS) or Building Related Illness (BRI).
A building's air duct network act as its respiratory system. Dirt, dust, debrisand microbial growth that accumulate inside of air ducts hidden from view andmake it difficult for the building to (breath) properly and function efficiently.
HVAC Testing & Commissioning
Indoor Air Quality Test
The quality of air within our working environment is extremely importantASHRAE following an extensive survey concluded that productivity can beimproved by 10 - 25% by improving air quality. We provide air qualityinspections to determine whether the property is suffering from Sick BuildingSyndrome (SBS) or Building Related Illness (BRI).
A building's air duct network act as its respiratory system. Dirt, dust, debrisand microbial growth that accumulate inside of air ducts hidden from view andmake it difficult for the building to (breath) properly and function efficiently.
HVAC Testing & Commissioning
Indoor Air Quality Test
The quality of air within our working environment is extremely importantASHRAE following an extensive survey concluded that productivity can beimproved by 10 - 25% by improving air quality. We provide air qualityinspections to determine whether the property is suffering from Sick BuildingSyndrome (SBS) or Building Related Illness (BRI).
A building's air duct network act as its respiratory system. Dirt, dust, debrisand microbial growth that accumulate inside of air ducts hidden from view andmake it difficult for the building to (breath) properly and function efficiently.
HVAC Testing & Commissioning
Operating and Maintenance Manuals
We pride ourselves as one of the leading professionals in the preparation ofElectro-Mechanical Services Operating and Maintenance manuals, complyingwith BSRIA standards which has been widely accepted by the reputed Clients,Consultants and Contractors in the United Arab Emirates.
A well prepared Operating and maintenance manual is a handy tool of themaintenance staff to carry out effective maintenance on any plant orequipment installed at any facility.
Poor and unplanned maintenance affects the performance and life of theequipment resulting in untimely breakdown and increased costs affectingproductivity.
On the other hand effective maintenance carried out on any piece ofequipment complying with the manufacturers recommendations prolong thelife of the equipment and reduces down time and operational costs.
Our professional team work in line with the requirements of all parties involvedto prepare professional and tailor made manuals complying with the setstandards on each project.
HVAC Testing & Commissioning
Operating and Maintenance Manuals
We pride ourselves as one of the leading professionals in the preparation ofElectro-Mechanical Services Operating and Maintenance manuals, complyingwith BSRIA standards which has been widely accepted by the reputed Clients,Consultants and Contractors in the United Arab Emirates.
A well prepared Operating and maintenance manual is a handy tool of themaintenance staff to carry out effective maintenance on any plant orequipment installed at any facility.
Poor and unplanned maintenance affects the performance and life of theequipment resulting in untimely breakdown and increased costs affectingproductivity.
On the other hand effective maintenance carried out on any piece ofequipment complying with the manufacturers recommendations prolong thelife of the equipment and reduces down time and operational costs.
Our professional team work in line with the requirements of all parties involvedto prepare professional and tailor made manuals complying with the setstandards on each project.
HVAC Testing & Commissioning
Operating and Maintenance Manuals
We pride ourselves as one of the leading professionals in the preparation ofElectro-Mechanical Services Operating and Maintenance manuals, complyingwith BSRIA standards which has been widely accepted by the reputed Clients,Consultants and Contractors in the United Arab Emirates.
A well prepared Operating and maintenance manual is a handy tool of themaintenance staff to carry out effective maintenance on any plant orequipment installed at any facility.
Poor and unplanned maintenance affects the performance and life of theequipment resulting in untimely breakdown and increased costs affectingproductivity.
On the other hand effective maintenance carried out on any piece ofequipment complying with the manufacturers recommendations prolong thelife of the equipment and reduces down time and operational costs.
Our professional team work in line with the requirements of all parties involvedto prepare professional and tailor made manuals complying with the setstandards on each project.
HVAC Testing & Commissioning
Witnessing, Verification and Inspection
For owners and operators of all electro-mechanical services, witnessing,inspection and verification of plant and equipment installed is a mandatoryprocess. Your facilities can benefit from our multi-disciplinary team of highlyqualified inspection engineers, who can provide mandatory inspectionservices as well as independent third party inspection, verification andendorsement.
