ssen003 nests - stage gate - decision to proceed v1
TRANSCRIPT
SHE Transmission New Suite of Transmission Structures: NeSTS (SSEN003)
Stage Gate – Decision to Proceed
September 2018
Contents and Overview
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 2 of 20
Contents
Overview of NeSTS .................................................... 2
Executive Summary ................................................... 3
NeSTS Stage 1 Progress ............................................. 4
Stage Gate Inputs ...................................................... 6
Stage Gate Outputs:
Refreshed NIC Business Case ........................................ 10
Refreshed NIC Business Case Supporting Information . 15
Decision to Proceed ................................................. 18
Appendices
1. SSEN003 NeSTS: Design Selection (SDRC 11.1)
2. SSEN003 NeSTS: Outputs of Stakeholder Engagement (SDRC 11.2)
3. SSEN003 NeSTS: Creation of Technical Specifications (SDRC 11.3)
4. Main Contractor’s Design Endorsement Report
5. Main Contractor’s Cost Comparison Report
6. TNEI Refresh of Overhead Line Volumes
Note: Appendices 4 & 5 are considered confidential.
Overview of NeSTS
Scottish Hydro Electric Transmission plc (SHE Transmission) is developing a New Suite of Transmission Structures (NeSTS), which are planned to be deployed on the Transmission Network
Overhead lines (OHLs) built using transmission structures are the most visible element of the transmission network, and the impact OHLs have on the environment can cause stakeholders concern.
The only available alternative to the steel lattice structures traditionally used in OHL construction is the T‐Pylon. Developed by National Grid Electricity Transmission (NGET), the T‐Pylon reduces the visual impact of OHLs but may be unsuited to areas with challenging terrain and propensity for severe weather events.
Establishing new infrastructure in these areas is essential to connect renewable generation, so there is a need for a new type of structure to address stakeholder concern.
The NeSTS project will develop innovative designs for OHL structures based on new technologies and techniques. The new suite of structures will then be deployed on the transmission network.
The NeSTS Project seeks to prove the following benefits:
o Improved OHL environmental performance by lowering visual and construction impacts; and
o Lower OHL whole life asset costs via reduced land, construction, maintenance and outage requirements.
Executive Summary
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 3 of 20
The Project has designed a new suite of transmission structures in response to stakeholder inputs.
Stakeholders support the project and have assessed that the new supports could reduce the environmental impact of overhead lines.
The NeSTS designs have been endorsed by a main construction contractor and have been used to design an overhead line in parallel with a traditional lattice design.
The main contractor estimates that the costs of construction using NeSTS are comparable to those using lattice steel, and there is potential for cost saving in operation of the OHL assets.
A refreshed analysis of future OHL requirements has indicated that there is still substantial need for new OHLs which could benefit from lower environmental impact enabled by NeSTS.
The Project is making good progress towards its aims and objectives on paper, and SHE Transmission has approved its progress to Phase 2.
This report summarises the Project’s Phase 1 design progress and the evidence SHE Transmission have used to make this decision. It is submitted to seek approval of the decision by Ofgem, as instructed in the Project Direction.
Figure 1: NeSTS 132kV Medium Duty Double Circuit D2
Support
NeSTS Stage 1 Progress
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 4 of 20
The Project initially targeted its design focus at 275kV
OHLs, and selected its design concept based on this
insulation level.
During the subsequent development of a design
prototype, the business case for the OHL being used for
the NeSTS parallel design was reviewed in response to
changing background generation.
The OHL was re‐specified to be insulated at 132kV, and
the NeSTS prototype and parallel design processes were
re‐focussed to produce corresponding 132kV designs.
The translation of form, fit and function from 275kV to
132kV has been successfully implemented, and the
comparative environmental benefits retained.
Comparative visualisation of the NeSTS 275kV Medium
Duty design and a L8RD lattice equivalent are shown in
Figure 2.
Comparative visualisation of the NeSTS 132kV Medium
Duty Double Circuit design and a L7c lattice equivalent are
shown in Figure 3.
