July 26, 2002 Jae Yu: MRI 2002 Meeting 2
Introduction• We (UTA) were successful in persuading DØ
collaboration to adopt DØ Regional Analysis Center scheme– A proposal completed – Collaboration had a chance to look at it– World-wide finance committee has well accepted the scheme
and enthusiastic about the proposal• Significant amount computing research necessary to
implement and employ Grid into DØ• The MRI gave a significant head-start toward UTA
becoming an ATLAS Tier II site– Will generate even more significant research for full scale
ATLAS Grid implementation
July 26, 2002 Jae Yu: MRI 2002 Meeting 3
MRI2002- Year 1 Spending Plan
Items Budget Equipments Capacity
RAID Array $124,375 24 192 drives
IDE Disks $37,201 153 24.5TB
Disk servers $19,600 4
GB Switches $14,800 4 40 GB ports
Rack Encl. $9,720 4
Proc. PCs $98,500 40 91.2GHz
July 26, 2002 Jae Yu: MRI 2002 Meeting 4
What do we construct in the year 1?
Storage Racks
Disk/file Server
Disk/file Server
Disk/file Server Disk/file Server
Gbit switch Gbit switchGbit switch
RAID Arrays+IDE Disks
RAID Arrays+IDE Disks
RAID Arrays+IDE Disks
RAID Arrays+IDE Disks
RAID Arrays+IDE Disks
RAID Arrays+IDE Disks
Gbit switch
Processing PCs
ProcessingPC Rack
Total Storage Space:> 24.5TBTotal Processing CPU power: 91.2GHz
July 26, 2002 Jae Yu: MRI 2002 Meeting 5
Implementation Schedule & Plan-Yr. 1
• Sept. 15, 2002: Purchase10% of the equipment• Sept. 15 – Oct. 31
– System Installation & Burn-in– Software (both DØ and Grid) installation
• Install DØ Reconstruction and Analysis software• Install UTA-DØ MC production software
– Establish Data transfer from FNAL– Execute Analysis programs and begin MC production
July 26, 2002 Jae Yu: MRI 2002 Meeting 6
• Oct. 31, 2002: Complete purchasing the Remainder• Oct. 31 – Dec. 31, 2002:
– System Installation and Burn-in– Software (both DØ and Grid) installation– Constant transfer and fill disks with DØ Data– Establish and implement Grid enabled batch control system– Establish user pool to become a DØRAC– Start DØ Reconstruction
• Jan. 2003: DØRAC workshop
Yr. 1 Implementation-cont’d
July 26, 2002 Jae Yu: MRI 2002 Meeting 7
Necessary Venders
• Fiber channel IDE RAID array venders• IDE DISK venders • Processing farm PC and disk/file server venders• Gbit switch venders• RACK enclosure venders
July 26, 2002 Jae Yu: MRI 2002 Meeting 8
Where do we want to be in the year 2005?
• A proposal to the DØ collaboration has been written and submitted to establish DØ Regional Analysis Centers
• We want to become a DØ RAC w/ the following minimum capacity– Disk Storage Capacity: >110TB (Need additional 85.5TB)– Total Processing CPU power: >400 GHz (Need additional
310GHz)– Network: Minimum 1GBit/sec outside connection– Person power: 2 system support (Need one more)– Tape storage: >70TB (Don’t have this yet)
• Ultimately become an ATLAS Tier II site, building upon this infrastructure
July 26, 2002 Jae Yu: MRI 2002 Meeting 9
MRI2002- Year 2 Spending Plan
Items Budget Equipments Capacity
RAID Array $99,500 19 152 Drives
IDE Disks $37,201 153 24.5TB
Disk servers $4,900 1
GB Switches $22,200 5 50 GB ports
Rack Encl. $14,580 6
Proc. PCs $98,500 40 91.2GHz
July 26, 2002 Jae Yu: MRI 2002 Meeting 10
MRI2002- Year 3 Spending Plan
Items Budget Equipments Capacity
RAID Array $99,500 19 152 Drives
IDE Disks $32,333 133 21.3TB
Disk servers $9,800 2
GB Switches $11,100 3 30 GB ports
Rack Encl. $7,290 3
Proc. PCs $87,900 35 79.8GHz