ssen003 nests - stage gate - decision to proceed v1

20
SHE Transmission New Suite of Transmission Structures: NeSTS (SSEN003) Stage Gate – Decision to Proceed  September 2018  

Upload: others

Post on 18-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

SHE Transmission New Suite of Transmission Structures: NeSTS (SSEN003) 

Stage Gate – Decision to Proceed 

 

September 2018 

 

Page 2: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

 

Contents and Overview  

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 2 of 20 

Contents 

Overview of NeSTS .................................................... 2 

Executive Summary ................................................... 3 

NeSTS Stage 1 Progress ............................................. 4 

Stage Gate Inputs ...................................................... 6 

Stage Gate Outputs:  

Refreshed NIC Business Case ........................................ 10 

Refreshed NIC Business Case Supporting Information . 15 

Decision to Proceed ................................................. 18 

 

Appendices 

1. SSEN003 NeSTS: Design Selection (SDRC 11.1) 

2. SSEN003 NeSTS: Outputs of Stakeholder Engagement (SDRC 11.2) 

3. SSEN003 NeSTS: Creation of Technical Specifications (SDRC 11.3) 

4. Main Contractor’s Design Endorsement Report 

5. Main Contractor’s Cost Comparison Report 

6. TNEI Refresh of Overhead Line Volumes 

 

Note: Appendices 4 & 5 are considered confidential. 

 

 

 

 

 

 

 

 

 

 

 

 

Overview of NeSTS 

Scottish Hydro Electric Transmission plc (SHE Transmission) is developing a New Suite of Transmission Structures (NeSTS), which are planned to be deployed on the Transmission Network  

Overhead lines (OHLs) built using transmission structures are the most visible element of the transmission network, and the impact OHLs have on the environment can cause stakeholders concern.  

The only available alternative to the steel lattice structures traditionally used in OHL construction is the T‐Pylon. Developed by National Grid Electricity Transmission (NGET), the T‐Pylon reduces the visual impact of OHLs but may be unsuited to areas with challenging terrain and propensity for severe weather events.  

Establishing new infrastructure in these areas is essential to connect renewable generation, so there is a need for a new type of structure to address stakeholder concern. 

The NeSTS project will develop innovative designs for OHL structures based on new technologies and techniques. The new suite of structures will then be deployed on the transmission network.   

The NeSTS Project seeks to prove the following benefits:  

o Improved OHL environmental performance by lowering visual and construction impacts; and 

o Lower OHL whole life asset costs via reduced land, construction, maintenance and outage requirements. 

Page 3: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Executive Summary 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 3 of 20 

The Project has designed a new suite of transmission structures in response to stakeholder inputs. 

Stakeholders support the project and have assessed that the new supports could reduce the environmental impact of overhead lines. 

The NeSTS designs have been endorsed by a main construction contractor and have been used to design an overhead line in parallel with a traditional lattice design. 

The main contractor estimates that the costs of construction using NeSTS are comparable to those using lattice steel, and there is potential for cost saving in operation of the OHL assets. 

A refreshed analysis of future OHL requirements has indicated that there is still substantial need for new OHLs which could benefit from lower environmental impact enabled by NeSTS. 

The Project is making good progress towards its aims and objectives on paper, and SHE Transmission has approved its progress to Phase 2. 

This report summarises the Project’s Phase 1 design progress and the evidence SHE Transmission have used to make this decision.  It is submitted to seek approval of the decision by Ofgem, as instructed in the Project Direction. 

 

Figure 1: NeSTS 132kV Medium Duty Double Circuit D2 

Support

Page 4: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

NeSTS Stage 1 Progress 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 4 of 20 

The Project initially targeted its design focus at 275kV 

OHLs, and selected its design concept based on this 

insulation level. 

During the subsequent development of a design 

prototype, the business case for the OHL being used for 

the NeSTS parallel design was reviewed in response to 

changing background generation.  

