specification for neoprene coating on the riser...

17
Specification for Neoprene Coating on the Riser Casing 1of17 Specification for Neoprene Coating on the Riser Casing

Upload: phungquynh

Post on 03-Feb-2018

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        1 of 17 

Specification for Neoprene Coating on the Riser Casing

Page 2: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        2 of 17 

TABLE OF CONTENTS   

1.SCOPE ........................................................................................................................................................3

2.DEFINITIONS............................................................................................................................................3

3.REFERENCES, CODES AND STANDARDS..........................................................................................3

4.CONTRACTOR RESPONSIBILITIES .....................................................................................................5

5.GENERAL SPECIFICATIONS .................................................................................................................5

6.MANUFACTURING AND IN-PROCESS TESTING ..............................................................................8

7.ACCEPTANCE TESTING/QUALIFICATION TESTING.......................................................................10

8.STORAGE, HANDLING AND SHIPPING ..............................................................................................11

  APPENDIX A:  SUMMARY OF TESTS 

APPENDIX B:  VENDOR DATA REQUIREMENTS LIST (VDRL) 

APPENDIX C:  INSPECTION MATRIX 

APPENDIX D:  RUBBER ADHESION TEST FIGURE:  RUBBER ADHESION TEST 

Page 3: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        3 of 17 

1.  SCOPE 

 This specification describes the requirements for material and the application of neoprene coating to the bundle riser casing to serve as the splash zone coating and to serve as vortex suppression strakes  for BP Exploration,  Inc.'s (BPX)  Green  Canyon  Block  200  Field Development Project (Troika). 

 This  specification  shall govern  the materials, application,  inspection,  repairs,  handling  of bare  and  coated  pipe,  and  other requirements  for  the  control  of  external coating  using  neoprene  rubber.    The  work includes the furnishing of all labor, materials, tools and equipment and the performance of all  operations  and  incidentals  necessary  for the coating, handling, storage and shipping of coated  pipe.  Furthermore,  the  work  shall meet  any  additional  requirements  stated elsewhere in the CONTRACT. 

  

2.  DEFINITIONS 

 For  the  purpose  of  this  specification,  the following definitions shall apply: 

 COMPANY:    CONTRACTOR:  The  company,  firm  or 

individual  with  whom COMPANY  enters  into  a CONTRACT  to  which  this specification applies. 

 CONTRACT:  The entire written and signed 

agreement  between  the COMPANY  and CONTRACTOR. 

 

STANDARDS:  Industry  codes,  standards, and  recommended  practices referenced herein. 

 WORKS:  The  location(s)  at  which 

manufacturing,  inspection and testing are performed. 

  2.1  CONTRACTOR REPRESENTATIVE  

Vendor  shall  designate  in  writing  to COMPANY  an  authorized  representative  to serve  as  liaison with  COMPANY  on matters associated with this specification and on the purchase order or CONTRACT referencing this specification.    This  representative  shall  be designated  prior  to  the  performance  of services associated with this specification and the purchase order or CONTRACT referencing this specification. 

  2.2  DOCUMENT PRECEDENCE  

In the event of conflict between documents, the priority shall be as follows: 

 a) Purchase order or CONTRACT b) This specification c) Referenced STANDARDS 

 However,  conflicts  shall  be  reviewed  and resolved  with  COMPANY's  representative prior  to  initiation  or  continuation  of  the services  to be performed  in association with the purchase order or CONTRACT. 

  

3.  REFERENCES, CODES AND STANDARDS 

 The  latest  versions  of  the  following  codes, STANDARDS and guidelines are  incorporated 

Page 4: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        4 of 17 

by  reference, as applicable  in  the context of this specification. 

 a)  American  Society  of  Mechanical Engineers  ANSI/ASME B31.8  Gas  Transmission  and 

Distribution  Piping Systems 

 ANSI/ASME B31.4:  Liquid  Transportation 

Systems  for Hydrocarbons,  Liquid Petroleum  Gas, Anhydrous  Ammonia and Alcohols 