Mandatory Witnessing & Inspection ServicesReview and verification of design drawings and technical data.Witnessing, inspection, verification and approval of new, used or in-service local or imported plant and equipmentWitnessing, verification and approval of installations.
Independent Third Party Inspection, Verification and EndorsementServicesInspection before, during and after InstallationCompliance Inspection on Imported and In-service Equipment andMachinery.Condition Monitoring and Plant Assessment;Non-Destructive Evaluation (Witness and Verification of Test Report);
and endorsement of Failure Investigation and Analysis Reports.
AdvantagesRespond to defects detected at an early stage to save costs.Improve safety and quality through our comprehensive and credibleinspections.Take advantage of business opportunities through compliance tovarious codes, standards, specifications and design requirements.Minimize the inspection time required for facilities that have been shutdown or are under construction, saving your costs.
HVAC Testing & Commissioning
Witnessing, Verification and Inspection
For owners and operators of all electro-mechanical services, witnessing,inspection and verification of plant and equipment installed is a mandatoryprocess. Your facilities can benefit from our multi-disciplinary team of highlyqualified inspection engineers, who can provide mandatory inspectionservices as well as independent third party inspection, verification andendorsement.
Mandatory Witnessing & Inspection ServicesReview and verification of design drawings and technical data.Witnessing, inspection, verification and approval of new, used or in-service local or imported plant and equipmentWitnessing, verification and approval of installations.
Independent Third Party Inspection, Verification and EndorsementServicesInspection before, during and after InstallationCompliance Inspection on Imported and In-service Equipment andMachinery.Condition Monitoring and Plant Assessment;Non-Destructive Evaluation (Witness and Verification of Test Report);
and endorsement of Failure Investigation and Analysis Reports.
AdvantagesRespond to defects detected at an early stage to save costs.Improve safety and quality through our comprehensive and credibleinspections.Take advantage of business opportunities through compliance tovarious codes, standards, specifications and design requirements.Minimize the inspection time required for facilities that have been shutdown or are under construction, saving your costs.
HVAC Testing & Commissioning
Witnessing, Verification and Inspection
For owners and operators of all electro-mechanical services, witnessing,inspection and verification of plant and equipment installed is a mandatoryprocess. Your facilities can benefit from our multi-disciplinary team of highlyqualified inspection engineers, who can provide mandatory inspectionservices as well as independent third party inspection, verification andendorsement.
Mandatory Witnessing & Inspection ServicesReview and verification of design drawings and technical data.Witnessing, inspection, verification and approval of new, used or in-service local or imported plant and equipmentWitnessing, verification and approval of installations.
Independent Third Party Inspection, Verification and EndorsementServicesInspection before, during and after InstallationCompliance Inspection on Imported and In-service Equipment andMachinery.Condition Monitoring and Plant Assessment;Non-Destructive Evaluation (Witness and Verification of Test Report);
and endorsement of Failure Investigation and Analysis Reports.
AdvantagesRespond to defects detected at an early stage to save costs.Improve safety and quality through our comprehensive and credibleinspections.Take advantage of business opportunities through compliance tovarious codes, standards, specifications and design requirements.Minimize the inspection time required for facilities that have been shutdown or are under construction, saving your costs.
