specification for foundation fieldbu essar

31
SPECIFICATION FOR FOUNDATION FIELDBUS INDEX CLAUSE DESCRIPTION PAGE 1 Scope 4 2 Conflicts and Deviations 4 3 References 4 4 Definitions 5 5 System Design 6 6 Wiring Design 7 7 Fieldbus Devices 12 8 Non-Device Element Selection 13 9 Host Requirements 15 10 Consideration For Detail Engineering 18 11 Documentation 18 12 Factory Acceptance Test (FAT) 20 13 Site Acceptance Test (SAT). 21 14 Installation and Checkout 21 15 Maintenance Shop Fieldbus System and Tools Level Update 21 16 Fieldbus Spare Parts and Revision Program 22 17 Foundation Fieldbus Training 22 Annexure A Fieldbus Glossary of Terms 25

Upload: viotani4812

Post on 15-Apr-2016

214 views

Category:

Documents


0 download

DESCRIPTION

x

TRANSCRIPT

Page 1: Specification for Foundation Fieldbu Essar

SPECIFICATION FOR FOUNDATION FIELDBUSINDEXCLAUSE DESCRIPTION PAGE1 Scope 42 Conflicts and Deviations 43 References 44 Definitions 55 System Design 66 Wiring Design 77 Fieldbus Devices 128 Non-Device Element Selection 139 Host Requirements 1510 Consideration For Detail Engineering 1811 Documentation 1812 Factory Acceptance Test (FAT) 2013 Site Acceptance Test (SAT). 2114 Installation and Checkout 2115 Maintenance Shop Fieldbus System and Tools Level Update 2116 Fieldbus Spare Parts and Revision Program 2217 Foundation Fieldbus Training 22Annexure A Fieldbus Glossary of Terms 25

Page 2: Specification for Foundation Fieldbu Essar

1 SCOPE

The use of FOUNDATION™ Fieldbus based control system is to be followed in the Refinery expansion project of Essar Oil Limited, Vadinar, Jamnagar.

This specification defines the requirement for design, specification, installation, configuration; commissioning and maintenance for FOUNDATION™ Fieldbus based control systems.

The specification covers the minimum requirements for the design and installation of H1 Foundation Fieldbus (FF) system based on 31.25 kbps physical layer as defined in ISA 50.02

This specification is intended for use by Detail engineering contractor and by Control System vendor for integrated services.

FOUNDATION™ Fieldbus systems include instruments and host that covers all applications and aspects of instrumentation and control.

A FOUNDATION™ Fieldbus based control system shall not be used for the following systems

• Emergency Shutdown System• Fire and Gas System,• Burner Management System,• Compressor Anti-surge Control System• Close Loop Control with scan time faster than 300 msec.• Discrete Motor Monitoring & Control System• Complex Control loops with multiple maths function• Instruments commercially not available (Nucleonic Instruments)• Packages Control System

2 CONFLICTS AND DEVIATIONS

Any conflicts between this Specification and other applicable Engineering Standard, Materials System Specifications, Standard Drawings, or industry standards, codes, and forms shall be resolved in writing by the Essar Engineering Centre, Mumbai.

3 REFERENCES

3.1 Essar Engineering Centre References

3.2 Industry Codes and Standards

The International Society for Measurement and Control (Refer latest standards)

ISA 5.1 Instrumentation Symbols and IdentificationISA 50.02, Part 2 Fieldbus Standard for Use in Industrial Control Systems, Part

2: Physical Layer Specification and Service DefinitionFF-569 FOUNDATION™ Fieldbus Host Interoperability Support Test ProceduresFF-816 FOUNDATION™ Specification 31.25 kbits/s Physical Layer ProfileFF-890 FOUNDATION™ Specification Function Block Application ProcessAG-163 FOUNDATION™ Application Guidelines for 31.25kbps & IS SystemAG-181 FOUNDATION™ System Engineering Guidelines.AG-140 FOUNDATION™ Application Guidelines for 31.25kbps & wiring system

Page 3: Specification for Foundation Fieldbu Essar

FF 940 FOUNDATION™ Communication ProfileIEC61158-2 Digital data communication for measurement and control

fieldbus for use in Industrial control system Part 2 through Part 6

IEC60079-27 Electrical apparatus for explosive gas atmosphere Part-27: Fieldbus intrinsically safe concept (FISCO) and Fieldbus non-incendive concept (FNICO)

NFPA 70 National Electrical Codes (National Fire Protection Association)

4 DEFINITIONS

All definitions of Fieldbus terms and acronyms used in this document can be found in appendix 'A'.A typical fieldbus segment that shall consist of the following components, reference Figure 1:

• H1 - Foundation Fieldbus Interface Card (Redundant)• FFPS - Foundation Fieldbus Power Supply (Redundant)• JB - Junction Box• BPS - Bulk power Supply (24 V DC) (Redundant)• FBB - Foundation Fieldbus Barrier• HPT - High Power Trunk• Fieldbus Devices, (e.g., transmitters, transducers, Temp Multiplexers etc.)

Figure 1 – Fieldbus Segment Components

Live Service not allowed on trunk upto last JB

5 SYSTEM DESIGN

The philosophy of selection, design and application of process instrumentation on Foundation Fieldbus shall be based on intrinsically safe (IS) installation in hazardous areas. The High Power Trunk (HPT) design shall be adopted which by definition of the HPT is a technique that combines different safety techniques to allow high power on the trunk and intrinsically safe or energy limited output on the spurs.

The HPT approach meets the intrinsically safe EEx ia FISCO requirement at the field device level and uses increased safety techniques (EEx e) for the trunk. This combination of safety techniques allows the

Page 4: Specification for Foundation Fieldbu Essar

full implementation of 32 devices, 1900 m total cable length (Trunk + Spur) with type A cable, 100 m maximum spur length without compromise, even when connecting to FISCO field devices.

The HPT design for intrinsically safe applications uses the Fieldbus barrier that is situated within an EEx e enclosure taking its power from 2-wire field bus trunk and behaves like a 4 output EEx ia FISCO power supply. As the trunk uses EEx e safety techniques for its protection, conventional fieldbus supplies can be used, providing typical outputs in the region of 24-32V at 350 mA - 500 mA.

The use of conventional fieldbus supplies enables the provision of true redundancy for both the H1 host and the power supplies, ensuring system availability in the case of failure. By using conventional fieldbus supplies, Advanced Diagnostics on the fieldbus physical layer also becomes available, providing predictive maintenance on a part of the installation that typically causes most problems.

The fieldbus barrier design concept shall ensure the following:

1. Intrinsic safety on the outputs (spurs)2. Galvanic isolation between the non IS fieldbus segment (Trunk) and the IS fieldbus segment (spurs) and between the output circuits. The Trunk is galvanically isolated from the outputs.3. Fieldbus terminator connected at both end of the FF trunk.

FF design should be followed for all monitoring & Control loops. For skin temperature monitoring FF multiplexer shall be used.

5.3 Basic Segment Loading Requirements

Note: Prior to defining Fieldbus segments, the process control strategy should be complete, the P&ID’s available, instruments selected, and instrument locations determined.