 ANSI/ASME B31.3:  Chemical  Plant  and 

Petroleum  Refinery Piping 

 b)  American Petroleum Institute  

API Spec 5L  Specification for Line Pipe   c)  COMPANY SPECIFICATIONS  

  Specification  for Handling,  Transporting and Storing of Line Pipe 

 d)  Steel Structures Painting Council  

SSPC‐SP‐1  Solvent Cleaning  SSPC‐SP‐5  White  Metal  Blast 

Cleaning  SSPC‐VIS‐1  Pictorial  Surface 

Preparation  for  Painting Steel Surfaces 

 e)  National  Association  of  Corrosion 

Engineers  

RP‐02‐74  Recommended  Practice, High  Voltage  Electrical 

Inspection  of  Pipeline Coatings  Prior  to Installation 

 f)  American  Society  for  Testing  and 

Materials  

ASTM D‐149  Test  Methods  for Dielectric  Breakdown Voltage  and Dielectric Strength  for  Solid Electrical  Insulating Materials  at Commercial  Power Frequencies 

 ASTM  D‐257  Test  Methods 

for  D‐C  Resistance  or Conductance  of Insulating Materials 

 ASTM  D‐412  Standard  Test 

Method  for  Rubber Properties in Tension 

 ASTM  D‐471  Standard  Test 

Method  for  Rubber Property  ‐  Effect  of Liquids 

 ASTM  D‐624  Standard  Test 

Method  for  Rubber Property  ‐  Tear Resistance 

ASTM  D‐1149 Standard  Test Method  for  Rubber Deterioration  ‐Surface Zone  Cracking  in  a Chamber 

 ASTM  D‐2240 Standard  Test 

Method  for  Rubber Property  ‐  Durometer Hardness 

  

Page 5: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        5 of 17 

4.  CONTRACTOR RESPONSIBILITIES 

 CONTRACTOR  shall  obtain  COMPANY's written  approval  for  any  changes  from  the requirements  of  this  specification,  or references,  STANDARDS,  codes,  and drawings.    In  case  of  conflict  between documents, the CONTRACT shall govern. 

 This  document  is  not  intended  to  be  all inclusive, and the use of the requirements set forth herein does not relieve CONTRACTOR of responsibility to perform all services in a safe manner,  to  meet  applicable  codes  and STANDARDS  specified  by  COMPANY,  to comply  with  government  regulations  or  to supply  a  product  capable  of  performing  its intended service. 

 CONTRACTOR  shall  submit a Work Plan one week after the CONTRACT is signed. This plan shall include but is not limited to: 

 QA/QC Plan Coating Procedures Schedule List of Materials and Equipment Location 

  4.1  CONTRACTOR‐SUPPLIED MATERIALS  

CONTRACTOR  shall  supply  all  coating materials  required  for  the  application  of neoprene on the riser casing. 

  4.2  COMPANY‐SUPPLIED ITEM  

COMPANY shall furnish API Spec 5L X‐70 riser casing  line  pipe.    CONTRACTOR  shall  take receipt of  the  line pipe after  inspection and shall notify COMPANY of any discrepancies or damage. 

  

5.  GENERAL SPECIFICATIONS 

  5.1  GENERAL  

The materials used  in  the neoprene  coating shall  have  properties  listed  in  the  following sections. 

 5.1.1  Elastomer  

The  elastomer  shall  be  unvulcanized  pre‐shrunk material.    It shall be compounded  to meet  or  exceed  the  following  properties when vulcanized. 

 Hardness Rating ‐ Shore A Durometer  63 – 68  (ASTM‐2240)  Tensile Strength 2000 psi minimum  (ASTM‐412)  Ultimate Elongation 500% minimum  (ASTM‐412)  Tear Resistance ‐ Angle Tear, Die C 200 lbs./in. minimum   (ASTM‐624)  Ozone Resistance 100 hrs.  (ASTM‐1149) 

412  Water Absorption Volume Change 5% maximum  (ASTM‐471)   Dielectrical Strength Greater than 533 volts/mil  (ASTM D‐149)  Volume Resistivity Greater than 3.25 x 1011 ohm‐cm  (ASTM 

D‐257)  

The  elastomer  materials  shall  be  handled, stored  and  applied  according  to  the manufacturer's  specifications, or  as directed by  an  authorized  representative  of  the 

Page 6: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        6 of 17 

coating  manufacturer.    Each  material container  shall  be  marked  with  a  durable marking  material  to  display  the  date  of manufacturer, material  trade name, number and  batch  number.    Each  batch  of material shall  be  certified  in  writing,  including  the results of property tests that were conducted for quality assurance before packaging. 

