southern african power pool powering africa – sapp strategies by eng. musara beta sapp chief...
TRANSCRIPT
SOUTHERN AFRICAN POWER POOL
www.sapp.co.zw
Powering Africa – SAPP Strategies
ByEng. Musara Beta
SAPP Chief Market Analyst
Zimbabwe Mining & Infrastructure Indaba 20149 October 2014
Meikles Hotel, Harare, ZIMBABWE
SOUTHERN AFRICAN POWER POOL
1. INTRODUCTION TO THE SAPP
2. POWER SUPPLY CHALLENGES IN THE SAPP
3. SAPP STRATEGIES TO MEET DEMAND
4. SAPP COMPETITIVE MARKET
5. CONCLUSIONS
CONTENTS
SOUTHERN AFRICAN POWER POOL
1. INTRODUCTION TO THE SAPP
1.1 Key Facts
DR CongoTanzania
Zambia
Angola Malawi
Zimbabwe
MozambiqueBotswanaNamibia
South AfricaLesotho
Swaziland
12 Countries 280 Million people Installed Generation
Capacity - 58 GW Available Generation
Capacity - 51 GW Peak Demand - 54 GW Consumption - 400TWh
SOUTHERN AFRICAN POWER POOL
No Full Name of National Power Utility Status Abbreviation Country
1 Botswana Power Corporation OP BPC Botswana
2 Electricidade de Mocambique OP EDM Mozambique
3 Electricity Supply Corporation of Malawi NP ESCOM Malawi
4 Empresa Nacional de Electricidade NP ENE Angola
5 ESKOM OP Eskom South Africa
6 Lesotho Electricity Corporation OP LEC Lesotho
7 NAMPOWER OP Nam Power Namibia
8 Societe Nationale d’Electricite OP SNEL DRC
9 Swaziland Electricity Board OP SEB Swaziland
10 Tanzania Electricity Supply Company Ltd NP TANESCO Tanzania
11 ZESCO Limited OP ZESCO Zambia
12 Zimbabwe Electricity Supply Authority OP ZESA ZimbabweNo Full Name of Private Utility Status Abbreviation Country13 Copperbelt Energy Corporation ITC CEC Zambia14 Lunsemfwa Hydro Power Company IPP LHPC Zambia15 Hidro Cahora Bassa OB HCB Mozambique16 Mozambique Transmission Compamy OB MOTRACO Mozambique
OP: Operating NP: Non-Operating ITC: Independent Transmission Company OB: Observer IPP: Independent Power Producer
1.2 SAPP Membership
SOUTHERN AFRICAN POWER POOL
2. POWER SUPPLY CHALLENGES IN SAPP
No Country Utility
Installed Capacity
[MW] As at Aug 2014
Available Capacity
[MW] Aug 2014
Forecast/ Peak
Demand
Capacity Shortfall including reserves,
MW
Calculated Reserve Margin, %
1 Angola ENE 2,195 1,772 1599
2 Botswana BPC 892 680 610
3 DRC SNEL 2,442 1,251 1342
4 Lesotho LEC 72 72 138
5 Malawi ESCOM 351 351 326
6 Mozambique EDM /HCB 2308 2,279 850
7 Namibia NamPower 501 392 635
8 South Africa Eskom 44,158 41,074 37661
9 Swaziland SEC 70 70 219
10 Tanzania TANESCO 1396 1,159 905
11 Zambia ZESCO / CEC/LHPC 2,128 2,029 2287
12 Zimbabwe ZESA 2,045 1,540 1961
58,558 52,669 48,533 (2,758) 7.9%
54,616 49,387 45,703 (1,253) 7.5%
TOTAL SAPP
Total Interconnected SAPP
As at Aug 2014, total SAPP installed capacity was 58.6 GW
SOUTHERN AFRICAN POWER POOL
Demand for power in Southern African has been increasing at an average rate of 3% per annum.