Figure 2: Visualisation of NeSTS 275kV Medium Duty and L8RD Benchmark in Upland Moorland
NeSTS Stage 1 Progress
© Scottish and Southern Electricity Networks SSEN03 NeSTS Design Selection Rev 1.0
Uncontrolled if Printed Page 5 of 20
Figure 3: Visualisation of NeSTS 132kV Medium Duty Double Circuit and L7c Benchmark in Upland Moorland
The parallel design process used to inform this Stage Gate is based on the NeSTS 132kV Medium Duty Double Circuit suite.
However, due to better fitting the Project’s programme, the current intention is to construct a 132kV single circuit NeSTS OHL in Phase 2 of the project, and this design is currently being developed.
The Project plans to complete the technical specification of the 275 and 132kV medium duty double circuit suites, as reported in Appendix 3: SSEN003 NeSTS: Creation of Technical Specifications.
Stage Gate Inputs
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 6 of 20
Stakeholder Support
The Project has engaged with many different stakeholders, and the outputs of these engagements are driving the NeSTS design.
Work with statutory and non‐statutory consultees to understand their concerns regarding the environmental impact of OHLs has been undertaken. This has included detailed explanation of the OHL design process and the practical constraints involved.
Consultee assessment was used to select the NeSTS design concept and customers have been polled to confirm that their opinion aligns with that expressed by their consultee representatives.
The assessment and selection process is reported in Appendix 1: SSEN003 NeSTS: Design Selection.
Design Response to Stakeholder Input
The engagement with consultees provided several inputs
to the subsequent design refinement process.
International Transmission Owners (TOs) and their supply
chain have been engaged to understand lessons learned
from steel monopole OHL projects, and thus embody the
best available technology into the NeSTS designs.
These outputs of stakeholder engagement are reported in
Appendix 2: SSEN003 NeSTS: Outputs of Stakeholder
Engagement.
A chart summarising consultee stakeholder assessment of
NeSTS improved visual impact performance compared to
lattice steel designs is shown in Figure 4. A neutral
response is translated into a 3, a very good response into
a 5, and a very poor response into a 1. The thin lines
superimposed on the chart bars indicate the range of
responses.
The chart shows that consultee stakeholders anticipate a
substantial reduction in the visual impact of OHLs
constructed using NeSTS supports in comparison to lattice
steel alternatives, and that their assessments of NeSTS
are more convergent than their assessments of lattice
steel.
Figure 4: Consultee Stakeholder Visual Impact Assessment Summary
Stage Gate Inputs
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 7 of 20
Design Endorsement and Publication
NeSTS designs are intended for use across Great Britain’s (GBs) network, and licensees have been engaged to understand lessons learned from previous projects, explain the Project objectives and designs, and share its learning.
The designs have been subjected to scrutiny by structure manufacturers and main construction contractors as part of the process of developing technical specifications.
A design endorsement report for the NeSTS 132kV Medium Duty Double Circuit suite from a main construction contractor is shown in Appendix 4: Main Contractor’s Design Endorsement Report.
The Project has an agreement in principle that the NeSTS
technical specifications will be published by the ENA as
part of the 43 series of OHL technical specifications,
subject to their review by the ENA OHL panel.
These publication plans are detailed in Appendix 3:
SSEN003 NeSTS: Creation of Technical Specifications.
Figure 5: Visualisation of a NeSTS 132kV Double Circuit Medium Duty versus a L7c Overhead line
Stage Gate Inputs
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 8 of 20
Cost Comparison from Parallel Design
Parallel designs for an overhead line have been
compared: one using the NeSTS 132kV double circuit
medium duty suite of structures, and the other using the
traditional L7c lattice steel suite.
Visualisations of each design are shown on the Project’s
website, and excerpted images are shown in Figure 5.
A main construction contractor has estimated the costs of
each design. Their analysis is presented in Appendix 5:
Main Contractor’s Cost Comparison Report, and a
summary infographic of it is shown in Figure 6.
It shows that the estimated costs of each option are
comparable.
An increase in structure procurement and delivery costs is
almost balanced by a reduction in installation and
foundation costs, leaving a 1.7% higher estimate for
construction using NeSTS.
Figure 6: Summary Infographic of NeSTS Parallel OHL Cost Comparison
Stage Gate Inputs
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 9 of 20
Refresh of Future OHL Requirements
The Project commissioned TNEI to refresh the overhead
line volumes in the market assessment report presented
in the NeSTS NIC full bid submission. The result is shown
in Appendix 6: TNEI Refresh of Overhead Line Volumes.
