staff college, kalkere post, bannerghatta road, bengaluru ... · staff college, kalkere post,...

163
Staff College, Kalkere Post, Bannerghatta Road, Bengaluru – 560 083 TENDER NOTICE FOR PROPOSAL FOR SUPPLY, TESTING, INSTALLATION AND COMMISSIONING OF 1 NO. 200 KVA DIESEL GENERATOR AT UNION BANK OF INDIA, STAFF COLLEGE, BENGALURU-560 083 Union Bank of India invites sealed tenders in bid systems for the proposed work of supply, Testing, Installation and Commissioning of 1 No. 200 KVA Diesel generator at Union Bank of India, Staff College, Bengaluru-560083. The estimated cost of work is Rs.25,95,000/-. The detailed information regarding, eligibility norms and tender document shall be available during aforesaid period at the Bank‟s website www.unionbankofindia.comandwww.govtenders.nic.in. The last date for submission of tender is 22 nd October 2018 till 15.00 hrs. ASST.GENERAL MANAGER REF NO:UBI:RFP:08:2018 DATE: 01-10-2018 1 SIGN & SEAL OF CONTRACTOR

Upload: others

Post on 19-Mar-2020

25 views

Category:

Documents


0 download

TRANSCRIPT

Staff College, Kalkere Post, Bannerghatta Road, Bengaluru – 560 083

TENDER NOTICE FOR PROPOSAL FOR SUPPLY, TESTING, INSTALLATION AND COMMISSIONING OF 1 NO.

200 KVA DIESEL GENERATOR AT UNION BANK OF INDIA,

STAFF COLLEGE, BENGALURU-560 083

Union Bank of India invites sealed tenders in bid systems for the proposed work

of supply, Testing, Installation and Commissioning of 1 No. 200 KVA Diesel

generator at Union Bank of India, Staff College, Bengaluru-560083. The

estimated cost of work is Rs.25,95,000/-. The detailed information regarding,

eligibility norms and tender document shall be available during aforesaid period at

the Bank‟s website www.unionbankofindia.comandwww.govtenders.nic.in.

The last date for submission of tender is 22nd October 2018 till 15.00 hrs.

ASST.GENERAL MANAGER

REF NO:UBI:RFP:08:2018 DATE: 01-10-2018

1

SIGN & SEAL OF CONTRACTOR

Staff College, Kalkere Post, Bannerghatta Road, Bengaluru – 560 083

TENDER ENQUIRY FOR 1 NO 200 KVA DIESEL GENERATOR

TENDER PROPOSAL FOR SUPPLY, TESTING, INSTALLATION AND COMMISSIONING OF 1 NO. 200 KVA

DIESEL GENERATOR ATUNION BANK OF INDIA, STAFF COLLEGE, BG ROAD, BENGALURU-560 083.

GENERAL TERMS AND CONDITIONS

SPECIAL CONDITIONS OF CONTRACT &

TECHNICAL SPECIFICATIONS

OWNER:

UNION BANK OF INDIA,

STAFF COLLEGE,

BANNERGHATTA ROAD,

KALKERE POST,

BENGALURU-560 083

Phone Number: 080-22639001

080-22639006 080-22639020 080-22639050

Email id: [email protected] [email protected]

[email protected]@unionbankofindia.com

[email protected]

2

SIGN & SEAL OF CONTRACTOR

INDEX

Sr.No. Contents Page No.

1. NOTICE FOR INVITING TENDER 5

2. PREFACE 7

3. INSTRUCTIONS WITH REGARD TO SUBMISSION 9

OF TENDERS

4. DECLARATION 12

5. TENDER FORM 13

6. SUPPLEMENTARY CONDITION 16

7. INDEMNITY BOND 17

8. ARTICLES OF AGREEMENT 18

9. GENERAL INSTRUCTIONS TO CONTRACTORS AND 37

SPECIAL CONDITIONS

10. THE CONDITIONS HEREINBEFORE REFERRED TO 43

11. APPENDIX / MEMORANDUM TO CONDITION OF 81

CONTRACT

12. SAFETY CODE 82

13. APPROVED LIST OF MATERIALS. 88

14. TECHNICL SPECIFICATIONS 89

15. PRICE BID 155

3

SIGN & SEAL OF CONTRACTOR

ELIGIBILITY CRITERIA SL.NO CRITERIA DOCUMENTS REQUIRED 1 The vendor should have completed minimum

of 5 supply and Installation of Diesel Generators each contract value of Rs. And above in the last 3 years.

Work or der and Completion certificates from the concerned clients.

2 The vendor must have GST registration number and PAN number

Copies of the registration certificate and PAN card copy hall be enclosed.

3 RFP document should contain application fee of Rs.500/- and EMD amount of Rs.26,000/-

Demand draft / PO and drawn in favor of Union Bank of India payable at Bengaluru.

4

SIGN & SEAL OF CONTRACTOR

1. NOTICE INVITING TENDER

To

M/s________________________________

________________________________

________________________________

Dear Sir,

Sub: TENDER PROPOSAL FOR SUPPLY, TESTING, INSTALLATION AND COMMISSIONING OF 1

NO. 200 KVA DIESEL GENERATOR ATUNION BANK OF INDIA, STAFF COLLEGE,BG ROAD, BENGALURU-560 083.

Sealed, item rate, tenders are invited in the prescribed format from vendors carrying out

supply, Installation and Commissioning of 1 No. 200 KVA Diesel Generator at Union Bank of

India, Staff College, Bengaluru as per following details:

Name of the work

: Tender Proposal for Supply, Installation, Testing and

Commission of 1 No. 200 KVA Diesel Generator at

Union Bank of India, Staff College, Bengaluru-

560 083.

Estimated Cost of the Work : 25,95,000/-

Earnest Money Deposit : 26,000/- by Demand Draft /PO and drawn in Favor of

Union Bank of India payable at Bengaluru.

Period of completion : 10 Weeks

Validity of Tender : 120 DAYS

Date of Issue of Tender :

From 01.10.2018

Last Date for submission of Tender :22nd

October 2018 up to 3.00 PM

Date & Time of opening of : 22nd

October 2018 at 3.30 PM

Technical Bid

Date & Time of Pre-bid Meeting

:10th

October 2018 at 11.00 AM

5

SIGN & SEAL OF CONTRACTOR

1) The tender document can be obtained from the office of the. Chief Manager ,Union Bank of India, Staff College,Bannerghatta road, kalkere post,Bengaluru-560 083, on paymentof Rs.500/- (non-refundable) in form of Payorder / Demand draft in favour of Union Bank of India payable at Bengaluru and should be submitted in original, duly stamped, and sealed and drop in the tender box at the following address:-

Union Bank of India, Staff College, Bannerghatta road, Kalkere post, Bengaluru-560 083.

2) The item rates under the contract include for full, final & entire completion of all works in

all respects described in contract & as shown in drawings forming part of the contract.

Contractor must quote item rates for all the items of work. Tenders will be opened in the

presence of contracting agencies or their authorized representatives.

3) The sealed envelope should contain tender comprising Technical Bid and price bid in

separate envelopes and marked as "Tender Proposal for Supply, Testing, Installation and

Commissioning of 1 No. 200 KVA Diesel Generator at UBI, Staff College, Bengaluru" and

shall contain application and necessary documents /credentials, - General conditions,

Special Conditions & Technical Specifications, EMD, Brouchers and price bid etc.

4) The tenderer must use only the tender forms issued for the purpose to fill in the rates.

Intimation of tender quoted by letter, telegrams / telex will not be acceptable.

5) Tenderers are advised not to make any alteration/modification in the tender documents,

Item of work or in any respect whatsoever. Violation of this requirement will make the

tender liable for rejection.

6) In case of postal delivery, the tenderer has to ensure that tender is reached before the due

date and time. The bank will not be responsible for damage in the transit and delay of

receipt of tender, if any or sent by a special messenger. Tender received late shall be

rejected.

7) Every page of the tender documents should be signed by the person or persons submitting

the tender in token of his/their having acquainted himself/themselves with the General

and Special Conditions of Contract, Specifications etc., as laid down. Any tender with any

of the documents not so signed will be subjected to rejection.

8) This notice inviting tenders, the conditions of tender and the duly completed form of

tender etc., will form part of the Agreement to be executed by the successful tenderer

with the bank.

9) Drawings and other information if any to be submitted with the tender

10) The Union Bank of India shall not be bound to accept the lowest tender and Reserves

the right to accept or reject any or all the tenders without assigning any reason

whatsoever.

For UNION BANK OF INDIA

ASST. GENERAL MANAGER Encl: One Set of tender documents Issue to M/s.

______________________________________________________________________________________

Date:

Signature:

6

SIGN & SEAL OF CONTRACTOR

2. PREFACE

1.1 M/s. Union Bank of India, Staff College, Bannerghatta road, Kalkere post, Bengaluru-560 083

hereinafter referred to as "Employer" or "Owner" have decided to install 1 No. 200 KVA

Diesel Generator at its Union Bank of India, Staff College, Bannerghatta road, Kalkere post,

Bengaluru-560083

Scope of Work

Scope of work covered under this tender shall be supply of the necessary equipments,

installation, erection, testing, commissioning & maintenance of 1 No. 200 KVA Diesel

Generator with the specified systems. The skilled and unskilled labours, lifting tools,

scaffoldings and tackles as well as any other material or equipments that may be required

to make installation complete in all respect, will be provided by the contractor. The actual

extent of work vis-a-vis the systems shall and include as indicated in the specifications but

not limited to following: -

Design, supply, assembly, inspection, transportation, delivery at site, of 1 No. 200 KVA

Diesel Generator for Union Bank of India, Staff College, Bannerghatta road, Kalkere post,

Bengaluru-560083 with all accessories and auxiliaries.

Brief Project Profile

i) Location of the Site:

Union Bank of India, Staff College, Bannerghatta road, Kalkere post, Bengaluru-560 083.

1.1 All decisions as to the selection of Contractor, award of Work, will be made by UnionBank of

India. The Bank reserves the right to reject one or all tenders or accept any tender without

assigning any reason.

1.2 The Project consists of Design, supply, assembly, inspection, transportation, delivery at

site, of 1 No. 200 KVA Diesel Generator at Union Bank of India, Staff College, Bannerghatta

road, Kalkere post, Bengaluru-560 083. The project is to be implemented without

hampering day to day working of the Bank. The Contractor will carry the project in phased

manner. The complete activity of Supply, Installation and Testing of 1 No. 200 KVA Diesel

generator is to be completed in the period of 10 Weeks. On award of work the successful

tenderer shall submit various documents including drawings if any for review of the Bank

and schedule (Refer Annexure IV) for submission & execution for approval.

1.3 The one who is awarded the contract will be the "Contractor".

1.4 The Contractor has to carry out his Work according to General Conditions of Contract,

Special Condition of Contract, Technical Specifications, bill of Quantities and working

drawings approved by the Bank.

1.5 The privilege of authorship and ownership of drawings and designs of the structures remain

with Union Bank of India. The drawings and designs prepared by the Contractor and

approved by the Bank shall be used only for the purpose specified in this contract and all

the drawings issued shall be returned to the Bank on Completion of the Work.

7

SIGN & SEAL OF CONTRACTOR

1.6 The Officer Incharge / Engineer / Architect authorized by Employer to represent the site of

work is authorized to ask the Contractor to discontinue any work which does not meet the

expected and or specified requirements and/or work already executed, may be rejected

and asked to be removed for the same reason.

8

SIGN & SEAL OF CONTRACTOR

3. INSTRUCTION WITH REGARD TO SUBMISSION OF TENDER

1) Rates should be quoted both in figures and words in columns specified. All erasures and

alterations made while initials of the tenderer must attest filling the tender.

Overwriting of figures is not permitted. Failure to comply with either of these

conditions will render the tender invalid and it will be the option of Union Bank of

India to accept or reject the tender. No request of any change in rate or conditions

after opening of the tender will be entertained.

2) In the case of figures, the word `Rs.' should be written before the figures of rupees and

the word `P' written after the decimal figures e.g. Rs. 3.25 P. In the case of words, the

word Rupee should similarly precede and the words "Paise only" should be written at

the end, closely following each the percentage rate. The word "only" should not be

written in the next line unless the rate quoted is in whole Rupees closely followed by

the word "only": The amount should invariably be up to two decimal places.

3) The different Schedules should be filled as follows:

(a) The “Rate" Column wherever applicable to be legibly filled in ink in both figures

and words.

(b) The "Amount" Column also to be legibly filled in ink in both figures and words.

(c) All corrections to be initialed.

(d) No over writing is allowed.

(e) The figure of percentage of rate shall be legibly filled in ink in both figure and

words.

4) Errors in the bill of quantities shall be dealt with in the following manner.

a. In the event of any discrepancy between the rates quoted in words and the rates in

figures the former shall prevail.

b. In the event of an error occurring in the amount column of the bills of quantities as

a result of the wrong extension of the unit rate and the quantity, the unit rate

shall be regarded, as firm and extension shall be amended on the basis of the

rates.

c. All the errors in totaling in the amount column and in carrying forward the totals

shall be corrected.

5) The tender shall be signed and dated at all places provided therein. Also all pages,

drawings and corrections / alterations shall be initialed. The tender submitted on

behalf of a firm shall be signed by all the partners of the firm or by an authorized

representative having power of attorney and necessary authority on behalf of the firm

to enter into the proposed contract. Otherwise the tender may be rejected by Union

Bank of India.

6) The time allowed for completion of works is 10 Weeks from the date of

commencement of the work is reckoned from the Seventh day from the date of Letter

of Intent. Time shall be considered the essence of contract.

9

SIGN & SEAL OF CONTRACTOR

7) The tender shall be accompanied by earnest money of 26,000/- (Twenty Six Thousand

rupees only) by way of Demand Draft/Pay Order only favoring UNION BANK OF INDIA,

payable at Bengaluru or Bank Guarantee of Equivalent Amount issued by a

Nationalized Bank or Scheduled commercial Bank and valid for the period of completion

of work. Tender submitted without earnest money shall be summarily rejected. The

contractor whose tender is accepted will have to deposit as initial security deposit a

further sum (Rupees 22,500/-) to make up 2% of the value of the accepted tender

including the earnest money. The initial security deposit will have to be made within

15 days from the date of acceptance of tender, failing which the Bank at his

discretion may revoke the letter of acceptance and forfeit the earnest money deposit

furnished along with the tender.

8) The Earnest Money will be retained in the case of the successful tenderer as part of the

security for due fulfillment of the Contract. No interest shall be paid on this deposit.

Failure to enter into the Contract agreement within the stipulated time of 20 days

from the date of acceptance of work order shall entail the forfeiture of the Earnest

Money Deposit. The Earnest money of unsuccessful tenderers will be released

afterissue of work order, without any interest.

9) The tenderer shall submit his tender after carefully examining the whole of the tender

document and the terms and conditions of contract, the drawings and specifications,

the schedule of quantities etc., and also after examining the site and conditions

prevailing in and around site.

10) The Bank does not bind himself to accept the lowest or any tender and reserve to

themselves the right of accepting the whole or any part of the tender and tenderer is

bound to perform the same at the rates quoted. The Bank will not be bound to accept

the lowest tender and reserves the right to accept or reject any or all the tender

without assigning any reasons whatsoever. The work may also be divided among the

contracting agencies depending on the exigencies of the bank.

11) Tenders shall remain valid for a period of 120 days from the date of opening of the

tender which period may be extended by mutual agreement and the tenderer shall not

cancel or withdraw the tender during the initial validity period of 120 days.

12) The successful tenderer shall be bound to implement the Contract and mobilize

and sign specified agreements within 20 days from the date of acceptance of

work order.

13) Tenderers must include in their rates, GST (State & Central Govt.) and any other tax

& duty or other levy by the central and state government applicable on the date of

submitting tender. Deductions in respect of income tax (TDS) or turnover levied as per

government notification and/or guidelines shall be made from the Contractor's interim

10

SIGN & SEAL OF CONTRACTOR

and final bills, and deposited with the relevant authority by the Bank, on his behalf. Any

shortfall in deposit thereof shall be made up by the contractor, before submitting his final

bill. Due to change in taxes structure by orders from Central Govt. / State Govt. after

opening of tenders shall be reimbursed to the contractor as per actual and upon verifying

the proof of having made the payment.

14) This contract shall be an item rate contract. The Contractor shall be paid for actual

quantity of work done, as measured at site including any deviation plus or minus. The rate

of any non-schedule items of work shall be decided as mentioned in the conditions of

contract.

15) The tender drawings exhibited/enclosed are preliminary drawings intended for the

guidance of the Contractor only. They may be subject to revision and alteration without

vitiating any of the terms of the contract and the Contractor shall be bound to execute the

works as shown on the final drawings without claiming any extra payment.

16) No correspondence will be entertained in respect of this tender other than any

clarifications strictly pertaining to this tender.

17) The tender price quoted by a tenderer shall be kept strictly confidential and shall not

be divulged to any other party even approximately before the time limit for delivery

of tender. The only exception be for obtaining an insurance quotation, you may give

your insurance company or agent any essential information they ask for, so long as it is

done in strict confidence. No information about other's

18) Tender price should be obtained and no arrangement with anyone else should be made

whether or not he submit the tender.

19) The employer will provide electricity & water supply.

20) Contractor should sign at the end of every page prior to submitting the tender.

21) Conditional tenders will be summarily rejected.

22) COMPLETION PERIOD OF THE PROJECT WILL BE 10 Weeks.

Progress chart linked up with completion period to be counted from 7th

day

of acceptance of work order.

For UNION BANK OF INDIA

ASST. GENERAL MANAGER

11

SIGN & SEAL OF CONTRACTOR

4. D E C L A R A T I O N

1. Having examined the drawings, general and special conditions of contract,

specifications and bill of quantities for the execution of the above-named work, we,

the undersigned, offer to execute, complete and maintain the whole of the said work

in conformity with the said drawings, conditions of contract, specification and bill of

quantities.

2. We undertake, if our tender is accepted, to commence the work within 7 days from the

date of acceptance of Letter of Intent/Work order and to complete and deliver the

whole of the work comprised in the contract within 20 weeks calculated from the last

day of the aforesaid period in which the work are to be commenced. We also

understand that some part of the work will have to be completed by us in a shorter

period as per the requirement of the Employer.

3. We are submitting the Earnest Money Deposit of Rs.26,000/- in form of Pay order/D.D

in favor of Union Bank of India payable at Bengaluru, sum not exceeding one percent

of the above named sum of the performance of the Contract. The terms of the

Guarantee shall be as approved by you.

4. We agree to abide by this tender for a period of 120 days from the date fixed for

receiving the same and it shall remain binding upon us and may be accepted at any

time before the expiration of that period.

5. Unless and until a formal agreement is prepared and executed, this tender, written

acceptance thereof together with pre-contract correspondence and modified

conditions as stated in the Letter of Intent/Work Order shall constitute a binding

contract between us.

6.

Place

Date

We understand that you are not bound to accept the lowest or any tender you may

receive and the bank has right to award/reject, the tender received.

SIGNATURE

NAME & DESIGNATION

SEAL OF ORGANISATION

12

SIGN & SEAL OF CONTRACTOR

5. TENDER FORM

(On Contractors Letter Head)

To,

The Asst.General Manger

Union Bank of India,

Staff College,BG Road,

Bengaluru-560083

Sub: TENDER PROPOSAL FOR SUPPLY, TESTING, INSTALLATION AND COMMISSIONING OF 1 NO. 200

KVA DIESEL GENERATOR ATUNION BANK OF INDIA, STAFF COLLEGE, BANNERGHATTA ROAD, KALKERE POST, BENGALURU-83

Sir,

1. We have read and examined the following documents as received by us:

a) Notice Inviting Tender.

b) Instructions to Tenderers.

c) Conditions of Contract.

d) Supplementary Conditions.

e) Specifications.

f) Drawings.

g) Schedule of Quantities.

h) Addition condition of contract.

2. We are well aware and familiar with CPWD, Schedule of Rates 2016-17 and their

specifications, CPWD Specification, BIS publication and National Building code which shall

apply to this contract to supplement any missing details in this contract in order of

preference.

3. Further to the above, we have visited and examined the site of the proposed works and

have acquired the requisite information relating thereto as affecting the tender invited by

Bank.

4. We agree that any other terms or conditions of contract or any general reservation which may

be printed on any correspondence emanating from us in connection with this tender or with any

contract resulting from this tender shall not be applicable to this tender or to the contract.

5. We have obeyed the rules about confidentiality of tenders and will continue to do

so as long as they apply.

13

SIGN & SEAL OF CONTRACTOR

6. We are enclosing along with our tender an earnest money of Rs.26,000/-(Rupees

TwentySix thousand ONLY)favoring Union Bank of India, payable at BENGALURU (Pay

Order No/BG No.------- dated ----------- drawn on ----------------------). We hereby agree that

this sum shall be forfeited by Union Bank of India in the event of our tender being accepted

and if we fail to execute the contract when called upon to do so.

7. Subject to and in accordance with paragraphs 3 & 4 above and the terms and conditions

contained or referred to in the documents listed in paragraph 1, we agree and offer to

execute all the Works referred to in the said documents upon the terms and conditions

contained or referred to therein and to carry out such deviations as may be ordered to be

valued as per the conditions of contract.

8. We undertake to complete and deliver the whole of the works within a period i.e. 10

Weeks as specified in the contract and further confirm that the time allowed for

completion is adequate. Time allowed for completion of entire job or part job assigned

shall be reckoned from the seventh day of the date of acceptance of work order. We shall

be under the obligation to pay the sum as stated in the contract for every day that the

works shall remain incomplete, damages as compensation subject to the conditions of

contract relating to extension of time.

9. We hereby agree that unless & until a formal agreement is prepared & executed in

accordance with the Articles of agreement, this tender together with your acceptance

thereof, shall constitute a binding contract between us.

10. We agree to pay initial security deposit of 2% rupees 52,000.00/-(including Earnest

Money 1%) of the contract amount by way of DD/PO in favor of UNION BANK OF INDIA,

payable at BENGALURU. This amount shall be released after virtual completion of work.

We further agree for a deduction of 8% from the running bill as retention money till

accumulating total security deposit.

11. Validity of the tender is 120 days from the date of opening of tender or it may be beyond

120 days if mutually accepted.

12. The bank is at liberty to accept or reject any tender, without assigning any reasons

whatsoever.

13. The work may be split up in the first instance as per exigencies of the bank. But it may be

split up in more parts or parts combined if so desired by the Bank without assigning any

reasons whatsoever. We will not have any claim either for loss of profit or revision in rates.

14. Adherence to the pert chart/Bar chart will be ensured by us as the project is to be

executed in a very strict time frame.

14

SIGN & SEAL OF CONTRACTOR

15. We are aware that the quantities of work indicated in the bill of quantities are

approximate, may vary to any extent, even it may be omitted; we will not have any

claim of any kind against the bank.

Signed in the capacity of duly authorized to sign tenders for and on behalf of

Address……………………………………..

Telephone No…………………………..

Telex No.

Fax No.

Date:

15

SIGN & SEAL OF CONTRACTOR

6. SUPPLEMENTARY CONDITION

INDEMNITY BOND

On the acceptance of his tender, the contractor will be required to execute an Indemnity Bond

with-in 20 days of issue of work order in favor of the bank against third party claims, civil or

criminal complaints, site mishaps and other accidents or disputes, against any damages, loss or

expenses due to or resulting from any negligence or breach of duty on the part of the

contractor, his subcontractors or his employees and agents etc., as per the appropriate

Indemnity Bond attached.

It will also be covered by labour laws of the Govt. of India and Karnataka State Laws.

Any other conditions suggested by the Bank may be added subsequently.

16

SIGN & SEAL OF CONTRACTOR

7. INDEMNITY BOND

(On Non-Judicial Stamp Paper-Rs.100)

KNOW all men by these presents that I/We

______________________________ do hereby execute Indemnity Bond in favour of the

Union Bank of India on this ____________ day of _______2018.

WHEREAS Union Bank of India, (Staff College, Bannerghatta road, Kalkere post, Bengaluru-

560083) have appointed ____________________________________

as the Contractors for their Proposed Union Bank of India Project at New Hostel Building,

Staff College, Bannerghatta road, Kalkere post, Bengaluru-560 083.

THIS DEED WITNESS AS FOLLOWS:

I/We ___________________________________________________________hereby do Indemnify and save harmless Union Bank of India, Staff college, Bannerghatta against

1. Any third-party claims, civil or criminal complaints/liabilities, site mishaps and other accidents or disputes and/or damages occurring or arising out of any mishaps at the site due to faulty work, negligence, faulty construction and/or for violating any law, rules and regulations in force, for the time being while executing/executed works by me/us.

2. Any damages, loss or expenses due to or resulting from any negligence or breach of duty on the part of me/us or my sub contractor's if any, servants or agents.

3. Any claim by an employee of mine/ours or of sub-contractors if any, under the Workmen's Compensation Act and Owners Liability Act, 1939 or any other law, rules and regulations in force for the time being and any Acts replacing and/or amending the same or any of the same as may be in force at the time and under any law in respect of injuries to persons or property arising out of and in the course of the execution of the contract work and/or arising out of and in the course of employment of any workman/employee.

Any act or omission of mine/ours of sub-contractors if any, our/their servants or agents which may involve any loss, damage, liability, civil or criminal action.

IN WITNESS WHEREOF THE __________________________________________ has set

his/their hand on this day of _____________________ 2017.

SIGNED AND DELIVERED BY THE

NAME AND ADDRESS

AFORESAID __________________

(Contractor)

IN THE PRESENCE OF WITNESSES:

17

SIGN & SEAL OF CONTRACTOR

8. ARTICLES OF AGREEMENT

ARTICLES OF AGREEMENT made at _______ this ______day of ______ Two Thousand Eighteen.

BETWEEN

UNION BANK OF INDIA, a body corporate constituted under the Banking Companies (Transfer of

Undertakings) Act, 1970 and having its Staff College, Bannerghatta, Bengaluru hereinafter

called “the Bank” (which expression shall, unless it be repugnant to the context or meaning

thereof, include its successors and assigns) of the ONE PART

AND MESSRS _________________________, having its registered office at

________________ _______________________________________, hereinafter called the

“Contractor” (which expression shall unless repugnant to the context or meaning thereof,

include its successors and permitted assigns) of the OTHER PART.

WHEREAS

i. The Bank is desirous of Installation of 1 No. 200 KVA Diesel Generator at Union Bank of

India, Staff College, Bengaluru-560083.

ii. The Bank has already appointed and retained M/s Innovarch Architect (I) Pvt.Ltd having

its Office at #47/5, Lavelle Road, Bengaluru-560001 and Registered Office at as above

address as Architect for the Works or the Project.

iii. The Bank has caused the drawings and bills of quantities showing and describing the

Works to be done to be prepared by or under the direction of the Architects /

Architect;

iv. The Bank had invited tenders for Installation of 1 No. 200 KVA Diesel Generator at

Union Bank of India, Staff College,Bannerghatta road,Kalkere post, Bengaluru-560083

work in accordance with the general conditions of contract, special conditions of

contract, technical specifications, bills of quantities and working drawings, as prepared

by the M/s Innovarch Architect (I) Pvt.Ltd and furnished to the Contractor.

v. Having examined the general conditions of contract, special conditions of contract,

technical specifications, bills of quantities and working drawings as prepared by the

Architects / Architect, the Contractor offered to execute, complete and maintain the

whole of the Works relating to the Project in conformity with the said general

conditions of contract, special conditions of contract, technical specifications, bills of

quantities and working drawings and in accordance with instructions issued by the

Architects / Architect and the Contractor submitted its tender for the contract sum of

Rs.__________________towards the said work.

vi. The tender submitted by the Contractor was, after negotiations, modified/altered

upon the Contractor agreeing to revise the rates of certain items and further offering a

rebate for execution and completion of the Project thereby reducing the tender

amount to Rs._________________________as confirmed by its letters dated

________.

18

SIGN & SEAL OF CONTRACTOR

vii. Towards the implementation of the Project, the Contractor has supplied the Bank with

a fully priced copy of the said bills of quantities (which copy is hereinafter referred to

as “the Contract Bills”) and the

Contract Bills have been signed by or on behalf of the parties hereto:

viii. The Contractor has already agreed with the Bank to implement and execute the

Project in full on the basis of the contract documents as hereinafter defined on the

terms and conditions therein contained;

ix. The parties are now executing this Agreement setting out the basic terms of the

agreement between them for smooth implementation and execution of the Project

without any unnecessary difference or dispute.

NOW IT IS HEREBY AGREED as follows:

1. The Contract Document is comprising of

i. Tender document including technical bid (Vol.-I) and pre-bid (Vol.-II).

ii. Notice Inviting Tender issued vide letter _____________________

iii. Subsequent letters issued by the Bank

vide_____________________

iv. Clarifications submitted by the contractor vide letter dt.____________.

v. Minutes of Meeting held on _________

vi. Rebate / Discount offered by the contractor vide letter_____________

vii. Work Order issued by the Bank vide letter ___________

viii. Acceptance letter ___________ from the contractor

ix. Drawings numbering as mentioned in the Annexure 11 of the Tender document

enclosed along with the tender document.

1.a Unless the context otherwise requires the contract documents above mentioned shall be

harmoniously construed and in the chronological order.

1.b Unless otherwise expressly provided under these presents, contract documents (iii) to

(ix) above shall be construed as modifying only those general and special terms and

conditions in tender document in so far and to the extent referable to the clauses in the

said tender document.

1.c. Unless otherwise stated expressly hereunder, all the general and special terms

and conditions shall apply and binding on the contractor.

2. The Contract Document is complimentary. What is called for in any one shall be as binding as called for by all. The aforesaid shall

form integral part of contract and in the event of any inconsistency between any

provisions herein the provisions of the Contract Documents shall prevail. When any of

the General and Special Conditions are at variance, the condition stipulated in the

Special Conditions of Contract shall supercede relevant provisions in General

Conditions. For all matters not specifically provided for herein the provisions of

General and Special Conditions in the Tender Documents shall apply and the rights and

19

SIGN & SEAL OF CONTRACTOR

Liabilities of the parties shall be decided accordingly. The decision of the Bank /

Architect in this regard shall be final and binding.

3. All time limits statedin the Contract Document are of the essence of the

contractwhere the work has to be completed within 10 Weeks failing which

liquidateddamages will be recovered @ 1% of contract amount for per week of

delay subject to maximum recovery of 10% of the contract amount.

4. For the consideration hereinafter mentioned, the Contractor shall carry out and

complete the Works in conformity with the contract documents and in accordance with

the instructions issued by the Architect from time to time including all modifications

extra and additional works and obligations to be carried out either on the Site or at any

factory or work shop or any other place for subsequent incorporation as required for

the due performance of the contract.

5. The general character and the scope of the Works is illustrated and defined by

thespecifications and the bills of quantities herewith attached and by the signed

drawings. The scope includes furnishing all materials, labour, tools, equipment and

management necessary for and incidental to the construction and completion of the

Works. If the Contractor shall find any discrepancy in or divergence between the

contract drawings and/or the contract bills he shall immediately give to the Architect a

written notice specifying the discrepancy or divergence and the Architect shall issue

instructions in regard thereto which shall be complied with by the Contractor.

6. INTENT

The intention of arrangement is to secure the performance of the Contractor “obligations

to the satisfaction of the Bank / Architect / Architect. All labour, material, equipment,

constructional plant and transportation necessary for the proper execution of the

Project is to be provided by the Contractor and should only be of the approved

manufacturer/agencies respective kinds as described in the Contract Documents which

is to be subjected from time to time to such tests as the Engineer/ Architect‟s

representative may direct. In case the required material/services of approved

manufacturers/agencies are not available or are not upto the mark the Contractor shall

procure material/ services from such other manufacturer/agencies as may be approved

by the Architect / Bank and the Contractor shall submit rate analysis for such material.

7. EXTENT

The Contractor shall carry out and complete the Works in every respect in accordance

with this contract and with the directions of and to the reasonable satisfaction of the

Architect. The Architect may in their absolute discretion and from time to time issue

further drawings, details and/or written instructions and written explanations whole of

which are collectively referred to as Architects‟ instructions. All such drawings and

instructions shall be consistent with the Contract Document true developments thereof

as reasonably inferable there from.

8. TYPE OF CONTRACT

The Contract is an item rate contract. The Contractor shall be paid for the actual

quantity of Work done, as measured at Site, at the rates quoted by him in the Contract

Bills. The contractor has

20

SIGN & SEAL OF CONTRACTOR

i. Been informed that the schedule of approximate quantities is liable to alteration by

omission, deduction, substitution or additions at the discretion of the Architect/Bank

without affecting the terms of the contract and no compensation to Contractor.

ii. Fully and correctly understood the meaning of all the tender documents, the General

Conditions of Contract, Special Condition of Contract, Technical Specifications, Bill of

Quantities and working drawings or part thereof.

9. CONTRACTORS COVENANTS

i. The Tender form conditions, priced schedule of quantities, contract drawings and

General and Special Conditions of Contract, specifications, Drawings, priced Bill of

Quantities, Schedule of Rates and Prices, if any, Tender, pre-contract correspondence,

Letter of Intent/Acceptance, Work order, shall be read and construed as forming part

of this agreement and the Contractor shall abide by and submit themselves to all the

conditions and stipulations contained therein; which are not specifically incorporated

herein;

ii. The Contractor shall obtain necessary permissions/ certificates/ order from the

Competent Authority in respect of workmen employed by them for the Project and hall

keep the Bank safe, harmless and reimburse all amounts/expenses incurred or suffered

by the Bank in connection with any such claim;

iii. The Contractors shall not make any claim as regards want of information of any

particular point or any change in the rate or conditions save and except as provided

herein;

iv. The Contractors shall have a duly authorized agent at the place of Work to accept

services of notice and to agree to extras, omissions, additions and substituted items of

Works and rates from the commencement of the Work until it is virtually completed.

v. In the event of any discrepancy between the details and/or description given in the Bill

of Quantities, the Drawings and the Technical Specifications, such item shall be

deemed to have been priced in accordance with the details and/or description

confirming to the most superior provisions contained in any of the following: -

a) Bill of Quantities

b) Drawings

c) Technical Specifications

vi. It shall be understood that the details and/or description not specifically mentioned in

the Bill of Quantities and/or the drawing shall be the same as those mentioned in the

Technical Specification. Any further interpretation of above Clause shall be at the

discretion of the Architects, whose decision shall be final and binding on the parties to

the contract.

vii. The Contractors shall not make any claim for increase in the contract consideration on

the basis of incorrectness and insufficiency of the information available at the time of

submitting the Tender and/ or incorrectness and insufficiency of the rates and prices

stated in the price bill of quantity and schedule of rates and prices or otherwise

21

SIGN & SEAL OF CONTRACTOR

alleging insufficiency of the tender amount to cover their obligation under the contract

or matters concerning the execution of the Project.

viii. The Contractor shall be fully responsible for the adequacy, stability and safety of all

site operations and methods of construction, provided that the Contractor shall not be

responsible, except as may be expressly provided in the Contract, for the design or

specification of the Permanent Works, or for the design or specification of any

Temporary Works prepared by the Architect.

ix. The Contractor shall promptly inform the Architect of any error, omission, fault and

other defects in design, drawing or specifications for the Works, which are discovered

while reviewing the Contract Documents or in the process of execution of the Works.

x. The Contractor shall arrange for the permits and licenses for release of materials,

which are under Government control subject to the Bank giving all the necessary

assistance and upon being advised by the Architect signing any forms or applications

that may be necessary.

10. The Contractor shall comply with the provisions of all labour legislation including

there requirements of

a) The Payment of Wages Act

b) Workmen‟s Compensation Act

c) Contract Labour (Regulation & Abolition) Act, 1970 and Central Rules 1971.

d) Apprentices Act 1961

11. The Contractor shall keep the Bank saved harmless and indemnified against claims if

any of the workmen and all costs and expenses as may be incurred by the Bank in

connection with any claim that may be made by any workmen.

12. GENERAL CONDITIONS

i. The schedules of Quantities given in the Contract Bill are provisional and are meant to

indicate the intent of the Work and to provide a uniform basis for tendering. The Bank

reserves the right to increase or decrease any of the quantities or to totally omit any

item of Work and the Contractor shall not claim any extras or damages on these

grounds.

ii. Any error in description or in quantity or omission of items from the Contract Bill shall

not vitiate this Contract but shall be treated as a variation.

iii. The rates quoted by the Contractor in the priced bill of quantities (Contract Bills) shall be

treated as firm and the contract sum shall be deemed to have been calculated with

reference to the cost of execution of Works as set out inn Contract Documents and shall not

be adjusted or altered for any reason other than any adjustments on account of statutory

rise or fall in the cost of labour and/or material or any other matters affecting the cost of

execution of Works, or price variation adjustment formula if provided.

22

SIGN & SEAL OF CONTRACTOR

13. Notwithstanding anything contained elsewhere in any of the clauses of the tender,the

prices/rates quoted for each item/Work in the Bills of Quantities shall be deemed to

be inclusive of all direct and indirect costs, duties, taxes, sales tax, consignment tax,

octroi/local tax, Works contract tax, etc. on any of inputs, royalty on quarried items

etc. that may be involved in completing the item/Work as required in the fulfillment

of all obligations under the contract and to the satisfaction of the Engineer. Additional

Taxes / Levies by Central / State Government legislations after opening of tender shall

be reimbursed to the contractors as per actual.

14. All the interim payments shall be regarded as payments by way of advance against

the final payment only and not as payments for Work actually done and completed,

and shall not preclude the repairing of bad, unsound, and imperfect or unskilled Work

to be removed and taken away and reconstructed, or re-erected or be considered as

an admission of the due performance of the contract, or any part thereof in any

respect or the accruing of any claim, nor shall, it conclude, determine or affect in

anyway the power of the Bank under these conditions or any of them as to the final

settlement and adjustment of the accounts or otherwise or in any other way vary or

affect the contract. The final bill shall be submitted by the Contractor within one

month of the date fixed for completion of the

Work or of the date of certificate of completion furnished by the Architect and

payment shall be made within eight (8) weeks from the date of receipt of final

Certificate from the Architect.