 5.1.2  Bonding agents  

The primer and other bonding agents shall be compatible with  the elastomer material and shall  be  as  recommended  by  the  elastomer manufacturer.    Full  descriptions  of  the bonding agents to be used shall be submitted by CONTRACTOR  to COMPANY prior  to use.  The  descriptions  shall  include  a  statement from  the  elastomer manufacturer  as  to  the suitability  of  the  bonding  agents  for  this application. 

 The  bonding  agent  shall  be  handled,  stored and applied according  to the manufacturer's specifications, or as directed by an authorized representative  of  the  bonding  agent manufacturer.   Each material container shall be marked with  a durable marking material to display the date of manufacturer, material name, neoprene rubber and batch number. 

 5.1.3  Tape  

Tape  or  other  exterior  molding  shall  meet with  neoprene  rubber  manufacturer's approval,  and  shall  be  removed  after neoprene rubber has cured. 

 5.1.4  Abrasive  

Material for abrasive cleaning shall be a steel grit  and/or  shot  particle  of  a  size  that  will produce  an  angular  profile  of  not  less  than 2.5  mils  nor  more  than  4.0  mils  in  depth.  Worn  abrasive  shall  be  replaced  with  new material.    The  abrasive  material  and compressed  air  for  blasting  shall  be  free  of 

impurities,  water  and  oil.    Adequate separators, dryers and traps shall be provided and kept air free of condensate. 

5.2  EQUIPMENT AND LABOR  5.2.1  Condition of Equipment  

All  equipment  and  tools  furnished  by CONTRACTOR  shall  be  of  good  quality, maintained  in good operating  condition and suitable  for  use  to  apply materials  required by  this specification.   All equipment shall be subject  to  approval  by  COMPANY.  Equipment  shall  be  capable  of  coating  joint lengths up to 42 feet long. 

 5.2.2  Rubber Wheels  

All  cleaning  and  coating machines  and  pipe moving wheels  or  rollers  shall  be  equipped with  rubber wheels or wheels  covered with hard fiber to prevent marking or denting the pipe.    Knurled  steel  or  other  type  wheels, capable of marking or  indenting  the pipe or coating shall be prohibited. 

 5.2.3  Holiday Detector  

The  electrical  equipment  used  to  test  the coating  shall  be  portable,  low  amperage, adjustable  voltage,  pulse‐type  holiday detector using audible signaling devices.  The holiday detector shall be furnished with a coil spring electrode or a suitable brush‐type and pointed or tipped electrode. 

 5.2.4  Autoclave  

The autoclave shall be capable of vulcanizing the elastomer under raised temperature and pressure.    It  shall  be  large  enough  to accommodate each joint of pipe for curing as a monolithic piece of neoprene 

 5.2.5  Labor  

Page 7: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        7 of 17 

CONTRACTOR  shall  provide  supervision  and labor  for  the  entire  coating  operation  from the time of receiving the pipe to  loading out for transport.  CONTRACTOR shall provide the necessary facilities for COMPANY supervision and inspection of all the work. 

  5.3  SURFACE PREPARATION  5.3.1  Preparation for Blasting  

Before blast cleaning, external  surfaces shall be  inspected  and  pre‐cleaned  according  to SSPC‐SP‐1  to  remove oil, grease and  loosely adhering  deposits.    Visible  oil  and  grease spots  shall  be  removed  by  solvent  wiping.  Only  COMPANY  approved  safety  solvents which do not  leave  a  residue  shall be used.  Pipe  ends  shall  be  protected  by  plugs  to prevent  entry  of  abrasive  inside  the  pipe during blasting.  Any abrasive that gets inside the pipe shall be removed before coating. 

 5.3.2  Preheating  

There is no preheating requirement.  5.3.3  Blasting  

The  pipe  surface  to  be  coated  shall  be cleaned  to a  "White Metal"  finish according to  SSPC‐SP‐5.    The  blast  pattern  shall  be  a uniform,  angular  anchor  profile  with  a minimum depth of 2.5 mils to a maximum of 4.0  mils.    For  consistent  surface  finish,  a stabilized working mix of the cleaning media shall  be  maintained  by  frequent  small additions  of  a  new  grit  commensurate with consumption.    Infrequent  large  additions shall be avoided.  The cleaning media working mix  shall  be  kept  clean  of  contaminants  by continuous  effective  operation  of  blasting machine scalping and air wash separators. 