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
The One Tower @ TECOM DEWAN
The Abu Dhabi InternationalAirport Expansion -Catering South Side
ADAC
Souq Extra (Mall) - SiliconOasis, Dubai
JOHN R HARRIS
Asset Enhancement Worksin Burjman Centre - 1
SEED
Al Wasl Box Park EO
TAJ Downtown Hotel DAR / IBA
LULU Regional HQ - Dubai DAR / IBA
Bay Square @ Business Bay(12 Building & CommonBasement)
KHATIB ALAMI
G+3 GEMS WillingtonAcademy @ DSO
PJSI
Air College Al Ain - CMW-13019 - C002-02
CMW
Bawabat Al Sharq - Phase2A Buildings
AECOM
Construction of StableComplex @ Endurance Villa- Al Lissaili, Dubai
EO
Construction of ADNOCFilling Station - MotorWorld, Abu Dhabi
DORSCH
Al Falah Community - AbuDhabi (2080 Villas)
WS ATKINS
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
The One Tower @ TECOM DEWAN
The Abu Dhabi InternationalAirport Expansion -Catering South Side
ADAC
Souq Extra (Mall) - SiliconOasis, Dubai
JOHN R HARRIS
Asset Enhancement Worksin Burjman Centre - 1
SEED
Al Wasl Box Park EO
TAJ Downtown Hotel DAR / IBA
LULU Regional HQ - Dubai DAR / IBA
Bay Square @ Business Bay(12 Building & CommonBasement)
KHATIB ALAMI
G+3 GEMS WillingtonAcademy @ DSO
PJSI
Air College Al Ain - CMW-13019 - C002-02
CMW
Bawabat Al Sharq - Phase2A Buildings
AECOM
Construction of StableComplex @ Endurance Villa- Al Lissaili, Dubai
EO
Construction of ADNOCFilling Station - MotorWorld, Abu Dhabi
DORSCH
Al Falah Community - AbuDhabi (2080 Villas)
WS ATKINS
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
The One Tower @ TECOM DEWAN
The Abu Dhabi InternationalAirport Expansion -Catering South Side
ADAC
Souq Extra (Mall) - SiliconOasis, Dubai
JOHN R HARRIS
Asset Enhancement Worksin Burjman Centre - 1
SEED
Al Wasl Box Park EO
TAJ Downtown Hotel DAR / IBA
LULU Regional HQ - Dubai DAR / IBA
Bay Square @ Business Bay(12 Building & CommonBasement)
KHATIB ALAMI
G+3 GEMS WillingtonAcademy @ DSO
PJSI
Air College Al Ain - CMW-13019 - C002-02
CMW
Bawabat Al Sharq - Phase2A Buildings
AECOM
Construction of StableComplex @ Endurance Villa- Al Lissaili, Dubai
EO
Construction of ADNOCFilling Station - MotorWorld, Abu Dhabi
DORSCH
Al Falah Community - AbuDhabi (2080 Villas)
WS ATKINS
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Wild Flower - 33 VillaJumeirah Golf Estate -Dubai
Engineering ConsortiumConsulting Engineers /DAMAC
Al Raha Gardens GHD
Gourmet Tower @ MarinaMall
MEINHARDT
Zayed Military City -CMW-15069-C001
CMW
Zabeel Palace Main & WestGate
WSP
H.E.Juma Al Majid Villa @Khawaneej
Client
Construction of GYMBuilding and RelatedFacilities @ Jabel Ali Villa
Engineers Office
RAK Mall - LULU – Ras AlKhaimah
Eng.Adnan Saffrini
Zabeel II – Majlis forH.H.Sheikh Ahmed BinMohammed Al Maktoum
Engineers Office
Gulf Petrochen Project @Fujairah
Mott Mc Donald
Weatherford ManufacturingUnit – Abu Dhabi
SPEC
Fly Dubai Office @ AspionTower
Client
MBG Laboratory - Dubai Engineers Office
Lulu Hypermarket - Dibba Concept Design
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Wild Flower - 33 VillaJumeirah Golf Estate -Dubai
Engineering ConsortiumConsulting Engineers /DAMAC
Al Raha Gardens GHD
Gourmet Tower @ MarinaMall
MEINHARDT
Zayed Military City -CMW-15069-C001
CMW
Zabeel Palace Main & WestGate
WSP
H.E.Juma Al Majid Villa @Khawaneej
Client
Construction of GYMBuilding and RelatedFacilities @ Jabel Ali Villa
Engineers Office
RAK Mall - LULU – Ras AlKhaimah
Eng.Adnan Saffrini
Zabeel II – Majlis forH.H.Sheikh Ahmed BinMohammed Al Maktoum
Engineers Office
Gulf Petrochen Project @Fujairah
Mott Mc Donald
Weatherford ManufacturingUnit – Abu Dhabi
SPEC
Fly Dubai Office @ AspionTower
Client
MBG Laboratory - Dubai Engineers Office
Lulu Hypermarket - Dibba Concept Design
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Wild Flower - 33 VillaJumeirah Golf Estate -Dubai
Engineering ConsortiumConsulting Engineers /DAMAC
Al Raha Gardens GHD
Gourmet Tower @ MarinaMall
MEINHARDT
Zayed Military City -CMW-15069-C001
CMW
Zabeel Palace Main & WestGate
WSP
H.E.Juma Al Majid Villa @Khawaneej
Client
Construction of GYMBuilding and RelatedFacilities @ Jabel Ali Villa
Engineers Office
RAK Mall - LULU – Ras AlKhaimah
Eng.Adnan Saffrini
Zabeel II – Majlis forH.H.Sheikh Ahmed BinMohammed Al Maktoum
Engineers Office
Gulf Petrochen Project @Fujairah
Mott Mc Donald
Weatherford ManufacturingUnit – Abu Dhabi
SPEC
Fly Dubai Office @ AspionTower
Client
MBG Laboratory - Dubai Engineers Office
Lulu Hypermarket - Dibba Concept Design
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
German Hospital – AbuDhabi
CLIENT
Gulf PharmaceuticalIndustries L.L.C
Gulf Pharmaceutical
Abu Dhabi Business Hub RAMAHI ENGG.