15. INSURANCE

i. Without limiting the obligations and responsibilities under Contract Clause for Care

of Work the Contractor shall affect third party insurance with an insurer and in terms

approved by the Bank in the joint names of the Bank and the Contractor

ii. against all loss or damage from whatever cause arising, other than the excepted

risks stated in contract clause of the General Conditions for which the Contractor is to

be held responsible under the terms of the Contract so as to cover the Bank and the

Contractor during the period beginning with commencement of the Works until the

date stated in the Certificate of Completion for the whole of the Works.

iii. Against any loss or damage occasioned by the Contractor in the course of any

operations carried out by him for the purposes of completing the outstanding Work

during the Defects Liability period pursuant to the Undertaking given at the time of

applying for the issue of Certificate of Completion.

iv. Against any loss or damage occasioned by the Contractor in the course of any

operations carried out by him for rectifying any defect in perfection or fault appearing

during the progress of the Work or during the Defects Liability Period.

23

SIGN & SEAL OF CONTRACTOR

v. Against any loss or damage occasioned by the Contractor in the course of any

operations carried out by him for searching the cause of any defect, imperfection or

fault appearing during the progress of the Works or during the Defects Liability Period.

vi. Against any liability for or in respect of any damages or compensation payable at

law in respect of or in consequence of any accident or injury to any workmen or other

person in the employment of the sub-Contractor provided the sub-contractors shall not

have insured against such contingency. (Insurance against accident etc. to workman)

vii. Unless otherwise instructed the Contractor shall insure the Works and keep them

insured until the virtual completion of the contract against loss or damage by fire

and/or earthquake, flood.

viii. The Contractor shall maintain Contractors‟ all risks insurance policy covering loss,

damage, theft, burglary etc. of all materials and equipments, temporary Works and

the Work shall be insured for a total sum equal to the value of all such items plus 10%

of such value.

ix. Provided always that all the insurance under the contract documents shall be

arranged by the Contractor from a first class insurance company having a branch near

the site who can deal with all matters pertaining to the subject, the insurance must be

placed with a company approved by the Bank, in the joint names of the Bank and the

Contractor for such amount and for any further sum if called to do so by the Bank, the

premium of such further sum being allowed to the Contractor as an authorized extra.

16. The Contractor shall deposit the policy and receipt for premiums paid with the Bank

within 21 (twenty-one) days from the date of issue of Work order unless otherwise

instructed. In default of the Contractor insuring as provided above, the Bank on his

behalf may so insure and may deduct the premiums paid from any money due, or which

may become due to the Contractor. The Contractor shall as soon as the claim under

the policy is settled or the Work reinstated by the Insurance Company should they

elect to do so, proceed with due diligence with the completion of the Works in the

same manner as though the insured risk/contingency has not occurred and in all

respects under the conditions of the contract. The Contractor in case of rebinding or

reinstatement after the occurrence of the insured risk/contingency shall be entitled to

such extension of time for completion as the Bank may deem fit.

16.1.1 Such insurance shall continue during the whole of the time of continuance of Work

and/or during such time that any persons are employed by him on the Works and shall

when required produce before the Bank or the Architect, such policy of insurance and

the receipt for payment of the earlier premium and the current premium.

24

SIGN & SEAL OF CONTRACTOR

16.1.2 The insurance shall be effective in such manner that the Bank is indemnified under the

policy. In the event of the sub-contractor having effected an insurance against accident

etc. to the workmen the Contractor shall require such sub-contractor to produce to the

Bank / Architect when required, such policy of insurance and the receipt for the

payment of the current premium, then in that event insurance under clause (vii) hereof

by the Contractor shall not be necessary.

17 The Contractor shall provide for adequate cover to the Bank as per the provisions of

Workmen Compensation Act.

18 The Contractor shall make available the insurance cover notes before the

commencement of the Work and shall notify any change in the nature or extent of the

Work and also make available additional insurance of Works if required in special

circumstances.

19 DEFECTS LIABILITY

19.1 Any defects, shrinkages or other faults which shall appear within the Defects Liability

Period of 12 months from the date of handing over the works and which are due to

materials or workmanship not in accordance with this contract or on account of failure

on the part of the Contractor to comply with any of his obligations expressed or implied

shall be specified by the Architect in a schedule of defects which he shall deliver to the

Contractor not later than 14 days after the expiration of the Defects Liability Period,

and within a reasonable time after receipt of such schedule the defects, shrinkages and

other faults therein specified shall be made good by the Contractor and (unless the

Architect shall otherwise instruct, in which case the contract sum shall be adjusted

accordingly) entirely at his own cost.

19.2 The Contractor shall make good at his own costs and to the satisfaction of the Architect,

all defects, shrinkages or small faults arising in the opinion of the Architect / engineer

from Work or materials not being in accordance with the drawings or specifications or

schedule of quantities or the instructions of the Engineer / Architect, which may appear

within the

”Defects Liability Period of 12 months from the date of handing over completed site”

referred to in the Appendix to General Conditions. All defects, shrinkages or small

faults arising from any other cause not attributable to the Contractor shall be rectified

by the Contractor as an additional work.

19.3 In the event of failure of the Contractor to carry out any such work to the satisfaction of

the Engineer / Architect, the Bank shall be entitled to carry out the same at the

Contractor‟s costs and all expenses consequential and incidental thereto shall be

deducted by the Bank from any monies due or to become due to the Contractor.

19.4 When in the opinion of the Engineer / Architect any defects, shrinkages or other faults

which he may have required to be made good under sub-clause (1) and (2) of this

condition shall have been made good he shall issue a certificate to that effect, and

completion of making good defects shall be deemed for all the purposes of this contract

to have taken place on the day named in such certificate.

25

SIGN & SEAL OF CONTRACTOR

20 SPECIAL RISK

The Contractor shall not be liable for or in respect of any consequences arising out of

any special risks as enumerated in Clause 65 of the General Conditions. The

responsibilities, rights and liabilities of the parties in such case shall be determined

with respect to Clause 65 of the General Conditions.

21 STATUTORY OBLIGATIONS, NOTICES, FEES AND CHARGES

The Contractor shall comply with and give all notices required by any Act of Parliament,

any instrument rule or order made under any Act of Parliament, or any regulation or

byelaw of any local authority or of any statutory undertaker which has any jurisdiction with

regard to the Works or with whose systems the same are or will be connected. The

Contractor before making any variation from the contract drawings or the contract bills

necessitated by such compliance shall give to the Engineer / Architect a written notice

specifying and giving the reason for such variation and the Engineer / Architect may issue

instructions in regard thereto. If within 7 days of having given the said written notice the

Contractor does not receive any instructions in regard to the matters therein specified, he

shall proceed with the Work confirming to the Act of Parliament, instrument, rule, order,

regulation or byelaw in question and any variation thereby necessitated shall be deemed to

be a variation required by the Engineer / Architect.

22 MATERIALS, WORKMANSHIP, SAMPLES, TESTING OF MATERIALS

22.1All the Works specified and provided for in the specifications or which may he required

to be done in order to perform and complete any part thereof shall be executed in the

best and most workmanlike manner with materials of the best and approved quality of

the respective kinds in accordance with the particulars contained in and implied by the

specifications and as represented by the drawings or according to such other additional

particulars, and instructions as may from time to time be given by the Architect

/Engineer during the execution of the Work, and to his entire satisfaction.

22.2If required by the Architect /Engineer the Contractor shall have to carry out tests on

materials and workmanship in approved materials testing laboratories or as prescribed by

the Architect /Engineer at his own cost to prove that the materials etc., under test

conform to the relevant I.S. Standards or as specified in the specifications. The necessary

charges for preparation of mould (in case of concrete cube) transporting, testing etc.,

shall have to be borne by the Contractor. No extra payment on this account should in any

case be entertained.

22.3In case contractor is delaying or refusing or avoiding testing of material, the

Architect/engineer shall arrange for carrying out testing of material and the necessary

expenditure in carrying out the testing, transportation and incidental expenses shall be

recovered from the contractor.

23 All the materials (except where otherwise described)stores and equipment required

for the full performance of the Work under the contract must be provided through

normal channels and must include charge for import duties, sales tax, octroi and other

26

SIGN & SEAL OF CONTRACTOR

charges and must be the best of their kind available and the Contractor/s must be

entirely responsible for the proper and efficient carrying out of the Work. The Work must

be done in the best workmanlike manner. Samples of all materials to be used must be

submitted to the Architect/Engineer when so directed by the Architect / Engineer and

written approval from Architect / Engineer must be obtained prior to placement of

order.

24 During the inclement weather the Contractor shall suspend concreting and plastering

for such time as the Architect /Engineer may direct and shall protect from injury all

Work when in course of execution. Any damage (during constructions) to any part of the

Work for any reason due to rain, storm or neglect of Contractor shall be rectified by the

Contractor in an approved manner at no extra cost.

25 If the Work be suspended by reason of rain, strike, lock-outs or any other cause, the

Contractor shall take all precautions necessary for the protection of Work and at his own

expenses shall make good any damage arising from any of these causes.

26 The Contractor shall cover up and protect from damage from any cause, all new Work

and supply all temporary doors, protection to windows, and any other requisite

protection for the execution of the Work whether by himself or special tradesmen or sub-

contractor and any damage caused must be made good by the Contractor at his own

expenses.

27 SUBSTITUTION

Should the Contractor desire to substitute any materials and workmanship, he/they must

obtain the approval of the Bank / Architect in writing for any such substitution well in

advance. Materials designated in this specification indefinitely by such term as “Equal”

or “Other approved” etc. specific approval of the Bank/Architect has to be obtained in

writing. The term equivalent means, if material specified is not available, then after

satisfying to the fact, the Architect / engineer may give other material to be used which

will be subject to adjustment in purchase prices.

28 INSPECTION OF WORKS

28.1 All materials and workmanship shall be subject to inspection, examination and test at

any and all times during manufacture and/or construction. The Architect may issue

instructions requiring the Contractor to open up for inspection any Work covered up or

to arrange for or carry out any test at any and all times.

28.2 The Architect / Engineer shall have the right to reject the defective material and

workmanship or require its correction.

28.3 The test of any materials or goods (whether or not already incorporated in the Works)

or of any executed Work, and the cost of such opening up or testing (together with the

cost of making good in consequence thereof) shall be added to the contract sum unless

provided for in the contract bills or unless the inspection or test shows that the Work,

materials or goods are not in accordance with this contract.

27

SIGN & SEAL OF CONTRACTOR

28.4 The Architect / Engineer may issue instructions in regard to the removal from the site

of any Work, materials or goods, which are not in accordance with this contract.

28.5 The Engineer may (but not reasonably or veraciously) issue instructions requiring the

dismissal from the Works of any person employed thereon.

28.6 On the failure of the Contractor to comply with any of the Engineer’s instructions the

Engineer may proceed to replace or correct such material/workmanship entirely at the

cost of the Contractor.

29 REMOVAL OF IMPROPER WORK

The Bank shall during the progress of the Work have power to order in writing from

time to time the removal from the Work within such reasonable time or times as may

be specified in the order of any materials which in the opinion of the Architect /

Engineer are not in accordance with specification or instructions, the substitution or

proper re-execution of any Work executed with materials or workmanships not in

accordance with the drawings and specifications or instructions. In case the Contractor

refuses to comply with the order the Bank shall have the power to employ and pay

other agencies to carry out the Work and all expenses consequent thereon or

incidental thereto as certified by the Architect / Engineer shall be borne by the

Contractor or may be deducted from any money due to or that may become due to the

Contractor. No certificate, which may be given by the Engineer, shall relieve the

Contractor from his liability in respect of unsound Work or bad materials.

30. PROTECTIVE MEASURES

30.1 The Contractor from the time of being placed in possession of the site must make

suitable arrangements for watching, lighting and protecting the work, the site and

surrounding property by day, by night, on Sundays and other holidays.

30.2 Contractor shall indemnify the Bank against any possible damage to the building, roads,

or members of the public in course of execution of the work.

30.3 The contractor shall provide necessary temporary enclosures etc. for the protection of

the work and materials and for altering and adopting the same as may be required and

removing on completion of the works and making good all works disturbed.

31. NOTICE AND PATENTS OF APPROPRIATE AUTHORITY AND OWNERS.

31.1 The Contractor shall conform to the provisions of any Acts of the Legislature relating to

the Work, and to the Regulations and Bye-laws of authorities, and/or any water,

lighting and other companies, and/or authorities with whose systems the structures

were proposed to have connection and shall before making any variations from the

drawings or specification that maybe associated to so conform, give the Architect /

Engineer written notices, specifying the variations proposed to be made and the

reasons for have making them and apply for instruction thereon. The Architect /

Engineer on receipt of such intimation shall give a decision within a reasonable time.

28

SIGN & SEAL OF CONTRACTOR

31.2 The Contractor/s shall arrange to give all notices required for by the said Acts,

Regulations or Bye-laws to be given to any authority, and to pay to such authority or to

any public officer all fees that may be properly chargeable in respect of the Work and

lodge the receipts due with the Bank.

32. ASSIGNMENT AND SUB-LETTING

32.1 The whole of the Works included in the contract shall be executed by the Contractor

and the Contractor shall not directly or indirectly transfer, assign or underlet the

contract or any part, share or interest therein nor, shall take a new partner, without

written consent of the Bank and no subletting shall relieve the Contractor from the full

and entire responsibility of the contract or from active superintendence of the Work

during their progress.

32.2 The Contractor shall not assign the Contract or any benefit or interest therein or there

under, otherwise than by a charge in favour of the Contractor‟s bankers of any monies

due or to become due under this Contract, without the prior written consent of the

Bank.

32.3 The Contractor shall not sub-let the whole of the Works except where otherwise

provided by the contract, the Contractor shall not sublet any part of the Works without

the prior written consent of the Engineer, which shall not be unreasonably withheld,

and such consent, if given shall not relive the Contractor from any liability or obligation

under the contract and he shall be responsible for the acts, defaults and neglects of any

sub-contractor, his agents, servants or workmen as fully as if they were the acts,

defaults or neglects of the Contractor, his agents, servants or workmen. Provided

always that the provision of labour on a piecework basis shall not be deemed to be a

subletting under this clause. The Contractor shall co-ordinate and shall be responsible

for all aspects of his sub-contractor(s) without being relieved of any of his obligation

under the contract.

32.4 If, the contracting agencies are violating the tender terms and sub-let the work without

bank‟s consent and the same is brought to the notice of the Bank, the Bank will

beentitled to recover 10% of such work as penalty besides initiating measures as

provided in contract.

32.5 If, at any time during the execution of the Works, the Architect / Engineer shall require

the Contractor to make boreholes or to carry out exploratory excavation, such

requirement shall be ordered in writing and shall be deemed to be an addition ordered

under the provisions of the General Conditions unless a provisional sum in respect of such

anticipated Work shall have been included in the Bill of Quantities.

32.6 The Contractor shall in connection with the Works provide and maintain at his own costs

all lights, guards, fencing and watching when and where necessary or required by the

Architect / Engineer or the Bank, or by any duly constituted authority, for the

execution and for the protection of the Works, and/or for the safety and convenience of

the public / others.

29

SIGN & SEAL OF CONTRACTOR

32.7 The Contractor shall, in accordance with the requirements of the Architect Engineer, afford

all responsible opportunities for carrying out their Work to any other Contractors employed

by the Bank and their workmen and to the workmen of the Bank and of any other duly

constituted authorities who may be employed in the execution on or near the Site of any

Work not included in the contract or of any contract with the Bank may enter into in

connection with or ancillary to the Works. The Contactor will not be paid any compensation

on this account.

32.8 Shall keep the Site reasonably free from unnecessary store of constructional plant

and machinery, wreckage and rubbish during progress of Works and on completion

leave the whole site clean and in a workmanlike condition to the satisfaction of the

Architect / Engineer.

33. Default of Contractor

33. 1 If the Contractor

i. being a company presents

(other than a voluntary

reconstruction) or

a petition for winding up and/or goes into liquidation

liquidation for the purposes of amalgamation or

ii. shall make an assignment or a composition for the benefit of the greater part, in

number of amount of his creditors or shall enter into a Deed or arrangement with

his creditors, or

iii. if a Receiver of the Contractor‟s firm appointed by the court shall be unable, within

fourteen days after notice to him requiring him to do so, to show to the reasonable

satisfaction of the Bank that he is able to carry out and fulfill the contract, and if so

required by the Bank to give reasonable security therefore, or if the Contractor shall

suffer execution to be issued, or

iv. shall suffer any payment under this contract to be attached by or on behalf of and

of the creditors of the Contractor, or

v. shall assign, charge or encumber this contract or any payments due or which may

become due to the Contractor without the consent in writing of the Bank first

obtained, there under, or

vi. shall agree to carry out the contract under a committee of inspections of his

creditors, or

vii. shall have an execution levied on his goods, or

viii. shall use improper materials or workmanship in carrying on the Works, or

ix. shall in the opinion of the Bank not exercise such due diligence and make such due

progress as would enable the Work to be completed within due time agreed upon,

and the Architect / Engineer certifies in writing that the Contractor has failed to

commence the Works or failed to proceed with the Works after the suspension order

when so called upon by the Architect / Engineer, or

x. Shall abandon the contract,

30

SIGN & SEAL OF CONTRACTOR

xi. Without reasonable excuse has failed to commence the Works or have suspended

the progress of Works for 28 days after receiving from the Architect / Engineer

written notice to proceed on.

xii. has failed to remove materials from the site or to pull down or replace for 28 days

after receiving from the Architect / Engineer written notice that the said materials

or Work has been condemned and rejected by the Architect / Engineer under these

conditions or

xiii. despite previous writings by the Architect / Engineer in writing has failed to execute

Works in accordance with the contract, or is persistently or flagrantly neglecting to

carry out his obligations under the contract or as to the detriment of good

workmanship or in defiance of the Architect /Engineer‟s instructions to the contrary,

sublet any part of the contract then and in any of the said cases the Bank may

notwithstanding previous Waiver.

xiv. determine the contract by after giving 14 days notice in writing to the effect as

hereinafter mentioned, but without thereby affecting the powers of the Bank or the

obligations and liabilities of the Contractor the whole of which shall continue in

force as fully as if the contract, had not been so determined and as if the Works

subsequently executed had been executed by or on behalf of the Contractor

(without thereby creating any trust in favour of the Contractor)

xv. further the Bank or his agent, or servants, may enter upon the Site and take

possession of the Work and all Constructional Plant, amenities, unused materials,

tools, scaffolding, sheds, machinery, steam and other power, utensils and materials

lying upon premises or the adjoining lands or roads reserved for the execution of the

Works and sell the same as his own property or may employ the same by means of

his own servants and workmen in carrying on and completing the Works or by

employing any other Contractors or other persons or person to complete the Works,

and the Contractor shall not in any way interrupt or do any act, matter of thing to

prevent or hinder such other Contractors or other persons or person employed from

completing and finishing or using the materials and plants for the Works when the

Works shall be completed, or as soon thereafter as conveniently may be, the Bank

shall give notice in writing to the Contractor to remove his surplus materials and

plants and should the Contractor fail to do so within a period of 14 days after

receipt by him the Bank may sell the same by Public Auction and shall give credit to

the Contractor for the amount so realized.

33.2 Any expenses or losses incurred by the Bank in getting the Works carried out by other

Contractors shall be adjusted against the amount payable to the Contractor by way of

selling his tools and plants or due on account of Work carried out by the Contractor

prior to engaging other Contractors or against the Security Deposit.

33.3 Upon such entry and expulsion by the Bank the Architect / Engineer may adopt an

appropriate mode at his discretion and certify the amounts, if any that had at the time

of such entry and expulsion reasonably been earned in respect of the work actually

31

SIGN & SEAL OF CONTRACTOR

done by him and the value of any unused or partially used materials, any Constructional

Plant and any amenities brought into existence exclusively for execution of the Works.

33.4 If the Bank shall enter and expel [the Contractor] under this Clause, he shall not be

liable to pay to the Contractor any money on account of the Contract, until the

expiration of the Defects Liability Period and thereafter until the costs of execution,

damages for delay in completion, if any, and all other expenses incurred by the Bank

have been ascertained and the amount thereof certified by the Architect / Engineer.

The Contractor shall then be entitled to receive only such sum or sums, if any, as the

Architect/Engineer may certify would have been payable to him upon due completion

by him after deducting the said amount. If such amount shall exceed the sum which

would have been payable to the Contractor on due completion by him, then the

Contractor shall, upon demand, pay to the Bank the amount of such excess and it shall

be deemed a “debt due” by the contractor to the Bank and shall be recoverable

accordingly.

34. DEFAULT OF THE BANK

34. 1 The Contractor may, if –

a. The Bank does not pay to the Contractor the amount due on any certificate within six

weeks from the receipt of Certificate from the Architect honoring certificates named

in the appendix to these conditions and continues such default for 7 days after receipt

by registered post or recorded delivery of a notice from the Contractor stating that

notice of determination under this condition will be served if payment is not made

within 7 days from receipt thereof; or

b. The Bank interferes with or obstructs the issue of any certificate due under

this contract; or

c. The carrying out of the whole or substantially the whole of the uncompleted Works is

suspended by the Bank for a continuous period of 90 days;

d. The Bank becomes bankrupt or makes a composition or arrangement with his creditors

or has a winding up order or (except for the purposes of reconstruction) a resolution

for voluntary winding up passed or a receiver or manager of his business or undertaking

is duly appointed, or possession is taken by or on behalf of the holders of any

debentures secured by a floating charge, of any property comprised in or subject to

the floating charge,

e. if the Bank gives a formal notice of his inability to meet his contractual obligations

after giving 14 days prior written notice by registered post or recorded delivery to the

Bank with a copy to the Architect / Engineer terminate the employment of the

Contractor PROVIDED that such notice shall not be given unreasonably or veraciously.

34.2 Upon the expiry of 14 days notice referred to herein, the Contractor shall with all

reasonable dispatch remove from the site all constructional plant brought by him

thereon.

32

SIGN & SEAL OF CONTRACTOR

34.3 Upon such determination, without prejudice to the accrued rights or remedies of either

party or to any liability which may accrue either before the Contractor or any sub-

contractors shall have removed his temporary buildings, plant, tools, equipment, goods

or materials or by reason of his or their so removing the same, the respective rights and

liabilities of the Contractor and the Bank shall be as follows, that is to say:

a. The Contractor shall with all reasonable dispatch and in such manner and with such

precautions as will prevent injury, death or damage of the classes in respect of which

before the date of determination he was liable to indemnify the Bank remove from the

site all his temporary buildings, plant, tools, equipment, goods and materials and shall

give facilities for his sub-contractors to do the same;

b. After taking into account amounts previously paid under this contract the

Contractor shall be paid by the Bank for;

• The total value of Work completed at the date of determination;

• The total value of Work begun and executed but not completed at the date of

determination, the value being ascertained if such Work were a variation required by

the Architect / Engineer;

• The cost of materials or goods properly ordered for the Works for which the

Contractor shall have paid or for which the Contractor is legally bound to pay, and on

such payment by the Bank any materials or goods so paid for shall become property of

the Bank;

• The reasonable cost of removal under paragraph (a) of this sub-clause.

• And in addition, the amounts payable in respect of any preliminary item, so far as the

work or service comprised therein has been carried out or performed and a proper

proportion as certified by the Architect / Engineer of any such item, work or service

comprised in which has been partially carried out or performed.

• A sum certified by the Bank being the amount of any expenditure reasonably incurred

by the Contractor in the expectation of completing the whole of the Works in so far as

such expenditure shall not have been covered by the payments made under this clause.

• The reasonable costs of repatriation of all the Contractor‟s staff and workmen, employed

on or in connection with the Works at the time of such termination.

Provided always that against any payment due from the Bank under this sub-clause, the

Bank shall be entitled to be credited with any outstanding balances due from the

Contractor for advances in respect of constructional plant and materials and any other

sums which at the date of termination were recoverable by the Bank from the

Contractor under the terms of the Contract. The Bank shall also return all Bank

Guarantees and Retention after proper accounts have been settled between the

Contractor and the Bank.

Provided that in addition to all other remedies the Contractor upon such determination

take possession of and shall have a lien upon all unfixed goods and materials, which

may have become the property of the Bank until payment of all monies due to the

Contractor from the Bank.

33

SIGN & SEAL OF CONTRACTOR

34.4 If a war or other circumstances outside the control of both the parties, arises after the

Contract is made, so that either party is prevented from fulfilling his contractual

obligations, or under the law governing the Contract, the parties are released from

further performance, then the sum payable by the Bank to the Contractor in respect of

the Work executed shall be the same as that which would have been payable under

Clause 32 hereof as if the Contract had been terminated under the provisions of Clause

32 hereof. Performance of obligations becoming more onerous shall not be considered

as a cause for “Frustration”.

35 NOTICES

35.1 All certificates, notices or written orders to be given by the Bank or by the Architect /

Engineer to the Contractor under the terms of the Contract shall be served by sending

by registered post or by Courier or delivering the same to the Contractor‟s principal

place of business, or such other address as the Contractor shall nominate for this

purpose.

35.2 All notices to be given to the Bank or to the Architect / Engineer under the terms of the

Contract shall be served by sending by registered post or by Courier or delivering the

same to the respective addresses nominated for that purpose in Part II of these

conditions.

35.3 Either party may change a nominated address to another address in the country where

the Works are being executed by prior written notice to the other party and the

Architect / Engineer may do so by prior written notice to both parties.

36 ARBITRATION

36.1 Wherever, in any of the documents forming part of the Contract, the Architect / Bank

has been vested with the final powers, his decision, opinion, certificate or any other

discretion shall be final conclusive and binding on the parties and shall be without

appeal. All other matters shall be subject to the right of arbitration.

36.2 All disputes or differences of any kind whatsoever save and except matters referred to

in clause 1) arising out of or in connection with the Contract, whether during the

progress of Work or after Completion and shall after written notice by either party to

the contract to the other of them and to the Bank hereinafter mentioned be referred

for adjudication to two Arbitrator, one each to be nominated by the Contractor and the

Bank, who shall thereafter appoint an Umpire. The provisions of Indian Arbitration and

Conciliation Act 1996 shall apply for the purposes.

36.3 The Work under the Contract shall, however, continue during the arbitration

proceedings and no payment due or payable to the Contractor shall be withheld on

account of such proceedings.

36.4 The Arbitrator shall be deemed to have entered on the reference on the date he issued

notice to both the parties fixing the date of the first hearing.

34

SIGN & SEAL OF CONTRACTOR

36.5 The Arbitrator may from time to time, with the consent of the parties, enlarge the time

for making and publishing the award.

36.6 The Arbitrator shall give a separate award in respect of each dispute or difference

referred to him. The Arbitrator shall decide each dispute in accordance with the terms

of the contract and give a reasoned award. The venue of arbitration shall be such place

as may be fixed by the Arbitrator in his sole discretion.

36.7 The fees, if any, of the Arbitrator shall, if required to be paid before the award is made

and published, be paid half and half by each of the parties. The cost of the reference

and of the award including the fees, if any, of the Arbitrator who may direct to and by

whom and in what manner, such costs or any part thereof shall be paid and may fix or

settle and amount of costs to be so paid.

36.8 The award of the Arbitrator shall be final and binding on both the parties.

36.9 Subject to aforesaid the provisions of the Arbitration & Conciliation Act 1996 or any

statutory modification or re-enactment thereof and the rules made there under, and

for the time being in force, shall apply to the arbitration proceeding under this clause.

36.10 The Bank and the Contractor hereby also agree that arbitration under clause shall be a

condition precedent to any right to action under the contract with regard to the

matters hereby expressly agreed to be so referred to arbitration.

AS WITNESS the hands of the said Parties.

Signed by the said

In the presence of

Witness

Name:

Address

Signed by the said

In the presence of

Witness

Name:

Address

Bank Contractor

35

SIGN & SEAL OF CONTRACTOR

DOCUMENTS ATTACHED TO THE AGREEMENT FORMING PART & PARCEL OF

THE AGREEMENT

• Tender document & tender drawings.

• NIT vide .

• Addendum issued vide

• Contractor‟s letter dated

• Work order vide.

36

SIGN & SEAL OF CONTRACTOR

9. GENERAL INSTRUCTIONS TO CONTRACTORS AND SPECIAL CONDITIONS

1. Canvassing in connection with tenders is strictly prohibited and the tenders submitted

by the contractors who resort to canvassing will be liable to rejection.

2. The Tender Form must be filled in English and all entries must be made by the hand

and written in ink, if any of the documents is missing, or unsigned, the Tender may be

considered invalid by the Bank in its discretion.

3. 50% of retention money and initial security deposit will be returned against submission

of Bank Guarantee valid for a period of 12 months of Defect Liability Period and after

I) issue of virtual completion certificate by the Architect of the work. II) Contractor‟s

removal of his material, equipments, labour force, temporary sheds / stores, etc. from

the site (excepting for small presence required, if any, for defect liability period and

approval by the bank)

Balance 50% of retention money and security deposit shall be released to the

contractor fourteen days after the end of completion of defect liability period

provided he has satisfactorily carried out all the works and attended to all the defects

in accordance with the conditions of contract including site clearance.

4. The contractor shall not assign the contract. He shall not sub-let any portion of the

contract except with the written consent of the Bank. In case of breach of these

conditions, the Bank may serve a notice in writing on the contractor rescinding the

contractor whereupon the Security Deposit shall stand forfeited to the Bank, without

prejudice to his other remedies against the contractor. Central Govt. / State Govt.

organization will not be allowed to sublet the work on back-to-back basis.

5. The contractor shall carry out of all the work strictly in accordance with Drawings,

details and instructions of the Architect, Architect and the Bank. If in the opinion of

the Architect, Architect or the Employer, changes have to be made in the design and

with the prior approval in writing of the Employer, they desire the contractor to carry

out the same; the contractors shall carry out the same without any extra charge. The

Bank‟s decision in such cases shall be final and shall not be open to arbitration.

6. A Schedule of probable quantities in respect of each work and specifications

accompany these special conditions. The Schedule of probable quantities is liable to

alteration by omission, deductions or additions at the discretion of the Architect/

Bank. No claim will be entertained from the contractor on account of loss of profit

over revising the tender rates.

37

SIGN & SEAL OF CONTRACTOR

7. The Tenderer must obtain for himself on his own responsibility and at his own expenses

all the information which may be necessary for the purpose of filling of Tender and for

entering into a contract and must examine the drawings and must inspect the site of

the work and acquaint himself with all local conditions, means of access to the work,

nature of the work and all matters pertaining thereto. No compensation will be paid on

account of not getting proper information.

8. The rates quoted in the Tender shall be inclusive of all charges for clearing of site

before commencement as well as after completion, water, electrical consumption,

meters, double-scaffolding, centering, boxing, staging, planking, timbering and

pumping out water, including bailing, fencing, planking, timbering and pumping out

water, including bailing, fencing, hoarding, plant and equipment, storage sheds,

watching and lighting by night as well as day, including Sundays and Holidays,

temporary plumbing and electric supply, protection of the public and safety of

adjacent roads, streets, cellars, vaults, open pavements, walls, houses, buildings and

all other erections, matters or things and the contractor shall take down and remove

any or all such centering, scaffolding, staging, planking, timbering, strutting, shoring,

etc. as occasion shall require or when ordered so to do, and fully reinstate and make

good all matters and things disturbed during the execution of the work and to the

satisfaction of the Bank / Architect.

9. Time allowed for carrying out the work as mentioned in the Memorandum shall be

strictly observed by the contractor and its shall be reckoned from the 10 days after

acceptance of order to commence the work or the date of handing over the site to the

contractor whichever is later. The work shall throughout the stipulated period of the

contract be proceeded with all due diligence and if the contractor fails to complete

the work within the specified period i.e. 10 Weeks, he shall be liable to pay

compensation as defined in the conditions of contract.

38

SIGN & SEAL OF CONTRACTOR

10. The contractor shall not be entitled to any compensation for any loss suffered by him

on account of delays in commencing or executing the work, whatever the case of

delays may be, including delays arising out of modifications to the work entrusted to

him or in any sub-contract connected therewith or delays in awarding contracts for

other trades if the project or in commencement or completion of such works or in

procuring government controlled or other building materials or in obtaining water and

power connections for construction purposes or for the other reasons whatsoever and

the Employer shall not be liable for any claim in respect thereof. The Employer does

not accept liability for any sum besides the Tender amount, subject to such variations

as are provided for herein.

11. The successful Tenderer is bound to carry out any items of work necessary for the

completion of the job even though such items are not included in the quantities and

rates. Schedule of instructions in respect of such additional items and their quantities

will be issued in writing by the Architect / Architect with the prior consent in writing

of the Bank.

12. The successful Tenderer must co-operate with the other contractors appointed by the

Employer so that the work shall proceed smoothly with the least possible delay and to

the satisfaction of the Architects / Architect.

13. The contractor must bear in mind that all the work shall be carried out strictly in

accordance with the specifications made by the Architect / Architect and also in

compliance of the requirements of the Authorities concerned and no deviation on any

account will be permitted.

14. (i) The rates quoted in the Schedule rates also include the expenditure for providing all

the water required for the work and the contractor shall make his own arrangements

for the supply of good quality water including obtaining Municipal connection for his

labour as well as for construction purpose and all charges shall be borne by him. If

Municipal water connection is not available and should it become necessary for the

contractor to drill a bore well for obtaining water for construction purposesor to bring

water from outside by Tankers, The Bank shall not be liable to pay any charges in

connection therewith.

(ii) The rates quoted in the Tender shall also include Electric consumption charges for

Power. If no power is available at site, the contractor shall have to make his own

arrangement to obtain electric power connection and maintain at his own cost an

efficient service of electric light and power and shall pay for the electricity consumed.

39

SIGN & SEAL OF CONTRACTOR

(iii) For water and power, the contractor to whom the work is allotted shall

maintain the same in good working conditions.

(iv) Contractor for other trades appointed by the Bank shall also be allowed to use

water and power available by fixing reasonable charges mutually agreed.

(v) Any dispute regarding payment for water and power charges by the other

contractor and or by subsidiary agencies appointed by the Bank to the contractor, who

has obtained the temporary connections and allowed sub–connections, will be settled

by the Bank / Architect and the decision taken by the Bank / Architect shall be final

and shall be that of the contractor.

(vi) The Bank as well as the Architect shall give all possible assistance to the

Contractor to obtain the requisite permission from the various authorities, but the

responsibility for obtaining the same shall be that of the contractor.

(vii) If no such facility is available at the site of work and if available found

inadequate, it shall be the responsibility of the contractor to make his own

arrangement for obtaining water and power at his cost.

15. The contractor will have to obtain completion / clearance certificate in respect of

services such as water supply, sewerage, etc. The contractor will also obtain

permanent water connection for the entire project. The Bank will pay necessary fee to

be made to Govt. authorities.

16. The Contractor shall strictly comply with provision of safety code annexed hereto.

17. The contractor shall indemnify Union Bank of India, against any claim or legal action

arising out of the said Act due to the failure of non-compliance of the provisions of the

said Act and the penalty or any other amount levied by the authorities, shall be

recoverable from the payments due to the contractors.

18. The Contractor shall comply with the provision of the Apprentices Act, 1961, and the

Rules and Orders issued there under from time to time. Failure to do so will be in a

breach of the contract and the Architect / Architect and the Bank may in their

discretion cancel the contract. The contractor shall also be liable for any pecuniary or

other liabilities arising on account of any violation by him of the provisions of the Act.

19. The Security Deposit of the successful Tender will be forfeited if he fails to

comply with any of the conditions of the contract.

20. The contractor shall be responsible for the observance of all Central Rules and

Regulation framed by the Central Government under the Contract Labour (Regulation

and Abolition) Act, 1970. The Bank shall be entitled to deduct all damages, which it

might suffer on account of non-observance of these rules by the Contractor, from the

amount payable to the Contractor.

40

SIGN & SEAL OF CONTRACTOR

21. Contractors are not allowed to remove materials brought at Site against

which advances have been paid.

22. The Contractor is to provide at all times during the progress of the works and the

maintenance period / defect liability period proper means of access, with ladders,

gangways, etc., and the necessary attendance to move and adopt as directed for the

inspection or measurement of the works by the Architect or their representatives.

23. Materials shall be of approved quality and the best of their kind available and shall

generally conform to I.S. Specifications. The Contractor shall order all the materials

required for the execution of work as early as necessary and ensure that such

materials are on site well ahead or requirement for use in the work. The work involved

calls for approved standard of workmanship combined with speed and to the entire

satisfaction of the Architect/ Architect. All the material shall be approved by the

Architect / Bank before use. Contractor to arrange samples well in time.

24. The Contractors shall after completion of the work clear the Site of all debris and left-

over materials at his own expenses to the entire satisfaction of the Bank / Architect

and Municipal or other public authorities.

25. The contractor herewith agrees that in respect of inspection of works by the Chief

Technical Examiner of the works, wing of Central Vigilance Commission and the bills of

the contractor including all supporting vouchers, abstract etc. to be made after

payment of the bills and if as a result of such audit and technical examination any sum

is found to have been over paid in respect of any work done by the contractor under the

contract of any work claimed by him to have been done by him under the contract and

found not to have been executed or any work is found not to have been executed in

accordance with the contract, the contractor shall be liable to refund the amount of

over payment made already and it shall be lawful for the bank to recover the same from

him in any manner the bank deems fit either from any payments due and / or becoming

due to the contractor or from the security deposit or retention money or through any

further bills and / or final bill or in any other manner whatsoever not excluding through

recourse to legal action. The certification of bills / measurements by Architect /

Architect and Engineer will be scrutinized by the Bank‟s Central Office / Audit /

Vigilance and any deficiency will be corrected accordingly. Contractor cannot insist for

payment just because it is signed by Architect / architect / engineer. The contractor

herewith agrees to co-operate with the Bank / Architect while such examinations of

works and redo the things without any extra cost to the Bank. It is essential and agreed

condition of the contract that any such action taken by the bank shall deemed to be the

fully legal and valid and binding on the contractor.