 5.3.4  After Blasting  

After  blast  cleaning,  the  pipe  surface  to  be coated  shall  be  examined.    All  surface imperfections,  such  as  slivers,  scabs,  burrs, weld splatter or gouges shall be removed by grinding.  Grinding is only allowed in so far as it will  not  reduce  the wall  thickness  of  the pipe to less than 92% of its nominal specified wall thickness.   Pipe that cannot be repaired or  that  is  dented  shall  not  be  coated.    All ground  areas  shall  be  blasted  again  to  the above requirements. 

 After blasting,  the  inside and outside of  the pipe  shall be  left  clean  and  free of abrasive materials, dust or other blasting  residue.   A brush  off  air  blast  or  vacuum  type  cleaner shall be used to clean the entire pipe. 

 The cleaned pipe surfaces shall be protected from  conditions of high humidity,  rainfall or surface moisture.   The  cleaned pipe  surface shall  be  coated within  two  hours  after  it  is cleaned, and shall not be allowed to flash rust before coating.   Total elapsed time between grit blasting and coating of the blast cleaned surface shall be kept to a minimum to avoid the formation of oxides on the surface. 

  5.4  COATING APPLICATION  5.4.1  Application of Bonding Agents and Elastomer  

The  primer  shall  be  applied  as  soon  after blasting  as practicable but never more  than two hours after blast cleaning.   Care shall be taken  to  ensure  that  the  condition  of  the metal surface remains as per SSPC‐PC‐5 until it  is  primed.    Another  blasting  shall  be required  if  these  conditions  are  not  met.  From blasting on  through  the  application of bonding agents and elastomers, the pipe shall be kept at  least 5 degrees F above  the dew point. 

 The  application  of  the  bonding  agents  and elastomer  shall  be  performed  according  to 

Page 8: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        8 of 17 

the manufacturers'  recommendations.    If an extruded  coating  process  is  used  in  the application,  batch  changes  on  any  one  pipe joint shall not be allowed. 

 CONTRACTOR  shall  submit  comprehensive procedures  for  the  proposed  operations  to COMPANY for approval prior to application. 

 5.4.2  Vulcanizing  

Vulcanizing shall take place within eight hours of elastomer application.   Elastomer shall be vulcanized  in  an  autoclave  using  a combination of temperature and pressure as recommended  by  the  elastomer manufacturer.   CONTRACTOR  shall  submit  a complete  description  of  the  procedure  for the vulcanizing to COMPANY prior to coating. 

 5.4.3  Dimensions  

The pipe shall be coated with a 1.0‐inch thick neoprene and shall have a cut back of six (6) inches  from  each  pipe  end.    Each  coating edge shall be beveled at a 90 degree angle. 

  5.4.4  Field Joints  

CONTRACTOR  shall  supply  COMPANY  with sufficient  quantities  plus  10  percent  waste allowance of neoprene wrap around sleeves, bonding agents and tape to be used for field joint coatings.  The wrap around sleeves shall be of the same material and thickness as the elastomer  applied  to  the  pipe.    The circumferential  edge  of  the  wrap  around sleeve shall have an overlap of three  inches.  The  minimum  width  of  the  wrap  around sleeve shall be 12  inches wide to completely cover  the  cut  back  area  for  the  pipe  field joint. 

 The  two  part  bonding  agent  shall  be  3M company  B/A  2216  epoxy  adhesive  quick hardening type able to set in one hour at the 

application  temperature,  with  maximum bond strength achieved in 24 hours. 

 The tape shall be suitable for this application according  to  the  adhesive  manufacturer's specifications.    CONTRACTOR  shall  provide application  procedures  and  temperature ranges.  The tape shall be able to temporarily hold the wrap around sleeves in position until the  bonding  agent  hardens.    The  tape  shall then be removed. 

 5.4.5  Repairs  

Coating  defects  from  visual  inspection, hardness  tests,  sounding  tests,  thickness measurements, bond  tests, holiday detector and  obvious  mechanical  damage  or  other defects  shall  be marked  by  chalk  or  crayon and repaired by CONTRACTOR. 