New Machinery &Component RepairWorkshop – ICAD-3
SPEC
ADMM F1 Driving SchoolRefurbishment Works
Clarke Samadhin
Mosque @ Jumeirah MERAAS
Commercial Development -Sector ME-9 / Plot No. 157
ADCP
Construction of HorseStable and Horse RacingTrack @ NAS
Engineers Office
Commercial Development -Salim Ahmed Ali Al Ghuss
ADCP
DADNA Farm Palace -Fujairah
Engineers Office
Beacon Education Schoolsat Al Raha Gardens
ATKINS
G + 3 GEMS WillongtonAcademy @ DSO
PJSI
Burj Dubai Development,Old Town
MACE
Commercial Development –Plot No. C-62, ME-10
ADCP
Rotana Hotel RefurbishmentWorks - SZR, Dubai
Al Manar
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
German Hospital – AbuDhabi
CLIENT
Gulf PharmaceuticalIndustries L.L.C
Gulf Pharmaceutical
Abu Dhabi Business Hub RAMAHI ENGG.
New Machinery &Component RepairWorkshop – ICAD-3
SPEC
ADMM F1 Driving SchoolRefurbishment Works
Clarke Samadhin
Mosque @ Jumeirah MERAAS
Commercial Development -Sector ME-9 / Plot No. 157
ADCP
Construction of HorseStable and Horse RacingTrack @ NAS
Engineers Office
Commercial Development -Salim Ahmed Ali Al Ghuss
ADCP
DADNA Farm Palace -Fujairah
Engineers Office
Beacon Education Schoolsat Al Raha Gardens
ATKINS
G + 3 GEMS WillongtonAcademy @ DSO
PJSI
Burj Dubai Development,Old Town
MACE
Commercial Development –Plot No. C-62, ME-10
ADCP
Rotana Hotel RefurbishmentWorks - SZR, Dubai
Al Manar
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
German Hospital – AbuDhabi
CLIENT
Gulf PharmaceuticalIndustries L.L.C
Gulf Pharmaceutical
Abu Dhabi Business Hub RAMAHI ENGG.
New Machinery &Component RepairWorkshop – ICAD-3
SPEC
ADMM F1 Driving SchoolRefurbishment Works
Clarke Samadhin
Mosque @ Jumeirah MERAAS
Commercial Development -Sector ME-9 / Plot No. 157
ADCP
Construction of HorseStable and Horse RacingTrack @ NAS
Engineers Office
Commercial Development -Salim Ahmed Ali Al Ghuss
ADCP
DADNA Farm Palace -Fujairah
Engineers Office
Beacon Education Schoolsat Al Raha Gardens
ATKINS
G + 3 GEMS WillongtonAcademy @ DSO
PJSI
Burj Dubai Development,Old Town
MACE
Commercial Development –Plot No. C-62, ME-10
ADCP
Rotana Hotel RefurbishmentWorks - SZR, Dubai
Al Manar
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Shamma School @ Al Ain UPA
G + 2 School @ Baniyas NEBPackage (01) Al QadisiyyaSchool - Type B
The Kindergarten Starters(G+2)
Arkiplan
Al Shafar Office @Business Bay
Holford Associates
Package (01) Al QadisiyyaSchool - Type B
UPA
Villa for Mr.Abdullah AlHabbai @ Al Khawaneej 1st
Engineers Office
Pullman Intl. Hotel – FirstFloor @ DCC - Dubai
WATERMAN
Hilton JBR Project - StairCase Pressurization System
Bureau Veritas
Villa for Mr.AhmadFalaknaz @ Al Saffa
Client
Safeer Mall - Fujairah Consultair
Mr.Hamad Al GhurairResidential Villa – AlKhawaneej
Client
Commercial Development –Plot No. C-62, ME-10
ADCP
Rasas Al Mansoory Bidg. –M10, Plot No. 54, Musaffah
GERMAN MERIT
Ericcson office @ Jabel AliDown Town
Client
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Shamma School @ Al Ain UPA
G + 2 School @ Baniyas NEBPackage (01) Al QadisiyyaSchool - Type B
The Kindergarten Starters(G+2)
Arkiplan
Al Shafar Office @Business Bay