26. Contractors are requested to note that no extra item or deviated item of work to be

executed without taking prior permission, the Bank shall not be held responsible for

the payment of such works executed. Contractors will have to submit all the

41

SIGN & SEAL OF CONTRACTOR

particulars including purchase bills/price list for the materials along with the rate

analysis for verification of item rates.

27. If it is observed the existing compound wall, gates railings are damaged then the

contractors will have to make good the same at their own cost.

28. If contractors fail to pay the taxes/royalties to the Authorities concerned, the bank

reserve their rights to recover the said amount from the amount payable to the

contractor and pay the same to the Authorities concerned.

29. Work is to be executed & measurements are to be paid as per the detail specification

& description of item given in the Standard Specification Book except for the items

which are specifically mentioned in the tender for which the details of item and mode

of measurements to be followed as indicated separately in the conditions of

contractors.

30. Work is to be executed & measurements are to be paid as per the detail specification &

description of item given in the Standard Specification Book except for the items which

are specifically mentioned in the tender for which the details of item and mode of

measurements to be followed as indicated separately in the conditions of contractors.

30. If there are any contracting clauses mentioned in the tender, the interpretation of the

same will be done by the Architect / Architect. However, the decision of the Bank will

be final and binding.

31. After awarding the work, contractor shall get registered with the office of the Labour

commissioner and inform Bank accordingly. Contractors shall follow all rules and

regulations stipulated by the Labour Commissioner strictly.

32. Contractors shall quote consistent rates for the items of similar nature or analogous in

specifications for the sections in schedule of quantities. If it is observed that the rates

quoted for similar nature of items or analogous in specification under different

sections, are inconsistent, then the Bank reserves his right to consider the lowest of

rates for all such items and work out the final amount for payment, unless the

competent authority finds that there is justifications for such inconsistent rates.

33. The contractor shall give a list of his relatives working with the bank along with

their designations and addresses.

34. No employee of the bank is allowed to work as a contractor for a period of two years

of his retirement from bank service, without the previous permission of the bank. The

contract is liable to be cancelled if either the contractor or any of his employees is

found at any time to be such a person who had not obtained the permission of the

bank as aforesaid before submission of the tender or engagement in the contractor‟s

service.

42

SIGN & SEAL OF CONTRACTOR

10. THE CONDITIONS HEREINBEFORE REFERRED TO

1. Definition of terms / interpretation:

In construction these conditions, the specification schedule of quantities and contract

agreement, the following words shall have the meanings herein assigned to them

expect where the subject or context otherwise requires.

(a). “Employer/ / owner / Bank” shall mean” Union Bank of India, Government of India

undertaking” having Staff College, Bannerghatta road, kalkere post. Bengaluru-560083

and any of its employees‟ representatives authorized on their behalf.

(b) “Architects / Architect” – shall mean M/s Innovarch Architect (I) Pvt.Ltd having its Office

at #47/5, Lavelle Road, Bengaluru-560001, or in the event of his or their ceasing to be

Architect / Architect for the purpose of this contract such other person as the Bank

shall nominate for the purpose.

(c) “Contractors” (in case of partnership) shall mean………………………….and

…………trading as partners in the name and style of. …………………and shall include

partners for the time being of the said firm and the legal representatives of a

deceased partner.

“Contractors” (in case of individuals) shall mean………………………….and…………trading

in the name and style of. …………………and shall include his/ their heirs, legal

representative assigns or successors.

“Contractors” (in case of company) shall mean…………a company incorporated under ………19……….and having its registered office at…………and shall include its successors and

assigns.

(d) “Site” shall mean “Work Place located at New Hostel Building, Union Bank of India,Staff College, Bannerghatta, Bengaluru include any building and erections thereon and any other land (inclusively), as aforesaid, allotted by the Bank for the contractors use.

(e) Site Engineer / Engineer: The Engineer appointed by the Bank / Architect /

Architect for the management of the project.

43

SIGN & SEAL OF CONTRACTOR

(g) “The works” shall mean the work or works to be executed or done under this contract.

(h) “This Contract” shall mean Articles of Agreement, the special conditions, the general

conditions of contract, the appendix, the schedule of quantities and specifications,

attached hereto and duly signed.

(i) “Notice in writing” or written notice shall mean a notice in written, typed or printed

characters sent (unless delivered personally or otherwise proved to have been

received), by registered post to the last known private or business address or

registered office of the addressee and shall be deemed to have been received when in

the ordinary course of post, it would have been delivered.

(j) “Act of Insolvency” shall mean any Act of Insolvency as defined by the

Presidency Towns Insolvency Act, or the Provincial Insolvency Act or any

amending such original.

(k) “The Schedule of Quantities”shall mean the schedule of quantities as specified and

forming part of this contract.

(l) “Priced Scheduled of Quantities” shall mean the schedule of quantities duly priced with the

accepted quoted rates of the contractor.

(m) "Net Prices” If in arriving at the contract amount, the contractor shall have added to

or deducted from the total of the items in the Tender any sum either as a percentage

or otherwise, then the net price of any item in the Tender shall be the sum arrived at

by adding to or deducting from the actual figure appearing in the Tender as the price

of that item a similar percentage or proportion of the sum so added or deducted of the

sum so added or deducted by the contractor the amount of any Prime Cost items and

provisional sums of money shall be deducted from the total amount of the Tender. The

expression “net rates” or “net prices” when used with reference to the contract or

accounts shall be held to mean rates or prices so arrived at.

2. SCOPE OF WORK:

The work consists of carrying out Supply, Installation, Teting and Commissioning of 1 No.200 KVA Diesel Generator at Union Bank of India,Staff College, Hostel Block, Bannerghatta road, Bengaluru and making the system operational. It includes furnishing all materials, labour, tools and equipment and management necessary for and incidental to the construction and completion of the work.

44

SIGN & SEAL OF CONTRACTOR

3. CONTRACTOR’S RESPONSIBILITY

The Contractor shall carry out and complete the said work in every respect in

accordance with this contract and with the directions of and to the satisfaction of

Architect /Bank. The Architect may in his absolute discretion and in consultation with

the Bank (with prior approval from the Bank) and from time to time issue drawings

and/or written instruction, details directions and explanations which are hereafter

collectively

referred to as “Architect /Bank‟s Instruction”.

In regard to: -

a. The variations or modifications of the design, quality or quantity of works or the

additions or omission or substitution of any work.

b. Any discrepancy in the drawings or between the schedule of quantities and/or

drawings and or drawings and or specification.

c. The removal from the site of any defective materials brought thereon by the

contractor and the substitution of any other materials thereof.

d. The removal and/or re-execution of any works executed by the contractor.

e. The dismissal from the works of any person employed thereupon.

f. The opening up for inspections of any work covered up.

g. The amending and making good of any defects under clauses 19 hereof and those arising

during the maintenance / defect liability period.

The contractor shall forthwith comply with and duly execute any work comprised in

such Architect /Bank instructions, provided always that the verbal instructions,

directions, and explanations given to the contractor or his representative upon the

works by the Architect /Bank shall, if involving a variation, be confirmed in writing by

the contractor within seven days, and if not dissented from in writing within a further

seven days by the Architect, such shall be deemed to be Architect /Bank instructions

within the scope of the Contract.

4. VISIT TO SITE

The contractor shall visit the site and make himself thoroughly acquainted with the local site

condition, nature and requirements of the works,facilities of transport condition, effective

labour and materials, access and storage for materials and removal of rubbish. The

tenderer shall provide in their tender for cost of carriage, freight and other charges as also

for any special difficulties and including police restriction for transport, etc. for proper

execution of work as indicated in the drawings. The successful tenderer will not be entitled

to any claim of compensation for difficulties faced or losses incurred on account of any site

condition which existed before the commencement of the work or which in the opinion of

the Bank or Architect might be deemed to have reasonably been inferred to be so existing

before commencement of work.

45

SIGN & SEAL OF CONTRACTOR

5. AGREEMENT

The successful contractor is required to sign agreement as may be drawn up to suit

local conditions and shall pay for all stamps and legal expenses, incidental thereto.

6. PERMITS AND LICENSES

The contractor will arrange permits and licenses for release of materials, which are

under Government control. The Bank will render necessary assistance, sign any forms

or applications that may be necessary.

The contractor shall at his own cost arrange for storage shed adequate for taking

delivery and storing of the quantity of controlled materials released by the authorities

or supplied by the Bank. The costs of storing, transporting, etc. of all materials

including those under Government control are to be included by the tenderer in his

quoted rates.

The Bank / Architect shall be indemnified against all Government or legal actions for

theft or misuse of any controlled materials in the custody of the contractor.

7. GOVERNMENT AND LOCAL RULES

The contractor shall conform to the provisions of all local Bye-laws and Acts relating to

the work and to the Regulations etc. of the Government and Local Authorities and of

any company with whose system the structure is proposed to be connected. The

contractor shall give all notices required by said Act, Rules, Regulations and Bye-laws,

etc. and pay all fees payable to such authority / authorities for execution of the work

involved. The cost, if any, shall be deemed to have been included in his quoted rates,

taking into account all liabilities for license, fees for footpath encroachment and

restorations etc. and shall indemnity the Bank against such liabilities and shall defend

all actions arising from such claims or liabilities.

46

SIGN & SEAL OF CONTRACTOR

8. QUANTITY OF WORK TO BE EXECUTED

The quantities shown in the schedule of quantities are intended to cover the entire

new structure indicated in the drawings but the Bank reserves the right to execute

only a part or the whole or any excess thereof without assigning any reason therefore.

9. VARIATIONS TO BE APPROVED BY THE BANK / ARCHITECT Notwithstanding anything

herein contained, the Architect or his representative shall not, without prior

concurrence in writing of the Bank, issue any instructions, verbal or in writing, the

Architect can get the work done upto an amount of Rs. 25,000.00 (Rupees Twenty-five

thousand only) and all instruction issued to the contractor should forthwith be brought

to the notice of the Bank. The contractor shall submit through the Architect, a

statement of variations giving rise quantity and rates duly supported by analysis of

rates, vouchers, etc. The rates on scrutiny and final acceptance by the Bank shall form

a supplementary tender. The Bank shall not be liable for payment of such variations

until these statements are sanctioned by the bank.

10. DRAWINGS AND SCHEDULE OF QUANTITIES AND AGREEMENT.

The contractor on the signing hereof shall be furnished by the Architect free of cost

one copy of each of the said drawings and of the specifications and one copy of all

further Drawings issued during the progress of the works. Any further copies of such

drawings required by the contractor shall be paid by him. The contractor shall keep

one copy of all drawings on the works and the Architect / Bank or their representatives

shall at all reasonable times have access to the same.

11. CONTRACTOR TO PROVIDE EVERYTHING NECESSARY:

The contractor shall provide everything necessary for the proper execution of the

works according to the intent and meaning of the Drawings, Schedule of quantities and

Specification taken together whether the same may or may not be particularly shown

or described therein provided that the same can be reasonably be inferred there from,

and if the contractor finds any discrepancies therein, he shall immediately and in

writings, refer the same to the Bank / Architect whose decision shall be final and

binding.

The contractor shall provide himself for ground and fresh water for carrying out of the

works at his own cost. The Bank shall on account be responsible for the expenses

incurred by the contractor for hired ground or fresh water obtained from elsewhere.

47

SIGN & SEAL OF CONTRACTOR

(i) The rates quoted against individual items will be inclusive of everything necessary to

complete the said items work within the contemplation of the contract, and beyond

the unit price no extra payment will be allowed for incidental or contingent work,

labour and /or materials inclusive of all taxes and duties whatsoever except for

specific items, if any, stipulated in the tender documents.

(ii) The contractor shall supply, fix and maintain at his own cost, for the execution of any

work, all tools, tackles, machineries and equipment’s and all the necessary centering,

scaffolding, staging, planking, timbering, strutting, shoring, pumping, fencing,

boarding, watching and lighting by night as well as by day required not only for the

proper execution and protection of the said work but also for the protection of the

public and safety of any adjacent roads, streets, walls, houses, buildings, all other

erections, matters and things and the contractor shall take down and remove any or all

such centering, scaffolding, plumbing, timbering, strutting, shoring etc., as occasion

shall be required or when ordered so to do, and shall fully reinstate and make good all

matters and things disturbed during the execution or when ordered so to do, and shall

fully reinstate and make good all matters and things disturbed during the execution of

works to the satisfaction of the Bank / Architect.

(iii) The Contractor shall also provide such temporary road on the site as may be necessary

for the proper performance of the contract, and for his own convenience but not

otherwise. Upon completion, such roads shall be broken up and leveled where so

required by the drawings unless the Bank shall otherwise direct.

(iv) The contractor shall at all times give access to workers employed by the Bank or any

men employed on the buildings and to provide such parties with proper sufficient and

if required, special scaffolding, hoists and ladders and provide them with water and

lighting and leave or make any holes, grooves etc., in any work, where directed by the

Bank as any be required to enable such workman to lay or fix pipes, electrical wiring,

special fittings etc. The quoted rates of the tenderers shall accordingly include all

these above-mentioned contingent works. Special fittings etc. The quoted rates of the

tenderers shall accordingly include all these above-mentioned contingent works.

48

SIGN & SEAL OF CONTRACTOR

12. AUTHORITIES NOTICES AND PATENTS

The contractor shall confirm to the provisions of any Act of the legislature relating to

the works, and to regulations and bye-laws of any authority, and or any water electric

supply and other companies and /or authorities with and whose the systems the

structures is proposed to be connected, and shall, before making any variations from

the drawing or specifications that may be associated to so confirming, give to the

Architect written notice, specifying the variations proposed to be made and the reason

for making it and apply for instructions thereon. In case the contractor shall not within

ten days receive such instructions, he shall proceed with the work confirming to the

provisions, regulations, or byelaws in questions, and variations so necessitated shall be

dealt with under clause 13 hereof.

The contractor shall bring to the attention of the Architect / bank all notices required

by the said Acts, regulations or bye-law to be given to any authority and pay to such

authority, or to any public office, all fees that may be properly chargeable in respect

of the said work, and lodge the receipt with the Architect / Bank.

The contractor shall indemnify the Bank against all claims in respect of patent rights,

royalties, and damages to buildings, roads or members of public in course of execution

of work and shall defend all actions arising from such claims and shall keep the Bank

saved harmless and indemnified in all respects from such actions, costs and expenses.

13. CLEARING SITE AND SETTING OUT WORKS

The site shall be cleared of all obstructions, loose stone, and material rubbish of all

kind. All holes or hollows either originally existing or produced by removal of loose

stone or material shall be carefully filled up with earth, well rammed and leveled of as

directed at his own cost. The contractor shall set out the works and shall be

responsible for the true and perfect setting out of the work and for the correctness of

the positions, dimensions, levels and the alignment of all the parts thereof. If at any

time any error in this respect shall appear during the progress of any part of work or

within the period of one year from the completion of the works, the contractor shall at

his own expenses rectify such error to the satisfaction of the Architect / Bank.

49

SIGN & SEAL OF CONTRACTOR

14. DATUM

The average ground level will be considered as the crown of the nearest road, which

should be taken as “Datum” which is however, subject to final confirmation by the

Bank / Architect. All levels shown in the drawings are to be strictly adhered to.

16. BENCHES

The contractor is to construct and maintain proper benches of all the main walls, in

order that the lines and levels may be accurately checked at all times. These benches

will consist of sandalwood post of adequate length and minimum diameter 75mm to be

driven in the ground at suitable distance as directed encased with brickwork. The wire

nails will be driven on the top of sandlwood post on the center lines of columns, walls,

inside and outside faces of foundation trenches, in order that lines may be stretched

between the benches and accurate intersection of excavation. Centre line of walls,

columns, etc. may be clearly indicated and checked at any time if it is so required.

17. CONTRACTOR IMMEDIATELY TO REMOVE ALL OFFENSIVE MATTERS

All soil, filth or other matters of any offensive nature taken out of any trench, sewer,

drain, cesspool or other place shall not be deposited on the surface but shall be at

once carted away by the contractor to place provided by him.

The contractor shall keep the foundations and works free from water and shall provide

and maintain at his own expenses electrically or other power-driven pumps and other

plant to the satisfaction of the Bank for the purpose, until the building is handed over

to the Bank. The contractor shall arrange for the disposal of the water so accumulated

to the satisfaction of the Bank and local authority and no claims will be entertained

afterwards if he does not include in his rates for the purpose.

18. MATERIALS, WORKMANSHIP, SAMPLES, TESTING OF MATERIALS:

All the works specified and provided for in the specifications or which may be required

to be done in order to perform and complete any part thereof shall be executed in the

best and most workman like manner with materials of the best and approved quality of

the respective kinds in accordance with the particulars contained in and implied by the

specifications and represented by the drawings or according to such other additional

particulars and instructions as may from time to time be given by the Bank / Architect

during the execution of the work, and to his entire satisfaction.

50

SIGN & SEAL OF CONTRACTOR

The contractor shall have to carry out test on materials and workmanship in approved

materials testing laboratories or as prescribed by the Bank / Architect at own cost to

prove the materials quality and test sample, confirm to the relevant I.S. Standard or as

specified in the specifications. The necessary charges for preparation of mould (in case

of concrete cube) transporting testing etc. shall have to borne by the contractors. No

extra payment on this account should in any case be entertained.

All the materials (except where otherwise described) store and equipment required for

the full performance of the work under the contract must be provided through normal

channels and must include charges for import duties, sales tax, octroi and other

charges and must be the best of their kind available and the contractors/must be

entirely responsible for the proper and efficient carrying out the work. The work must

be done in the best workman like manner. Samples of all materials to be used must be

submitted to the Bank / Architect when so directed by the Engineer/ Architect and

written approval from Bank / Architect must be obtained prior to placement of order.

The Contractor shall set up a field laboratory with necessary equipment for day-to-day

testing of material like sand, brick, aggregate etc.

19. INCLEMENT WEATHER

During the inclement weather, the contractor shall suspend concreting and plastering

for such time as the Bank / Architect may direct and shall protect from injury all work

when in course of execution. Any damage (during construction) to any part of the work

for reasons due to rain, storm, or neglect of contractor shall be rectified by the

contractor in an approved manner at no extra cost.

Should the work be suspended by reason of rain, strike, lockouts or any other cause,

the contractor shall take all precautions necessary for the protection of work and at his

own expenses shall make good any damage arising from any of these causes. The

contractor shall cover up and protect from damage, from any cause, all new work and

supply all temporary doors, protection to window, and any other requisite protection

for the execution of the work whether by himself or special tradesmen or sub-

contractor and any damage caused must be made good by the contractor at his own

expenses.

51

SIGN & SEAL OF CONTRACTOR

20. MATERIALS AND WORKMANSHIP TO CONFORM TO DESCRIPTIONS: All materials and

workmanship shall so far as procurable be of the respective kinds described in the

schedule of quantities and / or specifications and in accordance with the Architect‟s

instructions, and the contractor shall upon the request of the Architect furnish him

with all invoices, accounts, receipts and other vouchers to prove that the materials

comply therewith. The contractor shall at his own cost arrange for and / or carry out

any test of any materials which the architects may require.

21. CONTRACTOR’S SUPERINTENDENCE & REPRESENTATIVE ON THE WORKS.

The contractor shall give all the necessary personal superintendence during the

execution of the works, and as long thereafter as the Bank / Architect may consider

necessary until the expiration of the defects liability period stated in the Appendix

hereto. The contractor shall also during the whole time the works are in progress

employ;

a) an experienced qualified Engineer as required who shall be in constantly attendance

at work while the men are at work. Any directions, explanations, instructions, or

notices given by the Bank / Architect to such representative shall be held to be given to

the contractor.

For non-compliance, an amount of Rs. 20,000/- pm / per Engineer shall be deducted

from the contractor for the period required engineers are not provided. However,

deduction of payment shall not exonerate contractor for his responsibility for

executing quality work.

22. DEPLOYMENT OF LABOURS

No labourers below the age of eighteen years shall be employed on the work.

Any labourers supplied by the contractor to be engaged on the work on day-work basis

either wholly or partly under the direct order or control of the Bank or his

representative shall be deemed to be a person employed by the contractor.

The contractor shall comply with the provisions of all labour legislation including the

requirement of

a) The payment of Wages Act

b) Workmen‟s Compensation Act

c) Contract Labour (Regulation & Abolition) Act, 1970 and Central Rules 1971.

52

SIGN & SEAL OF CONTRACTOR

23. FACILITIES TO BE PROVIDED TO WORKERS

The contractor shall comply at his own cost with the order of requirement of any

Health Officer of the State or any local authority or of the Bank regarding the

maintenance of proper environmental sanitation of the area where the contractor‟s

labourers are housed or accommodated, for the prevention of small pox, cholera,

plague, typhoid, malaria and other contagious diseases. The contractor shall provide,

maintain and keep in good sanitary condition adequate sanitary accommodation and

provide facilities for pure drinking water at all times for the use of men engaged on

the works and shall remove and clear away the same on completion of the works.

Adequate precautions shall be taken by the contractor to prevent nuisance of any kind

on the works or the lands adjoining the same.

The contractor shall arrange to provide first-aid treatment to the labourers engaged on

the works. He shall within 24 hours of the occurrence of any accident at or about the

site or in connection with execution of the works, report such accident to the Bank and

also the competent authority where such report is required by law.

24. DISMISSAL OF WORKMEN

The contractor shall at the request of the Bank / Architect immediately dismiss from

the works, any person employed thereon by him who may in the opinion of the Bank /

Architect incompetent or misconduct himself and such person shall not be engaged

again. Such discharges shall not be the basis of any claim for compensation or damages

against the Bank or any of their officer or employee.

25. ACCESS TO WORK

The Bank / Architect and their responsible representative shall at all reasonable times have

free access to the works and/ or to the workshops, factories or other places where

materials are being prepared or constructed for the work and also to any place where the

materials are lying or from where they are being obtained the contractor shall give every

facility to the Bank, the Architect and their representative necessary for inspection and

examination and test of the materials and the workmanship. No. Persons not authorized by

the Bank or the Architect except the representatives of Public Authorities shall be allowed

on the works at any time.

53

SIGN & SEAL OF CONTRACTOR

26. ASSIGNMENT / SUB-LETTING

The whole of the works included in the contract shall be executed by the contractor

and the contractor shall not directly or indirectly transfer, assign, or under-let the

contract or any part share there of or any interest therein without the prior written

consent of the Bank and no undertaking shall relive the contractor of the full and

entire responsibility of the contract or from active superintendence of works during

their progress. Central Govt. / State Govt. companies shall not be allowed to sublet

the work on back-to-back basis / labour basis without approval from the Bank. In case,

in case contractor sub-let the work, the bank will be entitled to deduct 10% of cost of

work executed besides initiating other measures provided in the contract.

27. VARIATIONS

No alterations, omissions or variations shall vitiate this contract, but in case the

Architect thinks proper at any time during, the progress of the works to make any

alterations in, or additions to or omissions from, the work or any alteration in the kind

or quality of materials to be use therein and shall give notice thereof in writing under

his hand to the contractor, the contractor shall alter, add to, or omit from, as the case

may be, in accordance with such notice, but the contractor shall not do any work extra

to or make any alterations or additions to or omissions from the works or any

deviations from any of the provisions of the contract, stipulation specifications or

contract drawings without the previous consent in writing of the Architect /Architect /

bank and the values of such extras, alternations, additions or omissions shall in all

cases be determine by the Architect with the prior approval in writing of the Bank in

accordance with the provision of the Clause hereof, and the same shall be added to, or

deducted from the contract amount, as the case may be accordingly.

54

SIGN & SEAL OF CONTRACTOR

28. SCHEDULE OF QUANTITIES

The Schedule of quantities, unless otherwise stated shall be deemed to have been

prepared in accordance with the standard method of quantity measurement.

Any error in description or in quantity or in omission of items from the Schedule of

quantities shall not vitiate this contract but shall rectified and the value thereof shall

be added to or deducted, from the contract amount (as the case may be), provided

that no rectification of errors, if any, shall be allowed in the contractors Schedule of

rates.

The contractor shall be deemed to have satisfied himself before tendering as to the

correctness and sufficiency of this tender for the works and the prices stated in the

Schedule or quantities and or the schedule of rates and prices which rates and prices

shall cover all his obligations under the contract and all matters and things necessary

for the proper completion of works.

The quantities of work may vary to any extent or may be omitted; the contractor

cannot claim loss of profit / overhead on this account.

29. MEASUREMENT OF WORKS

(i) The Architect may from time to time intimate to the contractor and the Bank that he

requires works to be measured, and the contractor shall forth with attend or send a

qualified agent to assist the Architect in taking such measurements and calculations

and to furnish all the particulars or to give all assistance required by any of them.

(ii) The Engineer will take measurement of the work jointly with the contractor and enter

the same in measurement books. Based on these measurements the contractor will raise

the bill as per the prescribed format. Architect to verify the bill/measurement and issue

certificate stating that the work completed is as per the specifications and the

measurement claimed for the works, are actually executed at site. This certificate shall

be issued within 7 days after bill submission by the Contractor. The bank to release bill

amount within 10 days. If for some reason checking of the bill / measurement is not

completed, 75% of the bill amount at least shall be released within 10 days and the

balance within 30 days.

(iii) Should the contractor not attend or neglect or omit to send such agent then the

measurement taken by the Architect or a person approved by him shall be final and

binding on the contractors.

(iv) The contractor or his also supply without charge the requisite number of persons with

means and materials necessary for the purpose of measurements or examinations at

any time and from time to time of the work or counting weighting of the materials,

etc.

(v) All authorized extra works, omissions and all variations made without the Architect‟s

knowledge, if subsequently sanctioned by him in writing (with the prior approval in

writing of the Bank) shall be included in such measurement.

55

SIGN & SEAL OF CONTRACTOR

(vi) Measurements shall be recorded as per IS 1200 mode measurement and in metric

system. Measurement shall be recorded in 100 pages bounded measurement book to be

supplied by Union Bank of India. Such measurement shall be recorded by the Engineer

or Bank‟s officer and not by contractor. M.B. shall be kept in the custody of the

Architect/ Bank.

30. PROCEDURE FOR MEASUREMENT AND BILLING OF WORK IN PROGRESS:

a. Advance against materials brought at Site:

Contractor may be allowed Secured advance on security for materials brought to site

for execution on contracted item of work to the extent of 75% of the value of the

materials (as detailed in terms of payment) provided that the materials of the

imperishable nature is safeguarded against losses due to the contractor postponing

execution of the work or to the storage or misuse the materials and against the

expenses entitled for their proper watch and safe custody. Recoveries of advances so

made would be from running bills. The secured advance may be given against the

following materials brought to the site and stored properly.

i) Cables, wires, electrical fixtures, switches and non-perishable material as decided

by the Bank/Architect.

The Contractors will have to submit the bills for the materials purchased, in triplicate,

to verify the cost of the materials purchased and brought at Site.

No advances against perishable materials purchased and brought at Site will be made.

The Contractors will have to keep the materials at Site under their safe custody and

at their risk and cost.

The Bank is not responsible for damages and losses of such materials brought at site.

The contractor to submit undertaking marking lien on the material brought at

site against which bank has granted advance payment.

56

SIGN & SEAL OF CONTRACTOR

31. PROCEDURE FOR MEASUREMENT AND BILLING OF WORK IN PROGRESS:

a. Advance against materials brought at Site:

Contractor may be allowed Secured advance on security for materials brought to site

for execution on contracted item of work to the extent of 75% of the value of the

materials (as detailed in terms of payment) provided that the materials of the

imperishable nature is safeguarded against losses due to the contractor postponing

execution of the work or to the storage or misuse the materials and against the

expenses entitled for their proper watch and safe custody. Recoveries of advances so

made would be from running bills. The secured advance may be given against the

following materials brought to the site and stored properly.

a. Cables, wires, electrical fixtures, switches and non-perishable material as

decided by the Bank/Architect.

The Contractors will have to submit the bills for the materials purchased, in triplicate,

to verify the cost of the materials purchased and brought at Site.

No advances against perishable materials purchased and brought at Site will be made.

The Contractors will have to keep the materials at Site under their safe custody and

at their risk and cost.

The Bank is not responsible for damages and losses of such materials brought at site.

The contractor to submit undertaking marking lien on the material brought at

site against which bank has granted advance payment.

b. Running Account Payments to be regarded as Advances:

All running account payments shall be regarded as payments by way of advance against

the final payment only and not as payments for work actually done and completed and

accepted and shall not preclude the requiring of bad, unsound and imperfect or

unskilled work to be removed and taken away and reconstructed or re-erected or be

considered as an admission of the due performance of the contract, or any part

thereof, in this respect, or the accruing of any claim, nor shall it conclude, determine

or effect in any way the powers of the bank / Architect under these conditions or any

of them as to the powers of the bank / Architect under these conditions or any of them

as to the final settlement and adjustment of the accounts or otherwise, or in any other

way vary/affect the contract. The final bill shall be submitted by the contractor within

two months of the date fixed for completion of the work, otherwise the Architect /

Engineer-in-charge‟s certificate of the measurement and of the total amount payable for

the work accordingly shall be final and binding on all parties.

57

SIGN & SEAL OF CONTRACTOR

31. COMPLETION CERTIFICATE

(i) APPLICATION FOR COMPLETION CERTIFICATE

The Architect /Engineer-In-Charge shall normally issue to the contractor the

completion certificate within one month after receiving, an application thereof from

the contractor and after verifying from the completion documents and satisfying

himself that the work has been completed in accordance with and as set out in the

construction and erection drawing and contract documents.

The contractor, after obtaining the completion certificate, is eligible to present the

final bill for the work executed by him under the terms of contract.

(ii) Completion Certificate

Within one month of the completion of the work in all respects, the Contractor shall be

furnished with a certificate by the Architect / Engineer-In-Charge of such completion

but no certificate shall be given nor shall the work be deemed to have been completed

until all scaffolding, surplus materials and rubbish is cleared of the site completely.

The work will not be considered as complete and taken over by the Bank, until all the

temporary works, labour and staff colonies etc., constructed, are removed and the

works site cleared to the satisfaction of the Architect / Engineer.

If the Contractor shall fail to comply with the requirements of this clause on or before

the date fixed for the completion of the work, the Architect / Engineer-In-Charge may

at the expenses of the contractor remove such scaffolding, surplus materials and

rubbish and dispose off the same as he thinks fit and clean up the site and the

contractor shall forthwith pay the employer for all expenses so incurred and shall have

no claim in respect of any such scaffolding or surplus materials as aforesaid except of

any sum actually realized by the sale thereof.

58

SIGN & SEAL OF CONTRACTOR

(iii) CERTIFICATE (to be issued by the Architect / engineer) It is certified that various

items of works claimed in the

……………………………… RA Bill by Contractor ………………………………. has been completed to

the extent claimed and at appropriate rates and that the items are in accordance with

and fully confirming to he standard and/or prescribed specifications and drawings.

Quality and rates verified. The material supplied and work done conform tender

specifications. We further

certify that we have checked the measurement to the extent of 100 per cent of

each item claimed in this bill. As net amount of Rs………………

(Rupees ……………………………) is recommended to be paid to the contractor

making the total upto date payment of Rs………………………..………..

(Rs. ……………………………………………..……………………………….)

Quality and rates verified. The material supplied and

work done confirm with the tender specifications.

DATE: SITE ENGINEER/ARCHITECT

The above certification shall be endorsed in the relevant Measurement

Book also by the Architect.

iv. FORMAT FOR RUNNING BILL

ON LETTER HEAD OF CONTRACTOR

Running Bill No. …………………….

Tender Amount Rs. ……………………

Value of work done Rs. ……………………

Less rebate (-) Rs. ……………………

Net Value of work done Rs. ……………………

Extra variation items after settlement @100% Rs. ……………………

Extra variation items without settlement @75% Rs. ……………………

Total

Add: Cost of material on site @ 75% Rs. ……………………

___________________

Total payable Rs. ……………………

Deductions

1. Retention money Rs. ……………………

2. Recovery of advance if any Rs. ……………………

3. Income-tax Rs. ……………………

4. Any other Rs. ……………………

5. Total bill paid till last bill Rs. ……………………

___________________

59

SIGN & SEAL OF CONTRACTOR

Total deductions Rs. ……………………

Net payable Rs. ……………………

Amount certified for payment Rs. ……………………

Note: This page shall be signed and stamped by the Site Engineer, Contractor and

Project Architect.

v. FORMAT FOR RUNNING BILL (To be submitted by the Contractor)

I Name of the Contractor / :

Agency

II Name of the Work :

III Sr.No. of the Bill :

IV Sr.No. of the Previous Bill :

V Reference to Agreement No. :

VI Date of written order to :

commence

VII Date of Completion as per :

Agreement

VIII Date of Measurements :

XI Present status of work :

Slno. Items Description Unit Rate Qty. as per Tender

Measurement Amount Rs

1 2 3 4 5 6

60

SIGN & SEAL OF CONTRACTOR

Up to previous RA Bill Up to date gross Present bill Remark

Qty Amt. Qty. Amt. Qty. Amt.

7 8 9 10 11 12 13

Note:

1. If part rate is allowed for any item, it should be indicated with reasons for the

allowing such a rate.

If adhoc payment is made, it should be mentioned specially.

61

SIGN & SEAL OF CONTRACTOR

32. ENGINEER

The Site Engineer or any representative of the Architect / Architect, or the Bank shall

have power to give notice to the contractor or to his representative, of non-approval of

any work or materials and such work shall be suspended or the use of such materials

shall be discontinued until the decision of the Architect is obtained. The work will be

from time to time be examined by the Architect / the Bank‟s Engineer or the Architect‟s

representative, but such examination shall not in any way exonerate the Contractor

from the obligations to remedy any defects which may be found to exist at any stage of

the works or after the same is complete. Subject to the limitations of this clause, the

contractor shall take instructions only from the Architect / Bank.

33. DUTIES OF ENGINEER

1. To make a thorough study of contract documents, Architectural/Structural drawings

and other details so as to bring out ambiguities/discrepancies between them and to

obtain clarification from the Competent Authority well in time to avoid delays.

2. To render a certificate to the Competent Authority to the effect that he has

studied the contract documents, drawings and specifications.

3. To approve the centerline layout of building pegged out on site by the contractor

and the benches for ground floor and other levels.

4. To take charge of objects of value and antiquity found on site or in excavations,

immediately, after their discovery, to hold them in safe custody and to hand them over

to the Competent Authority of the Bank for further action.

5. To approve the foundation strata when the appropriate depth of excavation is

reached in consultation with the architects.

6. To ensure that the quality of materials and workmanship as laid down in the contract is

maintained and the accuracy of dimension shown on drawings is attained in the

construction.

7. To watch the validity of the building permission issued by the Local Authority and to

ensure that the revalidation, if necessary, is obtained well in time.

8. To arrange periodical reconciliation of cement and steel account and ensure that

proper recoveries are affected from contractors running account bills.

62

SIGN & SEAL OF CONTRACTOR

9. To maintain the under noted records at the site of work, in addition to normal

routine requirements of an office:

a. Daily Progress Record

b. Work Site Order Book.

c. Instruction by Bank‟s Officers.

d. Test Registers of other materials/fittings, fixtures, and equipments as Stipulated in the

tender.

e. Register of Drawings and Working Details.

f. Log Book of Defects.

g. The Site Engineer should maintain in a Hindrance Register giving details of

Commencement and removal of each hindrance.

h. Dismantled Materials Account Register.

i. To record measurements of completed work jointly with the Contractor and to

process them in running account bills.

j. To receive running account bills from the contractor and to forward them after

checking, to the Competent Authority with his comments and recommendations and

accompanied by all supporting documents.

k. To submit to the Competent Authority the Progress Report fortnightly.

10. To watch that the concerned contract does not lapse for want of extension of time.

Therefore, to keep it alive and in operation from point of consideration that “Time is the

essence of contract”.

11. To ensure that progress on every contract is in accordance with the appropriate stage

of its Time and Progress Chart.

12. To prevent contractor from proceeding with any work on which the contractor has got

intentions of raising claims of extra/deviated items, until the Competent Authority

approves the work to continue.

13. To receive the Final Bill from the contractor, to check it, and forward it with his

comments and recommendations to the Competent Authority with all the supporting

documents duly attached.

14. To submit the final summary of costs for the project to the Competent Authority.

15. To submit the Competent Authority authentic information on and the under noted

records pertaining to the completed work in order to enable the Competent Authority

to finalize them in the due course:

63

SIGN & SEAL OF CONTRACTOR

a) Record i.e. as completed drawings.

b) Record of Standard Measurements for periodical services.

c) Inventory of fittings and fixtures.

To hand over to the Competent Authority a “first draft” of “A Note of Comprehensive

Information to the User” containing detailed instructions on how to use and maintain the

completed building to the best advantage of the Bank.

34. PRICES FOR EXTRAS ETC. ASCERTAINMENT OF NON-TENDER ITEMS The contractor

may, when authorized, and shall, when directed in written by the Architect / Architect

with the approval of the Bank, add to, omit from, or vary the works shown upon the

drawings, or described in the specification or included in the schedule of quantities,

but contractor shall make no addition, omission or variation without such authorization

or direction. A verbal authority or direction by the Architect / Architect shall, if

confirmed by them in written seven days, be deemed to have been given in writing.

Any such extra is herein referred to as authorized extra and shall be made in

accordance with the following provisions.

(a) (i) The net rates or prices in the original tender shall determine the valuations of the

extra tender shall determine the valuation of the extra work where such extra work is

of similar character and executed under similar conditions as the work priced therein.

(ii) Rates for all items, wherever possible, should be derived out of the rates given

in the priced schedule of quantities.

b) The net prices of the original tender shall determine the value of the items omitted,

provided if omissions vary the conditions under which any remaining items of works are

carried out, the prices for the same shall be valued under sub-clause C hereof.

(c) Where the extra works are not of similar character and /or executed under similar

conditions as aforesaid or where the omissions vary the conditions under which any

remaining items of works are carried out or if the amount of the whole of the contract

works or to any part thereof shall be such that

(d) Where extra work cannot be properly measured or valued the contractor shall be

allowed days work prices as the priced schedule of quantities or, if not so stated, then

in accordance with the local day work rates and wages for the district; provided that

in either case vouchers specifying the daily time (and if required by the Architect, the

workman‟s name) and materials employed to be delivered for verification to the

Architect, or his representative at to the Architect or his representative at or before

the end of the week following that in which the work has been executed.

