specifications

116
HAMEL PARK RENOVATION CITY OF BEVERLY HILLS TECHNICAL SPECIFICATIONS TABLE OF CONTENTS DIVISION 2 SITE CONSTRUCTION 02050 SITE DEMOLITION 02110 SITE CLEAR AND GRUB 02210 SITE GRADING 02230 SUBGRADE PREPARATION 02310 EARTHWORK 02441 IRRIGATION 02445 TEMPORARY CHAIN LINK FENCING 02461 PLAY EQUIPMENT 02470 SITE FURNISHINGS 02480 PLANTING 02515 CONCRETE PAVING AND CURBS 02540 RESILIENT SURFACING 02710 STORM DRAINAGE 02780 UNIT PAVERS DIVISION 3 CONCRETE 03110 CONCRETE FORMWORK 03210 CONCRETE REINFORCEMENT 03300 CAST IN PLACE CONCRETE 03310 FOOTINGS AND FOUNDATIONS 03320 COLORED CAST-IN-PLACE CONCRETE 03380 CONCRETE CURING DIVISION 4 MASONRY 04220 CONCRETE UNIT MASONRY DIVISION 5 METALS 05510 METAL FABRICATIONS 05710 ORNAMENTAL METALS DIVISION 9 COATINGS 09900 PAINTING DIVISION 16 ELECTRICAL To Be Provided by DESIGN WEST

Upload: j-mar-de-vera

Post on 29-Sep-2015

5 views

Category:

Documents


0 download

DESCRIPTION

aashhdshshdjdffhddjfhdjdhfdhjfnmvncmvncmvnjcvncvcjvhjdhvjfhfhjfjff

TRANSCRIPT

  • HAMEL PARK RENOVATION CITY OF BEVERLY HILLS TECHNICAL SPECIFICATIONS TABLE OF CONTENTS

    DIVISION 2 SITE CONSTRUCTION 02050 SITE DEMOLITION 02110 SITE CLEAR AND GRUB 02210 SITE GRADING 02230 SUBGRADE PREPARATION 02310 EARTHWORK 02441 IRRIGATION 02445 TEMPORARY CHAIN LINK FENCING 02461 PLAY EQUIPMENT 02470 SITE FURNISHINGS 02480 PLANTING 02515 CONCRETE PAVING AND CURBS 02540 RESILIENT SURFACING 02710 STORM DRAINAGE 02780 UNIT PAVERS

    DIVISION 3 CONCRETE 03110 CONCRETE FORMWORK 03210 CONCRETE REINFORCEMENT 03300 CAST IN PLACE CONCRETE 03310 FOOTINGS AND FOUNDATIONS 03320 COLORED CAST-IN-PLACE CONCRETE 03380 CONCRETE CURING

    DIVISION 4 MASONRY 04220 CONCRETE UNIT MASONRY

    DIVISION 5 METALS 05510 METAL FABRICATIONS 05710 ORNAMENTAL METALS

    DIVISION 9 COATINGS 09900 PAINTING

    DIVISION 16 ELECTRICAL To Be Provided by DESIGN WEST

  • Site Demolition 02050-1

    SECTION 02050 - SITE DEMOLITION PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

    The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded.

    Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section.

    1.02 SCOPE OF WORK

    A. Furnish materials, labor, transportation, services, and equipment necessary to perform all site demolition work as indicated on the Drawings complete as shown and as specified herein.

    B. Related Work:

    Sub-grade Preparation Section 02230 Earthwork Section 02310

    1.03 REFERENCES

    A. Comply with the applicable reference specifications as specified in the GENERAL

    PROVISIONS and in accordance with applicable laws, codes and regulations required by the City.

    B. Comply with the current provisions of the following Codes and Standards:

    1. ASTM - American Society for Testing and Materials. 2. Standard Specifications B Agency Specified 3. Uniform Building Code

    1.04 QUALITY ASSURANCE

    A. Regulatory Requirements: Demolish existing site improvements as indicated on the Drawings, in an orderly and careful manner. Comply with all local codes and ordinances.

    B. Equipment: Use equipment specifically designed for the demolition of each type of

    material.

    C. Labor: Employ workmen skilled in the use of the equipment being utilized for demolition. 1.05 DELIVERY, STORAGE, AND DISPOSAL

    A. Delivery and Storage: Do not deliver to the job site nor store thereon demolition equipment and materials prior to receiving written notice to proceed. Confine storage to areas approved by the City.

  • Site Demolition 02050-2

    B. Disposal: Legally dispose of off site products of demolition during or at end of each day's work. Contractor shall pay all disposal costs associated with the project.

    1.06 PROJECT CONDITIONS

    A. Existing Conditions: Inspect site prior to commencing work. Determine scope of applicable site conditions. Prior to commencement of demolition activities, Contractor shall document in writing and photograph all existing conditions, including, without limitation, sidewalks, curbs, trees, fencing, and other elements, specifically areas that interface with private property. Digital copies of all photos, at a size no smaller than 4" x 6" at 150 dpi minimum resolution, shall be provided to the City and Project Landscape Architect for future reference. The contractor shall be held responsible for any damages not documented in the submittal prior to commencement of demolition activities.

    B. Access and Testing: Make test excavations and borings required to determine existing conditions, subject to City's convenience.

    C. Acceptance: Commencing work constitutes Contractor's acceptance of site conditions,

    both surface and subsurface. No extra payment shall accrue to Contractor by virtue of unknown conditions or difficulties of performing this demolition work.

    1.07 PROTECTION

    A. Protection of Existing Trees and Shrubs to Remain 1. Operations: Do not store materials or equipment, permit burning, or operate or park

    equipment under the branches of existing plants to remain except as actually required for construction in those areas.

    2. Barriers: Provide barricades, fences or other barriers as necessary at the drip line to

    protect existing plants to remain from damage during construction.

    3. Notification: Notify Project Engineer when Contractor feels construction activities may damage existing plants to remain.

    4. Replacement of Damaged Plants:

    a. Replace existing plants to remain that are damaged during construction with

    accepted plants of the same species and size as those damaged at no cost to City.

    b. Project Engineer will determine extent of damage and value of damaged plants.

    B. Protection of Existing Site Improvements 1. References: Verify and maintain benchmarks, monuments and other reference points.

    Replace if disturbed or destroyed.

    2. Protection: Protect existing improvements noted to remain within designated limit(s) of work. Supply shoring, bracing, reinforcing and barricades as required. Refer to drawings for limit of work.

  • Site Demolition 02050-3

    Maintain a minimum distance of 18 from edge of footing excavation to the southern park property line. Hand excavation of footing trench may be necessary to avoid damage/loss or private property plant material at southern boundary of project. Hand excavate, expose, and report any root(s) originating from southern adjacent property that is 3 in diameter of larger. Do not cut any root larger than 3 prior to inspection, and direction from City representatives.

    At northern park property line, keep wall footing in place, sawcut to height indicated

    by City representative. Refer to 3.02 B for additional instructions.

    3. Utilities: Keep in operation existing utility circuits and piping to remain including sprinkler irrigation except at the direction of the Project Engineer. Provide 48-hour notice of interruption of service. Notify Project Engineer should utilities not shown on Drawings be found during demolition.

    4. Repair: If damage to site improvements to remain occurs during the course of the

    work, restore to the satisfaction of the City at no additional cost. PART 2 B NOT APPLICABLE PART 3 B EXECUTION 3.01 PREPARATION

    A. Verification: Verify with Owner items to be removed prior to commencement of work.

    B. Compliance: Proceed with demolition in an orderly and careful manner, in compliance with local codes and ordinances.

    C. Disposal: Legally dispose of demolished materials off site unless otherwise directed by

    Owner.

    3.02 DEMOLITION

    A. Utilities:

    1. Capping: Disconnecting and capping of utilities must be in accordance with the regulations of the utility company affected.

    B. Paving and Walls:

    1. Sawcutting: Accurately and cleanly sawcut existing concrete paving, walls, and

    footings as shown on Drawings, and as directed in field by City representative and/or Landscape Architect. Confine cuts to areas shown. To avoid damage to adjacent improvements, after establishment of grade, sawcut wall on northern property line and leave footing in place.

    2. Finishing: Rough grade excavated areas as necessary to achieve the final line and grade

    as called for in other Sections of this work. Compact the grade to the density of the

  • Site Demolition 02050-4

    surrounding area. The final surface shall be smooth, even and tight, free from loose or soft areas.

    C. Subgrade: Fill depressions made by demolition and restore excavated areas to a smooth

    and even grade. Compact the grade to the density of the surrounding soil and per the project=s soil report.

    3.03 DE-WATERING

    A. General: Provide and operate equipment and do ditching and pumping necessary to keep the project area free from water.

    B. Storm Water: Pump off storm runoff or other water until such time as new work in other

    Sections shall effectively remove such water.

    C. Protection: Take measures required to dispose of surface and subsurface water in compliance with municipal requirements.

    D. Debris: Prevent transport of soil, aggregate or debris off site where practical.

    END OF SECTION 02050

  • Site Clear and Grub 02110-1

    SECTION 02110 - SITE CLEAR AND GRUB PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

    The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded.

    Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section.

    1.02 SCOPE OF WORK:

    Furnish all material, equipment and labor necessary to perform all clearing and grubbing work complete, including but not limited to the following:

    Protection of trees indicated on drawings to remain.

    Clearing and grubbing of all vegetation from site work areas.

    Removal and disposal of all deleterious materials.

    Furnishing, developing, applying and providing dust control watering equipment as required for the project.

    1.03 RELATED WORK SPECIFIED ELSEWHERE:

    Site grading Section 02210 Planting Section 02480 Irrigation Section 02441

    1.04 RESPONSIBILITY AND COORDINATION:

    Contractor shall secure and maintain all required permits and licenses, and pay all fees necessary to legally complete the work of this section.

    Contractor shall notify utility companies for all utilities to be cut off, modified or relocated, and shall maintain and protect all active utilities.

    1.05 PROTECTION AND SAFETY:

    Contractor shall provide signs in necessary places to exclude persons, except those connected with the work, from entering the working area. Contractor is responsible for preventing unauthorized persons from entering working area.

    Protect the project site and adjacent properties from dirty water, mud and water accumulated due to Contractor's operations, rainfall runoff or water that enters the project site from any other

  • Site Clear and Grub 02110-2

    sources. PART 2 - MATERIALS - Not applicable. PART 3 - EXECUTION 3.01 SUBMITTALS:

    Pre-demolition Photographs: Show conditions of existing adjacent construction, specifically areas that interface with private property and site improvements that might be misconstrued as damaged by demolition operations. Submit before work begin as specified in 02050 - Site Demolition, 1.07 A. Record Documents: Accurately record locations of utilities and subsurface obstructions.

    3.02 GENERAL REMOVAL WORK:

    Removal work shall be carefully done to avoid damage to all existing facilities to remain. 3.03 SITE CLEARANCE AND DISPOSAL:

    Clear the sites to be improved of grass, shrubs, weed growth, rubbish and debris, and existing concrete/ asphalt slabs, etc., that are to be removed for construction of the improvements shown on the construction plans. Rocks and broken masonry larger than four inches in the greatest dimension, shall be removed to a minimum depth of l2" below finished grade within areas to be planted, and within full depth of overexcavation in all other areas. Hand excavate, expose, and report any root(s) originating from southern adjacent property that is 3 in diameter of larger. Do not cut any root larger than 3 prior to inspection, and direction from City representatives.

    All deleterious materials shall be disposed of off the site in a legal manner by the Contractor, who shall make all necessary arrangements and pay all related costs.

    Miscellaneous existing underground facilities, drainage devices, secondary water lines, cables, abandoned oil and water lines, leaching fields, irrigation pipes, wiring, etc, located l2 inches or more below finish grade may be abandoned in place or removed as necessary for proper completion of the work. All miscellaneous active lines that are uncovered during the grading operations shall be protected.

    3.04 UTILITIES:

    Inactive or abandoned utilities shall be disconnected, removed, and plugged or capped subject to the local governing ordinances.

    Should the Contractor encounter any existing underground utilities not shown on the drawings, he shall at once notify the Engineer who will determine further procedure.

    3.05 DEBRIS BURNING:

    Burning of debris will not be permitted.

  • Site Clear and Grub 02110-3

    3.06 DUST CONTROL:

    Dust shall be kept to a minimum during site clearing operations by means of wetting the site or other approved method. Wash down all existing sidewalks and roadways on and off the site daily and after all operations are complete. Comply with all dust control requirements, SWPPP and NPDES.

    END OF SECTION 02110

  • Site Grading 02210-1

    SECTION 02210 - SITE GRADING PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

    See Section 02310 - Earthwork - for further information

    The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded.

    Drawings, project manual, and general provisions of the Contract, including General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section.

    1.02 SCOPE OF WORK:

    Furnish all material, equipment and labor as necessary to perform all earthwork complete, including, but not limited to, the following: Rough grading as shown on the plans, including cut, fill, backfill and backfill compaction Subgrade preparation for walks, slabs and other facilities Finish grading of the site Excavation and backfill for all footings, trenches, structures, etc. Soil compaction as required Protective measures Dust and noise abatement

    1.03 RELATED WORK SPECIFIED ELSEWHERE: Site Clear and Grub - Section 02110. Excavation and backfill for any mechanical, plumbing, irrigation, drainage or electrical work - appropriate sections Fine finish grading in landscaped areas - Section 02480

    1.04 QUALITY ASSURANCE: A. All work shall comply, without limitations, with the requirements of the following:

    (2) Storm Water Quality Associations - Stormwater Best Management Practice Handbook (BMP Handbook) Construction Edition.

    (3) SWPPP & NPDES Requirements

    B. Tests and Inspections:

    (1) All work in this section shall be subject to the observation and testing as required by the Soils Engineer selected by the City. The Soils Engineer shall submit a compaction report to the City, certifying the Contractor's compliance with the plans, specifications, soils reports and City grading ordinance in placing all fills

  • Site Grading 02210-2

    and backfills. The Soils Engineer shall conduct all specified tests to insure compliance. Soils Engineer shall also test, identify and make recommendations on borrow site fill materials as specified in this section.

    (2) Number and location of soils tests to be at the discretion of the Soils Engineer to

    assure uniformity and compliance with the City grading ordinance, but at least one test per two vertical feet of fill, but not less than one test per 500 cubic yards, all as approved by the City.

    (3) The costs of services of the Soils Engineer, specified field density and maximum

    density tests, compaction reports and certificates of compliance, shall be borne by the City. Additional tests and re-compactions made necessary by inadequate compaction, inadequate materials provided by contractor, and inaccurate excavations shall be paid for by the Contractor at no additional cost to the City.

    1.05 GRADING OPERATIONS:

    The grading contractor shall be responsible for determining their own earthwork quantities for bidding purposes. The quantities shown on the plans are the engineer=s estimate only and are for the sole purpose of determining city plan check and permit fees. Contractor is responsible for all fine grading and coordination with the landscape and irrigation contractor to achieve all fine grades shown on the plans. All import or export necessary to achieve the grades as shown on the plans is the responsibility of the contractor and shall be included in the contract prices including, but not limited to, spoils.

    1.06 WATER: Contractor shall make arrangements with the City of Beverly Hills Public Works to obtain construction water. This includes, without limitation, payment for a hydrant meter and water usage for entire job.

    1.07 JOB CONDITIONS: A. Protection of Existing Items:

    (1) The Contractor shall furnish, place and maintain all shoring and bracing as may be required for protection of existing structures and utility services during execution of the work. The adequacy of and responsibility for this shall be the Contractor's completely.

    (2) All bench marks, monuments and other reference points shall remain undisturbed

    unless specifically directed otherwise by the City.

    (3) Contractor shall dig by hand as necessary to protect existing underground utilities and existing irrigation lines, in all areas where existing utilities and/or irrigation lines and wires are located.

  • Site Grading 02210-3

    B. Protection of Public:

    The Contractor shall provide such barricades, temporary fences, gates, lights, warning signs, guards, and other measures as may be necessary to assure safety and to deter trespassers. These provisions shall be maintained during the entire duration of the work. These temporary facilities shall be constructed, painted, and maintained in strict conformance with the requirements of applicable codes and other governing authorities.

    C. Coordination with Others:

    (1) Contractor shall give written notice to the Owner, utility agencies, and other legal authorities prior to starting work.

    (2) Contractor shall coordinate his operations with other trades, utility firms, and

    other affected public departments to assure continuity for both access and service of all utility, service distribution lines, in conformance with applicable requirements of these organizations. No services to any property shall be impeded.

    D. Abandoned and Unknown Utilities:

    (1) Abandoned lines, meters and boxes, obstructions or piping, shall be removed, plugged, or capped in accordance with the requirements and approval of the agencies affected, or as directed by the City Inspector. Coordinate all such work with applicable mechanical or electrical trade having responsibility. Remove all abandoned utility lines, pipes, or conduits, to a point outside new construction lines.

    (2) Where unmarked utility lines or other underground obstructions or piping are

    uncovered within the work area, notify the City Inspector or the agencies or service utility companies having jurisdiction and take necessary measures to prevent interruption of service. Should such lines or services be damaged, broken, or interrupted through the Contractor's own negligence, those services shall be repaired immediately and restored by him at his own expense.

    PART 2 - MATERIALS 2.01 DRAIN ROCK:

    Drain rock for all infiltration areas shown on plan shall be ASTM C33 #57 rock, unless otherwise directed by City Inspector.

    2.02 IMPORT:

    A. All import soil used for fill in landscape areas (if deemed necessary) shall be Class `A'

    topsoil per Standard Specifications, Section 212. B. All import soil used for structural fill shall be non-expansive, predominantly granular

    material free from organic contaminants, and capable of attaining the required compacted densities.

    C. All import soil must be approved at the borrow site by the Soils Engineer.

  • Site Grading 02210-4

    2.03 FILL MATERIAL:

    A. All fill material must be approved by the Soils Engineer. B. On-site excavated materials may be used as approved by the Soils Engineer. Landscape fill

    shall be Class `A' topsoil. C. Rocks larger than 3 inches in diameter shall be removed from all fills to be compacted.