Holford Associates
Package (01) Al QadisiyyaSchool - Type B
UPA
Villa for Mr.Abdullah AlHabbai @ Al Khawaneej 1st
Engineers Office
Pullman Intl. Hotel – FirstFloor @ DCC - Dubai
WATERMAN
Hilton JBR Project - StairCase Pressurization System
Bureau Veritas
Villa for Mr.AhmadFalaknaz @ Al Saffa
Client
Safeer Mall - Fujairah Consultair
Mr.Hamad Al GhurairResidential Villa – AlKhawaneej
Client
Commercial Development –Plot No. C-62, ME-10
ADCP
Rasas Al Mansoory Bidg. –M10, Plot No. 54, Musaffah
GERMAN MERIT
Ericcson office @ Jabel AliDown Town
Client
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Shamma School @ Al Ain UPA
G + 2 School @ Baniyas NEBPackage (01) Al QadisiyyaSchool - Type B
The Kindergarten Starters(G+2)
Arkiplan
Al Shafar Office @Business Bay
Holford Associates
Package (01) Al QadisiyyaSchool - Type B
UPA
Villa for Mr.Abdullah AlHabbai @ Al Khawaneej 1st
Engineers Office
Pullman Intl. Hotel – FirstFloor @ DCC - Dubai
WATERMAN
Hilton JBR Project - StairCase Pressurization System
Bureau Veritas
Villa for Mr.AhmadFalaknaz @ Al Saffa
Client
Safeer Mall - Fujairah Consultair
Mr.Hamad Al GhurairResidential Villa – AlKhawaneej
Client
Commercial Development –Plot No. C-62, ME-10
ADCP
Rasas Al Mansoory Bidg. –M10, Plot No. 54, Musaffah
GERMAN MERIT
Ericcson office @ Jabel AliDown Town
Client
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Bright Point Hospital - AbuDhabi
STH Society
B+G+2+R Commercial andResidential Building
LECASSA
Safa Hyper Market - Al Ain AEC
American College ofCreative Science - Phase 3
Consultair
Dubai Festival City Mall -CHW
Client
General Authority of IslamicAffairs & Endowment - AlAin
KEO / GRANADA
G +1 Villa @ Jumeirah Engineers Office
Byrne Office andWarehouse
Client
SAFA Villa Extension-2 @Al Safa
Engineers Office
Al Tayer Motors L.L.C -SZR
CLIENT
Vasan Eye Care CLIENT
Islamic Affairs Commercial,Administration Building -Al Ain
KEO / GRANADA
G+3 LabourAccommodation @ JebelAli Industrial Area
CLIENT
Princess Tower KEO
SAFA Villa Extension-2 @Al Safa
Engineers Office
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Bright Point Hospital - AbuDhabi
STH Society
B+G+2+R Commercial andResidential Building
LECASSA
Safa Hyper Market - Al Ain AEC
American College ofCreative Science - Phase 3
Consultair
Dubai Festival City Mall -CHW
Client
General Authority of IslamicAffairs & Endowment - AlAin
KEO / GRANADA
G +1 Villa @ Jumeirah Engineers Office
Byrne Office andWarehouse
Client
SAFA Villa Extension-2 @Al Safa
Engineers Office
Al Tayer Motors L.L.C -SZR
CLIENT
Vasan Eye Care CLIENT
Islamic Affairs Commercial,Administration Building -Al Ain
KEO / GRANADA
G+3 LabourAccommodation @ JebelAli Industrial Area
CLIENT
Princess Tower KEO
SAFA Villa Extension-2 @Al Safa
Engineers Office
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Bright Point Hospital - AbuDhabi
STH Society
B+G+2+R Commercial andResidential Building
LECASSA
Safa Hyper Market - Al Ain AEC
American College ofCreative Science - Phase 3
Consultair
Dubai Festival City Mall -CHW
Client
General Authority of IslamicAffairs & Endowment - AlAin
KEO / GRANADA
G +1 Villa @ Jumeirah Engineers Office