64

SIGN & SEAL OF CONTRACTOR

Actual cost of materials ………..

Rs.

Add for Labour charges ……….. Rs.

Add for Taxes, Transportation, If any.………..Rs.

Add for Wastage of Materials

(Upper Limit 5% wherever applicable)

.……..Rs.

Add for water and electricity Charges if any required, upper limit 2% of basic cost of materials. Rs. Add for 10% towards contractor‟s overheads and profit Rs. Final rate arrived. Rs

35. UNFIXED MATERIALS WHEN TAKEN INTO ACCOUNT TO BE THE PROPERTY OF

THE BANK

Where in any certificate (of which the contractor has received payment), the Architect

has included the value of any unfixed materials intended for and /or placed on adjacent

to the works, such materials shall become the property of the Bank and they shall not

be removed except for use upon the works, without the written authority of the

Architect/Bank. The contractor shall be liable for any loss of or damages to such

materials.

36. REMOVAL OF IMPROPER WORKS

The Architect/Bank shall, during the progress of the works, have power to order in

writing from time to time the removal from the work within such reasonable time or

times as may be specified in order, of any materials which in the opinion of the

Architect/Bank are not in accordance with the specifications or the instructions, the

substitution of proper materials, the removal and proper re-execution of any work

executed with materials or workmanship not in accordance with the drawings and

specification instruction and the contractor shall forthwith carry out such order at his

own cost. In case of default on the part of the contractor to carry such order, the Bank

shall have the power to employ and pay other persons to carry out the same and all

expenses consequent thereon, or incidental thereto, shall be deducted by the Bank

from any money due or that may become due, to the contractor.No certificate, which

may have been issued by the Architect, shall relive the contractor from his liability in

respect of unsound work of bad materials.

65

SIGN & SEAL OF CONTRACTOR

37. CONCEALED WORK:

The contractor shall give due notice to the Bank / architects whenever any work is to

be buried in the earth, concrete or in the bodies of walls or otherwise becoming

inaccessible later on, in order that the work may be inspected and correct dimensions

taken before such burial, in default whereof the same shall, at the opinion of the Bank

/ architect be either opened up for measurement at the contractor‟s expense or no

payment may be made for such materials. Should any dispute or differences arise after

the execution of any work as to measurements etc., or other matters which cannot be

conveniently tested or checked, the notes of the employer / architects shall be

accepted as correct and binding on the contractor.

38. DEFECTS AFTER COMPLETION

The contractor shall make good at his own cost and to the satisfactions of the Bank all

defects, shrinkage, settlements or other faults, which may appear within 12 months

after completion of the work. In default the Bank may employ and pay other persons

to amend and make good such damages, losses and expenses consequent thereon or

incidental there to shall be made good and borne by the contractor and such damages,

loss and expenses shall be recoverable from him by the Bank or may be deducted by

the Bank, in lieu of such amending and making good by the contractor, deduct from

any amount due to the contractor, a sum equivalent to the cost of amending such work

and in the event of the amount retained being insufficient, recover that from the

contractor from the amount retained as retention money together with any expenses

the Bank may have incurred in connection therewith.

39. CERTIFICATE OF VIRTUAL COMPLETION & DEFECTS LIABILITY PERIOD

The work shall not be considered as completed until the architect has certified in

writing that they have been virtually completed. The defects Liability Period shall

commence from the date indicated in the virtual completion certificate issued by the

Architect.

40. NOMINATED SUB-CONTRACTORS

All specialist, Merchants, Tradesmen and others executing any work of supplying and

fixing any goods for which prime cost prices or provisional sums are included in the

Schedule of Quantities and/or Specifications who may be nominated or selected by the

Architect/ Bank are hereby declared to be Sub-Contractors employed by the

Contractors and are herein referred to as nominated Sub-Contractors.

No nominated Sub-Contractor shall be employed on or in connection with the works

against whom the Contractor shall make reasonable objection or (save where the

Architect and Contractor shall otherwise agree) who will not enter into a Contract

providing: -

66

SIGN & SEAL OF CONTRACTOR

a. That the nominated Sub-Contractor shall indemnify the Contractor against the same

obligations in respect of the Sub-Contract as the Contractor is under in respect of this

contract.

b. That the nominated Sub-Contractor shall indemnify the Contractor against claims in

respect of any negligence by the Sub-Contractor, his servants or agents or any misuse

by him or them of any scaffolding or other plant, the property of the Contractor or

under any workmen‟s

Compensation Act in force.

c. Payment shall be made to the nominated Sub-Contractor within fourteen days of his

receipt of the Architect‟s Certificates provided that before any certificate is issued, the

contractor shall upon request furnish to the architect proof that all nominated Sub-

Contractor‟s accounts included in the previous Certificate have been duly discharged; in

default whereof the Employer may pay the same upon a Certificate or the Architect

and deduct the amount thereof from any sums due to the Contractor. The exercise of

this power shall not create privacy of Contract as between Employer and Sub-

Contractor.

41. OTHER PERSONS ENGAGED BY THE BANK

The Bank reserves the right to execute any part of the work included in this contract

by other agency or persons and contractor shall allow all reasonable facilities and use

of his scaffolding for the execution of such work. The main contractor shall extend all

co-operations in this regard.

67

SIGN & SEAL OF CONTRACTOR

42. INSURANCE

a. IN RESPECT OF DAMAGE TO PERSONS AND PROPERTY

(i) The contractor shall be responsible for all injury to the work or to persons, animals or

things, and for all damages to the structural and / or decorative part of the property which

may arise from the operation or neglect of himself or of any nominated sub-contractor or

any of his / sub-contractor‟s employee, whether such damage/ injury arises from carelessness,

accident or any other cause whatsoever in any way connected in the carrying out of this

contract. This clause shall be held to include inter alias, any damage to buildings, whether

immediately adjacent or otherwise, and any damage to the roads, streets, foot-paths,

bridge or ways as well as damage caused to the building and work forming the subject of this

contract by rain, wind or other inclement of the weather. The contractor shall indemnify the

Bank and hold it harmless in respect of all and any expense arising from such injury or

damage to persons or property as aforesaid and also in respect of any claim made in respect

of injury and damage under any Act of any Legislature or otherwise and also in respect of

any award of compensation or damage consequent upon such claims.

(ii) The contractor shall reinstate all damage of every sort mentioned in this clause, so as

to deliver up the whole of the contract works complete and perfect in every respect

and so as to make good or otherwise satisfy all claims for damage to the property or

third parties.

(iii) The contractor shall indemnify the Bank against all claims which may be made against

the Bank by any member of the Public or third party in respect of any thing which may

arise in respect of the works or in consequence thereof and shall at his own expense

arrange to effect and maintain, until the virtual completion of the contract, with an

approved office, a Policy of Insurance in the name of the Bank and the contractor

against such risks and deposit such policies with the Bank from time to time during the

currency of this contract. The contractor will also similarly indemnify the Bank of all

claims which may be made upon the Bank whether under the Workmen‟s Compensation

Act or any other statute in force during the currency of this contract or at common law

in respect of any employee of the contractor or any sub-contractor and shall at his own

expense effect and maintain, until the virtual completion of the contract, with an

approved office, a Policy of Insurance in the joint name of the Bank and the Contractor

against such risks and deposit such policy or policies with the Bank from time to time

during the currency of the contract.

(iv) The contractor shall be responsible for any liability which may be excluded from the

Insurance Policies above referred to and also for all other damages to any person

animal or property arising out of incidental or defective carry in out of this contract.

He shall also indemnify the Bank in respect of any cost, charges or expenses arising out

of claims or proceeding and also in respect of any award of composition and damages

arising there from.

68

SIGN & SEAL OF CONTRACTOR

(iv) The Bank shall be entitled to deduct the amount of any damage, compensation, cost,

charges and expenses arising from or accruing from, or in respect of, any such claims

or damage from any or all sums due or to become due to the contractor without

prejudice to the Bank‟s other rights in respect thereof.

b. FIRE INSURANCE

(i) The Contractor shall, within fourteen days from the date of commencement of works,

insure the works at his cost and keep them insured until the virtual completion of the

contract, against loss or damage by fire and / or earthquake, flood with an office to be

approved by the Architect in the joint name of the Bank and the Contractor (the name

of the former being placed first in the policy), for the contract amount only. The

Contractor shall deposit the policy and receipts for the premium with the owner within

21days from the date of issue of work order, unless otherwise instructed by

commencement of the works, unless otherwise instructed by the Architect. In default

of the Contractor insuring as provided above, the Bank or the Architect on his behalf,

may so insure the works and may deduct the premium paid from any money due or

which may become due to the Contractor without prejudice to the other rights of the

Bank in respect of such default. In case it becomes necessary to suspend the works, the

Contractor shall as soon as the claim under the policy is settled, or work reinstated by

the Insurance office should they elect to do so, proceed with all due diligence with the

completion of the works in the same manner as though the incident had not occurred

and in all respects under the same conditions of the Contract. The contractor in case

of rebuilding or reinstatement after fire, shall be entitled to such extension of time for

completion as the Bank / Architect deemed fit.

(ii) The amount so due as aforesaid shall be the total value of the works duly executed and

of the contract materials and goods delivered upon the site for use in works upto and

including a date not more than seven days prior to the date of the said Certificate less

the amount to be retained by the Employer (as hereinafter provided) and less any

installments previously paid under this clause. Provided that such Certificate shall only

include the value of the said materials and goods as and from time to time as they are

reasonably, properly and not prematurely brought upon the site and then only if

properly stored and/or protected against weather.

c) The Contractors will have to take out following Insurance

Policies: Contractors All Risks Insurance Policy to cover-

Earthquake- Fire & Shock

Landslide/Rockslide/Subsidence.

Flood/Inundations.

Storm/Tempest/Hurricanes/Typhoon /Cyclone Collapse.

Theft/Burglary.

Damage to material brought at Site and to be subsequently used in the work.

69

SIGN & SEAL OF CONTRACTOR

Third party Insurance Policy

a. For accidental loss or damage caused to the property of other persons.

b. For fatal or non-fatal injury to any person other than insured own employees or work

men of employees of the owner of the works any other construction work thereon, or

member of the Insured‟s family or of any of the aforesaid; directly consequent upon of

solely due to the construction of any property described in the Schedule.

c. Workmen‟s Compensation Insurance.

43. ACCOUNTS RECEIPTS & VOURCHERS:

The contractor shall, upon the request of the employer furnish them with all the

invoices, accounts, receipts and other vouchers that they may require in connection

with the works under this contract. If the contractor shall use materials less than what

he is required under the contract, the value of the difference in the quantity of the

material he was required to use and that he actually used shall be deducted from his

dues. The decision of the Bank shall be final and binding on the contractor as to the

amount of materials the contractor is required to use for any work under this contract.

45. LIQUIDATED DAMAGES / DAMAGES FOR NON-COMPLETION

If the Contractor fails to complete the works by the date stated in the Appendix or

within any extended time and the Architect certifies in writing that in his opinion, the

same ought reasonably to have been completed, the Contractor shall pay the Bank

liquidated damages @ 1% of the contract amount per week of delay subject to

maximum deduction of 10% of the contract amount.

46. TOOLS, STORAGE OF MATERIALS, PROTECTIVE WORKS AND SITE

OFFICE REQUIREMENTS

i) The contractor shall provide, fix up and maintain in an approved position proper office

accommodation for the contractor‟s representative and staff which offices shall be open

at all reasonable hours to receive instruction notices or communications and clear

away on completion of the works and make good all work disturbed.

ii) All drawings maintained on the site are to be carefully mounted on Boards of

appropriate size and covered with a coat of approved varnish. They are to be protected

from ravages of termites, ants and other insects.

Iii) The contractor shall provide at his own cost all-artificial light required for the work and

to enable other contractors and sub-contractors to complete the work within the

specified time.

70

SIGN & SEAL OF CONTRACTOR

iv) The contractor shall provide a suitable temporary hut for the watchmen and clear

away the same when no longer required and to provide all necessary attendance,

lights, etc. required.

v) The contractor shall arrange for temporary latrines for the use of workers and

field staff and keep the same in a clean and sanitary condition to the

satisfaction of the Public Health Authorities and shall cause such latrines and

soil to be cleared away whenever necessary and shall make good all the works

disturbed by these conveniences.

v) Every precaution shall be taken by the contractor to prevent the breeding of

mosquitoes on the works during the construction and all receptacles, cisterns,

water tans, etc., used for the storage of water must be suitably protected against

breeding of mosquitoes. The contractor shall indemnify the Employer against any

breach of rules in respect of anti-malarial measures.

vi) The contractor shall not fix or place any placards or advertisement of any

description or permit the same to be fixed or placed in or upon any boarding,

gantry, building structure other than those approved by the Bank.

71

SIGN & SEAL OF CONTRACTOR

47. PROTECTIVE MEASURES

The contractor from the time of being placed in possession of the site must make

suitable arrangements for watching, lighting and protecting the work, the site

and surrounding property by day, by night, on Sundays and other holidays.

Contractor shall indemnify the Bank against any possible damage to the building,

roads or members of the public in course of execution of the work.

The contractor shall provide necessary temporary enclosures, gates, entrances, etc. for

the protection of the work and materials and for altering and adoption the same as

may be required and removing on completion of the works and making good all works

disturbed.

Storage of materials: The contractor shall provide and maintain proper sheds for

theproper storage and adequate protection of the materials etc. and other work that

may be executed on the site including the tools and materials of sub-contractors and

remove same on completion.

Cement godown shall be constructed for storing about six weeks‟ requirement of

cement and stored as per norms with a stack of 10 bags each and 2 feet opening all

around with 2 feet passage of each stack. Structure shall be water-proof from all

the sides and top. Cement should be stored one feet above the ground level and

have pucca raised floor.

So also, reinforcement bars are to be stored above the ground level to prevent the

same from getting rusted.

Tools: Theodolite levels, prismatic compass, chain, steel and metallic taps and all other

surveying instruments found necessary on the works shall be provided by the contractor

for the due performance of this contract as instructed by the site engineer

All measuring tapes shall be of steel and suitable scaffolding and ladders that may be

required for safely taking measurement shall be supplied by the contractor.

The mistries and the supervisors on the works shall carry with them always a one

meter or two-meter steel tape, a measuring tape of 30 meters, a spirit level, a plum

bob and a square and shall check the work to see that the work is being done

according to the drawing and specifications. The Site Engineer will use any or all

measuring instruments or tools belonging to the contractors as he chooses for checking

the works executed or being executed on the contract.

72

SIGN & SEAL OF CONTRACTOR

The contractor should cover in his rates for making provisions for all reasonable

facilities for the use of his scaffolding, tools and plant etc. by sub-contractors for their

work.

48. DATE OF COMMENCEMENT & COMPLETION

The Contractor shall be allowed admittance to the Site on the “Date of

Commencement” stated in the Appendix hereto, or such later date as may be specified

by the Architect / Architect and he shall there upon and forthwith begin the works and

shall regularly proceed with and complete the same (except the painting or other

decorative works the Architect /

Architect may desire to delay) on or before the “Date of Completion” stated in the

Appendix subject nevertheless to the provision for extension of time hereinafter

contained.

49. TIME OF COMPLETION, EXTENSION OF TIME & PROGRESS CHART

(i) Time of completion: The entire work is to be completed in all respects within the

stipulated period i.e. 20 Weeks. The work shall be deemed to be commenced within 7

days from the date of acceptance of work order or date of handing over of site,

whichever is later. Time is the essence of the contract and shall be strictly observed by

the contractor. The work shall not be considered as complete until the Bank /

Architects have certified in writing that this has been completed and the Defects

Liability Period shall commence from the date of such certificate.

(ii) Extension of time: If in the opinion of the Architect / Architect the work has been

delayed

(a) by force majeure; or

(b) by reason of any exceptionally inclement weather or

(c) by reason of proceedings taken or threatened by or dispute with adjoining or

neighboring owners or public authorities arising otherwise then through the Contractors

own default or

(d) by the works or delay or the other Contractors or tradesmen engaged or nominated by

the Bank or the Architect and not referred to in the Schedule of Quantities and/or

specification or

(e) by reasons of the Architect‟s instructions as per clause 2 hereof or

(f) by reason of any combination of workmen or strike or lock-out affecting any of the

building trades or

(g) in consequence of the Contractor not having received in due time necessary

instructions from the Architect for which he shall specifically applied in writing or

(h) from other cause which the Bank may consider as beyond the control of the

Contractor or

73

SIGN & SEAL OF CONTRACTOR

(i) In the event, the value of work exceeds the value of the Priced Schedule of Quantities

owing to variation, the architect may with the previous approval in writing of the Bank

make a fair and reasonable extension of time for the completion of the Contract works.

In case of such strike or lockout, the Contractor shall as soon as give written notice

thereof to the Architect / Architect, but the Contractor nevertheless constantly use his

endeavor to prevent delay and shall do all that may be reasonably required to the

satisfaction of the Architect/Bank to proceed with the work and on his doing so that it

will be ground of consideration by the Bank for an extension of time as above provided.

The decision of the Bank as to the period to be allowed for an extension of time for

completion hereunder (which decision shall be final and binding on the contractor)

shall be promulgated at the conclusion of such strike or lock-out and the Bank shall

then, in the event of an extension being granted, determine and declare the final

completion date. The provision in clause with respect to payment of liquidated

damages shall, in such case, be read and construed as if the extended date fixed by

the Bank were substituted for and the damage shall be deducted accordingly.

(iii) PROGRESS OF WORK: During the period of construction the contractor shall maintain

proportionate progress on the basis of a Programme Chart submitted by the contractor

immediately before commencement of work and agreed to by the Bank / Architects.

Contractor should also include planning for procurement of scare material well in

advance and reflect the same in the Programme Chart so that there is no delay in

completion of the project

50. FAILURE BY CONTRACTOR TO COMPLY WITH ARCHITECT /

CONSUSLTANT’S INSTRUCTION

If the Contractor after receipt of written notice form the Architect / Architect requiring

compliance within ten days fails to comply with such further drawings and/or

Architect‟s instructions, the Bank may employ and pay other persons to execute any such

work whatsoever the may be necessary to give effect thereto, and all costs incurred in

connection therewith shall be recoverable from the Contractor by the Bank on the

Certificate of the Architect / Architect as a debt or may be deducted by him from any

moneys due to the Contractor.

51. Idle labour:

Whatever the reasons may be, no claim for idle labour, additional establishment cost

of hire and labour charges of tools and plants would be entertained under any

circumstances.

52. Idle labour:

Whatever the reasons may be, no claim for idle labour, additional establishment cost

of hire and labour charges of tools and plants would be entertained under any

circumstances.

74

SIGN & SEAL OF CONTRACTOR

53. Suspension:

If the contractor except on account of any legal restraint upon the Bank preventing

the continuance of the work or in the opinion of the employer shall neglect or fail to

proceed with due diligence in the performance of his part of the contract or if he shall

more than once make default, the Bank shall have the power to give notice in writing

to the contractor requiring the work to be proceeded within a reasonable manner and

with reasonable dispatch, such notice purport to be a notice under this clause.

After such notice shall have been given the contractor shall not be at liberty to

remove from the site of the works or from any ground contiguous thereto any plant

or materials to subsist from the date of such notice being given until the notice

shall have been complied with. If the contractor fails to start the work within

seven days after such notice has been given to proceed with the works as therein

prescribed, the employer may proceed as provided in clause Termination of

Contract by employer.

54. TERMINATION OF CONTRACT BY THE BANK

If the Contractor being a individual or a Firm, commits any “act of insolvency” or shall

be adjudged an Insolvent or being an Incorporate company, shall have an order for

supervision of the court and the official Assignee or the Liquidator in such acts of

insolvency and winding up, as the case may be, shall be unable within seven days after

notice to him requiring him to do so, to show the reasonable satisfaction of the

Architect that he is able to carry out and fulfill the Contract and to give security

therefore, if so required by the Architect / Architect.

OR if the Contractor (whether an individual, Firm or Incorporated Company) shall suffer

execution or other process of court attaching property to be issued to the Contractor.

OR shall suffer any payment under this Contract to be attached by or on behalf of

any of the creditors of the Contractors.

OR shall assign or sublet this Contract without the consent in writing of the Bank

first obtained.

OR shall charge or encumber this Contract or any payment due or which may

become due to the Contractor hereunder.

OR if the architect / Architect shall certify in writing to the Bank that the contractor:

i. Has abandoned the Contract, or

ii. Has failed to commence the works, or has without any lawful excuse under these

conditions suspended the progress of the works for fourteen days after receiving from

the Architect notice to proceed, or

75

SIGN & SEAL OF CONTRACTOR

iii. Has failed to proceed with the works with such due diligence and failed to make such

due progress as would enable the works to be completed within the time agreed upon,

or

iv. Has failed to remove materials from the Site or to pull down and replace work within

seven days after receiving from the architect written notice that the said materials or

work were condemned and rejected by the Architect under these conditions or,

v. Has neglected or failed persistently to observe and perform all or any of the acts,

matters or things by this Contract to be observed and performed by the contractor to

observe or perform the same.

Then and in any of the said cases the Bank may, notwithstanding any previous waiver,

after giving seven days notice in writing to the Contractor, determine the Contract but

without thereby affecting the powers of the Architect/Bank or obligations and liabilities of

the Contractor, the whole of which shall continue in force as fully as if the contract has

not been so determined, and as if the work subsequently executed had been executed by

or on behalf of the Contractor, And further, the Bank by his agent or servants may enter

upon and take possession of the work and all plant, tools, scaffoldings, shed, machinery,

steam and other power utensils and materials lying upon the premises or on the adjoining

land or roads and use the same as his own property or may employ the same by means of

his own servants and workmen in carrying on and completing the works or by the

employing

any other contractor or person or persons to complete the works and the contractor shall

not in any way interrupt or do any act, matter or thing to prevent or hinder such other

contractor or other person or persons employed for completing or finishing or using the

materials and plant for the work. When the work shall be completed or as soon as

thereafter as convenient the Architect shall give a notice to the Contractor to remove his

surplus materials and plant, and should the Contractor fail to do so within the period of

fourteen days after receipt thereof by him, the Bank may sell the same by public auction,

and give credit to the Contractor for the net amount realised. The architect shall

thereafter ascertain and certify in writing under his hand what (if anything) shall be due

or payable to, or by the employer, for the value of the said plant and materials so taken

possession of by the Bank and the expense or loss which the bank shall have been put to in

procuring the works to be completed and the amount, if any, owing to the Contractor and

the amount, which shall thereupon be paid by the Bank to the Contractor or by the

Contractor to the Bank, as the case may be and the certificate of the architect shall be

final and conclusive between the parties.

54. Certificates & payments:

The Contractor shall be paid by the Bank from time to time by installments under

Interim certificates to be issued the Architect / Architect to the Contractor on account

of the works executed when in the opinion of the Architect, work to the approximate

value named in the appendix as value of work for Interim Certificates (or less at the

reasonable discretion of the Architect / Architect has been executed in Accordance

with this

76

SIGN & SEAL OF CONTRACTOR

contract, subject, however, to a retention of the percentage of such value named in

the appendix hereto as “retention percentage from Interim Certificate”, until the total

amount retained shall reach the named in the Appendix as

“Total Retention Money”, after which time the installments shall be upto the full value

of the work subsequently so executed and fixed in the building. The Architect /

Architect may in his discretion include the Interim Certificate, such amount, as he may

consider proper on accounts of material delivered upon the site by the contractor for

use in the works. And when the works have been virtually completed and the Architect

/ Architect shall have certified in writing that they have been completed, the

55. EXCEPTED MATTERS / MATTERS TO BE FINALLY DECIDED BY THE BANK /

ARCHITECT / ARCHITECT:

The decisions, opinion, direction, certificate (except for payment) with respect to all

or any of the matters under this tender shall be final and conclusive and binding on the

parties hereto and shall be without appeal. Any other decision, opinion, direction,

certificate or valuation of the architect or any refusal of the architect to give any of

the same, shall be subject to the right of arbitration and review. The Architect to give

recommendations/ opinion in respect of interpreting the various clauses. However, the

decision from the competent authority of the bank shall be final and binding.

56. SETTLEMENT OF DISPUTES BY ARBITRATION

Wherever, in any of the documents forming part of the Contract, the Architect / Bank

has been vested with the final powers, his decision, opinion, certificate or any other

discretion shall be final conclusive and binding on the parties and shall be without

appeal. All other matters shall be subject to the right of arbitration.

All disputes or differences of any kind whatsoever save and except matters referred to

in clause 1) arising out of or in connection with the Contract, whether during the

progress of Work or after Completion and shall after written notice by either party to

the contract to the other of them and to the Bank hereinafter mentioned be referred

for adjudication to two Arbitrator, one each to be nominated by the Contractor and the

Bank, who shall thereafter appoint an Umpire. The provisions of Indian Arbitration and

Conciliation Act 1996 shall apply for the purposes.

The Work under the Contract shall, however, continue during the arbitration

proceedings and no payment due or payable to the Contractor shall be withheld on

account of such proceedings.

The Arbitrator shall be deemed to have entered on the reference on the date he issued

notice to both the parties fixing the date of the first hearing.

The Arbitrator may from time to time, with the consent of the parties, enlarge the time for making and publishing the award.

77

SIGN & SEAL OF CONTRACTOR

The Arbitrator shall give a separate award in respect of each dispute or difference

referred to him. The Arbitrator shall decide each dispute in accordance with the terms

of the contract and give a reasoned award. The venue of arbitration shall be such place

as may be fixed by the Arbitrator in his sole discretion.

The fees, if any, of the Arbitrator shall, if required to be paid before the award is

made and published, be paid half and half by each of the parties. The cost of the

reference and of the award including the fees, if any, of the Arbitrator who may direct

to and by whom and in what manner, such costs or any part thereof shall be paid and

may fix or settle and amount of costs to be so paid.

The award of the Arbitrator shall be final and binding on both the parties.

Subject to aforesaid the provisions of the Arbitration & Conciliation Act 1996 or any

statutory modification or re-enactment thereof and the rules made thereunder, and for

the time being in force, shall apply to the arbitration proceeding under this clause.

The Bank and the Contractor hereby also agree that arbitration under clause shall be a

condition precedent to any right to action under the contract with regard to the

matters hereby expressly agreed to be so referred to arbitration.

The Bank and the contractor hereby also agree that arbitration under clause shall be a

condition precedent to any right to action under the contract with regard to the

matters hereby expressly agreed to be so referred to arbitration.

Jurisdiction: All matters arising out of or in any way connected with this contract

shallbe deemed to have arisen in BENGALURU and only the courts in BENGALURU shall

have jurisdiction to determine the same.

57. RIGHT OF TECHNICAL SCRUTINY OF FINAL BILL

The Bank shall have right to cause a technical examination of the works and the final bill

of the works and the final bill of the contractor including all supporting vouchers, abstracts,

etc., to be made at the time of payment of the final bill. If as a result of this examination or

otherwise any sum is found to have been overpaid or over certified, it shall be lawful for

the Bank to recover the sum. The Bank reserves the right to alter / reduce amount certified

by Architect / Engineer, if noticed that certification is not proper.

78

SIGN & SEAL OF CONTRACTOR

The subject wok will be scrutinized by the Chief Technical Examiner‟s

Office, a technical wing of Central Vigilance Commission and other Vigilance and Audit

Authorities of the Bank. Decision of this Authority shall be binding on the contractor.

Any discrepancy noted defected shall be rectified by the contractor free of cost or

appropriate amount will be recovered from the contractor‟s payment.

58. BANK ENTITLED TO RECOVER COMPENSATION PAID TO WORKMEN:

The Bank is obliged, by the virtue of the provisions of the workmen‟s compensation Act,

1923, or any statutory modification or re-enactment thereof to pay compensation to a

workman employed by the contractor in execution of the works, the Bank shall be

entitled to recover from the contractor the amount of compensation so paid, and

without prejudice to the rights of the bank under said Act. The Bank shall be at liberty

to recover such amount or any part thereof by deducting it from the security deposit or

from any sum due to the contractor under this contract or otherwise. The bank shall

not be bound to contest any claim made against it under the said Act, except on

written request of the contractor and upon his giving to the bank full security to the

satisfaction of the Bank for all costs for which the Bank might become liable in

consequence of contesting such claim.

59. ABANDONMENT OF WORKS:

If at any time after the acceptance of the Tender, the Employer shall for any reasons

whatsoever not require the whole or any part of the works to be carried out, the

Architect / Bank shall give notice in writing to the contractor who shall have no claim

to any payment of compensation or otherwise whatsoever on account of any profit or

advantage which be might have derived from the execution of the whole works but

which did not derived in consequence of the foreclosure of the whole or part of the

work.

60. RETURN OF SURPLUS MATERIALS: Notwithstanding anything to the contrary contained in any or all the clauses of this

contract, where any material for the execution of the contract is procured with the

assistance of the Bank by purchase made under orders or permits or licenses issued by

the Government, the contractor shall hold the said materials economically and solely

for the purpose of the contract and not dispose of them without the prior written

permission of the bank, if required by the Bank, at the price to be determined by the

Architect having due regard to the condition of the materials, the price to be

determined not to exceed the purchase price thereof inclusive of Sales Tax, Octroi

Duty and other such levies paid by the contractor in respect thereof. In event of the

breach of the aforesaid condition, the contractor shall, in addition to being liable to

action for contravention of the terms of license or permit and /or criminal breach of

trust, be liable to Bank for all such moneys, advantage or profits resulting or which in

the usual course would have resulted to him by reason of such breach.

79

SIGN & SEAL OF CONTRACTOR

61. RIGHTOF BANK TO TERMINATE CONTRACT IN THE EVENT OF DEATH

OF CONTRACTOR IF INDIVIDUAL.

Without prejudice to any of the rights or remedies under this contract, if the

contractor, being individual dies, the Bank shall have the option of terminating the

contract without incurring any liability for such termination.

62. Security arrangement at Site

Upon taking possession of the site, the contractor shall make arrangement of security

by posting required number of security guards and flood light arrangement.

80

SIGN & SEAL OF CONTRACTOR

11. APPENDIX / MEMORANDUM TO CONDITIONS OF CONTRACT

Estimated cost Rs.25,95,000/-

EMD EMD shall be Rs. 26,000.00 /-payable in form of

Demand Draft / Pay Order favoring Union Bank of

India payable at BENGALURU or BG till completion

of work assigned.

The amount of ISD shall be 2% i.e. Rs52,000/- (1 %

Initial security deposit EMD+1% security deposit) of the accepted value of the

tender including EMD

Date of commencement 7th

day from the date of acceptance of work order

OR date of site possession, whichever is later.

Time for completion of As per time schedule given in tender document i.e.

work 10 weeks.

Retention money to be 8% of the certified gross value of each running bill,

deducted from the bills. till accumulating total security deposit including

ISD.

Total Security Deposit 10% (2%-Initial security deposit+8% Retention

money) of Contract amount / value of final bill

Whichever is maximum.

Defect Liability Period Twelve months from the virtual completion.

However, if all the works or more than one works

awarded to one contractor the defects liability

period will be reckoned from the date of virtual

Completion of last work.

Period Of Final 1 months.

Measurement

Liquidated damages Shall be 1% of contact amount per week of delay

subject to ceiling of 10 % of the accepted contract

Amount.

Period for honouring Final 6 Weeks from the date of receipt of final certificate

Certificate from the Site Engineer/Architect in charge

Recovery towards taxes. As per rules applicable from time to time.

As per work completed at site after submission of

running bill the payment will be made to the contractor

after certification of Bank’s site engineer and Project

Terms of Payment Architect.

81

SIGN & SEAL OF CONTRACTOR

12. SAFETY CODE

1. Personal Safety Equipments:

a. All necessary personal safety equipment as considered adequate by the Engineer

should be kept available for the use of the person employed on the site and

maintained in a condition suitable for immediate use, the contractor should take

adequate steps to ensure proper use of equipment by those concerned.

b. Those engaged in welding works shall be provided with welder‟s protective eyesight lids.

c. The contractor shall not employ men below the age of 18 years and women on the

work in any form.

d. When the work done near any public place where there is risk of drawings all necessary

equipments should be provided and kept ready for use and all necessary steps taken

for prompt rescue of any person in danger and adequate provision should be made for

prompt first aid treatment of all injuries likely to be sustained during the course of the

work.

e. These shall be of good mechanical constructions sound material and adequate strength

and free from patent defect and shall be kept in good repair and in good working

order.

f. Every rope used in hoisting or lowering materials or as means of suspension shall be of

durable quality and adequate strength and free from patent defects.

g. Every crane driver or hoisting appliance operator shall be properly qualified and no

person under the age of 21 years shall be in charge of any hoisting including any

scaffolding winch or give signals to operator.

h. In case of every hoisting machine and of every chain ring hook, shackle shovel and

pulley block used in hoisting or as means of suspension the safe working load shall be

ascertained by adequate means. Every hoisting machine and all gear referred to above

shall be plainly marked with the safe working load. In case of a hoisting machine

having a variable safe working load, each safe working load and the conditions under

which it is applicable shall be clearly indicated. No part of any machine or any gear

referred to above in this paragraph shall be loaded beyond the safe working load

except for the purpose of testing.

i. In case of departmental machines, the safe working load shall be notified by the

Engineer. As regards contractor‟s machines, the contactor shall notify the safe working

load of the machine to the Engineer whenever he brings any machinery to site of work

and get verified by the Engineer concerned.

82

SIGN & SEAL OF CONTRACTOR

j. Motors, gearing, transmission, electrical wiring and other dangerous parts of hoisting

appliances should be provided with efficient safeguards. Hoisting appliances should be

provided with such means as will reduce to the minimum of the risk of any part of a

suspended load becoming accidentally displaced. When workers are employed on

electrical installations which are already energized, insulating mats, wearing apparel,

such as gloves, sleeves and boots as may be necessary, should be provided. The

workers should not wear any rings, watches and carry keys or other materials, which

are good conductors of electricity.

k. All scaffolds, ladders and other safety devices mentioned or described herein shall be

maintained in safe condition and no scaffold, ladder or equipment shall be altered or

removed while it is in use.

Adequate washing facilities should be provided at or near places of work.

l. These safety provisions should be brought to the notice of all concerned by display on a

notice board at a prominent place at work spot. The person responsible for compliance

of the safety code shall be named therein by the contractor.

m. To ensure effective enforcement of the rules and regulations relating to safety

precautions the arrangements made by the contractor shall be open to inspection by

the Labour Officer, Engineer of the Department or their representatives.

n. Notwithstanding the above clause there is nothing in these to exempt the contractor

from the operation of any other Act or Rule in force in India.

83

SIGN & SEAL OF CONTRACTOR

2. Electrical

a. All Electrical equipment brought to site should be checked by the site electrical

supervisor staff of Contractor, for the suitability of the equipment and certified by

them. This certificate should be prominently displayed on the equipment.

b. All electrical equipment to be properly earthed.

c. The distribution board for temporary supply to have an ELCB of 30mA capacity to be

provided for the hand tools circuits.

d. All connections through the distribution boards to be made with a plug and socket and

no loose wires, with wooden splinters.

e. All hand tools to be earthed.

f. All wielding equipments to be provided with a cutout switch.

g. The wielding cables should be of adequate length for the earthing of the job and usage

of rods etc is not permitted.

h. All wires/cables to run only above ground level at height of min 2.5 m

i. All outdoor light fixtures left unattended for the nighttime work must be checked for

water tightness.

j. While working with operating equipment they should be disconnected electrically and

the fuses to be handed over to the supervisor for safe keeping.

3. Vehicular Traffic (Applicable to vehicles owned by the Contractor)

a. All vehicles delivering the goods must be driven by licensed driver

b. Cleaners not to drive

c. The vehicle must be in good condition

d. Unsafe acts like carrying people on running boards etc. should be avoided

e. When outside vehicles come, the contractor to ensure safe discharge of goods and

send out immediately.

f. Wherever possible all heavy machinery and equipment to be unloaded using a crane,

or a derrick.

4. Material Handling

a. All heavy equipment to be unloaded using a crane of a derrick only.

b. All lifting tackles, chain pulley blocks, chain pulley blocks, slings, ropes, webs

and any part lifting a load, must be tested yearly, for safe carrying capacity.

This certificate to be carried in a file by the contractor with identification marks

of the item.

c. Wheel barrows / handcarts to be used for transportation of items within the

site.

84

SIGN & SEAL OF CONTRACTOR

5. Violation

a. Any violations of safety norms will be viewed very seriously by Employer.

For minor violations, the contractor will be fined and the fines deducted from the

outstanding bills. If the major violations recur, then the contract will be terminated.

Indemnity Clause

The seller shall be responsible for and bound to make good and relieve the Buyer from

any reliability loss or claim whatsoever in respect of injuries (whether fatal or

otherwise) to any person or any loss or injury or damage to any property real or

personal (whether belonging to the buyer or to any other part) arising out of or in the

course of or caused by the execution of the work contracted for and shall indemnify

the buyer against all actions, costs and expenses whatsoever by reason or on account

thereof.

85

SIGN & SEAL OF CONTRACTOR

PROFORMA FOR APPLICATION FOR EXTENSION OF TIME PERIOD

1. Name of Contractor :

2. Name of the work as given in the :

Agreement

3. Agreement No. :

4. Estimated tender amount :

5. Date of Commencement of work as :

per Agreement

6. Period allowed for completion of :

work as per Agreement.

7. Date of Completion stipulated in :

Agreement.

8. Period for which extension of time :

has been give previously

a) Ist extension vide Architect‟s :

/Bank‟s letter

No. Dated Month Days

b) 2nd extension vide Architect‟s : /Bank‟s letter

No. Dated Month Days

c) 3rd extension vide Architect‟s : /Bank‟s letter

No. Dated Month Days

d) 4th extension vide Architect‟s/Bank‟s : letter

No. Dated Month Days

Total extension previously given :

86

SIGN & SEAL OF CONTRACTOR

9. Reason‟s for which extensions have :

been previously given (Copies of the

previous applications should be

attached)

10. Period for which extension is applied :

for

11. Hindrances on account of which :

extension is applied for with dates

on which hindrances occurred and

the period for which these are likely

to last.

a) Serial No.

b) Nature of Hindrance

c) Date of occurrence

d) Period for which it is likely to last.

e) Period for which extension required

for this particular hindrance

f) Over lapping period if any, with

reference to item (e) above

g) Net extension applied for

h) Remarks, if any

12. Extension of time required for extra :

work

13. Details of extra work and the :

amount involved

a) Total value of extra work

b) Proportionate period of extension of

time on estimated amount put to

tender.