Redundant H1 Interface cards shall be used for all segments.Each segment shall have an enabled backup Link Active Scheduler (LAS) in a field transmitter device.Note: The preferred location of the backup LAS is in a monitoring only (i.e., not used for control) fielddevice.The 'primary' LAS shall reside in the H1 interface card.

5.4 Segment Executions Time

The suggested number of devices per segment, for monitoring shall be limited to twelve (12) devices.

Each segment shall operate with a single specified macrocycle execution time. Multiple macrocycles shall not be used on a single segment, even if available in a vendor's particular product.

The vendor's configuration software shall automatically allocate sufficient unscheduled (free asynchronous) time as required by the vendor.

Notes: Function block execution frequencies must be compatible with both system loading and process control objectives. The execution frequency of all function blocks contained within a single fieldbus segment is defined by that segment's macrocycle time. This macrocycle time, which can typically range from 250ms to several seconds (depending on the nature of the application), is configured for each fieldbus segment. Some vendor's configuration products allow devices on the same segment to operate at different macrocycle times.

However, backup LAS devices are not capable of managing these multiple macrocycles, so this feature may not be used. The order of execution should be automatically determined by the vendor's configuration software, based on the connections between function blocks on the fieldbus segment.

Page 5: Specification for Foundation Fieldbu Essar

Note that the macrocycle contains unscheduled time required for non-deterministic bus communications, such as alarm transmission, set point changes, etc. The vendor's recommended unscheduled time should be allocated for each macrocycle. Note that the minimum may change based on how much bus required communication is configured as deterministic. While it is hoped that the vendor's configuration software will manage and maintain minimum unscheduled time, this is not necessarily true, and must be verified.

Network \ Segment Execution Time.

The network/segment macro cycles should match the DCS module execution times. Each network/segment should operate with a single specified macro cycle execution time. Multiple macro cycles shall not be used on a single network/segment without the approval of Client. Care should be to ensure that the network does not become overloaded.

Use a default segment execution time of one (1) second unless otherwise approved by the Client. Further guidance on segment times is given below.

Network/Segment Execution Time

The network/segment macro cycles should match the module execution times.

Macrocycle

The Macrocycle should have minimum of 50% unscheduled (free asynchronous) time. The unscheduled time Calculation shall allow for spare capacity requirement. Therefore newly commissioned segment should have minimum of 50% unscheduled time.

The suggested maximum numbers of devices per segment for the following listed execution times are as Follows:

• For segments with monitor only measurements, limit segment to twelve (12) devices. (10 in use + 2 Spare)

• For loops requiring 1-second macrocycle time, limit segment to twelve (12) devices with 4 valves. (6 TX+ 4 CV+ 2 SPARE)

• For loops requiring 0.5-second macrocycle time, limit segment to six (6) devices with 2 valves. (2 TX+ 2 CV+ 2 SPARE)

• For loops requiring 0.25-second macrocycle time, limit segment to three (3) devices with 1 valve. (1 TX+ 1 CV+ 1 SPARE)

Typically

• 1 Second macro cycle time to be considered for all parameters other than temperature monitoring• 2 Second macro cycle time to be considered for temperature monitoring points• Each macro cycle should have a minimum of 50% unscheduled time with allowances for spare

capacity Requirement

In line with the above the segment loading philosophy:

Typical calculation for MUX- Assuming each MUX has a macro cycle time of 8 x 32 msec = 256 mSec, Max of 4 MUX shall be

connected to each segment having 2 sec macro cycle time. (They can be connected to any FBB).Each MUX shall be connecting to 6 elements (T/c or RTD’s – 2 spare channels left for future elements).No other FF devices shall be assigned to this segment.

- Assuming each FF device other than MUX has a macro cycle time of 40 mSec, for 12 FF devices, the scheduled time shall be 12 x 40 = 480mSec. Hence 12 FF devices can be accommodated in

Page 6: Specification for Foundation Fieldbu Essar

each segment with a 1 sec macro cycle time. As defined in the FF design spec, 10 devices are to be considered per segment with 2 as future spare.

- Generally, MUX will not be combined with other FF devices in the same segment, however, if a situation arise where combination of FF devices and MUX would be required, the loading of the devices shall follow the Segment macro cycle time of 1 second.In such a case, there shall be 1 MUX + max of 6 other FF devices (Including 2 futures spare). Accordingly the total cycle time would be 1 x 256 mSec + 6 x 40 mSec = 496 mSecs.

5.5 Control Element Definition (FF Loop Criticality)

• Criticality Level 1

Failure of a Level 1 valve will result in a total system trip, causing a shutdown of the entire unit, or other Unavoidable losses in excess of $10M. Normal Valve failure mode is to be used for this classification.

Application: Level 1 positioners with their associated measurement device shall reside on H1 Segment with no other Control loops. Additional monitoring devices may be allowed.

• Criticality Level 2

Failure of a level 2 valve will result in a total system trip, causing a shutdown of the entire unit, or other Unavoidable losses in excess of $100K. However, the Level 2 valve’s process dynamics allow time for quick recovery from the failure, either by quickly fixing a fault or by taking manual control. The material and energy capacity of associated vessels, geographic location, and elevation/accessibility of such valves should be considered. The difference in Level 1 and 2 valves are dependent on operations ability to respond to a single Failure.

Application: Level 2 positioners with their associated measurement shall reside on H1 Segment with no other Level 1 or Level 2 Positioners and can have one Level 3 Positioner. (i.e. Total of 2 Positioners maximum).

• Criticality Level 3-Failure of this valve will not result in any short-term risk of total unit shut down or major operating losses. Level 3 valves can go to their fail position without requiring immediate operator action.

Application: Level 3 positioners with their associated measurement shall reside on H1 Segment, up to 2 other level 3 Positioners (i.e. Total of 3 off level-3 positioners maximum). Consideration should be given to the impact of common mode failure on the same segment. Regulatory control loop associated with “ spared” vital and essential equipment should be allocated on different segment.

• Criticality Level 4- No Control

Failure of this Level 4 devices are measurement only devices that shall not be used for control and may be configured in a way that could interrupt control on a network/segment. This class includes MAI, MAO, MDI, and MDO block communication devices.