The OHL was re‐specified to be insulated at 132kV, and 

the NeSTS prototype and parallel design processes were 

re‐focussed to produce corresponding 132kV designs. 

The translation of form, fit and function from 275kV to 

132kV has been successfully implemented, and the 

comparative environmental benefits retained. 

Comparative visualisation of the NeSTS 275kV Medium 

Duty design and a L8RD lattice equivalent are shown in 

Figure 2. 

Comparative visualisation of the NeSTS 132kV Medium 

Duty Double Circuit design and a L7c lattice equivalent are 

shown in Figure 3. 

 

 

 

 

 

Figure 2: Visualisation of NeSTS 275kV Medium Duty and L8RD Benchmark in Upland Moorland 

Page 5: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

NeSTS Stage 1 Progress  

© Scottish and Southern Electricity Networks                  SSEN03 NeSTS Design Selection Rev 1.0  

Uncontrolled if Printed                  Page 5 of 20 

 

 

Figure 3: Visualisation of NeSTS 132kV Medium Duty Double Circuit and L7c Benchmark in Upland Moorland 

The parallel design process used to inform this Stage Gate is based on the NeSTS 132kV Medium Duty Double Circuit suite. 

However, due to better fitting the Project’s programme, the current intention is to construct a 132kV single circuit NeSTS OHL in Phase 2 of the project, and this design is currently being developed. 

The Project plans to complete the technical specification of the 275 and 132kV medium duty double circuit suites, as reported in Appendix 3: SSEN003 NeSTS: Creation of Technical Specifications. 

 

Page 6: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Inputs 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 6 of 20 

Stakeholder Support 

The Project has engaged with many different stakeholders, and the outputs of these engagements are driving the NeSTS design.  

Work with statutory and non‐statutory consultees to understand their concerns regarding the environmental impact of OHLs has been undertaken. This has included detailed explanation of the OHL design process and the practical constraints involved. 

Consultee assessment was used to select the NeSTS design concept and customers have been polled to confirm that their opinion aligns with that expressed by their consultee representatives. 

The assessment and selection process is reported in Appendix 1: SSEN003 NeSTS: Design Selection. 

 

Design Response to Stakeholder Input 

The engagement with consultees provided several inputs 

to the subsequent design refinement process.  

 

International Transmission Owners (TOs) and their supply 

chain have been engaged to understand lessons learned 

from steel monopole OHL projects, and thus embody the 

best available technology into the NeSTS designs. 

These outputs of stakeholder engagement are reported in 

Appendix 2: SSEN003 NeSTS: Outputs of Stakeholder 

Engagement. 

A chart summarising consultee stakeholder assessment of 

NeSTS improved visual impact performance compared to 

lattice steel designs is shown in Figure 4. A neutral 

response is translated into a 3, a very good response into 

a 5, and a very poor response into a 1. The thin lines 

superimposed on the chart bars indicate the range of 

responses.  

The chart shows that consultee stakeholders anticipate a 

substantial reduction in the visual impact of OHLs 

constructed using NeSTS supports in comparison to lattice 

steel alternatives, and that their assessments of NeSTS 

are more convergent than their assessments of lattice 

steel. 

 

 

Figure 4: Consultee Stakeholder Visual Impact Assessment Summary

Page 7: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Inputs 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 7 of 20 

Design Endorsement and Publication 

NeSTS designs are intended for use across Great Britain’s (GBs) network, and licensees have been engaged to understand lessons learned from previous projects, explain the Project objectives and designs, and share its learning. 

The designs have been subjected to scrutiny by structure manufacturers and main construction contractors as part of the process of developing technical specifications. 

A design endorsement report for the NeSTS 132kV Medium Duty Double Circuit suite from a main construction contractor is shown in Appendix 4: Main Contractor’s Design Endorsement Report. 