14. Total extension of time required for :

11 & 12

Submitted to the Architect/Bank ……………………………………………….

Date: Signature of Contractor

87

SIGN & SEAL OF CONTRACTOR

13. APPROVED LIST OF MATERIAL

Description Brand

Grey Cement (43 or 53 Grade) White Cement Putty

A.C.C, L&T, AMBUJA, Jaypee, J.K Birla White, J.K.

Birla White Putty

Steel (Thermo Mechanically Treated Steel) High strength deformed bars or mild steel reinforcement

TATA, SAIL, RINL or equivalent

Burnt Brick Masonry

Good quality locally available material approved by Engineer / Architect.

DG Set Kirloskar, Cummins,

88

SIGN & SEAL OF CONTRACTOR

14. TECHNICAL SPECIFICATIONS

1.0 EXCAVATION & FILLING

GENERAL: This item refers to the clearing of site for construction to start and excavation and filling of all

open foundations, wet or dry, for the column footings, trenches, pavements, inspection pits and

basements, plinths, areas for leveling, drainage lines, etc., Metalling refers to the aggregate layer

below floors, pavements etc.,

CLEARING THE SITE: The site of which the structure is to be built as shown on the plan and the area required

for setting out and other operations shall be cleared of all obstruction, loose stones,

materials and rubbish of all kinds, stumps, brush wood, shrubs and other growth, roots being entirely grubbed up without extra cost. The materials obtained will be the property of the

Company and the materials pronounced useful by the Architect shall be conveyed and properly

stacked within a lead of 300m and as directed by the Architect.

All holes or hollows, whether originally existing or produced by the removal of loose stones or

brushwood, shall be carefully filled up with each well rammed and leveled off up to the level of

already filled and existing ground as directed.

Trees on the site shall not be cut unless authorized by the Architect and shall not be damaged

during construction. The above work of cleaning the site shall be reckoned to be included in the

Rate paid for various items and no extra shall be paid.

EXCAVATION:

Excavation shall include careful removal of all materials of whatever nature and whether dry or

wet, necessary for the construction of work, exactly in accordance with Lines, Levels, grades and curves shown on the plans or as directed by the Architect. It shall be taken to

exact widths and levels of the lowest step of foundation / footing and the sides shall be left

to plumb where the nature of the soil permits it. Any shoring, strutting and timbering or

cutting of extra widths of trenches required for providing working space shall be done by

the contractor. The Contractor shall notify the architect before starting excavation and take

cross section levels (for purposes of measurements jointly with the Architect before the

ground is disturbed.

Bottom of the foundation shall be leveled both longitudinally and transversally or stepped

as directed, should any of the excavation be carried down to a level below the specified

level, the contractor shall fill in such extra excavation at his own cost with 1:4:8 ordinary

grade concrete will rammed in position until it is brought up to the proper level; filling in

with excavated material not being permitted for the purpose. Where such extra excavation

is necessary due to removal of loose boulders, the extra excavation and concrete for filling

shall be paid under relevant items of Bill of Quantities. The corners of the excavated pits

89

SIGN & SEAL OF CONTRACTOR

shall be made true and square and all lose debris shall be removed to the satisfaction of the

Architect. Before any foundation concrete is places, the Architect shall inspect the foundation trenches. If any loose patches as packets come to light on inspection, these

shall be dug out as directed and filled and rammed with 1:4:8 ordinary grade concrete,

just before laying the foundation concrete, all bottom of trenches shall be lightly watered and thoroughly rammed.

SHORING: Any shoring, strutting and timbering required for protecting the sides of excavation and for

ensuring the safety of workmen and equipment, shall not be paid for separately. The contractor

shall be responsible for the design of the shoring with shall however be strong enough to resist side

thrust and prevent slips, blows and damage to adjacent works and properly. It shall be removed as

directed after all the items of work for which it is required are completed.

PROTECTION AND SAFETY: Foundation pits, read blockades, obstruction and similar excavations shall be adequately fenced

and marked to avoid accidents. Adequate protective measures shall be taken to see that the foundation excavation does not affect or damage adjoining structures. All measures

required for ensuring safety of the excavation, the people working in or near the excavation and of

properly and people in the vicinity shall be taken by the contractor at his own cost, he being

entirely responsible for any injury to life and damage to property caused by his negligence or

accident due to his constructional operations.

DISPOSAL OF EXCAVATED MATERIALS:

All materials excavated from foundation or whatever kind they may be, shall be placed at a

distance more than 1.5m as directed by the Architect from the edge of the foundation. All

excavated material will remain the property of the employer. Rate for excavation shall include for

the sorting out of useful materials and stacking them separately as directed. Materials suitable for

filling or other use shall be stacked in convenient places.

Materials suitable for filling or other use shall be stacked in convenient places. Materials not useful

in any way shall be disposed off. The Architect shall be the final authority as to what is useful

rubble. The site shall be left clean of all debris at the completion of the work.

DE- WATERING:

The Rate quoted for excavation shall include bailing or pumping out all water which may accumulate in the excavation during the progress of the work either from seepage, rain or

any other cause and diverting surface flow, if any, by bund or other means. The bunds

shall be removed after their purpose is served. Pumping out water from any foundation

90

SIGN & SEAL OF CONTRACTOR

enclosure or trenches shall be done generally in such a manner as to preclude the possibility

of any damage to the foundation trenches, concrete or masonry or any adjacent structure.

The excavation shall be kept free from water:

a. During inspection and measurement.

b. When placing of concrete or masonry are in progress and until they have come above

the Natural water level.

c. Till the Architect considers that the concrete or mortar have set and hardened

Sufficiently.

d. During back filling and consolidating.

FILLING:

As filling for the foundations, plinths and area leveling in and around the site of work shall

be done from selected material from the excavation. Filling shall be done to the original

ground level or the elevation shown on the plan, or as directed by the Architect for filling, the materials shall be placed in layers of 15cm (compacted thickness) moistened and well

compacted. The contractor shall make necessary provisions for achieving the same without extra

cost.

Only when the excavated each is not adequate or suitable for fill, approved materials from outside

will be used for filling, the approved fill materials brought from outside will be paid for at the

respective item Rate.

Filling shall be done after the concrete or masonry in the foundation has full set and it

shall be done in such as manner as not to cause undue thrust on any part of the structure.

For filling in plinth payment will be made separately, at the Rates quoted in bill of

quantities. BLASTING:

No blasting shall be permitted for excavation of foundation even in rocky formation.

CLASSIFICATION OF EXCAVATED MATERIALS :

All materials encountered in the excavated shall be classified into the following classes.

a. Soils shall include Sand, Gravel, Soft Moorum, Clay, Silt and other similar soft or loose materials

and all material of earthy or sandy nature, small size stones or gravel, soft and hard moorum

etc., which can be ploughed or excavated by ordinary spaced, pick, shovel etc., without

resorting to barring , wedging and / or blasting.

b. Soft rock shall include rocks such as slate, shale, congloms- rates, all decomposed and

weathered rock, highly fissured rock, old masonry, concrete foundation and pavements and all boulders less than 0.3 cu.m which can be removed by barring, wedges etc., but not by

ordinary spade, pick shovel etc.,

91

SIGN & SEAL OF CONTRACTOR

c. Hard rock shall include all rock occurring in masses and boulders larger than 0.3 cu.m in

volume, which in the opinion of the Architect can best be removed by blasting but, on account

of restriction to blasting at this site, will have to be removed by cold chisels or wedges, line

drilling or jack hammers.

The decision of the Architect regarding the classification of soil and rock shall be final and binding.

GRADED COARSE AGGREGATE LAYER BELOW AND FLOOR, PAVEMENTS AND

PLINTH PROTECTION :

a. Graded coarse aggregate layer of thickness specified in the Bill of Quantities or shown

on the drawings shall be provided after the structural foundations and plinth

constructions have been build and the filling in the plinth has been watered and

thoroughly consolidated. Excavation for cable ducts, pits, trenches and packets other than

those for structural foundations and plinth shall be made only after the graded coarse

aggregate layer is laid and consolidated.

b. MATERIALS : The aggregate to be of the quality as specified for concrete elsewhere.

The sizes to be used are 50mm to 40mm, 40mm to 25mm, and 25mm to 20mm.

c. CONSTRUCTION PROCEDURE : The bed on which the graded coarse aggregate layer is to laid shall be cleared of all loose materials, leveled, watered and compacted and

got approved by the Architect before laying the aggregate layer.

The metal shall be mixed thoroughly in the proportion of 2 parts of 50mm metal, to 1 part

of 40mm and 25mm each. The mixing shall be done before laying the same at site. It shall

be laid in 2 layers of 11.5 thickness and each layer shall be consolidated to a thickness of 7.5cm by and 8T to 10T capacity roller. While laying, rolling and consolidating, precautions shall be taken to ensure that no damage occurs to the masonry or any other portion of

the structure. But special care shall be taken for compaction near masonry or any other

portion of the structures. Proper manual and vibratory tamping equipment shall be

employed for satisfactory compaction in such areas. Weak / hungry spots if any shall be

rectified at contractors own cost.

After the graded coarse aggregate has been thoroughly consolidated, moorum to completely

fill the interstices shall be applied gradually over the surface and dry rolling shall be done withmoorum. Finally, the surface shall be finished with a layer of moorum moistened and rolled

over, so as to provide an even surface. The maximum thickness of the finished moorum layer shall

not exceed 12mm. The quoted Rate shall include the moorum layer also.

92

SIGN & SEAL OF CONTRACTOR

2.0 CONCRETE FOR PLAIN AND REINFORCED WORKS (Ordinary grade and controlled grade):

GENERAL :

a. This item relates to the supply, preparation, placing and curing of all concrete work in plain,

and reinforced portions of works referred to under respective items in the bill of quantities.

b. Concrete for the purposes of this specification is broadly classified into two classes, viz.,

1. Ordinary grade concrete and

2. Controlled grade concrete.

These classes are defined separately elsewhere in these specifications.

c. All operations relating to mixing, placing and curing shall be subject to the approval of the

Structural Engineer and the contractor shall provide unhindered access for this purpose for

inspection and selection in samples.

d. All materials to be used in the work shall have been approved by the Structural Engineer prior

to their incorporation in the work. For this purpose, the contractor shall whenever called upon

to do so, furnish samples of materials in adequate quantities and carry out all tests on

materials and concrete specimens. Testing shall be done in close liaison with Structural

Engineer or his representative and methods of tests shall generally follow the standard methods

described in relevant Indian Standard Specification for methods of tests. All the cost of

supplying required samples of materials, preparing all samples and carrying out all tests in an

approved laboratory shall be borne by the contractor. The contractor shall install a small

laboratory at site which shall be equipped to made routine tests on concrete cubes and

materials for concrete.

No concrete work shall be cast in the absence of the Architect‟s representative.

Before placing the concrete the Structural Engineer shall have inspected and approved

all reinforcement in place form work and Centering and arrangements for concreting. At

least 24 hours notice shall be given for this Purpose. Any concrete placed in violation of

this provision Shall be rejected.

MATERIALS :

All materials used in the work shall be new and of quantities and standard specified.

Materials delivered to the work shall be equal in quality to the approved samples which

shall be deposited with the Structural Engineer at least 35 days before they are required

in the works.

93

SIGN & SEAL OF CONTRACTOR

Delivery of materials shall be made sufficiently in advance of constructional requirements to

enable further samples to be selected., and tested, if so desired by the Structural

Engineer. No material shall be used in the work until approved. Approved materials should

be stored in such a manner that by no means the qualities are changed due to any reason.

Materials failing to comply with these specification shall be immediately removed from the works

at contractor‟s cost. CEMENTS :

a. Unless otherwise stated in these specifications or drawings are approved by the

Structural Engineer, all cement to be used in the concrete shall be ordinary Portland cement

conforming to IS : 269.

b. It shall be stored in a dry place in regular piles not exceeding 10 bags high and in

such a manner that it is adequately protected from moisture and Contamination.

Different consignments shall be stacked separately so that they can be used in the order

in which they are received. If necessary, cement shall be screened at the contractor‟s

expense to remove any lumps. No cement which has become damaged shall be used in

the work.

c. Any cement stored at the site for longer that one month shall be re-tested before use,

if so ordered, if, on retesting, the cement does not comply with this specification, the

consignment from which the sample has been drawn shall be rejected and removed

from the site. The cost of removal and subsequent replacement by cement of

satisfactory quality shall be borne by the Contractor.

ADMIXTURE : No admixture shall be used in the concrete unless approved in writing by the Structural Engineer.

Approval shall be based on the evidence that with passage of time, neither the compressive

strength of concrete is reduced nor are other requisite qualities of concrete and steel impaired by

the use of such admixtures. Calcium chloride or any admixture containing this compound shall not

be used under the circumstances.

FINE AGGREGATES :

a. Fine aggregates shall consist of natural sand manufactured sand or any approved combination

thereof. The sand shall be of siliceous material, sharp, hard, strong and durable and shall be

free from adherent coating or clay, dirt, alkali, organic material, deleterious matter and

lumps, etc., in excess of the limits stated in (d) below.

94

SIGN & SEAL OF CONTRACTOR

b. GRADATION : The grading of fine aggregate shall conform to either grading zone II or grading

zone III defined in Table II, clause 4 of IS 383. Grading shall be determined in accordance with

IS 2380 (Part 1). Method of tests for Aggregates for concrete Part – 1. Particle size and shape.

c. SPECIFIC GRAVITY : Normal sand having specific gravity below 2.5 (saturated surface dry

basis ) determined in accordance with IS : 2386 (Part-III) “ Methods of tests for Aggregates for

concrete Part- III- Specific Gravity, density, voids, absorption and bulking” shall not be used

without special permission of the Engineer.

d. DELETERIOUS MATERIALS : Fine aggregate shall not contain injurious amounts of dust, clay

lumps, soft or elongated flaky particles, shale, alkali, organic matter, loam, mica and other

deleterious substance in quantities in excess of the limits of deleterious materials, given in

Table I of IS : 383.

e. ORGANIC IMPURITIES : All fine aggregates shall be free from injurious amounts of organic

matter, Aggregates, when tested in accordance with IS : 2386 (Part-II). “ Methods of Test

for Aggregates for concrete : “Part II - Estimation of Deleterious Materials and Organic

Impurities and producing a color darker than the standard shall be rejected unless, when tested

for mortar making properties the mortar develops a compressive strength at 7 and 28 days of

not less than 95% of that developed by a similar mortar made from another portion of the sand

sample which has been washed in 3% solution of sodium hydroxide followed by thorough rinsing

in water, Mortar cubes shall be made and tested in accordance with IS : 2386 (Part-VI)

Measuring Mortar Making Properties of Fine Aggregate”.

f. SOUNDNESS : When tested to find cycles of sulphate soundness test in accordance with IS:2386

(Part-V) “Methods of test for aggregate for concrete, Part-V –Soundness” and

IS:383 the weighted percentage of loss shall not be more that 8% by weight when sodium

sulphate is used and 12% when magnesium sulphate is used.

g. SCREENING AND WASHING : Natural or manufactured sand shall be prepared for use by such

screening or washing or both as necessary to remove all objectionable foreign matter which

separating the sand grains to the required size fractions. NATURAL SAND SHALL BE WASHED

UNLESS SPECIFIC WRITTEN AUTHORITY IS GIVEN BY THE STRUCTURAL ENGINEER TO USE SAND

THAT MEETS SPECIFICATION STANDARDS OF CLEANLINESS WITHOUT WASHING.

COURSE AGGREGATE :

a. SOURCES OF SUPPLY : Aggregates shall, where possible, be supplied from a sources

that normally produces aggregate satisfactory for concrete work, and if required by

the structural Engineer, the contractor shall supply evidence to this effect. If required by the

structural Engineer, the contractor shall supply samples to make preliminary tests on concrete cubes made from such aggregates.

95

SIGN & SEAL OF CONTRACTOR

b. Coarse aggregates shall generally conform to the requirements of IS:383 and shall consist of

hard, strong, durable particles of crushed stones and shall be free from elongated soft pieces,

vegetable matter and other deleterious matter. It shall have no adherent coating. Flaky and

elongated particles shall be avoided.

c. SIZE AND GRADING : Maximum size of coarse aggregates for use in reinforced concrete work

shall be limited generally to 20mm (3/4”), for the concrete used in plain concrete

work and in massive RCC members having sufficiently wide spacing of reinforcements, use of

40mm (1.5”) size graded aggregate may be permitted. In no case shall the aggregate size

exceed 1/3 times the thickness of member. The grading of coarse aggregate shall be selected

from the standard grading given in Table II of IS : 383. The method of determining the grading

of coarse aggregate shall be according to IS :2386 (Part-I). “Methods of test for aggregate for

concrete Part-I. Particle size and shape”.

d. SPECIFIC GRAVITY : Normal aggregate shall have a specific gravity (saturated surface dry basis)

not less than 2.6. Determination of specific gravity shall be done in accordance with IS:2386

(Part III) “Methods of Test for Aggregate for concrete : Part-III Specific gravity, Density, Voids,

Absorption and Bulking”.

e. DELETERIOUS MATTER : Amount of deleterious matter determined in accordance with IS:

2386 (Part-II). “Methods of Test for Aggregate for concrete : Part-II - “Estimation of

deleterious matter and organic impurities” shall not exceed the limits given in Table I of IS :

383.

f. WASHING : The coarse aggregate shall be washed if required by the Structural Engineer and

only clean fresh water shall be used for this purpose.

CARE AND STORAGE OF CONCRETE AGGREGATES :

Aggregate stock piles shall be arranged and used in a manner as to avoid excessive segregation or

contamination with other materials or with other sizes of like aggregates. To ensure that this

condition is met, any test for determining conformance to the requirements of this specification

shall be performed on samples collected from the aggregates at the point of batching.

Stock piles shall be build in successive horizontal layers of not more than 1 m thickness, with

each layer being completed before the next is started.

96

SIGN & SEAL OF CONTRACTOR

The aggregate piles shall be allowed to drain until it has reached uniform moisture content and the

last one foot of layer from the stock pile of aggregate shall not be used if the stock piles are on

ground.

WATER :

a. Water used for both mixing and curing shall be free from injurious amounts of

deleterious matter. No extra payment will be made on this account and the tests in the

Laboratory shall be done free of cost.

b. The pH value of water shall generally lie between 6 and 8 where water contains excess

of acid, alkali, sugar or salt, the Engineer may refuse to permit its use.

CLASSES OF CONCRETE :

Two classes of concrete are covered by this specifications.

a. ORDINARY GRADE CONCRETE :

1. The proportions for ordinary concrete are chosen arbitrarily as stated in Table I and the

batching of materials shall be done by volume. The cement shall be considered to occupy 35

litres per bag of 50 kg. All cement bags used in the work shall be weighed and their

quantity adjusted to 50 kg, before use at contractor‟s cost.

2. The mix proportions for each portion or the work shall be stated in the drawing and shall

be one of the proportions given in the Table I below. Each one of the mixes given in the

Table I shall give 28 days works cube strength indicated against it. The richer mix shall

be used at junctions where members of different proportions meet. Control test cubes

(15cm sides) as per IS: 516 shall be cast at the rate of 3 Nos. for every 30 cu.m or less,

concrete cast per day and tested at 28 days.

3. The water-cement ratio shall not be more than that indicated in the table I above. The cement

content in each nominal mix shown above may be increased suitably to overcome difficulties of

placement and compaction so that the water-cement ratio given above is not exceeded.

In the case of vibrated concrete, the limit of water-cement ratio given above may have to be

reduced to avoid segregation.

The above water requirements are based on the assumption that all aggregates are dry. When

moist or wet aggregates are used, water added to the batch shall be reduced suitably to

maintain the total water cement ratio as stated above. 4. Quantity of fine aggregate is based on the assumption that dry sand is used. When using moist

sand, suitable allowance shall be made for bulking so as to avoid under sanded mixes.

97

SIGN & SEAL OF CONTRACTOR

5. If the quality of materials used in the work do not give the strengths appropriate to

the mix proportions indicated in Table I above, then such concrete shall be designated

as belonging to the appropriate lower grade. Ordinary grade concrete proportioned for

a given designation as per Table I above shall not however be placed in a higher grade

on the ground that the test strengths are higher than the minimum specified. No

interpolation shall be permitted.

CONTROLLED CONCRETE :

1. All concrete used for structural applications shall be controlled grade concrete. The

concrete shall be designated by the works cube strength Kg/ cm2 at 28 days evaluated

as per clause (4) below. Thus, concrete designated as M200 shall mean concrete having

a cube strength of 200 Kg/cm2 at 28 days.

2. Mix proportions used for a particular designation of concrete shall be based on the results

of preliminary tests carried out on samples of materials proposed for use in the works.

Any of the recognized methods of mix design such as Read Note No.4 (H.M.S.O. London)

or any other approved method may be used in the design of trial mixes. Trial mixes

shall take into consideration the workability required at site for placing the concrete in

the structure. Preliminary test will have to be made if the source of the materials

changes or any changes in mix proportions are to be made in the course of construction.

3. PRELIMINARY TESTS : The cube strengths of concrete as observed during the preliminary tests

carried out under laboratory condition shall have a minimum value as mentioned in Table I. PP

23 of IS : 456- 1964.

4. WORKS CUBE TESTS : Test specimens for works cube tests shall be secured. Prepared and tested generally in accordance with IS: 516. Cubes shall preferably be cast near the point

of placing the concrete and shall be cured in a manner identical to the method used for

curing the structural member, the concrete of which they represent.

A minimum of 6 cubes shall be cast for each 3 Cmt or portion thereof, comprising of one

pour of concrete of one grade being placed. At least one half of the cubes prepared

shall be tested at 28 days in an approved laboratory at the contractor‟s cost. The

balance half may be tested at 7 days and after a suitable correlation between 7 days

and 28 days tests has been established at site, the 7 day test may be used as an

indication of trends in the quality control of concrete.

The criteria for evaluating the test results shall be as follows :

- Not more than one out of 5 consecutive cubes tested shall give a value less than the specified

strength and this reduced strength shall not be less than 90% of the specified strength and

- the average strength of the specimen tested shall not be less than the specified

strength.

98

SIGN & SEAL OF CONTRACTOR

5. All materials shall be batched by weight, except water which may be measured by volume

in graduated containers.

Cement shall be weighed separately. The accuracy of all weighing devices shall be maintained

within 1 % and the devices shall be checked periodically as directed by the Engineer. The weigh

batch machine shall be Heatley Gresham or of other approved make.

Cumulative batching of materials may be permitted provided the method of measurement given

the above specified accuracy.

All machines and methods used for batching shall be subject to the approval of the Engineer.

6. The quantity of the mixing water shall be controlled throughout the works. At least one

determination of moisture content shall be made every day, preferably just before

commencement of the concreting work. Determination of moisture content of the

aggregate shall follow the procedure given in IS: 2386 (Part III) “Methods of Test of

Aggregate for Concrete; Part III Specific Gravity, Density, Voids, Absorption and Bulking.

7. At least one test for workability shall be done for every 30 Cft of concrete cast per pour or

per day, whichever is less.

8. All controlled grade concrete shall be compacted by mechanical vibration.

BATCHING & MIXING :

a. The aggregate shall be handled from the stock piles to the batching plant/ mixer in

such a manner as to prevent segregation. Aggregate shall not get mixed with earth or

any foreign matter during the handling process.

b. The approved type of weigh batcher shall be used for proportioning the ingredients at

the mixer for all controlled concrete. Accuracy of weigh batcher as required in clause

3.3(b) (v) shall be checked periodically and at least once a week.

Proportioning of aggregates for ordinary grade concrete, proportioned by volume, may

be done in batch boxes of size which are multiples of 35 litres which shall be batched in

this case in bag lots.

All batch boxes shall be checked periodically and at least once a week for accuracy of

dimensions. Water for controlled concrete and ordinary grade concrete may be measured

either by weight or volume, volume of water may be measured either by weight or volume,

volume of water shall be measured in graduated container.

c. Mechanical batch mixers shall be used for mixing all concrete, use of manual mixing shall not

be permitted for any type of concrete. Mixers shall conform to IS: 1791. d. The contents of the hopper shall be emptied in one operation into the drum of the mixer taking care to prevent loss of cement by being blown away in high wind.

99

SIGN & SEAL OF CONTRACTOR

At the start of the day, when some mortar is likely to adhere to the walls of the drum and blades and cause the mixed batch to be harsh and stony, the proportions of coarse aggregate shall be slightly reduced for the first one or two batches.

d. The batch shall be so charged into the mixer that some water will enter in advance of

the cement and the aggregates, water shall continue to flow for a period which may

extend to the end of the first 25 percent of the specified mixing time.

e. Each batch shall be mixed thoroughly until the mixachieves uniform color and

Consistency. In no case shall the mixing time, reckoned from the time all the material

from the hopper has entered the drum be less than 1 ½ minutes.

h. The drum shall be completely emptied before the next batch is introduced.

i. Adequate mixing capacity shall be provided at the site so as to deliver continuously the

required quantities of concrete for a pour. Quantity of material mixed per batch shall not

exceed manufacturer‟s rated capacity.

PREPARATION BEFORE PLACING:

a. All sawdust, clips and other construction debris and extraneous matter shall be removed from

the interior of the forms.

b. Hardened concrete and foreign matter shall be removed from the inner surfaces of all

conveying equipment such as barrow, trucks, chutes, etc.,

c. All surfaces of concrete and semi-porous sub-grade shall be wetted and excess water drained

away before the concrete is place on it.

d. No concrete shall be placed when the temperature of the atmosphere exceeds 38 Deg. C unless

adequate arrangements are made for pre-cooling the ingredients and shutters. The

arrangements shall be subject to the Structural Engineer‟s approval.

JOINT AND EMBEDDED PARTS :

CONSTRUCTION JOINTS :

a. Construction joints shall be made at only these positions shown on the drawing or a locations

approved by the Structural Engineer.

b. The surface of the concrete at all construction joints shall be cleaned of all laitance and

loose particles of concrete and thoroughly cleaned. All surface of construction joints shall

be roughened either by wire brush just after the concrete has set or by picking so as

to expose the coarse aggregate but not to dislodge them. Immediately prior to

100

SIGN & SEAL OF CONTRACTOR

concreting, the surface of the joint shall be dampened (but not saturated). Placing of a grout

layer is not generally recommended. c. Whenever special details are given in the drawing for construction joints they shall be strictly

adhered to. No payment shall be made for construction joints.

EMBEDDED ITEMS, CUTOUTS, OPENINGS AND RECESSES:

a. All sleeves inserts anchors and embedded items required for adjacent work or for its support

shall be placed prior to concreting.

b. All other contractors, whose work is related to the concrete are must be supported by it shall

be given ample notice and opportunity to introduce and /or furnish embedded items before the

concrete is placed.

c. Voids and slots in sleeves, anchors and inserts shall be filled temporarily with readily

removable material to prevent the entry of concrete into the voids.

d. Certain embedment relating to other contractor‟s work shall have to be fabricated and fixed in

position on instructions of the Structural Engineer. Payments shall be made under the relevant

item in the Schedule of quantities.

CONVEYING :

a. Concrete shall be handled from the mixer to the place of final deposition as rapidly as possible

by methods that will prevent segregation or loss of ingredients. No concrete shall be used

which does not reach its position within 30 minutes from the time water is added to the mixer.

b. Conveying equipment shall be of size and design to ensure the optimum flow of mixed concrete

at the delivery and shall be approved. In general, all equipment shall be of non-absorbent

materials. Use of long troughs, chutes etc. shall be permitted only with the written approval of

the Structural Engineer. In case of such conveyors leads to the production of inferior quality of

concrete, the Structural Engineer may order discontinuance of their use and substitution of

alternative satisfactory methods of placing. The addition of water at any point of concrete shall

be prohibited.

DEPOSITING :

a. Concrete shall be deposited continuously in layer of such thickness that no concrete shall

be placed on concrete which has hardened sufficiently to cause formation of seams or

planes of weakness within the section. The rate of placing shall be such that the already

placed concrete which is being integrated with fresh concrete is still plastic an has not

passed the safe re-vibration limit.

101

SIGN & SEAL OF CONTRACTOR

b. Concrete shall not be permitted to drop freely from a height of more than 1.5 meter and strike

the formwork at an angle. Concrete shall be deposited as nearly as practicable in

the final position to avoid segregation due to re-handling of flowing.

c. Struts, Stays, Braces, serving temporarily to hold the forms to correct shape, position and

alignment pending the placing of concrete at their location shall be removed when the

concrete placing has reached an elevation rendering their use unnecessary. These temporary

members shall be entirely removed from the forms and not buried in the concrete.

d. When placing concrete on a slope, it shall start at the bottom. The concrete shall be

placed against the face of the previously placed concrete and not away from it.

e. Care shall be taken not to displace reinforcement an embedded parts during the placing and

compaction of concrete.

COMPACTION :

a. All concrete shall be thoroughly compacted by means of mechanical vibration. The

Structural Engineer shall remain the final deciding authority on the type of vibrators to

be used for any particular case.

b. As far as practicable, only internal vibration shall be used for compacting concrete,

unless specified otherwise, Internal-vibrators of high frequency type shall generally conform

to the requirements of IS:2505 and shall be preferably of electric or pneumatic power

driven type. Use of immersion vibrators for compacting concrete shall generally follow the

commendation of IS:3558 c. Use of other types of concrete vibrators shall be permitted only if the use of immersion

vibrators is found impractical on account of the size of members or inadequate working

clearance for the vibrating head of immersion vibrators d. Shutters vibrators, if permitted, shall generally conform to the requirements of IS:4656.

“Specification for form vibrators for concrete”. e. Adequate number of vibrating units shall be provided to compact the concrete at the rate of

placing envisaged. In order to provide against breakdown of units, sufficient

stand by units driven by alternative power units shall also be arranged. f. Only trained and experienced operators shall be permitted to handle and operate the vibrators.

102

SIGN & SEAL OF CONTRACTOR

CURING AND PROTECTION :

The concrete shall be initially protected form damage on account of impact, undue pressure,

excessive heat, drying winds and rain, etc., by covering with wet sacking, session on similar

absorbent material soon after the initial set. After the final set, the concrete shall be kept

continuously wet preferably by continuous spraying with water or by ponding for a period of at

least 10 days from the date of casting, provided the temperature of atmosphere during this period

has been continuously above 10 Deg.C. When the temperatures are lower, the structural other

methods of curing may be used only on written permission from the Structural Engineer.

FAILURE TO MEET SPECIFICATION REQUIREMENTS AND LOAD TESTING OF CONCRETE STRUCTURES :

Concrete structures constructed under this specifications shall meet all applicable requirements as

regards appearance, dimensions, strength and durability (Particularly concrete cover to

reinforcement). In the event of the failure of the structure to meet the requirements, the

Structural Engineer may reject the structure and order its removal and re- building all at contractor‟s cost or accept the same subject to satisfactory performance under load test conducted generally as per requirements to IS:456. The cost for conducting

such tests as well as provision of suitable deflect meters for measurement of deflection shall

be borne entirely by the contractor.

As an alternative to load tests, the taking out of cores from concrete in accordance with IS:

1139 and testing the same in accordance with IS:516 and using the test results in conjunction with structural analysis of the structure may also be required by the Structural

Engineer. The cost of taking out core samples and testing the same shall be borne by the

Contractor. The contractor must provide for hammer testing equipment which shall always be kept

at site.

3.0 STEEL REINFORCEMENT

GENERAL : This item covers the requirements for supply and installation of all steel reinforcement in

reinforced concrete.

MATERIAL : Classification of Steel Reinforcement Material Specifications : Items of Steel reinforcement in the Bill of quantities are classified according to the following types

of steel. a. Mild steel reinforcement : Shall cover all hot rolled mild steel bars conforming to IS:432 (Part I)

Grade I. b. High yield strength deformed bar reinforcement : Shall cover, unless stated specifically in the

specifications or drawings, either hot rolled deformed steel bars conforming to IS:1149 or cold

twisted deformed steel bars conforming to IS:1786.

103

SIGN & SEAL OF CONTRACTOR

CERTIFICATES OF TEST FOR REINFORCEMENT:

For each consignment of bar reinforcement used in the works, the contractor shall, if required by

the Structural Engineer, supply a certificate of tests performed by a recognized testing laboratory

or the manufacturer and give the ultimate strength, yield stress and elongation and the results of

cold bend test. All the tests shall be conducted in accordance with the applicable and relevant

Indian Standard Specification. If so required by the Engineer, the contractor shall arrange to get

the chemical composition of the bars tested and obtain a certificate of test results.

All the costs of sampling and testing shall be borne by the contractor.

STORAGE HANDLING AND PROTECTION:

a) Reinforcing steel different varieties and sizes shall be stored separately and in a manner

which will permit easy identification and prevent mixing up of different sizes and types.

b) Reinforcing bars shall be stored at the site in such a manner as to prevent rusting

and contamination of the surface by deleterious materials like dirt, oil, grease, paint,

etc., When placed in the work, all reinforcement shall be free of loose mill scale,

rust and any deleterious matter. However, removal of tight adhering mil scale and

mild rust is not necessary.

c) Steel reinforcement shall always be protected from damage due to impact and rough

handling.

FABRICATION, BENDING & SPLICING :

a. Bars shall be cut to size and bent to shape in according with the appropriate dimensions shown

in the drawings. When an overall or an internal dimension of bent bar is specified, the

tolerance unless otherwise specified, shall be as in Table XI of IS :2502.

b. Any excess in length supplied over the total of length of the various portions of the

bar between ends, including the specified tolerance or not shall be taken up in the end

anchorage‟s or in that portion of the bar indicated by the Structural Engineer.

c. Bars shall be bent cold gradually by machine or any other means approved by the

Structural Engineer except in case of mild steel bars larger than 28mm. If a proved by

the Structural Engineer, mild steel bars greater than 28mm dia and conforming to IS:432

only may be bent hot at cherry red heat (not exceeding 850 Deg.C). Bars bent hot shall

be allowed to cool gradually in air and shall bars shall not be hot bent.

d. Bars having cracks or splits shall be rejected.

104

SIGN & SEAL OF CONTRACTOR

e. All bars shall be properly tagged for easy identification.

f. All reinforcement shall be furnished in full length indicated in the drawing. Splicing of bars

expect those shown on the drawings will not be permitted without the written authority of the

Structural Engineer. No payment will be made for steel in the laps for splices in bars provided

for Contractor‟s convenience or at his request.

g. At a tension splice, the minimum clear distance between bars shall be maintained. Splices in

adjacent tension bars shall be staggered. At a compression splice each side of

lapped bars may be in contact but the minimum clear spacing between the splice and

an adjacent splice shall be that specified for adjacent unspliced bars.

h. In no case shall the clear distance between two adjacent bars be less than the diameter

of the bar (larger of the diameters to be considered in the adjacent bars are of different

diameters) or 6mm more than the maximum size of coarse aggregate used in the

concrete. i. Unless otherwise stated in the working drawing, provisions of clause 25.4 of IS : 456 regarding

cover to the reinforcement shall be followed.

PLACING & FASTENING :

All steel reinforcement shall be accurately placed in position shown on the drawing and

firmly held during the placing and setting of Concrete. Bars shall be tied together with

mild steel 16 swg (1.625mm) or 18 swg(1.219mm) dia annealed binding wire

(conforming to IS:280) at all intersections except where the spacing of intersections is less

than 30cm in each direction when alternate Intersections shall be tied. Binders shall

tightly embrace the bars with which they are intended to be in contact and shall be securely

held. Placing of bars on layers of fresh concrete as the work progresses shall not be permitted. Adjusting

bar spacing in concrete already poured shall not be permitted after such time when the re-

vibration of the surrounding concrete is no longer effective.

Distance of the bars from the formwork shall be maintained by approved concrete spacer blocks,

ties, hangers and other approved supports. Metal chairs which are in contact with the exterior

surface of concrete where specially allowed shall be galvanized or painted with epoxy. Layers of bars shall be supported at correct spacing by precast mortar blocks or

other equally suitable devices approved by the structural engineer. The mortar for the

precast blocks shall have the same composition as the concrete in which it is embedded

and shall have cured for at least 28 days before being place in position. The use of pebbles,

pieces of broken stone or bricks, metal pipe or wooden blocks will not be permitted.

105

SIGN & SEAL OF CONTRACTOR

No reinforcement shall be bent when in position in the work without the approval of the Structural

Engineer, whether or not it is partly embedded in concrete. Workmen will not be permitted to

crimp or bar extensions until the concrete has sufficient strength so as not be damaged and no

movement of the bar is possible.

WELDING AND COUPLING :

Field Welding of reinforcing bars will not be permitted without the written consent of the

Structural Engineer. Such approval will require identification of the type of steel used. Where

welding is permitted it shall be at suitably staggered locations and at such places where the stress

in steel in service does not exceed 75 % of the maximum permissible stress.

Procedure of welding mild steel reinforcing bars shall generally follow the requirements of IS:2751

“Code of Practice for welding of Mild steel Bars used for Reinforced Concrete Construction”.

Welders employed for this work shall have passed relevant qualification tests for welders, specified

in IS:2571. Welding of bars other than hot rolled mild steel conforming to IS:432 shall not be

permitted.

Whenever plans call for the use of couplers to join bars, such couplers to join bars, such couplers

shall have sufficient cross section to transmit the full strength of the bars. The ends of bars to be

joined by coupling shall be upset for a sufficient length so that the effective cross section after

cutting the screw threat shall not be less that the normal cross section of the bar.

The screw thread shall be IS: metric coarse pitch conforming to IS:1330 and relevant to the

diameter of bar to be coupled.