Byrne Office andWarehouse
Client
SAFA Villa Extension-2 @Al Safa
Engineers Office
Al Tayer Motors L.L.C -SZR
CLIENT
Vasan Eye Care CLIENT
Islamic Affairs Commercial,Administration Building -Al Ain
KEO / GRANADA
G+3 LabourAccommodation @ JebelAli Industrial Area
CLIENT
Princess Tower KEO
SAFA Villa Extension-2 @Al Safa
Engineers Office
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Princess Haya Office @Dubai Health Care City
Engineers Office
Pullman Hotel AdditionalWorks - Pullman Hotel,MOE
NOR
Carrefour Market @ AlGhurair Centre
J.M.REGNAULT &PARTNERS
Lakhani Villa @ EmiratesHills
Al Saraya
ENOC 104-2 ENOC
MAF Policlinic @ DeiraCity Centre
Client
Zoom @ Souk Al Bahar ENOC
Zoom @ Al Raffa - Dubai ENOC
Zoom Market @ BusinessBay
ENOC
Zoom Market @ JLT ENOC
Gems United Indian School,Block 1 @ Baniyas
NEB
Business Park Building -First Floor, Phase 2,3&4 -Dubai World Central
DWC
Business Park Building(A12) @ DWC
DWC
Halcrow Office – AbuDhabi
HALCROW
33/11 kV Substations atTaweelah (101-1& 101-2)
ADDC
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Princess Haya Office @Dubai Health Care City
Engineers Office
Pullman Hotel AdditionalWorks - Pullman Hotel,MOE
NOR
Carrefour Market @ AlGhurair Centre
J.M.REGNAULT &PARTNERS
Lakhani Villa @ EmiratesHills
Al Saraya
ENOC 104-2 ENOC
MAF Policlinic @ DeiraCity Centre
Client
Zoom @ Souk Al Bahar ENOC
Zoom @ Al Raffa - Dubai ENOC
Zoom Market @ BusinessBay
ENOC
Zoom Market @ JLT ENOC
Gems United Indian School,Block 1 @ Baniyas
NEB
Business Park Building -First Floor, Phase 2,3&4 -Dubai World Central
DWC
Business Park Building(A12) @ DWC
DWC
Halcrow Office – AbuDhabi
HALCROW
33/11 kV Substations atTaweelah (101-1& 101-2)
ADDC
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Princess Haya Office @Dubai Health Care City
Engineers Office
Pullman Hotel AdditionalWorks - Pullman Hotel,MOE
NOR
Carrefour Market @ AlGhurair Centre
J.M.REGNAULT &PARTNERS
Lakhani Villa @ EmiratesHills
Al Saraya
ENOC 104-2 ENOC
MAF Policlinic @ DeiraCity Centre
Client
Zoom @ Souk Al Bahar ENOC
Zoom @ Al Raffa - Dubai ENOC
Zoom Market @ BusinessBay
ENOC
Zoom Market @ JLT ENOC
Gems United Indian School,Block 1 @ Baniyas
NEB
Business Park Building -First Floor, Phase 2,3&4 -Dubai World Central
DWC
Business Park Building(A12) @ DWC
DWC
Halcrow Office – AbuDhabi
HALCROW
33/11 kV Substations atTaweelah (101-1& 101-2)
ADDC
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
33/11 kV Substations atTaweelah (101-3)
ADDC
33/11 kV Substations atICAD Residential City
P..B.POWER / ADDC
33/11 kV Substations at AlAin (Contract no. A-39001)
ADDC
132/33 Kv DEWASubstation @ Mushrif,Dubai
DEWA
132/33 Kv DEWASubstation @ Campus,Dubai
DEWA
132/33 Kv DEWASubstation @ Perl Jumeira,Dubai
DEWA
DEWA Substation @Business Bay Creek Village,Dubai
DEWA
DEWA Substation @ Arjan,Dubai
DEWA
DEWA Substation @ CanalBridge, Dubai
DEWA
DEWA Substation@Wellness Village, Dubai
DEWA
DEWA Substation @ DohaRoad, Dubai
DEWA
DEWA Substation @Theme Park, Dubai
DEWA
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
33/11 kV Substations atTaweelah (101-3)
ADDC
33/11 kV Substations atICAD Residential City