It reports that following the changes to renewable energy
policy in 2015 and changes in NGET’s Electricity Ten Year
Statements (ETYS), on average, 121km of new OHL are
forecast to be required annually through to 2026. This
compares to the forecast average requirement for 250km
annually which was referenced in the NeSTS NIC bid
submission in 2015.
Using this and NGET’s Future Energy Scenarios (FES), the
total forecast OHL demand by 2050 in Scotland in each of
the FES is shown in Table 1.
Future Energy Scenario Total OHL Demand by 2050 in Scotland (km)
Community Renewables 4,528
Consumer Evolution 4,349
Two Degrees 4,466
Steady Progression 4,320
Table 1: Total Need for OHL in Scotland by 2050 in Each Future Energy Scenario
Stage Gate Outputs:
Refreshed NIC Business Case
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 10 of 20
Introduction
SHE Transmission, NGET and Scottish Power Transmission
(SPT) share statutory duties as transmission licensees: to
ensure the development and maintenance of an efficient,
coordinated and economical system of electricity
transmission; to facilitate competition in the supply and
generation of electricity; and to have due regard for
preservation of amenity. The drive toward a low carbon
electricity sector, and in particular, the growth in new
renewable generation in remote areas, requires an
increase in network capacity through the creation of new
infrastructure. The cost of new infrastructure will be
factored into GB electricity consumers’ bills.
TNEI analysis, based upon information contained in
NGET’s Electricity Ten Year Statement, shows that on
average, up to 121km new OHL projects are planned each
year on the GB transmission network until 2026 (see
Appendix 6 for further details). Increasing volumes of
renewable generation combined with the anticipated
increase in future electrical demand require significant
investment to provide the necessary network capacity.
SHE Transmission is investing to upgrade and reinforce
the network, with a £3bn ‐ £5bn investment programme
in progress. The other TOs have similar investment plans
during this period.
Deriving the business case
This section describes the approach used to ensure the
NeSTS business case is robust and how results from the
project are designed to be statistically sound.
SHE Transmission, with support from TNEI, has used
several sources of data to calculate the project’s business
case. These include (i) National Grid’s Electricity Ten Year
Statement (ETYS) (ii) National Grid’s Future Energy
Scenarios 2017 (FES) and (iii) NGET’s Transmission Entry
Capacity(TEC) Register, supplemented by additional
information from SHE Transmission and Project
stakeholders.
Future OHL Build Requirements
The ETYS was analysed to identify the projected volumes
of additional OHL required by each of the TOs during the
2017‐2026 period. This new infrastructure is largely
driven by the growth in new renewable generation and
increased electricity demand. This analysis is described in
more detail in TNEI’s report, contained in Appendix 6.
Beyond 2026, the FES have been used as a basis for
assessing the need for new infrastructure in the longer
term. The FES models a range of scenarios for the
development of the GB transmission system, which have
been used for TNEI’s analysis.
The TEC Register holds details of generation projects
seeking to connect to the transmission network, at
various stages of scoping, consenting and construction.
The TEC Register was also considered as part of TNEI’s
analysis. Overall, the analysis contained in Appendix 6
suggests that on average 121km of new infrastructure will
be required each year.
Stage Gate Outputs:
Refreshed NIC Business Case
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 11 of 20
Calculating financial benefits
In the FES, four scenarios are considered; Steady
Progression, Two Degrees; Consumer Evolution and;
Community Renewables. In order to avoid overstating
the business case for NeSTS, SHE Transmission and TNEI
have used a cautious approach to quantify benefits.
Therefore we have opted to consider only the Steady
Progression and the Two Degrees scenarios to assess the
potential financial benefits.
The new designs are applicable to 132kV, 275kV and
400kV and learning will be made available to all GB
network licensees. However, it is recognised that NeSTS
will not be applicable for every new OHL project.
Therefore, TNEI’s analysis of new infrastructure plans to
2050 is based on the following assumptions:
1. Most new infrastructure at 132kV will take place
in Scotland. A review of the RIIO: ED1 business
plans for English and Welsh distribution network
operators did not indicate a significant volume of
new 132kV OHL build. For this reason, the
business case has discounted 132kV in England
and Wales.