Application: All Open Loops shall reside on H1 Segment, up to maximum of 12 (10 in use+ 2 Spare) devices per segment

5.6 FF Control Module & Function Block Naming

Each Fieldbus control strategy or module will be named based on a reasonable and consistent format for the facility. The naming convention shall be reviewed by Essar Engineering Centre.5.6.2 Unless specified differently, each FF function block shall use a field device tag name for its maindescriptive =name and a 'suffix' defining the function or block type for which it is defined

Page 7: Specification for Foundation Fieldbu Essar

(e.g., FT5010_AI, FT5010_AO, etc.).5.6.3 In the event that a FF device has more than one identical function block, each shall be uniquely identified witha sequential numeral(e.g., FT5010_AI_1, FT5010_AI_2, etc.).6 WIRING DESIGN6.1 SEGMENT TOPOLOGYThe fieldbus installation shall use the 'tree', or 'combination' topology as shown in Figure-2. The ‘spur’ and‘daisy chain’ topology (i.e., routing the trunk directly through each device) shall not be used.Notes: Components of fieldbus segments can be connected together in various architectures known astopologies.The topology selected is usually driven by the physical device location in order to reduceinstallation costs. Hence, plot plans are used in addition to P&ID's and instrument indexes in thedesign of a fieldbus segment.Most often, after the above design considerations are weighed, the following three topologies are used: ‘(SeeFigure 2)• A tree topology is used when several related instruments are physically located close toeach other. A fieldbus junction box is located close to the instruments with spursextending from it to each instrument.• A spur topology is used when several related instruments are located in the samedirection from the host device but not necessarily close to each other. In this case, atrunk line is extended from the host to the farthest instrument and spurs are extendedfrom it as it runs past each instrument. It is not to be followed.• A spur/tree topology is used when some combination of the above instrument localesexists. Note that spurs are permitted to extend only from trunk lines and not from otherspur lines.Daisy chain topology may appear to reduce total wiring run length and connection cost, but it has asignificant disadvantage. That disadvantage is maintainability and reliability downstream of each device.When a device is removed from a daisy chain topology segment, all downstream devices are alsodisconnected.TrunkSpurTo H1CardTree TopologyJunctionBox (JB)To H1CardSpur TopologyTo H1CardJunctionBoxCombinationTopologyTo H1CardDaisy-ChainTopology(JB) (JB) (JB) (JB)(JB)Do Not UseFigure 2 – Fieldbus Topologies6.2 DISTANCE CONSTRAINTS6.2.1 The maximum allowed length of a fieldbus segment is 1900 meters (6232 ft.) with Type A cables. This

Page 8: Specification for Foundation Fieldbu Essar

total segment length is computed by adding the length of the main trunk line and all the spurs that extendfrom it.Do not use6.2.2 Total Segment Length = Trunk + All SpursNote: The maximum length given is specified in the ISA 50.02 Fieldbus standard. The length of asegment is limited by voltage drop and signal quality (i.e., attenuation and distortion).6.3 SPURS6.3.1 Only one (1) FOUNDATION™ Fieldbus (FF) device shall be connected to each spur.6.3.2 Though the maximum spur length can be 120 meters (394 ft.) but 100 meters (max) is to be considered fordesign. The spur length is the length of the cable from the 'wiring block' to the FF device.Note: A spur is a drop off of the main trunk line. The trunk is considered to be the main cable run and willcontain segment terminators at each end.6.4 CABLE TYPES6.4.1 Trunk (Homerun) Cabling6.4.1.1 Either ISA 50.02 Type 'A' cable 18 AWG , 5 pair individually shielded cable (Belden orEquivalent) shall be used for all trunk wiring.6.4.1.2 Four pair shall be used for the 4 segments and the one pair will be kept as spare.Between integrated JB / primary & secondary JB, the trunk shall be 1 pair, Type A, 18 AWG6.4.2 Spur CablesSingle pair Type 'A' cable 18 AWG, as defined in ISA 50.02, shall be used for all spur cabling.6.4.3 Color Coding6.4.3.1 For all FF cables, spur and trunk, the outer jacket color shall be orange.6.4.3.2 For all FF cables, spur and trunk, the conductor color code shall be;(+ Signal) Orange(- signal) BlueDrain/shield Tinned copper conductor6.5 WIRING POLARITYWiring polarity shall be maintained throughout the segment design and installation.6.6 FIELDBUS POWER CONSUMPTION6.6.1 Fieldbus devices may be powered either from the segment (bus), or locally powered, depending on the devicedesign.6.6.2 The total current draw from all devices on the segment must not exceed the rating of the FFPS – 'FOUNDATION™ Fieldbus Power Supply'. The segment design must take into account:6.6.2.1 Total device quiescent current draw.6.6.2.2 One spur short circuit fault (i.e., ~50 mA additional current draw).6.6.2.3 25% additional current load over and above that calculated from 6.6.2.1 and 6.6.2.2 above.Commentary Note: The acronym 'FFPS' will be used in lieu of 'fieldbus power supply' throughout thisdocument to avoid confusion with the bulk power supply (BPS).6.7.3 The number of bus powered (two-wire) devices on a segment is limited by the following factors:6.7.3.1 Output voltage of the FFPS.6.7.3.2 Current consumption of each device.6.7.3.3 Location of device on the segment, (i.e., voltage drop).6.7.3.4 Location of the FFPS.6.7.3.5 Resistance of each section of cable, (i.e., cable 'type').6.7.3.6 Minimum operating voltage of each device.6.7.3.7 Additional current consumption due to one spur short circuit fault, ~50 mA.6.7.3.8 25% spare capacity.Commentary Note: The length of a fieldbus wiring system and the number of devices on a segmentare limited by power distribution, attenuation and signal distortion. The ISA 50.02 estimates how longa fieldbus cable can be and still have adequate signal quality, (i.e., acceptable attenuation anddistortion). Calculating power distribution for a segment is relatively simple and can be easilyperformed.6.8 VOLTAGE DROP

Page 9: Specification for Foundation Fieldbu Essar

6.8.1 Circuit analysis shall be carried out for each fieldbus segment to determine the operating voltage at eachdevice. The calculated voltage at the device shall exceed the devices minimum voltage rating by 4 volts,(e.g., minimum Vdc required by device = 9 volts, therefore the calculated minimum voltage seen at thedevice shall be 13 Vdc).The calculated voltage at each device shall be shown on the Instrument SegmentDiagram (ISD) or Bus Coupler Arrangement Drawing.Commentary Notes: The additional 4-volts at each device have been specified as a spare power margin forfuture device additions to the segment.Per the FOUNDATION fieldbus specification, field devices must sense a DC voltage between 9 and 32 volts forproper operation.The power used by fieldbus devices varies by device type and manufacturer. Specific minimum voltage andcurrent requirements are contained in the product specifications for each device. The voltage and currentrequirement for each device shall be taken into consideration while conducting the circuit analysis of thesegment. A Fieldbus FOUNDATION certified device is required to be capable of operating at > 9 Vdc.6.9 FF SEGMENT EARTHING6.9.1 FF trunks and spurs cables shall be earthed. FF trunks and spur cables shall be provided with an overallshield, which shall only earthed at DCS end. This earth is expected to be located in the satellite building. Theoverall shield shall not be earthed at the FF device end.6.10 WIRING PRACTICES TO MEET ELECTRICAL HAZARDOUS AREA RATING6.10.1 Class I Division 2 Areas (and Zone 2) & Class I Division 1 Areas (and Zone1)6.10.1.1 EExe Enclosure for trunk, EExe isolator switch for barriers, on trunk line, non arcing/non sparkingterminals with connect/disconnect facility, EEx ia spurs.6.10.1.2'Nonincendive circuits' as defined in NFPA 70, National Electrical Code Section 500- 4(f)(1) shall not beused.7 FIELDBUS DEVICES7.1 Following are the minimum requirements for Field bus Devices.7.1.1 The device shall satisfy the requirements of the Fieldbus Foundation specifications and shall have FFCHECKMARK. The Devices shall be certified for intrinsic safety EEx ia (ATEX or equivalent certification).7.1.2 Foundation Field bus Device shall be certified as passing the ITK 4.61 or later and shall include DeviceDescription (DD) and Common File Format (CFF) files.7.1.3 The FF device and all function blocks shall be tested and certified by the vendor of the control system Host.7.1.4 The Devices shall be provided with Flash memory for downloading the revised firmware in future.7.1.5 Function block shall be downloadable into the devices by the end user.Wiring Block Wiring Block Wiring BlockMarshalling PanelSatellite BuildingIntermediate FFJunction BoxFF Spur Junction BoxFF Device1 Pair, Type AType ATrunkcableType ATrunk