 

The Project has an agreement in principle that the NeSTS 

technical specifications will be published by the ENA as 

part of the 43 series of OHL technical specifications, 

subject to their review by the ENA OHL panel.  

These publication plans are detailed in Appendix 3: 

SSEN003 NeSTS: Creation of Technical Specifications. 

 

 

 

 

 

Figure 5: Visualisation of a NeSTS 132kV Double Circuit Medium Duty versus a L7c Overhead line 

 

 

Page 8: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Inputs 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 8 of 20 

Cost Comparison from Parallel Design 

Parallel designs for an overhead line have been 

compared: one using the NeSTS 132kV double circuit 

medium duty suite of structures, and the other using the 

traditional L7c lattice steel suite. 

Visualisations of each design are shown on the Project’s 

website, and excerpted images are shown in Figure 5. 

A main construction contractor has estimated the costs of 

each design. Their analysis is presented in Appendix 5: 

Main Contractor’s Cost Comparison Report, and a 

summary infographic of it is shown in Figure 6. 

 

It shows that the estimated costs of each option are 

comparable.  

An increase in structure procurement and delivery costs is 

almost balanced by a reduction in installation and 

foundation costs, leaving a 1.7% higher estimate for 

construction using NeSTS. 

 

 

 

Figure 6: Summary Infographic of NeSTS Parallel OHL Cost Comparison 

Page 9: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Inputs 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 9 of 20 

Refresh of Future OHL Requirements 

The Project commissioned TNEI to refresh the overhead 

line volumes in the market assessment report presented 

in the NeSTS NIC full bid submission. The result is shown 

in Appendix 6: TNEI Refresh of Overhead Line Volumes. 

It reports that following the changes to renewable energy 

policy in 2015 and changes in NGET’s Electricity Ten Year 

Statements (ETYS), on average, 121km of new OHL are 

forecast to be required annually through to 2026. This 

compares to the forecast average requirement for 250km 

annually which was referenced in the NeSTS NIC bid 

submission in 2015. 

Using this and NGET’s Future Energy Scenarios (FES), the 

total forecast OHL demand by 2050 in Scotland in each of 

the FES is shown in Table 1. 

 

 

 

 

 

 

 

 

Future Energy Scenario Total OHL Demand by 2050 in Scotland (km) 

Community Renewables 4,528

Consumer Evolution  4,349 

Two Degrees  4,466 

Steady Progression  4,320 

Table 1: Total Need for OHL in Scotland by 2050 in Each Future Energy Scenario 

 

Page 10: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 10 of 20 

Introduction 

SHE Transmission, NGET and Scottish Power Transmission 

(SPT) share statutory duties as transmission licensees: to 

ensure the development and maintenance of an efficient, 

coordinated and economical system of electricity 

transmission; to facilitate competition in the supply and 

generation of electricity; and to have due regard for 

preservation of amenity.  The drive toward a low carbon 

electricity sector, and in particular, the growth in new 

renewable generation in remote areas, requires an 

increase in network capacity through the creation of new 

infrastructure.  The cost of new infrastructure will be 

factored into GB electricity consumers’ bills. 

TNEI analysis, based upon information contained in 

NGET’s Electricity Ten Year Statement, shows that on 

average, up to 121km new OHL projects are planned each 

year on the GB transmission network until 2026 (see 

Appendix 6 for further details). Increasing volumes of 

renewable generation combined with the anticipated 

increase in future electrical demand require significant 

investment to provide the necessary network capacity.  

SHE Transmission is investing to upgrade and reinforce 

the network, with a £3bn ‐ £5bn investment programme 

in progress.  The other TOs have similar investment plans 

during this period. 

Deriving the business case 

This section describes the approach used to ensure the 

NeSTS business case is robust and how results from the 

project are designed to be statistically sound.   