    2.04 GRANULAR BEDDING MATERIAL: Where called for on the plans, granular bedding material shall be crushed stone or pea gravel conforming to the following gradient:

    Sieve Size Passing

    3/4" 100 1/2" 95 4" 5

    2.05 CRUSHED MISCELLANEOUS BASE:

    Crushed miscellaneous base (CMB) shall consist entirely of crushed rock, rock dust and broken portland cement concrete conforming to the requirements of Section 200-2.4.1 of the Standard Specification and the Soils Investigation Report, maximum size aggregate shall be 3/4 inch.

    PART 3 - EXECUTION 3.01 GENERAL:

    A. All demolition and clearing and grubbing of objectionable materials must be completed to

    the satisfaction of the Soils Engineer before starting earthwork grading and excavation. B. Survey/Staking:

    Contractor shall provide all survey services necessary for horizontal and vertical control points, layouts, lines and levels, staking of work. See Section 01050 - Field Engineering - for further information

    Any corrections to the grading work required to obtain proper drainage and to bring it into conformance with the intent of the plans and specifications and City codes shall be performed by Contractor at no additional cost to the City.

    C. Contractor shall check all existing grades prior to initiating grading work as necessary to

    verify that the project can be graded as proposed. Any discrepancies found should immediately be brought to the attention of the City in writing.

  • Site Grading 02210-5

    3.02 ROUGH GRADING: A. Rough grading of the site shall be in accordance with indicated contours, elevations, and

    limit lines shown on the plans and shall be sufficient to allow for the depths of paving, sub-base, topsoil, and compacted fills. Tolerance for rough grading is 1/10th of a foot. In all areas, appearance and positive drainage will be governing factors in acceptability of grades.

    B. Graded material shall not be left in loose layers, but shall be stockpiled for use as

    compacted fill or compacted in thin layers as grading takes place in accordance with the requirements for compacted fill.

    C. Scarification to a minimum depth of six (6) inches or to a depth permitting twelve (12)

    inches of controlled compacted fill shall be performed on all areas indicated to be overexcavated.

    D. The Soils Engineer shall inspect all scarified surfaces prior to placement of compacted fill.

    3.03 CONTROLLED FILL: A. Fill material shall be spread in uniform lifts of six (6) to eight (8) inches of uncompacted

    thickness. B. Prior to starting compaction, the fill material shall be brought to optimum moisture

    content by spraying with water if too dry, and aeration if too wet. C. Thoroughly mix each lift to assure uniform distribution of water content. D. Bring fills to suitable elevations above required grades to provide for effects of shrinkage

    and settlement. E. For all areas designated to receive slabs and pavement and within a perimeter five (5) feet

    outside these areas, each lift shall be compacted to a minimum of 95% of maximum density as determined by ASTM D1557-70.

    F. Where fill is required in planting areas each lift shall be compacted to a minimum of 85%

    maximum density. G. Perform all compaction by suitable mechanical equipment and methods approved by the

    Soils Engineer. H. Inspection and field tests shall be carried on during grading by the Soils Engineer to assist

    the Contractor in obtaining the required degree of compaction and the proper moisture content. Where compaction of less than 90% is indicated, additional compactive effort shall be made with adjustment of the moisture content as necessary until a minimum of 90% compaction is obtained.

    I. The material in any soft or spongy spots shall be removed to such depth as directed by the

    Soils Engineer and replaced with suitable material, properly compacted. J. Sub-grades to receive slabs and pavements shall be finished to a tolerance of plus or minus

    one-half (l/2) inch.

  • Site Grading 02210-6

    3.04 FINE GRADING:

    Fine grading as specified in this section is distinguished from finish grading specified under Section 02480 Landscape Planting. Finish grades shall slope to drain without water pockets or irregularities and shall conform to the intent of all plans and specifications after thorough shrinkage, settlement and compaction of the soil. Fine grading shall allow for soil preparation work as specified under section 02480 Landscape Planting, such that finish grades shall meet the elevations & grades indicated on the plans. Finish grades shall meet all existing or established controls of sidewalks and curbs, and shall be of uniform slope and grade between points of fixed elevations or elevation controls and from such points to established grades. Tolerance for finish grading is l/4 inch, plus or minus.

    Any corrections to the grading work required to obtain proper drainage and to bring it into conformance with the intent of the plans and specifications and City codes shall be performed by Contractor at no additional cost to the City.

    3.05 EXCAVATION: The Contractor shall make all necessary excavation for footings and slabs and to any additional excavation necessary to provide ample room for installation of concrete forms where required.

    Bottom of excavations shall be level, free from loose material and brought to the indicated or required grades in undisturbed earth. All excavations shall be kept free from standing water. The Contractor shall do all pumping or draining that may be necessary in carrying on the work. Should excavations for footings, through error, be excavated to a greater depth of size than indicated or required, such additional depth or size shall be filled with concrete, at the Contractor's expense.

    3.06 BACKFILLING: Select site material shall be used for backfill of trenches and shall be free from large stones and clods. All bedding to be per codes. Also refer to subsections 2.04 - Granular Bedding Material and 2.05 - Crushed Miscellaneous Base in this section. Backfill shall be deposited in layers of maximum six inch thickness. Layers of backfill shall be moistened with water, the amount to be rigidly controlled to insure optimum moisture conditions for the type of fill material used. Excess water causing saturated earth beneath footings, walks, and curbs will not be permitted. Backfill shall be compacted by suitable means to a minimum 90%.

    3.07 DUST AND NOISE ABATEMENT: During the entire period of construction, site areas shall be kept sprinkled as necessary to reduce dust in the air and annoyance to surrounding properties. Adhere to the requirements of City ordinances for dust and noise control and NPDES.

    END OF SECTION 02210

  • Subgrade Preparation 02230-1

    SECTION 02230 BBBB SUB-GRADE PREPARATION

    PART 1 - GENERAL

    1.01 GENERAL CONDITIONS

    Requirements of the Contract Documents, including but not limited to, the General, Special, and Technical Provisions, apply to work in this Section with the same force and effect as though repeated in full herein.

    1.02 SCOPE OF WORK

    Furnish materials, labor, transportation, services, and equipment necessary to perform all sub-grade preparation work for the park as indicated on the Drawings complete as shown and as specified herein. Related Work:

    Earthwork Section 02310 Concrete Formwork Section 03110 Concrete Reinforcement Section 03210 Cast-In-Place Concrete Section 03310

    1.03 REFERENCES

    Comply with the applicable reference specifications as specified in the GENERAL PROVISIONS and in accordance with applicable laws, codes and regulations required by the City of Beverly Hills, CA.

    Comply with the current provisions of the following Codes and Standards:

    ASTM - American Society for Testing and Materials. Standard Specifications Uniform Building Code

    PART 2 - MATERIALS

    2.01 SUITABLE MATERIALS

    General: Fill, backfill, and embankment materials shall be suitable selected or processed clean, fine earth, rock, or sand, and free from grass, roots, brush, or other vegetation; contamination; or deleterious material. The size, gradation, and properties of the materials shall be in accordance with the requirements of the Soil Report and these specifications.

    Aggregate base materials under pavements shall be crushed aggregate base material constructed to the thickness shown or specified. The percentage composition by weight of aggregate base shall conform to the Standard Specifications.

    PART 3 - EXECUTION 3.01 SUBGRADE PREPARATION

    Excavate and shape subgrade to line, grade, and cross-section shown on the Drawings.

  • Subgrade Preparation 02230-2

    Subgrade is that area on which pavement, surfacing, base, sub-base, or a layer of other material which may be specified, is to be placed.

    Plow or scarify subgrade to a depth of 6" below the final subgrade elevation; and by harrowing, dry rolling and breaking clods, the earth shall be brought to finely divided condition. Remove boulders, hardened material, or rock encountered. The earth shall be uniform for the full depth and width of the subgrade.

    Water loose earth to a uniform depth of 4". Harrow the earth to mix the wet earth with the dry beneath, until the whole mass of loose material is at the proper state of moisture for compaction.

    The finished subgrade, immediately prior to placing subsequent material thereon, shall be in accordance with the Standard Specifications and project soils report.

    The finished surface of the subgrade, at any point, shall not vary more than 0.05' above or 0.2' below the elevation indicated on the drawings unless approved in writing by Hand excavate, expose, and report any root(s) originating from southern adjacent property that is 3 in diameter of larger. Do not cut any root larger than 3 prior to inspection, and direction from the City Representative.

    The City will not provide any additional compensation to the Contractor for hard rock or caliches excavation. Refer to the project soils report for test boring information and analysis.

    3.02 BASE

    Base shall be readily compacted and spread with equipment that will provide a uniform layer conforming to the planned section.

    3.03 CLEANUP

    Upon completion of the subgrade preparation and base, remove surplus construction materials, earth and debris so that the job site is left in a neat and orderly condition.

    END OF SECTION 02230

  • SECTION 02310 BBBB EARTHWORK

    PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

    Section 02210 - Site Grading The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6 (except as modified herein), apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded.

    Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section.

    1.02 SCOPE OF WORK

    Furnish materials, labor, transportation, services, and equipment necessary to perform all earthwork operations related to the park as indicated on the Drawings complete as shown and as specified herein. The work of this Section includes all earthwork required for construction of the WORK. Such earthwork shall include, but not be limited to, the loosening, overexcavation and recompaction, removing, loading, transporting, depositing, and compacting in its final location of all materials wet and dry, as required for the purposes of completing the work specified in the Contract Documents, which shall include, but not be limited to, the furnishing, placing, and removing of sheeting and bracing if necessary to safely support the sides of all excavation; all pumping, ditching, draining, dewatering, and other required measures for the removal or exclusion of water from the excavation; the supporting of structures above and below the ground; all backfilling around structures and all backfilling of trenches and pits; the disposal of excess excavated materials; alluvial removals, selective grading of expansive soils, soil importing or exporting, borrow of materials to make up deficiencies for fills, and all other incidental earthwork, all in accordance with the requirements of the Contract Documents.

    Related Work:

    Site Demolition Section 02050 Site Grading Section 02210 Sub-grade Preparation Section 02230

    1.03 REFERENCES

    All work will be done in accordance with applicable laws, codes and regulations required by the City of Beverly Hills, CA. Work shall comply with the rules and regulations of local, state and federal agencies having jurisdiction, including, without limitation, SWPCP and NPDES. Nothing contained herein shall be construed as permitting work that is contrary to such rules, regulations and codes.

  • Earthwork 02310-2

    Comply with the current provisions of the following Codes and Standards, without limitation: 1. ASTM - American Society for Testing and Materials 2. Standard Specifications (as specified in the General Provisions [Part 1 is specifically excluded])

    3. CBC B California Building Code, Title 24, Part 2, Chapter 18 and Chapter 33

    4. Storm Water Quality Association B Stormwater Best Management Practice Handbook (BMP

    Handbook) Construction Edition.

    5. State Water Resources Control Board Order No. 92-08-DWQ

    6. ASTM C136 B Method for Sieve Analysis of Fine and Coarse Aggregation

    7. ASTM D448 B Sizes of Aggregate for Roadway and Bridge Construction

    8. ASTM D1556 B Test Method for Density of Solid in Place by the Sand-Cone Method

    9. ASTM D1557 B Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 10 lb. Rammer and 18 inch Drop

    10. ASTM D2922 B Test Methods for Density of Soil and Soil-Aggregate in Place by Nuclear

    Methods (Shallow Depth)

    11. ASTM D2937 B Test Method for Density of Solid in Place by the Drive-Cylinder Method

    12. ASTM D3017 B Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth)

    13. Coordinate work of this section with Permit provisions of State Water Resources Control

    Board Order No. 92-08-DWQ and the Storm Water Pollution Prevention Plan. 1.04 SUBMITTALS

    Submittals, including samples of materials, shall be in accordance with the GENERAL PROVISIONS. Samples: Submit a one-half cubic foot sample of proposed import soils (if required) per the project=s soil report for Soils Engineer=s review and approval; identify location and source of import soil.

    1.05 QUALITY ASSURANCE

    General: All soils testing and inspection during earthwork operations, other than agricultural suitability and chemical analysis of proposed soils, will be done by a testing laboratory of the City=s choice, at the city=s expense except as specified in Paragraph 1.5.C below.

    Where soil material is required to be compacted to a percentage of maximum dry density, the maximum dry density at optimum moisture content will be determined in accordance with the

  • Earthwork 02310-3

    latest version of ASTM D 1557. In-place field density tests will be performed in accordance with ASTM D 1556, (sand cone) and/or ASTM D 2922 and ASTM D 3017 (nuclear gauge). The number and location of field density tests will be determined by the Soils Engineer.

    In case the tests of the fill or backfill show non-compliance with the required density, the CONTRACTOR shall accomplish such remedy as may be required to ensure compliance. Subsequent testing to show compliance shall be by a testing laboratory selected by the City and shall be at the CONTRACTOR=s expense. All imported fill material not specified in the contract shall be tested at the CONTRACTOR=s expense and approved by the Soils Engineer.

    1.06 PROJECT CONDITIONS

    Existing Conditions: The existing topographic conditions are shown on the drawings for reference only. Upon beginning the earthwork, Contractor represents that he has inspected the site and satisfied himself as to actual grades and levels and the true conditions under which the work is to be performed. Promptly notify the City=s Representative of unexpected subsurface conditions. The Contractor is required to submit a "Site Acceptance" letter before earthwork operations begin. Soil Classification: Excavated materials are not classified as to type.

    1.07 PROTECTION

    Protection: 1. Protect excavations by shoring, bracing, sheeting, underpinning, or other methods, as

    required to prevent cave-ins or loose dirt from entering excavations. Barricade open excavations and post warning lights at work adjacent to public streets and walks. Coordinate with all ordinances.

    2. Cover holes and trenches when work is not in progress. Fence or barricade changes of

    plane more than 45 degrees horizontally and more than 3 feet vertically. 3. Maintain bench marks, monuments, and other reference points. If disturbed or destroyed,

    replace as directed, at no cost to the owner 4. Protect existing berms and slopes from disruption. If slopes are disturbed, return to existing

    conditions at no additional cost to the City. 5. Underpin adjacent structure(s), including utility service lines, which may be damaged by

    excavation operations. 6. Protect existing natural areas and landscape improvements from damage. 7. Promptly repair damage to adjacent facilities caused by earthwork operations. Cost of

    repair at Contractor's expense. Provide erosion and sedimentation control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways according to requirements of the Storm Water Pollution Prevention Plan.

  • Earthwork 02310-4

    Inspect, repair, and maintain erosion and sedimentation control measures during earthwork operations.

    PART 2 - MATERIALS 2.01 SUITABLE FILL AND BACKFILL MATERIAL REQUIREMENT

    General: Fill, backfill, and embankment materials shall be suitable selected or processed clean, fine earth, rock, or sand, and free from grass, roots, brush, or other vegetation; contamination; or deleterious material. The size, gradation, and properties of the materials shall be in accordance with the requirements of these specifications.

    Suitable materials may be obtained from onsite excavations, may be processed onsite materials, or may be imported provided these materials meet all the requirements in the Contract Documents. If imported materials are required to meet the requirements of this Section or to meet the quantity requirements of the project, the Contractor shall provide the imported fill materials and the required conformance reports of test results at no additional expense to the City, unless a unit price item is included for imported materials (including the appropriate required testing reports) in the bidding schedule.

    2.02 FILL FOR MISCELLANEOUS LANDSCAPE WORK

    General Landscape Construction 1. Mound Construction: Fill material similar to existing on-site soil with all rocks, etc., over

    4" in diameter removed prior to placement. No rocks larger than 2" in diameter are allowed in top 6" of mound.

    2. Miscellaneous Landscape Filling: Fill material similar to existing on-site soil with all rocks, etc. over 2" in diameter removed prior to placement.

    3. Remove and dispose of rocks, etc. removed during soil processing offsite. 4. Imported fill material shall be inspected, tested, and approved by the Soils Engineer prior to

    use in work. Copy of tests will be given to the City. 2.03 PLANTING SOIL FOR PLANT BACKFILL

    Native soil tilled and free of noxious weeds and chemicals. Soil must be approved as growing medium from soils lab report with any supplementary additives as directed by soils lab report. Copy of the soil lab report will be given to the City.

    2.04 USE OF FILL AND BACKFILL MATERIAL TYPES

    The Contractor shall use the types of materials as designated on the Drawings and herein for all required fill, backfill, and embankment construction hereunder. Where these Specifications conflict with the requirements of any local agency having jurisdiction, or with the requirements of a material manufacturer, the City shall be immediately notified. In case of conflict therewith, the order or precedence in the Contract or Terms and Conditions shall govern.

  • Earthwork 02310-5

    PART 3 - EXECUTION 3.01 PREPARATION

    Establish extent of grading and excavation by area and elevation. Designate and identify datum elevation and project engineering reference points. Set required lines, levels and elevations.

    Do not cover or enclose work of this Section before obtaining required inspections, tests, approvals, and location recording.

    3.02 EXISTING UTILITIES

    Before starting grading and excavation, establish the location and extent of underground utilities in

    the work area. Exercise care to protect existing utilities during earthwork operations. Perform excavation work near utilities by hand and provide necessary shoring, sheeting, and supports as the work progresses.

    Maintain, protect, relocate, or extend, as required, existing utility lines to remain which pass through the work area. Protect active utility services uncovered by excavation. Notify respective utility companies of damage caused to active utilities immediately. Remove abandoned utility service lines from areas of excavation. Cap, plug, or seal abandoned lines at source of connection and identify termination points at grade level with markers.

    Accurately locate and record abandoned and active utility lines rerouted or extended on project record documents.