Page 10: Specification for Foundation Fieldbu Essar

cableFOUNDATION FIELDBUS EARTHING ARRANGEMENT7.1.6 Capable of performing continuous diagnostics, including self test functions, to provide specific diagnosticinformation at the Man Machine Interface (MMI).7.1.7 All Fieldbus instruments shall include menus and method’s (wizards) to allow easy setup and calibrationfrom the MMI.7.1.8 FF Device shall have three support files .FFO, SYM and CCF which contain information necessary toconfigure the Host systems. The support files shall include two Device Description Files and one CapabilityFile, as defined in Fieldbus Foundation specification FF-940. The capabilities file and DD files shall beprovided by the device vendor and shall not be downloaded from the Foundation Fieldbus website.7.1.9 Device vendors shall provide DTM (Device Type Manager) files for all devices and shall develop these filewhere they are not available. The DTM files shall be compatible with the host DCS system using FDT/DTMtechnology.7.1.10 Standard programmatic interface shall follow FDT Group 1.2 standards. Any revision to host OperatingSystem or device DD shall not require changes to the DTM for EDD.7.1.11 Most Foundation Fieldbus devices can be powered directly from the Fieldbus. The DC supply voltage canrange from 9-32 Vdc. The transmitting device delivers ± 10 mA at 31.25 kbits/s into a 50 ohm equivalent loadto create a 1.0 volt peak-to-peak voltage modulated on top of the direct current (DC) supply voltage.7.1.12 Loss of power or disturbance to one power supply module shall not result in the reset of a field device in anycircumstances.7.1.13 In order to reduce commissioning time each field device must be pre configured by the manufacturer asindicated on the instrument datasheet.7.1.14 Temperature multiplexers shall be with 8 input and the input can be RTD or T/C.7.1.15 None of the device shall be polarity sensitive.7.1.16 All field bus devices shall have capability to perform continuously their own self diagnostics to check theirhealth state.7.1.17 Where ever specified for FF devices (Transmitters installed on high columns and open area like tank farms)shall be provided with necessary surge protection device in the concerned spur in the JB.7.2 Multi-Input TransmittersMulti-input transmitters using FOUNDATION Fieldbus Multiple Analog Input (MAI) function block(s) shall beused for monitor only applications.7.3 Handheld Fieldbus TestersFieldbus testers with following features shall be provided per process unit for the end user as essentialcommissioning accessories & also for future field Maintenance.Monitor signal level, noise level, DC power, LAS, Packet traffic, Device count, Framing errors, monitors deviceadd & drop, shield short, Low FF and HF average and peak noise, network health, certified for both zone1and zone2 and for both IS and Non IS devices and JB’s, PC downloadable through USB port.All data stored in the FBT’s shall be downloadable into a PC thru cable.8 NON-DEVICE ELEMENT SELECTION8.1 Foundation Fieldbus Power Supplies (FFPS)8.1.1 FFPS are required for each fieldbus segment.

Page 11: Specification for Foundation Fieldbu Essar

8.1.2 FFPS shall be redundant and output current limited.8.1.3 FFPS shall have redundant input power connections.8.1.4 Two separate, independent, fused circuits shall source power to the FFPS. One (1) circuit shall bepowered from the primary bulk power supply and the second (2) circuits shall be powered from thesecondary (redundant) bulk power supply8.1.5 All fieldbus power supplies shall be for 4 or 8 segment & true redundant type ie. with separate redundantpower & conditioning unit built in.8.1.6 Failure or faults in any of the redundant FFPS shall be annunciated in the Host system.8.1.7 Fieldbus power supplies shall be encapsulated type & without any exposed component on the mother board.8.1.8 All power supply modules shall be “hot swappable”.8.1.9 All the power supply modules shall be repairable’8.1.10 All power supply modules shall be fully isolated and having individual LED indication for each segment.8.1.11 All power supply modules shall have built in Alarm feature and should support Advance Diagnostic features.8.2 Terminators8.2.1 Each fieldbus segment must have exactly two terminators. The terminator in the field will be at the end oftrunk. ( last FFB JB of the segment )8.2.2 All terminators located in the field shall be installed in a junction box. No terminators shall be installed inthe FF devices.8.3 Bulk power Supplies (BPS)8.3.1 The 24 Vdc BPS shall be redundant.8.3.2 Two separate, independent, UPS circuits shall source power the redundant BPS. The UPS distributionpanel shall be considered the common point where these two separate circuits originate8.3.3 Over current protection shall be provided for each feed supplying power to an individual or gang of FFPS.8.4 Foundation Fieldbus Barriers (FBB)8.4.1 The Fieldbus Barrier shall be Bus powered type.8.4.2 Each FBB shall have four spurs.8.4.3 All spurs shall be IS and short circuit protected.8.4.4 LED indication shall be there for power On and Fault condition for each spur.8.4.5 The Fieldbus Barrier shall have intelligent Power Management features i.e. powering up of each field deviceone by one to avoid high inrush current and maintain low startup current.8.4.6 The Field bus Barrier shall have ambient Temperature withstanding upto 75 Deg C with 100 % RH.8.4.7 Each FBB shall have separate earthing bus bar.8.4.8 All the Trunk and Spur shall have Reverse Polarity protection.8.4.9 All the Spurs shall have Deenergising feature ie in case of a fault condition the voltage will get clamped andthere will no current drainage. The Spur will be energized only after the short is removed/repaired. This willensure proper voltage even at the furthest end of the segment.8.4.10 The enclosure for field bus barrier shall be designed in such a way to accommodate maximum 3 nos of FBBalong with locking type isolation switch for each FBB, SPD’s (surge protection device) for Trunks at bothends. The Trunk and spur cables inside the enclosure shall be properly accessible for servicing purpose.Proper care shall be taken for proper spacing of components inside the enclosure to avoid heat andconsequent temperature buildup. The total assembly along with FBB shall be tested at manufacturer’s facility