P..B.POWER / ADDC
33/11 kV Substations at AlAin (Contract no. A-39001)
ADDC
132/33 Kv DEWASubstation @ Mushrif,Dubai
DEWA
132/33 Kv DEWASubstation @ Campus,Dubai
DEWA
132/33 Kv DEWASubstation @ Perl Jumeira,Dubai
DEWA
DEWA Substation @Business Bay Creek Village,Dubai
DEWA
DEWA Substation @ Arjan,Dubai
DEWA
DEWA Substation @ CanalBridge, Dubai
DEWA
DEWA Substation@Wellness Village, Dubai
DEWA
DEWA Substation @ DohaRoad, Dubai
DEWA
DEWA Substation @Theme Park, Dubai
DEWA
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
33/11 kV Substations atTaweelah (101-3)
ADDC
33/11 kV Substations atICAD Residential City
P..B.POWER / ADDC
33/11 kV Substations at AlAin (Contract no. A-39001)
ADDC
132/33 Kv DEWASubstation @ Mushrif,Dubai
DEWA
132/33 Kv DEWASubstation @ Campus,Dubai
DEWA
132/33 Kv DEWASubstation @ Perl Jumeira,Dubai
DEWA
DEWA Substation @Business Bay Creek Village,Dubai
DEWA
DEWA Substation @ Arjan,Dubai
DEWA
DEWA Substation @ CanalBridge, Dubai
DEWA
DEWA Substation@Wellness Village, Dubai
DEWA
DEWA Substation @ DohaRoad, Dubai
DEWA
DEWA Substation @Theme Park, Dubai
DEWA
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
132/11 kV Substation @Culture Village - Dubai
DEWA
33/11 kV PrimarySubstation @ Sorouh AlGhadeer
P..B.POWER / ADDC
FEWA Substation - 33/11kV Dhaid Substation
FEWA
FEWA Substation - 33/11kV Hospital Substation inU.A.Q
FEWA
FEWA Substation - 33/11kV Waterfront Substation inUAQ
FEWA
FEWA Substation - 33/11kV Qidfa Substation inFujairah
FEWA
FEWA Substation - 33/11kV AASMAH Substation
FEWA Substation - 33/11kV Corniche Substation inFujairah
FEWA
FEWA
FEWA Substation - 33/11kV IDHEN Substation
FEWA
FEWA Substation - 33/11kV R.A.K Main Substation -
FEWA
Zayed Military City – AlMaqta Project (Sites 1559,1536 & 1649)
KN PARTNERS
CMW-11006-C002 - AlHamra, Western Region
CMW
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
132/11 kV Substation @Culture Village - Dubai
DEWA
33/11 kV PrimarySubstation @ Sorouh AlGhadeer
P..B.POWER / ADDC
FEWA Substation - 33/11kV Dhaid Substation
FEWA
FEWA Substation - 33/11kV Hospital Substation inU.A.Q
FEWA
FEWA Substation - 33/11kV Waterfront Substation inUAQ
FEWA
FEWA Substation - 33/11kV Qidfa Substation inFujairah
FEWA
FEWA Substation - 33/11kV AASMAH Substation
FEWA Substation - 33/11kV Corniche Substation inFujairah
FEWA
FEWA
FEWA Substation - 33/11kV IDHEN Substation
FEWA
FEWA Substation - 33/11kV R.A.K Main Substation -
FEWA
Zayed Military City – AlMaqta Project (Sites 1559,1536 & 1649)
KN PARTNERS
CMW-11006-C002 - AlHamra, Western Region
CMW
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
132/11 kV Substation @Culture Village - Dubai
DEWA
33/11 kV PrimarySubstation @ Sorouh AlGhadeer
P..B.POWER / ADDC
FEWA Substation - 33/11kV Dhaid Substation
FEWA
FEWA Substation - 33/11kV Hospital Substation inU.A.Q
FEWA
FEWA Substation - 33/11kV Waterfront Substation inUAQ
FEWA
FEWA Substation - 33/11kV Qidfa Substation inFujairah
FEWA
FEWA Substation - 33/11kV AASMAH Substation
FEWA Substation - 33/11kV Corniche Substation inFujairah
FEWA
FEWA
FEWA Substation - 33/11kV IDHEN Substation
FEWA
