![Page 1: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/1.jpg)
Stakeholder workshop
August 11 2020
![Page 2: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/2.jpg)
1
12:45 PM – 01:00 PMNext StepsDiscussion of process for receiving comments, key dates, etc.
11:20 AM – 12:45 PMSystem Hardening for Electric Utility ResiliencyJohn Mader, Wildfire Safety Advisory Board
11:10 AM – 11:20 AMBreak
10:30 AM – 11:10 AMComments Regarding Wildfire Mitigation Plan Guidance and MetricsRespondents:Katy Morsony, The Utility Reform NetworkJoseph Mitchell, Mussey Grade Road AllianceHenry Burton, California Public Advocates OfficeTyson Swetek, Wildfire Mitigation Program Manager for SDG&EStakeholder comments will be read from Webex “chat box,” time permitting
09:45 AM – 10:30 AMWildfire Mitigation Plan Guidance and MetricsArthur O’Donnell, Wildfire Safety Division
09:30 AM – 09:45 AMIntroduction and Opening RemarksIntroductions, preview of issues to address, and timelines for action
Adjourn 01:00 PM
Participants must call-in to access
audio800-857-1917
Passcode: 3827548
Wildfire Safety Division
August 11, 2020Day 1 Agenda
![Page 3: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/3.jpg)
2
Introductions
![Page 4: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/4.jpg)
3
Objectives for today
• Share 2021 WMP cycle timeline
• Share WMP guidelines and metrics revisions, and discuss feedback
• Review WSAB SHEUR threshold
• Share next steps for metrics4
2
3
1
![Page 5: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/5.jpg)
4
2021 WMP Timeline
August 26, 2020 – deadline to submit comments to WSD
October 31, 2020 – WSD submits WMP recommendations to CPUC
December 1, 2020 – CPUC considers WMP updates
![Page 6: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/6.jpg)
5
Wildfire Mitigation Plan Guidance and MetricsArthur O'Donnell, Wildfire Safety Division
![Page 7: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/7.jpg)
6
The 2021 WMP guideline updates address 3 key changes
Increased standardization
Improved structure
Updated metrics & data
To address while minimizing additional lift for all stakeholders
![Page 8: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/8.jpg)
7
Final recommendations will incorporate input from a variety of stakeholders:
• WSAB Recommendations2
• Utilities and outside stakeholders3
• Public comment – including Jan 20204
• Other outside agencies5
• Lessons learned from 2020 WMP review1
![Page 9: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/9.jpg)
8
DRAFT MATERIAL – WORK IN PROGRESS
Standardized data across utilities
Ratepayer impact metrics
Consistent & transparent submissions
Goals vs objectives vs targets
Local outcome & outreach metrics
Citing state & federal rules
Separate PSPS section
IOU training practices & worker quals
IOU contact info, expert quals & citations
All recommendations considered – Nine prioritized for 2021
9
8
7
6
5
4
3
2
1
![Page 10: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/10.jpg)
9
Recommendation 1: Standardized data across utilitiesData taxonomy & schema to ensure 1. Consistent formatting 2. Streamlined reporting3. Cross-utility comparison
![Page 11: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/11.jpg)
10
Recommendation 2: Consistent & transparent submissions1. Consistent format to track progress
2. WMP completeness checklist
3. Quarterly data submissions tied to annual WMP update
![Page 12: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/12.jpg)
11
Recommendation 3: Local outcome & outreach metricsHigher spatial granularity for:1. PSPS & wildfire metrics (see D.20-
05-051)2. Community outreach metrics (see
D.20-03-004)3. Initiative data
![Page 13: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/13.jpg)
12
Recommendation 4: Ratepayer impact metrics1. Separate control (i.e., ongoing)
initiatives from those started in WMP cycle
2. Report impact to ratepayers from new initiatives & expansions to controls
![Page 14: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/14.jpg)
13
Recommendation 5: Goals vs. objectives vs. targets
Goal – All utilities aligned with WSD goal
Objectives – Utility-specific "milestones"
Program targets – Metrics to track progress
![Page 15: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/15.jpg)
14
Recommendation 6: Citing state and federal rules
Each WMP program's narrative includes:1. State and federal rules associated2. State and federal proceedings
associated
![Page 16: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/16.jpg)
15
Recommendation 7: IOU training practices & worker qualificationsIOUs required to disclose:1. Current training practices2. Gaps in wildfire mitigation expertise3. Plans to fill gaps
![Page 17: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/17.jpg)
16
Recommendation 8: IOU contact info, expert quals & citationsIOUs required to report:1. Contact info for people executing WMP
[redacted]2. Credentials of experts referenced [in
appendix]3. Citations to research referenced [in
appendix]
![Page 18: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/18.jpg)
17
Recommendation 9: Separate PSPS section
1. New section specific to PSPS
2. PSPS reporting requirements consolidated
3. Additional PSPS reporting required
![Page 19: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/19.jpg)
18
Upcoming dates
August 26, 2020Deadline to share your comments for consideration by the WSD• 20 page limit• Please email comments to
[email protected] and to service list 18-10-007
October 31, 2020WSD submits WMP guideline and SCA process recommendations to CPUC
December 1, 2020Statutory deadline for Commission consideration of WMP guideline and SCA process updates
![Page 20: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/20.jpg)
19
Comments regarding WMPGuidance and MetricsKaty Morsony, The Utility Reform NetworkJoseph Mitchell, Mussey Grade Road AllianceHenry Burton, California Public Advocates OfficeUtility Representative TBD
![Page 21: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/21.jpg)
20
Break
![Page 22: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/22.jpg)
21
System Hardening for Electric Utility ResiliencyJohn Mader, Wildfire Safety Advisory Board
![Page 23: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/23.jpg)
22
Next Steps
![Page 24: Stakeholder workshop...Stakeholder workshop August 112020. 1 Next Steps 12:45 PM – 01:00 PM. Discussion of process for receiving comments, key dates, etc. ... •Share 2021 WMP cycle](https://reader034.vdocuments.site/reader034/viewer/2022051806/6001b774607383441459a021/html5/thumbnails/24.jpg)
23
Upcoming dates
August 26, 2020Deadline to share your comments for consideration by the WSD• 20 page limit• Please email comments to
[email protected] and to service list 18-10-007
October 31, 2020WSD submits WMP guideline and SCA process recommendations to CPUC
December 1, 2020Statutory deadline for Commission consideration of WMP guideline and SCA process updates