specificity of decontamination and remediation · pdf filespecificity of decontamination and...
TRANSCRIPT
IAEAInternational Atomic Energy Agency
Specificity of decontamination and remediation
activities after accident
Sergey Mikheykin
D-R PMU, Kozloduy NPP site
Workshop on development of specific decontamination techniques for RBMK dismantlement and/or highly active material from contaminated areas from accident conditions,
Visaginas, Lithuania, 24-28.08.2015
IAEA
Definition
Any unintended event, including operating
errors, equipment failures
and other mishaps, the consequences or
potential consequences of which are
not negligible from the point of view of
protection or safety.
[IAEA SAFETY GLOSSARY. TERMINOLOGY USED IN NUCLEAR SAFETY
AND RADIATION PROTECTION. 2007 EDITION]
2IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Accidents/INES
3
Off Site Impact
On Site Impact
IAEA
Waste after accidents
4
The main differences in waste management system in normal
operation and after accident are wide spectrum of wastes
(liquid, solid: soil, concrete, metals, debris, vegetation etc) and
large volume of radioactive wastes. For severe accident and
cleanup, waste volumes are expressed in tens thousands or
even millions of m3.
Special RWM strategies needed to address accident and
cleanup waste due to the very large volumes, range of
activities, timeframe, etc.
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
EXAMPLES
5
Major accident
(INES Level 7):
Chernobyl
NPP,
Ukraine
1986 The releases from Unit 4 continued for 10 days, and included
radioactive gases, condensed aerosols and a large
amount of fuel particles. Area of more than 200 000 km2
Major accident
(INES Level 7):
Fukushima
Daiichi NPP,
Japan
2011 Tepco estimates published in May 2012 showed a total of about
1020 PBq released to the atmosphere over 12-31 March 2011
(after which very little was released). Apart from noble gases this
comprised 500 PBq iodine-131, 10 PBq Cs-137 and 10 PBq Cs-
134. In iodine-131 equivalent terms this comes to 500 + 400 + 40 =
940 PBq Iodine-131 released to atmosphere
Serious
accident (INES
Level 6)
Mayak
Reprocessing
plant
Kyshtym
USSR
1957 Some 15 000–20 000 km2 received contamination higher than 3.7
kBq/m2 of Sr-90. This delineated an area of approximately 1000
km2 that became known as the East Urals Radioactive Trace.
Accident with
wider
consequences
(INES Level 5):
Three Mile
Island TMI-2,
USA
1979 Approximately 2500 m3 of water with an activity of 1 TBq/m3 were
released into the auxiliary building, fuel handling building, service
building and diesel generator building.
Experiences and Lessons Learned Worldwide in the Cleanup and
Decommissioning of Nuclear Facilities in the Aftermath of Accidents,
IAEA Nuclear Energy Series, No. NW-T-2.7
IAEA
EXAMPLES
6
Accident with
local
consequences
(INES Level
4):
A-1 Jaslovské
Bohunice,
Slovakia
1977 Fuel integrity was lost as a result of two fuel loading events
resulting in extensive damage of fuel cladding and release of
radioactivity.
Serious
incident (INES
Level 3)
THORP
Reprocessing
Plant
Sellafield Ltd,
UK
2006 Following plant mass balance calculations, a pool of 83 m3 of
product liquor was discovered within the feed clarification cell of the
THORP reprocessing plant. No liquor was lost to the environment
and no persons were injured or contaminated following this event.
Incident (INES
Level 2)
Atucha NPP
Argentina
2005 Overexposure of a worker at a power reactor exceeding the annual
limit.
Anomaly
(INES Level
1):
(Reactor)
Mihama NPP
Japan
2004 A water pipe in a turbine building adjoining the Mihama 3 reactor
burst suddenly as workers prepared to conduct a routine safety
inspection. Though no radiation was released, the steam explosion
killed five plant workers and injured others.
Experiences and Lessons Learned Worldwide in the Cleanup and
Decommissioning of Nuclear Facilities in the Aftermath of Accidents,
IAEA Nuclear Energy Series, No. NW-T-2.7
IAEA
The principle events
7
Event Plant Date Current Status
Windscale 1957 Care and Maintenance / Safe Enclosure
TMI -2 1979 Care and Maintenance / Safe Enclosure
Chernobyl 1986 Post Accident Clean up / Safe Enclosure
Fukushima 2011 Emergency Response / Stabilisation
Kyshtym 1957 Site Remediation
A1 Safe Enclosure / Decommissioning
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Differences
8
## D&D Emergency
1 Facility is under regulation control within all
operation time
Lost control as result of accident
2 Records keeping, good knowledge about site No records, lack of information about present
status of contamination and infrastructure
3 Control to constructive materials, process and main
equipment
No control, partially demolished constructions and
shields
4 Operations in according with licensed
decontamination plan
Needs in quick responds, possibilities for untypical
solutions
5 Need development of Decontamination plan at 1-5
years before shutdown of facility
Decontamination plan developing AFTER accident
6 Standard management approaches Emergency management under pressing of time,
irradiation and “unknowns”, many “surprises”
7 Strong regulation control, strong implementation of
safety standards for operations
Possibility to change of safety limits
8 Work of professional teams (selected as result of
competition/tender process)
Needs in well - skilled personnel (radiophobia)
9 D&D activity should provide the owner of the
Facility
Owner may have no resources, needs in the
Governmental or International support
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Role
• Decontamination and remediation starting with the start
of post-accidental works. The role of these actions are
reduction of risk for personnel from
irradiation/inhalation and protection of environment
from the distribution of radioactive substances with
natural factors as wind and water streams (rain, snow
melting, groundwater streams).