SHE Transmission, with support from TNEI, has used 

several sources of data to calculate the project’s business 

case.  These include (i) National Grid’s Electricity Ten Year 

Statement (ETYS) (ii) National Grid’s Future Energy 

Scenarios 2017 (FES) and (iii) NGET’s Transmission Entry 

Capacity(TEC) Register, supplemented by additional 

information from SHE Transmission and Project 

stakeholders. 

Future OHL Build Requirements 

The ETYS was analysed to identify the projected volumes 

of additional OHL required by each of the TOs during the 

2017‐2026 period. This new infrastructure is largely 

driven by the growth in new renewable generation and 

increased electricity demand. This analysis is described in 

more detail in TNEI’s report, contained in Appendix 6.  

 

Beyond 2026, the FES have been used as a basis for 

assessing the need for new infrastructure in the longer 

term. The FES models a range of scenarios for the 

development of the GB transmission system, which have 

been used for TNEI’s analysis.  

The TEC Register holds details of generation projects 

seeking to connect to the transmission network, at 

various stages of scoping, consenting and construction.  

The TEC Register was also considered as part of TNEI’s 

analysis.  Overall, the analysis contained in Appendix 6 

suggests that on average 121km of new infrastructure will 

be required each year.   

Page 11: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 11 of 20 

Calculating financial benefits 

In the FES, four scenarios are considered; Steady 

Progression, Two Degrees; Consumer Evolution and; 

Community Renewables.  In order to avoid overstating 

the business case for NeSTS, SHE Transmission and TNEI 

have used a cautious approach to quantify benefits.  

Therefore we have opted to consider only the Steady 

Progression and the Two Degrees scenarios to assess the 

potential financial benefits. 

The new designs are applicable to 132kV, 275kV and 

400kV and learning will be made available to all GB 

network licensees. However, it is recognised that NeSTS 

will not be applicable for every new OHL project. 

Therefore, TNEI’s analysis of new infrastructure plans to 

2050 is based on the following assumptions: 

1. Most new infrastructure at 132kV will take place 

in Scotland.  A review of the RIIO: ED1 business 

plans for English and Welsh distribution network 

operators did not indicate a significant volume of 

new 132kV OHL build. For this reason, the 

business case has discounted 132kV in England 

and Wales. 

2. NGET are likely to use the T‐Pylon for new 400kV 

OHL projects, as it has been specifically designed 

for application in the NGET territory.  400kV 

projects in England and Wales have therefore 

also been excluded from the business case. 

3. Analysis of the TEC register suggests that there 

are a limited number of renewable projects 

which will require new build OHL infrastructure 

to connect to the network.  Therefore, these 

have also been excluded from the analysis. 

Full details of the methodology, assumptions and results 

are contained in Appendix 6. 

 

 

 

 

Page 12: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 12 of 20 

NeSTS Financial Benefits 

NeSTS construction costs for the trial OHL are forecast to 

be comparable to those of building an equivalent lattice 

steel OHL.  

SHE Transmission considers this a reasonable basis for 

constructing a NeSTS OHL to allow the assessment of 

actual and potential costs. 

The Project is targeting cost savings in several elements of 

OHL construction, as detailed in the NeSTS NIC bid 

submission. Updates on the learning related to these 

elements and the main contractor’s cost comparison 

follow in Appendix 5: Main Contractor’s Cost Comparison 

Report: 

Foundations: The benefits in moving to a monopole style 

construction that is less invasive and generally simpler are 

supported by stakeholder feedback and the main 

contractor’s cost comparison, although the scale of the 

cost benefit will vary with ground conditions.  

The Project has designed caisson foundations, and 

discussed their construction with the GB and international 

supply chain, but is unable to use them on the rocky 

ground which has been encountered on the OHL design 

work so far.  

The potential benefits of this type of foundation will be 

reported in Phase 2. 

Installation: The forecast benefits of shorter and less 

complex construction are supported by the main 

contractor’s cost comparison and stakeholder feedback. 

This element has not yet been exposed to competitive 

tendering, and, TOs in the USA report that construction 

contractor costs for steel monopole OHL construction 

have decreased with experience and innovation of 

installation processes in their territory.  