Page 12: Specification for Foundation Fieldbu Essar

and duly certified. Separate DIN mounted Terminator shall be provided inside the enclosure if more than oneFBB is in the segment.8.4.11 Fieldbus Sement Device AllocationControl LoopsFF BarrierJB Size CriticalLevel 1CriticalLevel 2CriticalLevel 3Max.AdditionalDevicesTotalSpursUsedAvailableSpares1 None None 1 3 1None 1 None 1 3 1None None 1 1 3 11 FBJunctionBox( 4 SpurMax) None None None 3 3 11 None None 4 6 2None 1 None 4 6 2None 1 1 2 6 2None None 1 4 6 2None None 2 2 6 2None None 3 None 6 22 FBJunctionBox( 8 SpurMax)None None None 6 6 21 None None 7 9 3None 1 None 7 9 3None 1 1 5 9 3None None 1 7 9 3None None 2 5 9 3None None 3 3 9 33 FBJunctionBox( 12 SpurMax)None None None 9 9 3Note: Each Controller is taken as one analogue input and one analogue output. Dueallowance for additional loop devices will be required for cascade loops and splitranged controller application.8.5 Repeater

Page 13: Specification for Foundation Fieldbu Essar

Repeaters shall not be used, unless permitted. (See note below)If a segment (network) needs to extend further than the 1900 meter length constraint, then a repeater may beconsidered.Note: Using a repeater to extend the segment length shall not be a standard design practice. In the caseswhere it is economically justified, a repeater may be considered to extend the total segment length. Thiswould typically be in cases where the H1 interface card cannot be located relatively close to the process,(e.g., flare systems). The repeater segment design must be reviewed and approved in writing from client.9 HOST REQUIREMENTS9.1 Host FF Interoperability9.1.1 All FF Host systems shall have completed Host Interoperability Support Testing (HIST) at FOUNDATIONFieldbus facilities, based on HIST Procedures document FF-569. FF Host systems shall support all featuresspecified in the HIST.9.1.2 A letter of conformance to the Host Interoperability System Test shall be provided to verify test completionand feature support.9.1.3 All supported FF HIST features shall be integrated seamlessly into the existing control system's engineering,configuration, maintenance, and operations system.9.1.4 The Host System supplier shall have an interoperability test laboratory setup to ensure that all third partydevices used in the project have been successfully tested and certified with their system, reference section9.2 Host Control System RequirementsIn addition to the FF requirements specified in this document, Host systems shall meet all requirementsspecified in "Distributed Control Systems".9.3 Host FF Feature IntegrationAll Host FF functions, including engineering, configuration, maintenance, and operational display functions,hall be integrated into a single, seamless Host system. Engineering, configuration, maintenance andoperational features shall apply consistently and seamlessly to conventional analog or discrete I/O, smartHART and proprietary I/O, bus based I/O, and FF systems. Separate software tools, displays, or procedures -specific for FF and different from conventional - are not acceptable.9.4 Host-To-Device Revision Download CapabilityHosts shall have the capability to download software revisions to FOUNDATION Fieldbus devices.9.5 Host Configuration Features9.5.1 Host FF configuration shall be consistent in method and 'look and feel' with conventional configuration.9.5.2 Internal mirror or shadow function blocks used by control systems to map FF function blocks to internalproprietary function blocks must be completely transparent to the configurator and operator. Single, uniqueand independent function block and parameter tag names must be used for both configuration and operation.Duplicate shadow blocks/parameters with tag names different from FF block/parameters are not acceptable.9.5.3 The Host FF configuration tool shall seamlessly and transparently integrate with, and maintain, the masterconfiguration database. Saves, restores and partial downloads of the master control system database shallbe seamlessly and transparently accomplished for both FF and conventional control strategies by the sameconfiguration tool.

Page 14: Specification for Foundation Fieldbu Essar

9.5.4 The Host configuration tool shall be capable of:9.5.4.1 Offline FF configuration, e.g., to configure FF strategies with no segment or FF devices connected. TheHost shall be capable of configuring all FF function blocks and parameters and support of DeviceDescription (DD) services and Common File Format (CFF) specification.9.5.4.2 Soft simulating and testing any and all FF control strategies.9.5.4.3 Importing non-native, bulk configuration data for developing configuration of larger project databases.9.5.4.4 Simple or complex online FF control strategy creation or modification.9.5.4.5 Transparently managing the macro cycle schedule including maintaining minimum unscheduled acyclic time,coordinating integration of proprietary and FF function block execution times, and providing alerts andmessages for FF configuration errors.9.5.4.6 Partial or incremental downloads to target function blocks and link schedulers without disrupting theoperating segment strategies.9.5.4.7 Master database saves and restores of targeted strategies or FF segments.9.6 Host Commissioning and Maintenance Functions9.6.1 The Host shall be capable of commissioning, setup, and maintaining all FF devices. This function must beintegrated into the Host and available from Host workstations. The following functions shall be supported:9.6.1.1 Add a new FF device to a segment. Add a future FF device to a segment through use of placeholdertemplates.9.6.1.2 Move FF devices from/between offline, spare, standby, commissioned, and mismatch states and manage alladdress changes transparently. Manual address changes shall not be required.9.6.1.3 Simple and complex commissioning functions including transmitter range changes, zeroing, and control valvepositioner setup.9.6.1.4 Support for DD methods and menu's (wizards) for all maintenance functions to walk technicians through thenecessary maintenance procedures.9.6.1.5 Provide specific maintenance displays, organized in a logical manner, for all FF devices using Englishlanguage descriptors and definitions with access to all parameters. Screens shall not use lists of FF functionblock parameters.9.6.1.6 Ability to mirror existing FF device configuration (all FBs and parameters) onto a new FF device to allow quickdevice replacements.9.6.1.7 Display of commissioning and maintenance screens shall be from the operator/engineering workstation.9.6.2 Asset Management SystemsAsset Management Systems separate from the Host operator/engineering workstations may be used tomanage and display real-time and historical diagnostic & maintenance information. However, it may notreplace commissioning and maintenance function integrated into the Host as described above.9.7 Host FF Operating Tools:FF features required for integration include:9.7.1 Internal mirror or shadow function blocks used by control systems to map FF function blocks to internalproprietary function blocks must be completely transparent to the operator. Operating displays must usesingle, unique and independent tag names. Duplicate tag names for the same function are not acceptable.9.7.2 FF function block operation, including use of data quality, status, windup and bad value indication and mode

