spending plans and schedule jae yu july 26, 2002

10
Spending Plans and Schedule Jae Yu July 26, 2002

Upload: tamsin-french

Post on 03-Jan-2016

221 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: Spending Plans and Schedule Jae Yu July 26, 2002

Spending Plans and Schedule

Jae YuJuly 26, 2002

Page 2: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 2

Introduction• We (UTA) were successful in persuading DØ

collaboration to adopt DØ Regional Analysis Center scheme– A proposal completed – Collaboration had a chance to look at it– World-wide finance committee has well accepted the scheme

and enthusiastic about the proposal• Significant amount computing research necessary to

implement and employ Grid into DØ• The MRI gave a significant head-start toward UTA

becoming an ATLAS Tier II site– Will generate even more significant research for full scale

ATLAS Grid implementation

Page 3: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 3

MRI2002- Year 1 Spending Plan

Items Budget Equipments Capacity

RAID Array $124,375 24 192 drives

IDE Disks $37,201 153 24.5TB

Disk servers $19,600 4

GB Switches $14,800 4 40 GB ports

Rack Encl. $9,720 4

Proc. PCs $98,500 40 91.2GHz

Page 4: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 4

What do we construct in the year 1?

Storage Racks

Disk/file Server

Disk/file Server

Disk/file Server Disk/file Server

Gbit switch Gbit switchGbit switch

RAID Arrays+IDE Disks

RAID Arrays+IDE Disks

RAID Arrays+IDE Disks

RAID Arrays+IDE Disks

RAID Arrays+IDE Disks

RAID Arrays+IDE Disks

Gbit switch

Processing PCs

ProcessingPC Rack

Total Storage Space:> 24.5TBTotal Processing CPU power: 91.2GHz

Page 5: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 5

Implementation Schedule & Plan-Yr. 1

• Sept. 15, 2002: Purchase10% of the equipment• Sept. 15 – Oct. 31

– System Installation & Burn-in– Software (both DØ and Grid) installation

• Install DØ Reconstruction and Analysis software• Install UTA-DØ MC production software

– Establish Data transfer from FNAL– Execute Analysis programs and begin MC production

Page 6: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 6

• Oct. 31, 2002: Complete purchasing the Remainder• Oct. 31 – Dec. 31, 2002:

– System Installation and Burn-in– Software (both DØ and Grid) installation– Constant transfer and fill disks with DØ Data– Establish and implement Grid enabled batch control system– Establish user pool to become a DØRAC– Start DØ Reconstruction

• Jan. 2003: DØRAC workshop

Yr. 1 Implementation-cont’d

Page 7: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 7

Necessary Venders

• Fiber channel IDE RAID array venders• IDE DISK venders • Processing farm PC and disk/file server venders• Gbit switch venders• RACK enclosure venders

Page 8: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 8

Where do we want to be in the year 2005?

• A proposal to the DØ collaboration has been written and submitted to establish DØ Regional Analysis Centers

• We want to become a DØ RAC w/ the following minimum capacity– Disk Storage Capacity: >110TB (Need additional 85.5TB)– Total Processing CPU power: >400 GHz (Need additional

310GHz)– Network: Minimum 1GBit/sec outside connection– Person power: 2 system support (Need one more)– Tape storage: >70TB (Don’t have this yet)

• Ultimately become an ATLAS Tier II site, building upon this infrastructure

Page 9: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 9

MRI2002- Year 2 Spending Plan

Items Budget Equipments Capacity

RAID Array $99,500 19 152 Drives

IDE Disks $37,201 153 24.5TB

Disk servers $4,900 1

GB Switches $22,200 5 50 GB ports

Rack Encl. $14,580 6

Proc. PCs $98,500 40 91.2GHz

Page 10: Spending Plans and Schedule Jae Yu July 26, 2002

July 26, 2002 Jae Yu: MRI 2002 Meeting 10

MRI2002- Year 3 Spending Plan

Items Budget Equipments Capacity

RAID Array $99,500 19 152 Drives

IDE Disks $32,333 133 21.3TB

Disk servers $9,800 2

GB Switches $11,100 3 30 GB ports

Rack Encl. $7,290 3

Proc. PCs $87,900 35 79.8GHz