2. NGET are likely to use the T‐Pylon for new 400kV
OHL projects, as it has been specifically designed
for application in the NGET territory. 400kV
projects in England and Wales have therefore
also been excluded from the business case.
3. Analysis of the TEC register suggests that there
are a limited number of renewable projects
which will require new build OHL infrastructure
to connect to the network. Therefore, these
have also been excluded from the analysis.
Full details of the methodology, assumptions and results
are contained in Appendix 6.
Stage Gate Outputs:
Refreshed NIC Business Case
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 12 of 20
NeSTS Financial Benefits
NeSTS construction costs for the trial OHL are forecast to
be comparable to those of building an equivalent lattice
steel OHL.
SHE Transmission considers this a reasonable basis for
constructing a NeSTS OHL to allow the assessment of
actual and potential costs.
The Project is targeting cost savings in several elements of
OHL construction, as detailed in the NeSTS NIC bid
submission. Updates on the learning related to these
elements and the main contractor’s cost comparison
follow in Appendix 5: Main Contractor’s Cost Comparison
Report:
Foundations: The benefits in moving to a monopole style
construction that is less invasive and generally simpler are
supported by stakeholder feedback and the main
contractor’s cost comparison, although the scale of the
cost benefit will vary with ground conditions.
The Project has designed caisson foundations, and
discussed their construction with the GB and international
supply chain, but is unable to use them on the rocky
ground which has been encountered on the OHL design
work so far.
The potential benefits of this type of foundation will be
reported in Phase 2.
Installation: The forecast benefits of shorter and less
complex construction are supported by the main
contractor’s cost comparison and stakeholder feedback.
This element has not yet been exposed to competitive
tendering, and, TOs in the USA report that construction
contractor costs for steel monopole OHL construction
have decreased with experience and innovation of
installation processes in their territory.
The Project plans to explore and report on the potential
of related benefits in Phase 2.
Structure Costs: The cost parity to lattice steel structures
foreseen is not supported by the main contractor’s cost
comparison or supply chain feedback. The increased steel
weight required and the inclusion of tertiary coating in
the factory mean that unassembled structure costs will be
higher than for lattice steel supports.
However, this element has not yet been exposed to
competitive tendering, and, a competitive market for the
supply of steel monopoles exists globally.
The Project plans to explore and report on the potential
of related benefits in Phase 2.
Conductor Systems: The twin earth wire costs reported in
the NIC submission have not been realised as the design
chosen only requires a single earth wire. The conductor
system costs will therefore be the same as those of an
equivalent lattice steel design.
Off‐site Manufacture: The reduced number of
components and reduced assembly requirements are
supported by the main contractor’s estimate of
preliminary cost and stakeholder feedback.
Operating Costs: Ownership cost benefits may exist in the
form of lower land and maintenance costs. NeSTS
footprints are c75% lower than the lattice equivalent, and
consequently wayleave costs are expected to be lower.
The NeSTS supports facilitate easier inspection and
factory applied paint systems are expected to offer longer
intervals between re‐painting.
These benefits will be estimated in Phase 2 of the Project.
Project Management and Consenting Costs: The reduced
project duration implied by the reduced installations and
preliminary costs are expected to result in lower TO
project management costs. Similarly, if stakeholder and
customer support results in faster consenting, TO
consenting costs may be reduced.
The potential for these benefits will be estimated in Phase
2 of the Project.
Following Phase 1 of the Project, SHE Transmission
continues to anticipate that these elements could
generate considerable savings if a successful trial leads to
GB‐wide deployment.
Based on updated information from the supply chain
engagement, SHE Transmission continues to estimate that
the cost of new OHL projects could be reduced by up to
10% over a whole asset life, where projects could realise
all the available benefits.
Stage Gate Outputs:
Refreshed NIC Business Case
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 13 of 20
The information contained in Appendix 6 indicates that
the majority of the OHL work planned by the TOs is for
reinforcement or refurbishment projects. The financial
benefits for TO reinforcement and refurbishment projects
flow directly to transmission customers through
Transmission Use of System charges.