INSPECTION: No concrete shall be deposited until the structural engineer has inspected the

reinforcement in place and approved the same. Concrete placed in violation of this provision will

be rejected.

The quoted price per ton of steel reinforcement in place shall cover full compensation for

furnishing the material, labour, tools and tackle, plant and equipment, supporting devices and all

other incidental work required to complete the work as per the above specification.

Welded or coupled joints where required by the Structural Engineer or indicated on drawings shall

be counted and classified according to the diameter of bar joints and paid for at the same rate as a

lap length of the relevant bar.

Based on the “Approved for Construction” drawing showing reinforcement details, the contractors

shall prepare bar bending schedule and submit the same, for the approval of the engineer. To avoid

duplication of work and permit rechecking the approved schedule shall be deemed to represent

faithfully the information given on drawing.

106

SIGN & SEAL OF CONTRACTOR

4.0 MASONRY WORK

MATERIALS :

Bricks : Bricks shall be first class well chamber table moulded bricks of the best quality.

Thecontractor shall submit samples and have these tested and submit the test results for approval

prior to work commencement. The bricks shall have a crushing strength of not less than 45

Kg/Sq.cm when dry.

Concrete blocks: Concrete block shall be of best quality blocks confirming to IS standards. The

concrete blocks shall have the compressive strength of 50 kgs/sq.cm. The concrete blocks should

be of uniform size.

Cement : Cement for mortar shall conform to IS: 269 generally and to the requirements of clause

3.2.1 of this document. Contractor may substitute masonry cement conforming to IS : 3466

provided no change in the rate quoted for brick masonry is required.

Masonry cement conforming to IS:3466 is brought on the site, shall be stacked separately and

adequate and approved provision shall be made to prevent mixing of the same with ordinary

Portland cement conforming to IS :269.

Sand : Sand for masonry shall conform to the requirements of IS :2116. Water shall conform

to the requirements stipulated in clause 3.2.6 of IS:2116.

Mortar : The mortar for masonry shall be composed of good quality of cement and 6 parts of

dry sand proportion to volume. The mortar for half brick walls shall be good portion.

The unit measurement shall be a standard in volume (50Kg) assumed to be 35 liters (0.0354

CuM) and should be measured in boxes of suitable size. Its quantity may be corrected for

volume.

Cement and sand shall be mixed together thoroughly over clean dry platform until the

mixture is of the green color. Water shall then be added to obtaining a solution of

consistency of a stiff paste, care been taken to add just sufficient water for the purpose.

Only that quantity of mortar shall be mixed and to be placed in the work within one hour of

the mixed of the mortar unused for more than one hour from the time of mixing shall be

rejected and removed from the site.

WORKMANSHIP:

a. Only skilled and experienced masons shall take up laying the brick masonry.

b. All bricks shall be thoroughly soaked in water at least six (6) hours before they are placed at

the work. At the time of laying, the surface shall be just moist but not too wet to cause

dripping of water.

107

SIGN & SEAL OF CONTRACTOR

c. No bats or cut brick shall be used in the work unless it is absolutely necessary around irregular

openings or for adjusting the dimensions of different courses and for closures, in which case,

full bricks shall be laid at the corners, the bats being placed in the middle courses.

d. The bricks shall be laid in mortar to lines, levels and shapes as shown in the drawings,

slightly pressed and thoroughly bedded in the mortar and all joints shall be properly flushed

and completely packed with mortar so that no hollows are left. Edges of bricks shall not be

damaged during handling. Vertical joints shall not come one over the other in the adjacent

courses and shall not normally be nearer than one quarter of the brick length.

e. Fixtures, plugs, frames and doors and windows etc., shall be placed in the positions shown in

plan while laying the courses and not later by removal of bricks already laid.

f. Verticality the walls and the horizontality of the courses shall be checked frequently by means

of plumbs and spirit levels respectively.

g. Bond : Unless otherwise specified in the plans or ordered by the Architect the bond used shall

be English.

h. Joints : Joints shall not exceed 10mm in thickness. All joints shall be struck flush with

the face when placing for all the walls requiring plastered finish. Joints of brickwork

shown to be exposed in the drawing shall be raked out not less than 10mm deep when

the mortar is green to receive subsequent pointing treatment.

i. Rate of raising : The brick masonry shall not be raised more than 60cm (2‟) per day and

courses shall be raised in uniform height as for as possible. Where this is not possible,

the bricks shall be stepped so as to enable the latter courses of masonry to bond with

the former. The brickwork shall be done in stages as directed by the Architect to

ensure that the load transmitted to the structure does not exceed that for which it has

been designed.

j. Scaffolding : Scaffolding may be double or single as warranted by the working conditions.

Scaffolding may be of timber ballies, bamboos or tubular steel sections. All scaffolding shall be

built of adequate strength to support all conceivable loads likely to come on them. Put log

holes shall be made good by brick to match the face work and holes

behind shall be made good by filling solidly with 1:4:8 cement concrete.

k. Watering : All brickwork when laid shall be initially protected against hot sun and drying winds,

if necessary by covering with wet sacking or similar other absorbent material. The brick work

shall be kept wet for a period of at least 14 days after laying. At no time shall the mortar be

allowed to dry.

108

SIGN & SEAL OF CONTRACTOR

l. Bad work : Should the mortar perish, i.e., become dry or powdery through neglect of watering

or the masonry be hollow or the work done not according to plans and

specification, the work shall be pulled down and rebuilt, all at the contractor‟s cost.

j. The maximum permissible tolerances in masonry should be as specified in IS : 1905-1969 –

Table I.

Half Brick Walls/Partition walls :

Half Brick walls shall be constructed wherever shown in the drawing. These shall be all of

stretchers only and half bricks shall not be used. The mortar to be used shall be cement sand

mortar 1:4 and as per specification mentioned elsewhere. The work shall be carried out as per IS:

2212.

Reinforcements consisting of 2 bars of 8mm shall be provided after every fourth course with

concrete. The M.S. bars shall be well anchored at the ends of the partition. These bars shall be

fully embedded in concrete and overlaps if any shall be min. 12” (30cm) and shall conform to

specifications mentioned under “Steel Reinforcement”.

Whenever the height of the walls is more than 2.1M and R.C runner shall be provided if so

instructed by the Structural Engineer at the rate of one runner forever 1.5M height. The R.C.C

runner and reinforcement in the brickwork shall be included in the rate of the brick masonry.

Care shall be taken to see that the wall is not disturbed till it is full set. All scaffolding, shuttering

and form work for R.C.C work connected to the newly built wall shall be constructed with utmost

care, so that the stability of the wall is fully secured. While making the shuttering for the R.C.C

runner nailing planks to the wall shall not be permitted. While curing, the water is to be sprinkled

by the hose to the wall and not be throwing and splashing across the wall.

CONCRETE BLOCK WORK:

Hollow or solid concrete blocks shall conform to IS 2185 and shall be regular in size and shape and

of the specified strength.

Blocks shall be property cured before being brought to Site and shall have a texture such that

plaster and/or render will readily adhere to it.

The Contractor shall supply samples for the approval of the Engineer and all blocks supplied shall

conform strictly to the approved samples.

Half or three quarter size blocks may be used wherever required to make up lengths of walls but

broken blocks shall not be used. Precast concrete screen or special blocks or „jail‟ work for decorative purposes shall be as specified on the drawings or as directed by the Engineer. Sample blocks shall be submitted to the Engineer

for approval and blocks supplied shall strictly conform to the approved samples.

109

SIGN & SEAL OF CONTRACTOR

MORTAR:

Mortar shall be prepared in accordance with IS 2250. Mixes for cement mortar shall be as specified

for the respective items of work. Sand shall be natural sand in accordance with IS 383, passing a 4.75mm size IS sieve, and shall be

free from clay, shale, loam, alkali, organic and other deleterious matter and shall be of sound,

hard, clean durable particles. Sand shall be approved by the Engineer and, if so directed, shall be

thoroughly washed until it is free of any contamination.

Gauge boxes for sand shall be of such dimensions that one complete 50Kg bag of cement forms one

until.

For the preparation of cement mortar the ingredients shall first be thoroughly mixed dry. Water

shall then be added and the mixing continued until a uniform mix of the required consistency is

achieved.

Cement mortar shall preferably be machine mixed, though hand mixing in troughs may be allowed

with the approval of the Engineer. Mortar so mixed shall be used within 25 (Twenty Five) minutes

of mixing. Mortar left unused within the specified period shall be rejected and disposed of by the

Contractor to the Satisfaction of the Engineer. Re-tempering of mortar shall not be permitted.

The Contractor shall arrange at his own cost for tests on mortar samples, if so directed by the

Engineer.

WORKMANSHIP:

Block work shall be plumb, square and properly boned with broken joints. The thickness of the

courses shall be uniform with courses horizontal. All connected work shall be carried out at tone

level and no portion of the work shall be left more than one course lower than the adjacent work.

Blocks shall be laid so that all joints are well filled with mortar. Joints shall not be less than 6mm

and not more than 8mm thick. Face joints shall be raked to a minimum depth of 10mm by ranking

tools during the progress of work when the mortar is still green so as to provide a proper key of

pointing, plastering or rendering. When pointing, plastering of rendering is not required joints shall

be struck flush. For pointed block work or block work without plaster or render approved, smooth textured

concrete blocks shall be used.

Faces of block work shall be cleaned daily and all mortar droppings cleaned off and removed. Top

surfaces of each course shall be thoroughly cleaned before other courses are laid. If mortar in

lower courses has begun to set joints shall be raked out to a depth of 12mm before laying is

continued.

110

SIGN & SEAL OF CONTRACTOR

Where blocks are to be used for load bearing walls the uppermost course of blocks supporting slabs

or other structural members shall be solid or treated as directed by the Engineer.

Miscellaneous inserts in block work, e.g. sleeves, wall ties, anchors, conduits, structural steel, steel

lintels and the like shall be installed by the Contractor and these items shall be deemed to be

included in the quoted rates for block work. The supply of such inserts by the Contractor will be

paid separately in accordance with the relevant items of the Bill of Quantities.

Opening, arches, chases, pockets and the like shall be provided as shown on the drawings to

receive windows, louvers, doors frames and the like.

Wall ties and flashings shall be built into block work in accordance with the drawings and

Specifications. It shall be clearly understood that the rates quoted by the Contractor shall be

deemed to include for leaving openings, forming arches, cutting chases, pockets and the like in

block work for various trades.

COURSED RUBBLE MASONRY

GENERAL: This specifications refers to providing materials and construction of coursed rubble masonry

foundations, plinth, basement walls and superstructure.

STONES:

Stones to be used in the masonry shall generally conform to IS : 1805. They shall be trap, granite,

quartzite or genesis. The stones shall stand weathering well and when immersed in water for 24

hours shall not absorb water more than 5% of its dry weight when tested according to IS:1124. The

stone of the required quality shall be attained form quarries approved by the Architect. All stones

shall generally be freshly quarried.

The stones shall be kept free from dirt, dust, oil or any other injurious materials which may attack

the stone or mortar or prevent adhesion of mortar. Stones with skins shall not be used.

Different categories of stones such as face stone, backing stone hearting stone, headers, quoins,

etc., shall be collected in advance to suffice at least for a week‟s requirement and shall be stacked

separately category wise.

a. Face and Backing stones :

These stones shall be chisel dressed top and bottom, true and square for at least 5 cm (2”)

back from the face the rest of the width shall tail into the work and shall not project below

or above the plans of dressing. No stone shall tail to a point. The vertical joints shall be

chisel dressed for a depth of not less than 4 cm (1.5” from the face. Individual stones shall

have its length less than 1 ½ times the height.

111

SIGN & SEAL OF CONTRACTOR

The face stones and backing stones shall be selected from the mass of quarry stones for their

greater size, good beds close grain and uniform colour. 50 percent of the stones shall be more than

0.010 Cu.m (about 1/3cft.) in walls up to 50 cm. (about 20”) in thickness an 0.015 Cu.m (about

1/2cft.) in thicker walls.

b. Through Stones :

One through stone shall be provided per half square meter of facing evenly distributed. They shall

be about 0.03 sq.m (about 1.3 sq.ft) in face area and shall have a tailing of the full width of the masonry when the width is 60 cm. (about 2‟) or less. If the wall or masonry be over 60

cm. (about 2‟) in width line of headers overlapping each other by at least 15cm (about 6”) shall be

laid right through the wall from face to back. The length of the interior headers shall not be less than

45cm (about 18”) and their average cross sectional area shall not be less than 0.025 sq.m (about ¼ sq.ft). Face header shall be distinctly marked on its

face.

c. Vertical headers :

For the massive work with the width of a meter (about 3.28‟) and above, vertical headers

45cm. (about 18”) long or depth of two courses whichever is more shall be provided at the

rate of one for every sq.metre (About 10.76 sq.ft) of area in plan. For every course a new

set of headers shall be introduced at this rate in a staggered pattern. Their average sectional

area shall not be less than 0.03 sq.m (1/3 sq.ft)

d. Hearting stones : These can be rubble stones. In walls of 50cm. (about 20”) and less than 30 percent of the

stones shall not be less than 0.10 cu.m (about 1/3 cft). The hearting stones shall be hammer

dressed on the top and bottom beds. A small proportion of spills and chips can be used

to fill the hollows between the sides of the hearting stones in each course so as to avoid

thick mortar joints. However spills shall not be used for making up the height of hearting

to that of the course.

e. Quoins :

The quoins shall be of selected stone and shall normally be 19cm x 29cm (about 8” x 10” x 16”) or as

directed by the architect. The faces of quoins shall be rough tooled or provided the same type of dressing as that of the face stones as directed. Chisel draft of about 40mm (about 1

½”) shall be provided on each side of the exposed corner.

The beds and top shall be dressed square to the face and rough tooled to 10 cm. (about 4”) from the

face and vertical joints similarly dressed to 4 cm.(about 1.5”) from the face. In this embedded portion the length of the side shall not be less than that of the exposed side opposite by more than 9.8 cm (about 3”) for the longer side and 5cm (about 2”) for the shorter side.

112

SIGN & SEAL OF CONTRACTOR

MORTAR :

Cement, sand and water shall be as specified elsewhere in this document. Cement and sand shall

be mixed in specified proportions. Sand being measured in measuring boxes. The proportions will

be by volume on the basis of 50Kg. bag of cement being equal to 35 liters (about 1.2cft.). The

mortar may be hand mixed or machine mixed.

Preparation : In hand mixed mortar, cement and sand in the specified proportions shall be

thoroughly mixed, dry on a clean impervious platform by turning over at least 3 times till a

homogeneous mixture of uniform colour is obtained. Fresh and clean water as specified above shall

be added gradually through a hose and thoroughly mixed to form a stiff plastic mass of uniform

colour so that each particle of sand shall be completely covered with a film of wet cement. The

water cement ratio may be as directed by the Engineer.

Mixing platform shall be so arranged that no deleterious extraneous material shall get mixed with

mortar nor the mixing water of the mortar shall flow out. Machine mixed mortar shall be prepared

in approved mixer. About 5 percent to 10 percent of mixing water be put into the mixer and sand

and cement in the required

proportions shall be then added. The remainder of water, quantity of which shall be predetermined

by consideration of strength and consistency shall be added uniformly. Mixing will be continued

until all particles and sand are uniformly coated with cement paste. Mixing for 1 ½ to 2 minutes

will normally be sufficient. Water cement ratio will be as per hand mixed mortar. The mortar so

prepared shall be used within 30 minutes of adding water. Only such quantity of mortar shall be

prepared as can be used within 30 minutes. The mortar remaining unused after that period of

mortar which has partially hardened or is other wise damaged shall not be retempered or remixed.

It shall be destroyed or thrown away.

CONSTRUCTION :

The masonry shall be laid to lines levels, curves and shapes shown in the plans. All iron, stone,

concrete or other fixtures, plugs, frames, etc., if any, shall be built and bonded in at places shown

on the plan or as directed by the Engineer as the work proceeds and not inserted or joggled on

after the masonry is advanced. Holes of the required size and shape shall be left in the masonry

during construction itself for fixing pipes service lines or for passage of water. After the service

lines, pipes etc., are fixed the extra hollow left if any shall be filled with 1:4:8 cement concrete

and the face shall be neatly embedded in the required positions while laying the masonry. Iron

fixtures shall be embedded in 1:4:8 cement concrete.

Stones in the hearting shall be laid on their broadest face which gives better opportunity to

fill the space between stones. Stratified stones must be laid on their natural bed. All bed joints

shall be normal to the pressure upon them. The stones shall be wetted before laying in

mortar. Each mason shall be supplied by the contractor with a vessel full of water and a

113

SIGN & SEAL OF CONTRACTOR

tumbler for wetting stones, care being taken not to spill any water on green masonry. The bed

which is to receive the stone shall be cleaned. Wetted and covered with a layer of fresh mortar. All

stones shall be laid full in mortar both in bed and vertical joints and settled carefully in place with

a mallet immediately on placement and solidly bedded in mortar before it has set.

clean chips and spills, carefully selected to fit in space shall be wedged into the mortar joints

wherever necessary to avoid thick joints of mortar. In case any stone already set in mortar is

disturbed or the joint broken the stone shall be taken out without disturbing the adjoining stones

and joints and the stones reset in fresh mortar. Attempts must never be made to slide one stone

over another already laid.

Watering :All masonry shall be initially protected from sun, rain, etc., by wet hessian or strawtill

setting and thereafter kept continuously wet for 14 days from the date of laying, unless other

length of period is ordered in the special provisions. Watering shall be done carefully in the

beginning through a hose so as to wash the mortar out of the joints. On Sundays, holidays, at the close of day‟s work and other periods of cessation of work, the masonry is to be kept continuously wet for the specified period of curing and laborers are to be employed for

the purpose. Should the contractor fail to water the work to the satisfaction of the Architect, the

latter may order the masonry to be dismantled at the contractors cost.

Bad work : Should the mortar perish, i.e., become dry, white or powdery through neglect of watering or if the

masonry shows hollow joints or non-adherence of mortar to the stones or if the work does not

conform to plans and these specifications, the work must be pulled down and rebuilt at the contractors expense without any delay after the order of the Architects to do so.

Final Finish : All masonry shall be washed down on completion and all stains and adhering mortar removed

from the face as the scaffolding is being lowered and removed.

Wet foundations: In wet foundations, or other situations where water is met with, the work space shall be kept free

of water by the contractor while the masonry is in progress and until the Engineer considers the

mortar has sufficiently set. Dewatering shall be carried out in such a way as not to injure the

concrete or masonry in any way. Dewatering shall also be done when required for taking checking

measurements, passing foundation etc., Dewatering will be included in the rate of masonry.

Scaffolding : Scaffolding shall be double or single, but the ends of poles should not be placed in the position

of header stones. Scaffolding shall be erected with steel sections or pipes, bullies or

bamboos of adequate strength so as to be safe for all construction operations. The contractor

shall take all measures to ensure the safety of the work and working people. Any instruction

114

SIGN & SEAL OF CONTRACTOR

of the Architects in this respect shall also be complied with. The contractor shall be entirely

responsible for any damage to properly or injury to persons resulting from ill-erected scaffolding,

defective ladders and materials or otherwise arising out of his default in this respect. Proper

scaffolding shall be provided to allow easy approach to every part of the work. Overhead work shall

not be allowed. Put- log holes shall be made good by stones to match the face work when

scaffolding is being removed after ensuring that all holes behind are solidly filled in with 1:4:8

concrete.

Rate of raising masonry: The rate of raising coursed rubble masonry brought up in uniform levels may be limited to a height

of 60cm. (about 2‟) per day in case of cement mortar. But fresh course shall be laid over masonry

previously laid within 4 hours of its laying.

ITEM TO INCLUDE :

Coursed rubble masonry laid in cement/mortar of specified proportion, built in any position

to any height of depth and to lines, level, curved and batters shown on the plans or as

ordered by the Architects including quoins, headers etc., and striking joints and curing.

Erecting and removing all scaffolding, ladders and use of plant required for execution of the

item, safety of the labour and inspection of the work including compensation for any injury,

damage etc., Dewatering to allow construction in the dry and proper setting of masonry.

Cleaning the site round the masonry.

All labour, use of tools, materials and other items incidental to satisfactory completion of the item.

5.0 PLASTERING & POINTING

CEMENT PLASTERING WITH NEERU FINISH:

GENERAL : This specification refers to the furnishing of materials and plastering the surfaces of concrete,

brick or rubble masonry.

MATERIALS: Cement and water shall be as specified for the item of concreting. Sand shall conform to

IS:1542. Neeru shall be prepared of class „C‟ lime (i.e., pure fat lime) as mentioned in IS:712. All impurities, ashes or pieces improperly burnt shall be screened or picked out

before slaking. The lime shall be slaked with water not less than one week or more than

two weeks before use.

115

SIGN & SEAL OF CONTRACTOR

The slaked lime shall be screened through. Storage shall comply with IS:712. The slaked lime

if stored, shall be kept in a weather-proof and damp-proof closed shed with impervious floor

and sides to protect it against rain, moisture, weather and extraneous materials mixing with

it. The lime shall be used when fresh, i.e., within 14 days of its removal from kiln. All lime

that has been in any way damaged by rain, moisture, dirt, air slaking or any other cause shall

be rejected and all rejected material shall be removed from the work site forthwith. Sample

of lime shall be got approved by the Architect who shall keep it in his office for reference.

Lime shall be slaked and mixed with sufficient water to form a thick paste. It shall be reduced

to a fine paste by grinding.

It shall then be passed through a fine sieve (3mm mesh) to remove all unslaked particles and

foreign matter and allowed to mellow under water for at least 10 days in large slaking tanks. The

surplus water of the top shall be allowed to run off. The slaked lime paste thus formed shall be

used to preparing neeru.

The neeru shall be prepared by mixing together 4 parts of this lime paste and 1 part of fine sieved

sand by volume. Jute fiber finely chopped shall be added to the above mortar at the rate of 4kg. of

jute to every cu.meter of lime sand mixture (1 lb.of jute for every 4cft of lime-sand mixture). The

mixture shall then be properly ground to a fine paste.

The neeru thus prepared shall be kept moist until used and no more than what can be consumed in

15 days shall be prepared at a time. Field testing shall be carried out as specified in IS:1624 cement mortar shall have the proportion of

cement to sand as mentioned in the item.

SURFACE PREPARATION :

All joints in the face work that is to be plastered shall be raked out to a depth equal to not less

than the width of the joints or as directed by the Architect. The raking shall be done taking care

not to allow any chipping of masonry. In new work the raking out shall be done when the mortar in

the joints is still green. Smooth surfaces of concrete, old plaster etc., must be suitable roughened

to provide necessary bond for the plaster. All dirt, soot, oil paint or any other material that might

interfere with satisfactory bond shall be removed. In the case of stone masonry, bushing on the

walls to receive the plaster shall not be more than 12mm scrubbed with fresh water and kept wet

for 6 hours prior to plastering. It shall be kept damp during the progress of the work. The plastering

shall not be commenced unless the preparatory work is passed in writing by the Architect.

116

SIGN & SEAL OF CONTRACTOR

PLASTERING OPERATION :

Patches of plaster 15cm x 15cm (about 8” x8”) shall be put on about 3m (about 10‟) apart as gauges to ensure even plastering in one plans. In all plaster work the mortar, shall be firmly applied

with somewhat more than the required thickness and sell pressed into the joints and on the surface

and rubbed and leveled with a flat wooden rule to give required thickness. Long surface shall be

finished to plain or curved surfaces as shown on the plan or directed by the Architect and shall

present a neat appearance. The mortar shall adhere to the masonry surface intimately when set

and there should be no hollow sound when struck. Plastering shall be done from top- downward. In

any continuous face of a wall, finishing treatment of any type should be carried out continuously

and day to day breaks made to coincide with architectural breaks in order to avoid unsightly

junctions. All exposed angles and junctions with door frames etc., shall be carefully finished; arises

shall be beaded if ordered.

Neeru shall be applied to

the prepared and partially set but somewhat plastic surface with

steel trowel to

a thickness

slightly

exceeding 1.5mm (about 1/16”) and rubbed down

to

1.5mm

(1/6”) thickness and polished to a perfectly smooth and even finish, working from top tobottom.

While trawling is going on, soap stone power contained in thin muslin bags shall be dusted over the

surface and worked in. Moistening shall be commenced as soon as the plaster has hardened

sufficiently and is not susceptible to injury. Soaking of wall shall be avoided and only be much

water as can be readily absorbed shall be used.

All plaster work shall be kept damp continuously for a period of 14 days. To prevent excessive

evaporation on the sunny or windward side of the buildings in hot, dry weather, matting or gunny

bags may be hung over on the outside of the plaster in the beginning and kept moist. Should the

mortar of the plaster perish through neglect of watering or for any other default and if the work is

not done as specified above, the plaster shall be removed and redone at the contractor‟s expense.

PRECAUTIONS :

The standard of workmanship, shall be of the VERY BEST quality and the whole of plastering is

to be carried out in the best possible manner to the entire satisfaction of the Architect. Tools

and accessories used in plaster work shall conform of IS: 1630-1960. Metal tools shall be

cleaned after each operation. All tools shall be examined to see that they are thoroughly

cleaned before plastering is begun. The programming of other building operations before,

during and after plastering, shall be according to the instructions contained in IS:1661. All

general precautions as specified in IS :1661 clause 9, shall be taken and preparation of the

background shall be done as laid down in clause 13 of IS:1661. Care shall be taken to see

that other parts of the work or adjacent works are not damaged while plastering. Scaffolding

shall be as specified for the item of masonry.

117

SIGN & SEAL OF CONTRACTOR

GENERAL : The preparation of the surface, programming of work, general precautions and other

miscellaneous details shall be as detailed under „Neeru finished plaster‟.

Base coat : The base coat shall be of cement mortar 1:6 or otherwise specified in the item and shall

be done as given under specification. The thickness of a base coat shall be 12mm (1/2”).

Final Coat : The finishing coat shall be of cement mortar 1:4 and 6mm (1/4”) thick. The mortar shall contain

sand with slightly larger proportion of coarse material and shall be approved by the Architect. After

application, the surface shall be finished with wooden float to the correct plane. Then it shall be

treated with wetted sponge rubber by which sand particles stand out and give an even finish as

approved by the architect. A sample over a considerable area shall be first made in consultation

with the architect and shall be approved before starting the work.

Curing shall be perfect and to be continued for at least 14 days.

ROUGH CAST PLASTER :

GENERAL : The specification for sand faced plaster shall be applicable to Rough Cast Plaster also,

subject to the following:

BASE COAT :

The first coat of plaster shall be of cement mortar 1:4 mixed and applied according

to relevant provisions of IS:1661. The finished thickness of the first coat shall be 12mm

for brick masonry or concrete surfaces and 15mm for rubble stone masonry. The

plaster shall be laid by throwing the mortar (by using a strong whipping motion) on

the prepared surface with a trowel in uniform layer, and pressed to form a good

bond. The surface shall be roughened.

SECOND COAT :

The second coat shall be the rough cast mixture consisting of aggregate which may vary insize

form 5mm to 8mm and may consist of specially graded mixture mixed with fine sand and

cement. The proportion of cement to sand to aggregate shall be 1:1.5:3. It shall be flung

upon the first coat with large trowels to form an ever protective coat. The second coat must

be applied while the first coat is still soft and plastic. The work shall generally conform

to requirements IS:1661. The thickness of the coat shall be about 12mm.

118

SIGN & SEAL OF CONTRACTOR

ITEM TO INCLUDE :

As per relevant portion of specification for Neeru plaster. It shall include also the base coat and

finishing rough case plaster as above.

ORDINARY CEMENT PLASTER :

GENERAL: The preparation of the surface, programming of work, general precautions and other miscellaneous

details shall be as detailed under „Cement Plastering with Neeru finish‟.

The base coat shall be of cement mortar 1:6 or otherwise specified in the item and

shall be done as indicated under „Cement plastering with neeru finish‟. The thickness of this base coat shall be 12mm.

FINAL COAT:

The finishing coat shall be of cement mortar 1:3 and 6mm thick. After application of the mortar,

the surface shall be finished with wooden float to the correct plane. The surface shall be finished

off with a rendering of pure cement and polished. A sample over a considerable area shall be first

made in consultation with the Architect and shall be approved before starting the work.

POINTING IN MASINRY WORKS:

Type of Pointing:

Pointing, where specified, shall be of the following types, recessed, ruled, flush and raised and cut.

Surface Preparation : All joints in the face work that are to be pointed shall be raked out of a depth equal to not less

than the width of the joints or as directed by the Architect. The raking shall be done taking care

not to allow nay chipping of masonry. In new work the raking out shall be done when the mortar in

the joints is still green.

The joints shall be brushed clean of dust with wire brush and wetted thoroughly for 6 hours before

pointing is commenced.

Application and Finishing :

Specifications for cement and water shall be given for the item of concreting . Sand shall conform

to IS :1542. Cement mortar shall have the proportion of cement to sand as mentioned in the item.

The mortar shall be pressed into prepared joint with pointing trowel and finished as specified to

the dimensions as shown in the drawing. The superfluous mortar shall be cut - off from the edges of

the line sand the surface of masonry shall be cleared of all mortar

119

SIGN & SEAL OF CONTRACTOR

finish to be free of slack spots, cut faces and other blemishes. Finished work of pointing shall be to

exact size and shape stipulated and edges shall be strong neat and clear. In recessed pointing the mortar shall be simply struck of with a trowel and the work left showing

the line and the surface of the masonry themselves.

In flush pointing along horizontal joints at all courses ruled lines are formed on flushed surface to

the required size.

In case of raised pointing, it shall project from the wall facing with its edges cut parallel so as to

have a uniformly faired band about 6mm raised & width 10mm or more as directed, showing the

line and the surface of masonry themselves.

Curing:

The pointing shall be kept wet for 7 days. During this period it shall be suitably protected from all damages.

WATER PROOF PLASTER :

General : This specification refers to the furnishing of materials and plastering the surfaces of concrete,

brick or rubble masonry with water proof plaster.

Materials : Cement and water shall be as specified in IS : 3. Sand shall conform to IS : 1542.

Surface Preparation : Same as specification No. IS –7 Clause 7.13.

Plastering operation: Watering proofing compound of approved made like Fosoloc/ Foffe / Equivalent shall be mixed

with cement in proportion as recommended by the manufacturer of the water proofing compound.

Cement mortar shall have the proportions of water proofing compound, cement, and sand as

mentioned in the item. The plastering operations shall generally conform to the specifications in IS

7.1.4.

NOTE:

1. All the information and details sought above shall be furnished in

“BID" by the tenderer.

2. The above maintenance specifications and penalty is applicable during the

free maintenance period also.

120

SIGN & SEAL OF CONTRACTOR

TECHNICAL SPECIFICIATIONS FOR DIESEL GENERATOR

1.0 PREFACE

1.1 This tender is for supply and commissioning of 1 no. 200 KVA DG set with acoustic

enclosure , CPCB-II compliant and AMF (auto mains failure) panel for proposed Hostel

Block, Union Bank of India, Staff college, Bannerghatta road, Bangalore.

1.2 Consultant has been appointed by Union Bank of India, Staff College, Bannerghatta road,

Bangalore. Consultant shall prepare the necessary plans, shall give approval of drawing etc.

Consultant is entirely independent of the suppliers and contractors and does not accept any

services or benefits from them. Consultant shall represent the Client (Union Bank of India)

for the work under this contract.

1.3 Drawings and designs prepared by Consultant shall be used only for the purpose specified

in this contract and all drawings issued shall be returned to Client after completion of the

work.

1.4 The one who is awarded the contract will be the "VENDOR".

1.5 The Vendor shall supply the DG set as per Technical specification, drawings etc. and

Contract Agreement will be called "DOCUMENTS OF THE CONTRACT".

2.0 SCOPE OF WORK

2.1 This specification covers the technical requirements of design, engineering, manufacture,

assembly, testing, at works and delivery in well packed condition of silent type (with acoustic

enclosure) diesel generator set, CPCB-II compliant complete with all required accessories and

control equipment to supply continuous electrical power. The scope shall also include

Installation and Commissioning, third party inspection of the DG set, AMF panel along with

provisions for BMS out puts and supply of commissioning/mandatory spares.

This standard shall be read in conjunction with job schedule.

The scope but not limited to the following: -

(a) Diesel engine, complete with all the required accessories and components.

(b) Alternator for operation with the above diesel engine, complete with all the required

accessories and compounds.

(c) Fuel oil system comprising of fuel oil tank, supply pump, filter, piping, valves fittings

etc.

(d) Air intake system comprising of air blower, air filter, turbo charger etc.

(e) Lubrication oil system comprising of lube oil pump, filter, cooler, piping, valves

fittings etc.

(f) Jacket cooling system comprising of radiator, water circulation pump, necessary piping

and fittings etc.

(g) Starting system complete with battery, battery cable, battery charger, starter motor,

control system, local control panel on Engine. etc.

(h) All inter connecting piping, valves, fittings etc.

(i) Torsional vibration damper at the free end of the crank shaft.

(j) Speed regulation system.

(k) A common base frame suitable for assembly of engine and alternator with

their accessories. Anti vibration mounting pad shall also be supplied.

121

SIGN & SEAL OF CONTRACTOR

(l) Exhaust manifold complete with silencers, metallic expansion

bellows . Exhaust Piping shall not be included.

(m) All necessary instruments for monitoring and safe starting, running and stopping of the

D.G. set their auxiliaries complete with tubing and cabling.

(n) All safety and protective devices.

(o) Cabling material between local control panel and all equipment within the

battery limit including cables, racks, earthing terminating materials etc.

(p) Acoustic enclosure (central Pollution Control Board approved) made of 14/16 SWG

CRCA sheet steel, powder coated as per manufacturer Standarad.

(q) All other items not specified here but, necessary for safe, satisfactory and uninterrupted

operation of D.G. set.

(r) Set of special tools and tackles required for installation and maintenance.

(s) All other services for making DG set with its control and protection features complete

in all respect.

(t) Auto Mains Failure, Auto Synchronizing and Auto Load Sharing Panel.

2.2 Following services but not limited to, will form a part of Vendor‟s work and prices quoted

will be deemed to include:

a) Supply of all equipment, materials, accessories, consumable, hardware, and mandatory

spares

as well as commissioning spares.

b) Packing and forwarding of above.

c) Transporting to site.

d) Preparation of all manufacturing shop drawing / wiring drawings etc.

e) Preparation of final As Built drawings of all drawings prepared.

Note: Unloading of DG set at site shall be done by Union Bank of India.

3.0 GENERAL

3.1 Applicable Specifications

The specification for the DG set is as detailed hereinafter. These specifications shall be read

in

Conjunction with the relevant Indian Standard, Indian Electricity Rules and Chief fire

officer‟s

Recommendations and the obtainable local practice as detailed in various regional

handbooks. Wherethe specifications in any of the standards are at variance with the

Specifications detailed herein, themost stringent amongst them shall govern. Contractor shall

ensure that execution of total work is inaccordance to this.

3.2 Quality & Completeness of Supply

It is not the intent to specify completely herein all finer details of the equipment to be

supplied.

Nevertheless, the equipment shall be complete & operative in all respect and shall conform to

highest standard of engineering, design and workmanship.

Any material or accessories which may not have been specifically mentioned but which is

necessary orusual for satisfactory and trouble free operation and maintenance of the

equipment, shall be provided without any extra charge.

The vendor shall supply all branded new material & accessories, as specified herein and shall

conform to these Specifications as well as IS specification. When IS standard does not exist,

such material /sample shall be submitted for Engineer‟s approval with test certificate from

Government approved laboratories.

122

SIGN & SEAL OF CONTRACTOR

Contractor shall produce, on demand, such details as called for by the Engineer to prove

genuineness of the material.

The vendor must replace rejected materials within 7 (seven) days.

3.3 Drawings by vendor

3.3.1. For bidding

The bidder shall submit offer with the following documents in two sets.

- Schedule of deviations from technical specifications.

- List of proposed makes, for the items listed in the tender.

- Technical datasheets & Catalogues major items, highlighting the offered models.

- Other documents and comments, if any.

3.3.2. For approval before construction/erection

The Vendor shall submit the following documents.

a) For all the supplies, the vendor shall submit the following documents in 4 sets for approval.

- General arrangement drawings, with all dimensions, showing: space-requirements, weights

(for

transport and service conditions), requirements of civil works (compatible with the tendered

Specifications), fixing and mounting facilities, connection devices, etc.

- Electrical drawings, showing: power single line and functional/control multi line diagrams,

terminalblocks, components‟ list with make, type, quantity, etc.

- Quality assurance plan and bar-chart showing manufacturing schedule.

The vendor shall incorporate all comments and submit revised drawings in stipulated time till

all

drawings are finally approved for manufacturing.

3.3.3. Final

The vendor shall submit the following documents, reflecting the true final as built situation,

in 6 sets and one soft copy in CD.

a) The drawings including wiring diagrams as revised and “as built”.

b) Inspection and preliminary testing certificates and reports and shipping release.

c) Test certificates of kWh meters from Government approved Lab or Electric Supply Co. of

concerned area.

d) Guarantee certificates.

e) Instruction & maintenance manuals, Cataloguers etc.

f) Any other certificate / report as called for by the Engineer.

3.4 Testing

The vendor shall carry out all required tests, at no extra cost, on equipment as per

specification in the presence of TPI agency / Client in order to enable the Client to determine

whether the equipment comply with the specifications. The Contractor shall offer each and

every equipment, before dispatch, for test at the manufacturer‟s works or incase Client waives

inspection, test certificate shall be furnished for their review and approval.

All the drawings shall be approved before starting the work.

3.5 Workmanship

Good workmanship and neat appearance are the prerequisites for compliance with the various

sections of these specifications. Work shall be carried out in accordance with the statutory

rules and local regulations in force and conform to relevant I.E Rules and I.S. Specifications.

Poor workmanship will be liable for penalization

123

SIGN & SEAL OF CONTRACTOR

3.6 Standard to be followed.

The design, manufacture and testing of the equipment covered by this standard shall comply

with the latest issue of the following codes and other relevant Indian standard specifications

unless otherwise specified in the specification sheet.

(i) BS 649 – Diesel engines for general purpose.