The Project plans to explore and report on the potential 

of related benefits in Phase 2. 

Structure Costs: The cost parity to lattice steel structures 

foreseen is not supported by the main contractor’s cost 

comparison or supply chain feedback. The increased steel 

weight required and the inclusion of tertiary coating in 

the factory mean that unassembled structure costs will be 

higher than for lattice steel supports.  

 

However, this element has not yet been exposed to 

competitive tendering, and, a competitive market for the 

supply of steel monopoles exists globally.  

The Project plans to explore and report on the potential 

of related benefits in Phase 2. 

Conductor Systems: The twin earth wire costs reported in 

the NIC submission have not been realised as the design 

chosen only requires a single earth wire. The conductor 

system costs will therefore be the same as those of an 

equivalent lattice steel design. 

Off‐site Manufacture: The reduced number of 

components and reduced assembly requirements are 

supported by the main contractor’s estimate of 

preliminary cost and stakeholder feedback. 

Operating Costs: Ownership cost benefits may exist in the 

form of lower land and maintenance costs. NeSTS 

footprints are c75% lower than the lattice equivalent, and 

consequently wayleave costs are expected to be lower. 

The NeSTS supports facilitate easier inspection and 

factory applied paint systems are expected to offer longer 

intervals between re‐painting.  

These benefits will be estimated in Phase 2 of the Project. 

Project Management and Consenting Costs: The reduced 

project duration implied by the reduced installations and 

preliminary costs are expected to result in lower TO 

project management costs. Similarly, if stakeholder and 

customer support results in faster consenting, TO 

consenting costs may be reduced. 

The potential for these benefits will be estimated in Phase 

2 of the Project. 

Following Phase 1 of the Project, SHE Transmission 

continues to anticipate that these elements could 

generate considerable savings if a successful trial leads to 

GB‐wide deployment.  

Based on updated information from the supply chain 

engagement, SHE Transmission continues to estimate that 

the cost of new OHL projects could be reduced by up to 

10% over a whole asset life, where projects could realise 

all the available benefits. 

Page 13: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 13 of 20 

 

The information contained in Appendix 6 indicates that 

the majority of the OHL work planned by the TOs is for 

reinforcement or refurbishment projects.  The financial 

benefits for TO reinforcement and refurbishment projects 

flow directly to transmission customers through 

Transmission Use of System charges. 

 

 

SHE Transmission has adopted a conservative view that 

NeSTS will be suitable for up to 15% of the anticipated 

projects and has calculated cost savings on this basis. 

Should NeSTS be applied to up to 15% of new OHL 

projects between 2023 and 2050 and achieves a 

reduction in costs of 10%, this could facilitate savings of 

up to £68.9 million, as shown in Table 2: Potential NeSTS 

Benefits. 

 

 

Number of projects 2023 to 2050  Two Degrees Steady Progression

Benefit at 5% cost saving (£m) if 5 % of OHL projects are NeSTS‐compatible 

£11.5M £11.2M

Benefit at 10% cost saving (£m) if 15% of OHL projects are NeSTS‐compatible 

£68.9M £67.1M

Table 2: Potential NeSTS Benefits 

 

Page 14: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 14 of 20 

Accelerates Low Carbon Sector 

New transmission infrastructure is driven by the TOs’ 

requirement to respond to increasing renewable energy 

generation connections.  

By offering a new lower impact option for OHL 

construction, NeSTS should enable improved stakeholder 

and consultee response to some OHL developments, 

thereby speeding up the consenting and connection 

processes. 

This combined with reduced construction time will 

accelerate some renewable energy connections, and 

hence the low carbon sector. 

 

 

Innovation with a Purpose 

NeSTS will enable GB TOs to offer alternative options to 

customers where some lattice steel overhead lines or 

underground cables are impractical. 