Page 15: Specification for Foundation Fieldbu Essar

switching, must be supported by, and transparently integrated into the control system operation andoperating displays. Differences in operation or displays between FF devices or loops and conventional loopsare not acceptable.9.7.3 FF process alarms and device alerts must be supported by, and integrated into the control system.Differences between conventional and FF alarm management and alarm displays are not acceptable.9.7.4 FF trend data via trend objects shall be supported by the Host control system and transparently integratedinto real-time and historic trends displays.10.0 CONSIDERATION FOR DETAIL ENGINEERING10.1 5 Pair cable shall be used as Trunk cable from FF marshalling to Intermediate JB with 4 pair to be usedfor 4 segments and 1 pair will be spare. 1 pair cable shall be used between Intermediate JB & spur JB’s aswell as between spur JB’s and Field devices10.2 The Trunk + Spur length should not exceed 1700 mtr.10.3 The trunk length should not exceed 1000 mtr.10.4 The individual spur length should not exceed 100 mtr.10.5 Each segment shall be designed for Max 12 devices (10 installed + 2 spare)10.6 Power requirement shall be designed to cater min 10V to each FF device including spare device as indicatedin section 10.5.10.7 Detail engineering contractor (DEC) shall validate FF Instrument Segment Diagram as defined in section11.3 by using In-tools validation tool with respect to total cable length (Derived from 3D Model or InstrumentPlot plan), Device operating Voltage (Min 10 VDC), Total number of devices on segment based on loopcriticality & segment cycle time, Field Bus Barrier voltage requirement (17 VDC) etc guidelines defined in thisspecification. The Segment Loading shall be verified by Integrated DCS System Vendor (ISV) with respect tooverall loop configuration.11 DOCUMENTATIONFOUNDATION Fieldbus system design requires the same documentation as conventional control systemdesigns. However, some documents must be altered for FOUNDATION Fieldbus architecture.Documentationalterations, additions, and deletions required for FF use are defined below.11.1 Control Philosophy Document11.1.1 A control philosophy guideline document shall be created for all FF projects. The guideline shall define alltypical control strategies, with control modules, function blocks and all parameter configurations defined. Thisguideline shall set function block and control module philosophy for this and future FF projects at the facility.11.1.2 As part of the guideline, a narrative shall be provided for each typical function block and control module, todescribe in detail the parameter setting and subsequent blocks/module operation. Included shall be narrativediscussion on parameter configuration and operation for signal 'status', bad value determination, failure modeswitching, Initialization feature, anti-reset windup feature, etc. The guideline shall highlight any differences inconfiguration or operation between FF and non-FF control strategies.11.1.3 The control philosophy guideline document shall include a risk assessment philosophy (method) which

Page 16: Specification for Foundation Fieldbu Essar

defines how and why specific Fieldbus devices are assigned to segments. The philosophy shall includeconsideration for segment loading constraints and multiple segments per H1 card. See section 5.7 for riskassessment and segment loading criteria.11.2 PIPING AND INSTRUMENTATION DIGRAMS (P&ID's)11.2.1 Fieldbus instrumentation shall be shown on the P&ID as per Essar Engineering Centre standards with thefollowing exceptions:11.2.1.1Fieldbus instrument balloons shall be conventional, with the addition of a Foundation Fieldbus indication onthe top right side of the instrument bubble, shown as: FF11.2.1.2The line symbology for FF signal wiring shall be the standard 'dashed' electric signal per ISA 5.1. 11.2.1.3 Thecontrol or logic function balloons shall be shown independent of the hardware in which it is contained.Note: PID, selectors, or arithmetic function blocks shall be shown functionally on the P&ID, (i.e., not shown asshared balloons with the device they reside in).11.2.1.3 The control or logic function balloons shall be independent of the hardware in which it is contained.Note: PID, selectors, or arithmetic function blocks shall be shown functionally on the PID, (i.e., not shown as ashared balloons with the device they reside in).11.2.2 All functions within the same field device shall be tagged with the same number, with individual functionlettering appropriate for the application.Note: For example using a multi-variable Coriolis meter, the instrument tagging would be FT-1010, DT-1010,and TT-1010 for flow, density and temperature, respectively.11.2.3 Multivariable Fieldbus transmitters (e.g., multiple process measurements from the same transmitter) shall berepresented with connected instrument balloons.11.3 INSTRUMENT SEGMENT DIAGRAMSThe Instrument Loop Diagram (ILD) shall be replaced with an Instrument Segment Diagram (ISD).The ISDis a hardware-wiring diagram intended to show the physical connections and layout of the segment. Soft dataincluding display, function block, and configuration data shall not be shown.In addition to standard loop drawing information, ISDs shall include the following FF system details:11.3.1 A consistent method for identifying all signal wires is required in any control system;The following is a recommended network/ segment naming convention –###ISD-NN MM PP where:### - Indicates the plant/area number to which the segment is connectedNN - Indicates node number / controller nameMM = module number / card numberPP = segment or port numberThe title block shall contain the 'segment name'. The segment name shall consist of the "Plant Area nameController Name, Card Number and Port Number".For example if the Controller name is '01', card number is '08' and we are using Port 1, the segment nameShall be “138 ISD-010801.”11.3.2 All segment connections inclusive of the H1 interface card, BPS, FFPS, through the field devices,terminations, junction boxes, and terminators.11.3.3 All segment and field device tagging.11.3.4 All spur cables shall be labeled with the instrument tag number.11.3.5 All cable distances with voltage drop calculation results.11.3.6 The Backup LAS device shall be identified.11.3.7 Terminator locations shall be clearly identified.

Page 17: Specification for Foundation Fieldbu Essar

11.4 INSTRUMENT SPECIFICATION SHEETS:FOUNDATION Fieldbus instrumentation shall use the standard Essar Engineering Centre ISS's, with thefollowing line item additions:11.4.1 LAS capable (yes/no)11.4.2 Minimum Operating Voltage (Vdc)11.4.3 Quiescent Current Draw (mA)11.4.4 Polarity Sensitive Termination (yes/no)11.4.5 DD revision level11.4.6 Channel number and Description, (e.g., Channel 1 - Sensor 1, Channel 2 - Body Temperature, Channel 3 -Sensor 2, etc.).11.4.7 Function Blocks Available, (e.g., AI_1, AI_2, PID_1, etc.)12 FACTORY ACCEPATANCE TEST (FAT)12.1 Systems that are staged at a vendor's facilities shall be tested according to Factory Acceptance Test (FAT)

procedures produced for each project.12.2 FAT criteria shall be developed by the vendor and approved by consultant/client.12.3 For any Fieldbus logic not tested during FAT, either because logic simulation is not available or all fieldbusdevices cannot be connected, then the untested Fieldbus logic must be tested during SAT.12.4 The following test shall be conducted for each segment:Each H1 card segment (port), including spares, shall be operationally tested by live connection of at leastone Fieldbus device. The Fieldbus device shall be connected to the terminal block designated for the fieldwiring or system cable.12.5 The following tests shall be conducted one time only on a selected segment:12.5.1 A complete functional test shall be conducted for one-of-each FF device used on this project (i.e., boththird-party and Control System Vendor products). This test will include, but is not limited to, plug-and-playinterconnectivity to Host system; configured fail-safe operation, verify access to all device function blocks,and actual device operation, (e.g. simulate process inputs for transmitters, etc.12.5.2 The test shall include configuration, calibration checks, and setup for each type of FF device. Examples arechanging RTD sensor types; configuring and calibration check of transmitter span, zeroing P & DPtransmitters, zeroing elevation on DP level transmitters, setup etc. The intent of this requirement is to verifythe ease of access to calibration wizards and setup procedures via the Host system.12.5.3 All calibration and setup procedures, for each device, shall be demonstrated to Essar Engineering Centrepersonnel. Each procedure shall be documented in detail by the vendor and approved by EssarEngineering Centre.12.5.4 Vendor shall develop a redundancy fail-over test procedure for the H1 interface cards and Fieldbus powersupplies. The test shall verify that automatic fail over shall not cause an upset, (i.e., I/O signal bumps, loss ofoperator view, mode changes, etc.). All H1 interface cards and FFPS shall be tested. Essar EngineeringCentre shall approve the fail-over test procedures.13 SITE ACCEPTANCE TEST (SAT)The FF SAT test shall contain the same scope as covered in the FF FAT.For any Fieldbus logic not tested during FAT, either because logic simulation was not available or becauseall of the fieldbus devices could not be connected, then the untested Fieldbus logic must be tested duringSAT.14 INSTALLATION AND CHECKOUTThe Control System Vendor shall develop a separate installation and checkout procedure for the Fieldbus