 Procedure  for  the  repair  of  coating  defects shall  be  approved  by  COMPANY  before starting  work.    All  repairs  shall  be  at  the discretion of COMPANY and only two repairs are allowed per pipe  joint.   No defect  larger than  one  square  foot  is  eligible  for  repairs.  Repairs  shall  be  as  good  as  the  rest  of  the coating  and  meet  the  provisions  of  this specification.   Repairs  shall  satisfy  all of  the tests of this specification except the adhesion test.   Repairs  that  fail  the  tests are  rejected and the entire joint coating is to be removed and new coating applied. 

  

6.  MANUFACTURING AND IN‐PROCESS TESTING 

  6.1  INSPECTION AND TESTING  6.1.1  COMPANY Access for Inspection  

COMPANY  representatives  shall  be  given ready  access  to  inspect  the  CONTRACTOR's 

Page 9: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        9 of 17 

quality  control  procedures,  methods  and results  for  the  coating materials, equipment and CONTRACTOR's work. 

 All stages of the work shall be subject to full time inspection by COMPANY or COMPANY's representative.    Such  inspection  shall  not relieve CONTRACTOR of  the responsibility to provide materials  and  workmanship  to  this specification. 

 6.1.2  Inspection of COMPANY Supplied Pipe  

Upon  receipt  of  line  pipe  or  pipe  bend material  supplied  by  COMPANY, CONTRACTOR  shall  perform  a  thorough inspection.  Any damage to the material such as  dents,  gouges,  buckles,  ovalization  or damage to the weld bevels shall be recorded against the pipe mill number and reported to COMPANY. 

 COMPANY  may  request  CONTRACTOR  to make  repairs  at  COMPANY's  expense  or instruct  CONTRACTOR  to  set  aside  and  not coat  pipe  pending  COMPANY's  further instructions. 

 Any  damage  discovered  during  subsequent stages of the coating or inspection operations shall be made  good by CONTRACTOR  at his expense. 

 6.1.3  Joint Identification  

For  each  joint  of  pipe,  the  following measurements,  information  and  pipe identification  shall  be  recorded  before coating operations start. 

 • Pipe mill number   • Joint length   • Weight of bare pipe   

• Any  other  information  stenciled  on  the outside or inside of the pipe 

 If the pipe mill number is not stenciled on the inside of  the pipe  it  shall be paint  stenciled there before coating.  Pipe joint identification and  pipe  bend  marks  according  to  the drawings  shall  be  paint  stenciled  on  the neoprene coating. 

 6.1.4  Blasting Cleaning  

Inspection of  the blasted surface shall be by comparison to the white metal blast cleaning standards in SSPC‐VIS‐1. 

  6.2  TESTING OF ELASTOMER MATERIALS  

Prior to use, the elastomer shall be tested to the requirements as noted below: 

 Hardness Rating 63 ‐68  Shore A Durometer (ASTM‐2240)  Tensile Strength (ASTM‐412) 

2000 psi minimum    Ultimate Elongation (ASTM‐412) 

500% minimum  Tear Resistance, Die C   200 lbs/in minimum 

(ASTM‐624)  

Each  batch  of  elastomer  or  fraction  thereof shall be  tested.   A batch  shall be defined as one load of the mixer used to compound the material or 700  lbs. whichever  is  less.   Three samples from each batch shall be tested.  

 Previously,  run  test  documents  shall  be submitted  to  COMPANY  to  show  that  the elastomer  compound  to  be  used meets  the following requirements: 

 Ozone Resistance    100 hours    (ASTM‐1149)  

Page 10: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        10 of 17 

Water Absorption, Volume Change 5% maximum(ASTM‐471) 

 Tests for the batch tests and the certification tests  shall  be  performed  on  cured  samples.  All  tested  samples  shall meet or exceed  the specified  requirements.    Test  certificates  as per  ASTM  standards  shall  be  provided  to COMPANY  for  approval  prior  to  use  of  the elastomer material. 

   

7.  ACCEPTANCE TESTING/QUALIFICATION TESTING 

  7.1  VISUAL INSPECTION  

The  coating  shall  be  inspected  for imperfections,  lack  of  bond  at  joints  and ends,  blister,  lamination  and  any  apparent irregularity.  Any visually detected flaws shall be clearly marked with a waterproof crayon or marker  using  a  contrasting  color  to  the coating. 

 COMPANY  has  the  right  to  accept,  reject, request  repairs  or  require  further  tests  at CONTRACTOR's expense. 