    3.03 SITE GRADING B GENERAL

    Perform grading within contract limits, including adjacent transition areas, to new elevations, levels, profiles, and contours indicated. Provide uniform levels and slopes between new elevations and existing grades. Obtain approval of scarified subgrade surfaces by City's Representative prior to filling operations. Scarify, dry, and compact soft and wet areas; remove and replace unsuitable subgrade materials with an approved fill material. Take corrective measures before placing fill materials.

    Thoroughly scarify existing soil surface to a depth of 10" and as shown on the Soils Report and verify scarification with City's Representative prior to placing fill material in mounded areas.

    Spread approved fill material uniformly in layers not greater than 12" of loose thickness over entire fill zones of planting areas.

    1. Lift thickness requirements may be modified by City=s Representative to suit equipment and

    materials or other conditions when required to assure satisfactory compaction.

  • Earthwork 02310-6

    2. Place and compact each layer of fill before placing additional fill material. Repeat filling until proposed grade, profile or contour is attained.

    3. Suspend fill operations when satisfactory results cannot be obtained because of environmental

    or other unsatisfactory site conditions. Do not use over-saturated fill materials. Do not place fill material on over-saturated subgrade surface.

    4. Grade surfaces to assure positive drainage and to prevent ponding and pockets of surface

    drainage. Install drainage swales as indicated on the Drawings. 5. Protect finish graded areas from traffic and erosion. Keep free of trash and debris. Repair and

    reestablish grades in settled, eroded and damaged areas.

    If, in the opinion of the City, the completed site grading does not reflect the Contract Documents, an independent surveyor may be hired to verify the grades. If the grades are correct, the City will pay for the survey. If the grades are incorrect, the cost of the survey will be deducted from the Contract price.

    3.04 BACKFILLING / FILLING FOR PAVING & WALLS

    Before filling, remove debris, large rocks, formwork and loose material.

    Proof-roll areas to receive fill with rubber tired roller of sufficient weight. Weak areas or areas where excessive pumping is noted shall be removed, and if required by the City, replaced with select fill. Prior to placing fill, scarify surface to a depth of 6 inches. Moisture content of loosened material shall be such that first layer of fill will readily bond to surface.

    Top 6 inches shall be free from rocks larger than 3 inches diameter.

    Place in maximum 8-inch lifts and compact per ASTM D 1557 at optimum moisture content (-1% to +3%). This lift and compaction requirement does not apply to planting areas. Moisten fill to allow drying to correct moisture content before compaction. Do not place fill on subgrade that is over-saturated. Paving subgrade per plan and soils report.

    Allowing for total thickness of finish paving and base material, fill under paving to bring subgrade to proper elevation.

    Soft areas that develop under construction operations shall be scarified, aerated or moistened. Compact to full depth required to obtain specified density for each layer.

    3.05 EXCAVATING

    It is the Contractor's responsibility to investigate the likelihood of caliches or hard rock excavation. The City will not provide any additional compensation to the Contractor for hard rock or caliches excavation.

  • Earthwork 02310-7

    3.06 FINISH GRADING

    Grade uniformly with rounded surfaces at tops and bottoms of abrupt changes in plane. Hand grade steep slopes, areas that are inaccessible for machine work and areas around existing plants.

    Slope graded surfaces to drain water away from structures, walls, etc.; minimum slope is 1/4 inch per foot. Grade areas to elevation and slopes indicated without depressions causing pocketing of surface water or humps, producing localized runoff and erosion. Ponding of water on site is not allowed. Finish surfaces to be not more than 0.10 foot above or below established grade elevation.

    See Subsection 3.03 Soil Preparation under Section 02480 Planting for additional fine grading requirements.

    3.07 DRAINAGE

    Provide drainage of the working area at all times. 3.08 DISPOSAL OF WASTE MATERIALS

    Legally dispose excess excavated material, including rock from site. 309 CLEANING

    Upon completion of earthwork operation, clean areas within contract limits, remove tools and equipment. Provide site clear, clean, free of debris and suitable for site work operations.

    Remove and dispose of properly off site all rocks and other debris from grading operations.

    END OF SECTION 02310

  • Irrigation 02441-1

    SECTION 02441 - IRRIGATION

    PART I - GENERAL 1.01 SCOPE:

    The work required is indicated on the drawings and includes, but is not limited to, lawn and shrub irrigation systems, automatic controller, remote control valves, quick coupler valves, and water and electric services.

    1.02 SUBMITTALS:

    A. Materials List:

    1. Complete material list shall be submitted prior to performing any work. Catalog data and full descriptive literature must be submitted whenever the use of the items different than those specified is requested. Notarized certificate must be submitted by plastic pipe and fitting manufacturer indicating that material complies with specifications, unless material has been previously approved.

    2. Material list shall be submitted using the following format (double spaced between

    each item):

    Item Description Manufacturer Model

    1. Pressure Pipe Lasco Sch. 40 2. Lawn Head Rainbird 1804-SAM-PRS Etc. Etc. Etc. Etc.

    B. Record Drawings:

    1. Record accurately on one set of contract drawings all changes in the work

    constituting departures from the original contract drawings.

    2. The changes and dimensions shall be recorded in a legible and workmanlike manner to the satisfaction of the City. Prior to final inspection of work, submit record drawings to City for approval.

    3. Dimensions from two permanent points of reference (buildings, monuments,

    sidewalks, curbs, pavement, etc.). Data to be shown on record drawing shall be recorded day to day as the project is being installed. All lettering on drawings shall be minimum 1/8 inch in size.

    4. Show locations and depths of the following items:

    a. Point of connection. b. Routing of sprinkler pressure lines (dimension maximum 100 feet along

    routing) c. Gate valves.

  • Irrigation 02441-2

    d. Sprinkler control valves. e. Quick coupling valves. f. Routing of control wires. g. Related equipment (as may be directed).

    5. Maintain record drawings on-site at all times. Upon completion of work, transfer

    all as-built information and dimensions to reproducible sepia prints. 1.03 INSPECTIONS:

    A. Inspections Will Be Required For:

    1. Pressure test of irrigation main line.

    2. Coverage test.

    3. Final inspection/start of maintenance. Final inspection shall be performed by the City in the presence of owner or his representative.

    4. Final acceptance.

    B. Inspection Requests:

    Contractor shall notify the City Inspector in advance for requesting all inspections as follows:

    Pressure supply line installation and testing - 36 hours (1 2 working days) System layout - 36 hours (1 2 working days) Coverage Tests - 36 hours (1 2 working days) Final Inspection - 48 hours (2 working days)

    When inspections have been conducted by other than the City Inspector, the Contractor shall show evidence of when and by whom these inspections were made.

    No inspection will commence without "record" prints. In the event the Contractor calls for an inspection without up to date "record" prints, without completing previously noted corrections, or without preparing the system for inspection, the inspection will be canceled and the Contractor back charged for the direct costs of all City personnel time and consultant time lost.

    C. Closing In Uninspected Work:

    Do not allow or cause any of the work of this section to be covered up or enclosed until it has been inspected, tested, and approved by the City.

    D. Coverage Test:

    When the sprinkler system is completed, Contractor shall perform a coverage test in the

  • Irrigation 02441-3

    presence of the City and the Landscape Architect to determine if the water coverage for planting areas is complete and adequate. This test shall be accomplished before any planting.

    E. Hydrostatic Tests:

    1. All pressure lines shall be tested under a hydrostatic pressure of 150 psi for a period

    of not less than two hours.

    2. All hydrostatic tests shall be made in the presence of the City. No pressure line shall be backfilled until it has been inspected, tested, and approved in writing.

    3. Contractor shall furnish necessary force pump and all other test equipment.

    1.04 TURNOVER ITEMS:

    A. Controller Charts:

    1. Record drawings must be approved by City before charts are prepared.

    2. Provide one plastic laminated controller chart for each automatic controller. Chart shall show the area covered by controller.

    3. The chart is to be a reduced copy of the actual "record" drawing. In the event the

    controller sequence is not legible when the drawing is reduced, it shall be enlarged to a readable size.

    4. Chart shall be a blackline print with a different color used to show the area of

    coverage for each station.

    5. When completed and approved, the chart shall be hermetically sealed between two pieces of plastic, each piece being a minimum 20 mils in thickness.

    B. Operation and Maintenance Manuals:

    1. Two individually bound copies of operation and maintenance manuals shall be

    delivered to the City 10 calendar days prior to final inspection. The manuals shall describe the material installed.

    2. Each complete, bound manual shall include the following information:

    a. Index sheet stating Contractor's address and telephone number, duration

    of guarantee period, list of equipment including names and addresses of local manufacturer representatives.

    b. Complete operating and maintenance instructions for all equipment. c. Spare parts lists and related manufacturer information for all equipment.

  • Irrigation 02441-4

    C. Equipment:

    1. Supply as part of this contract the following items:

    a. 4 additional sprinkler heads of each type and spray pattern shown. b. Two (2) wrenches for disassembly and adjustment of each type of

    sprinkler head involved. c. Three 30-inch sprinkler keys for manual operation of control valves. d. Two keys for each automatic controller. e. Two couplers with a 3/4" bronze hose bib. Bent nose type with hand

    wheel and two coupler keys. f. One soil probe 36 inches in length, Oakfield Model B, or equal. g. One valve box cover key or wrench. h. One 5-foot tee wrench for operating gate valves 3 inches or larger. i. Backflow device valve handles and Public Works inspection

    documentation.