(ii) IS-10000 – Methods of test for internal combustion engine.

(iii) ASME codes(applicable to Diesel Generator)

(iv) IS 4722 – Rotating Electrical Machines.

(v) Oil coolers as per TEMA class “C”

(vi) BS : 2623 Alternator

(vii) IS : 1460 Diesel Fuels.

(viii) IS : 4691 Degrees of protection provided by enclosures for rotating electrical

machinery.

(ix) IS 10002 Performance requirements of Diesel Engine for General purpose above 20KW

(x) Indian Electricity Act & Rules.

(xi) Any other Standards/ Codes (BS & IS) applicable.

The design and operational features of the equipment offered shall also comply with the

provisions of latest issue of the Indian Electricity Rules and other statutory regulations. The

vendor shall, wherever necessary, make suitable modification in the equipment to comply

with the above.

4.0 GENERAL SCOPE

4.1 This specification describes the minimum specific requirements for supply design,

engineering, manufacture, procurement, packaging, testing, providing assistance to the

electrical vendor for Erection and commissioning of Diesel Generator Sets required for

Hostel Block Union Bank of India, Staff College, Bannerghatta road, Bangalore.

.

4.2 The intent of these specification is to supplement, highlight and modify (where specified)

therequirements as given in Standard / General Specifications enclosed with this tender

document.

4.3 In case of any conflict between this job specification and other enquiry documents, the

Following preferential order shall govern:

i. Data Sheets

ii. Technical Specification

iii. Standard Specifications for Diesel Engine, Emergency generator set, panel, battery &

battery charger, acoustic enclosure.

iv. Other Indian/International Standards attached herewith or referred to.

4.4 Compliance with this specification shall not relieve the Bidder of the responsibility of

furnishing equipment and accessories of proper design, materials and workmanship to meet

thespecified start up and operating conditions.

4.5 All Union Bank of India specifications, Data Sheets/Job Specifications etc. as per the list

of attachments provided elsewhere, shall form a part of this specification.

124

SIGN & SEAL OF CONTRACTOR

4.6 No deviations or exceptions are permitted from this specification and other attached

or

referred specifications as a rule. Only those deviations which are technically infeasible

to

be met shall be considered. In case no deviations are furnished it shall be considered

that

Bidder’s offer is in total conformity with all the datasheets, documents listed under List

of Attachments, the referred codes, standards and recommended practices.

5.0 DETAIL SCOPE

I. Design, Supply, testing, Installation and Commissioning of 1 no. 200 KVA, Prime rated

Diesel Generator set, speed of Diesel engine not exceeding 1500 RPM, four stroke engine,

designed for operating on high speed diesel, 415 V Diesel Generator sets consisting of water-

cooled engine alternator and engine mounted radiator and suitable for AMF START along

with all accessories and components such as exhaust pipes (as per the norms, refer formula

given elsewhere), fuel system etc. complete erection and installation on foundation as per

civil drawing of DG manufacturer, connecting to all completed accessories and components

and integrating the performance of all sub-systems, providing assistance for the electrical

vendor for Change over Panel testing and commissioning and performance testing, the entire

scope includes installation of the plant system including all connected structural, electrical

and necessary civil work for DG foundation as per the details from the DG supplier as

required for the proper and efficient functioning of DG sets as specified in Specification / Bill

of Quantities and Drawings.

10.0 VENDOR DATA AND DRAWING REQUIREMENTS

10.1 Bidder shall furnish the Drawings /Documents for Union Bank of India/Consultant

review / approval.

10.2 Bidder to note that during detail engineering, all civil works related design/drawings

such as

foundation design etc. shall be given to the owner/Union Bank of India appointed vendor for

his review and approval. Similarly bidder to provide all layout related data / drawings for

Union Bank of India‟s review and approval.

10.3 Bidder shall furnish all the information at the time of bidding as specified in the relevant

vendor data requirement forms. Bidder shall make his offer complete and comprehensive to

enable the processing of the offer without any technical queries / discussions.

11.0 SITE TESTING

The vendor to provide necessary assistance to the electrical vendor for executing the

following

tests at site in the presence of the client‟s representative before energisation.

a. Checking the alignment by engine manufacturer‟s representative and obtaining approval.

b. Insulation resistance test on alternator, control panel and cabling / Bus bar trunking.

c. Checking the engine safeties for satisfactory operation.

d. Checking vibration levels.

e. Testing of individual protective devices on engine and alternator and ensuring that the

wiring is carried out properly.

f. Full load running for continuously. All the readings shall be logged to evaluate the

fuel consumption, lube oil pressure, water & oil temperature vis-à-vis the electrical load. The

expenses occurred running DG while testing in the form of in form of fuel/Diesel, Man power

etc, should be borne by the contractor.

125

SIGN & SEAL OF CONTRACTOR

g. The noise level at 1m from the enclosure and the temperature rise inside the enclosure shall

be measured.

h. Any deviation from the guaranteed parameters shall be made good and these performances

Parameters should be measured once again till the required results are achieved.

i. The DG set shall be deemed to be commissioned after satisfactory performance of all

associated equipment.

12.0 HANDING OVER/TAKING OVER

The clients will take over the DG set for operation on completion of the following.

a. DG set are installed, tested and commissioned as per the specifications.

b. Original test certificates are furnished for engine, alternator, acoustic enclosure and

centrifuge

all other bought out items.

c. Load trials are successfully conducted including the performance of acoustic enclosure and

Ventilation fans.

d. Approvals are obtained from Pollution Control Board and Electrical Inspectorate.

e. 6 sets of AS BUILT documentation, spare parts list, maintenance chart and operation and

maintenance manual are to be submitted along with soft copy.

f. The set shall be handed over with first fill of lube oil along with spares mentioned.

13.0 DOCUMENTATION

As a part of the equipment supply, following documentation shall be furnished on award of

order.

a. General arrangement plan of DG set.

b. Piping schematic diagram

c. Foundation plans for DG set & control panel.

d. Layout of fuel and exhaust piping.

e. Layout and constructional details of acoustic treatment.

f. Calculations for ventilation system design.

g. Engine wiring diagram.

h. Test certificate for engine and alternator.

i. Governor system along with write-up.

j. Installation, operation and maintenance instructions for diesel engine, alternator.

k. Spare parts list.

l. Approval from Pollution Control Board authorities for CPCB-II compliance of the DG

set.

14.14 STORING:

The panels shall be stored in well ventilated dry places. Suitable polyethylene covers shall be

provided for necessary protection against moisture.

14.15 ERECTION:

The AMF panel supplied by the DG vendor will be installed by the electrical vendor.

Necessary

assistance for proper installation of the panel as follows shall be extended by the DG vendor

to

the electrical vendor.

The panel shall be shall be installed on suitable foundation. Foundation shall be per the

dimensions supplied by the panel manufacturer. The foundation shall be flat and level.

Suitable grouting holes shall be provided in the foundation. Suitable MS base channel shall

beembedded in foundation on which the panel can be directly installed. The switch boards

shall

126

SIGN & SEAL OF CONTRACTOR

Be properly aligned and bolted to the foundation by bottom plate or top plate as the case may

be, by using brass Siemens type compression glands. The individual cables shall then be led

through the panel to the required feeder compartments for necessary terminations. The cables

shall be clamped to the supporting arrangements. The switch board earth bus shall be

connected to the local earth grid.

14.16 PRE-COMMISSION TESTS:

Panels shall be commissioned only after the successful completion of the following tests.

The tests shall be carried in the presence of owner or his authorized representative.

a) All main and auxiliary bus bar connections shall be checked and tightened.

b) All wiring terminations and bus bars joints shall be checked and tightened.

c) Wiring shall be checked to ensure that it is according to the drawings.

d) All wiring shall be tested for insulation resistance by a 1000 Volts Megger.

e) Phase rotation tests shall be conducted.

f) Suitable injection tests shall be applied to all the measuring instruments to establish the

correctness and accuracy of calibration and working order.

g) Suitable injection tests shall be applied to all the measuring instruments to establish the

correctness and accuracy of calibration and working order.

h) Panel boards shall be meggared phase to phase and phase to neutral, using a 1000 V

meggar with all switchgear in closed position. The meggared value should not be less than

2.5 mega ohms between phase and 1.5 mega ohms between phase & neutral & earth.

i) The test shall be carried out by applying 2.5 KV for one minute between Air, Three phases

&Earth .between phases and board shall with stand the same.

j) The panel boards shall be meggered phase to phase end.

All relay and protective devices shall be tested for correctness of settings and operation by

introducing a current generator and ammeter in the circuit.

DATA SHEETS

Data Sheet for Diesel Generator package

A. Vendor's scope:

Sl no Description Supply Installation at

site

Supervision of

site works (ITC)

1 Diesel Generator complete

with brushless excitation and

AVR system, frame earthing

connections & lubrication

system.

Yes skid mounted

( necessary

assistance to

electrical

vendor)

Yes

2 Generator control panel with

AMFsystem and control /

metering andauxiliary

equipments.

Yes Yes

2.1 Line Cubicle for CT /PT Yes Yes

2.2 Neutral Cubicle for CTs Yes Yes

2.3 Line side breaker in cubicle No No

3 Synchronizing equipment Yes Yes

4 Power and Control cabling

inbetween the package

quipment

Yes Yes

127

SIGN & SEAL OF CONTRACTOR

5 Earthing within the battery

limits and connection to main

earthing grid

No Yes

6 Battery & battery charger for

control power requirement of

the complete

DG set.

Yes Yes

7 Fabricated steel cable trays

and

racks as required for cabling

in the battery limits

Yes Yes

8 Spares for commissioning No

9 Spares for two years trouble

free operation

No

10 Obtaining approvals of

KEB/BECOM and Pollution

Control Board.

CPCB

compliance

certificate to

be provided

by vendor

Note: 'Yes' indicates activity in vendor's scope.

Data Sheet-Part-2

(Data furnished by purchaser)

1.0 Site Conditions

1.1 Design ambient temp, for electrical equipment design (IS:9676) : 42 °C

(For machines wish acoustic enclosure, this temperature is applicable-for the ambience

outside

acoustic enclosure)

2.0 Equipment location : Open on all side Ventilation: Adequate

Notes :

1.0 The equipment/components shall be procured from any of the approved vendors. It is

preferable to source the equipments from one approved vendor.

2.0 Make of components other than specified above can be offered during order execution in

casethe availability of the above makes is a problem. The alternate make of components shall

beevaluated post order, based on the track record and test certificates to be furnished by

vendor/contractor. In case alternate makes are not found acceptable, components shall be

strictly asper above vendor list.

128

SIGN & SEAL OF CONTRACTOR

MINIMUM TECHNICAL REQUIREMNTS

SL. DESCRIPTION UNION BANK OF INDIA

REQUIREMENT

VENDOR’S OFFER

A ALTERNATOR

1 MAKE KIRLOSKAR / CUMINS / CROMPTON / STAMFORD / EQUIVALENT

2 MODEL NO. VENDOR TO SPECIFY

3 CAPACITY 1 no. 200 KVA

4 VOLT/PHASE/

FREQUENCY

415V / 3-PHASE / 50Hz / 4 WIRE

5 PROTECTION DRIP PROOF CONSTRUCTION AS PER IS:4691.

VENDOR TO SPECIFY THE DEGREE OF PROTECTION.

6 INSULATION CLASS H

7 EXCITATION BRUSHLESS SELF EXCITATION THROUGH A SUITABLE TRANSFORMER

RECTIFIER COMBINATION GIVING :-

FLAT AND RISING CHARACTERISTICS PROTECTION FROM DISCHARGE EASY

ARRANGEMENT TO REMAGNETISE

8 VOLTAGE REGULATOR SHUNT FIELD &AUTOMATIC VOLTAGE

REGULATORS TO BE PROVIDED.VENDOR TO GIVE ALL

DETAILS LIKE MODEL NO. ETC.

9 SPACE HEATERS 240 V , SINGLE PHASE LOCATED IN THE

LOWER PART OF STATOR FRAME

SHOULD CUT OFF AUTOMATICALLY

WHEN ALTERNATOR STARTS RUNNING

SEPERATE POWER CONNECTION TO BE

GIVEN WITH A PUSH BUTTON IN CONTROL PANEL

10 TERMINAL BOX SUITABLE CLAMPING ARRANGEMENT FOR CONNECTING THE CABLES TO THE

TERMINALS WITH SUITABLE CP BRASS CABLE GLANDS

10.1 GLAND SIZE TO BE SUITABLY PROVIDED

11 OVER LOAD SHOULD TAKE 10% IN EXCESS OF THE

RATED OUTPUT FOR 1 HOUR OUT OF 12 CONTINUOUS HOURS OF OPERATION

DURING WHICH TEMPERATURE SHOULD NOT EXCEED PRESCRIBED LIMITS OF

CLASS 'F' INSULATION

12 UNBALANCED LOAD SHOULD BE CAPABLE OF CARRYING LOAD OF 25% WITH OUT ANY DAMAGE

TO ANY PART PROVIDED RATED

CURRENT IS NOT EXCEEDED.

129

SIGN & SEAL OF CONTRACTOR

CORRESPONDING VOLTAGE UNBALANCE

SHOULD NOT EXCEED +/-2% OF

AVERAGE TERMINAL VOLTAGE

13 SHORT CIRCUIT SHOULD WITHSTAND SHORT CIRCUIT

AT TS TERMINALS FOR 3 SECONDS WITH EXCITATION ADJUSTED TO

DEVELOP RATED VOLTAGE AT NO LOAD WITHOUT ANY DAMAGE

14 SUB TRANSIENT FAULT SHOULD NOT EXCEED 15 TIMES THE FULL LOAD CURRENT.

15 EARTHING 2 NOS. SEPARATE FROM NEUTRAL

TERMINAL

16 FIELD WINDING SHOULD BE FULLY INSULATED FROM

CORE

B DIESEL ENGINE

1 MAKE KIRLOSKAR / CUMMINS / GREAVES /

CATTERPILLAR / ASHOK LEYLAND

1.1 MODEL NO. VENDOR TO SPECIFY

2 CAPACITY VENDOR TO SUBMIT THE

CALCULATIONS OF ENGINE TO SUIT

THE ALTERNATOR

3 TYPE IC ENGINE

4 CYLINDER VENDOR TO QUOTE

LINERS PLATEAU HONED WET LINERS

PISTON GRAPHITE QUOTED THREE RING PISTON CERAMIC QUOTED TOP PISTON

RING IMPORTED VALVE STEM SEAL THREE STAGE AIR CLEANER

5 RPM VENDOR TO QUOTE

6 COOLING SYSTEM

6.1 TYPE JACKET WATER SYSTEM

6.2 RADIATOR WATER COOLED WITH IN BUILT EXPANSION VOLUME

6.3 FAN BLOWER TYPE WITH GUARD

6.4 CORROSION RESISTOR TO CHECK CORROSION, RUST, ACIDITY & REMOVE IMPURITIES

7 ASPIRATION VENDOR TO QUOTE

8 OVERLOAD 10% IN EXCESS FOR 1 HOUR IN ANY 12

CONTINUOUS HOURS OF OPERATION

9 FUEL OIL SYSTEM

9.1 FUEL PUMP WITH FILTER

9.2 FUEL TANK FABRICATED FROM 5 MM THICK MILD STEEL PLATE , PAINTED WITH

SYNTHETIC ENAMEL PAINT OVER TWO COATS OF RED OXIDE PRIMER

130

SIGN & SEAL OF CONTRACTOR

9.2.1 CAPACITY 8 HRS RUNNING CAPACITY

9.2.2 STAND FOR MOUNTING THE FUEL TANK

10 LUBE OIL SYSTEM AUTOMATIC PRESSURE LUBRICATION BY ENGINE DRIVEN GEAR TYPE PUMP

11 AIR INTAKE OIL BATH TYPE/DRY TYPE WITH AIR

FILTER

12 EXHAUST INDUTRIAL TYPE SILENCER WITH

NECESSARY ADAPTOR PIPING & SPARK ARRESTOR

13 STARTING SYSTEM ELECTRICAL STARTING

13.1 STARTER TO BE PROVIDED

13.2 BATTERIES VOLTAGE TO BE SPECIFIED

MAKE:EXIDE/INDEX

LEADS FOR THE BATTERIES

NOTE: INITIAL BATTERY CHARGING SHALL BE DONE BY SUPPLIER

13.3 BATTERY CHARGER

14 GOVERNING SYSTEM ELECTRONIC

14.1 TYPE CLASS A1

14.2 SPEED DROP -4% TO 4%

14.3 NOMINAL SPEED VENDOR TO QUOTE

14.4 FREQUENCY VARIATION RATE SHALL NOT EXCEED 0.5Hz PER SECOND

14.5 OVER SPEED TRIP

MECHANISM

SHOULD CUT OFF FUEL IN

CASE SET REACHES THE OVER SPEED BETWEEN 110%

TO 130% OF RATED

EMERGENCY STOP PUSH

BUTTON SHALL BE PROVIDED FOR TRIPPING THE ENGINE.

NECESSARY RPM INDICATOR, TACHOGENERATOR TO BE

PROVIDED.

15 COUPLING CLOSED COUPLED

16 INSTRUMENT PANEL TO BE MOUNTED ON ENGINE AND SHOULD HAVE

STARTING SWITCH WITH KEY

ENGINE RPM / HOUR METER

LUBE OIL PRESSURE GAUGE

WATER TEMPERATURE GAUGE

AMMETER FOR BATTERY

CHARGING

C. GENERAL

1 BASE FRAME ENGINE COUPLED WITH

ALTERNATOR SHOULD BE MOUNTED ON A ROBUST

FABRICATED STEEL FRAME.

2 ANTI-VIBRATION

MOUNTING PADS

TO BE PROVIDED

131

SIGN & SEAL OF CONTRACTOR

2.2 MAKE DUNLOP / AVMEC

2.3 DUTY VENDOR TO QUOTE

2.4 NO. OF PADS VENDOR TO QUOTE

3 DRAWINGS AND DATAS

4 PRINTS OF THE FOLLOWING TO BE SUBMITTED. ( TO BE

PROVIDED AFTER AWARD OF PURCHASE ORDER)

OUTLINE DIMENSIONAL DRAWINGS AND THE

GENERAL ARRANGEMENT OF DG AND CONTROL PANEL

SHOWING ALL REQD.

CLEARANCES

FOUNDATION PLAN

DRAWINGS FOR DG SET AND

CONTROL PANEL

FUEL OIL SYSTEM, LUBE OIL

SYSTEM, JACKET WATER SCHEME WITH

INTRUMENTATION AND

CONTROL WITH WRITE-UP.

GOVERNOR SYSTEM AND

VOLTAGE REGULATOR WITH

WRITE-UP.

DG SET INSTRUMENTATION

AND CONTROL SYSTEM WITH WRITE-UP.

4 INSTRUCTION MANUALS 6 SETS FOR INSTALLATION,

(TO BE SUBMITTED IN 4 COPIES AFTER THE AWARD

OF PURCHASE ORDER) & MAJOR OVERHAULING

5 PACKING ENGINE COUPLED WITH

ALTERNATOR SHOULD BE SUITABLY PACKED. SUPPLIER

HAS TO PROVIDE TARPAULIN FOR COVERING THE

ASSEMBLED DG SET.

6 PAINTING DG SET TO BE THOROUGHLY CLEANED AND DEGREASED.

ALL RUST SHARP EDGES AND

SCALES SHALL BE REMOVED. ALL EXTERNAL PARTS SHALL

BE FINISHED AND PAINTED WITH TWO COATS OF PRIMER

AND TWO COATS OF EPOXY ENAMEL PAINT

7 INSTALLATION By Vendor

8 COMMISSIONING DG SET TO BE COMMISSIONED BY THE

SUPPLIER

132

SIGN & SEAL OF CONTRACTOR

9 UNLOADING & STACKING AT SITE

By Vendor

D. AUTO MAINS FAILURE PANEL

1 BODY FABRICATED OUT OF 14 SWG

CRCA SHEET, CUBICLE TYPE, POWEDER COATED FINISH,

FLOOR MOUNTED

HINGED DOORS WITH DUST PROOF GASKET & THUMB

KNOB.

KNOCKOUT GLAND PLATE TO BE PROVIDED AT THE

BOTTOM

2 MCCB WITH OVERLOAD / UNDERVOLTAGE /SHORT

CIRCUIT PROTECTION DEVICE

2.1 CAPACITY VENDOR TO QUOTE

2.2 MAKE VENDOR TO QUOTE

2.3 OTHER FEATURES VENDOR TO QUOTE

3 KW METER TO BE PROVIDED

3.1 CAPACITY VENDOR TO QUOTE

3.2 MAKE TO BE PROVIDED

3.3 OTHER FEATURES VENDOR TO QUOTE

4 KWH METER TO BE PROVIDED

4.1 CAPACITY VENDOR TO QUOTE

4.2 MAKE TO BE PROVIDED

4.3 OTHER FEATURES VENDOR TO QUOTE

5 AMMETER TO BE PROVIDED 1 NO FOR

AC , 1 NO DC

5.1 RANGE VENDOR TO QUOTE

5.2 MAKE TO BE PROVIDED

5.3 SELECTOR SWITCH OF KAYCEE MAKE

5.4 OTHER FEATURES VENDOR TO QUOTE

6 FREQUENCY METER TO BE PROVIDED

6.1 RANGE VENDOR TO QUOTE

6.2 MAKE TO BE PROVIDED

6.3 OTHER FEATURES VENDOR TO QUOTE

7 VOLTMETER TO MEASURE BOTH LINE & PHASE VOLTAGE FOR AC

7.1 RANGE VENDOR TO QUOTE

7.2 MAKE TO BE PROVIDED

7.3 SELECTOR SWITCH TO BE PROVIDED

7.4 OTHER FEATURES VENDOR TO QUOTE

8 CURRENT TRANSFORMER TO BE PROVIDED

8.1 CAPACITY VENDOR TO QUOTE

133

SIGN & SEAL OF CONTRACTOR

8.2 MAKE TO BE PROVIDED

8.3 NO OF CURRENT VENDOR TO QUOTE

TRANSFORMERS

9 SAFETY CONTROLS AUDIO / VISUAL WITH ONE

HOOTER ALARM FOR THE

FOLLOWING :

10 INDICATION LAMPS TO INDICATE :

11 BATTERY CHARGER TO BE PROVIDED

12 AUTO LOAD SHARING, AUTO SYNCHRONISING

AND AUTO MAINS

FAILURE ARRANGEMENT

TO BE PROVIDED

13 BMS OUTPUT TO BE PROVIDED FOR MDM

METER.

TECHNICAL DATA SHEET

ENGINE

Sl. No.

Description Units Bidder to indicate

1 Name of manufacturer

2 No of Diesel Engine No

3 Power rating of the engine @ 1500 RPM KW

4 Engine rating at site condition KW

5 Model of Engine

6 Standard Rating type

7 Gross Engine BHP BHP

8 Gross Engine KW KW

9 Length (Engine Alone) mm

10 Width (Engine Alone) Mm

11 Arrangement of Cylinder

12 Height (Engine Alone) Mm

13 No. of Cylinders No

14.a Bore mm

14.b No. of strokes No

15 Displacement Lit

134

SIGN & SEAL OF CONTRACTOR

16 Compression ratio no

17 BMEP of the engine KPa

18 Direction of rotation

19 Operating Speed

20 „V‟ angle degree

21 Firing order

22 Aspiration of engine

23 Piston speed of engine m/sec

24 Max. over speed allowed (Trip set at) RPM

25 Max. Engine rating at site with 10% overload KW

26 Total dry weight of engine Kg

27 Total wet weight of engine kg

28 horse power consumed by engine driven

accessories

KW/HP

29 Mechanical efficiency of the engine %

30 Thermal efficiency of the engine %

31 Ref. standards for these engines

32 Height of base rail used for the engine mm

EXHAUST SYSTEM

1 Exhaust system back pressure permitted

(max.)

KPa

2 Diameter of engine exhaust outlet (inside) mm

3 No. of exhaust outlets required No

4 No. of silencers supplied with each engine No

5 Noise reduction provided by the silencers Db(A)

6 Restriction offered by silencers

7 Exhaust gas flow rate CF/M

8 Exhaust gas flow rate M3/min

9 Exhaust gas temp (stack) Deg. C

10 Exhaust silencer type

11 Height of each chimney m

Heat exchangers (Shell & Tube Type) Lube Oil

Jacket Water System

1 No. of heat exchanger per DG set

Construction Features

1 Type

135

SIGN & SEAL OF CONTRACTOR

Shell side

1 Fluid circulated Lube Oil Jacket Water

2 Quantity of fluid circulated M3/hr

3 Temperature – inlet Deg. C

4 Temperature – outlet Deg. C

Tube Side

1 Fluid circulated Raw cooling Water

2 Quantity of fluid circulated M3/hr

3 Temperature – inlet Deg. C

4 Temperature – outlet Deg. C

Material Specification

1 Shell

2 Tubes

3 Tube sheet

4 Gaskets

Position of Center of Gravity(Approx.)

1 Forward from rear face of the block mm

2 Above crank shaft centerline mm

3 Right of crankshaft centerline mm

a) Specific Fuel Consumption

1 Specific Fuel Consumption @ 100% load g/bkWHr

2 Specific Fuel Consumption @ 75% load g/bkWHr

3 Specific Fuel Consumption @ 50% load g/bkWHr

4 Tolerance g/bkWHr

b) Fuel Consumption in Liters

1 Specific Fuel Consumption @ 100% load Lit/hr

2 Specific Fuel Consumption @ 75% load Lit/hr

3 Specific Fuel Consumption @ 50% load Lit/hr

4 Tolerance Lit/hr

5 Density of fuel considered Kg/lit

6 Alternator Efficiency considered %

AMMETER TO BE

PROVIDED 1 NO FOR

AC , 1 NO DC

RANGE VENDOR

TO QUOTE

136

SIGN & SEAL OF CONTRACTOR

MAKE As per DG Manufactur

er

Recommendation

SELECTOR SWITCH As per DG

Manufacturer

Recommendation

OTHER FEATURES VENDOR

TO QUOTE

FREQUENCY METER TO BE

PROVIDED

RANGE VENDOR TO QUOTE

MAKE As per DG

Manufacturer

Recommendation

OTHER FEATURES VENDOR

TO QUOTE

VOLTMETER TO

MEASURE BOTH LINE

& PHASE VOLTAGE

FOR AC

RANGE VENDOR TO QUOTE

MAKE As per DG Manufactur

er Recommen

dation

SELECTOR SWITCH As per DG

Manufacturer

Recommen

dation

7 OTHER FEATURES VENDOR TO QUOTE

137

SIGN & SEAL OF CONTRACTOR

8 CURRENT TRANSFORMER TO BE PROVIDED

9 CAPACITY VENDOR TO QUOTE

D. MAKE As per DG

Manufactur

er Recommen

dation

1 NO. OF CURRENT VENDOR TO QUOTE

TRANSFORMERS

SAFETY CONTROLS AUDIO /

VISUAL

WITH ONE

2 HOOTER ALARM FOR THE FOLLOWING :

2.1 INDICATION LAMPS TO

INDICATE :

2.2 BATTERY CHARGER TO BE PROVIDED

2.3 AUTO MAINS FAILURE ARRANGEMENT TO BE

PROVIDED

3 BMS OUTPUT TO BE

PROVIDED FOR ALL

METERS

STANDARD SPECIFICATIONS FOR DIESEL GENERATOR SET

1.0 SCOPE

This specification defines the minimum requirements for the supply of self-excited Internal

Combustion Engine driven Emergency Generator and associated electrics suitable for

installation in unclassified / safe area.

Unless otherwise specified in the Schedule of Quantities (SOQ)/ data sheet the emergency

generator and associated electrics shall be complete with –

a. Alternator will be brushless excitation system complete with AVR.

b. Generator Control Panel to include AMF system, Auto / Manual control, auxiliary devices,

battery and charger. This panel shall also include generator breaker and generator protection

relays if specified in the data sheet.

The control panel shall be capable of integration with BMS system and shall be

microprocessor based and programmable.

c. Any other part / accessories not specifically mentioned above but considered necessary

for safe and reliable operation.

138

SIGN & SEAL OF CONTRACTOR

2.0 CODES AND STANDARDS

2.1. The equipment shall comply with the requirements of latest revision of following

standards

issued by BIS (Bureau of Indian standards) unless otherwise specified.

IS-5 Colours for ready mix paints and enamels

IS - 2253 Designation for type of construction and mounting arrangement of rotating

electrical machines.

IS-4691 Degree of protection provided by enclosures of Rotating Electrical

Machinery.

IS-4722 Rotating electrical machines. ,-

IS – 4728 Terminal marking and direction of rotation for rotating electrical

machinery.

IS – 4889 Methods of determination of efficiency of rotating electrical machines.

IS - 6362 Designation of Methods of Cooling of Rotating Electrical Machines.

IS – 7132Guide for testing synchronous machines.

IS - 7306 Methods of determining synchronous machines quantities from tests.

IS - 7372 Lead acid storage battery for motor vehicle.

IS-7816 Guide for testing of insulation resistance of rotating machines.

IS- 12065 Permissible limits of noise level for rotating electrical machines.

IS - 12075 Mechanical vibration of rotating electrical machines with shaft heights 56 mm

and higher - measurements, evaluation and limits of vibration severity

IS - 12802 Temperature rise measurement of rotating electrical machines.

IS - 13364 Part-I -AC Generators up to 20 K.VA driven by reciprocating internal combustion

engine.

IS- 13364 Part-II-AC Generators above 20 and up to 1250 KVA driven by reciprocating

.internal combustion engine,

IS -13947 Low voltage Switchgear and Control gear: General Rules.

2.2. In case of imported equipments standards of the country of origin shall be applicable if

these

standards are equivalent or stringent than the applicable Indian standards.

2.3. The. equipment shall also conform to the provisions of Indian Electricity rules and other

statutory regulations currently in force in the country.

2.4. In case Indian standards are not available for any equipment, standards issued by

IEC/BS/VDE/IEEE/NEMA or equivalent agency shall be applicable.

2.5. In case of any contradiction between various referred standards/specifications/data sheet

and

statutory regulations the following order of priority shall govern:

• Statutory regulations.

• Data sheets.

• Job specification.

• This specification.

• Codes and standards.

139

SIGN & SEAL OF CONTRACTOR

3.0 SITE CONDITIONS

Generator shall be suitable for operating satisfactorily in conditions available in Bangalore.

conditions shall be as specified in the Data Sheet. If not specifically mentioned

therein, a maximum ambient temperature of 42° C and an altitude not exceeding 1000 meters

above mean sea level shall be considered.The specified maximum ambient temperature shall

be considered outside the enclosure for

machines having acoustic enclosure.

6.0 DESIGN AND CONSTRUCTION

6.1 The generator design shall meet the requirement specified in data sheet and shall be

suitable

for the site conditions specified therein.

6.2 The generator shall be mounted on a common base frame together with prime mover

unless

otherwise agreed. The generator shall be provided with necessary lifting hooks and two earth

terminals on opposite sides for connection to main earth grid.

6.3 Various generator windings (stator, rotor of Main Generator, Exciter) shall be designed

having insulation class: -

• • Class of insulation - „H‟ class.

6.8 The terminal box (es) and cubicles shall have sufficient space for the termination of

quantity of cable or bus duct as specified in data sheet.

6.9 All terminals shall be stud type. The terminal boxes / cubicles shall be complete with

tinned

copper lugs and single compression nickel plated brass cable glands for the quantity and type

of power cables as specified in the data sheet. Where single core cables are specified, gland

plates shall be of non magnetic material (Stainless steel or Aluminum)

6. 10 All parts and accessories shall be suitable to withstand stresses due to over speed / over

load /short circuit conditions specified.

6.11 Bearings

6.11.1 Bearings shall be grease lubricated ball or roller bearing or of the manufacturers

standard type.

In all cases the bearings shall be chosen to give a minimum L-10 rating of 5 years (40,000hrs)

at rated operating conditions.

6.11.2 Grease lubricated bearings shall be capable of grease injection from outside without

removal of covers. The bearing boxes shall be provided with labyrinth seals to prevent loss of

grease or entry of dust or moisture. When grease nipples are provided those shall be

associated, where necessary, with appropriately located relief devices which ensure passage

of excess grease

through the hearings.

6.11.3 Sleeve type bearing shall either be ring lubricated or forced-oil lubricated, depending

on the loading. Sleeve bearing shall be of proven track record (PTR). While offering sleeve

bearings, list of past supplies shall be furnished.

6.11.4 With forced oil lubrication system the oil inlet and outlet lines of generator bearings

shall be connected to the oil supply system. Preference shall be given to central system from

which oil

to the bearings of driver is also supplied.

140

SIGN & SEAL OF CONTRACTOR

6.12 Generator enclosure protection class shall be as specified in data sheet.

6.13 The direction of rotation of the rotor of the machine shall be compatible with that of the

prime

mover. A clear indication of the direction of rotation shall be given on either end of the

machine.

6.14 Space heaters shall be installed within the enclosure. Location and maximum surface

temperature of the heaters shall be such that no damage can be caused to any insulation.

Healers shall be suitable for operation on a single-phase 240 V AC supply unless otherwise

specified.

6.15 Field winding shall have insulation class and temperature limitations as per para 5.3

above.

The field winding shall be capable of operating at 125 % of rated field voltage for at least one

minute starting from hot initial condition, i.e. stabilized temperatures at rated load conditions.

(Rated field voltage is the voltage applied at the field winding for producing rated terminal

voltage at rated load and speed).

6.16 All cabling on the generator skid shall be in GI perforated cable trays / conduits. All

cables

shall be identified close to their termination point. Double compression type cable glands

shall

be used for cable termination.

6.17 Auxiliary Terminal Boxes

Separate Terminal boxes of sturdy construction shall be provided for Space Heater and other

devices like RTDs, with sufficient space for connecting the cables as indicated in the

requisition.

6.18 A rating plate of stainless steel shall be fixed on the generator frame and shall give the

information as per IS: 4722.

6.19 Auxiliary motors

All auxiliary motors shall be three phase, 415 V, 50 Hz squirrel cage type suitable for DOI.

starting. Insulation class shall be „B‟ unless other wise specified. All motors shall have IP -55

enclosures and shall conform to relevant Indian Standards.

6.20 Battery Bank

6.20.1 The battery shall be lead acid, high discharge automotive type suitable for engine

starting duty and conforming to IS: 7372. The battery shall be placed on battery stands made

of steel with

suitable PVC coating. One no. each of the accessories viz. hydrometer, thermometer, cell

testing voltmeter, pair of rubber gloves, spanner, acid resistant jug and funnel, teak wood

holder for the hydrometer etc. shall be supplied with each battery set.

6.20.2 The battery capacity shall be adequate for six (3+3) consecutive starts of the engine

under cold engine condition, without recharging, with additional 10% spare capacity. The

auto starting

system shall successively carry out 3 (three) automatic start attempts but if diesel engine fails

to start even after three attempts then an alarm shall be communicated on this account and

remaining 3 (three) start attempts can be carried out manually as per operator‟s decision.

141

SIGN & SEAL OF CONTRACTOR

7.0 EXCITATION SYSTEM

7.1 The generator shall be self-exciting, i.e. it shall generate its nominal voltage without the

use of external power sources, even after long idle periods or after a short circuit .The

generator shall

be provided with brushless type solid state self-excitation system with automatic voltage

regulator. The excitation system shall include the automatic voltage regulator, AC exciter and

rotary rectifier.

7.2 The field of the exciter shall be fed from the stator winding and AVR. AC voltage

generated in the AC exciter shall be rectified by the rotary rectifier assembly and fed to the

main field

circuits. The rotor winding of the AC exciter, the rectifier assembly, main field winding of the

generator and other accessories on rotor parts shall be rigidly fastened .to the shaft and the

connection with different items shall be anti-loosening type. The exciter capacity shall be at

least 20 % more than the maximum requirement at-any time. The exciter winding shall be

insulated as per para 5.3 above.

7.3 The rotary rectifier set shall consist of rectifiers, zener diodes, fuses, field discharge

resistors,

condensers, etc. Rotor circuit shall be designed to take care of rectification of AC voltage and

for proper field suppression through discharge resistors. The rating of the Diode Bridge and

armature shall be such that the full load rated current can be supplied with one branch in

operation.

7.4 All components shall be mounted considering the effects of the centrifugal forces.

7.5 Automatic solid-state voltage regulator (AVR) shall be provided with the following

features as a minimum:

• Short circuit protection

• Manual voltage control

• Voltage builds up circuitry

• Over voltage protection

7.6 The AVR can be installed either in the generator control panel or at the generator. In latter

case the AVR shall be located in a separate housing or in a clearly segregated section of” the

main terminal box.

8.0 SYSTEM OPERATION

8.1 Modes of Operation

The emergency generator and associated electrics shall normally be in an unattended area.

The control system shall be suitable for unattended operation. The control system shall

operate in fail-safe mode and shall include all controls and protection necessary for the safe

operation of the DG set. The generator and associated electrics shall function as per the

following schemes:

• Auto start on mains failure scheme (AMF), if specified.

• Manual start in Service/Test mode

• Manual stop upon supply restoration

8.1.1 Automatic start on mains failure

This shall be effective in Auto position of Auto / Manual selector switch located in local

control panel. The generator shall normally be at rest. Upon failure of normal supply, a start

impulse (in the form of changeover of a dry contact) shall be provided by others. Using this

impulse, generator shall start automatically and rated speed and voltage shall be built up.

Once 142

SIGN & SEAL OF CONTRACTOR

the‟ voltage-monitoring relay senses generator healthy voltage, an impulse shall be given for

closing of generator breaker or contactor.

All accessories required for starting and completion of various sequence of operation for the

above purpose shall be provided as part of generator.

8.1.2 Manual start

8.1.2.1 In Service Mode

This shall be effective in manual position of Auto/Manual switch and service position of

service /.test selector switch located in control panel. The scheme of operation shall be same

as of auto mode as per clause 8. 1.1 above except that starting command shall be extended

manually using the push button (instead of command from AMF sequence) from the local

control panel. Provision shall also be kept for manual start from owner‟s remote control

panel.