SHE Transmission has adopted a conservative view that
NeSTS will be suitable for up to 15% of the anticipated
projects and has calculated cost savings on this basis.
Should NeSTS be applied to up to 15% of new OHL
projects between 2023 and 2050 and achieves a
reduction in costs of 10%, this could facilitate savings of
up to £68.9 million, as shown in Table 2: Potential NeSTS
Benefits.
Number of projects 2023 to 2050 Two Degrees Steady Progression
Benefit at 5% cost saving (£m) if 5 % of OHL projects are NeSTS‐compatible
£11.5M £11.2M
Benefit at 10% cost saving (£m) if 15% of OHL projects are NeSTS‐compatible
£68.9M £67.1M
Table 2: Potential NeSTS Benefits
Stage Gate Outputs:
Refreshed NIC Business Case
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 14 of 20
Accelerates Low Carbon Sector
New transmission infrastructure is driven by the TOs’
requirement to respond to increasing renewable energy
generation connections.
By offering a new lower impact option for OHL
construction, NeSTS should enable improved stakeholder
and consultee response to some OHL developments,
thereby speeding up the consenting and connection
processes.
This combined with reduced construction time will
accelerate some renewable energy connections, and
hence the low carbon sector.
Innovation with a Purpose
NeSTS will enable GB TOs to offer alternative options to
customers where some lattice steel overhead lines or
underground cables are impractical.
The lower requirements for operative hours at site, both
during construction and for planned maintenance, aligns
with SHE Transmission’s health and safety policy by
reducing staff and contractor exposure to hazards, and its
strategy to focus on safe and efficient operations of
assets.
Relevance and Timing
The Project aligns with SHE Transmission’s strategy to put
the needs of current and future customers at the heart of
everything it does, and to use resources sustainably.
NeSTS is suited to SHE Transmission’s portfolio of
renewable generation connection projects in challenging
and sensitive environments.
The Project is on schedule to deliver its learning by 31
March 2022 as defined in the Project Direction.
Stage Gate Outputs:
Refreshed NIC Business Case Supporting Information
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 15 of 20
OHL Line Costs using Traditional Designs
To assess the cost benefit of the proposed solution it is
first necessary to understand the cost of traditional OHL
projects. There can be significant cost variance
depending on specific project requirements. However, the
benefits have been assessed using information available
in the TO Charging Statements. Note that NGET costs
were not available for this analysis. To enable comparison
with the original business case in the NIC submission,
these values have not been updated in this refresh.
Base Case Costs per OHL Voltage in £000s/km
TO 275kV 132kV
SPT £1,833 £834
SHE Transmission £1,103 £793
Average Cost £1,468 £814
Table 3: Base Case Costs per OHL Voltage
Stage Gate Outputs:
Refreshed NIC Business Case Supporting Information
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 16 of 20
OHL Costs using NeSTS
Using NeSTS instead of traditional lattice steel supports
has the potential to reduce the cost of OHL projects in the
following areas:
Foundations: The estimated foundation costs for the
NeSTS OHL line in the parallel design reported in
Appendix 5 are 3.6% less expensive than those for the L7c
lattice steel OHL line.
This comparison is based on ground conditions which do
not allow use of the caisson style of foundation detailed
in the NIC submission, which is favoured by owners of
steel monopole transmission lines. Consequently, the full
benefits available could not be realised on this OHL
project.
The Project has designed caisson foundations, similar to
those referenced in the NIC submission, whose costs will
be estimated and reported in Phase 2.
Installation: The estimated installation costs for the
NeSTS structures are 49.4% lower than those for L7c in
the main contractors cost comparison. The Project
anticipates that experience and innovation of installation
processes, and competition for supply of these services in
GB could deliver further benefits.
Structure Costs: The estimated costs of NeSTS structures
are 130% more expensive than L7c supports in the main
contractor’s cost comparison. Delivery costs are 182%
higher, as there is no GB manufacturing capability for this
scale of folded steel monopole.
The Project has engaged with several suppliers of steel
monopoles but has yet to expose NeSTS designs to
competition for their supply to an OHL project.
A competitive market for the supply of steel monopoles
exists globally and the Project anticipates that this cost
differential would be substantially reduced by a GB‐wide
deployment, possibly involving the evolution of a GB
manufacturing capability.
