spectra halfday pdf
TRANSCRIPT
NILEX Inc.
Materials and Construction
for Earth and Water
Roads (Paved & Unpaved) Woven & Nonwoven Geotextiles; Geogrids; Paving Membranes &
Reinforcements.
MSE Systems (Mechanically Stabilized Earth Retaining Walls & Slopes) Precast Concrete Panels; Modular Concrete Blocks;
Steepened Slopes – vegetated & rock-faced.
Erosion & Sediment Control Erosion Blankets; Silt Fence; Geo-Ridge; Articulated Concrete,
Cellular & Gabion Revetments.
Drainage Strip Drains; Sheet, Wall & Deck Drains; Multi-Flow; Weeping Tile.
Containment Geomembranes & Geosynthetic Clay Liners (GCLs).
Ground Modification Wick Drains & Earthquake Drain Installation.
Nilex Applications:
Office Locations:
Edmonton-Head Office
Calgary
Burnaby
Vernon
Grand Prairie
Saskatoon
Winnipeg
GEOSYNTHETIC FUNCTIONS
• Separation
• Filtration
• Drainage
• Subgrade
Improvement
• Granular Base
Reinforcement
Non-Woven Geotextiles
• Needlepunched
• Spunbonded
SEPARATION FUNCTION
Without Geosynthetic With Geosynthetic
Separation Function
• For subgrade CBR’s <3, benefit roughly
equal to 150 mm of base gravel that would
otherwise be contaminated
FILTRATION
FILTRATION
APPLICATION
GEOSYNTHETICS
PRODUCT TYPE
FUNCTION NON-WOVEN
FABRIC
WOVEN
FABRIC
GEOGRID
BASE REINFORCEMENT
SUBGRADE IMPROVEMENT
SEPARATION
FILTRATION
DRAINAGE
Fabric
IN-PLANE DRAINAGE
Reinforcement Functions
• Subgrade Improvement
– Tension membrane - high deformation
– Geogrids & Geotextiles
• Granular Base Reinforcement
– Lateral interlock - low deformation
– Geogrids only
Subgrade
Improvement
for
Pavement Systems
Subgrade Improvement
Base Reinforcement
Base vs. Subgrade
A Geogrid System Changes The
Dynamics of Load Interaction With the
Subgrade
Granular Base Reinforcement
Lateral Interlock
Confinement
Subgrade Improvement
Local Success Stories
Alaska Highway / Ft. Nelson / Nov.6, 2003
An Everyday Problem
The Solution Step 1 - Place Geogrid Over Subgrade
The Solution Step 2 - Place Fill Over Geogrid
Field Test - Gravel Road Construction
Over Very Soft Soils
Performed By:
Steve L. Webster - U.S. Army Corps of
Engineers
January 1996
Typical Northern Application
Subgrade Improvement
Geogrid Installation
18”
Lift
Alaska Hwy/Clarke Bypass Ft Nelson
Problem - to reduce section and save material costs.
Solution - BX 1200 - 100 mm savings over 47,000 m2 = $170,000 saved
plus TBR of 5.0 for lower lifecycle costs
Cold Weather Application Clarke
Bypass/ SYD’s Road / Ft. Nelson
Clarke Bypass - end dump on
existing fill and push forward
Syd’s Intersection/ snap ties
Syd’s Road
Princess Ave./ Ft. St. John
Original Design Structure 50mm AC, 150mm of 19mm base, 300 mm of 40 mm base
Princess Ave - Original design includes perforated perimeter subdrain c/w drain rock
and Amoco 4551 Geotextile on subgrade compacted to 95%
The Problem - Due to poor subgrade conditions of saturated silty clays the subase
needed to be increased by 400 mm but unable do to so due to N.G. lines.
Princess Ave - The Solution - BX 1100 and Amoco 4551 saving sub- exc. of 300 mm
with associated costs and time on uncompacted subgrade
Princess Ave./ Ft. St. John
Princess Ave / Urban Systems/
Amec/ DGS/ City crews
Dawson Creek Walmart - Problem - reduce section and create uniform bearing for
parking lot 25,000 m2 BX 1200
Dawson Creek Walmart - Solution
BX1200 - reduce base course thickness by 150 mm and
25 mm reduction in base course - savings = $ 105,600.00
(net savings = cost of geogrid - cost of gravel savings)
Additional Success Stories
Annually - City of Dawson Creek - various roads
Annually - City of Ft. St. John - virtually all total reconstruct
roads
2002 - Presporto Road - 2800 m2, BX 1100
2003 - Pouce Coupe Sideroad 35,000 m2 of BX1100 and
geotextile
Annually - DGS Contractors - ongoing basis for public and
private projects
2002 - Beaton River/Dawson const. - 263,000 m2 Amoco 4551
Geotextile
MOT - on going basis
Design
Example
Confinement
1992 Corps of Engineers
Several Grids Tested
1992 Corps of Engineers
Several Grids Tested Control Section
No Geogrid
Severe Rutting
Tensar Section
BX1200 Geogrid
Rutting Controlled
Both Sections
2” of ACP
6” of Base
Subgrade CBR=3
2,016 Passes
1992 Corps of Engineers Results
0.9 0.9 11.6
3.4
4.7
0
1
2
3
4
5
TBR
Grid A Grid B Control Grid D Grid E Grid F
Traffic Benefit Ratio (TBR)
= Ratio of reinforced/unreinforced traffic repetitions
2” Asphalt Concrete
14” Aggregate Base
Subgrade CBR = 3
Rut Criteria = 1”