    2. The above equipment shall be turned over to the City at the final inspection. 1.05 GUARANTEE:

    A. General: The entire sprinkler system, including all work done under this contract, shall be guaranteed against all defects and fault of material and workmanship for a period of one (1) year following the filing of the Notice of Completion. All materials used shall carry a manufacturer's guarantee of one (1) year.

    Should any problem with the irrigation system be discovered within the guarantee period, it shall be corrected by the Contractor at no additional expense to the City within ten (10) calendar days of receipt of written notice from the City. When the nature of the repairs as determined by the City constitute an emergency (e.g. broken pressure line) the City may proceed to make repairs at the Contractor's expense. Any and all damages to existing improvement resulting either from faulty materials or workmanship, or from the necessary repairs to correct same, shall be repaired to the satisfaction of the City by the Contractor, all at no additional cost to the City.

    B. Form of Guarantee: Guarantee shall be submitted on Contractors own letterhead as

    follows: FORM OF: GUARANTEE FOR SPRINKLER IRRIGATION SYSTEM We hereby guarantee that the sprinkler irrigation system we have furnished and installed is free from defects in materials and workmanship, and the work has been completed in accordance with the drawings and specifications, ordinary wear and tear and unusual abuse, or neglect excepted. We agree to repair or replace any defects in materials or workmanship which may develop during the period of one year from date of filing of the Notice of Completion and also to repair or replace any damage resulting from the repairing or replacing of such defects at no additional cost to the City. We shall make such repairs or replacements within 10 calendar days following written notification by the City. In the event of our failure to make such repairs or replacements within the time specified after receipt of written notice from the City, we authorize

  • Irrigation 02441-5

    the City to proceed to have said repairs or replacements made at our expense and we will pay the costs and charges therefore upon demand. PROJECT: LOCATION:

    SIGNED: ADDRESS:

    PHONE:

    C. After the system has been completed, the Contractor shall instruct the Parks Department

    Representative in the operation and maintenance of the system and shall furnish a complete set of operating instructions.

    D. Any settling of trenches which may occur during the one-year period following acceptance

    shall be repaired to City's satisfaction by the Contractor without any additional expense to the City. Repairs shall include the complete restoration of all damage to planting, paving or other improvements of any kind as a result of the work.

    1.06 IRRIGATION SYSTEM DESIGN:

    Irrigation design is based on 60 psi available water pressure at 10 gpm. Contractor shall verify working water pressure prior to construction. Should a discrepancy exist, notify Landscape Architect prior to beginning construction.

    PART II - MATERIALS 2.01 GENERAL:

    Materials or equipment installed or furnished that do not meet the City standards will be rejected and shall be removed from the site at no expense to the City.

    2.02 PIPE:

    A. Pressure supply line from point of connection through backflow prevention unit shall be Type K brass or copper pipe.

    B. Pressure supply lines 2-1/2 inches in diameter and up to 6 inches in diameter downstream of

    backflow prevention unit shall be Class 315 solvent weld PVC.

    C. Pressure supply lines 2 inches in diameter and smaller downstream of the backflow prevention unit shall be Schedule 40 solvent weld PVC.

    D. Non-pressure lines shall be Class 200 PVC.

  • Irrigation 02441-6

    2.03 COPPER PIPE AND FITTINGS:

    A. Copper pipe shall be Type 'K', hard tempered ASTM B 88 and fittings shall be wrought solder joint type in accordance with ANSI B16.22.

    B. Joints shall be soldered with silver solder, conforming to ASTM B206.

    2.04 BRASS PIPE AND FITTINGS:

    A. Brass pipe shall be 85 percent red brass, ANSI, Schedule 40 screwed pipe.

    B. Fittings shall be medium brass, screwed 125-pound class. 2.05 GALVANIZED STEEL PIPE AND FITTINGS:

    A. All galvanized steel pipe shall be Schedule 40, threaded, coupled, and hot-dipped galvanized, and shall comply with the requirements of ASTM A 120-66 or ASTM A 53-67.

    B. All fittings for galvanized steel pipe shall be 150-pound rated galvanized malleable iron,

    banded pattern.

    C. Pipe sizes indicated on the drawings are nominal inside diameter, unless otherwise noted. 2.06 PLASTIC PIPE AND FITTINGS:

    A. All plastic pipe shall bear the following markings: manufacturer's name, nominal pipe size, schedule or class, type of material, pressure rating in psi, NSF seal of approval, and the date of extrusion.

    B. All plastic pipe shall be extruded of an improved PVC virgin pipe compound.

    C. Rubber gasket PVC pipe, couplings, and fittings shall conform to ASTM D 1784 Type I,

    Grade I, 2,000-psi design stress. Couplings, rubber gaskets, and fittings shall be as approved by the pipe manufacturer.

    D. Ring-type rubber gasket couplings shall permit a 5 degree deflection of the pipe at each

    coupling (2-1/2 degree each side) without exfiltration or infiltration,, cracking or breaking.

    E. All fittings shall be standard weight Schedule 40 and shall be injection molded of an improved PVC fitting compound. Threaded plastic fittings shall be injection molded. All tees and ells shall be side gated.

    F. All threaded nipples shall be standard weight Schedule 80 with molded threads.

    E. All solvent cementing of plastic pipe and fittings shall be a two-step process, using primer

    and solvent cement applied per the manufacturer's recommendations. Cement shall be of a fluid consistency, not gel-like or ropy.

  • Irrigation 02441-7

    2.07 BACKFLOW PREVENTION UNITS:

    The backflow prevention unit shall be as indicated on the drawings. 2.08 VALVES:

    A. Gate Valves:

    1. Gate valves 2 inches or smaller shall have screwed joints and brass bodies.

    2. All gate valves larger than 3 inches in diameter shall have 2-inch-square operating units and have an arrow cast in the metal indicating the direction of opening. Valves shall have iron body and be bronze mounted.

    3. All gate valves larger than 2 inches and up to 3 inches in diameter shall conform to

    (1) or (2) above. 4. All gate valves shall have a minimum working pressure of not less than 150 psi and

    shall conform to AWWA standards.

    B. Quick Coupling Valves:

    Body of valves shall be brass with a wall thickness guaranteed to withstand normal working pressure of 150 psi without leakage. Valves shall have 3/4-inch female threads opening at base, with two-piece body. Construct valves to be operated only with a coupler, designed for that purpose. Coupler is inserted into valve and a positive, watertight connection shall be made between coupler and valve. Hinge cover shall be brass with a yellow rubber-like vinyl cover bonded to it.

    C. Manual Control Valves:

    Antisiphon-type valves shall be all bronze with swivel-type replaceable seating members and an approved vacuum breaker as an integral part of assembly.

    D. Remote Control Valves:

    Valves shall be spring-loaded, self-cleaning, packless diaphragm activated, of a normally closed type.

    2.09 VALVE BOXES:

    A. Valve boxes shall be fabricated from a durable, weather-resistant plastic material resistant to sunlight and chemical action of soils.

    B. The valve box cover shall be secured with a hidden latch mechanism or bolts.

    C. The cover and box shall be capable of sustaining a load of 1,500 pounds.

    D. Valve box extensions shall be by the same manufacturer as the valve box.

  • Irrigation 02441-8

    E. Gate valve boxes shall be round plastic boxes with bolt-down covers marked "GATE

    VALVE," heat branded in 2" high characters; AMETEK or approved equal.

    F. Remote control valve boxes shall be rectangular plastic boxes with bolt-down covers marked "CONTROL VALVE"; and with the valve identification number heat branded in 2" high characters; AMETEK or approved equal.

    G. Colors of boxes shall be as called for on the plans.

    2.10 AUTOMATIC CONTROLLER:

    Automatic controller shall be as called for on the plans. 2.11 ELECTRICAL:

    A. All electrical equipment shall be NEMA Type 3, waterproofed for exterior installation.

    B. All electrical work shall conform to local codes and ordinances. 2.12 WIRING:

    A. Remote control wire shall be direct-burial AWG-UF type, sized according to manufacturer's specifications, and in no case smaller than 14 gage.

    B. Connections shall be either epoxy-sealed packet-type or Penn-Tite connectors.

    C. Common wires shall be white in color. (Where two or more controllers are used, the

    common wires shall be white with a different color stripe for each controller.) Control wires shall be black (where two or more controllers are used, the control wires shall be a different color for each controller.) These colors shall be noted on as-built plans located on controller door.

    2.13 SPRINKLERS:

    Sprinklers shall be as called for on the plans. 2.14 PUMPS:

    Submit full data on all equipment and operating instructions for approval. When pumps are required, controller shall be equipped with a 110-volt pump starter relay as an integral part.

    PART III - EXECUTION 3.01 GENERAL:

    A. Water Supply:

    Connections to or the installation of the water supply shall be at the locations shown on the

  • Irrigation 02441-9

    civil engineers drawings. Minor changes caused by actual site conditions shall be made at no additional cost to the City.