Off‐site Manufacture: The estimated preliminary costs for
supply of a NeSTS OHL are 9.9% lower than for the L7c
equivalent in the main contractor’s cost comparison. The
Project anticipates that experience and innovation of
steel monopole line project and construction
management, and competition for supply of these
services in GB could deliver further benefits.
Reduced Operating Costs: Ownership cost benefits may
exist in the form of lower land and maintenance costs.
NeSTS supports have been designed to facilitate lower
maintenance costs. The reduced complexity of the
structures should enable faster and higher quality
inspections, both by climbing operatives and by drone
mounted cameras.
The factory applied paint system should enable less
frequent repainting and therefore lower refurbishment
costs. These attributes should enable reduced
maintenance outage requirements.
Wayleaves have not been agreed for the NeSTS designs,
and therefore this benefit cannot be reported yet. It is
anticipated that the footprint related component of these
costs will fall in proportion to the c75% reduction in as‐
built footprint.
In anticipating the future volumes of OHL required, it has
been presumed that the majority of OHL required by
NGET in England and Wales will use the T‐Pylon design;
therefore, they have been excluded from the calculations.
Similarly, it has been assumed that 400kV works in
Scotland will be delivered using recent designs such as the
SSE400 used for the Beauly‐Denny line.
In order to ensure a conservative, sensible view of
potential benefits, SHE Transmission postulated that a
traditional steel lattice or T‐Pylon may be used for new
OHL deployment at 132kV and 275kV – to this end, we
have assumed that only between 5% and 15% of future
new build OHL will be suitable for NeSTS.
SHE Transmission has focussed on the two most prudent
scenarios in the FES to estimate benefits. Note that all of
the benefits arising from cost reductions in infrastructure
projects will flow directly to transmission customers
through TNUoS
Stage Gate Outputs:
Refreshed NIC Business Case Supporting Information
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 17 of 20
NeSTS continues to represent good value for customers
with only relatively modest volumes of OHL requiring to
be built in order to recover the Project’s costs. Based on
the costs identified in the TOs Charging Statements
referenced in the NIC submission, the volume of new
275kV or 132kV OHL required to recover the Project costs
is shown below in Table 4.
Table 4: Minimum OHL Distance to Recover NIC Cost
Average Cost
£000s/km
10% Cost Reduction Minimum distance
to recover NIC cost
275kV OHL £1,468 £146k 45km
132kV OHL £813 £81k 82km
Decision to Proceed
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 18 of 20
The SHE Transmission Steering group has considered the
evidence detailed in this report and has concluded that
the Project is making good progress towards its aims and
objectives.
Stakeholders support the project and have assessed that
the new supports could reduce the environmental impact
of overhead lines.
The NeSTS designs have been endorsed by a main
construction contractor and have been used to design an
overhead line in parallel with a traditional lattice design.
The main contractor estimates that the costs of
construction using NeSTS are comparable to those using
lattice steel, and there is potential for further cost saving
in a deployment to business as usual if the trial is
successful.
A refreshed analysis of future OHL requirements has
indicated that there is a substantial need for new OHLs
which could benefit from lower environmental impact
enabled by NeSTS.
SHE Transmission has therefore decided that the Project
should proceed to Phase 2 including the construction of a
trial OHL, and seeks Ofgem approval in response to this
submission as instructed in the Project Direction.
This page is intentionally blank.
© Scottish and Southern Electricity Networks SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0
Uncontrolled if Printed Page 19 of 20
SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 – September 2018
Scottish and Southern Electricity Networks is a trading name of: Scottish and Southern Energy Power Distribution Limited Registered in Scotland No. SC213459;
Scottish Hydro Electric Transmission plc Registered in Scotland No. SC213461; Scottish Hydro Electric Power Distribution plc Registered in Scotland No.
SC213460; (all having their Registered Offices at Inveralmond House 200 Dunkeld Road Perth PH1 3AQ); and Southern Electric Power Distribution plc Registered
in England & Wales No. 04094290 having its Registered Office at No.1 Forbury Place, 43 Forbury Road, Reading, RG1 3JH which are members of the SSE Group
www.ssen.co.uk