In 2007, demand growth for South Africa was
4.9% and for the whole region 4.6%.
In the last 10 years demand in the SAPP increased by more than 32% which is equivalent to 13,000 MW (from 41,000 MW in 2004 to 54,000MW in 2013).
Unfortunately, there has been no corresponding investments in generation and transmission infrastructure, (11,469MW generation added from 2004 to 2013) resulting in the current supply deficit that the region is experiencing.
2. POWER SUPPLY CHALLENGES IN SAPP
SOUTHERN AFRICAN POWER POOL
Why has the SAPP run into supply deficit ?
1. Economic Growth of more than 5% in most of the SADC member countries resulting in unprecedented growth in electricity consumption and demand.
2. Increase in demand for base metals resulting in high metal prices on the World Market with new mining companies being established in the SADC region in the last few years.
3. Inadequate Investments in generation and transmission infrastructure over the last 20-years.
4. Electrification Programmes have partly contributed to the increased consumption and demand.
5. The challenge was identified and communicated but not adequately mitigated.
SOUTHERN AFRICAN POWER POOL
3. SAPP STRATEGIES TO MEET DEMAND
The SAPP has proposed the following measures:
1. Demand Management based on others experiences: Power Conservation Programme (PCP)
Study and understand the concept of PCP Formulate and adopt PCP for SADC
Demand Side Management (DSM) Mechanism to provide financial support for
development and implementation of DSM in the SADC Develop local manufacturing capability to support DSM
initiatives. SADC Policy for efficient use of electrical energy
1.Incandescent versus CFLs 2.Minimum energy efficiency standards for new
connections
SOUTHERN AFRICAN POWER POOL
4,500 MW saving and Virtual Power Station established
0
1000
2000
3000
4000
5000
6000
7000
2012 2013 2014 2015 2016 2017 2018
Demand Reduction (MW)CFL SWH Commercial Lighting HWLC
DSM- SAPP VIRTUAL POWER STATION – WHERE IS THE SAPP?
SOUTHERN AFRICAN POWER POOL
Impact of DSM On Load Management[2009 – 2015]
If no load management options implemented, the deficit could have been worse
Situation improves and is better after load management.
All SAPP Members
4000045000500005500060000650007000075000800008500090000
2009
2010
2011
2012
2013
2014
2015
Year
MW
Capacity Required Peak Demand 2009 Plan
30000
3500040000
4500050000
5500060000
6500070000
7500080000
85000
2009
2010
2011
2012
2013
2014
2015
Year
MW
Capacity Required Capacity Planned Peak Demand after load reduction
SOUTHERN AFRICAN POWER POOL
2. Create an enabling environment for power sector investment: Policy and Legal framework Regulatory framework
SAPP Governance documents revised from 2006 to accommodate other players such as IPPs, Large Users etc in the structures of SAPP
3. Implement cost reflective and time of use tariffs in SADC member countries.
Creating an Enabling Environment
SOUTHERN AFRICAN POWER POOL
4. Supply Side Measures Maximize utilization of all installed supply option
Re-capitalization of power utilities Short and Medium-term generation projects
Ensure projects are properly prepared for financing Governments to prioritize funding of power projects
Create an enabling environment for renewable energy Develop a structure for the implementation of a least-cost
SAPP generating facility
• Provide Investment incentives to all Investors in the power sector, both local and foreign. Address policy issues relating to legal & regulatory
frameworks, i.e. enabling environment. Allow for VAT and tax exemptions for import of power
equipment and machinery for a defined period.