    B. Electrical Service:

    Contractor shall make 120V connection to the irrigation controllers.

    C. Layout:

    Layout irrigation systems and make minor adjustments required due to differences between site and drawings. Where piping is shown on drawings under paved areas, but running parallel and adjacent to planted areas, install the piping in the planted areas.

    D. Diagrammatic Intent:

    The drawings are essentially diagrammatic. The size and location of equipment and fixtures are drawn to scale where possible. Provide offsets in piping and changes in equipment locations as necessary to conform with structures and to avoid obstructions or conflicts with other work.

    E. Grades:

    Before starting work, carefully check all grades to determine that work may safely proceed, keeping within the specified material depths with respect to finish grade.

    F. Inspections:

    1. Prior to all work of this section, carefully inspect the installed work of all other

    trades and verify that all such work is complete to the point where this installation may properly commence.

    2. Verify that irrigation system may be installed in strict accordance with all pertinent

    codes and regulations, the original design, the referenced standards, and the manufacturer's recommendations.

    G. Discrepancies:

    1. In the event of discrepancy, notify the City and the Landscape Architect.

    2. Do not proceed with installation in areas of discrepancy until all discrepancies

    have been resolved.

    H. Field Measurements:

    Make all necessary measurements in the field to ensure precise fit of items in accordance with the original design. Contractor shall coordinate the installation of all irrigation materials with all other work.

  • Irrigation 02441-10

    3.02 TRENCHING:

    A. Dig trenches and support pipe continuously on bottom of ditch. Lay pipe to an even grade. Trenching excavation shall follow layout indicated on drawings to the depths below finished grade and as noted. Where lines occur under paved area, these dimensions shall be considered below subgrade.

    B. Provide minimum cover of 24 inches, maximum 30 inches on pressure supply lines 3 inches

    and larger.

    C. Provide minimum cover of 18 inches, maximum 24 inches on pressure supply lines 2 2 inches and smaller.

    D. Provide minimum cover of 18 inches, maximum 24 inches for control wires.

    E. Provide minimum cover of 12 inches, maximum 16 inches for non-pressure lines.

    F. Provide minimum cover of 24 inches, maximum 30 inches for all pipe sleeved under paving.

    G. Where it is necessary to excavate adjacent to existing trees, the Contractor shall avoid

    injury to trees and tree roots. Excavation in areas where 2-inch and larger roots occur shall be done by hand. All roots 2 inches and larger in diameter shall be tunneled under and shall be heavily wrapped with wet burlap to prevent scarring or drying. Where trenching machine is run close to trees having roots smaller than 2 inches in diameter, the wall of the trench adjacent to the tree shall be hand trimmed, making a clean cut through the roots. Roots 1 inch and larger in diameter shall be painted with two coats of Tree Seal or approved equal. Trenches adjacent to trees shall be closed within 24 hours.

    3.03 BACKFILLING:

    A. Initial backfill on all lines shall be of fine granular material with no foreign matter larger than 2 inch in size.

    B. Backfill shall be tamped in 4-inch layers under the pipe and uniformly on both sides for the

    full width of the trench and the full length of the pipe. Materials shall be sufficiently damp to permit thorough compaction, free of voids. Backfill shall be compacted to dry density equal to adjacent undisturbed soil and shall conform to adjacent grades.

    C. Flooding in lieu of tamping is not allowed without specific prior approval.

    D. Under no circumstances shall truck wheels be used to compact soil.

    E. Provide sand backfill a minimum of 6 inches over and under all piping under paved areas.

    3.04 PIPING:

    A. Piping under existing pavement may be installed by jacking, boring, or hydraulic driving. No hydraulic driving is permitted under asphaltic concrete pavement.

  • Irrigation 02441-11

    B. Cutting or breaking of existing pavement is not permitted.

    C. Carefully inspect all pipe and fittings before installation, removing dirt, scale, and burrs and reaming; install pipe with all markings up for visual inspection and verification.

    D. Exercise care in handling, loading, unloading, and storing plastic pipe and fittings; store

    plastic pipe and fittings under cover until ready to install; transport plastic pipe on a vehicle with a bed long enough to allow the pipe to lay flat, avoid undue bending and any concentrated external load.

    E. Remove all dented and damaged pipe sections.

    F. Contractor shall install concrete thrust blocking at all changes of direction and terminal

    points of pressure pipe.

    G. All lines shall have a minimum clearance of 6 inches from each other and 12 inches from lines of other trades.

    H. Parallel lines shall not be installed directly over one another.

    I. In solvent welding, use only the specified primer and solvent cement and make all joints in

    strict accordance with the manufacturer's recommended methods; allow solvent welds at least 15 minutes setup time before moving or handling and 24 hours curing time before filling.

    J. 360 degree applicators shall be used to apply primer and solvent on sizes 2 inches and

    larger.

    K. Centerload all plastic pipe prior to pressure testing.

    L. All threaded plastic-to-plastic connections shall be assembled using Teflon tape.

    M. For plastic-to-metal connections, work the metal connections first. Use a nonhardening pipe dope on all threaded plastic-to-metal connections, except where noted otherwise.

    3.05 ASSEMBLIES:

    A. Install all assemblies specified herein according to the respective detail drawings or specifications, using best standard practice.

    B. Install backflow assemblies at locations approved in the field and at height required by

    local codes.

    C. Valves shall be installed in shrub areas whenever possible per City standards.

    D. Each valve box shall be installed on a foundation of pea gravel backfill, 3 cubic feet minimum. Valve boxes shall be installed with their tops 3/4 inch above the surface of surrounding finish grade in lawn areas.

  • Irrigation 02441-12

    3.06 CONTROLLER:

    A. The exact location of the controller shall be approved by the City before installation. The electrical service shall be coordinated with this location.

    B. Controller shall be located in the storage room. Maintenance access shall be provided.

    C. Pump starter shall be connected to controller pump starter relay switch.

    D. The irrigation system shall be programmed to operate during the periods of minimal use of

    the design area. 3.07 WIRING:

    A. Wiring shall occupy the same trench and shall be installed along the same route as the pressure supply lines and shall be located below the supply lines wherever possible.

    B. Where more than one wire is placed in a trench, the wiring shall be taped together at

    intervals of 12 feet.

    C. All connections shall be of an approved type and shall occur in a valve box. Provide an 18-inch service loop at each connection.

    D. An expansion loop of 12 inches shall be provided at each wire connection and/or

    directional turn, and one of 24 inches shall be provided at each remote control valve.

    E. A continuous run of wire shall be used between a controller and each remote control valve. Under no circumstances shall splices be used without prior approval.

    3.08 FLUSHING THE SYSTEM:

    A. Prior to installation of sprinkler heads, the valves shall be opened and a full head of water used to flush out the lines and risers.

    B. Sprinkler heads shall be installed after flushing the system has been completed.

    3.09 SPRINKLER HEADS:

    A. Sprinkler heads shall be installed as designated on the drawings and per City standards.

    B. Spacing of heads shall not exceed maximum indicated on the drawings. 3.10 ADJUSTING THE SYSTEM:

    A. Contractor shall adjust valves, align heads, and check coverage of each system prior to coverage test.

    B. If it is determined by the City that additional adjustments or nozzle changes will be

    required to provide proper coverage, all necessary changes or adjustments shall be made

  • Irrigation 02441-13

    prior to any planting.

    C. The entire system shall be operating properly before any planting operations commence. 3.11 COMPLETION CLEANING:

    Upon completion of the work, Contractor shall smooth all ground surfaces; remove excess materials, rubbish, debris, etc,; sweep adjacent streets, curbs, gutters, walkways, and trails; and remove construction equipment from the premises.

    END OF SECTION F:\Specs\Irrigation.wpd

  • Temporary Chainlink Fencing 02445-1

    SECTION 02445 - TEMPORARY CHAINLINK FENCING 1.01 TEMPORARY FENCING:

    Install a 6' tall (min.) temporary construction fence prior to beginning any site work, at the frontage of the park property. The fence shall be chain link (new or used), free of openings or breaks in the fabric, with fence posts at 10' O/C maximum. Fencing shall incorporate green tennis court windscreen material, securely fastened to top and bottom of chain link fabric, for the entire secured perimeter of the fence line. The fence shall be maintained in place throughout the construction phase period through to the end of the ninety (90) day landscape maintenance period. Install ANo Trespassing@ signs minimum 20' o.c., with wording presented in both English and Spanish. The temporary fence shall be removed prior to final inspection/project acceptance at the end of the maintenance period.

    END OF SECTION 02445

  • Play Equipment 02461-1

    SECTION 02461 - PLAY EQUIPMENT PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

    The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded.

    Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section.

    1.02 SCOPE OF WORK:

    The work under this section shall include, without limitation, all labor, materials, and equipment required to install the play equipment complete as specified. The equipment shall be assembled on site as per manufacturing recommendations and this section. All work and equipment provided shall be subject to approval of the City.

    1.03 SHOP DRAWINGS OR CATALOGS:

    Six (6) copies of shop drawings which show complete details will be provided for all items requiring shop fabrication in accordance with Section 2-5.3 of the Standard Specifications.