• Decommissioning and site remediation after accident
are under strong pressure of irradiation, absence of full
information about present status of accidental site, time
pressure, absence of well skilled decontamination team
etc.
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015 9
IAEA
Phases of planning of post-accident
cleanup projects .
10
Post-Accident Cleanup Activities
Planning Phases for INES Scale 1-4 Planning Phases for INES Scale 5-7
Stabilize
Post-
Accident
Cleanup
Restore/
OperateCompletion Stabilize
Post-Accident Cleanup
Early Final After
Reactor control/Source Control X X
Decay heat removal NA X
Gain access & information for
stabilization
X X
Characterization O X O X X X
Facility condition assessment X O X
Fuel/Source condition
assessment
X X X
Enclosure Structures (large) NA X
Water storage If applies X O O
Gas and air processing and
release
If applies X
Water processing If applies X X O
Decontamination for access X X
Damaged fuel/source removal X X
Damaged fuel/source storage X X
Waste shipping & disposal X O O X O O
Decontamination for operation X NA
Return to operation X NA
Waste storage If applies X ?
Decontamination for cleanup X X
Establish completion conditions X X
IAEA
List of operations
11
Criteria Subjects Criteria Statements
1. Structural and
Boundary Integrity
Structural and boundary integrity will be such that: 1) inspection personnel are safe, 2) contamination or hazardous materials remaining in the facility are contained, and 3) intrusion by unauthorized personnel, as well as animals and plants, are prevented.
1. Nuclear Materials Nuclear fuel and debris will be removed to the extent practical. Residual fissile material must be reduced to a level such that criticality cannot occur.
1. Hazardous Materials Hazardous materials and chemicals will be removed in accordance with environmental regulations. Fixed in place hazardous materials remaining in the facility will be contained in limited areas or stabilized to prevent release. The amount and location of remaining hazardous materials will be documented.
1. Process Systems and
Equipment
Process systems and equipment have been abandoned in place, isolated or sealed off for safety of future personnel, or removed where there is a compelling reason to do so.
1. Service and Utility
Systems and
Equipment
Only systems required to support the monitored storage state and maintain the stable condition are operational. Other utility systems will be abandoned in place, isolated or sealed off for safety of personnel, or removed where there is a compelling reason to do so.
1. Personnel Safety Inspection personnel are safeguarded by stable conditions, postings, and written procedures that have been established in accordance with standard procedures for radiological protection and industrial safety practice.
1. Waste and Liquid
Effluents
Waste will have been removed to the extent practical. Waste may remain if removal is with extreme difficulty. The only liquids remaining are minor quantities that cannot be readily removed with installed equipment.
1. Radiation Protection Established in accordance with standard procedures. In particular, the periodic inspection path will be subjected to ALARA review. Contamination remaining in the facility will be contained in limited areas or stabilized to prevent release.
1. Housekeeping &
Miscellaneous
Materials
Valuable materials will be removed. Trash and non-contaminated furniture, loose equipment, etc. will be removed.
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Specificity of RWM
12
IAEA
Approaches
• Chernobyl – Decontamination ASAP
• Fukushima – Decontamination ASAR
• TMI-2 – Removal of the fuel debris 1985-
1990.
13IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Specificity of decontamination
• Much of the past decontamination experience at nuclear facilities relates to
the cleanup of buildings, equipment and paved surfaces in or adjacent to
nuclear reactors and other facilities during normal operations or
decommissioning.
• Decontamination experience ranges from the cleanup of highly active
components or buildings in reprocessing plants or in other facilities after a
serious accident, to operations on slightly contaminated equipment or
buildings being released for unrestricted use.
14
Dynamics of self-decontamination of the region of the Fukushima-1 NPP
contaminated by radioactive substances can predict that the maximum dose rate in
the region of contamination will decrease to the background level in approximately
200 years.
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Preparation works
• Characterization/monitoring
• Development of decontamination strategy
• Installation of safety barriers and ventilation
• Equipment
• Organization of waste and personnel routes
• Team creation, training
15IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Decontamination in Chernobyl Area
• During large-scaled decontamination campaign in 1986-
1989 about one thousand of settlements were treated, tens
of thousand inhabited and social buildings, more than
thousand of agricultural farms.