The lower requirements for operative hours at site, both 

during construction and for planned maintenance, aligns 

with SHE Transmission’s health and safety policy by 

reducing staff and contractor exposure to hazards, and its 

strategy to focus on safe and efficient operations of 

assets. 

 

 

 

 

 

 

 

 

Relevance and Timing 

The Project aligns with SHE Transmission’s strategy to put 

the needs of current and future customers at the heart of 

everything it does, and to use resources sustainably. 

NeSTS is suited to SHE Transmission’s portfolio of 

renewable generation connection projects in challenging 

and sensitive environments. 

The Project is on schedule to deliver its learning by 31 

March 2022 as defined in the Project Direction. 

 

Page 15: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case Supporting Information 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 15 of 20 

OHL Line Costs using Traditional Designs 

To assess the cost benefit of the proposed solution it is 

first necessary to understand the cost of traditional OHL 

projects.  There can be significant cost variance 

depending on specific project requirements. However, the 

benefits have been assessed using information available 

in the TO Charging Statements.  Note that NGET costs 

were not available for this analysis. To enable comparison 

with the original business case in the NIC submission, 

these values have not been updated in this refresh. 

 

 

 

 

 

 

Base Case Costs per OHL Voltage in £000s/km 

TO  275kV    132kV  

SPT   £1,833    £834  

SHE Transmission   £1,103    £793  

Average Cost    £1,468   £814 

Table 3: Base Case Costs per OHL Voltage 

 

 

   

Page 16: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case Supporting Information 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 16 of 20 

OHL Costs using NeSTS 

Using NeSTS instead of traditional lattice steel supports 

has the potential to reduce the cost of OHL projects in the 

following areas: 

Foundations: The estimated foundation costs for the 

NeSTS OHL line in the parallel design reported in 

Appendix 5 are 3.6% less expensive than those for the L7c 

lattice steel OHL line. 

This comparison is based on ground conditions which do 

not allow use of the caisson style of foundation detailed 

in the NIC submission, which is favoured by owners of 

steel monopole transmission lines. Consequently, the full 

benefits available could not be realised on this OHL 

project.  

The Project has designed caisson foundations, similar to 

those referenced in the NIC submission, whose costs will 

be estimated and reported in Phase 2. 

Installation: The estimated installation costs for the 

NeSTS structures are 49.4% lower than those for L7c in 

the main contractors cost comparison. The Project 

anticipates that experience and innovation of installation 

processes, and competition for supply of these services in 

GB could deliver further benefits.  

Structure Costs: The estimated costs of NeSTS structures 

are 130% more expensive than L7c supports in the main 

contractor’s cost comparison. Delivery costs are 182% 

higher, as there is no GB manufacturing capability for this 

scale of folded steel monopole. 

The Project has engaged with several suppliers of steel 

monopoles but has yet to expose NeSTS designs to 

competition for their supply to an OHL project.  

A competitive market for the supply of steel monopoles 

exists globally and the Project anticipates that this cost 

differential would be substantially reduced by a GB‐wide 

deployment, possibly involving the evolution of a GB 

manufacturing capability.  

Off‐site Manufacture: The estimated preliminary costs for 

supply of a NeSTS OHL are 9.9% lower than for the L7c 

equivalent in the main contractor’s cost comparison. The 

Project anticipates that experience and innovation of 

steel monopole line project and construction  

 

management, and competition for supply of these 

services in GB could deliver further benefits. 

Reduced Operating Costs: Ownership cost benefits may 

exist in the form of lower land and maintenance costs.  

NeSTS supports have been designed to facilitate lower 

maintenance costs. The reduced complexity of the 

structures should enable faster and higher quality 

inspections, both by climbing operatives and by drone 

mounted cameras.  

The factory applied paint system should enable less 

frequent repainting and therefore lower refurbishment 

costs. These attributes should enable reduced 

maintenance outage requirements.  