Page 18: Specification for Foundation Fieldbu Essar

system. This procedure shall be approved in writing by Essar.15 MAINTENANCE SHOP FIELDBUS SYSTEMS AND TOOLS15.1 Each project shall supply and install a complete fieldbus maintenance system in the maintenance shop. Theintent of this maintenance system is to allow Fieldbus instrument troubleshooting, calibration, and setup in theInstrument Maintenance shop.15.2 The Maintenance Fieldbus system will include all system hardware, software, and auxiliary equipmentrequired to connect and maintain Fieldbus devices in the shop. Equipment shall include but not be limited toa control system with dual Operator/Engineering workstations with complete software, control network withappropriate switches, chassis with controller & power supplies, redundant H1 cards, Bulk and FOUNDATIONFieldbus power supply (FFPS), and FBB JB with isolating switch, FBB & trunk wiring block. All workstationswill be mounted in appropriate 'shop-proof' furniture. The I/O chassis, power supplies, wiring and terminalblocks will be pre-wired and installed in an easy to access, caster mounted cabinet.15.3 All standard and special tools, test software, and test and calibration equipment required for the Fieldbussystem as specified in 7.3 shall be supplied by the project. A list of the tools, test and calibration equipmentshall be submitted to Essar for review and approval.15.4 The list of the standard tools and testing and calibration equipment required shall identify the following:15.4.1 Description of its service or simulation application.15.4.2 Manufacturer and Catalog No.15.4.3 Quantity recommended.15.5 Control System Vendor (ISV) shall provide design and performance specifications for all special tools, testsoftware, and test and calibration equipment.16 FILEDBUS SPARE PARTS AND REVISION LEVEL UPDATE PROGRAM16.1 The Control System Vendor (ISV) shall develop a Fieldbus device spare parts management program forthis facility within Essar Engineering Centre. This program shall provide management of:16.1.1 Stocking a sufficient quantity of Fieldbus spare instruments and associated software.16.1.2 Management, tracking, and update of Fieldbus spare instruments revision levels.16.1.3 Stocking a sufficient number of Fieldbus non-device element hardware e.g., Foundation fieldbus powersupplies, terminators, FBB, isolating switch, etc.16.2 The Control System Vendor shall develop and put in place an update program that assures the systemrevision level stays current.Notes: The control system must be kept current to assure it will work with new Fieldbus instrument revisions.Typically, a current revision level is also backwards compatible with older Fieldbus instrument revisions.While they look exactly the same, Fieldbus instruments are completely different from, and not replaceableby, conventional instruments. Thus, spare Fieldbus and conventional instruments must be keptsegregated and identified differently. In addition, Fieldbus instruments may have associated software thatmust be stored with it.For these reasons, a complete Fieldbus instrument spare parts management program must be developed.17 FIELDBUS TRAINING

Page 19: Specification for Foundation Fieldbu Essar

Control System Vendor (ISV) to provide FF training programs targeted for the following categories of companypersonnel:• Engineers(Overview, Maintenance, Advanced)• Operators (Overview)• Maintenance Supervisors (Overview, Maintenance)• Maintenance technicians (Overview, Maintenance)17.2 Courses and course requirements shall include following, but not limited to:• Foundation Fieldbus Architecture• Foundation Fieldbus terminology• Segment components, power and wiring.• Foundation Fieldbus communication and bandwidth issues.• Review of fieldbus function blocks.• Device Description language review.17.3 Foundation Fieldbus Maintenance courses shall be as follows:• Foundation Fieldbus Architecture• Foundation Fieldbus terminology• Detailed review of segment components, segment design, power, intrinsic safety and wiring.• Foundation Fieldbus Communication and Bandwidth issues.• Review of Foundation fieldbus blocks.• Device Description language review.• Maintenance tools and troubleshooting.• DD file maintenance and updating• Interface to AMS.17.4 Foundation Fieldbus Advance course:• H1 datalink layer.• H1 Bus monitor.• H1 System management• Fieldbus message specifications• High Speed Ethernet.• Object Dictionary• Function Block application process.• Advanced Control Strategies• DD file maintenance and updating.17.5 A training program based at the DCS suppliers facilities may be developed for engineers and supervisors.An on-site training program may be developed for the operators and maintenance technicians.The ISV vendor shall supply quotation for an on-site FF training simulator for on-going FF training support ofthe FF system.17.6 Training StagesThe ISV vendor to implement FF training in phases as described below:• Engineering Phase• Prior to FAT Phase• Prior to SAT PhaseCompany personnel to be trained in each phase shall be indicated by Essar Oil.Engineering phase and prior to FAT phase training will be held at FF vendor facilities.Prior to SAT phase training will be held at site.

Annexure A – Fieldbus Glossary of TermsAll Fieldbus terms and acronyms defined below are from the 'Glossary of Terms' section on the FOUNDATION websitewww.fieldbus.org. The entire FOUNDATION Fieldbus glossary has been copied to appendix-A.ABasic Device: A Basic Device is any device not having the capability to control communications onan H1 fieldbus segment.