  7.2  SOUNDING  

The  coating  shall  be  sounded  with  a  two pound  hammer  over  its  entire  length  along lines  spaced  every  foot  around  the circumference or every 90 degrees whichever is  less.   The hammer shall be brought to the elastomer surface through a vertical height of at  least  three  feet  with  a  minimum  of additional  acceleration.    CONTRACTOR  shall exercise caution when hitting the hammer on the pipe so as not to damage the neoprene or causing  loss of bond at  the point of  impact.  Coating  should  produce  a  uniform  pitch 

everywhere.    Any  marked  difference  in audible  pitch  or  rebound  response  of  the hammer shall be noted and the area marked as for visual flaws. 

 COMPANY  has  the  right  to  accept,  reject, request  repairs  or  require  further  tests  at CONTRACTOR's expense. 

  7.3  COATING HOLIDAY INSPECTION  

The entire coating shall be electrically spark‐tested  to detect  faults such as voids, cracks, thin spots or  foreign  inclusions.   The coating shall be tested using a coiled electrode except for the coating seams or joints which shall be tested with a pointed or tipped electrode. 

 The  test  voltage  shall be according  to NACE Standard RP‐02‐74 with a minimum of 15,000 volts.  The detector voltage shall be adjusted at least twice each shift because of the many variables such as temperature and humidity, e.g. one adjustment is to done in the morning and  another  before  starting  work  in  the afternoon.  The equipment shall be grounded according  to  the  equipment manufacturer's instructions  for  proper  inspection  of  the voltage. 

 Any  failure  of  the  coating  to  pass  holiday inspection  shall  result  in  rejection  by COMPANY  of  that  section  of  the  coating.  Rejection  will  require  either  complete recoating  or  repair  at  CONTRACTOR's expense. 

  7.4  THICKNESS MEASUREMENT  

Thickness  will  be  calculated  with  a  PI  tape measurement  and/or  caliper measurement.  Pipe will be  concentric within  the neoprene coating  because  coating  is  applied  in  sheet form and calendared to close tolerances. 

 

Page 11: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        11 of 17 

 7.5  HARDNESS TEST  

Hardness  tests  shall  be  taken  at  the  same locations  as  the  coating  thickness measurements.  Tests shall be comparable or calibrated  to match Shore A durometer  test specified  for  the  coating  material.    Tests results shall be within the range of 63 to 68 to be satisfactory. 

  7.6  RUBBER ADHESION TEST  

CONTRACTOR shall perform rubber adhesion tests as described in Appendix A. 

 CONTRACTOR shall perform rubber adhesion tests on at  least  two  joints of pipe  for each autoclave batch of neoprene. 

 Tests  that  fail  will  require  two  additional successful  tests  to  be made  from  the  same batch of neoprene. 

  7.7  FIELD JOINT ADHESION TEST  

CONTRACTOR  shall  prepare  a  Field  Joint Adhesion  Test  with  the  same  cleaning  and application  steps  that  will  be  performed  in the  field  construction.    Visual,  sound, hardness  and  tearing  tests will  be  done  on the field  joint  in the same way as  is done on the neoprene coated pipe and with the same test  requirements  to  be  satisfactory.  On successful  completion  of  the  test, CONTRACTOR  shall  prepare  a  written procedure for field joint application. 

  

8.  STORAGE, HANDLING AND SHIPPING 

 Pipe shall be handled and stored in a manner to  prevent  damage  to  pipe  walls,  beveled ends  and  coating  according  to  COMPANY 

Specification  No.SP‐051.    All  pipe  handling shall  be  with  equipment  approved  by COMPANY.    Pipe  or  coating  damaged  by CONTRACTOR  pipe  movements  shall  be repaired or replaced by CONTRACTOR to the satisfaction of COMPANY. 

 The coated pipe shall be stacked so that the exterior coating  is not  in contact with a hard surface which  could  cause  coating  damage.  Stacking height is limited to the restrictions of the  coating.    The  height  may  be  further reduced by COMPANY  if  there are observed effects to the pipe or coating due to stacking. 

 Pipe  will  be  transported  from  the  coating yard to the  job site by truck, rail or barge as specified  in  the  CONTRACT.    Pipe  shall  be transported  in  a  way  that  will  protect  the pipe and its coating.  Pipe shall be loaded for safe  shipping  according  to  existing  shipping standards and regulations. 