    1.04 GUARANTEE & LIABILITY INSURANCES:

    A. Manufacturer shall guarantee all materials and workmanship for a period of one (1) year exclusive of vandalism. Manufacturer will be required to provide product liability insurance coverage in the minimum amounts of $1,000,000.00 per incident.

    The Manufacturer will be required to provide complete installation drawings including specifications and a replacement parts list for all products.

    B. Contractor shall provide a written guarantee on his firms letterhead using City format, for

    all materials and workmanship for a period of one (1) year exclusive of vandalism. Written guarantee shall be submitted to the City at the final inspection prior to final acceptance of the work.

    1.05 PROPOSED SUBSTITUTIONS:

    Products proposed for substitution as "equals" to those specified are subject to the approval of the City. If at the time proposed equals are delivered to the site it is determined by the City that they are not equal to those specified, they shall be removed and products as specified provided by the contractor at no additional cost to the City.

    1.06 LOCATION INSPECTION:

    No equipment or apparatus or foundations for same shall be placed until location stakes have been

  • Play Equipment 02461-2

    inspected by the City Representative.

    PART 2 - MATERIALS 2.01 CHILD PLAY STRUCTURE #2:

    Shall consist of custom GameTime play equipment per quote #68488, prepared by Great Western Parks & Playground, (626)705-7134, or approved equal.

    2.02 SAFETY SURFACING

    Shall consist of custom design with TotTurf poured-in-place aliphatic rubber surfacing product, prepared by Great Western Parks & Playground, (626)705-7134, or approved equal.

    PART 3 - EXECUTION 3.01 GENERAL:

    Installation shall be in the approximate locations shown on the drawings. Final approval of precise location by the City is required. In case of conflict between construction plans and manufacturer's requirements, the more stringent shall apply.

    3.02 VANDAL RESISTANCE:

    All fasteners shall be either deformed or tack welded together to prevent unauthorized removal of the fasteners. Paint with galvi-con after deformation/welding.

    3.03 CONCRETE WORK:

    All concrete foundation work shall be performed in accordance with the Standard Specifications, Section 201. Per recommendations listed within the Soils Report, all concrete shall conform to Concrete Class Use Table, Section 201-1.1.3(A), of the Standard Specifications and shall be 658-CME-4500-P (4,500 pounds per square inch ultimate compressive strength at 28 days) unless otherwise noted. Concrete mix shall have a maximum water/ cement ratio of 0.45.

    3.04 CLEAN-UP:

    Project area shall be left clean and orderly upon completion.

    END OF SECTION 02461

  • Site Furnishings 02470-1

    SECTION 02470 - SITE FURNISHINGS PART 1 - GENERAL

    1.01 RELATED DOCUMENTS:

    The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded.

    Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section.

    1.02 SCOPE OF WORK:

    The work included in this section generally consists of providing all labor, equipment and materials necessary to install all site furnishings complete as shown on the plans and as described herein.

    1.03 SUBMITTALS:

    A. Contractor shall submit a written work schedule and cost breakdown for the various elements of the work at the pre-construction conference. Contractor shall also submit a complete list of materials along with manufacturers catalog data for all materials proposed for use in the work as a substitute for those specified herein.

    B. Manufacturer's Product Data: Submit six (6) copies of manufacturer's literature for each

    item of site furnishings.

    C. Submit suppliers certificates attesting that the materials furnished will meet specifications. 1.04 DELIVERY, STORAGE AND HANDLING:

    A. Contractor assumes all responsibility for storage of all materials relative to this project. City assumes no liability for losses or damages from any cause as a result of such storage.

    1.05 JOB CONDITIONS - PROTECTION:

    After slabs are poured and site furnishings are installed, all damage to surrounding turf and/or irrigation system shall be repaired by the contractor at the contractor's expense. All trees and shrubs in and around the project site shall be protected by the contractor and, if damaged, replaced at the contractor's expense. This provision is in effect until acceptance by owner of the complete project.

    1.06 LOCATION INSPECTION:

    No equipment, apparatus or foundations shall be placed until location stakes have been inspected and accepted by the City.

  • Site Furnishings 02470-2

    1.07 GUARANTEE & LIABILITY INSURANCES:

    A. Manufacturer shall guarantee all materials and workmanship for a period of one (1) year exclusive of vandalism. Manufacturer will be required to provide product liability insurance coverage in the minimum amounts of $1,000,000.00 per incident.

    The manufacturer will be required to provide complete installation drawings including specifications and a replacement parts list for all products.

    B. Contractor shall provide a written guarantee on his firm's letterhead for all materials and

    workmanship for a period of one (1) year exclusive of vandalism. Written guarantee shall be submitted to the City at the final inspection prior to final acceptance of the work.

    PART 2 - PRODUCTS 2.01 PICNIC TABLES:

    Shall be Dumor pedestal picnic table, or approved equal. Two styles of this picnic table are used on the project: 1. 4-Seat steel pedestal, model #101-40 2. 3-Seat steel pedestal, model #101-30 All picnic tables are to be black, and receive S-1 permanent embedment support. The picnic tables are available directly from The Wakefield Company (949)552-1130.

    2.02 TRASH RECEPTACLE:

    Shall be Dumor Receptacle 84 model #84-32-FTO with 32 gallon plastic liner, or approved equal. All trash receptacles are to be black, and receive S-1 permanent embedment support. The trash receptacles are available directly from The Wakefield Company (949)552-1130.

    PART 3 - EXECUTION 3.01 LAYOUT:

    Contractor shall stake/mark locations for all slabs and foundations and shall obtain the approval of their location from Landscape Architect prior to commencing any digging. Locations shall be adjusted to provide minimum clear distances required from all edges of slabs, trees, irrigation heads, or other obstructions.

    3.02 CONCRETE WORK:

    All concrete work shall conform with the standard specifications. Contractor shall obtain the approval of all forming from the City Inspector prior to pouring any concrete slabs. Foundations holes shall be inspected and approved by the Inspector prior to pouring concrete.

    3.03 FURNITURE INSTALLATION:

    A. All site furnishings shall be installed with vandal-proof hardware or made vandal-proof (deforming or peening).

  • Site Furnishings 02470-3

    B. Block outs for "after slab installation" will not be allowed. 3.04 CLEAN-UP:

    Contractor shall clean up and legally dispose of all unused materials, excess soil, and debris at regular intervals throughout the duration of the work, and as directed by the City Representative.

    3.05 PROTECTION OF EXISTING IMPROVEMENTS:

    Contractor shall protect all existing improvements from damage.

    END OF SECTION 02470

  • Planting 02480-1

    SECTION 02480 - PLANTING

    PART 1 - GENERAL

    1.00 RELATED DOCUMENTS:

    Drawings, project manual, and general provisions of the Contract, including, without limitations, General Conditions of the Contract, additional General Conditions of the Contract, and specification sections, apply to this section.

    1.01 SCOPE:

    The work required is indicated on the drawings and includes, but is not limited to: soil preparation; finish grading; planting trees; guying and staking trees; planting shrubs and ground cover; sod installation; soil erosion control; maintenance; plant establishment period; guarantees; and replacement.

    1.02 GUARANTEE:

    A. All trees installed under the contract shall be guaranteed against any and all poor, inadequate or inferior materials and/or workmanship for a period of one (1) year.

    B. During the guarantee period, any material found to be dead, missing, or in poor

    condition shall be replaced by the Contractor within ten (10) days of written notification. The City shall be the sole judge as to the condition of the material.

    C. Replacement shall be made in accordance with these specifications and the plans.

    D. Material and labor involved in replacing plant material shall be provided by the

    Contractor at no additional cost to the City. 1.03 INSPECTIONS:

    Inspections will be required. The Contractor shall contact the City at least 48 hours (2 working days) in advance of an anticipated inspection. At a minimum, an inspection will be required at each of the steps listed below:

    A. Upon completion of fine grading, and prior to commencement of soil preparation, for

    acceptance of fine grading work and taking of soils samples. B. Inspection of completed finish grading work per this section following soil amendment

    work. C. When trees are spotted for planting, but before planting holes are excavated.

    D. When planting and all other indicated or specified work has been completed.

    E. During application of pre-emergent chemical.

    F. At start of plant establishment and maintenance period.

  • Planting 02480-2

    G. At the end of the plant establishment period, concurrent with final acceptance of the

    project for maintenance by the City. This acceptance for maintenance will be confirmed in writing by the Landscape Architect and the Citys Representative.

    1.04 AGRONOMIC SOILS TEST:

    Contractor shall notify Landscape Architect upon completion of fine grading and prior to commencement of soil preparation work. The Contractor will obtain agronomic soils tests for all planting areas after completion of fine grading and prior to start of soil preparation work. Tests will be performed by City approved agronomic soils testing laboratory and will include a fertility and suitability analysis with written recommendations for soil preparation, planting backfill mix, auger hole requirements, and post plant fertilization program. The soils report recommendations shall take precedence over the minimum amendment and shall be approved by the Landscape Architect PRIOR to planting in writing, and fertilizer application rates specified herein only when they exceed