Supply Side Measures
SOUTHERN AFRICAN POWER POOL
Commissioned Generation CapacityPlanned Generation Capacity versus Actual Commissioned for period 2004-2013
Planned Gen. Capacity Actual Commissioned Difference: Planned minusYear (MW) Capacity (MW) Commissioned (MW)
2004 260 320 60 2005 520 490 (30) 2006 1,041 375 (666) 2007 2,441 1,696 (745) 2008 2,014 1,747 (267) 2009 2,400 2,187 (213) 2010 908 848 (60) 2011 1,751 1,230 (521) 2012 3,552 1,099 (2,453) 2013 1,992 1,477 (515)
Total 16,879 11,469 (5,410)
-
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Planned Gen. Capacity (MW)
Actual Commissioned Capacity (MW)
SOUTHERN AFRICAN POWER POOL
Generation Projects Planned for 2014 - 2018
No Country
2014 2015 2016 2017 2018 TOTAL1 Angola 150 0 1280 2271 0 3,701 2 Botswana - - - - 600 600 3 DRC - 430 150 240 1,620 2,440 4 Lesotho - - 35 - - 35 5 Malawi - - - - 74 74 6 Mozambique 175 - 40 - 600 815 7 Namibia - - 15 - 1,050 1,065 8 RSA 2,376 2,811 3,464 1,918 2,866 13,435 9 Swaziland - - - - - - 10 Tanzania - 150 500 460 700 1,810 11 Zambia 195 435 15 426 - 1,071 12 Zimbabwe - 15 - 420 2,400 2,835
2,896 3,841 5,499 5,735 9,910 27,881
COMMITTED GENERATION CAPACITY, MW
TOTAL
SOUTHERN AFRICAN POWER POOL
Demand and Supply Situation 2013-2018
Planned Capacity will exceed peak demand by 2016.
0100002000030000400005000060000700008000090000
2013 2014 2015 2016 2017 2018
Peak Demand Capacity Planned
SOUTHERN AFRICAN POWER POOL
Transmission Integration Projects
2018: Mozambique Malawi
2018:DRC - Angola – 400 kV
2018: Zambia - Tanzania - 400 kV
DRCDRC
TanzaniaTanzania
AngolaAngola
ZambiaZambiaMalawiMalawi
MozambiqueMozambique
ZimbabweZimbabwe
BotswanaBotswana
NamibiaNamibia
South AfricaSouth Africa
SwazilandSwaziland
LesothoLesotho
2015 -2018: ZIZABONA -220/330 kV
2020: MOZAMBIQUE BACKBONE -RSA
2015-2025: 765 kV Strengthening
2017: RSA Strengthening
2018: Botswana Strengthening
SOUTHERN AFRICAN POWER POOL
4. SAPP COMPETITIVE MARKET
SAPP Developed and started operating the Day Ahead Market (DAM) IN December 2009
SAPP is currently developing following markets for operation mid 2015
a) Month Ahead Market (MAM) Trading will be done for a month ahead (for delivery in
the next month)
b) Week Ahead Market (WAM) Trading will be done a week ahead (for delivery the
following week)
c) Intra Day Market (IDM) Trading will be done an hour ahead (for delivery in the
next hour in a day)
SOUTHERN AFRICAN POWER POOL
Trading in the various timeframes after NTP
24 hours
Own production
Monthly Forward trading
Bilateral contracts
Weekly forward trading
DAM TRADINGM
W
IDM trading
SOUTHERN AFRICAN POWER POOL
Market Performance Highlights – Market Share
Average Competitive Market share was almost 16%
Market share increased significantly from April 2014 through to August 2014.
0
50000
100000
150000
200000
250000
300000
350000
Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14
DAM & PDAM Trades (MWhr)
Non Investment Bilateral Trades (MWhr)
SOUTHERN AFRICAN POWER POOL
5. CONCLUSIONS
Projects Packaging is critical for projects to attract funding and be implemented
SAPP CC plays a critical role in mobilising grant funding and project coordination
A Master Plan for the regional power market is vital as it:
Helps to reduce capital costs by implementing least-cost projects for the benefit of the region.
Reduces excess capacity from the pool.
In the SAPP, SAPP Pool Plan noted that a saving of over US$48 billion could be realized if projects are implemented in a coordinated fashion.