Wayleaves have not been agreed for the NeSTS designs, 

and therefore this benefit cannot be reported yet. It is 

anticipated that the footprint related component of these 

costs will fall in proportion to the c75% reduction in as‐

built footprint. 

 

 

In anticipating the future volumes of OHL required, it has 

been presumed that the majority of OHL required by 

NGET in England and Wales will use the T‐Pylon design; 

therefore, they have been excluded from the calculations.  

Similarly, it has been assumed that 400kV works in 

Scotland will be delivered using recent designs such as the 

SSE400 used for the Beauly‐Denny line. 

In order to ensure a conservative, sensible view of 

potential benefits, SHE Transmission postulated that a 

traditional steel lattice or T‐Pylon may be used for new 

OHL deployment at 132kV and 275kV – to this end, we 

have assumed that only between 5% and 15% of future 

new build OHL will be suitable for NeSTS.  

SHE Transmission has focussed on the two most prudent 

scenarios in the FES to estimate benefits. Note that all of 

the benefits arising from cost reductions in infrastructure 

projects will flow directly to transmission customers 

through TNUoS   

Page 17: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Stage Gate Outputs: 

Refreshed NIC Business Case Supporting Information 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 17 of 20 

NeSTS continues to represent good value for customers 

with only relatively modest volumes of OHL requiring to 

be built in order to recover the Project’s costs. Based on 

the costs identified in the TOs Charging Statements 

referenced in the NIC submission, the volume of new 

275kV or 132kV OHL required to recover the Project costs 

is shown below in Table 4.

 

 

 

 

 

 

 

 

 

Table 4: Minimum OHL Distance to Recover NIC Cost 

 

 

 

 

 

 

 

Average Cost  

£000s/km 

10% Cost Reduction  Minimum distance 

to recover NIC cost 

275kV OHL  £1,468  £146k  45km 

132kV OHL  £813  £81k  82km 

Page 18: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

Decision to Proceed 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 18 of 20 

The SHE Transmission Steering group has considered the 

evidence detailed in this report and has concluded that 

the Project is making good progress towards its aims and 

objectives. 

Stakeholders support the project and have assessed that 

the new supports could reduce the environmental impact 

of overhead lines. 

The NeSTS designs have been endorsed by a main 

construction contractor and have been used to design an 

overhead line in parallel with a traditional lattice design. 

The main contractor estimates that the costs of 

construction using NeSTS are comparable to those using 

lattice steel, and there is potential for further cost saving 

in a deployment to business as usual if the trial is 

successful. 

A refreshed analysis of future OHL requirements has 

indicated that there is a substantial need for new OHLs 

which could benefit from lower environmental impact 

enabled by NeSTS. 

SHE Transmission has therefore decided that the Project 

should proceed to Phase 2 including the construction of a 

trial OHL, and seeks Ofgem approval in response to this 

submission as instructed in the Project Direction.

Page 19: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

This page is intentionally blank. 

© Scottish and Southern Electricity Networks                SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 

Uncontrolled if Printed                 Page 19 of 20 

Page 20: SSEN003 NeSTS - Stage Gate - Decision to Proceed v1

 

 

 

SSEN003 NeSTS: Stage Gate – Decision to Proceed Rev 1.0 – September 2018  

Scottish and Southern Electricity Networks is a trading name of: Scottish and Southern Energy Power Distribution Limited Registered in Scotland No. SC213459; 

Scottish Hydro Electric Transmission plc Registered in Scotland No. SC213461; Scottish Hydro Electric Power Distribution plc Registered in Scotland No. 

SC213460; (all having their Registered Offices at Inveralmond House 200 Dunkeld Road Perth PH1 3AQ); and Southern Electric Power Distribution plc Registered 

in England & Wales No. 04094290 having its Registered Office at No.1 Forbury Place, 43 Forbury Road, Reading, RG1 3JH which are members of the SSE Group  

www.ssen.co.uk