 The  field  joint  materials  consisting  of  the wrap around sleeves, two part bonding agent and  tape  shall  be  packed  in  boxes  and/or pallets  with  a  waterproof  outer  cover.  The packing  shall  be  suitable  for  transport  by truck and barge for storage at the fabrication site prior to use in the piping installation. 

  9.  PERFORMANCE OF WORK  

CONTRACTOR  shall  guarantee  that  work performed  on  external  coating  of  pipe  shall be  according  to  this  specification.  CONTRACTOR  further  guarantees  the application  of  the  coating  system  shall  be according to the specifications of the material manufacturer.    COMPANY  shall  have  full access rights to the CONTRACTOR's plant and property to observe that these specifications are being followed. 

Page 12: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        1 of 17 

APPENDIX A SUMMARY OF TEST REQUIREMENTS 

 Table 1 ‐ Elastomer Material Qualification/Acceptance Tests 

Hardness Rating 

Tensile Strength 

Ultimate Elongation 

Tear Resistance 

Ozone Resistance 

Water Absorption 

{Sec. 5.1.1, 6.2} 

{Sec. 5.1.1, 6.2} 

{Sec. 5.1.1, 6.2} 

{Sec. 5.1.1, 6.2} 

{Sec. 5.1.1, 6.2} 

{Sec. 5.1.1, 6.2} 

  

Table 2 ‐ Frequency of Tests Performed on Neoprene Bends coated Pipe 

Visual Inspection 

Sounding  Holiday Inspection 

Thickness  Hardness Test 

Rubber Adhesion Test 

Field Joint Adhesion Test 

 All coated joints 

2 joints for each autoclave 

batch 

1 successful field joint 

{Sec. 7.1}  {Sec. 7.2}  {Sec. 7.3}  {Sec.7.4}  {Sec. 7.5}  {Sec. 7.6}  {Sec. 7.7} 

  

Page 13: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        1 of 17 

APPENDIX B VENDOR DATA REQUIREMENTS LIST (VDRL) 

  CLIENT:   ___________________________________   P.O./S.C. NO.: _______________________  LOCATION:  Gulf of Mexico______  SELLER/SUBCONTRACTOR: ____________________________  EQUIPMENT TAG NO.(S): __________________________________________________________  DESCRIPTION(S):  Neoprene Coating _________________________________________________  The seller's/subcontractor's quotation shall state his intended compliance with this listing, as regards to the type of data required and schedule for data submittal, as well as the quantity and data form (reproducible, prints, etc.) indicated in the inquiry and purchase order/subcontract standard clauses.  The seller/subcontractor shall confirm responsibility for similar compliance by his subvendors and/or subcontractors.  As a part of  the seller's/subcontractor's quotation, any deviation(s)  from  the data submittal schedule shall be shown in the comments column.  All data submitted shall be  identified with equipment tag number, equipment description, buyer's job number, and purchase order/subcontract number.  AFTER ORDER IS PLACED, UNLESS OTHERWISE NOTED IN THE COMMENTS COLUMN, the following data submittal schedule shall apply:  

FOR  APPROVAL  DATA  DUE    3    WEEKS  AFTER  PURCHASE  ORDER/SUBCONTRACT  IS  PLACED, 

CERTIFIED CORRECT DATA DUE     4   WEEKS AFTER BUYER'S APPROVAL, RECORD DATA DUE   8  

WEEKS AFTER PURCHASE ORDER/SUBCONTRACT IS PLACED. 

ABBREVIATIONS:  Q = With Quotation, A = Approval, C = Certified, R = Record, P = Prints, RP = Reproducible, M = Microfilm, S = Shotdown 

Page 14: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        2 of 17 

VENDOR DATA REQUIREMENTS LIST (VDRL)   Data      Data Required Code  Data Description/Definition  Q  A    C  R  Comments  

Coating Schedule  3P  6P    6P 

QA/QC Plan  3P  6P    6P 

Surface Preparation Procedure    6P 

Coating Procedure    6P 

Repair Procedure    6P 

Material Certificates    6P 

Visual Inspection    6P    6P 

Sounding Inspection    6P    6P 

Holiday Inspection    6P    6P 

Thickness measurement    6P    6P 

Hardness Test     6P    6P 

Rubber Adhesion     6P    6P 

Field Joint Adhesion Test    6P    6P 

 

Page 15: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        1 of 17 

 APPENDIX C 

INSPECTION MATRIX  

 APPROVAL/DATE:  INSPECTION LEVEL:  C 

 

 SPECIFICATIONS/CODES/STANDARDS:  See Section 3 of this specification.  Other Sections/Paragraphs listed below are references to information with this specification. 