Page 20: Specification for Foundation Fieldbu Essar

Capabilities File: A Capabilities File describes the communication objects in a fieldbus device. Aconfiguration device can use Device Description (DD) Files and Capabilities Files toconfigure a fieldbus system without having the fieldbus devices online.Communications Stack: A Communications Stack is device communications software which providesencoding and decoding of User Layer messages, deterministic control of messagetransmission, and message transfer.Connector: A Connector is a coupling device used to connect the wire medium to a fieldbusdevice or to another segment of wire.Control Loop: A Control Loop is a group of Function Blocks (FBs) that execute at a specified ratewithin a fieldbus device or distributed across the fieldbus network.Coupler: A Coupler is a physical interface between a Trunk and Spur, or a Trunk and adevice.Data Link Layer (DLL): The Data Link Layer (DLL) controls transmission of messages onto the fieldbus, andmanages access to the fieldbus through the Link Active Scheduler (LAS). The DLLused by FOUNDATION fieldbus is defined in IEC 61158 and ISA S50. It includesPublisher/Subscriber, Client/Server and Source/Sink services.Device Description (DD): A Device Description (DD) provides an extended description of each object in theVirtual Field Device (VFD), and includes information needed for a control system orhost to understand the meaning of data in the VFD.EFieldbus: A Fieldbus is a digital, two-way, multi-drop communication link among intelligentmeasurement and control devices. It serves as a Local Area Network (LAN) foradvanced process control, remote input/output and high speed factory automationapplications.Fieldbus Access Sublayer (FAS): The Fieldbus Access Sublayer (FAS) maps the Fieldbus Message Specification(FMS) onto the Data Link Layer (DLL).Fieldbus Messaging Specification (FMS): The Fieldbus Messaging Specification (FMS) contains definitions ofApplication Layer services in FOUNDATION fieldbus. The FMS specifies servicesand message formats for accessing Function Block (FB) parameters, as well asObject Dictionary (OD) descriptions for those parameters defined in the Virtual FieldDevice (VFD).Flexible Function Block: A Flexible Function Block (FB) is similar to a Standard FB, except that the function ofthe block, the order and definition of the block parameters, and the time required toexecute the block are determined by an application-specific algorithm created by aprogramming tool. Flexible Function Blocks (FBs) are typically used for control ofdiscrete processes and for hybrid (batch) processes. A Programmable LogicController (PLC) can be modeled as a Flexible Function Block device.GH1: H1 is a term used to describe a fieldbus network operating at 31.25 kbit/second.H1 Field Device: An H1 Field Device is a fieldbus device connected directly to an H1 fieldbus. TypicalH1 Field Devices are valves and transmitters.H1 Repeater: An H1 Repeater is an active, bus-powered or non-bus-powered device used toextend the range over which signals can be correctly transmitted and received for agiven medium. A maximum of four Repeaters and/or active Couplers can be usedbetween any two devices on an H1 fieldbus network.High Speed Ethernet (HSE): High Speed Ethernet (HSE) is the Fieldbus Foundation's backbone network runningat 100 Mbit/second.HSE Field Device: An HSE Field Device is a fieldbus device connected directly to a High SpeedEthernet (HSE) fieldbus. Typical HSE Field Devices are HSE Linking Devices, HSEField Devices running Function Blocks (FBs), and Host Computers.

Page 21: Specification for Foundation Fieldbu Essar

HSE Linking Device: An HSE Linking Device is a device used to interconnect H1 fieldbus Segments toHigh Speed Ethernet (HSE) to create a larger network.HSE Switch: An HSE Switch is standard Ethernet equipment used to interconnect multiple HighSpeed Ethernet (HSE) devices such as HSE Linking Devices and HSE Field Devicesto form a larger HSE network.Input/Output (I/O) Subsystem Interface: An Input/Output (I/O) Subsystem Interface is a device used to connectother types of communications protocols to a fieldbus Segment or Segments.Interchangeability: Interchangeability is the capability to substitute a device from one manufacturer withthat of another manufacturer on a fieldbus network without loss of functionality ordegree of integration.Interoperability: Interoperability is the capability for a device from one manufacturer to interact withthat of another manufacturer on a fieldbus network without loss of functionality.JKLink: A Link is the logical medium by which H1 Fieldbus devices are interconnected. It iscomposed of one or more physical segments interconnected by bus Repeaters orCouplers. All of the devices on a link share a common schedule which isadministered by that link's current LAS.Link Active Scheduler (LAS): A Link Active Scheduler (LAS) is a deterministic, centralized bus scheduler thatmaintains a list of transmission times for all data buffers in all devices that need to becyclically transmitted. Only one Link Master (LM) device on an H1 fieldbus Link canbe functioning as that link's LAS.Link Master (LM): A Link Master (LM) is any device containing Link Active Scheduler (LAS)functionality that can control communications on an H1 fieldbus Link. There must beat least one LM on an H1 Link; one of those LM devices will be elected to serve asLAS.Link Objects: A Link Object contains information to link Function Block (FB) Input/Output (I/O)parameters in the same device and between different devices. The Link Object linksdirectly to a Virtual Communications Relationship (VCR).MNetwork Management (NM): Network Management (NM) permits FOUNDATION Network Manager (NMgr) entitiesto conduct management operations over the network by using Network ManagementAgents (NMAs). Each Network Management Agent (NMA) is responsible formanaging the communications within a device. The NMgr and NMA communicatethrough use of the Fieldbus Messaging Specification (FMS) and VirtualCommunications Relationship (VCR).Object Dictionary: An Object Dictionary (OD) contains all Function Block (FB), Resource Block (RB)and Transducer Block (TB) parameters used in a device. Through these parameters,the blocks may be accessed over the fieldbus network.Physical Layer: The Physical Layer receives messages from the Communications Stack and convertsthe messages into physical signals on the fieldbus transmission medium, and viceversa.QResource Block (RB): A Resource Block (RB) describes characteristics of the fieldbus device such as thedevice name, manufacturer and serial number. There is only one Resource Block(RB) in a device.Schedules: Schedules define when Function Blocks (FBs) execute and when data and status ispublished on the bus.Segment: A Segment is a section of an H1 fieldbus that is terminated in its characteristicimpedance. Segments can be linked by Repeaters to form a longer H1 fieldbus.Each Segment can include up to 32 H1 devices.Splice: A Splice is an H1 Spur measuring less than 1 m (3.28 ft.) in length.Spur: A Spur is an H1 branch line connecting to the Trunk that is a final circuit. A Spur can

Page 22: Specification for Foundation Fieldbu Essar

vary in length from 1 m (3.28 ft.) to 120 m (394 ft.).Standard Function Block (FB): Standard Function Blocks (FBs) are built into fieldbus devices as needed to achievethe desired control functionality. Automation functions provided by Standard FBsinclude Analog Input (AI), Analog Output (AO) and Proportional/Integral/Derivative(PID) control. The Fieldbus Foundation has released specifications for 21 types ofStandard FBs. There can be many types of FBs in a device. The order and definitionof Standard FB parameters are fixed and defined by the specifications.System Management (SM): System Management (SM) synchronizes execution of Function Blocks (FBs) and thecommunication of Function Block (FB) parameters on the fieldbus, and handlespublication of the time of day to all devices, automatic assignment of deviceaddresses, and searching for parameter names or "tags" on the fieldbus.Terminator: A Terminator is an impedance-matching module used at or near each end of atransmission line. Only two Terminators can be used on a single H1 segment.Transducer Block (TB): A Transducer Block (TB) decouples Function Blocks (FBs) from the localInput/Output (I/O) functions required to read sensors and command output hardware.Transducer Blocks (TBs) contain information such as calibration date and sensortype. There is usually one TB channel for each input or output of a Function Block(FB).Transmitter: A Transmitter is an active fieldbus device containing circuitry which applies a digitalsignal on the bus.Trunk: A Trunk is the main communication highway between devices on an H1 fieldbusnetwork. The Trunk acts as a source of main supply to Spurs on the network.User Application: The User Application is based on "blocks," including Resource Blocks (RBs),Function Blocks (FBs) and Transducer Blocks (TBs), which represent different typesof application functions.User Layer: The User Layer provides scheduling of Function Blocks (FBs), as well as DeviceDescriptions (DDs) which allow the host system to communicate with devices withoutthe need for custom programming.Virtual Communication Relationship (VCR): Configured application layer channels that provide for the transfer ofdata between applications. FOUNDATION fieldbus describes three types of VCRs:Publisher/Subscriber, Client/Server, and Source/Sink.Virtual Field Device (VFD): A Virtual Field Device (VFD) is used to remotely view local device data described inthe object dictionary. A typical device will have at least two Virtual Field Devices(VFDs).WXYZ