• Depending of decontamination technologies the dose rate
over different plots was decreased by a factor of 1.5 to 15.
• Actual effectiveness of the annual external dose decrease
after upper soil layer removal usually was 10 to 20% for
average population ranging from about 30% for children
visiting kindergarten and schools to less than 10% for
outdoor workers (herders, foresters, etc.).16IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Decontamination in Chernobyl Area
• 1. Removal of the upper 5-20 cm layer of soil (it depends
on the activity distribution in depth) in courtyards in front of
residential buildings, around public buildings, schools and
kindergartens, from roadsides inside a settlement.
• The removed most contaminated layer of soil gets placed
into the holes specially dug on the territory of a private
homestead land or on the territory of a settlement when
decontaminating the settlement as a whole. At that the
clean soil (sand) from the dug holes gets used for covering
decontaminated areas.
• Such technology excludes the formation of special burials
of radioactive waste.
17IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Decontamination in Chernobyl Area
• 2. Deep ploughing of private fruit gardens’ territories or
removal of the upper 5-10 cm layer of the soil. If vegetable
gardens have been ploughed up many times, and in this
case the activity distribution in soil will be uniform in the
layer 20-30 cm deep
• 3. Covering the decontaminated parts with a layer of
«clean sand/soil», or, where possible, with a layer of
gravel to attenuate residual radiation (see item 1).
• 4. Cleaning the roofs or their replacement (the roof
decontamination should be done before decontaminating
the under spread surface).
18IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Achievable Decontamination Factors
for Various Urban Surfaces.
19
http://www-ns.iaea.org/downloads/rw/projects/emras-urban-decontamination-of-
settlements-golikov.pdf
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Decontamination 1986
20
IAEA
Decontamination 1986
21
IAEA
Fukushima - Land decontamination
22
House and garden (to reduce airborne dose rate)
• Lots of radioactivity has washed out from roofs.
• Dirt in ditch, moss and weed in surrounding area
have a higher radioactivity.
Road and street (to reduce airborne dose rate)
• Lots of radioactivity has washed out from the
pavement.
• Dirt and grass on a side soil and in ditch is
effective.
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Fukushima - Land decontamination
23
Farmland (to reduce the radioactivity)
5,000 Bq/kg is the upper limit for agricultural utilization.
Soft remediation method, i.e. plowing, rotary harrowing, is applied to relatively low
contaminated area.
Strong remediation method, i.e. top soil removal, replacement by fresh soil,
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Specially designed
removal equipment
24
Soil treatment
IAEA
Remediation Technology
Test ConditionReduction of Cs Concentration
[Bq/kg]
Applicable Contamination Level [Bq/kg]
Surface soil removal Removal depth = ~4cm 10,370 → 2,599DF=4.0
10,000-25,000
Chemical fixation & Surface soil removal
Fixative = Mg compoundRemoval depth = ~3cm
9,090 → 1,671DF=5.4
> 25,000
Surface soil removal with Grass & Weed
Removal depth = ~3cm 13,600 → 327DF=42
> 25,000
Harrowing & muddy water drainage
15,254 → 9,689DF=1.6
5,000-10,000
Phytoremediation Plant = Sunflower Soil = 7,715Stem=52, Root=148 -
http://www.s.affrc.go.jp/docs/press/pdf/110914-06.pdf in Japanese
Farmland contaminated more than 5,000Bq/kg = 83km2
→ 3.0million tons of waste are generated by 5cm soil removal.
Demonstration test results for Remediation Technologies by MAFF* *: Ministry of Agriculture, Forestry and Fishers
25
IAEA
Urban decontamination
26
Decontamination of settlements is one of the main
countermeasures to be applied to reduce external exposure of
the public and clean-up workers during the initial stage of the
response to a severe nuclear emergency.
IAEA
Decontamination of Houses
27
IAEA
Waste disposal
28IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEAInternational Atomic Energy Agency
Radioactive waste management
flow sheets after accidents
IAEA
Contaminated Soil
Decontamination
(optionally)
Solidification (optionally)
Packaging
Removing from surface
Reuse
Reuse
Radiometric sorting
Storage
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Concrete
Radiometric separation
Solidification (optionally)
Packaging
Decontamination
(scrabbling etc.)
Reuse
Reuse
Crushing
Storage
IAEA
Metals
Melting (optionally)
Packaging
Decontamination
Reuse
Reuse
Fragmentation
Storage
IAEA
Sediments
Solidification
Packaging
Decontamination or
purification
Reuse
Storage
IAEA Workshop, Visaginas, Lithuania on August 20-24, 2015
IAEA
Water
Solidification
Packaging
Purification
Pure Water Reuse
Storage
Sediments, resins, sorbents
Reuse
IAEA
Debris
Incineration
Sorting
Wood, organics
Storage
Plastic,
Protection clothes
Compaction
Cables
Solidification
PackagingPackaging
IAEA
Thank you!
36