 INSPECTION LEVEL:  A = Pre‐Coating Meeting, Regular In‐Process 

Insp. Witness Tests, Final Insp., Doc. Review 

 B = One or More In‐Process Insp., Witness 

Tests, Final Inspection, Doc. Review   C = Witness Tests, Final Insp., Doc. Review   D = No Inspection, Review Vendor Submitted 

Documentation (if applicable)  INSPECTION ACTIONS:  1 = Observe/Verify by Inspection 2 = Review of Documentation 3 = Obtain Certification/Test Documents               

 

Page 16: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        2 of 17 

 

INSPECTION MATRIX  

  ACTIVITIES  1  2  3  COMMENTS 1  Precoating Meeting    X    QA Inspector to attend 2  Specification    X    Sec. 5 3  QA/QC Inspection Plan    X    Sec. 4 4  CONTRACTOR's Inspection of Line Pipe & 

Bends   X    Ref. Sec. 4.2 

5  Facilities & Equipment    X    Ref. Sec. 4 6  Coating Procedure  X  X    Sec. 4 7  Material Certificates    X  X  Ref. Sec. 4, 6.2 8  Surface Preparation    X  X  Ref. Sec. 5.3 9  Hardness Test  X  X  X  Ref. Sec. 7.5 10  Visual Inspection  X  X  X  Ref. Sec. 7.1 11  Sounding  X  X  X  Ref. Section 7.2 12  Coating Holiday Inspection  X  X  X  Ref. Section 7.3 13  Thickness measurement  X  X  X  Sec. 7.4 14  Rubber Adhesion  X  X  X  Sec. 7.6 15  Field Joint Adhesion Test  X  X  X  Sec.7.7 16  Preparation for Shipment  X  X    Ref. Section 8 17  Release for Shipment  X  X  X  QA Rept. to Release  

 

Page 17: Specification for Neoprene Coating on the Riser Casingengineering-experts.com/.../Specification_for_Neoprene_Coating_on... · Specification for Neoprene Coating on the Riser Casing

Specification for Neoprene Coating on the Riser Casing        1 of 17 

APPENDIX D RUBBER ADHESION TEST 

 Ref. ASTM D‐429 Method E, 90� Peel Test 

  The following procedure has been modified slightly from ASTM D‐429 Method E to allow testing on the actual coated pipe rather than laboratory prepared samples:  1. At one end of the pipe, on the 6" cut back length, prepare an area approximately 6 inches square in the 

same manner as the rest of the pipe is prepared to receive the neoprene coating.  This shall include the blast profile, primer application and cement application. 

 2. Apply a 4" long strip of 1" wide pressure sensitive tape running with the length of the pipe and near the 

edge of the prepared test area.   3. Using the same material as specified for the regular coating, apply an unvulcanized neoprene slab 2" wide 

x 5" long x 1/4" thick to the pipe on the prepared test area.  Orient the slab in such a manner that the 5" length  runs along  the  circumference of  the pipe and  that one end  just overlaps  the 1" wide pressure sensitive tape.  Pressure roll the neoprene slab to ensure intimate contact with the pipe. 

 4. Wrap  the  test  slab  tightly with nylon  tape  in  the same manner as  the  regular coating and cure  in  the 

autoclave.    5. After the pipe has been cured and the nylon tape removed, make two cuts in the test slab, parallel, one 

inch apart, running with the circumference, the full  length of the test slab.  The cuts should be through the full thickness of the test slab with the resulting 1" wide test strip centered on the slab. 

 6. Separate the 1" wide test strip at the masked end (pressure sensitive tape) and carefully peel the strap up 

a sufficient distance until the jaws of a suitable test clamp can be attached.   7. With a spring scale attached to the test clamp, pull the test strip with a 90� angle to the surface of the 

pipe.    Increase  the  force until  the  test  strip begins  to peel  away  from  the pipe.   The minimum  force required to maintain a uniform peel of the test strip from the pipe shall be 35 lbs. 

 8. After the test is completed, the neoprene slab shall be cut away from the pipe and the residue buffed off 

leaving the cut back on the pipe as originally specified