FEWA Substation - 33/11kV R.A.K Main Substation -
FEWA
Zayed Military City – AlMaqta Project (Sites 1559,1536 & 1649)
KN PARTNERS
CMW-11006-C002 - AlHamra, Western Region
CMW
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Military Works No.233/2010 – Al Ain
CMW
Zayed Military City – Camp51
CMW
Zayed Military City – JEWCBuilding
CMW
Zayed Military City – AlMaqta Project
KN PARTNERS
Military Facilities @Maleha, Sharjah J608
CMW
Constructions at Camp No.121516, CMW-13048-C001
CMW
Contract No. CMW-11041-C 004
CMW
Construction of SimulatorBuilding @ Mahawi
CMW
Construction of Car Storesand Car Wash Chamber @Mahawi
CMW
Construction of DifferentFacilities @ Sih HefairPhase
Al Torath
Maintenance Hanger &ATC Tower
CMW
Zayed II Military College,Building 1A&1B
CMW
Construction of Al QassimiADNOC Filling Station -Sharjah
Al Burj EngineeringConsultants
Construction of Al Kutbi Al Burj Engineering
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Military Works No.233/2010 – Al Ain
CMW
Zayed Military City – Camp51
CMW
Zayed Military City – JEWCBuilding
CMW
Zayed Military City – AlMaqta Project
KN PARTNERS
Military Facilities @Maleha, Sharjah J608
CMW
Constructions at Camp No.121516, CMW-13048-C001
CMW
Contract No. CMW-11041-C 004
CMW
Construction of SimulatorBuilding @ Mahawi
CMW
Construction of Car Storesand Car Wash Chamber @Mahawi
CMW
Construction of DifferentFacilities @ Sih HefairPhase
Al Torath
Maintenance Hanger &ATC Tower
CMW
Zayed II Military College,Building 1A&1B
CMW
Construction of Al QassimiADNOC Filling Station -Sharjah
Al Burj EngineeringConsultants
Construction of Al Kutbi Al Burj Engineering
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
Military Works No.233/2010 – Al Ain
CMW
Zayed Military City – Camp51
CMW
Zayed Military City – JEWCBuilding
CMW
Zayed Military City – AlMaqta Project
KN PARTNERS
Military Facilities @Maleha, Sharjah J608
CMW
Constructions at Camp No.121516, CMW-13048-C001
CMW
Contract No. CMW-11041-C 004
CMW
Construction of SimulatorBuilding @ Mahawi
CMW
Construction of Car Storesand Car Wash Chamber @Mahawi
CMW
Construction of DifferentFacilities @ Sih HefairPhase
Al Torath
Maintenance Hanger &ATC Tower
CMW
Zayed II Military College,Building 1A&1B
CMW
Construction of Al QassimiADNOC Filling Station -Sharjah
Al Burj EngineeringConsultants
Construction of Al Kutbi Al Burj Engineering
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
ADNOC Filling Station -Sharjah
Consultants
Construction of ADNOCService Station - Ajman
Al Burj EngineeringConsultants
Construction of ADNOCService Station - Mushrif,Abu Dhabi
Al Thorath EngineeringConsultants
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
ADNOC Filling Station -Sharjah
Consultants
Construction of ADNOCService Station - Ajman
Al Burj EngineeringConsultants
Construction of ADNOCService Station - Mushrif,Abu Dhabi
Al Thorath EngineeringConsultants
LIST OF PROJECTS
PROJECT NAME CONSULTANT / CLIENT
ADNOC Filling Station -Sharjah
Consultants
Construction of ADNOCService Station - Ajman
Al Burj EngineeringConsultants
Construction of ADNOCService Station - Mushrif,Abu Dhabi
Al Thorath EngineeringConsultants