8.1.2.2 In Test Mode

This shall be effective in test position of service / test selector switch. The scheme of

operation

shall be same as that of manual start in service mode as per above except that the closing

command for generator breaker /contactor shall not be extended automatically.

If periodic load test-run of generator is envisaged as per data sheet, the generator breaker

shall

be closed manually after synchronization with grid.

8.1.3 Stop upon restoration of grid mains supply

Unless specified otherwise in the datasheet, DG set shall be stopped automatically. This shall

be possible irrespective of the position of Auto / Manual selector switch which is located in

generator control panel.

8.2 Shut-down

It shall be possible to manually stop the generator in all operational cases including

emergency case by means of the push button provided in either generator control panel or

Owner‟s remote panel.

8.3 Starting time

Unless specified otherwise, the total time from the receipt of the starting impulse for the

generator till the set reaches rated speed and generator reaches rated voltage shall not be more

than 30 seconds. If this time is exceeded, an annunciation in the local control panel shall be

provided with a facility for repeat annunciation in Owner‟s panel.

8.4 Black start facility .

The generating unit shall be provided with all necessary „black start‟ facilities. External

power at 415 V TPN shall be made available by purchaser at one point for battery charging or

any other auxiliary equipment operation during stand -still period of generator. This power

shall not be available during start-up of the generator.

8.5 DC control supply

Unless it is specified that the DC control supply required for AMF/generator relay and control

function is being provided by vendor, all DC power supply requirement shall be met by DC

system consisting of battery and battery charger of suitable capacity to be supplied by the DG

set vendor.

DC control supply for AMF / generator control panel is provided by vendor, the engine

starting motor and other such special duty DC load required for DG system package shall still

be fed from the DC system battery & charger to be supplied by the DG set vendor.

During stand still period of DG set, charger of DC supplies shall be energized from the 415 V

feeder provided by purchaser as per para 8.4 above. 143

SIGN & SEAL OF CONTRACTOR

11.0 PACKING AND DESPATCH

11.1 All the equipment shall be divided into several sections for protection and ease of

handling

during transportation. The equipment shall be properly packed for selected mode of

transportation i.e. by ship/rail or trailer. The equipment shall be wrapped in polythene sheets

before being placed in crates/cases to prevent damage to finish. Crates/cases shall have skid

bottom for handling. Suitable lifting lugs etc. shall also be provided and lifting points shall be

clearly marked on the package. Special notations such as „Fragile‟, „This side up‟, „Center of

gravity‟, „Weight, Owner‟s particulars (PO nos.) etc., shall be clearly marked on the package

together with other details as per purchase order.

11.2 The equipment may be stored outdoors for long periods before installation. The packing

shall be completely suitable for outdoor storage in areas with heavy rains/high ambient

temperature unless otherwise agreed.

4.2 LIST OF MANDATORY SPARES

1. Lube oil filter : 4 Nos.

2. Fuel filter element coarse : 3 Nos.

3. Fuel filter element fine : 3 Nos.

4. All types of gaskets : 2 Sets.

5. All types of „O‟ rings : 2 Sets.

6. Dynamo Belt : 2 Nos.

7. Fan Belt Set : 2 Nos.

8 W. P. Belt : 2 Nos.

9. Setting Screw : 3 Sets

VENDOR'S DATA

5.1 PROPOSALS

The vendor's proposals shall as a minimum include the following:

(a) All data sheets, drawings and documents listed in the tender.

(f) An itemized list of special tools included in the offer.

(g) Any start-up, shutdown or operating restrictions required to protect the integrity of the

equipment.

(h) Any limitations of vendor's test-facility to carryout the specified tests,

(i) A specific statement that the scope of supply, the offered equipment/ systems and all its

components are in strict accordance with the data sheets, job specifications, this specifications

and all other attachments, except for specific deviations as listed in the proposal. ,

5.2 CONTRACT DATA (after placement of order)

5.2.1 General

5.2.1.1 Drawings and data as required after purchase order is specified in Vendor Data

Requirement.

Vendor to note that the drawing/ document descriptions/ titles as given' in the Vendor Data

Requirement are generic in nature. It is possible that against one drawing/ document specified

there are several drawings to be furnished by the vendor or vice versa.

Vendor shall complete & forward a document "Vendor Data Index & Schedule" to the

purchaser (Destination & contact person as per order).

This document shall list out in consolidated form all drawings and documents required by

purchaser ( As specified in Data Sheets, Specifications and Vendor Data Requirement forms

144

SIGN & SEAL OF CONTRACTOR

enclosed with the order). Against each drawing/ document vendor shall indicate the vendor's

drawing numbers, titles, Rev. No., category (whether for information or approval) and

schedule of submission.

This shall be the first document to be submitted by vendor within two weeks of order.

5.2.1.2 All transmittal letters (covers), drawings and data shall have a title block (in addition

to

vendor's standard title block) which shall as a minimum contain the following contract

information:

(i) Purchaser's Name

(ii) Project Name,

(iii) Equipment Name and Item No.

(iv) Purchase Order No.

Title Block on drawings shall be placed on the lower right hand corner.

5.2.1.3 All vendor data/ drawings/ documents shall be in English Language and in Metric

Systems of all purchaser's interface connections including those of vents, drains, fuel,cooling

water & Electrical/ Instrumentation,

iii) Direction of rotation viewing from the driving end.

iv) Weight of each assembly/ component,

v) The weight & location of center of gravity

5.2.1.4 Data specified in the VDR is the minimum requirements of Purchaser. Any additional

document/ data required or requested by Purchaser for engineering or construction shall also

be

made available by the vendor.

5.2.2 Co-ordination meeting

When specified, a co-ordination meeting shall be held at Purchaser's office, preferably within

2

weeks of order. An agenda shall be prepared for this meeting and would include the following

points related to technical aspects.

(a) Any clarifications required by the vendor on purchaser's order.

(b) Vendor Data Index & Schedule.

(c) Vendor Data Review/approval modalities.

(d) Sub-vendor lists proposed by vendor.

(e) Utility requirements.

(f) Preliminary General Arrangement & layout drawings & purchaser‟s interface

drawings.

5.2.3 Drawings

5.2.3.1 The number of prints and/or reproducible required and the times within which these

are

to be submitted by vendor are specified in Purchaser's inquiry/order.

5.2.3.2 The purchaser's review of the vendor's drawings shall not constitute permission to

deviate from any requirements in the purchase order / specifications unless specifically

agreed

upon in writing. After the drawings have been reviewed, the vendor shall furnish certified

copies in the quantity specified. All drawings must be clearly legible and shall be folded to

216

mm x 279 mm size. All transparencies shall be rolled.

5.2.3.3 Drawings/documents with following titles shall contain as a minimum the following

information:

a) General Arrangement Drawing

A general arrangement drawing shall indicate:

i) Outline dimensions (minimum three views) (All principal dimensions).

ii) Location (in all three planes), size, type, rating and identification

of the heaviest assembly/components that must be handled, far erection, 145

SIGN & SEAL OF CONTRACTOR

vi) Identification and weight, dimensions of the heaviest assembly / subassembly /

component required to be handled for maintenance,

vii) Maintenance clearances and dismantling clearances,

viii) Speed

ix) Layout of auxiliary equipment and operating platform,

x) Make, Type and Size of couplings and the location of guards,

xi) A list of reference drawings if any.

xii) A list of any special weather-protection and climatic features.

b) Foundation Drawings

A foundation drawing shall indicate complete information required for foundation design by

purchaser including the following:

a) Foundation bolt sizes & pipe sleeve details and pocket sizes & locations.

b) Grouting thickness and other necessary technical details.

c) Static weight of each independently grouted item (such as diesel engine, gear box (if

required),driven equipment, control panel etc.) and location of center of gravity of each of

such items in all three planes.

d) Weight distribution for each bolt/sub hole-plate location and total static weight.

e) Dynamic loads, if any, caused due to various items grouted independently. (The cause of

generation of such loads shall also be indicated).

f) The direction and magnitude of unbalance forces and moments (with their phase angles)

generated by the out of balance of the rotating / moving parts of the machine at the relevant

operating conditions. [These loads and their locations are to be given in all three planes.

These

shall be utilized for computing the amplitudes of vibration of the foundation].

g) GD2 value of each item resolved to driver speed.

h) Maximum permissible amplitude of vibration on the foundation at the base level.

(The location of the points on the foundation base where such amplitudes are not to be

exceeded shall be given in all three planes). The reference of relevant code, if any. shall also

be

indicated,

i) Total mass of rotating parts,

j) Total mass of reciprocating parts,

k) Suggested dynamic factor and ratio of weight of foundation to weight of machine.

I) Short circuit loads caused in motor drivers,

m) Operating speed of the machine and the driving motor,

n) Scope of Supply of the Foundation Bolts (unless otherwise specified, by vendor),

o) Maximum permissible magnitude of the unbalance forces and moments generated by

the out of balance of the rotating / moving parts of the machine as allowed by the relevant

codes, if any. (The reference of such code, if any, shall also be indicated),

p) Recommended separation margin (if any), between the machines operating speed and the

natural frequencies of the machine foundation system along with the basis of such

recommended separation margins.

[Note: Unless otherwise indicated by vendor, the dynamic forces as given in e) & 1) above

are

considered as additional static loads for designing the foundations statically". Such dynamic

forces are not unbalance forces and therefore, these shall not he utilized for computing the

amplitudes of vibration.)

5.2.4 Datasheet

The Vendor shall provide completely filled in data sheets, first for "As Purchased" and then

for "As Built". This shall be done by the vendor correcting and filling out the data sheets and

submitting copies to the purchaser.

146

SIGN & SEAL OF CONTRACTOR

5.2.5 Technical Data Manual/Mechanical catalogues

5.2.5.1 Mechanical catalogue is a compilation of "As Built" drawings and data,

manufacturing and test records, installation, operating and maintenance instructions.

5.2.5.2 Not later than two weeks after successful completion of all specified tests, the vendor

shall furnish the required number of mechanical catalogues for. .the equipment, any

auxiliaries and instruments that the vendor is providing. The mechanical catalogue shall

include the

following documents as a minimum:

i) All drawings and data as listed in the vendor data index & schedule. (For drawings,where

purchaser's approval is required, the final certified drawings shall be attached.)Sections shall

be organized in a manner that data & drawings related to one subject is grouped together such

as Mechanical, Electrical, Instrumentation etc. in hard and soft form

ii) All manufacturing, inspection and test data and records in hard and soft form.

iii) Installation and Instruction Manual

The vendor shall provide sufficient written instructions, including a cross-reference list

of all drawings, to enable the purchaser to correctly install the equipment and prepare

the equipment for start-up! It shall include any special information required for proper

installation that is not on the drawings, special alignment or grouting procedures, utility

specifications (including quantity) and all installation data.

iv) Operation and Maintenance Manual

This manual shall provide sufficient written instructions and data to enable purchaser to

correctly operate and maintain the equipment ordered. It shall include a section to cover

special instructions for operation at extreme environmental and/or extreme operating

conditions. The following shall be included in this manual:

a) Instructions covering start-up, normal shutdown, emergency shutdown,

operating limits .and routine operational procedures.

b) A description of equipment construction features and the functioning of

component parts or systems (such as control, lubrication, etc.).

c) Outline and sectional drawings, schematics and illustrative sketches in

sufficient details to identify all parts and clearly show the operation of all

equipment and components and the methods of inspection and- repair.

Standardized sectional drawings are acceptable only if they represent the actual

construction of the equipment.

v) Following information shall also be included in the Mechanical Catalogue:

1. Storage instructions for storing and preserving the equipment (including

auxiliary units) at the plant site before installation of the same.

2. Field test procedures and acceptance criterion.

5.2.5.3. Technical Data Manual/ Mechanical Catalogue shall be in Hard board folder(s) of

size 265mm x 315 mm (l0'/i" x 12'/z") and shall not be-more than 90 mm thickness;-it may be

of

several volumes and each volume shall have a volume number, index of volumes & index of

contents of that particular volume.

5.2.5.4 Title sheet (Top sheet) of each volume of mechanical catalogue shall contain the

contract

information as defined under 5.2.1.2 besides the volume number.

5.2.5.5 In case order contains more than one item, separate dedicated Technical Data Manual/

Mechanical Catalogues shall be submitted for each item.

147

SIGN & SEAL OF CONTRACTOR

3.0 GENERAL REQUIREMENTS

3.1 The offered equipment shall be brand new with state of the art technology and a proven

field

track record. No prototype equipment shall be offered.

3.2 Vendor shall ensure availability of spare parts and maintenance support services for the

offered equipment for at least 15 years from the date of supply.

3.3 Vendor shall give a notice of at least one year to the end user of equipment and Union

Bank of India before phasing out the product/ spares to enable the end user to place order for

spares and services.

3.4 The vendor shall be responsible for design, engineering and manufacturing of the

complete

system to fully meet the intent and requirements of this specification and attached data sheets.

The Battery Charger equipment shall be properly coordinated with the selected Battery to

ensure complete compatibility.

3.5 The Battery shall meet the requirements of data sheets and specifications attached with

the

Material Requisition/ Bid document.

4.0 POWER SUPPLY AND SITE CONDITIONS

All equipment shall be designed to operate with power supply and site conditions as specified

below and in the attached data sheet:

4.1 Power Supply

Unless specified otherwise, the following power supply shall be provided by purchaser at one

point for each engine:

Voltage : 415V +10%,TP+N

Frequency : 50Hz + 5%

System earthing : Solidly earthed

Fault level :50 kA through fuse.

4.2 Site Conditions

The site ambient conditions are indicated in attached data sheet. Unless specified otherwise,

all

equipment shall be suitable for installation and operation on the package skid, which shall be

located in a closed building with restricted ventilation.

If not specifically mentioned in the data sheet, an ambient temperature of 42°C and altitude

not

exceeding 1000m and minimum temperature of 10°C shall be considered for equipment

selection and battery sizing.

5.0 REQUEREMENTS FOR BATTERY UNITS

5.1 The batteries shall be lead acid, high discharge automotive type conforming to IS 7372

and

suitable for engine starting duty. The battery containers shall be of high quality translucent

plastic/ hard rubber. Terminal posts shall be properly sealed to prevent electrolyte leakage.

Venting device shall be anti-splash type. Batteries shall be placed on battery stands made of

steel with suitable PVC coating. All accessories like cell insulators, connectors, stand

insulators etc. shall be supplied with each set. All hardware shall be suitably coated/ plated to

prevent corrosion.

148

SIGN & SEAL OF CONTRACTOR

5.2 Ampere-hour capacity of the battery shall be selected based on the load cycle (to be

decided by the vendor), Ageing factor of 0.8 and temperature correction factor for specified

minimum

temperature. The battery capacity shall be adequate for six consecutive -starts of the engine

under cold engine conditions without recharging, with an additional 10% spare capacity. All

auxiliary loads for engine controls shall also be considered while defining the load cycle.

Also,

refer clause 8.0 of this specifications.

5.3 The battery shall be suitable for being quick charged from a fully discharged condition to

a

fully charged condition within 10-14 hours.

5.4 The following accessories shall be provided for preventive and routine maintenance of the

batteries at each location where the engines are to be installed:

1 no Hydrometer (syringe type)

1 no Thermometer

1 no Cell testing voltmeter with leads (Center zero type)

1 pair Rubber gloves

1 no Spanner

1 no Acid resistant jug and funnel

1 no Teak wood holder for the hydrometer.

6.0 REQUIREMENTS FOR BATTERY CHARGER

6.1 The charger shall be suitable for both float charging the battery while feeding all loads,

other than engine starting motor, as well as for quick charging the battery from fully

discharged condition to fully charged condition within 10-14 hours. The sizing of the battery

charger shall be based on the maximum continuous rating required to meet the above

conditions, with an additional 10% spare capacity. All DC loads for engine controls and

continuously operating auxiliaries shall also be considered for this purpose.

6.2 The charger shall be of solid-state design, constant voltage and current limit type. The

output voltage shall be stabilized to +1 % for mains variation of + 10% and load variation of

0 to100%. Each load shall be fed through a separate independent feeder. However, a separate

DC Distribution Board is not essential for this purpose and the outgoing feeder circuit can

form a part of the charger panel.

6.3 The charger shall have a 3 phase full wave controlled rectifier consisting of thyristors,

commutation circuits, diodes etc. and then- protective devices. A suitable filter circuit shall be

provided at the rectifier output to obtain a smooth DC output voltage. The maximum ripple

content in the charger output voltage shall be lower than the safe value recommended by

battery manufacturer, and in any case, shall not exceed 5% with battery disconnected.

6.4 The charger shall have auto as well as manual control facility through a lockable selector

switch.

6.4.1 Auto Mode

In the Auto mode, the charger shall automatically control the battery charging current/

voltage

to ensure optimum quick charging of the battery. After completion of boost charging, the

charger shall switch to float charging mode without any manual intervention.

149

SIGN & SEAL OF CONTRACTOR

6.4.2 Manual Mode

In the Manual mode, it shall be possible to charge the battery at any desired current, which is

safe for the battery. Fine control of the output voltage/ current shall be possible.

6.4.3 In both Auto and Manual modes, the battery charging current shall be limited to a safe

valueas prescribed by battery manufacturer by means of adjustable potentiometer control. A

backup timer of 0-24 hrs having range with no-volts hold feature shall be provided for

switching the charger from quick charging to float charging mode after the set time, under

any mode of

Operation.

6.5 The charger shall be complete with all interconnections within the panel. All connections

shall be made using 660/1100V grade copper conductor PVC insulated wires/ cables with

BIS marking for both power and control connections. Minimum 1.5mm2 conductor size shall

be used for control connections. However, control wiring for electronic circuits/ components

may use flat

ribbon cable or copper wire of minimum 0.5mm diameter. All control wiring shall be

enclosed

in PVC channels or otherwise neatly bunched together. Each wire shall be suitably identified

at

both ends by PVC ferrules. Crimping type lugs shall be used for termination.

6.6 All main and control transformers shall be natural air cooled dry type suitable for location

inside a panel. All semiconductor devices shall be natural air cooled with absolute case

temperatures limited to 75°C at highest load and ambient temperature. PCBs shall be of

copper

clad glass epoxy laminate construction. PCB tracks shall be tinned and solder masked. PCBs

shall be tropicalized to render them immune to dust, moisture and fungal growth.

6.7 Selection, sizing and suitability of all components used for various applications shall be

vendor‟s responsibility and the rating of components shall be increased, if required, to suit

associated components during execution of the order without any claim for extra price or

time.

All electronic power devices including thyristors, transistors, diodes etc. shall be rated under

operating conditions for at least 150% of the maximum current carried by the device. All

electrical components such as transformers, reactors, contactors, switches, busbar etc. shall be

rated for at least 125% of the maximum required rating. No electronic device shall experience

a PIV greater than 50% of its rated value. Series-parallel combination of smaller devices to

achieve specified rating shall not be acceptable.

6.8 A suitably sized earth bus of minimum size 25x3 mm2 copper shall be provided at the

bottom of the panel with provision to connect it to the owner‟s main earth grid at both ends.

6.9 The charger shall be suitably housed in a 1.6/ 2mm thick sheet steel enclosure having

minimum IP-41 degree of ingress protection. The panel shall be free standing, floor mounted

type with hinged doors and shall be suitable for bottom cable entry. The maximum and

minimum operating height shall be 1800mm and 300mm respectively. Eyebolts shall be

provided on the top cover for lifting. When removed, the eyebolts should not leave any

openings in the panel.

6.10 The charger panel surface shall be properly pre-treated for final powder coating . Epoxy

based powder coating of adequate thickness for rugged industrial use shall be acceptable.

Nameplates shall be of anodized aluminium or stainless steel.

150

SIGN & SEAL OF CONTRACTOR

7.0 CONTROL, PROTECTION, METERING AND INDICATION

The Charger shall be provided with the following features:

7.1 Controls

• Auto/ Manual selector switch

• ON/ OFF switch for incoming power supply

• Float/ Quick charging selector switch

• Potentiometer for coarse and fine control of output voltage

• Backup Timer.

7.2 Protection

• Fault protection on input and output circuits

• Suitable semiconductor fuses for all thyristors and semi conducting power devices.

7.3 Metering

• AC input voltmeter and ammeter with selector switch

• DC output voltmeter and ammeter

• All meters shall be of 72mm square size with accuracy class 1.5.

7.4 Indication

The following minimum indications shall be provided:

• AC power ON (3 lamps)

• Charger in „Float Charging‟ condition (Yellow)

• Charger in „Quick Charging* condition (Green)

• Charger failure (Amber)

Indicating lamps using Clustered/ Jumbo LEDs in place of filament lamps can also be

accepted. In addition, facility for remote indication of AC and DC failure shall be provided.

8.0 SPECIAL REQUIREMENTS

In addition to the above, Engines for Fire Water Pumps which are provided with backup

manual starting using an electric starter motor, shall have the following features:

8.1 A separate identical battery bank shall be provided for manual starting.

8.2 The charger shall be suitable for charging both battery banks for Automatic and Manual

starting in position.

8.3 The battery charger shall be fully rated for trickle charging both the battery banks

simultaneously.

8.4 Both battery banks for Automatic and Manual starting shall each be adequate for ten

consecutive starts without recharging with a cold engine under full compression in place of

six

consecutive starts specified at clause 5.2.

9.0 INSPECTION AND TESTING

9.1 Batteries shall have been fully Type tested and certificates for the same shall be furnished.

In

addition, the batteries shall be tested as per applicable standards at battery manufacturer‟s

works for the required duty cycle and other relevant acceptance tests.

9.2 High voltage withstand test (2 kV for 1 minute) shall be carried out on each charger.

9.3 Heat Run Test 151

SIGN & SEAL OF CONTRACTOR

Heat Run test at rated load and minimum supply voltage shall be carried out on each charger

for a period not less than 8 hours. During the test, the temperature of electronic power devices

should stabilize and remain constant for 1 hour, or the test shall be suitably extended until this

is achieved.

9.4 Functional tests shall be carried out on each charger to check the design and operation.

9.5 All tests shall be witnessed by Purchaser or his authorized representative and two weeks

prior

notice shall be given before the date of commencement of tests.

10.0 PACKING AND DESPATCH

All the equipment shall be divided into multiple sections for protection and ease of handling

during transportation. The equipment shall be properly packed for selected mode of

transportation, i.e. by ship/ rail or trailer. It shall be wrapped in polythene sheets before being

placed in crates/ cases to prevent damage to finish. The crates/ cases shall have skid bottoms

for handling. Special notations such as „Fragile‟, „This side up‟, „Center of, gravity‟,

„Weight‟, „Owner‟s particulars‟, „PO no.‟ etc., shall be clearly and indelibly marked on the

packages together with other details as per purchase order. Any damage to the materials

during transport shall be replaced by the vendor free of cost.

The equipment may be stored outdoors for long periods before installation. The packing shall

be completely suitable for outdoor storage in areas with heavy rains and high ambient

temperature unless otherwise agreed. In order to prevent movement of equipment/

components within the crates, proper packing supports shall be provided. A set of instruction

manuals for erection, testing and commissioning, a set of operation and maintenance manuals

and a set of final drawings shall be enclosed hi a waterproof cover along with the shipment.

152

SIGN & SEAL OF CONTRACTOR

STANDARD SPECIFICATIONS FORACOUSTIC ENCLOSURE

1. SCOPE OF SUPPLY:

Supply of containerized type ACOUSTIC ENCLOSURE suitable for 1 No. 200 KVA DG set

driven by radiator cooled diesel engine.

2. DESCRIPTION:

The acoustic enclosure shall be of free standing, floor mounting type integral with the DG set.

The enclosure shall be provided with rugged heavy-duty structural steel base frame with

chequered plate flooring on which the DG set is to be mounted. The enclosure shall be

prefabricated factory-built and modular in construction, so that it can be easily assembled at

site around the DG set. The enclosure shall consist of acoustically treated panels housed in

rugged steel frames, which shall be bolted together to from the body of the enclosure. Sliding

doors shall be provided, on either side, which shall also be acoustically treated, thereby

providing easy access to the DG set while minimizing the operating space requirements. The

construction of the acoustic enclosure shall be such that with both the acoustic doors open on

the either side, full access is available to the engine and alternator. For fresh air inlet into the

system a parallel baffle air inlet silencer shall be provided. Additionally, to augment the fresh

air inlet requirements, a forced air ventilation duct with associated silencer shall be provided

above the alternator. For hot air discharge, an acoustic discharge plenum shall be provided in

front of the engine radiator, for discharge of hot air into the surroundings through a parallel

baffle air outlet silencer. The enclosure shall have suitable openings in the roof module for

exhaust piping.

3. CONSTRUCTIONAL FEATURES:

a. The construction and design of the Acoustic enclosure shall be very rugged, durable and

shall be virtually maintenance free.

b. The acoustic panels shall be filled with a special grade high-density mineral wool retained

on the inside by perforated GI sheets specially designed for optimum sound attenuation.

c. The outer surface of the Acoustic Panels and all steel shall be fabricated of performed

14/16G corrugated CRCA sheet steel of a reputed make only.

d. All structural members such as angles / channels used in the construction of the enclosure

frame shall of reputed make only.

e. All materials used for Acoustic Enclosure shall be fire resistant / fire retardant grade.

f. The sheet steel treatment shall consist of degreasing, de-rusting and phosphating followed

by two coats of zinc chromate primer, followed by two coats of Zinpholite surface for

superior corrosion resistance and two coats of finish paint.

g. For effective Acoustic sealing, necessary gasketing material shall be provided.

h. All hardware and fittings used shall be passivated with zinc.

4. PERFORMANCE:

With the above Enclosure, to meet stringent MoEF/ CPCB norms of75 dBA @ 1mtr at 75%

load under free field conditions. The acoustic enclosure is made of CRCA sheets, High

quality noise absorbent and fire-retardant grade acoustic insulation material complying to IS

183.

5. DIMENSIONS:

It shall be ensured that at least 750mm (min.) clear space is available all around the Acoustic

Enclosure to ensure free air flow for the Genset as required and to facilitate accessibility for

generator operation and routine maintenance.

153

SIGN & SEAL OF CONTRACTOR

The enclosure shall be provided with suction fans to ensure that the adequate cooling and

combustion air is made available to the engine and the temperature within the enclosure is

limited to 5 deg C. above ambient. The fan shall be designed with sufficient static to draw the

requisite quality of air from the duct provided for this purpose. Calculations shall be

furnished to prove the adequacy of the ventilation system offered. The suction fans shall start

automatically when the temperature in the enclosure reaches 40 degree C, and shall continue

to run for 5 to 10 minutes after the load is disconnected. A temperature controller shall be

provided for this purpose housed in sheet steel enclosure.

Two light points controlled by a switch complete with 36W fluorescent Luminaries and

lamps shall be provided. Provision shall also be made for fixing a heat detector inside the

acoustic enclosure which will be connected to the central fire alarm panel.

Necessary openings shall be made for the entry of power cable and control cables, fuel

piping, exhaust piping, air inlet pipe etc.

With the installation of the acoustic enclosure, there shall not be any de-rating of the DG set.

The maximum temperature of oil and water shall not exceed the limits prescribed by the

manufacturer of the engine. The DG set shall give rated output continuously.

The ventilation system shall be designed to provide an air volume to suit the DG operation

with Continuous rating. The ventilation fan shall be of the axial flow type designed to handle

the static pressure estimated based on the inlet air duct size and length.

154

SIGN & SEAL OF CONTRACTOR

STAFF COLLEGE, BANNERGHATTA, BENGALURU-560 083

TENDER PROPOSAL FOR SUPPLY, TESTING, INSTALLATION AND COMMISSIONING OF 1 NO.

200 KVA DIESEL GENERATOR AT UNION BANK OF INDIA, STAFF COLLEGE,

BANNERGHATTA, BENGALURU-560 083

PRICE BID

OWNER:

UNION BANK OF INDIA

STAFF COLLEGE

BANNERGHATTA ROAD

KALKERE POST

BENGALURU-560083

155

SIGN & SEAL OF CONTRACTOR

SCHEDULE OF QUANTITIES AND RATES

1. Lump sum price quoted in the schedule and rates shall be inclusive of value of the

work described including all costs, expenses, taxes, duties, etc., which are

required in for the completion of the work described together with all risks and

liabilities and obligations set forth or implied in the contract.

2. The offer quoted shall remain firm during currency of the contract irrespective of

fluctuations in international market and dollar prices. Conditional offer submitted

is likely to be rejected. Any statutory changes in the tax structure i.e increase or

decrease by the State or Central Govt. shall be reimbursed/recovered separately as

per actuals.

3. All the materials, tools, plant, machinery etc., required for the work is to be

procured by the tenderer and his rates shall account for the same.

4. The rates quoted shall be firm till the completion of the work and no escalation

is payable.

5. Interim payment shall be regulated as per the Payment schedule.

156

SIGN & SEAL OF CONTRACTOR

Preamble to Schedule of Quantities 1. The preamble shall form part of the schedule of quantities and bidder to quote for

items in the schedule of quantities in conjunction with preamble. No deviation at

later date shall be entertained.

2. Manufacturing of DG set shall commence after obtaining drawings duly approved

by Consultant/Union Bank of India. The bidder shall also submit QAP/ITP for

approval by Consultant/Union Bank of India.

3. The successful bidder shall provide inspection of DG at manufacturer‟s location

before installation and commissioning of the DG set with prior advice of 7 days by

Union Bank of India and Project Architect. The charges for the same to visit the

manufacturers place by Representative of Project architect and Bank shall be

included in quoted rate and Vendor should bear the cost. Also DG set should be

tested as per specification before delivering to site.

4. After completion of manufacturing process of DG set, it should be tested for

running the same for 12 hours with full load capacity (200 kVA) and it should be

run for additional 1 hour with over load capacity at the manufacturer‟s place.

5. Third party inspection by approved Third party inspecting agency is also included

in scope of work and charges for the same shall be included in quoted rate.

6. Schedule of quantities and Technical Specification should be read in conjunction

while quoting the rates. Any deviation shall be furnished in the technical bid as

per prescribed format.

7. The party shall keep provision for Building Management System (BMS)

outputs such as voltage, frequency etc. which shall be integrated later by

another agency.

157

SIGN & SEAL OF CONTRACTOR

BILL OF QUANTITIES

Name of Work: Supply, Installation, Testing and Commissioning of 1 No.

200 KVA Diesel Generator at Union Bank of India, Staff College,

Bannerghatta road, Kalkere post, Bengaluru-560 083.

CIVIL WORKS:

SL.NO

DECRIPTION

UNIT

QUANTITY

RATE

AMOUNT

1

KSRB 2.2-6 : Excavation for foundation of DG set in pits up to 1mtr depth in Soil and erecting DG foundation as shown in drawing. Carrying out back filling of the balance excavated area and stacking and removing surplus earth within in a compound 30mtr away from the site as directed etc complete in all respect

Cum

22

3

KSRB 6-2.2 : Providing and constructing burnt brick masonry with approved quality of non-modular bricks of standard size of class designation 5.0 Newton per sqmm (table moulded) with cement mortar 1:6 for Basement and superstructure including cost of materials, labour charges, scaffolding, curing complete as per specifications. Specification No. KBS 6.2

Cum

8

4

KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @180kgs, with 20mm and down size graded granite metal coarse aggregates @0.85cum and fine aggregates @0.57cum machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2

Cum

2.5

5

KSRB 4-2.1 : Providing and laying in position reinforced cement concrete of design mix M25 with OPC cement @ 340kgs, with 20mm and down size graded granite metal coarse aggregates @0.70cum and fine [email protected], with superplastiser @ 3 liters confirming to IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return walls, walls (any thickness) including attached plasters, columns, piers, abutments, pillars, posts, struts, buttresses, bed blocks, anchor blocks, plinths etc., including cost of all materials, labour, HOM machinery, curing, complete but excluding cost of reinforcement as per specifications. Specification No. KBS 4.1, 4.6

Cum

11

158

SIGN & SEAL OF CONTRACTOR

159

SIGN & SEAL OF CONTRACTOR

6

KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for vertical surface such as walls at any thickness, including attached pilasters, buttresses, plinth cills and string courses cost of all materials, labour, complete as per specifications. Specification No. KBS 4.6.2

Sqm

19

7

KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500 (Item No. - 4.46.2, Page No. 17 )

Tonne

1

8

Supply & Installation of welded mesh panels of 76.2mm x 12.7mm, pregalvonized Hot dip Galvanized, Zincalu, Polyester powder coating, Thermoplastic coating Fencing all around the DG yard using 80x60x4mm steel sections with suitable size of beams of 2.3mts high, with lockable gate including providing concrete foundation for all vertical supports & raising the level of the yard if necessary, and providing one layer of 40mm Jelly stones, complete etc.

Sqm

60

9

KSRB 15.18-1 : Applying red lead ready mix priming coat over new steel or other metal surface including preparing the surface after thoroughly cleaning oil, grease, dirt and other foreign matter and scoured with wire brushes, fine steel wool, sand papers including cost of materials, labour, complete as per specifications.

Sqm

140

10

KSRB 15-18.2 : Providing and applying enamel metal paint two coats ( excluding priming coat ) over new steel or other metal surface brushing to give an even shade after cleaning oil, grease, dirt and other foreign matter, including cost of materials, labour, complete as per specifications. ---etc.,complete,with all lead & lifts and as per the detailed specifications and directions by the Engineer in charge of the work.

Sqm

140

11

Providing and installing of pre painted Galvolume iron Trapezoidal profiled sheet of approved make 1060mm width (1000 mm cover width), 28-30 mm crest height with crest distance of 200 mm c/c with 2 ribs at the centre for stiffening. The total coated thickness (TCT) of the sheet will be 0.47 mm +/– 0.02 mm tolerance Zinc-Al Alloy coating AZ150 gsm as per ASTM 1397/A755-550 mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 20-22 microns using self drilling/self tapping screws of 25mm length, to be fixed over the existing purlins, rafters, channels and trusses.

Sqm

55

12 Providing and installing of approved make

pre painted Galvalume iron. Accessories like plain ridges, plain gutter, plain flashing, corner Trim, etc. The total coated thickness (TCT) of the sheet will be 0.47 mm +/– 0.02 mm tolerance. Zinc-Al Alloy coating AZ150 gsm as per ASTM 1397/755-550 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 20-22 microns using self drilling/self tapping screws of 25mm length (width upto500-600 mm only), to be fixed over the existing purlins, rafters, channels and trusses.

Sqm

55

13 Fabricating, supplying and erecting M.S. tubular trusses of all spans with Prefabricated steel applications using quality material and are durable, reliable and corrosion and abrasion resistant .Welding shall confirm to latest structural welding code. Quality shall be on various parameters like shape, size, design gauge and polish. The entire trusses is anchored in MS round column with the help of welding. The work includes cutting, straightening, placing in position of M.S. pipes and welding wherever necessary and applying one coat of redoxide primer coat to all the members including cost of materials, labour charges, and hire charges of machineries for cutting, welding, grinding and erection equipments, with all lead and lift, transportation etc., complete as per specification.

Kgs

1500

14 Supplying, erection, testing and commissioning of 200 KVA Diesel Generating Set on existing CC platform Comprising of Diesel Engine Developing ..... BHP @ 1500 RPM confirming to BS 5514.The engine should be turbocharged, Air/water cooled with 10 % over load for 1hour in every 12 hours of operation coupled to suitable capacity alternator rated at 415V, 0.8 PF(lag) 50 Hz, 3 phase, 4 wire system, confirming to BS 5000/IS 4722. The alternator shall be of brushless type ,Screen protected, revolving field, Mounted on suitable Channel Iron Base Frame, Complete with suitable capacity Fuel Tank, required nos. of Batteries of 12/24V as per requirement, Including exhaust pipe of 20mtrs height. Acoustic enclosure as per CPCB Approved Norms

Each

1

160

SIGN & SEAL OF CONTRACTOR

15 Supply, Erection, testing and

commissioning of AMF panel suitable for

200 KVA DG set. The panel is of cubical

type base/floor mounting control panel

with hinged doors, undrilled bottom

gland plate, aluminum Bus Bar with the

accommodation for .....amps 4 pole

contactor for alternator with thermal

O/L relay,..... Amps 4 pole contactor

for mains, HRC fuse for short circuit

protection, Microprocessor based AMF

module with supply failure timer,

Restoration timer, 3 impulse automatic

engine start/stop logic, Mains/generator

voltage, ....capacity bypass switch and

frequency sensing, PCC 1301 controller

with water temperature/Lube oil

pressure/ engine speed,

Voltage/ampere/Frequency/ KVA,

Running-hour count, No of starts, Fault

indication, over /under speed, Fails to

start, Low oil pleasure, High engine

temperature, Under/over voltage, over

current, Earth fault relay, with

indications for Mains on, Load on Mains,

Battery charger on Push buttons AMf

module by pass Mode, Battery charger

unit with inbuilt Auto /Manual and

Flat/Boost facility. (160kva/250kw)

Each

1

16 Providing And supplying Powercable-

2RX240Sqm Cable including labour

charges as per specifications.

Mtrs

40

17 Supplying fixing and wiring earth

electrode for grounding of lifts,

transformers, DG sets etc. using 40mm

dia 2.9mm thick 2.5 mtr long GI pipe

with GI funnel with mesh and suitable

size reducer fixed on the top of the

earth electrode. The funnel should be

enclosed in a CC chamber of

400x400x400mm with a cast iron cover.

The earth electrode shall have

staggered holes of 12mm dia and the

electrode should be covered 150mm all-

round with alternate layers of salt and

charcoal from the bottom of the CC

chamber. The connection from the

electrode is to be established through

GI strip using GI bolts and nuts.

Nos

2

161

SIGN & SEAL OF CONTRACTOR

18 Supplying and running of GI/Copper

strips for grounding connections, using

necessary fixing materials as required.

GI strip 25x6mm

Mtr

30

19 Supplying and running of GI/Copper

strips for grounding connections, using

necessary fixing materials as required.

Copper strip 25x6mm

Mtrs

25

20 Providing And supplying Control cable

strips including labour charges as per

specifications.

Mtrs

40

162

SIGN & SEAL OF CONTRACTOR